CN117905481A - Large-section tunnel excavation structure and excavation method - Google Patents
Large-section tunnel excavation structure and excavation method Download PDFInfo
- Publication number
- CN117905481A CN117905481A CN202410101260.1A CN202410101260A CN117905481A CN 117905481 A CN117905481 A CN 117905481A CN 202410101260 A CN202410101260 A CN 202410101260A CN 117905481 A CN117905481 A CN 117905481A
- Authority
- CN
- China
- Prior art keywords
- excavation
- tunnel
- temporary
- construction
- area
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009412 basement excavation Methods 0.000 title claims abstract description 331
- 238000000034 method Methods 0.000 title claims abstract description 57
- 238000010276 construction Methods 0.000 claims abstract description 92
- 238000000465 moulding Methods 0.000 claims description 10
- 239000002689 soil Substances 0.000 claims description 8
- 239000002893 slag Substances 0.000 claims description 7
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 239000011435 rock Substances 0.000 abstract description 33
- 210000001624 hip Anatomy 0.000 abstract description 9
- 239000000463 material Substances 0.000 abstract description 6
- 229910000831 Steel Inorganic materials 0.000 description 24
- 239000010959 steel Substances 0.000 description 24
- 239000010410 layer Substances 0.000 description 17
- 238000010586 diagram Methods 0.000 description 12
- 239000004567 concrete Substances 0.000 description 3
- 238000013461 design Methods 0.000 description 3
- 238000005259 measurement Methods 0.000 description 3
- 239000011241 protective layer Substances 0.000 description 3
- 101001121408 Homo sapiens L-amino-acid oxidase Proteins 0.000 description 2
- 102100026388 L-amino-acid oxidase Human genes 0.000 description 2
- 101100012902 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) FIG2 gene Proteins 0.000 description 2
- 101100233916 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) KAR5 gene Proteins 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 238000005192 partition Methods 0.000 description 2
- 101000827703 Homo sapiens Polyphosphoinositide phosphatase Proteins 0.000 description 1
- 102100023591 Polyphosphoinositide phosphatase Human genes 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005422 blasting Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D19/00—Provisional protective covers for working space
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明公开了大断面隧道开挖结构,通过在待开挖地质体内形成有第一开挖区以及两个第二开挖区,两个第二开挖区间隔分布于第一开挖区的两侧,且第一开挖区以及两个第二开挖区均布置于隧道的两侧拱腰之间,第一开挖区以及两个第二开挖区均包括至少两个沿隧道的拱顶至仰拱的方向依次分布的开挖导洞,并且第一开挖区内与仰拱相邻的开挖导洞形成临时台阶,使得本发明在使用时对大断面隧道采用分部开挖,减小每部分开挖跨度和开挖高度,分部支护体系能够及时成环,减少对软弱围岩的多次扰动,有效控制围岩变形,确保开挖作业安全,减少了支撑材料用料,本发明还公开了大断面隧道开挖方法,降低了工程成本,提高了施工效率。
The invention discloses a large-section tunnel excavation structure. A first excavation area and two second excavation areas are formed in a geological body to be excavated. The two second excavation areas are spaced apart on both sides of the first excavation area, and the first excavation area and the two second excavation areas are arranged between the arch waists on both sides of the tunnel. The first excavation area and the two second excavation areas each include at least two excavation guide tunnels sequentially distributed along the direction from the arch crown to the invert arch of the tunnel, and the excavation guide tunnels adjacent to the invert arch in the first excavation area form a temporary step. When the invention is used, the large-section tunnel is excavated in sections, and the excavation span and excavation height of each section are reduced. The section support system can be ringed in time, and multiple disturbances to weak surrounding rocks are reduced. The deformation of the surrounding rocks is effectively controlled, the safety of the excavation operation is ensured, and the use of supporting materials is reduced. The invention also discloses a large-section tunnel excavation method, which reduces engineering costs and improves construction efficiency.
Description
技术领域Technical Field
本发明属于隧道施工技术领域,涉及大断面隧道开挖结构及开挖方法。The invention belongs to the technical field of tunnel construction, and relates to a large-section tunnel excavation structure and an excavation method.
背景技术Background technique
近年来,随着我国交通运输的跨越式发展,城市交通车流量越发提高,传统的两车道、三车道公路隧道现已无法满足同行需求,新建、扩建的公路隧道已广泛应用,高速公路隧道断面也增加到双向八车道,大跨度超大断面隧道施工技术相应产生,成为目前隧道工程建设主要攻克技术及研究热点。针对隧道建设过程出现超大断面的情况,现场一般采用单侧壁导坑法、双侧壁导坑法、CD法、CRD法等分部开挖方法。In recent years, with the leapfrog development of my country's transportation, the traffic volume of urban traffic has increased. Traditional two-lane and three-lane highway tunnels can no longer meet the needs of peers. Newly built and expanded highway tunnels have been widely used, and the cross-section of highway tunnels has also increased to eight lanes in both directions. Large-span and ultra-large cross-section tunnel construction technology has emerged accordingly, becoming the main technology and research hotspot for tunnel construction. In view of the situation of ultra-large cross-sections in the process of tunnel construction, the single-side wall pilot pit method, double-side wall pilot pit method, CD method, CRD method and other partial excavation methods are generally used on site.
以双侧壁导坑法开挖为例,该工法将隧道断面分为9个部分进行开挖,存在施工工序繁琐、工序衔接较多、机械化程度低、施工效率偏低、施工工期较长、工程成本较高、施工安全隐患较多等问题。Taking the double-side wall pilot tunnel excavation method as an example, this method divides the tunnel section into 9 parts for excavation. It has problems such as complicated construction procedures, many process connections, low degree of mechanization, low construction efficiency, long construction period, high project cost, and many construction safety hazards.
发明内容Summary of the invention
本发明的目的是提供大断面隧道开挖结构,解决现有技术中存在施工工序繁琐、工序衔接较多、机械化程度低、施工效率偏低、施工工期较长、工程成本较高、施工安全隐患较多的技术问题。The purpose of the present invention is to provide a large-section tunnel excavation structure to solve the technical problems in the prior art such as complicated construction procedures, many process connections, low degree of mechanization, low construction efficiency, long construction period, high project cost and many construction safety hazards.
本发明的另一个目的是提供大断面隧道开挖方法。Another object of the present invention is to provide a large-section tunnel excavation method.
本发明所采用的第一个技术方案是,大断面隧道开挖结构,包括待开挖地质体,待开挖地质体内形成有第一开挖区以及两个第二开挖区,两个第二开挖区间隔分布于第一开挖区的两侧,且第一开挖区以及两个第二开挖区均布置于隧道两侧拱腰之间,第一开挖区以及两个第二开挖区均包括至少两个沿隧道拱顶至仰拱的方向依次分布的开挖导洞,第一开挖区内与仰拱相邻的开挖导洞形成临时台阶。The first technical solution adopted by the present invention is a large-section tunnel excavation structure, including a geological body to be excavated, in which a first excavation area and two second excavation areas are formed, the two second excavation areas are distributed at intervals on both sides of the first excavation area, and the first excavation area and the two second excavation areas are arranged between the arch waists on both sides of the tunnel, the first excavation area and the two second excavation areas each include at least two excavation guide tunnels distributed in sequence along the direction from the tunnel arch to the invert arch, and the excavation guide tunnels adjacent to the invert arch in the first excavation area form temporary steps.
