CN201660850U - Temporary anchoring structure during construction of a self-anchored bridge - Google Patents
Temporary anchoring structure during construction of a self-anchored bridge Download PDFInfo
- Publication number
- CN201660850U CN201660850U CN2009202769535U CN200920276953U CN201660850U CN 201660850 U CN201660850 U CN 201660850U CN 2009202769535 U CN2009202769535 U CN 2009202769535U CN 200920276953 U CN200920276953 U CN 200920276953U CN 201660850 U CN201660850 U CN 201660850U
- Authority
- CN
- China
- Prior art keywords
- temporary
- bridge
- main
- anchor
- cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本实用新型属于建筑工程技术领域,特别涉及到自锚式桥梁施工过程中用于体系转换的临时锚固结构。其特征是:在施工主桥承台的同时一并浇筑临时锚碇,并在施工引桥下部结构时将靠近主桥的多个墩柱连为框架结构;待主缆安装就位并锚固于主梁端部锚块后,初次张拉临时锚碇上的临时锚索;在吊装中间部分主梁标准段的同时,逐步张拉临时锚碇上的临时锚索直至主桥合拢;主桥合拢后,有控制地分步释放临时锚碇处的临时锚索的张拉力,完成体系转换;调整全桥索力,拆除临时锚碇。本实用新型的效果和益处是充分利用桥梁已有结构形成临时锚固结构,缩小了临时锚碇的体积,降低了工程造价,缩短了施工工期;同时体系转换过程平稳安全,降低了施工过程中的风险。
The utility model belongs to the technical field of construction engineering, in particular to a temporary anchoring structure used for system conversion during the construction process of a self-anchored bridge. Its characteristics are: while constructing the cap of the main bridge, the temporary anchorage is poured together, and when the lower structure of the approach bridge is constructed, multiple piers close to the main bridge are connected to form a frame structure; after the main cable is installed in place and anchored to the main After the anchor block at the end of the beam, the temporary anchor cable on the temporary anchor is initially stretched; while the standard section of the main girder in the middle is hoisted, the temporary anchor cable on the temporary anchor is gradually stretched until the main bridge is closed; after the main bridge is closed , release the tensile force of the temporary anchor cables at the temporary anchorage step by step in a controlled manner, and complete the system conversion; adjust the cable force of the whole bridge, and remove the temporary anchorage. The effect and benefit of the utility model is to make full use of the existing structure of the bridge to form a temporary anchorage structure, which reduces the volume of the temporary anchorage, reduces the project cost, and shortens the construction period; at the same time, the system conversion process is stable and safe, and the construction process is reduced. risk.
Description
技术领域technical field
本实用新型属于建筑工程技术领域,涉及到桥梁工程施工过程中,采用体系转换的方法将临时地锚体系转换为永久自锚体系,尤其涉及到体系转换过程中的临时锚固结构。The utility model belongs to the technical field of construction engineering, and relates to a method for converting a temporary ground anchor system into a permanent self-anchor system by adopting a system conversion method in the construction process of bridge engineering, in particular to a temporary anchor structure in the system conversion process.
背景技术Background technique
自锚式桥梁传统上采用先架梁、后挂缆的施工顺序,这种施工方法需要设立大量的临时支架以支撑主梁。其一方面增加了工程造价,延长了施工工期;另一方面,干扰航道正常的交通秩序,且在大江大河或深海地区设立支架非常困难甚至是不可能实现的。这种施工方法使自锚式桥梁的应用推广受到了限制。Self-anchored bridges traditionally adopt the construction sequence of erecting beams first and then hanging cables. This construction method requires the establishment of a large number of temporary supports to support the main beam. On the one hand, it increases the project cost and prolongs the construction period; on the other hand, it interferes with the normal traffic order of the waterway, and it is very difficult or even impossible to set up supports in large rivers or deep sea areas. This construction method limits the application and popularization of self-anchored bridges.
