CN204326094U - The polygon steel pile foundation of transmission of electricity steel pipe pole - Google Patents
The polygon steel pile foundation of transmission of electricity steel pipe pole Download PDFInfo
- Publication number
- CN204326094U CN204326094U CN201420786896.6U CN201420786896U CN204326094U CN 204326094 U CN204326094 U CN 204326094U CN 201420786896 U CN201420786896 U CN 201420786896U CN 204326094 U CN204326094 U CN 204326094U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- pile foundation
- steel
- multilateral
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本实用新型公开了一种输电钢管杆多边钢桩基础,包括桩基础本体,所述桩基础本体包括由高强钢板弯制而成的多边钢管杆,所述多边钢管杆的横截面为多边形,所述多边钢管杆的上端焊接有法兰盘,所述法兰盘和所述多边钢管杆的外壁之间设有加强肋板;施工现场将桩基础本体打入杆位地下,基础施工即可完成,然后便可组立钢管杆,方便快捷。具有结构简单、易于加工的优点,而且可以直接打入地下,现场组立,使基础施工方便快捷,而且无养护期,能极大缩短施工周期,同时保护了原状土,更利于钢桩基础受力。
The utility model discloses a polygonal steel pile foundation with steel pipe rods for power transmission, which comprises a pile foundation body. The pile foundation body includes polygonal steel pipe rods bent from high-strength steel plates. The upper end of the multilateral steel pipe rod is welded with a flange, and a reinforcing rib is provided between the flange and the outer wall of the multilateral steel pipe rod; the pile foundation body is driven into the ground at the pole position at the construction site, and the foundation construction can be completed , and then steel pipe poles can be assembled, which is convenient and quick. It has the advantages of simple structure and easy processing, and it can be directly driven into the ground and assembled on site, which makes the foundation construction convenient and fast, and has no maintenance period, which can greatly shorten the construction period, protect the undisturbed soil at the same time, and is more conducive to the steel pile foundation force.
Description
技术领域technical field
本实用新型涉及一种输电钢管杆钢桩基础。The utility model relates to a steel pipe pole steel pile foundation for power transmission.
背景技术Background technique
输电钢管杆安装前,需要预先在施工现场制作桩基础,现有桩基础通常多采用钢筋混凝土结构,其施工复杂,施工时需要注意孔深是否符合设计要求;水泥、沙石是否满足要求;钢筋是否按照设计要求布置、焊接是否符合规程要求;根开是否有错;地脚螺栓是否和设计的一致等等问题,因此现有桩基础的施工复杂,而且养护周期长,造成整条线路工程施工时间过长;另外,圆形钢桩因加工工艺限制多一节一节焊接起来,不能直接打桩,需掏挖放入桩后再回填夯实,费时费力。Before the installation of steel pipe poles for power transmission, pile foundations need to be prepared on the construction site in advance. Existing pile foundations usually use reinforced concrete structures, and the construction is complicated. During construction, it is necessary to pay attention to whether the hole depth meets the design requirements; whether the cement and sand meet the requirements; Whether the layout is in accordance with the design requirements, whether the welding meets the requirements of the regulations; whether the root opening is wrong; whether the anchor bolts are consistent with the design, etc., so the construction of the existing pile foundation is complicated, and the maintenance period is long, resulting in the construction of the entire line. The time is too long; in addition, due to the limitation of the processing technology, the circular steel piles are welded one by one, so the piles cannot be directly driven.
实用新型内容Utility model content
本实用新型所要解决的技术问题是提供一种结构简单、易于加工,而且可以直接打入地下,现场组立,使基础施工方便快捷,而且无养护期,能极大缩短施工周期,同时保护了原状土,更利于钢桩基础受力的输电钢管杆多边钢桩基础。The technical problem to be solved by the utility model is to provide a structure that is simple, easy to process, and can be directly driven into the ground and assembled on site, so that the foundation construction is convenient and fast, and there is no maintenance period, which can greatly shorten the construction period and protect the ground. The undisturbed soil is more conducive to the multilateral steel pile foundation with steel pipe rods for power transmission.
为解决上述技术问题,本实用新型的技术方案是:输电钢管杆多边钢桩基础,包括桩基础本体,所述桩基础本体包括由高强钢板弯制而成的多边钢管杆,所述多边钢管杆的横截面为多边形,所述多边钢管杆的上端焊接有法兰盘,所述法兰盘和所述多边钢管杆的外壁之间设有加强肋板。In order to solve the above-mentioned technical problems, the technical solution of the utility model is: the multilateral steel pile foundation of transmission steel pipe rods, including the pile foundation body, the pile foundation body includes multilateral steel pipe rods bent from high-strength steel plates, and the multilateral steel pipe rods The cross section is polygonal, the upper end of the polygonal steel pipe rod is welded with a flange, and a reinforcing rib is provided between the flange and the outer wall of the polygonal steel pipe rod.
