[go: up one dir, main page]

CN201738227U - Ground-anchored and self-anchored hauling combined system bridge - Google Patents

Ground-anchored and self-anchored hauling combined system bridge Download PDF

Info

Publication number
CN201738227U
CN201738227U CN2009202769520U CN200920276952U CN201738227U CN 201738227 U CN201738227 U CN 201738227U CN 2009202769520 U CN2009202769520 U CN 2009202769520U CN 200920276952 U CN200920276952 U CN 200920276952U CN 201738227 U CN201738227 U CN 201738227U
Authority
CN
China
Prior art keywords
anchor
cable
anchored
bridge
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009202769520U
Other languages
Chinese (zh)
Inventor
张哲�
王会利
石磊
黄才良
邱文亮
檀永刚
潘盛山
许福友
谭岩斌
王德慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian University of Technology
Original Assignee
Dalian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian University of Technology filed Critical Dalian University of Technology
Priority to CN2009202769520U priority Critical patent/CN201738227U/en
Application granted granted Critical
Publication of CN201738227U publication Critical patent/CN201738227U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

地锚—自锚吊拉组合体系桥,属于建筑工程技术领域,特别涉及到桥梁工程中的复杂地质条件下大跨径桥梁的设计。其特征是:索塔与边孔墩施工后,开始悬臂拼装斜拉桥混凝土主梁;悬臂拼装到边孔完成后悬挂主缆,一端锚固在永久锚块上,另一端锚固在砼梁外端锚块上,而锚块用临时锚索拉在临时锚碇上;设有永久锚块的主梁梁端,水平支撑在桥台上;用缆索吊机吊装跨中各段钢主梁;合拢后,分批拆除临时锚索,主缆完全锚在主梁端部,完成由临时锚碇到自锚的体系转换。本实用新型的效果和益处是充分发挥材料性能,针对复杂地质条件,节省了庞大的锚碇,降低了工程造价,缩短了工期,降低了施工过程中的风险。

Figure 200920276952

The ground anchor-self-anchor suspension composite system bridge belongs to the technical field of construction engineering, and particularly relates to the design of long-span bridges under complex geological conditions in bridge engineering. Its characteristics are: after the construction of the cable tower and the side hole pier, the cantilever assembly of the concrete main beam of the cable-stayed bridge begins; after the cantilever is assembled to the side hole, the main cable is suspended, and one end is anchored on the permanent anchor block, and the other end is anchored on the outer end of the concrete beam. The anchor block is pulled on the temporary anchorage with temporary anchor cables; the beam end of the main girder with permanent anchor block is supported horizontally on the abutment; the steel girder in each section of the mid-span is hoisted by a cable crane; after closing, Temporary anchor cables are removed in batches, and the main cable is completely anchored at the end of the main girder, completing the system conversion from temporary anchorage to self-anchor. The effect and benefit of the utility model is to give full play to the material properties, save huge anchorages for complex geological conditions, reduce the project cost, shorten the construction period, and reduce the risk in the construction process.

Figure 200920276952

Description

地锚-自锚吊拉组合体系桥 Ground anchor-self-anchored suspension composite system bridge

技术领域technical field

本实用新型属于建筑工程技术领域,涉及到桥梁工程中的桥梁的设计,特别涉及到大跨径桥梁的设计。The utility model belongs to the technical field of construction engineering and relates to the design of bridges in bridge engineering, in particular to the design of long-span bridges.

背景技术Background technique

目前,在大跨径桥梁设计中通常采用以下几种桥型:At present, the following types of bridges are usually used in the design of long-span bridges:

1、斜拉桥1. Cable-stayed bridge

现在已建成最大跨径的斜拉桥是日本的多多罗大桥,其跨径达到890m。但是斜拉桥施工时的悬臂跨度达到500m左右时,它的空气动力稳定性确实令人担心,同时它的轴向水平压力会随着悬臂跨径的增大而迅速增加,致使主梁根部在近塔处会产生压屈失稳的现象。The cable-stayed bridge with the largest span that has been built now is the Tatara Bridge in Japan, with a span of 890m. However, when the cantilever span of the cable-stayed bridge reaches about 500m during construction, its aerodynamic stability is really worrying. At the same time, its axial horizontal pressure will increase rapidly with the increase of the cantilever span. Buckling instability will occur near the tower.

