CN1419068A - Construction method and device for fixing seabed pipeline - Google Patents

Construction method and device for fixing seabed pipeline Download PDF

Info

Publication number
CN1419068A
CN1419068A CN 02135974 CN02135974A CN1419068A CN 1419068 A CN1419068 A CN 1419068A CN 02135974 CN02135974 CN 02135974 CN 02135974 A CN02135974 A CN 02135974A CN 1419068 A CN1419068 A CN 1419068A
Authority
CN
China
Prior art keywords
fixing
stake pipe
fixing device
submarine pipeline
centralizing bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 02135974
Other languages
Chinese (zh)
Other versions
CN1246619C (en
Inventor
孙连芬
高天宝
路国章
吴进军
齐雅茹
李新军
钱孟祥
谢明智
许曙光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Oilfield Service Corp
Original Assignee
Shengli Oil Field Shengli Petroleum & Chemical Construction Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shengli Oil Field Shengli Petroleum & Chemical Construction Corp filed Critical Shengli Oil Field Shengli Petroleum & Chemical Construction Corp
Priority to CN 02135974 priority Critical patent/CN1246619C/en
Publication of CN1419068A publication Critical patent/CN1419068A/en
Application granted granted Critical
Publication of CN1246619C publication Critical patent/CN1246619C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention relates to a submerged pipeline fixing contruction method and its equipment. Said method includes the following steps: firstly, prefabricating fixing equipment in plant, transporting it to seaside field and assembling it and fixing pile pipe into one body, shipping and transferring them to place, using floating crane to lift the piling machine, fixing device and fixing pile pipe together and make the fixing pile pipe come into centering guide, and using asdic method to guide the centering guide accurately be in place, using piling machine to drive fixing pile pipe into sea-bed and make fixing equipment be in place and fixing floating part of the pipeline. Said invented equipment includes hydraulic vibration piling machine, pile pipe centering guide, fixing equipment, fixing pile pipe and others.