本发明所采用的第二个技术方案是,大断面隧道开挖方法,采用大断面隧道开挖结构,具体按以下步骤实施:The second technical solution adopted by the present invention is a large-section tunnel excavation method, which adopts a large-section tunnel excavation structure and is specifically implemented in the following steps:
步骤1,开挖两个第二开挖区内的开挖导洞,以在第二开挖区分别形成第一成型结构和第二成型结构;第一成型结构靠近第一开挖区的一侧为第一临时结构;第二成型结构靠近第一开挖区的一侧为第二临时结构;Step 1, excavating two excavation guide tunnels in the second excavation areas to form a first molding structure and a second molding structure in the second excavation areas respectively; a side of the first molding structure close to the first excavation area is a first temporary structure; a side of the second molding structure close to the first excavation area is a second temporary structure;
步骤2,对第一开挖区中靠近隧道的拱顶的开挖导洞进行开挖施工,形成第一开挖区中靠近隧道仰拱的开挖导洞所对应的临时台阶;Step 2, excavating the excavation guide tunnel near the arch of the tunnel in the first excavation area to form a temporary step corresponding to the excavation guide tunnel near the invert arch of the tunnel in the first excavation area;
步骤3,拆除第一临时结构、第二临时结构并对第一开挖区对应的拱顶、第一临时结构和第二临时结构的拱腰进行初期支护施工;Step 3, dismantling the first temporary structure and the second temporary structure and performing initial support construction on the arch corresponding to the first excavation area, the first temporary structure and the arch waist of the second temporary structure;
步骤4,继续对临时台阶以及隧道的仰拱进行开挖施工,形成隧道结构。Step 4: Continue excavating the temporary steps and the tunnel invert to form a tunnel structure.
本发明第二个技术方案的特点还在于:The second technical solution of the present invention is also characterized in that:
其中步骤1中第一成型结构的成型具体如下:The forming of the first forming structure in step 1 is specifically as follows:
两个第二开挖区中任一第二开挖区按照沿隧道的拱顶至仰拱的方向依次开挖各导洞,以在第二开挖区形成第一成型结构具体为:按照沿隧道的拱顶至仰拱的方向对靠近隧道的拱顶方向的开挖导洞开挖第一预设深度并进行初期支护施工,形成第一洞体结构;第一洞体结构包括第一临时仰拱以及第一临时结构,第一临时仰拱形成于第一洞体结构的底端,第一临时结构形成于第一洞体靠近第一开挖区的一侧;In any of the two second excavation areas, the pilot tunnels are sequentially excavated in the direction from the arch to the invert of the tunnel to form the first forming structure in the second excavation area. Specifically, the excavation pilot tunnel close to the arch direction of the tunnel is excavated to a first preset depth in the direction from the arch to the invert of the tunnel and initial support construction is performed to form a first tunnel structure; the first tunnel structure includes a first temporary invert and a first temporary structure, the first temporary invert is formed at the bottom end of the first tunnel structure, and the first temporary structure is formed on one side of the first tunnel close to the first excavation area;
继续按照沿隧道的拱顶至仰拱的方向开挖位于第一洞体结构下方的开挖导洞至第二预设深度,直至开挖完成对应的第二开挖区;第二预设深度小于第一预设深度;Continue to excavate the excavation pilot tunnel located below the first tunnel structure to a second preset depth along the direction from the arch to the invert of the tunnel until the corresponding second excavation area is excavated; the second preset depth is less than the first preset depth;
拆除第一临时仰拱并对已完成开挖的第二开挖区进行初期支护施工,得到第一成型结构;The first temporary invert is removed and initial support construction is performed on the second excavation area that has been excavated to obtain a first formed structure;
其中步骤1中第二成型结构的成型具体如下:The forming of the second forming structure in step 1 is specifically as follows:
另一第二开挖区按照沿隧道的拱顶至仰拱的方向依次开挖各导洞,以在另一第二开挖区形成第二成型结构,具体为:针对另一第二开挖区,按照沿隧道的拱顶至仰拱的方向对靠近隧道的拱顶方向的开挖导洞开挖第一预设深度并进行初期支护施工,形成第二洞体结构;第二洞体结构包括第二临时仰拱以及第二临时结构,第二临时仰拱形成于第二洞体结构的底端,第二临时结构形成于第二洞体靠近第一开挖区的一侧;The other second excavation area excavates the pilot tunnels in sequence along the direction from the arch to the invert of the tunnel, so as to form a second forming structure in the other second excavation area, specifically: for the other second excavation area, the excavation pilot tunnels close to the arch direction of the tunnel are excavated to a first preset depth along the direction from the arch to the invert of the tunnel and initial support construction is performed to form a second cave structure; the second cave structure includes a second temporary invert and a second temporary structure, the second temporary invert is formed at the bottom end of the second cave structure, and the second temporary structure is formed on one side of the second cave close to the first excavation area;
继续按照沿隧道的拱顶至仰拱的方向开挖位于第二洞体结构下方的开挖导洞至第二预设深度,直至开挖完成对应的第二开挖区;Continue to excavate the excavation pilot tunnel located below the second tunnel structure to a second preset depth along the direction from the arch to the invert of the tunnel until the corresponding second excavation area is excavated;
拆除第一临时仰拱并对已完成开挖的第二开挖区进行初期支护施工,得到第二成型结构;The first temporary invert is removed and initial support construction is performed on the second excavation area that has been excavated to obtain a second formed structure;
其中步骤2中临时台阶的成型具体如下:The forming of the temporary step in step 2 is as follows:
对第一开挖区中靠近隧道拱顶的开挖导洞进行开挖施工第一预设深度并进行初期支护施工,得到第三洞体;第一临时结构以及第二临时结构与位于隧道的拱顶的地质体共同围合形成第三洞体;Excavating the excavation pilot tunnel near the tunnel vault in the first excavation area to a first preset depth and performing initial support construction to obtain a third tunnel body; the first temporary structure and the second temporary structure are enclosed together with the geological body located at the tunnel vault to form the third tunnel body;
在第三洞体的底部施作第三临时仰拱,以使第一开挖区中靠近隧道的仰拱的开挖导洞所对应的地质体形成临时台阶;A third temporary invert is constructed at the bottom of the third tunnel body, so that a temporary step is formed in the geological body corresponding to the excavation guide tunnel of the invert close to the tunnel in the first excavation area;
其中步骤4中隧道结构形成具体如下:The tunnel structure formation in step 4 is specifically as follows:
对临时台阶以及隧道仰拱进行开挖施工至第三预设深度;第三预设深度小于第二预设深度;Excavating the temporary steps and the tunnel invert to a third preset depth; the third preset depth is less than the second preset depth;
对已完成开挖施工的第一开挖区域以及两个第二开挖区域进行支护施工,形成隧道结构;Carry out support construction on the first excavation area and two second excavation areas where excavation construction has been completed to form a tunnel structure;
其中步骤4中对已完成开挖施工的第一开挖区域以及两个第二开挖区域进行支护施工,形成隧道结构具体如下:对已完成开挖施工的第一开挖区域的仰拱以及两个第二开挖区域的仰拱进行初期支护施工并对隧道进行二次衬砌施工,形成隧道结构;In step 4, support construction is performed on the first excavation area and the two second excavation areas, where excavation construction has been completed, to form a tunnel structure as follows: initial support construction is performed on the inverted arch of the first excavation area and the two second excavation areas, and secondary lining construction is performed on the tunnel to form a tunnel structure;
其中二次衬砌施工,形成隧道结构具体为:The secondary lining construction to form the tunnel structure is as follows:
对已完成开挖施工的第一开挖区域的仰拱以及两个第二开挖区域的仰拱进行初期支护施工并对隧道进行二次衬砌施工;Carry out initial support construction on the inverts of the first excavation area where excavation construction has been completed and the two inverts of the second excavation area, and carry out secondary lining construction on the tunnel;
重复执行针对任一第二开挖区按照沿隧道的拱顶至仰拱的方向依次开挖各导洞,以在第二开挖区形成第一成型结构的步骤,直至洞通隧道,形成隧道结构;Repeat the step of sequentially excavating each pilot tunnel in any second excavation area along the direction from the arch to the invert of the tunnel to form a first forming structure in the second excavation area until the tunnel is bored through to form a tunnel structure;
其中对已完成开挖施工的第一开挖区域的仰拱以及两个第二开挖区域的仰拱进行初期支护施工并对隧道进行二次衬砌施工,形成隧道结构具体为:The inverted arches in the first excavation area and the two inverted arches in the second excavation area that have been excavated are initially supported and the tunnel is relined to form a tunnel structure as follows:
对已完成开挖施工的第一开挖区域的仰拱以及两个第二开挖区域的仰拱二次衬砌施工,形成隧道结构进行支护施工;The invert arch of the first excavation area and the invert arches of the two second excavation areas that have been excavated are relined to form a tunnel structure for support construction;
在已完成开挖施工的隧道的仰拱上填充渣土,并对已完成渣土填充之后的仰拱进行路面施工,形成隧道结构;Filling the invert of the tunnel that has been excavated with slag, and performing road surface construction on the invert after the slag filling has been completed, to form a tunnel structure;
其中针对任一第二开挖区按照沿隧道的拱顶至仰拱的方向依次开挖各导洞,以在第二开挖区形成第一成型结构的步骤之前,还包括利用具有预设参数的超前支护构件对第一开挖区以及两个第二开挖区进行超前支护施工。Wherein, for any second excavation area, each guide tunnel is excavated in sequence along the direction from the arch crown to the invert arch of the tunnel to form a first forming structure in the second excavation area, and the method also includes using an advance support component with preset parameters to perform advance support construction on the first excavation area and the two second excavation areas.