2、悬索桥2. Suspension Bridge

现在已建成最大跨径的悬索桥是日本的明石海峡大桥,主跨达到1991m。但是悬索桥主缆和主梁用钢量较大,增加了工程造价,同时大跨径悬索桥均为地锚式,需要庞大的锚碇,而且其体积随着跨径的增大而迅速增加。据报道,主跨1000m的悬索桥比同等跨径的斜拉桥造价要高出16.7%。另外,空气动力稳定性也是悬索桥向大跨径发展的制约因素。The suspension bridge with the largest span is the Akashi Kaikyo Bridge in Japan, with a main span of 1991m. However, the amount of steel used for the main cable and girder of the suspension bridge is large, which increases the construction cost. At the same time, the long-span suspension bridges are all anchored in the ground, requiring huge anchorage, and their volume increases rapidly with the increase of the span. According to reports, the cost of a suspension bridge with a main span of 1000m is 16.7% higher than that of a cable-stayed bridge with the same span. In addition, aerodynamic stability is also a restrictive factor for the development of suspension bridges with large spans.

3、斜拉-悬索协作体系桥3. Cable-stayed-suspension collaborative system bridge

这种桥型边跨采用斜拉结构,跨中采用悬索结构,发挥了斜拉桥和悬索桥的各自优点。国内建成世界第一座该类型的桥-贵州乌江大桥,主跨只有288m。伶仃洋大桥、白令海峡大桥等国内外多座跨海大桥均提出了这种方案,目前该桥型主要停留在方案设计阶段。所提出的方案,均为地锚体系,需要庞大的锚碇,施工难度大,工程造价高。This type of bridge adopts a cable-stayed structure for the side span and a suspension cable structure for the mid-span, giving full play to the respective advantages of the cable-stayed bridge and the suspension bridge. The first bridge of this type in the world - Guizhou Wujiang Bridge was built in China, with a main span of only 288m. Many domestic and foreign sea-crossing bridges, such as the Lingdingyang Bridge and the Bering Strait Bridge, have proposed this scheme. At present, the bridge type is mainly in the scheme design stage. The proposed schemes are all ground anchor systems, which require huge anchors, are difficult to construct, and cost high.

发明内容Contents of the invention

本实用新型要解决的技术问题是针对复杂地质条件,提出一种大跨径桥型设计方案。The technical problem to be solved by the utility model is to propose a large-span bridge design scheme for complex geological conditions.

本实用新型的技术方案是,先施工斜拉桥部分,再悬挂主缆,主缆一端锚固于永久隧道锚,另一端锚固在临时锚块上,然后吊装悬索桥部分的钢主梁。合拢后,拆除临时锚索,完成主缆体系转换,采用地锚-自锚体系。斜拉段采用混凝土梁,跨中悬索段采用钢梁。The technical solution of the utility model is to first construct the cable-stayed bridge part, then hang the main cable, one end of the main cable is anchored to the permanent tunnel anchor, and the other end is anchored to the temporary anchor block, and then the steel girder of the suspension bridge part is hoisted. After closing, remove the temporary anchor cable, complete the conversion of the main cable system, and adopt the ground anchor-self-anchor system. Concrete beams are used for the cable-stayed section, and steel beams are used for the mid-span suspension section.

具体步骤:Specific steps:

步骤1:索塔与边孔墩施工后,开始悬臂拼装斜拉桥混凝土主梁;Step 1: After the construction of the cable tower and the side hole pier, start the cantilever assembly of the concrete main girder of the cable-stayed bridge;

步骤2:悬臂拼装到边孔完成后悬挂主缆,一端锚固在永久锚块上,另一端锚固在砼梁外端锚块上,而锚块用临时锚索拉在临时锚碇上;Step 2: After the cantilever is assembled to the side hole, the main cable is suspended, one end is anchored on the permanent anchor block, the other end is anchored on the outer end anchor block of the concrete beam, and the anchor block is pulled on the temporary anchor by a temporary anchor cable;

步骤3:设有永久锚块的主梁梁端,水平支撑在桥台上;Step 3: The beam end of the main girder with permanent anchor blocks is horizontally supported on the abutment;

步骤4:用缆索吊机吊装跨中各段钢主梁;Step 4: Use a cable crane to hoist the steel girders of each section of the mid-span;

步骤5:合拢后,分批拆除临时锚索,主缆完全锚在主梁端部,完成由临时锚碇到自锚的体系转换;Step 5: After closing, the temporary anchor cables are removed in batches, the main cable is completely anchored at the end of the main beam, and the system conversion from temporary anchorage to self-anchor is completed;

步骤6:完成桥面铺装、栏杆施工,并进行全桥的索力调整,成桥。Step 6: Complete bridge deck pavement, railing construction, and adjust the cable force of the whole bridge to complete the bridge.