Description

Submarine pipeline is method of construction and device fixedly
(1) technical field
The present invention relates to and the supporting structure thing is dropped to the seabed and be fixed, particularly is fixedly method of construction and device of submarine pipeline.
(2) background technique
The Shengli Oil Field neritic area is because particularity, ocean current and the artificial structure's etc. of sea situation influence makes submarine pipeline unsettled section phenomenon occur with the standpipe joint near platform.Exposed unsettled section of submarine pipeline swings back and forth under the washing away of ocean current, wave.When its local location surpassed fatigue limit, pipeline just might rupture, and oil accident takes place, and caused heavy losses and seawater pollution.This problem must solve as early as possible.Through patent searching document and relevant scientific and technological data, do not find the patented technology and the effective measures that address this problem.
(3) summary of the invention
Purpose of the present invention just is to provide a kind of submarine pipeline fixedly method of construction and device, solves the fixation problem of unsettled section of submarine pipeline effectively, prevents to rupture because of swinging repeatedly, guarantees the operation of submarine pipeline long-term safety.
Above-mentioned purpose is to be realized by following technical proposals:
The process flow of this method of construction is: be prefabricated in the factory into earlier the submarine pipeline fixing device; At sea carry out simultaneously and reconnoitre location and sonar buoy demarcation under water.Fixing device is on-the-spot by the sea assembles with the stake pipe, and the integral installation shipping is delivered to the position.With the crane barge machine on the construction boats and ships pile driver, fixing device and stake pipe etc. are sling then, made a pipe enter centralizing bracket.Utilize sonar equipment to search out unsettled pipeline section again, and the guiding centralizing bracket is accurately in place.Utilize pile driver that the stake pipe is squeezed into the sea bed certain depth, fixing device is put in place; Meanwhile, control and adjustment centralizing bracket keep level, for stake pipe guiding, prevent from.At last, fix unsettled section of submarine pipeline by the U-shaped clamp of fixing device.
The isolated plant of this method of construction mainly contains: hydraulic vibration pile driver, stake pipe centralizing bracket, submarine pipeline fixing device, fixing stake pipe, electric travelling crane, hanging beam, construction boats and ships, crane barge machine, power unit, control unit, umbilical cables, and underwater hydraulic bag, underwater electronic bag, tilting level and sonar equipment.Wherein crane barge machine, power unit and control unit all place on the construction boats and ships.Hanging beam, electric travelling crane, hydraulic vibration pile driver, pipeline fixing device and fixing stake pipe are all played by the crane barge machine.Play hanger on four angles of stake pipe centralizing bracket of four lifting ropes is arranged below the hanging beam.One end of umbilical cables is connecting the control unit on the boats and ships of constructing, and the other end is connecting underwater hydraulic bag, underwater electronic bag, tilting level and the sonar equipment that is installed on the centralizing bracket.
Centralizing bracket in the above-mentioned isolated plant is made up of base, hanger, connecting flange, horizontal adjustemt oil cylinder, framework, clamping oil cylinder, link press span, oil cylinder fixed base, holding frame, roller and sonar.Respectively there are a hanger and one group of connecting flange in four angles, base top.The horizontal adjustemt oil cylinder piston vertically is installed above the upper flange plate.The cylinder sleeve of four oil cylinders is vertically mounted on four angles, framework bottom.The jacket water safety of four clamping oil cylinders is contained on the link press span, and link press span is installed on the holding frame.The piston of clamping oil cylinder is installed on the oil cylinder fixed base.Four groups of eight rollers are installed on the link press span.Sonar has four, is installed in the inside of four frames of base respectively.
Submarine pipeline fixing device in the above-mentioned isolated plant is made up of U-shaped clamp, cantilever beams, stake pipe, cutting ferrule body, locking nut, revolution support, attachment bolt, adjustment plate, attachment pegs, jack and adjustment spanner thereof, supporting baseplate.The U-shaped clamp clamps submarine pipeline for unsettled section, and the clamp two ends are fixed to above the cantilever beams with screw bolt and nut.Cantilever beams is welded on the cutting ferrule body.The cutting ferrule body is sleeved on a tube outside, and is locked on the pipe with locking nut.Revolution is supported and also is enclosed within the fixing stake tube outside, and places cutting ferrule body bottom.Adjustment plate, jack, supporting baseplate place fixing stake pipe inside from top to bottom successively.The fixing stake pipe is squeezed into sea bed by pile driver.
After technique scheme is implemented, the fixing device of stake on the pipe that is driven into sea bed can be fixed unsettled section pressure of submarine pipeline, can prevent from effectively to swing repeatedly because of ocean current, alluvion, no longer because of the tired pipeline fracture accident that takes place, guarantee the operation of submarine pipeline long-term safety, its economic benefit and social benefit are conspicuous.
(4) description of drawings
Accompanying drawing 1 is a method of construction process flow chart of the present invention.
Accompanying drawing 2 is that isolated plant of the present invention is being used view.
Accompanying drawing 3 is that stake pipe centralizing bracket master of the present invention looks schematic representation.
Accompanying drawing 4 is that the A of Fig. 3 is to schematic side view.
Accompanying drawing 5 is that the B of Fig. 3 is to schematic top plan view.
Accompanying drawing 6 is pipeline fixing device of the present invention and stake pipe overall structure schematic representation.
In the accompanying drawing 2, the 1st, hanging beam, the 2nd, hydraulic vibration pile driver, the 3rd, stake pipe centralizing bracket, the 4th, fixing stake pipe, the 5th, electric travelling crane, the 6th, submarine pipeline fixing device, the 7th, umbilical cables, the 8th, control unit, the 9th, construction boats and ships, the 10th, power unit, the 11st, crane barge machine.