为了克服上述支架施工方法的弊端,一种无支架施工方法,即先挂缆、后架梁的施工方法应运而生,已经建成通车的苏州竹园大桥就是采用此种方法施工的。该桥在施工过程中将主缆锚固于混凝土梁端锚块上,而锚块则通过临时锚索拉在临时锚碇上,这种临时锚固结构主要借鉴了地锚式桥梁的锚固原理,其在施工过程中与传统的地锚式桥梁在力学上是没有区别的,因此具有形式简单,受力明确的优点,但是该锚固结构需要修建庞大的临时锚碇,这势必会增加工程造价并延长施工工期。In order to overcome the disadvantages of the above-mentioned support construction method, a construction method without support, that is, the construction method of first hanging the cable and then erecting the beam came into being. The Suzhou Zhuyuan Bridge, which has been completed and opened to traffic, was constructed using this method. During the construction of the bridge, the main cable is anchored to the anchor block at the end of the concrete beam, and the anchor block is pulled on the temporary anchorage by a temporary anchor cable. In the construction process, there is no difference in mechanics from the traditional ground anchor bridge, so it has the advantages of simple form and clear force, but the anchor structure needs to build a huge temporary anchor, which will inevitably increase the project cost and prolong Construction period.
发明内容Contents of the invention
本实用新型的要解决的技术问题是提供一种自锚式桥梁施工过程中的临时锚固结构。这种结构不但可以降低工程造价,缩短施工工期,保证桥下通航。The technical problem to be solved by the utility model is to provide a temporary anchoring structure in the construction process of the self-anchored bridge. This structure can not only reduce the project cost, shorten the construction period, but also ensure the navigation under the bridge.
本实用新型的技术方案是,将引桥墩柱组成的框架结构,并与主桥边墩承台以及临时锚索共同组成自锚式桥梁施工过程中的临时锚固结构。The technical scheme of the utility model is that the frame structure composed of the bridge pier column, and the side pier cap of the main bridge and the temporary anchor cable together form the temporary anchor structure in the construction process of the self-anchored bridge.
本实用新型具体包含以下步骤:The utility model specifically comprises the following steps:
步骤1:在施工主桥承台的同时一并浇筑临时锚碇,并在施工引桥下部结构时将靠近主桥的多个墩柱连为框架结构;Step 1: Pour temporary anchorage while constructing the cap of the main bridge, and connect multiple piers close to the main bridge into a frame structure when constructing the lower structure of the approach bridge;
步骤2:待主缆安装就位并锚固于主梁端部锚块后,初次张拉临时锚碇上的临时锚索;Step 2: After the main cable is installed in place and anchored to the anchor block at the end of the main beam, tension the temporary anchor cable on the temporary anchor for the first time;
步骤3:在吊装中间部分主梁标准段的同时,逐步张拉临时锚碇上的临时锚索直至主桥合拢;Step 3: While hoisting the standard section of the main girder in the middle, gradually stretch the temporary anchor cables on the temporary anchor until the main bridge is closed;
步骤4:主桥合拢后,有控制地分步释放临时锚碇处的临时锚索的张拉力,完成体系转换;Step 4: After the main bridge is closed, release the tensile force of the temporary anchor cables at the temporary anchorage step by step in a controlled manner to complete the system conversion;
步骤5:调整全桥索力,拆除临时锚碇。Step 5: Adjust the cable force of the whole bridge and remove the temporary anchorage.
本实用新型的效果和益处是:Effect and benefit of the present utility model are:
临时锚固结构充分利用了桥梁结构已有的承台和桥墩,缩小了修建临时锚碇的体积,可以大幅节约工程造价,同时缩短了施工工期,还能保证施工期间桥下通航;临时锚固结构采用了主桥承台与引桥桥墩框架结构的组合结构来共同承担主缆的水平分力,锚固结构的总体承载能力增加。The temporary anchoring structure makes full use of the existing caps and piers of the bridge structure, reduces the volume of the temporary anchorage, can greatly save the project cost, shortens the construction period, and ensures navigation under the bridge during the construction period; the temporary anchoring structure adopts The combined structure of the main bridge cap and the approach bridge pier frame structure is used to jointly bear the horizontal force of the main cable, and the overall bearing capacity of the anchorage structure is increased.