本发明的有益效果是:The beneficial effects of the present invention are:
本发明的大断面隧道开挖结构通过在待开挖地质体内形成有第一开挖区以及两个第二开挖区,两个第二开挖区间隔分布于第一开挖区的两侧,且第一开挖区以及两个第二开挖区均布置于隧道的两侧拱腰之间,第一开挖区以及两个第二开挖区均包括至少两个沿隧道的拱顶至仰拱的方向依次分布的开挖导洞,并且第一开挖区内与仰拱相邻的开挖导洞形成临时台阶,使得本发明在使用时对大断面隧道采用分部开挖,减小每部分开挖跨度和开挖高度,分部支护体系能够及时成环,减少对软弱围岩的多次扰动,有效控制围岩变形,确保开挖作业安全;同时的,在将第一开挖区内与隧道的仰拱相连的开挖导洞作为临时台阶,使得本发明在使用时可以充分发挥下部围岩的承载力,由下台阶预留土和上台阶临时钢架支撑组成临时支撑体系,减少了支撑材料用料,降低了工程成本,提高了施工效率。The large-section tunnel excavation structure of the present invention forms a first excavation area and two second excavation areas in a geological body to be excavated, the two second excavation areas are spaced apart on both sides of the first excavation area, and the first excavation area and the two second excavation areas are arranged between the arch waists on both sides of the tunnel, the first excavation area and the two second excavation areas each include at least two excavation guide tunnels sequentially distributed along the direction from the arch top to the invert of the tunnel, and the excavation guide tunnels adjacent to the invert in the first excavation area form temporary steps, so that the present invention adopts partial excavation for the large-section tunnel when in use, reduces the excavation span and excavation height of each part, and the partial support system can be ringed in time, reduces multiple disturbances to the weak surrounding rock, effectively controls the deformation of the surrounding rock, and ensures the safety of the excavation operation; at the same time, the excavation guide tunnel connected to the invert of the tunnel in the first excavation area is used as a temporary step, so that the present invention can give full play to the bearing capacity of the lower surrounding rock when in use, and the temporary support system is composed of the reserved soil of the lower step and the temporary steel frame support of the upper step, which reduces the use of support materials, reduces the engineering cost, and improves the construction efficiency.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1为本发明的大断面隧道开挖结构的结构示意图;FIG1 is a schematic structural diagram of a large-section tunnel excavation structure of the present invention;
图2为本发明的大断面隧道开挖方法的流程图;FIG2 is a flow chart of a large-section tunnel excavation method according to the present invention;
图3为本发明的大断面隧道开挖方法步骤1中第一成型结构成型的流程图;FIG3 is a flow chart of forming the first forming structure in step 1 of the large-section tunnel excavation method of the present invention;
图4为本发明的大断面隧道开挖方法中步骤1.1中的隧道断面示意图;FIG4 is a schematic diagram of a tunnel cross section in step 1.1 of the large-section tunnel excavation method of the present invention;
图5为本发明的大断面隧道开挖方法中步骤1.2中的隧道断面示意图;FIG5 is a schematic diagram of the tunnel cross section in step 1.2 of the large-section tunnel excavation method of the present invention;
图6为本发明的大断面隧道开挖方法步骤1中第二成型结构成型的流程图;FIG6 is a flow chart of forming the second forming structure in step 1 of the large-section tunnel excavation method of the present invention;
图7为本发明的大断面隧道开挖方法中形成第二洞体结构时的隧道断面示意图;7 is a schematic diagram of a tunnel cross section when a second tunnel structure is formed in the large-section tunnel excavation method of the present invention;
图8为本发明的大断面隧道开挖方法中形成第二开挖区时的隧道断面示意图;FIG8 is a schematic diagram of a tunnel cross section when a second excavation zone is formed in the large-section tunnel excavation method of the present invention;
图9为本发明的大断面隧道开挖方法中形成临时台阶的流程示意图;FIG9 is a schematic diagram of a process for forming a temporary step in a large-section tunnel excavation method of the present invention;
图10为本发明的大断面隧道开挖方法中得到第三洞体时的隧道断面示意图;FIG10 is a schematic diagram of a tunnel cross section when a third tunnel body is obtained in the large-section tunnel excavation method of the present invention;
图11为本发明的大断面隧道开挖方法中形成临时台阶时的隧道断面示意图;FIG11 is a schematic diagram of a tunnel cross section when a temporary step is formed in the large-section tunnel excavation method of the present invention;
图12为本发明的大断面隧道开挖方法中完成隧道结构设计的流程图;FIG12 is a flow chart showing the completion of the tunnel structure design in the large-section tunnel excavation method of the present invention;
图13为本发明的大断面隧道开挖方法中开挖至第三预设深度时的隧道断面示意图;13 is a schematic diagram of a tunnel cross section when excavating to a third preset depth in the large-section tunnel excavation method of the present invention;
图14为本发明的大断面隧道开挖方法中进行二次衬砌施工后的隧道断面示意图;FIG14 is a schematic diagram of a tunnel cross section after secondary lining construction in the large-section tunnel excavation method of the present invention;
图15为本发明的大断面隧道开挖方法中进行二次衬砌施工的流程图;FIG15 is a flow chart of secondary lining construction in the large-section tunnel excavation method of the present invention;
图16为本发明的大断面隧道开挖方法添加准备工作流程后的整体流程图;FIG16 is an overall flow chart of the large-section tunnel excavation method of the present invention after adding a preparation workflow;
图17为本发明大断面隧道开挖方法具体实施后形成的隧道断面示意图;FIG17 is a schematic diagram of a tunnel section formed after the large-section tunnel excavation method of the present invention is implemented;
图18为本发明大断面隧道开挖方法不同工况下形成的隧道断面示意图。FIG18 is a schematic diagram of the tunnel section formed under different working conditions of the large-section tunnel excavation method of the present invention.