3.1 is bases in the accompanying drawing 3,4,5, the 3.2nd, and hanger, the 3.3rd, connecting flange, the 3.4th, the horizontal adjustemt oil cylinder, the 3.5th, framework, the 3.6th, the clamping oil cylinder, the 3.7th, link press span, the 3.8th, by cylinder fixed base, the 3.9th, holding frame, the 3.10th, roller, the 3.11st, sonar.
In the accompanying drawing 6, the 6.1st, U-shaped clamp, the 6.2nd, cantilever beams, the 6.3rd, attachment bolt, the 4th, fixing stake pipe, 6.5 be the cutting ferrule body, the 6.6th, locking nut, the 6.7th, revolution is supported, and the 6.8th, adjust plate, 6.9 be attachment pegs, the 6.10th, jack, the 6.11st, jack is adjusted spanner, the 6.12nd, supporting baseplate.
(5) embodiment
As shown in Figure 1, 2, method of construction process flow of the present invention is: beat before the fixing stake pipe 4, offshore construction preparatory work and fixing device prefabrication are carried out simultaneously, carry out on the one hand that the sea is reconnoitred under water, location and sonar buoy demarcate, on the other hand fixing device 6 ropings are assembled with fixing stake pipe 4 to the scene, beach, the integral installation shipping is delivered to the position again.Crane barge machine 11 on quilts such as pile driver 2, fixing device 6, the fixing stake pipe 4 construction boats and ships 9 is together sling, and makes fixing stake pipe 4 enter the center of centralizing bracket 3.Utilize the sonar equipment 3.11 on the centralizing bracket 3 to search out unsettled pipeline section, and guiding centralizing bracket 3 is accurately in place.With pile driver 2 fixing stake pipe 4 is squeezed into sea bed then, and fixing device 6 is put in place; Meanwhile, control and adjustment centralizing bracket 3 are fixing stake pipe 4 guiding while driving piles, and prevent that fixing stake pipe 4 from tilting.With U-shaped clamp 6.1 submarine pipeline is fixed on the fixing device 6 for unsettled section at last.
Isolated plant of the present invention scene is with state as shown in Figure 2.Crane barge machine 11 wherein, power unit 10 and control unit 8 all place on the construction boats and ships 9.Hanging beam 1, electric travelling crane 5, hydraulic vibration pile driver 2, pipeline fixing device 6 and fixing stake pipe 4 are all played by crane barge 11.Play hanger 3.2 on four angles of stake pipe centralizing bracket 3 of four lifting ropes is arranged below the hanging beam 1.One end of umbilical cables 7 is connecting the control unit 8 on the boats and ships 9 of constructing, and the other end is connecting underwater hydraulic bag, underwater electronic bag, tilting level and the sonar equipment 3.11 that is installed on the centralizing bracket 3.
On-site construction operations process of the present invention is shown in accompanying drawing 2~6:
1. preparation of construction
Carry out preliminry basic research under water by the diver, make a mark with the point location sonar buoy.On construction boats and ships 9, clamp the upper end portion of fixing stake pipe 4, and adjust the central position with the hydraulic fixture of pile driver 2.Put into the holding frame 3.9 of centralizing bracket 3 vertically downward to guarantee lifting back pile driver 2 and fixing stake pipe 4, clamping oil cylinder 3.6 is clamped the underpart of fixing stake pipe 4, adjust centralizing bracket 3 sling lengths, guarantee that lifting back pile driver 2, fixing stake pipe 4, centralizing bracket 3 are whole vertical with the sea level.
2. seek pipe, in place
Position mark according to explored submarine pipeline fixing stake pipe 4, pile driver 2 and centralizing bracket 3 are slowly put into water, under the guiding of the point location sonar (or diver) on the centralizing bracket 3, pile driver 2, fixing stake pipe 4 and centralizing bracket 3 are put on the position that is about to piling.After centralizing bracket 3 arrived seabeds, the section of the submarine pipeline that shows according to section sonar was measured the distance between centralizing bracket 3 centers and the submarine pipeline, adjusts the distance that centralizing bracket 3 reaches technical requirement by crane barge machine 11 and strand mill then.Controlling level is adjusted oil cylinder 3.4, by the level of trim and heel sensor monitors centralizing bracket 3, thus the perpendicularity on assurance fixing stake pipe 4 and sea level.The gps satellite positioning antenna is placed into the central position of pile driver 2, and the gps system received signal is demarcated, the geodetic coordinates of record fixing stake pipe 4, and the preservation data is standby.
3. piling
Unclamp the holding frame 3.9 of centralizing bracket 3, control clamping oil cylinder 3.6 strokes make holding frame 3.9 become the guide mechanism of fixing stake pipe 4.Connecting the power source of pile driver 2 drives piles.Fixing stake pipe 4 is gone into mud gradually under the guiding of holding frame 3.9.If centralizing bracket 3 is vibrated during run-off the straight, the signal that provides according to the trim on the centralizing bracket 3 and heel sensor then, controlling level is adjusted oil cylinder 3.6, guarantees that centralizing bracket 3 is vertical with the sea level all the time with fixing stake pipe 4.After fixing stake pipe 4 is gone into mud 5~6m, tilt no longer easily, holding frame 3.9 is all separated, so that the submarine pipeline fixing device 6 of fixing stake pipe 4 upper ends and pile driver 2 can pass through the degree of depth that continues to drive piles and require.Unclamp hydraulic fixture, crane barge machine 11 hangs out pile driver 2 and centralizing bracket 3, prepares to lay a root canal pile.
4. the unsettled pipeline section in seabed is fixed
After fixing stake pipe 4 was squeezed into the degree of depth of sea bed requirement, the fixing device 6 that is sleeved on its upper end portion can put in place.Under the diver water rotate cantilever beams 6.2 to the submarine pipeline with the submarine pipeline axis normal.By the upper-lower position of very heavy 6.10 adjustment cantilever beams 6.2, its upper surface is contacted with the submarine pipeline bottom.The contacting point pad is gone up rubber plate, the anticorrosive coat of the submarine pipeline that prevents to wear and tear.U type clamp 6.1 internal surfaces are loaded onto rubber plate, block submarine pipeline, and the clamp two ends are fixed on the overhang 6.2 with screw bolt and nut.Tighten set screw nut 6.6, outer cutting ferrule 6.5 is locked on the fixing stake pipe 4.Unsettled section device 6 that promptly is fixed of submarine pipeline forced to fix.