作为优选的技术方案,所述桩基础本体的外表面设有防腐层。As a preferred technical solution, an anti-corrosion layer is provided on the outer surface of the pile foundation body.
作为优选的技术方案,所述防腐层为油漆层。As a preferred technical solution, the anti-corrosion layer is a paint layer.
作为优选的技术方案,所述防腐层为镀锌层。As a preferred technical solution, the anti-corrosion layer is a galvanized layer.
由于采用了上述技术方案,输电钢管杆多边钢桩基础,包括桩基础本体,所述桩基础本体包括由高强钢板弯制而成的多边钢管杆,所述多边钢管杆的横截面为多边形,所述多边钢管杆的上端焊接有法兰盘,所述法兰盘和所述多边钢管杆的外壁之间设有加强肋板;施工现场将桩基础本体打入杆位地下,基础施工即可完成,然后便可组立钢管杆,方便快捷。具有结构简单、易于加工的优点,而且可以直接打入地下,现场组立,使基础施工方便快捷,而且无养护期,能极大缩短施工周期,同时保护了原状土,更利于钢桩基础受力。Due to the adoption of the above technical scheme, the multilateral steel pile foundation of transmission steel pipe rods includes a pile foundation body, and the pile foundation body includes multilateral steel pipe rods bent from high-strength steel plates. The upper end of the multilateral steel pipe rod is welded with a flange, and a reinforcing rib is provided between the flange and the outer wall of the multilateral steel pipe rod; the pile foundation body is driven into the ground at the pole position at the construction site, and the foundation construction can be completed , and then steel pipe poles can be assembled, which is convenient and quick. It has the advantages of simple structure and easy processing, and can be directly driven into the ground and assembled on site, which makes the foundation construction convenient and fast, and has no maintenance period, which can greatly shorten the construction period, protect the undisturbed soil at the same time, and is more conducive to the steel pile foundation force.
附图说明Description of drawings
图1是本实用新型实施例的结构示意图;Fig. 1 is the structural representation of the utility model embodiment;
图2是图1的A-A向剖视图。Fig. 2 is a sectional view taken along line A-A of Fig. 1 .
具体实施方式Detailed ways
如图1和图2所示,输电钢管杆多边钢桩基础,包括桩基础本体1,所述桩基础本体1包括由高强钢板弯制而成的多边钢管杆2,所述多边钢管杆2的横截面为多边形,所述多边钢管杆2的上端焊接有法兰盘3,所述法兰盘3和所述多边钢管杆2的外壁之间设有加强肋板4。As shown in Figures 1 and 2, the multilateral steel pile foundation with steel pipe rods for power transmission includes a pile foundation body 1, and the pile foundation body 1 includes multilateral steel pipe rods 2 bent from high-strength steel plates, and the polygonal steel pipe rods 2 The cross section is polygonal, the upper end of the polygonal steel pipe rod 2 is welded with a flange 3 , and a reinforcing rib 4 is provided between the flange 3 and the outer wall of the polygonal steel pipe rod 2 .
所述桩基础本体1的外表面设有防腐层。The outer surface of the pile foundation body 1 is provided with an anti-corrosion layer.
所述防腐层为油漆层。The anticorrosion layer is a paint layer.
所述防腐层为镀锌层。The anti-corrosion layer is a galvanized layer.
输电钢管杆多边钢桩基础,包括桩基础本体1,所述桩基础本体1包括由高强钢板弯制而成的多边钢管杆2,所述多边钢管杆2的横截面为多边形,所述多边钢管杆的上端焊接有法兰盘3,所述法兰盘3和所述多边钢管杆2的外壁之间设有加强肋板4;施工现场将桩基础本体打入杆位地下,基础施工即可完成,然后便可组立钢管杆,方便快捷。具有结构简单、易于加工的优点,而且可以直接打入地下,现场组立,使基础施工方便快捷,而且无养护期,能极大缩短施工周期,同时保护了原状土,更利于钢桩基础受力。The multilateral steel pile foundation of transmission steel pipe rods includes a pile foundation body 1, and the pile foundation body 1 includes a multilateral steel pipe rod 2 bent from a high-strength steel plate. The cross section of the polygonal steel pipe rod 2 is polygonal. The upper end of the rod is welded with a flange 3, and a reinforcing rib 4 is provided between the flange 3 and the outer wall of the multilateral steel pipe rod 2; the pile foundation body is driven into the ground at the pole position at the construction site, and the foundation construction is completed After completion, the steel pipe pole can be assembled, which is convenient and quick. It has the advantages of simple structure and easy processing, and can be directly driven into the ground and assembled on site, which makes the foundation construction convenient and fast, and has no maintenance period, which can greatly shorten the construction period, protect the undisturbed soil at the same time, and is more conducive to the steel pile foundation force.