图中,1.待开挖地质体,2.第一开挖区,3.第二开挖区,4.第一临时结构,5.第二层初期支护,6.第二临时结构,7.临时台阶,8.第一层初期支护,9.二次衬砌。In the figure, 1. geological body to be excavated, 2. first excavation area, 3. second excavation area, 4. first temporary structure, 5. second layer of initial support, 6. second temporary structure, 7. temporary steps, 8. first layer of initial support, 9. secondary lining.
具体实施方式Detailed ways
下面结合附图和具体实施方式对本发明进行详细说明。The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
本发明提供了大断面隧道开挖结构,具体如下述实施例所示:The present invention provides a large-section tunnel excavation structure, as shown in the following embodiments:
实施例1,大断面隧道开挖结构具体如下:Example 1, large cross-section tunnel excavation structure is as follows:
本实施例中,如图1所示,大断面隧道开挖结构,包括待开挖地质体1,待开挖地质体1内形成有第一开挖区2以及两个第二开挖区3,两个第二开挖区3间隔分布于第一开挖区2的两侧,且第一开挖区2以及两个第二开挖区3均布置于隧道的两侧拱腰之间,第一开挖区2以及两个第二开挖区3均包括至少两个沿隧道的拱顶至仰拱的方向依次分布的开挖导洞,且,第一开挖区2内与仰拱相邻的开挖导洞形成临时台阶7;In this embodiment, as shown in FIG1 , a large-section tunnel excavation structure includes a geological body 1 to be excavated, a first excavation area 2 and two second excavation areas 3 are formed in the geological body 1 to be excavated, the two second excavation areas 3 are distributed at intervals on both sides of the first excavation area 2, and the first excavation area 2 and the two second excavation areas 3 are arranged between the arch waists on both sides of the tunnel, the first excavation area 2 and the two second excavation areas 3 each include at least two excavation guide tunnels distributed in sequence along the direction from the arch crown to the invert arch of the tunnel, and the excavation guide tunnels adjacent to the invert arch in the first excavation area 2 form a temporary step 7;
在本实施例中,通过在待开挖地质体1内形成有第一开挖区2以及两个第二开挖区3,两个第二开挖区3间隔分布于第一开挖区2的两侧,且第一开挖区2以及两个第二开挖区3均布置于隧道的两侧拱腰之间,第一开挖区2以及两个第二开挖区3均包括至少两个沿隧道的拱顶至仰拱的方向依次分布的开挖导洞,并且第一开挖区2内与仰拱相邻的开挖导洞形成临时台阶7,使得本发明在使用时对大断面隧道采用分部开挖,减小每部分开挖跨度和开挖高度,分部支护体系能够及时成环,减少对软弱围岩的多次扰动,有效控制围岩变形,确保开挖作业安全;同时的,在将第一开挖区2内与隧道的仰拱相连的开挖导洞作为临时台阶7,使得本发明在使用时可以充分发挥下部围岩的承载力,由下台阶预留土和上台阶临时钢架支撑组成临时支撑体系,减少了支撑材料用料,降低了工程成本,提高了施工效率。In this embodiment, a first excavation area 2 and two second excavation areas 3 are formed in the geological body 1 to be excavated, the two second excavation areas 3 are spaced apart on both sides of the first excavation area 2, and the first excavation area 2 and the two second excavation areas 3 are arranged between the arch waists on both sides of the tunnel, the first excavation area 2 and the two second excavation areas 3 each include at least two excavation guide tunnels sequentially distributed along the direction from the arch crown to the invert arch of the tunnel, and the excavation guide tunnels adjacent to the invert arch in the first excavation area 2 form a temporary step 7, so that the present invention can be used for large-section tunnels when in use. The tunnel is excavated in sections to reduce the excavation span and excavation height of each section. The section support system can be ringed in time, reducing multiple disturbances to the weak surrounding rock, effectively controlling the deformation of the surrounding rock, and ensuring the safety of the excavation operation. At the same time, the excavation guide tunnel connected to the tunnel invert in the first excavation area 2 is used as a temporary step 7, so that the bearing capacity of the lower surrounding rock can be fully utilized when the present invention is used. The temporary support system is composed of the reserved soil of the lower step and the temporary steel frame support of the upper step, which reduces the use of support materials, reduces the engineering cost, and improves the construction efficiency.
实施例2,大断面隧道开挖结构的开挖方法具体如下:Embodiment 2, the excavation method of the large-section tunnel excavation structure is as follows:
本发明提出大断面隧道施工方法,应用于大断面隧道开挖结构;为了便于理解本发明,下述将第一开挖区2以及两个第二开挖区3均包括两个在竖向依次层叠设置的开挖导洞为例进行说明,如图2所示:The present invention proposes a large-section tunnel construction method, which is applied to a large-section tunnel excavation structure. To facilitate understanding of the present invention, the following description is made by taking an example in which the first excavation area 2 and the two second excavation areas 3 each include two excavation guide tunnels stacked vertically in sequence, as shown in FIG2 :
具体地,具体按以下步骤实施:Specifically, the following steps are implemented:
步骤1,如图3所示,针对任一第二开挖区3按照沿隧道的拱顶至仰拱的方向依次开挖各导洞,以在第二开挖区3形成第一成型结构;第一成型结构靠近第一开挖区2的一侧为第一临时结构4;Step 1, as shown in FIG3 , for any second excavation area 3 , guide tunnels are excavated in sequence along the direction from the arch to the invert of the tunnel to form a first forming structure in the second excavation area 3 ; a first temporary structure 4 is formed on one side of the first forming structure close to the first excavation area 2 ;
在本实施例中,将隧道断面从起拱线位置按左导洞、中导洞和右导洞(其中,左右导洞为第二开挖区3,中导洞为第一开挖区2分别分成上下台阶(其中上下导洞均为开挖导洞),左导洞分2部开挖,中导洞分2部开挖,右导洞分2部开挖,共分为6部分别开挖支护;先行钻眼爆破开挖左导洞上台阶,开挖进尺控制在1榀钢架距离,开挖完成后施作正洞第一层初期支护8,形成第一临时结构4:φ25中空注浆锚杆,锚杆长4.5m,间距100×60mm,梅花形布置每环18根、φ8钢筋网片:间距200×200mm、I22b型钢拱架:间距0.6m,全环施作,与围岩间保护层厚度4cm,临空一侧保护层厚度2cm、锁脚锚杆:8根长4.5m的φ42注浆小导管,最后喷射28cm厚C20混凝土;In this embodiment, the tunnel section is divided into upper and lower steps (wherein the upper and lower guide tunnels are both excavation guide tunnels) from the arch line position according to the left guide tunnel, the middle guide tunnel and the right guide tunnel (wherein the left and right guide tunnels are the second excavation area 3, and the middle guide tunnel is the first excavation area 2), the left guide tunnel is excavated in 2 parts, the middle guide tunnel is excavated in 2 parts, and the right guide tunnel is excavated in 2 parts, a total of 6 parts are excavated and supported separately; the upper step of the left guide tunnel is excavated by drilling and blasting first, and the excavation footage is controlled within the distance of 1 steel frame. After the excavation is completed, the first layer of the main tunnel is constructed. Initial support 8, forming the first temporary structure 4: φ25 hollow grouting anchor rod, anchor rod length 4.5m, spacing 100×60mm, plum blossom arrangement 18 per ring, φ8 steel mesh: spacing 200×200mm, I22b steel arch frame: spacing 0.6m, full ring construction, protective layer thickness between the surrounding rock 4cm, protective layer thickness 2cm on the side facing the air, locking anchor rod: 8 φ42 grouting small pipes with a length of 4.5m, and finally spraying 28cm thick C20 concrete;