Claims (4)

1. the fixing method of construction of a submarine pipeline, it is characterized in that being prefabricated in the factory into earlier submarine pipeline fixing device (6), at sea perform simultaneously and reconnoitre location and sonar buoy demarcation under water, fixing device (6) is on-the-spot by the sea assembles with fixing stake pipe (4), the integral installation shipping is delivered to the position, crane barge machine (11) on the usefulness construction boats and ships (9) is pile driver (2) then, fixing device (6) and fixing stake pipe (4) etc. are sling, make fixing stake pipe (4) enter centralizing bracket (3), utilize sonar equipment to search out unsettled pipeline section again, and guiding centralizing bracket (3) is accurately in place, utilize pile driver (2) that fixing stake pipe (4) is squeezed into the sea bed certain depth, fixing device (6) is put in place, meanwhile control and adjust centralizing bracket (3) maintenance level, be fixing stake pipe (4) guiding, prevent from, use the U-shaped clamp (6.1) of fixing device (6) to fix unsettled pipeline section at last.
2. the fixing device of method of construction special use of submarine pipeline, it is characterized in that comprising hydraulic vibration pile driver (2), stake pipe centralizing bracket (3), submarine pipeline fixing device (6), fixing stake pipe (4), electric travelling crane (5), hanging beam (1), construction boats and ships (9), crane barge machine (11), power unit (10), control unit (8), umbilical cables (7), and underwater hydraulic bag, the underwater electronic bag, tilting level and sonar equipment, crane barge machine (11) wherein, power unit (10) and control unit (8) all place on the construction boats and ships (9), hanging beam (1), electric travelling crane (5), hydraulic vibration pile driver (2), pipeline fixing device (6) and fixing stake pipe (4) are all hung (11) by the crane barge machine and, play hanger (3.2) on four angles of stake pipe centralizing bracket (3) of four lifting ropes is arranged below the hanging beam (1), one end of umbilical cables (7) is connecting the control unit (8) on the construction boats and ships (9), and the other end is connecting the underwater hydraulic bag that is installed on the centralizing bracket (3), the underwater electronic bag, tilting level and sonar equipment.
3. submarine pipeline according to claim 2 is the device of method of construction special use fixedly, it is characterized in that stake pipe centralizing bracket (3) is by base (3.1), hanger (3.2), connecting flange (3.3), horizontal adjustemt oil cylinder (3.4), framework (3.5), clamping oil cylinder (3.6), link press span (3.7), oil cylinder fixed base (3.8), holding frame (3.9), roller (3.10) and sonar (3.11) are formed, respectively there are a hanger (3.2) and one group of connecting flange (3.3) in four angles, base (3.1) top, horizontal adjustemt oil cylinder (3.4) piston vertically is installed above the upper flange plate, the cylinder sleeve of four oil cylinders is vertically mounted on four angles, framework (3.5) bottom, the jacket water safety of four clamping oil cylinders (3.6) is contained on the link press span (3.7), link press span (3.7) is installed on the holding frame (3.9), the piston of clamping oil cylinder (3.6) is installed on the oil cylinder fixed base (3.8), four groups eight rollers (3.10) are installed on the link press span (3.7), sonar (3.11) has four, is installed in the inside of (3.1) four frames of base respectively.
4. submarine pipeline according to claim 2 is the device of method of construction special use fixedly, it is characterized in that submarine pipeline fixing device (6) is by U-shaped clamp (6.1), cantilever beams (6.2), attachment bolt (6.3), fixing stake pipe (4), cutting ferrule body (6.5), locking nut (6.6), (6.7) are supported in revolution, adjust plate (6.8), attachment pegs (6.9), jack (6.10) and adjustment spanner (6.11) thereof and supporting baseplate (6.12) are formed, U-shaped clamp (6.1) clamps submarine pipeline for unsettled section, the clamp two ends are fixed to above the cantilever beams (6.2) with screw bolt and nut, cantilever beams (6.2) is welded on the cutting ferrule body (6.5), cutting ferrule body (6.5) is sleeved on fixing stake pipe (4) outside, and be locked on the fixing stake pipe (4) with locking nut (6.6), revolution is supported (6.7) and also is enclosed within fixing stake pipe (4) outside, and place cutting ferrule body (6.5) bottom, adjust plate (6.8), jack (6.10) and supporting baseplate (6.12) place fixing stake pipe (4) inside from top to bottom successively, and fixing stake pipe (4) is squeezed into sea bed by pile driver (2).
CN 02135974 2002-12-10 2002-12-10 Construction method and device for fixing seabed pipeline Expired - Lifetime CN1246619C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 02135974 CN1246619C (en) 2002-12-10 2002-12-10 Construction method and device for fixing seabed pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 02135974 CN1246619C (en) 2002-12-10 2002-12-10 Construction method and device for fixing seabed pipeline