本实用新型的效果和益处是:Effect and benefit of the present utility model are:

1.采用地锚-自锚组合体系,在地质条件好的一侧采用永久地锚体系,主梁也支撑在该侧的山体上,在地质条件差的一侧采用自锚体系。这种桥型因地制宜,经济合理;1. Adopt the combination system of ground anchor and self-anchor, adopt permanent ground anchor system on the side with good geological conditions, and the main beam is also supported on the mountain on this side, and use self-anchor system on the side with poor geological conditions. This bridge type is adapted to local conditions and is economically reasonable;

2.采用自锚体系,节省了庞大的锚碇,不仅降低了造价,而且缩短了工期;2. The use of self-anchoring system saves huge anchorage, not only reduces the cost, but also shortens the construction period;

3.斜拉桥部分的荷载是通过桥塔传递到塔基,而不像在悬索桥中要通过主缆将这部分荷载传给塔基,这就减小了主缆的直径,节省了材料;3. The load of the cable-stayed bridge part is transmitted to the tower foundation through the bridge tower, unlike in the suspension bridge, this part of the load is transmitted to the tower foundation through the main cable, which reduces the diameter of the main cable and saves materials;

4.施工过程中斜拉桥的悬臂缩短,成桥后悬索桥范围也减小,因此在施工过程中和成桥状态后的空气动力稳定性都得到了显著的提高,降低了施工过程中的风险;4. During the construction process, the cantilever of the cable-stayed bridge is shortened, and the range of the suspension bridge is also reduced after the completion of the bridge. Therefore, the aerodynamic stability during the construction process and after the completion of the bridge has been significantly improved, reducing the risk during the construction process ;

5.斜拉桥部分缩短,在近塔处主梁根部的轴向压力降低,在保证主梁稳定性的同时,又可以减小混凝土主梁的面积,降低工程造价;5. The part of the cable-stayed bridge is shortened, and the axial pressure at the root of the main beam near the tower is reduced. While ensuring the stability of the main beam, it can also reduce the area of the concrete main beam and reduce the construction cost;

6.在斜拉桥段采用混凝土主梁,而悬索桥段采用钢主梁,充分发挥材料性能,可以大幅节约造价。6. Concrete girders are used in the cable-stayed bridge section, while steel girders are used in the suspension bridge section to give full play to the material properties and greatly save the cost.

附图说明Description of drawings

图1是地锚-自锚吊拉组合体系桥临时锚碇示意图。Figure 1 is a schematic diagram of the temporary anchorage of the ground anchor-self-anchor suspension system bridge.

图中:1主缆;2主梁;3吊杆;4斜拉索;5主塔;6隧道锚;7边墩。In the figure: 1 main cable; 2 main beam; 3 suspender; 4 stay cable; 5 main tower; 6 tunnel anchor; 7 side pier.

图2是地锚-自锚吊拉组合体系桥成桥方案示意图。Figure 2 is a schematic diagram of the bridge completion scheme of the ground anchor-self-anchor suspension system.

图中:1主缆;2主梁;3吊杆;4斜拉索;5主塔;6隧道锚;8锚块。In the figure: 1 main cable; 2 main beam; 3 suspender; 4 stay cable; 5 main tower; 6 tunnel anchor; 8 anchor block.

具体实施方式Detailed ways

以下结合技术方案和附图,详细叙述本实用新型的具体实施方式。Below in conjunction with technical scheme and accompanying drawing, describe the specific embodiment of the utility model in detail.

斜拉桥主梁拼装就位后,悬挂主缆,主缆一端锚固于永久隧道锚,另一端锚固在临时锚块上。吊装中间钢箱梁,待主梁合拢之后,拆除临时锚索,完成主缆体系转换,然后调整全桥索力。After the main girder of the cable-stayed bridge is assembled in place, the main cable is suspended. One end of the main cable is anchored to the permanent tunnel anchor, and the other end is anchored to the temporary anchor block. The intermediate steel box girder is hoisted, and after the main girder is closed, the temporary anchor cables are removed to complete the conversion of the main cable system, and then the cable force of the whole bridge is adjusted.

主梁截面:斜拉桥部分主梁采用混凝土箱梁截面,悬索桥部分采用钢箱梁截面。Main girder section: part of the main girder of the cable-stayed bridge adopts the concrete box girder section, and the part of the suspension bridge adopts the steel box girder section.

材料特性:斜拉桥部分主梁和湿接缝采用C50混凝土,墩桩采用C30混凝土;悬索桥部分主梁采用Q345钢。Material properties: C50 concrete is used for part of the main girder and wet joints of the cable-stayed bridge, and C30 concrete is used for pier piles; Q345 steel is used for part of the main girder of the suspension bridge.

荷载等级:公路-I级。Load class: Highway-I class.

斜拉索与主缆材料特性:斜拉索与主缆采用挤包护层扭绞型拉索。Material characteristics of stay cables and main cables: Stay cables and main cables are twisted cables with extruded sheath.

Claims (1)

1. earth anchor-from anchor hangs and draws combined system birdge, and the co-operative system by cable stayed bridge and suspension bridge constitute is characterized in that: main push-towing rope one end is anchored in permanent tunnel anchor, and the other end is anchored at the girder end.
CN2009202769520U 2009-11-27 2009-11-27 Ground-anchored and self-anchored hauling combined system bridge Expired - Fee Related CN201738227U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202769520U CN201738227U (en) 2009-11-27 2009-11-27 Ground-anchored and self-anchored hauling combined system bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202769520U CN201738227U (en) 2009-11-27 2009-11-27 Ground-anchored and self-anchored hauling combined system bridge

Publications (1)

Publication Number Publication Date
CN201738227U true CN201738227U (en) 2011-02-09

Family

ID=43553505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202769520U Expired - Fee Related CN201738227U (en) 2009-11-27 2009-11-27 Ground-anchored and self-anchored hauling combined system bridge

Country Status (1)

Country Link
CN (1) CN201738227U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102154990A (en) * 2011-05-13 2011-08-17 长沙理工大学 Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge
CN102296526A (en) * 2011-07-20 2011-12-28 天津市市政工程设计研究院 Combination beam-concrete beam mixed cable stayed bridge system
CN110939067A (en) * 2019-12-09 2020-03-31 中铁大桥勘测设计院集团有限公司 Method for determining position of bridge closure section of collaboration system
CN112726378A (en) * 2020-12-31 2021-04-30 四川省交通勘察设计研究院有限公司 Main-tower-free cable-stayed bridge suitable for wide and deep canyons and construction scheme

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102154990A (en) * 2011-05-13 2011-08-17 长沙理工大学 Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge
CN102154990B (en) * 2011-05-13 2012-12-05 长沙理工大学 Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge
CN102296526A (en) * 2011-07-20 2011-12-28 天津市市政工程设计研究院 Combination beam-concrete beam mixed cable stayed bridge system
CN102296526B (en) * 2011-07-20 2013-05-29 天津市市政工程设计研究院 A Composite Beam-Concrete Beam Hybrid Cable-Stayed Bridge System
CN110939067A (en) * 2019-12-09 2020-03-31 中铁大桥勘测设计院集团有限公司 Method for determining position of bridge closure section of collaboration system
CN112726378A (en) * 2020-12-31 2021-04-30 四川省交通勘察设计研究院有限公司 Main-tower-free cable-stayed bridge suitable for wide and deep canyons and construction scheme

Similar Documents

Publication Publication Date Title
CN103088750B (en) Especial-big span suspension bridge of uniparted hyperboloid space rope net main cable and construction method thereof
CN101736686A (en) Self-anchored hybrid beam cable-stayed suspension cooperative system bridge
CN201826249U (en) Self-anchored hybrid beam cable-stayed suspension cooperative system bridge
CN102296525B (en) Support system mixed combined beam cable-stayed bridge and construction method thereof
CN100519943C (en) Non-cable single-tower stayed bridge
CN104695341B (en) Non-self-balanced beam string structure for reinforcing large-span continuous beam bridge
CN101736685A (en) Ground-anchored-self-anchored suspension combined system bridge
CN203080400U (en) Extra-large span suspension bridge with uniparted hyperboloid space cable net main cables
CN106884371B (en) A kind of non-uniform beam and suspension cable combined bridge structural system
CN102154990B (en) Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge
WO2023016573A1 (en) Construction method for steel-concrete main girder of cable-stayed bridge
CN201738227U (en) Ground-anchored and self-anchored hauling combined system bridge
CN103898834B (en) A kind of steel tube concrete combination beam and truss-like Sarasota cable-stayed bridge and construction method thereof
CN102108748B (en) Quadrilateral endless rope chord supporting structure and construction process
CN210395128U (en) Hollow core plate beam connection structure in bridge widening
CN104264578A (en) Steel-concrete combining bridge of self-anchored suspension cable-cable-stayed cooperative system
CN104775365B (en) A kind of construction method of cable-stayed bridge
CN110004816A (en) Corrugated steel web prestressed UHPC composite box girder and its construction method
CN1676753A (en) Self-anchored cable-stayed-suspension collaborative bridge
CN202170474U (en) Support system mixing type combined beam cable-stayed bridge
CN207244425U (en) Part earth anchored suspension bridge
CN201660850U (en) Temporary anchoring structure during construction of a self-anchored bridge
CN202214682U (en) Device is changed to cable-stay bridge suspension cable
CN107142830B (en) Steel pipe web prestress steel-concrete combined girder structure and construction method
CN212561103U (en) Super large span cable-stayed bridge with thrust pier

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110209

Termination date: 20121127