左导洞的上台阶开挖支护长度大于30m后,需要特别和明确说明的是,实施例中示例的第一预设深度为30m,进行左导洞下台阶部围岩的开挖;当中导洞的下台阶围岩承载力满足临时钢架支撑要求时,左导洞下台阶部开挖上端预留4m宽行车道,下端开挖至设计轮廓线,开挖进尺为1榀钢架距离,开挖完成后,采用第一临时结构400的支护参数施作初期支护,形成第一成型结构;After the excavation support length of the upper step of the left guide tunnel is greater than 30m, it is necessary to specifically and clearly explain that the first preset depth in the example in the embodiment is 30m, and the excavation of the surrounding rock of the lower step of the left guide tunnel is carried out; when the bearing capacity of the surrounding rock of the lower step of the middle guide tunnel meets the requirements of temporary steel frame support, a 4m wide lane is reserved at the upper end of the excavation of the lower step of the left guide tunnel, and the lower end is excavated to the design contour line, and the excavation footage is 1 steel frame distance. After the excavation is completed, the support parameters of the first temporary structure 400 are used for initial support to form a first forming structure;
左右导洞开挖步距不小于30m时,进行右导洞上台阶开挖,开挖进尺控制在1榀钢架距离,开挖完成后采用第一临时结构4的支护参数施作初期支护,得到第二临时结构6;When the excavation step distance of the left and right guide tunnels is not less than 30m, the upper step excavation of the right guide tunnel is carried out, and the excavation advance is controlled within the distance of one steel frame. After the excavation is completed, the support parameters of the first temporary structure 4 are used for initial support to obtain the second temporary structure 6;
如图6所示,对另一第二开挖区3按照沿隧道的拱顶至仰拱的方向依次开挖各导洞,以在另一第二开挖区3形成第二成型结构;其中,第二成型结构靠近第一开挖区2的一侧为第二临时结构6;As shown in FIG6 , the pilot tunnels are sequentially excavated in the other second excavation area 3 in the direction from the arch to the invert of the tunnel, so as to form a second forming structure in the other second excavation area 3; wherein the second forming structure is close to the first excavation area 2 on one side thereof as a second temporary structure 6;
在本实施例中,右导洞的上台阶开挖支护长度大于30m后,进行右导洞下台阶围岩的开挖。当中导洞的下台阶围岩承载力满足临时钢架支撑要求时,右导洞下台阶开挖上端预留4m宽行车道,下端开挖至设计轮廓线。开挖进尺为1榀钢架距离,开挖完成后,采用第一临时结构4的支护参数施作第一层初期支护8,得到第二成型结构;In this embodiment, after the excavation support length of the upper step of the right guide tunnel is greater than 30m, the excavation of the surrounding rock of the lower step of the right guide tunnel is carried out. When the bearing capacity of the surrounding rock of the lower step of the middle guide tunnel meets the requirements of temporary steel frame support, a 4m wide driving lane is reserved at the upper end of the excavation of the lower step of the right guide tunnel, and the lower end is excavated to the design contour line. The excavation advance is 1 steel frame distance. After the excavation is completed, the first layer of initial support 8 is applied using the support parameters of the first temporary structure 4 to obtain the second forming structure;
步骤2,如图9所示,对所第一开挖区2中靠近隧道的拱顶的开挖导洞进行开挖施工,以使第一开挖区2中靠近隧道的仰拱的开挖导洞所对应的地质体形成临时台阶7;Step 2, as shown in FIG9 , excavating the excavation guide tunnel near the arch of the tunnel in the first excavation area 2, so that the geological body corresponding to the excavation guide tunnel near the invert of the tunnel in the first excavation area 2 forms a temporary step 7;
在本实施例中,当左导洞与右导洞掌子面与中导洞掌子面相距6m~8m,需要特别和明确说明的是,第三预设深度为6m~8m时,可独立同步开挖和支护;中导洞开挖安全步距IV级围岩为40m,V级围岩50m,中导洞上台阶开挖进尺为1榀钢架距离,开挖完成后,采用第一临时结构4的支护参数施作第一层初期支护8;In this embodiment, when the left and right pilot tunnels are 6m to 8m apart from the middle pilot tunnel, it should be particularly and clearly stated that when the third preset depth is 6m to 8m, independent synchronous excavation and support can be performed; the middle pilot tunnel excavation safety step distance for IV grade surrounding rock is 40m, and for V grade surrounding rock is 50m, and the excavation footage of the upper step of the middle pilot tunnel is 1 steel frame distance. After the excavation is completed, the support parameters of the first temporary structure 4 are used to apply the first layer of initial support 8;
步骤3,拆除第一临时结构4、第二临时结构6并对第一开挖区2对应的拱顶、第一临时结构4和第二临时结构6的拱腰进行初期支护施工;Step 3, dismantling the first temporary structure 4 and the second temporary structure 6 and performing initial support construction on the arch corresponding to the first excavation area 2, the first temporary structure 4 and the arch waist of the second temporary structure 6;
在本实施例中,待初期支护拱顶变形稳定后,拆除第一临时结构4以及第二临时结构6,拆除过程中加强拱顶沉降量测,保证隧道安全;首先采取隔3m拆1m的方法,在两侧壁或中隔壁钢架顶部切开3m~5cm,量测隧道变形量和变形速率;隧道变形量和变形速率在正常范围内时,采取隔1m拆1m的方法,切开两侧壁或中隔壁支撑钢架顶部,观测隧道变形量和变形速率;严禁连续切开钢架,以防止临时支撑突然失稳,倒塌伤人;变形稳定后,分析监控量测结果,确保隧道初期支护的稳定性;In this embodiment, after the initial support arch deformation is stable, the first temporary structure 4 and the second temporary structure 6 are dismantled, and the arch settlement measurement is strengthened during the dismantling process to ensure the safety of the tunnel; firstly, the method of dismantling 1m every 3m is adopted, and 3m to 5cm is cut on the top of the steel frame of the two side walls or the middle partition wall to measure the deformation and deformation rate of the tunnel; when the deformation and deformation rate of the tunnel are within the normal range, the method of dismantling 1m every 1m is adopted, and the top of the supporting steel frame of the two side walls or the middle partition wall is cut to observe the deformation and deformation rate of the tunnel; it is strictly forbidden to cut the steel frame continuously to prevent the temporary support from suddenly becoming unstable and collapsing and injuring people; after the deformation is stable, the monitoring measurement results are analyzed to ensure the stability of the initial support of the tunnel;
步骤4,如图12所示,继续对临时台阶7以及隧道的仰拱进行开挖施工,形成隧道结构:Step 4, as shown in FIG12 , continues to excavate the temporary step 7 and the invert of the tunnel to form a tunnel structure:
在本实施例中,第一临时结构4以及第二临时结构6拆除后,开挖中导洞下台阶,开挖进尺控制在1榀钢架距离,开挖完成后采用第一临时结构4的支护参数施作第一层初期支护8;In this embodiment, after the first temporary structure 4 and the second temporary structure 6 are removed, the lower step of the middle guide tunnel is excavated, and the excavation advance is controlled within the distance of one steel frame. After the excavation is completed, the support parameters of the first temporary structure 4 are used to apply the first layer of initial support 8;