Publications (2)

Publication Number Publication Date
CN1419068A true CN1419068A (en) 2003-05-21
CN1246619C CN1246619C (en) 2006-03-22

Family

ID=4748448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 02135974 Expired - Lifetime CN1246619C (en) 2002-12-10 2002-12-10 Construction method and device for fixing seabed pipeline

Country Status (1)

Country Link
CN (1) CN1246619C (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101265995B (en) * 2008-05-06 2010-04-07 江苏省交通工程集团有限公司 Underwater pump tube and its construction method and concrete conveying method
CN101963257A (en) * 2010-09-30 2011-02-02 天津大学 Method for fixing seabed pipeline and preventing buckle propagation
CN102128311A (en) * 2010-12-09 2011-07-20 中国海洋石油总公司 Method and device for installing typical underwater manifold in swing mode
CN103133769A (en) * 2013-03-05 2013-06-05 中国海洋石油总公司 Method for placing cement briquettes of submarine pipeline
CN103822019A (en) * 2014-03-11 2014-05-28 东北石油大学 Suspension-in-water conveying pipeline and construction method thereof
CN104421491A (en) * 2013-08-22 2015-03-18 天津市海王星海上工程技术股份有限公司 Operation device and operation method for deepwater hanging subsea pipeline
CN104989875A (en) * 2015-05-19 2015-10-21 中国海洋石油总公司 Submarine pipeline flange underwater abutting joint installation method
CN105570535A (en) * 2016-01-14 2016-05-11 浙江海洋学院 Safety tunneling-preventing mechanism for submarine pipeline
CN106247012A (en) * 2016-08-16 2016-12-21 青岛理工大学 Pneumatic pressure access device for submarine pipeline
CN106704705A (en) * 2017-01-12 2017-05-24 中交天航南方交通建设有限公司 Water pipeline assembly operation method and system
CN108488485A (en) * 2018-04-03 2018-09-04 航天晨光股份有限公司 A kind of naval vessel Large Diameter Pipeline delivery hose suspension arrangement and its installation method
CN110410579A (en) * 2019-07-15 2019-11-05 中海石油深海开发有限公司 The installation method of deep water surface conductor pipe
CN113064175A (en) * 2021-03-26 2021-07-02 西京学院 Seabed vacuum pipeline with preset sonar sensors and installation method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101280862B (en) * 2007-04-03 2012-07-18 上海市基础工程有限公司 Seabed PE pipe rim spreading and imbedding construction method

