CN116084443A - Construction method for building foundation on underground civil air defense hole - Google Patents
Construction method for building foundation on underground civil air defense hole Download PDFInfo
- Publication number
- CN116084443A CN116084443A CN202211515980.XA CN202211515980A CN116084443A CN 116084443 A CN116084443 A CN 116084443A CN 202211515980 A CN202211515980 A CN 202211515980A CN 116084443 A CN116084443 A CN 116084443A
- Authority
- CN
- China
- Prior art keywords
- air defense
- civil air
- section
- hole
- treated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑施工技术领域,具体地说是一种地下人防洞上建筑基础施工方法。The invention relates to the technical field of building construction, in particular to a building foundation construction method on an underground air defense tunnel.
背景技术Background technique
人防洞是战争时用以掩蔽人员、储藏物资以及保护人民生命财产安全的重要场所,也是实施人民防空的重要物质基础。人防洞在特殊年代发挥了重要作用,然而废弃后的人防洞给当今时代的城市建设带来了相当大的施工难度,尤其是对于基础施工。人防洞位于基础埋深范围内时必须对人防洞进行处理后才能进行基础施工,常规的施工处理主要是采用明挖法,明挖法开挖后会形成较深的基坑,超过一定深度后还需要对开挖出的基坑进行支护方可进行下一步施工,成本较大,工期较长,危险性也较大。Civil air defense caves are important places for sheltering personnel, storing materials, and protecting people's lives and property during wars, and are also an important material basis for implementing civil air defense. Civil air defense tunnels have played an important role in special times, but abandoned civil air defense tunnels have brought considerable construction difficulties to urban construction in today's era, especially for foundation construction. When the civil air defense tunnel is located within the buried depth of the foundation, the foundation construction must be carried out after the civil air defense tunnel is treated. The conventional construction treatment mainly adopts the open cut method. After the open cut method is excavated, a deep foundation pit will be formed. After a certain depth It is also necessary to support the excavated foundation pit to carry out the next step of construction, the cost is relatively large, the construction period is long, and the risk is relatively large.
发明内容Contents of the invention
本发明的目的是针对以上不足,提供一种地下人防洞上建筑基础施工方法,兼顾经济性,可以解决传统明挖开挖处理的危险系数大、工期长、成本高的难题。The object of the present invention is to address the above deficiencies and provide a construction method for building foundations on underground civil air defense tunnels, which can solve the problems of large risk factor, long construction period and high cost of traditional open-cut excavation.
本发明所采用技术方案是:The technical scheme adopted in the present invention is:
一种地下人防洞上建筑基础施工方法,包括如下步骤:A method for constructing a building foundation on an underground air defense tunnel, comprising the steps of:
S1、定义影响建筑基础施工的人防洞部分为待处理段,确定待处理段的范围;S1. Define the part of the civil air defense tunnel that affects the construction of the building foundation as the section to be processed, and determine the scope of the section to be processed;
S2、在工程地对人防洞的待处理段进行测量防线,确定人防洞的待处理段的端头;S2, measure the line of defense of the section to be processed of the civil air defense tunnel at the engineering site, and determine the end of the section to be processed of the civil air defense tunnel;
S3、对人防洞的待处理段的两个端头处设置挡模;S3, form-stops are set at the two ends of the section to be processed in the air defense tunnel;
S4、从上部开设固化土输送通道,所述输送通道连通至人防洞的待处理段内;S4, set up the solidified soil conveying channel from the top, and the conveying channel is connected to the waiting section of the air defense tunnel;
S5、设置固化土搅拌场,并通过开设的固化土输送通道向人防洞的待处理段内输送固化土;S5, set the solidified soil mixing field, and transport the solidified soil to the waiting section of the air defense tunnel through the solidified soil conveying channel opened;
S6、待固定化龄期达到设定时间后进行建筑基础的正常施工。S6. After the immobilization age reaches the set time, proceed to the normal construction of the building foundation.
作为进一步的优化,本发明步骤S1中,将人防洞的测绘图与建筑基础的测绘图进行重叠,确定人防洞的测绘图与建筑基础的测绘图的重合区域,所述人防洞的待处理段范围略大于所述重合区域的范围。As a further optimization, in the step S1 of the present invention, the surveying map of the civil air defense tunnel and the surveying map of the building foundation are overlapped to determine the overlapping area of the surveying map of the civil defense tunnel and the surveying map of the building foundation, and the section to be processed of the civil defense tunnel The extent is slightly larger than the extent of the coincident region.
作为进一步的优化,本发明步骤S2中,在实际工程地点根据所述确定的人防洞的测绘图与建筑基础的测绘图的重合区域对人防洞大待处理段进行放线测量,确定人防洞的端头后在人防洞内进行标记。As a further optimization, in the step S2 of the present invention, at the actual project site, according to the overlapping area of the surveying drawing of the said determined civil air defense shelter and the surveying drawing of the building foundation, the large sections to be treated of the civil defense shelter are set out and measured, and the length of the civil defense shelter is determined. After the end, mark in the air defense hole.
作为进一步的优化,本发明步骤S3中,所述挡模包括若干依次连接成排的工字钢。As a further optimization, in step S3 of the present invention, the retaining form includes several I-beams that are sequentially connected in rows.
作为进一步的优化,本发明步骤S3中,在待处理段的人防洞的两端端头处的顶部和底部均开凿用于安装工字钢的安装孔,单侧的安装孔紧密排列,位于顶部的安装孔的深度大于工字钢与洞高之间的差值,位于顶部的安装孔的深度大于位于底部的安装孔的深度,且当安装完成后,工字钢的两端分别位于上部的安装孔内和下部的安装孔内,并将相邻工字钢之间的接缝进行焊接。As a further optimization, in step S3 of the present invention, installation holes for installing I-beams are excavated at the top and bottom of the two ends of the air defense tunnel of the section to be treated, and the installation holes on one side are closely arranged and located at the top. The depth of the installation hole is greater than the difference between the I-beam and the hole height, the depth of the installation hole at the top is greater than the depth of the installation hole at the bottom, and when the installation is completed, the two ends of the I-beam are respectively located at the upper In the installation hole and the lower installation hole, the joints between adjacent I-beams are welded.
作为进一步的优化,本发明步骤S4中,在人防洞的待处理段的延伸方向的中间位置开设所述固化土输送通道。As a further optimization, in step S4 of the present invention, the solidified soil conveying channel is opened in the middle of the extending direction of the section to be treated of the air defense tunnel.
作为进一步的优化,本发明在施工现场设置固化土搅拌场,所述固化土搅拌场分为材料存放区、原土输送区、拌和区和固化土存储输送区,且搅拌场的底部采用设定厚度的混凝土进行硬化,由中间向四周找坡,并设置排水系统。As a further optimization, the present invention sets a solidified soil mixing field at the construction site. The solidified soil mixing field is divided into a material storage area, an original soil transportation area, a mixing area and a solidified soil storage and transportation area, and the bottom of the mixing field adopts a set The thick concrete is hardened, the slope is found from the middle to the surrounding, and the drainage system is set.
作为进一步的优化,本发明所述固化土由土壤固化剂与原生土混拌制得,所述土壤固化剂的含量为12%。As a further optimization, the stabilized soil of the present invention is prepared by mixing a soil stabilizer with native soil, and the content of the soil stabilizer is 12%.
作为进一步的优化,本发明所述原生土直接在施工现场附近进行采集,制得的固化土为泥浆状态,浇筑固化土时应分层浇筑,单层浇注高度不超过2m,上层浇筑时应在下层浇筑终凝后进行。As a further optimization, the primary soil of the present invention is directly collected near the construction site, and the solidified soil is in a mud state. When pouring the solidified soil, it should be poured in layers. The single-layer pouring height should not exceed 2m. The lower layer is poured after final setting.
作为进一步的优化,本发明步骤S5中,固化土输送管的末端设置有导流组件,所述导流组件包括弯头和导槽,所述弯头固定连接在用于输送固化土的端部,所述导槽为半管结构,所述导槽与弯头之间转动连接,且导槽与弯头之间设置有弹簧,当弹簧处于自然状态时,所述导槽的长度方向沿弯头的出料方向。As a further optimization, in step S5 of the present invention, the end of the solidified soil conveying pipe is provided with a diversion assembly, the diversion assembly includes an elbow and a guide groove, and the elbow is fixedly connected to the end for transporting the solidified soil , the guide groove is a half-pipe structure, the guide groove and the elbow are connected in rotation, and a spring is arranged between the guide groove and the elbow, when the spring is in a natural state, the length direction of the guide groove along the bend The output direction of the head.