中导洞下台阶初期支护施作完毕且达到设计强度后,进行第二层初期支护5施工。第二层初期支护5施工前,先将仰拱用洞渣回填平整,为第二层初期支护5施作提供场地,第二层初支护采用I22b型钢拱架:60cm/榀、间距为200×200mm的φ8钢筋网和喷射24cm厚的C20混凝土,钢架靠围岩侧(隧道外侧)保护层厚度不小于4cm,临空侧(隧道内侧)不小于2cm;本发明采用双层初期支护形式,有效保证了隧道埋深较浅、开挖断面大情况下周边围岩的稳定性,且双层初支能够及时施作封闭成环,降低了隧道垮塌风险,提高了施工安全;After the initial support of the lower step of the middle guide tunnel is completed and reaches the designed strength, the second layer of initial support 5 is constructed. Before the construction of the second layer of initial support 5, the invert is backfilled and leveled with tunnel slag to provide a site for the construction of the second layer of initial support 5. The second layer of initial support adopts I22b steel arch frame: 60cm/frame, φ8 steel mesh with a spacing of 200×200mm and 24cm thick C20 concrete sprayed. The thickness of the protective layer of the steel frame on the surrounding rock side (outside of the tunnel) is not less than 4cm, and on the air side (inside of the tunnel) is not less than 2cm; the present invention adopts a double-layer initial support form, which effectively ensures the stability of the surrounding rock when the tunnel is shallow and the excavation section is large, and the double-layer initial support can be timely constructed to form a closed ring, which reduces the risk of tunnel collapse and improves construction safety;
完成第二次初期支护之后再进行二次衬砌施工,二次衬砌9施作应通过监控量测,在围岩与双层初期支护变形基本稳定后进行;二衬采用70cm厚C30钢筋混凝土结构,采用模板台车和有压泵送混凝土整体浇注,并在浇注过程中保证电、料的持续供应,浇注不得中断;After the second initial support is completed, the secondary lining construction will be carried out. The construction of the secondary lining 9 should be carried out after the deformation of the surrounding rock and the double-layer initial support is basically stable through monitoring and measurement; the second lining adopts a 70cm thick C30 reinforced concrete structure, and is poured as a whole using a formwork trolley and pressurized concrete pumping. During the pouring process, the continuous supply of electricity and materials is guaranteed, and the pouring shall not be interrupted;
在本实施例中,通过在待开挖地质体1内形成有第一开挖区2以及两个第二开挖区3,两个第二开挖区3间隔分布于第一开挖区2的两侧,且第一开挖区2以及两个第二开挖区3均布置于隧道的两侧拱腰之间,第一开挖区2以及两个第二开挖区3均包括至少两个沿隧道的拱顶至仰拱的方向依次分布的开挖导洞,并且第一开挖区2内与仰拱相邻的开挖导洞形成临时台阶7,使得本发明在使用时对大断面隧道采用分部开挖,减小每部分开挖跨度和开挖高度,分部支护体系能够及时成环,减少对软弱围岩的多次扰动,有效控制围岩变形,确保开挖作业安全;同时的,在将第一开挖区2内与隧道的仰拱相连的开挖导洞作为临时台阶7,使得本发明在使用时可以充分发挥下部围岩的承载力,由下台阶预留土和上台阶临时钢架支撑组成临时支撑体系,减少了支撑材料用料,降低了工程成本,提高了施工效率。In this embodiment, a first excavation area 2 and two second excavation areas 3 are formed in the geological body 1 to be excavated, the two second excavation areas 3 are spaced apart on both sides of the first excavation area 2, and the first excavation area 2 and the two second excavation areas 3 are arranged between the arch waists on both sides of the tunnel, the first excavation area 2 and the two second excavation areas 3 each include at least two excavation guide tunnels sequentially distributed along the direction from the arch crown to the invert arch of the tunnel, and the excavation guide tunnels adjacent to the invert arch in the first excavation area 2 form a temporary step 7, so that the present invention can be used for large-section tunnels when in use. The tunnel is excavated in sections to reduce the excavation span and excavation height of each section. The section support system can be ringed in time, reducing multiple disturbances to the weak surrounding rock, effectively controlling the deformation of the surrounding rock, and ensuring the safety of the excavation operation. At the same time, the excavation guide tunnel connected to the tunnel invert in the first excavation area 2 is used as a temporary step 7, so that the bearing capacity of the lower surrounding rock can be fully utilized when the present invention is used. The temporary support system is composed of the reserved soil of the lower step and the temporary steel frame support of the upper step, which reduces the use of support materials, reduces the engineering cost, and improves the construction efficiency.
实施例3Example 3
如图16所示,大断面隧道开挖方法,具体按以下步骤实施:As shown in Figure 16, the large-section tunnel excavation method is specifically implemented in the following steps:
步骤1具体按以下步骤实施,如图4和图5所示:Step 1 is specifically implemented according to the following steps, as shown in Figures 4 and 5:
步骤1.1,针对任一第二开挖区3,按照沿隧道的拱顶至仰拱的方向对靠近隧道的拱顶方向的开挖导洞开挖第一预设深度并进行初期支护施工,形成第一洞体结构;其中,第一洞体结构包括第一临时仰拱以及第一临时结构4,第一临时仰拱形成于是第一洞体结构的底端,第一临时结构4形成于第一洞体靠近第一开挖区2的一侧;Step 1.1, for any second excavation area 3, excavate a first preset depth in the excavation pilot tunnel in the direction from the tunnel vault to the invert and perform initial support construction to form a first tunnel structure; wherein the first tunnel structure includes a first temporary invert and a first temporary structure 4, the first temporary invert is formed at the bottom of the first tunnel structure, and the first temporary structure 4 is formed on one side of the first tunnel close to the first excavation area 2;
步骤1.2,继续按照沿隧道的拱顶至仰拱的方向开挖位于第一洞体结构下方的开挖导洞至第二预设深度,直至开挖完成对应的第二开挖区3;第二预设深度小于第一预设深度;Step 1.2, continue to excavate the excavation pilot tunnel located below the first cave structure to a second preset depth along the direction from the arch to the invert of the tunnel until the corresponding second excavation area 3 is excavated; the second preset depth is less than the first preset depth;
步骤1.3,拆除第一临时仰拱并对已完成开挖的第二开挖区3进行初期支护施工,得到第一成型结构;Step 1.3, dismantling the first temporary invert and performing initial support construction on the excavated second excavation area 3 to obtain a first formed structure;
如图7和图8所示:As shown in Figure 7 and Figure 8:
步骤1.4,针对另一第二开挖区3,按照沿隧道的拱顶至仰拱的方向对靠近隧道的拱顶方向的开挖导洞开挖第一预设深度并进行初期支护施工,形成第二洞体结构;其中,第二洞体结构包括第二临时仰拱以及第二临时结构6,第二临时仰拱形成于是第二洞体结构的底端,第二临时结构6形成于第二洞体靠近第一开挖区2的一侧;Step 1.4, for another second excavation area 3, excavate a first preset depth in the excavation pilot tunnel in the direction from the tunnel vault to the invert and perform initial support construction to form a second tunnel structure; wherein the second tunnel structure includes a second temporary invert and a second temporary structure 6, the second temporary invert is formed at the bottom of the second tunnel structure, and the second temporary structure 6 is formed on one side of the second tunnel close to the first excavation area 2;
步骤1.5,继续按照沿隧道的拱顶至仰拱的方向开挖位于第二洞体结构下方的开挖导洞至第二预设深度,直至开挖完成对应的第二开挖区3;Step 1.5, continue to excavate the excavation pilot tunnel located below the second tunnel structure to a second preset depth along the direction from the arch to the invert of the tunnel, until the corresponding second excavation area 3 is excavated;
步骤1.6,拆除第一临时仰拱并对已完成开挖的第二开挖区3进行初期支护施工,得到第二成型结构;Step 1.6, dismantling the first temporary invert and performing initial support construction on the second excavation area 3 that has been excavated to obtain a second formed structure;
在本实施例中,将大断面隧道采用分部开挖,减小每部分开挖跨度和开挖高度,分部支护体系能够及时成环,减少对软弱围岩的多次扰动,有效控制围岩变形,确保开挖作业安全;In this embodiment, the large-section tunnel is excavated in sections to reduce the excavation span and height of each section. The section support system can be ringed in time, reducing multiple disturbances to the soft surrounding rock, effectively controlling the deformation of the surrounding rock, and ensuring the safety of the excavation operation.