附图说明Description of drawings
图1是体系转换过程中的临时锚固结构立面示意图。Figure 1 is a schematic diagram of the elevation of the temporary anchorage structure during the system conversion process.
图中:1临时锚索PG1;2临时锚索PG2;3临时锚索PG3;4限位钢管;5主梁锚块;6临时锚碇;7框架结构。In the figure: 1 temporary anchor cable PG1; 2 temporary anchor cable PG2; 3 temporary anchor cable PG3; 4 limit steel pipe; 5 main beam anchor block; 6 temporary anchor; 7 frame structure.
图2是体系转换过程中的临时锚固结构平面示意图。Figure 2 is a schematic plan view of the temporary anchoring structure during system conversion.
图中:1临时锚索PG1;2临时锚索PG2;3临时锚索PG3;4限位钢管;5主梁锚块;6临时锚碇;7框架结构。In the figure: 1 temporary anchor cable PG1; 2 temporary anchor cable PG2; 3 temporary anchor cable PG3; 4 limit steel pipe; 5 main beam anchor block; 6 temporary anchor; 7 frame structure.
具体实施方式Detailed ways
以下结合技术方案和说明书附图详细叙述本实用新型的具体实施方式。The specific embodiment of the utility model is described in detail below in conjunction with the technical scheme and the accompanying drawings of the description.
1.根据设计计算结果将体系转换过程中的临时锚碇在施工主桥边墩承台的同时一并浇筑;将靠近主桥边墩的多个墩柱在施工引桥下部结构时连为框架结构;1. According to the design and calculation results, the temporary anchorage during the system conversion process will be poured at the same time as the side pier cap of the main bridge is being constructed; the multiple pier columns close to the side pier of the main bridge will be connected into a frame structure during the construction of the lower structure of the approach bridge ;
2.悬挂主缆,并将主缆锚固于混凝土梁端锚块上。梁端锚块、临时锚碇与引桥多个墩柱组成的框架结构通过临时锚索相连;2. Suspend the main cable and anchor the main cable to the anchor block at the end of the concrete beam. The frame structure consisting of beam end anchor block, temporary anchorage and multiple pier columns of the approach bridge is connected by temporary anchor cables;
3.在临时锚碇上初次张拉临时锚索;3. Pull the temporary anchor cable for the first time on the temporary anchorage;
4.吊装中间部分箱梁标准段,同时逐步张拉临时锚索的,直至主桥合拢;4. Hoist the standard section of the box girder in the middle, and gradually stretch the temporary anchor cable until the main bridge is closed;
5.主桥合拢后,开始释放临时锚索的索力完成体系转换过程。体系转换时,分三次逐步释放临时锚索的索力,且主桥两侧同步对称释放。具体实施过程为:首先释放PG1和PG2索力至50%,然后将PG3的索力一次性全部释放掉,最后释放PG1和PG2的剩余全部索力。5. After the main bridge is closed, start to release the cable force of the temporary anchor cable to complete the system conversion process. When the system is converted, the cable force of the temporary anchor cable is gradually released three times, and both sides of the main bridge are released synchronously and symmetrically. The specific implementation process is as follows: first release the cable forces of PG1 and PG2 to 50%, then release all the cable forces of PG3 at one time, and finally release all the remaining cable forces of PG1 and PG2.
6.调整全桥索力,拆除临时锚碇。6. Adjust the cable force of the whole bridge and remove the temporary anchorage.