以上显示和描述了本实用新型的基本原理、主要特征及本实用新型的优点。本行业的技术人员应该了解,本实用新型不受上述实施例的限制,上述实施例和说明书中描述的只是说明本实用新型的原理,在不脱离本实用新型精神和范围的前提下,本实用新型还会有各种变化和改进,这些变化和改进都落入要求保护的本实用新型范围内。本实用新型要求保护范围由所附的权利要求书及其等效物界定。The basic principles, main features and advantages of the present utility model have been shown and described above. Those skilled in the art should understand that the utility model is not limited by the above-mentioned embodiments. The above-mentioned embodiments and descriptions only illustrate the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model The new model also has various changes and improvements, and these changes and improvements all fall within the scope of the claimed utility model. The scope of protection required by the utility model is defined by the appended claims and their equivalents.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420786896.6U CN204326094U (en) | 2014-12-12 | 2014-12-12 | The polygon steel pile foundation of transmission of electricity steel pipe pole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420786896.6U CN204326094U (en) | 2014-12-12 | 2014-12-12 | The polygon steel pile foundation of transmission of electricity steel pipe pole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204326094U true CN204326094U (en) | 2015-05-13 |
Family
ID=53162470
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420786896.6U Expired - Lifetime CN204326094U (en) | 2014-12-12 | 2014-12-12 | The polygon steel pile foundation of transmission of electricity steel pipe pole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204326094U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105002922A (en) * | 2015-07-22 | 2015-10-28 | 国家电网公司 | Pile type precast foundation for steel pipe pole |
CN105002921A (en) * | 2015-07-22 | 2015-10-28 | 国家电网公司 | Steel pipe pole for electric transmission line |
CN107191055A (en) * | 2017-07-13 | 2017-09-22 | 国家电网公司 | A kind of electric pole |
CN114703882A (en) * | 2022-01-17 | 2022-07-05 | 东北石油大学 | A pull-up steel pile foundation with continuous trapezoidal ribs |
-
2014
- 2014-12-12 CN CN201420786896.6U patent/CN204326094U/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105002922A (en) * | 2015-07-22 | 2015-10-28 | 国家电网公司 | Pile type precast foundation for steel pipe pole |
CN105002921A (en) * | 2015-07-22 | 2015-10-28 | 国家电网公司 | Steel pipe pole for electric transmission line |
CN107191055A (en) * | 2017-07-13 | 2017-09-22 | 国家电网公司 | A kind of electric pole |
CN114703882A (en) * | 2022-01-17 | 2022-07-05 | 东北石油大学 | A pull-up steel pile foundation with continuous trapezoidal ribs |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204238248U (en) | A kind of pin-connected panel Prefabricated Concrete well | |
CN204326094U (en) | The polygon steel pile foundation of transmission of electricity steel pipe pole | |
CN203755352U (en) | Prefabricated slab for closing basement post-pouring settlement belt | |
CN204185845U (en) | A kind of water-proof pile board wall supporting and protection structure | |
CN205676882U (en) | A kind of novel supporting construction | |
CN102220764B (en) | Construction method of deep foundation pit bracing system | |
CN206015717U (en) | The underground pipe gallery of soft soil foundation | |
CN206220112U (en) | Length pulls together to control heavy stiff composite pile system | |
CN201981549U (en) | Precast electric pole pile | |
CN107191055A (en) | A kind of electric pole | |
CN204326061U (en) | A kind of pile tube be drawn out easily | |
CN104652426B (en) | A kind of saline soil area waterglass anticorrosion pile foundation construction method | |
CN203270550U (en) | Pipe-spray joint pile supporting underground wall structure | |
CN102296592A (en) | Construction method of cast-in-situ X-shaped reinforced concrete pile underground continuous wall | |
CN201943071U (en) | Implantable steel tube anchor rod with stabs | |
CN106400832B (en) | A kind of construction method of environment-friendly type assembled grouting behind shaft or drift lining steel cylinder pile foundation | |
CN102155015A (en) | Barbed implanted steel pipe anchor rod | |
CN202899148U (en) | Spiral ground anchor base | |
CN201908303U (en) | Square frame-shaped steel cavity concrete cast-in-situ well sinking protecting wall | |
CN202788874U (en) | Embedded grouting guide tube device in chamber lining concrete | |
CN201730107U (en) | Pile foundation of electric steel tube tower | |
CN203487541U (en) | Novel water-stop precast centrifugal rectangular pile building envelope | |
CN204282349U (en) | A kind of bamboo reinforced cement soil agitation pile | |
CN202007407U (en) | Deep foundation pit supporting system | |
CN103669343B (en) | Detachable combined pile and detachment construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20150513 |
|
CX01 | Expiry of patent term |