步骤2具体按以下步骤实施,如图10和图11所示:Step 2 is specifically implemented according to the following steps, as shown in Figures 10 and 11:
步骤2.1,对第一开挖区2中靠近隧道的拱顶的开挖导洞进行开挖施工第一预设深度并进行初期支护施工,得到第三洞体;其中,第一临时结构4以及第二临时结构6与位于隧道的拱顶的地质体共同围合形成第三洞体;Step 2.1, excavating the excavation pilot tunnel near the arch of the tunnel in the first excavation area 2 to a first preset depth and performing initial support construction to obtain a third tunnel body; wherein the first temporary structure 4 and the second temporary structure 6 and the geological body located at the arch of the tunnel are enclosed together to form the third tunnel body;
步骤2.1,在第三洞体的底部施作第三临时仰拱,以使第一开挖区2中靠近隧道的仰拱的开挖导洞所对应的地质体形成临时台阶7;Step 2.1, constructing a third temporary invert at the bottom of the third tunnel body, so that the geological body corresponding to the excavation guide tunnel of the invert close to the tunnel in the first excavation area 2 forms a temporary step 7;
在本实施例中,充分发挥下部围岩的承载力,由下台阶预留土和上台阶临时钢架支撑组成临时支撑体系,减少了支撑材料用料,降低了工程成本;In this embodiment, the bearing capacity of the lower surrounding rock is fully utilized, and a temporary support system is formed by the reserved soil of the lower step and the temporary steel frame support of the upper step, which reduces the support material and reduces the engineering cost;
步骤3,拆除第一临时结构4、第二临时结构6并对第一开挖区对应的拱顶、第一临时结构和第二临时结构的拱腰进行初期支护施工;Step 3, dismantling the first temporary structure 4 and the second temporary structure 6 and performing initial support construction on the arch corresponding to the first excavation area, the first temporary structure and the arch waist of the second temporary structure;
步骤4具体按以下步骤实施,如图13和图14所示:Step 4 is specifically implemented according to the following steps, as shown in Figures 13 and 14:
步骤4.1,继续对临时台阶7以及隧道的仰拱进行开挖施工至第三预设深度;其中,第三预设深度小于第二预设深度;Step 4.1, continue to excavate the temporary step 7 and the invert of the tunnel to a third preset depth; wherein the third preset depth is less than the second preset depth;
步骤4.2,对已完成开挖施工的第一开挖区2域的仰拱以及两个第二开挖区3域的仰拱进行初期支护施工并对隧道进行二次衬砌施工,形成隧道结构;Step 4.2, performing initial support construction on the inverted arch of the first excavation area 2 and the two inverted arches of the second excavation area 3, and performing secondary lining construction on the tunnel to form a tunnel structure;
在本实施例中,下台阶预留土作为承载墙的同时,还作为左右导坑上台阶的施工便道,可使各工作面同时施工,相较传统双侧壁多次开挖,仅需少量的开挖次数即可开挖完成,减少了两个侧壁下部的临时支护,工序简单,有效降低了对围岩的多次扰动,显著加快施工效率;In this embodiment, the reserved soil of the lower step is used as a bearing wall and also as a construction path for the upper steps of the left and right guide pits, so that each working surface can be constructed at the same time. Compared with the traditional double-side wall excavation, only a small number of excavations are required to complete the excavation, reducing the temporary support of the lower part of the two side walls, simplifying the process, effectively reducing the multiple disturbances to the surrounding rock, and significantly accelerating the construction efficiency;
如图15所示,步骤4.2具体如下:As shown in FIG. 15 , step 4.2 is as follows:
步骤4.2.1,对已完成开挖施工的第一开挖区2域的仰拱以及两个第二开挖区300域的仰拱进行初期支护施工并对隧道进行二次衬砌施工;Step 4.2.1, perform initial support construction on the inverts of the first excavation area 2 and the two inverts of the second excavation area 300, and perform secondary lining construction on the tunnel;
步骤4.2.2,重复执行针对任一第二开挖区3按照沿隧道的拱顶至仰拱的方向依次开挖各导洞,以在第二开挖区3形成第一成型结构的步骤,直至洞通隧道,形成隧道结构;Step 4.2.2, repeatedly executing the step of excavating each pilot tunnel in sequence along the direction from the arch to the invert of the tunnel for any second excavation area 3 to form a first forming structure in the second excavation area 3, until the tunnel is penetrated to form a tunnel structure;
实施例4Example 4
步骤4.2隧道结构的搭建具体还包括:Step 4.2 The construction of the tunnel structure specifically includes:
步骤4.2.1,对已完成开挖施工的第一开挖区2域的仰拱以及两个第二开挖区3域的仰拱二次衬砌施工,形成隧道结构进行支护施工;Step 4.2.1, secondary lining construction is performed on the inverted arch of the first excavation area 2 and the two inverted arches of the second excavation area 3, to form a tunnel structure for support construction;
步骤4.2.2,在已完成开挖施工的隧道的仰拱上填充渣土,并对已完成渣土填充之后的仰拱进行路面施工,形成隧道结构;Step 4.2.2, filling the invert of the tunnel that has been excavated with slag, and performing pavement construction on the invert after the slag filling has been completed, to form a tunnel structure;
在本实施例中,充分利用双侧壁分部开挖时隧道围岩安全稳定的有利因素,在分部开挖工序较多的情况下简化开挖分部,增大各部分开挖的作业空间,机械化作业效率得到较大提高,加快了施工进度。In this embodiment, the favorable factors of safety and stability of the tunnel surrounding rock during the partial excavation of the double side walls are fully utilized, the excavation divisions are simplified when there are many partial excavation processes, the working space of each partial excavation is increased, the mechanized operation efficiency is greatly improved, and the construction progress is accelerated.
上述实施例中在步骤1之前,如图16所示,还包括:In the above embodiment, before step 1, as shown in FIG16 , the following further includes:
利用具有预设参数的超前支护构件对第一开挖区2以及两个第二开挖区3进行超前支护施工;Using advance support components with preset parameters to perform advance support construction on the first excavation area 2 and the two second excavation areas 3;
在本实施例中,隧道开挖施工前,现场成立专业的超前地质预测预报小组,并将该项工作纳入施工工序管理;采用地面预报和洞内超前预报相结合的模式,主要以洞内超前预报为主,洞内超前预报主要通过TSP203地质超前预报系统、超前钻孔等手段进行;In this embodiment, before the tunnel excavation construction, a professional advanced geological prediction team is set up on site, and this work is included in the construction process management; a mode combining ground prediction and in-tunnel advanced prediction is adopted, mainly in-tunnel advanced prediction, which is mainly carried out by means of TSP203 geological advanced prediction system, advanced drilling, etc.