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101265995B (en) * 2008-05-06 2010-04-07 江苏省交通工程集团有限公司 Underwater pump tube and its construction method and concrete conveying method
CN101963257A (en) * 2010-09-30 2011-02-02 天津大学 Method for fixing seabed pipeline and preventing buckle propagation
CN102128311A (en) * 2010-12-09 2011-07-20 中国海洋石油总公司 Method and device for installing typical underwater manifold in swing mode
CN102128311B (en) * 2010-12-09 2012-10-24 中国海洋石油总公司 Method and device for installing typical underwater manifold in swing mode
CN103133769A (en) * 2013-03-05 2013-06-05 中国海洋石油总公司 Method for placing cement briquettes of submarine pipeline
CN103133769B (en) * 2013-03-05 2015-05-06 中国海洋石油总公司 Method for placing cement briquettes of submarine pipeline
CN104421491A (en) * 2013-08-22 2015-03-18 天津市海王星海上工程技术股份有限公司 Operation device and operation method for deepwater hanging subsea pipeline
CN103822019A (en) * 2014-03-11 2014-05-28 东北石油大学 Suspension-in-water conveying pipeline and construction method thereof
CN104989875A (en) * 2015-05-19 2015-10-21 中国海洋石油总公司 Submarine pipeline flange underwater abutting joint installation method
CN105570535A (en) * 2016-01-14 2016-05-11 浙江海洋学院 Safety tunneling-preventing mechanism for submarine pipeline
CN106247012A (en) * 2016-08-16 2016-12-21 青岛理工大学 Pneumatic pressure access device for submarine pipeline
CN106704705A (en) * 2017-01-12 2017-05-24 中交天航南方交通建设有限公司 Water pipeline assembly operation method and system
CN106704705B (en) * 2017-01-12 2019-12-17 中交天航南方交通建设有限公司 Method and system for assembling a water pipeline
CN108488485A (en) * 2018-04-03 2018-09-04 航天晨光股份有限公司 A kind of naval vessel Large Diameter Pipeline delivery hose suspension arrangement and its installation method
CN110410579A (en) * 2019-07-15 2019-11-05 中海石油深海开发有限公司 The installation method of deep water surface conductor pipe
CN113064175A (en) * 2021-03-26 2021-07-02 西京学院 Seabed vacuum pipeline with preset sonar sensors and installation method
CN113064175B (en) * 2021-03-26 2023-10-27 西京学院 Submarine vacuum pipeline with preset sonar sensor and installation method

Also Published As

Publication number Publication date
CN1246619C (en) 2006-03-22

Similar Documents

Publication Publication Date Title
CN1246619C (en) Construction method and device for fixing seabed pipeline
RU2140595C1 (en) Unit for vertical laying of pipe line in water basin (versions)
CN107130600B (en) A kind of construction method for migrating formula automatic deviation correction single pile pile gripper construction mechanism
CN109853567B (en) Pile sinking method for offshore wind power rock-socketed steel pipe pile
US6039506A (en) Method and apparatus for the offshore installation of multi-ton packages such as deck packages and jackets
CN116348370A (en) Installation of wind turbines on floating foundations
CN1720165A (en) Riser installation vessel and method of using the same
JPH09508186A (en) High tension leg platform and its installation method
US6517291B1 (en) Riser tensioning construction
US20120201608A1 (en) Foundation for offshore wind turbine and method and means for its transportation and installation in deepwaters
US4909671A (en) Method for installation of a buoyant body on a sea bottom
CN102586784B (en) Method for assembling direct current cathode protection system outside platform
US5054963A (en) Tether system for an offshore based work platform
CN112411603A (en) Installation and construction process of offshore wind power booster station
CN216546599U (en) A hang and put device that is used for coastal waters geotechnical engineering shipborne reconnaissance to equip
US6244786B1 (en) Method for offshore load transfer operations and, a floater for offshore transport installation and removal of structural elements
JP2020117067A (en) Frame lifting device for vessel
CN2584986Y (en) Device for fixing submarine pipeline
CN1047814C (en) Offshore well saving apparatus and method
KR100568613B1 (en) Thruster mounting device and method of drilling ship
NZ249983A (en) Lifting cargo from rocking ship: system senses when ship has minimum kinetic energy
CN115258092A (en) Floating type water photovoltaic integral installation method
GB2222190A (en) Installing large, heavy structures on the sea bottom
CN217399592U (en) Steel construction device under complicated marine condition environment
JPH0833010B2 (en) Caisson installation method and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SINOPEC OILFIELD SERVICE CORPORATION

Free format text: FORMER OWNER: SHENGLI PETRO-CHEMICAL BUILDING CO LTD, SHANGLI OIL FIELD

Effective date: 20150710

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150710

Address after: 100029 Beijing Chaoyang District Hui Xin a No. twelve layer 6

Patentee after: SINOPEC OILFIELD SERVICE Corp.

Address before: 257073 Shandong province Dongying City West Road No. 444 Technology Development Center

Patentee before: SHENGLI OIL FIELD SHENGLI PETROLEUM & CHEMICAL CONSTRUCTION Corp.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20060322