材料特性:临时锚碇采用C30混凝土;临时锚索采用标准强度1670Mpa的平行钢丝。Material characteristics: Temporary anchors are made of C30 concrete; temporary anchor cables are made of parallel steel wires with a standard strength of 1670Mpa.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202769535U CN201660850U (en) | 2009-11-27 | 2009-11-27 | Temporary anchoring structure during construction of a self-anchored bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202769535U CN201660850U (en) | 2009-11-27 | 2009-11-27 | Temporary anchoring structure during construction of a self-anchored bridge |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201660850U true CN201660850U (en) | 2010-12-01 |
Family
ID=43231267
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009202769535U Expired - Fee Related CN201660850U (en) | 2009-11-27 | 2009-11-27 | Temporary anchoring structure during construction of a self-anchored bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201660850U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103266570A (en) * | 2013-05-28 | 2013-08-28 | 中交二公局第五工程有限公司 | Method for accurately installing and positioning suspension bridge main cable anchor system |
CN105926443A (en) * | 2016-04-21 | 2016-09-07 | 中铁十七局集团第二工程有限公司 | Construction method for continuous rigid frame side span by first girder installation and then closure |
CN113123233A (en) * | 2021-03-03 | 2021-07-16 | 中交二航局第二工程有限公司 | Anchorage design and construction method |
-
2009
- 2009-11-27 CN CN2009202769535U patent/CN201660850U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103266570A (en) * | 2013-05-28 | 2013-08-28 | 中交二公局第五工程有限公司 | Method for accurately installing and positioning suspension bridge main cable anchor system |
CN103266570B (en) * | 2013-05-28 | 2015-07-15 | 中交二公局第五工程有限公司 | Method for accurately installing and positioning suspension bridge main cable anchor system |
CN105926443A (en) * | 2016-04-21 | 2016-09-07 | 中铁十七局集团第二工程有限公司 | Construction method for continuous rigid frame side span by first girder installation and then closure |
CN113123233A (en) * | 2021-03-03 | 2021-07-16 | 中交二航局第二工程有限公司 | Anchorage design and construction method |
CN113123233B (en) * | 2021-03-03 | 2022-11-25 | 中交二航局第二工程有限公司 | Anchorage design and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100969005B1 (en) | Constructing method of suspension bridge and temporary cable therefor | |
CN102418315B (en) | Construction Method of Concrete Steel Tube Arch Bridge with Large Bridge Width Erected by Low Buckle Towers | |
CN103233427B (en) | Sling tensioning and system conversion method for double-tower three-span plane main cable self-anchorage type suspension bridge | |
CN108374347A (en) | A kind of high-speed railway large span cable-carried arch bridge steel lagging jack buckling and hanging system construction method | |
CN101736686A (en) | Self-anchored hybrid beam cable-stayed suspension cooperative system bridge | |
CN100519943C (en) | Non-cable single-tower stayed bridge | |
CN201047060Y (en) | Truss type rope arch-type bridge structure | |
CN101054791A (en) | Joist type cable arch bridge structure and its construction method | |
CN110761168A (en) | Design and construction method of cable-first beam-second self-anchored suspension bridge | |
CN201826249U (en) | Self-anchored hybrid beam cable-stayed suspension cooperative system bridge | |
CN105648917A (en) | Cable-beam synchronization construction method for composite beam self-anchored suspension bridge | |
CN110284420A (en) | Full precast pier-the suspended deck structure of Self-resetting and its assembly method for being easy to repair after shaking | |
WO2023016573A1 (en) | Construction method for steel-concrete main girder of cable-stayed bridge | |
CN107190627A (en) | Part earth anchored suspension bridge and its construction method | |
CN102154990A (en) | Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge | |
CN101736685A (en) | Ground-anchored-self-anchored suspension combined system bridge | |
CN114781026A (en) | A construction control method for a cable-stayed bridge with a single leaning tower | |
CN104314013B (en) | Two Cantilever Construction Methods of a kind of pole asymmetrical array beam | |
CN201660850U (en) | Temporary anchoring structure during construction of a self-anchored bridge | |
CN109797659A (en) | A kind of mobile asynchronous construction method of bracket of Wavelike steel webplate continuous bridge | |
CN115030052B (en) | A rapid and safe construction and intelligent monitoring and control method for continuous arch bridges | |
CN107419670A (en) | Hybrid structure of arch and beam formula continuous rigid frame bridge winds up walking cradle construction device and method | |
CN102286929B (en) | Hinged arch springing of arch center | |
CN107905123B (en) | A kind of multi-joint continuous rigid frame end bay temporary T structure cantilever construction transforming methods of structural system | |
CN101736695A (en) | Temporary anchoring structure in self-anchored bridge construction process |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20101201 Termination date: 20121127 |