需要特别和明确说明的是,在本实施例中示例的预设参数的超前支护构件包括:超前支护采用φ42×4mm超前小导管,管口0.5m范围内不开孔,其余部分按10cm间距交错设置注浆孔,孔径8mm,水平搭接长度不小于1m。小导管长4.5m,环向间距35cm~45cm,每环70根(双层140根),外插角分别为缓倾角10°~14°,和陡倾角30°~40°,上下两层交错布置,按拱部125°范围布置,临时支护小导管长4.5m,环向间距40cm,每环30根,外插角10°~14°;It should be specially and clearly stated that the advance support components of the preset parameters in the present embodiment include: the advance support adopts a φ42×4mm advance small conduit, no holes are opened within 0.5m of the pipe mouth, and the rest of the part is staggered with grouting holes at a spacing of 10cm, with a hole diameter of 8mm and a horizontal overlap length of not less than 1m. The small conduit is 4.5m long, with an annular spacing of 35cm to 45cm, 70 per ring (140 double-layer), and the external insertion angles are respectively a gentle angle of 10° to 14° and a steep angle of 30° to 40°. The upper and lower layers are staggered and arranged within the range of 125° of the arch. The temporary support small conduit is 4.5m long, with an annular spacing of 40cm, 30 per ring, and an external insertion angle of 10° to 14°;
在具体实施时,如图17和图18所示,左导洞上台阶开挖支护长度大于30m后,进行左导洞下台阶围岩的开挖;当中导洞下台阶围岩承载力不满足临时钢架支撑要求时,先对其进行注浆加固围岩,开挖左导洞下台阶时上端预留1.5m宽度,下端预留4m宽行车道(也即是,左导洞的下台阶的顶面靠近中导洞一侧预留宽度为1.5m,左导洞的下台阶的底部预留宽度为4m作为车行道)。开挖进尺为1榀钢架距离,开挖完成后,采用第一临时结构400的支护参数施作第一层初期支护。In specific implementation, as shown in Figures 17 and 18, after the excavation support length of the upper step of the left guide tunnel is greater than 30m, the surrounding rock of the lower step of the left guide tunnel is excavated; when the bearing capacity of the surrounding rock of the lower step of the middle guide tunnel does not meet the requirements of the temporary steel frame support, grouting is first performed to reinforce the surrounding rock, and when excavating the lower step of the left guide tunnel, a 1.5m width is reserved at the upper end, and a 4m wide roadway is reserved at the lower end (that is, the top surface of the lower step of the left guide tunnel close to the side of the middle guide tunnel has a reserved width of 1.5m, and the bottom of the lower step of the left guide tunnel has a reserved width of 4m as a roadway). The excavation advance is the distance of one steel frame. After the excavation is completed, the first layer of initial support is applied using the support parameters of the first temporary structure 400.
右导洞上台阶开挖支护长度大于30m后,进行右导洞下台阶围岩的开挖。当中导洞下台阶围岩承载力不满足临时钢架支撑要求时,先对其进行注浆加固围岩,开挖右导洞下台阶时上端预留1.5m宽度,下端预留4m宽行车道(也即是,右导洞的下台阶的顶面靠近中导洞一侧预留宽度为1.5m,左导洞的下台阶的底部预留宽度为4m作为车行道);开挖进尺为1榀钢架距离,开挖完成后,采用第一临时结构400的支护参数施作第一层初期支护;After the excavation support length of the upper step of the right guide tunnel is greater than 30m, the excavation of the surrounding rock of the lower step of the right guide tunnel is carried out. When the bearing capacity of the surrounding rock of the lower step of the middle guide tunnel does not meet the requirements of the temporary steel frame support, grouting is first used to reinforce the surrounding rock. When excavating the lower step of the right guide tunnel, a width of 1.5m is reserved at the upper end and a 4m wide carriageway is reserved at the lower end (that is, the top surface of the lower step of the right guide tunnel close to the side of the middle guide tunnel has a reserved width of 1.5m, and the bottom of the lower step of the left guide tunnel has a reserved width of 4m as a carriageway); the excavation advance is the distance of one steel frame. After the excavation is completed, the first temporary structure 400 support parameters are used to apply the first layer of initial support;
在本实施例中,可根据掌子面前方下台阶围岩情况进行动态调整开挖工序,若下台阶预留土承载力不满足作为承载墙的要求时,可先对其进行注浆加固,待承载力达到要求时,继续进行施工。In this embodiment, the excavation process can be dynamically adjusted according to the surrounding rock conditions of the lower step in front of the face. If the bearing capacity of the reserved soil in the lower step does not meet the requirements as a bearing wall, it can be grouting reinforced first, and construction can continue when the bearing capacity meets the requirements.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202410101260.1A CN117905481A (en) | 2024-01-24 | 2024-01-24 | Large-section tunnel excavation structure and excavation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202410101260.1A CN117905481A (en) | 2024-01-24 | 2024-01-24 | Large-section tunnel excavation structure and excavation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN117905481A true CN117905481A (en) | 2024-04-19 |
Family
ID=90696564
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202410101260.1A Pending CN117905481A (en) | 2024-01-24 | 2024-01-24 | Large-section tunnel excavation structure and excavation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN117905481A (en) |
-
2024
- 2024-01-24 CN CN202410101260.1A patent/CN117905481A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102071947B (en) | Construction Method of Weak Surrounding Rock Section at Entrance of Long-span Tunnel | |
CN102758632B (en) | Rock stratum double initial support layering method for establishing large-scale underground structure | |
CN111188629B (en) | Construction method for sudden change of tunnel bifurcation section and expanding excavation | |
CN108278115A (en) | A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop | |
CN107201908B (en) | Construction method for deep-buried central ditch of tunnel in severe cold region | |
CN101324072A (en) | Construction Method of Permeable Rib Arch Beam Tunnel | |
CN108412502B (en) | A kind of deep tunnel passes through upper-soft lower-hard ground construction method | |
CN102704957A (en) | Shed-frame method for shallowly burying large-sized underground structure construction | |
CN103089270B (en) | Excavating method suitable for large section loess tunnels | |
CN105201516B (en) | A kind of main structure of subway station and its tetrad arch PBA excavating construction methods | |
CN105587320B (en) | Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method | |
CN106761778A (en) | A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground | |
CN109538210A (en) | A kind of soft extremely irregularcoal seam fully mechanized coal face gob-side entry retaining method of high methane three | |
CN110017149A (en) | A kind of ledge tunneling is suitable to build underground structure and construction method | |
CN108867692A (en) | The protection of city big cross section open trench tunnel Nearby Structure and tunnel foundation pit method for digging | |
JP4132442B2 (en) | Tunnel construction method | |
CN115717536A (en) | Inclined shaft forward-hole-entering and top-raising construction method for large-section tunnel in weak water-rich stratum | |
CN104131566A (en) | Method for constructing basement foundation pit without horizontal braces | |
CN107191206A (en) | A kind of step construction method of Shallow-buried Large-span Tunnel Unit two six | |
CN203499695U (en) | Reinforcing structure for shallow-buried tunnel in bustling urban area | |
CN113216976A (en) | Tunnel HCD excavation method suitable for soft rock and gravel soil | |
CN112922646A (en) | Building method of underground excavation station excavated by large-section single-span support through superposed arch-wall integrated type | |
CN115467690B (en) | New structure system of shallow-buried large-span underground excavation subway station and construction method thereof | |
CN117905481A (en) | Large-section tunnel excavation structure and excavation method | |
CN112664206B (en) | Milling and excavating method for soft and weak cladding shallow-buried large-section tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |