CN202227701U
CN202227701U CN2011203133079U CN201120313307U CN202227701U CN 202227701 U CN202227701 U CN 202227701U CN 2011203133079 U CN2011203133079 U CN 2011203133079U CN 201120313307 U CN201120313307 U CN 201120313307U CN 202227701 U CN202227701 U CN 202227701U
Authority
CN
China
Prior art keywords
base
guardrails
guardrail
horizontal channel
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011203133079U
Other languages
Chinese (zh)
Inventor
曾平雨
曾发勇
张明星
郐国雄
汪永胜
徐聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Industry Corp Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN2011203133079U priority Critical patent/CN202227701U/en
Application granted granted Critical
Publication of CN202227701U publication Critical patent/CN202227701U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a pin-connected panel horizontal channel device belongs to steel construction apparatus field. The channel includes: a base and two guardrails; the base is of a flat plate type structure, and two side edges of the base are installation surfaces for installing two guardrails; two guardrails are of a frame structure, the two guardrails are arranged on two sides of the base respectively, and the bottom of each guardrail is fixedly connected with the side edge of the side base. This horizontal passage device can avoid the construction of setting up horizontal passage in the high altitude, has reduced the danger that sets up horizontal passage between the high altitude steel construction floor and causes, can accelerate the construction progress of whole engineering, compares the scaffold frame horizontal passage of setting up in traditional high altitude, has advantages such as safe, swift, high-efficient to effectively reduce labour cost, economic benefits is showing.

Description

Assembled horizontal passage device
Technical Field
The utility model relates to a steel construction apparatus field especially relates to a horizontal passageway device of pin-connected panel of the horizontal passageway of floor standard who uses as steel construction installation engineering.
Background
At present, a horizontal safety channel is generally erected between high-altitude floors by scaffold steel pipes in steel structure installation engineering. The mode needs to carry out high-altitude scaffold erection operation, is long in time consumption and large in labor consumption, and easily forms steel pipes and objects caused by falling of fasteners during assembly of scattered steel pipes. And because steel construction installation rate is very fast, therefore the steel pipe scaffold who adopts the spare part sets up horizontal escape way and exists: (1) the erection speed is low, the demand of labor force is large, the erection time is long, and the construction line operation is not easy to be rapidly carried out. (2) The scaffold has large assembling amount of parts, high danger, easy formation of object striking injury and is not beneficial to control and control of site hazard sources. (3) The integrity is poor, the quality reliability of the scaffold steel pipe is poor, and serious safety accidents are easily caused by a small number of defective steel pipes and fasteners. Particularly, under the condition that the installation operation surfaces of high-rise steel structures are overlapped frequently, horizontal channels formed by scaffolds are erected everywhere, which wastes labor and time and is poor in safety when used at high altitude.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a pin-connected panel horizontal channel device can regard as the floor standard horizontal channel that steel construction installation engineering used, adopts bolted connection, has the installation and simply uses reliably, can effectively avoid high altitude scaffold to set up the danger of the high altitude construction that horizontal channel caused.
The utility model aims at realizing through the following technical scheme:
the utility model discloses embodiment provides a pin-connected panel horizontal channel device, the device includes:
a base and two guardrails; wherein,
the base is of a flat plate type structure, and two side edges of the base are installation surfaces for installing two guardrails;
two guardrails are of a frame structure, the two guardrails are arranged on two sides of the base respectively, and the bottom of each guardrail is fixedly connected with the side edge of the side base.
In the channel device, the bottom of each guardrail is fixedly connected with the side edge of the side base in a welding mode.
In the above passage device, the device further includes: a plurality of fixing members;
a plurality of mounting holes are formed in the mounting surfaces on the two side edges of the base;
the bottom of each guardrail is provided with a plurality of fixing holes corresponding to the mounting holes on the mounting surfaces on the two side edges of the base;
the guardrails arranged on the two sides of the base correspond to the mounting holes on the side mounting surface of the base on the side through the fixing holes at the bottom of the guardrail, and the corresponding fixing holes and the mounting holes are connected through the fixing parts, so that the two guardrails are fixedly connected on the two sides of the base.
In the channel device, the base is a flat plate structure consisting of a base plate, a steel springboard and a connecting part; the base plate is formed by welding profile steel, and the steel springboard is laid on the base plate and is fixedly connected with the base plate through a connecting part.
In the above channel device, the base plate is formed by welding a plurality of section steels.
In the above channel device, the plurality of mounting holes are respectively provided on both side edges of the base plate of the base.
In the above channel device, the connecting member of the base is a steel wire.
In the channel device, each guardrail is of a frame structure consisting of a plurality of upright posts and cross bars; wherein a plurality of pole settings vertical interval parallel arrangement, a plurality of horizontal pole level sets up and connects between each pole setting.
In the above channel device, the plurality of fixing holes of each guardrail are respectively arranged at the bottom end of each upright rod of the guardrail.
In the above channel device, the bottoms of the upright posts of the guardrails are also provided with a protection plate, and the protection plate is horizontally arranged outside each upright post and fixedly connected with each upright post.
According to the technical scheme provided by the aforesaid, the utility model discloses embodiment forms a pin-connected panel horizontal channel device on the both sides limit of base through with two guardrail fixed connection. During the use, can use between the floor of this horizontal passage device integral hoisting in the steel construction to avoided the high altitude to set up the construction of horizontal passage, reduced the danger that sets up horizontal passage between the high altitude steel construction floor and cause, can accelerate the construction progress of overall engineering, compare the scaffold horizontal passage of setting up in traditional high altitude, have advantages such as safe, swift, high-efficient, and effectively reduce labour cost, economic benefits is showing.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly described below, and it is obvious that the drawings in the description below are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic view of a split structure of a horizontal channel provided in an embodiment of the present invention;
fig. 2 is a schematic overall structure diagram of a horizontal channel provided in an embodiment of the present invention;
fig. 3 is a schematic structural diagram of a base of a horizontal channel according to an embodiment of the present invention;
fig. 4 is a schematic structural view of a guardrail of a horizontal channel provided by an embodiment of the present invention.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the following specific embodiments, and it should be understood that the described embodiments are only some embodiments of the present invention, but not all embodiments. Based on the embodiment of the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The embodiments of the present invention are described in further detail below.
The embodiment of the utility model provides a pin-connected panel horizontal channel device can be used in steel construction engineering, as the horizontal channel between the floor, as shown in figure 1, 2, the device includes: a base 1 and two guardrails 2; wherein,
the base 1 is of a flat plate type structure, and two side edges of the base are installation surfaces 11 for installing two guardrails;
two guardrails 2 are frame type structures, two guardrails 2 are respectively arranged on two sides of the base 1, and the bottom of each guardrail is respectively fixedly connected with the side edge of the side base.
In the horizontal channel device, the bottom of each guardrail 2 can be fixedly connected with the side edge of the side base through a welding mode. The integral horizontal channel device (shown in figure 2) formed in the way is convenient to integrally hoist between steel structure construction floors for use.
The other mode is as follows: the device still includes a plurality of fixed parts, and the mode that the bottom of each guardrail 2 can be connected through a plurality of fixed parts 3 respectively with the side 11 fixed connection of place side base 1 specifically is: a plurality of mounting holes 13 are arranged on the mounting surfaces of the two side edges 11 of the base 1;
the bottom of each guardrail is provided with a plurality of fixing holes 3 corresponding to the mounting holes on the mounting surfaces on the two side edges of the base;
the guardrails arranged on the two sides of the base correspond to the mounting holes in the side mounting surface of the base on the side through the fixing holes in the bottom of the guardrail, and the corresponding fixing holes and the corresponding mounting holes are connected through the fixing parts, so that the two guardrails are fixedly connected to the two sides of the base, and the two guardrails and the base form an integral horizontal channel device.
The concrete structure of the base in the horizontal channel device is a flat plate structure composed of a base plate 11, a steel springboard 12 and a connecting part (not shown in the figure) as shown in fig. 3; the base plate is formed by welding profile steels (can be formed by welding a plurality of profile steels, and can be formed by welding seven profile steels generally according to the length of a channel), the steel springboard is laid on the base plate and is fixedly connected with the base plate through a connecting part, and the connecting part can adopt steel wires; the plurality of mounting holes 13 on the base are respectively arranged on two side edges of the base plate of the base.
The two rails of the above-mentioned passage means are substantially identical in structure, as shown in fig. 4, and each rail is a frame-like structure formed by a plurality of uprights 21 and crossbars 22; wherein a plurality of upright posts 21 are arranged in parallel at vertical intervals, and a plurality of cross bars 22 are horizontally arranged and connected among the upright posts; a plurality of fixed orificess of each guardrail set up respectively in each pole setting 21 bottom of this guardrail, and a plurality of pole setting bottoms of each guardrail still are equipped with guard plate 23, and the level of guard plate 23 sets up in each pole setting outside and each pole setting fixed connection.
During the in-service use, install passageway base plate earlier, this base plate is formed by the welding of polylith shaped steel, lays the steel springboard above the base plate to it is fixed firm to use the steel wire, its both ends of base plate rest respectively in the installation on the main girder steel of steel construction. Through placing on three main girder steels, guarantee the stability of whole horizontal passage.
Then install the guardrail of upper portion both sides (two guardrails form the envelope system of horizontal passageway), the guardrail of both sides all passes through the base of bolt and lower part (being the base plate firm in connection of base), finally forms the standard horizontal passage device of pin-connected panel. The enclosure structure system formed by the two guardrails in the horizontal channel device can be directly welded or bolted into a whole with the base plate of the base according to the implementation condition, and integral hoisting is adopted during installation, so that the number of assembled parts can be reduced, and the hoisting and dismounting difficulty can be increased.
The horizontal channel device can be used for various loading tests after being assembled for the first time, and can be put into use after being qualified so as to improve the safety.
The assembled horizontal channel device can be used for mechanical construction by using a tower crane, and is high in efficiency;
when a horizontal channel is erected between the floors of the frame, any high-altitude scattered scaffold does not need to be erected, so that high-altitude danger is effectively reduced, and the striking injury of objects is avoided.
The utility model discloses pin-connected panel horizontal channel device has effectively reduced the danger of high altitude construction when setting up horizontal channel between the floor for the whole construction progress of engineering, compares the horizontal channel that traditional scaffold set up, has advantages such as safe, swift, high efficiency, has effectively reduced labour's cost moreover, and economic benefits is showing.
The above description is only for the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present invention are all covered by the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. An assembled horizontal channel device, characterized in that, the device includes:
a base and two guardrails; wherein,
the base is of a flat plate type structure, and two side edges of the base are installation surfaces for installing two guardrails;
two guardrails are of a frame structure, the two guardrails are arranged on two sides of the base respectively, and the bottom of each guardrail is fixedly connected with the side edge of the side base.
2. The assembled horizontal channel device according to claim 1, wherein the bottom of each guardrail is fixedly connected with the side edge of the side base respectively through welding.
3. The sectional horizontal channel apparatus according to claim 1, further comprising: a plurality of fixing members;
a plurality of mounting holes are formed in the mounting surfaces on the two side edges of the base;
the bottom of each guardrail is provided with a plurality of fixing holes corresponding to the mounting holes on the mounting surfaces on the two side edges of the base;
the guardrails arranged on the two sides of the base correspond to the mounting holes on the side mounting surface of the base on the side through the fixing holes at the bottom of the guardrail, and the corresponding fixing holes and the mounting holes are connected through the fixing parts, so that the two guardrails are fixedly connected on the two sides of the base.
4. The modular horizontal channel assembly of claim 1 or 3, wherein the base is a flat plate structure consisting of a base plate, a steel gangway and connecting members; the base plate is formed by welding profile steel, and the steel springboard is laid on the base plate and is fixedly connected with the base plate through a connecting part.
5. The modular horizontal channel assembly of claim 4, wherein the base plate is formed by welding a plurality of steel sections.
6. The modular horizontal channel assembly of claim 4, wherein the plurality of mounting holes are disposed on each of two sides of the base plate of the base.
7. The sectional horizontal channel device according to claim 4, wherein the connecting member of the base is a steel wire.
8. The modular horizontal pathway arrangement of claim 1, wherein each said barrier is a frame-like structure formed from a plurality of uprights and cross-bars; wherein a plurality of pole settings vertical interval parallel arrangement, a plurality of horizontal pole level sets up and connects between each pole setting.
9. The modular horizontal channel assembly of claim 6, wherein the plurality of securing holes of each guardrail are respectively disposed at the bottom ends of the uprights of the guardrail.
10. The assembled horizontal channel device according to claim 6, wherein the bottom of the upright posts of each guardrail is further provided with a protection plate, and the protection plate is horizontally arranged on the outer side of each upright post and fixedly connected with each upright post.
CN2011203133079U 2011-08-25 2011-08-25 Assembled horizontal passage device Expired - Lifetime CN202227701U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011203133079U CN202227701U (en) 2011-08-25 2011-08-25 Assembled horizontal passage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011203133079U CN202227701U (en) 2011-08-25 2011-08-25 Assembled horizontal passage device

Publications (1)

Publication Number Publication Date
CN202227701U true CN202227701U (en) 2012-05-23

Family

ID=46078290

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011203133079U Expired - Lifetime CN202227701U (en) 2011-08-25 2011-08-25 Assembled horizontal passage device

Country Status (1)

Country Link
CN (1) CN202227701U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453206A (en) * 2014-12-09 2015-03-25 重庆建工第九建设有限公司 Scaffold plate
CN105189889A (en) * 2013-04-12 2015-12-23 Peri有限公司 Lattice girder for weather protection roof, and weather protection roof having multiple lattice girders
CN108385995A (en) * 2018-04-10 2018-08-10 中建八局第二建设有限公司 A kind of site operation escape way
CN110424702A (en) * 2019-07-02 2019-11-08 上海外高桥造船有限公司 Overbridge device
CN110439198A (en) * 2019-07-26 2019-11-12 中铁十八局集团有限公司 A kind of piece for assembling type fence for steel structural rod piece high-altitude intelligent operation
TWI684700B (en) * 2018-08-10 2020-02-11 潤弘精密工程事業股份有限公司 Scaffold system and scaffold structure thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105189889A (en) * 2013-04-12 2015-12-23 Peri有限公司 Lattice girder for weather protection roof, and weather protection roof having multiple lattice girders
CN104453206A (en) * 2014-12-09 2015-03-25 重庆建工第九建设有限公司 Scaffold plate
CN108385995A (en) * 2018-04-10 2018-08-10 中建八局第二建设有限公司 A kind of site operation escape way
CN108385995B (en) * 2018-04-10 2023-12-01 中建八局第二建设有限公司 Site construction safety channel
TWI684700B (en) * 2018-08-10 2020-02-11 潤弘精密工程事業股份有限公司 Scaffold system and scaffold structure thereof
CN110424702A (en) * 2019-07-02 2019-11-08 上海外高桥造船有限公司 Overbridge device
CN110439198A (en) * 2019-07-26 2019-11-12 中铁十八局集团有限公司 A kind of piece for assembling type fence for steel structural rod piece high-altitude intelligent operation

Similar Documents

Publication Publication Date Title
CN202227701U (en) Assembled horizontal passage device
CN202324571U (en) Overhanging type double-row scaffold
CN101775907A (en) Space truss structure aerial pairing integral slide installation method
CN204780560U (en) Steel suspension bridge assembly structure
CN210798252U (en) Assembled outer protection frame system
CN202925957U (en) Instrumentalized extension-type safety protection shed
CN108277994B (en) Method for quickly dismantling safety protection shed of overhead high-speed rail operation line
CN103967263A (en) Novel hydraulic automatic climbing discharging platform
CN203947758U (en) Novel hydraulic automatic climbing discharging platform
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN201347616Y (en) Split type steel welding operation platform
CN203022328U (en) Climbing operation platform
CN107795133B (en) Integral protective frame platform and construction method thereof
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN202828032U (en) Helicopter deck
CN201722937U (en) Sliding platform for installation of net rack
CN201401000Y (en) Special hanging basket for installing noise barrier roof boards
CN212866803U (en) Construction practicality operation platform in elevator well
CN212404902U (en) Light-duty pin-connected panel bridge bottom surface construction platform
CN203392657U (en) Machine maintenance platform
CN103114712B (en) Buckle steel platform support system and construction method thereof
CN214653222U (en) Anti-climbing device for tower crane
CN218116158U (en) Pier hanging flower basket installation operation platform
CN205077876U (en) Prestressed steel strand pulling machine and tensioning jack suspension device
CN218439466U (en) A wood system platform sling for pedestrian well ladder overhauls

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120523