本发明具有以下优点:The present invention has the following advantages:
1、避免大开挖,节省工期,提高安全性。1. Avoid large excavation, save construction period and improve safety.
传统对人防洞的处理通常采用明挖将人防洞揭露后再进行施工,由于人防洞一般埋深在地下几米的位置,开挖将形成高度较大的深窄基坑,安全性较低,且开挖和支护工期较长,费时费力。采用本方法只需在局部开孔安设侧模后回填固化土即可,施工快捷,安全性高。The traditional treatment of civil air defense holes usually uses open excavation to expose the civil air defense holes before construction. Since the civil air defense holes are generally buried several meters underground, the excavation will form a deep and narrow foundation pit with a high height, which is less safe and The excavation and support construction period is long, time-consuming and labor-intensive. With this method, it is only necessary to backfill the solidified soil after the side forms are installed in the local openings, and the construction is quick and safe.
2、成本低廉,经济节约。2. Low cost and economical.
无论是明挖还是素混凝土回填,相应的施工机械、人工和材料成本都较为高昂,本方法取材于现场,材料成本低廉,工期短,经济节约。Whether it is open excavation or plain concrete backfill, the corresponding construction machinery, labor and material costs are relatively high. This method is based on on-site materials, with low material costs, short construction period, and economical savings.
3、利用现场现有土料,绿色环保,节能减排。3. Utilize the existing soil materials on site, which is environmentally friendly, energy-saving and emission-reducing.
回填材料就近采用现场填土制拌成固化土,不需要外购商品混凝土减少了建材消耗和土方外运成本,既节约成本又绿色环保,减少了碳排放,环境效益与经济效益双赢。The backfilling material is mixed into solidified soil by on-site filling nearby, and there is no need to purchase commercial concrete, which reduces the consumption of building materials and the cost of earthwork transportation. It not only saves costs, but also is environmentally friendly and reduces carbon emissions. The environmental and economic benefits are a win-win situation.
4、固化土抗渗性较好,可提高基础的整体防水能力。4. The solidified soil has good impermeability, which can improve the overall waterproof ability of the foundation.
固化土本身具有较好的抗渗性,在基础施工完成后可以充当基础的挡水层,提高基础整体的防水能力,能解决后期地下室渗水的普遍难题。The solidified soil itself has good impermeability. After the foundation construction is completed, it can act as the water-retaining layer of the foundation, improve the waterproof ability of the foundation as a whole, and solve the common problem of water seepage in the basement in the later stage.
附图说明Description of drawings
为了更清楚地说明本发明实施例中的技术方案,下面将对实施例中描述中所需要使用的附图作简要介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域的普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following will briefly introduce the drawings used in the descriptions of the embodiments. Obviously, the drawings in the following descriptions are only some embodiments of the present invention. For those skilled in the art, other drawings can also be obtained based on these drawings without creative effort.
下面结合附图对本发明进一步说明:Below in conjunction with accompanying drawing, the present invention is further described:
图1为待处理的地质结构剖面示意图;Fig. 1 is the sectional schematic diagram of geological structure to be processed;
图2为挡模的设置结构示意图;Fig. 2 is the setting structure schematic diagram of retaining mold;
图3为固化土作业示意图;Fig. 3 is the schematic diagram of solidifying soil operation;
图4为完成建筑基础施工后的示意图;Fig. 4 is the schematic diagram after finishing building foundation construction;
图5为导流组件的结构示意图;Fig. 5 is a structural schematic diagram of a diversion assembly;
图6为施工现场俯视示意图。Figure 6 is a schematic top view of the construction site.
其中:1、原始地层,2、人防洞,3、建筑基础,4、地上建筑,5、挡模,6、固化土,7、固化土搅拌场,8、固化土输送管,9、弯头,10、导槽,11、弹簧。Among them: 1. Original stratum, 2. Civil air defense hole, 3. Building foundation, 4. Above-ground building, 5. Blocking formwork, 6. Solidified soil, 7. Solidified soil mixing field, 8. Solidified soil conveying pipe, 9. Elbow , 10, guide groove, 11, spring.
具体实施方式Detailed ways
下面结合附图和具体实施例对本发明作进一步说明,以使本领域的技术人员可以更好地理解本发明并能予以实施,但所举实施例不作为对本发明的限定,在不冲突的情况下,本发明实施例以及实施例中的技术特征可以相互结合。The present invention will be further described below in conjunction with accompanying drawing and specific embodiment, so that those skilled in the art can better understand the present invention and can implement it, but the embodiment given is not as the limitation of the present invention, in the case of no conflict Next, the embodiments of the present invention and the technical features in the embodiments can be combined with each other.
需要理解的是,在本发明实施例的描述中,“第一”、“第二”等词汇,仅用于区分描述的目的,而不能理解为指示或暗示相对重要性,也不能理解为指示或暗示顺序。在本发明实施例中的“多个”,是指两个或两个以上。It should be understood that in the description of the embodiments of the present invention, words such as "first" and "second" are only used to distinguish the purpose of description, and cannot be understood as indicating or implying relative importance, nor can they be understood as indicating or imply order. "Multiple" in the embodiments of the present invention refers to two or more.
本发明实施例中的属于“和/或”,仅仅是一种描述关联对象的关联关系,表示可以存在三种关系,例如,A和/或B,可以表示:单独存在A,单独存在B,同时存在A和B这三种情况。另外,本文中字符“/”一般表示前后关联对象是一种“或”关系。The term "and/or" in the embodiment of the present invention is only an association relationship describing associated objects, indicating that there may be three relationships, for example, A and/or B, which can mean: A exists alone, B exists alone, There are three situations A and B at the same time. In addition, the character "/" in this article generally indicates that the contextual objects are an "or" relationship.
如图1和图6所示为原始地层1的剖面示意图,依图中所示,想要建设的建筑基础位于人防洞2的上方,建筑基础3上的上方预建地上建筑4,本实施例提供一种地下人防洞上建筑基础施工方法,兼顾经济性和安全性因素,具体的包括如下步骤:As shown in Fig. 1 and Fig. 6, it is the schematic cross-sectional view of the
S1、定义影响建筑基础3施工的人防洞2的部分为待处理段,确定待处理段的范围;S1, define the part of the
本步骤的具体实施过程为:将人防洞2的测绘图与建筑基础3的测绘图进行重叠,确定人防洞2的测绘图与建筑基础3的测绘图的重合区域,如图6所示,所述人防洞2的待处理段范围略大于所述重合区域的范围。The specific implementation process of this step is: the surveying drawing of civil
S2、在施工现场对人防洞2的待处理段进行测量放线,确定人防洞2的待处理段的端头;S2, at the construction site, the section to be processed of the civil
本步骤中,在实际工程地点根据所述确定的人防洞2的测绘图与建筑基础3的测绘图的重合区域对人防洞的待处理段进行放线测量,确定人防洞2的两个端头后在人防洞内进行标记。In this step, at the actual project site, according to the overlapping area of the survey drawing of the civil
S3、对人防洞2的待处理段的两个端头处设置挡模5,如图2所示;S3,
本步骤中,所述挡模5包括若干依次连接成排的工字钢,具体的的施工过程中:在待处理段的人防洞2的两端端头处的顶部和底部均开凿用于安装工字钢的安装孔,单侧的安装孔紧密排列,位于顶部的安装孔的深度大于工字钢与洞高之间的差值,位于顶部的安装孔的深度大于位于底部的安装孔的深度,即当安装工字钢时,现将工字钢的上端伸入到位于顶部的安装孔内,直至将工字钢由倾斜状态转变至立正状态并足以伸入到位于底部的安装孔内时,将工字钢的下端伸入到位于底部的安装孔内,当安装完成后,工字钢的两端分别位于上部的安装孔内和下部的安装孔内,并将相邻工字钢之间的接缝进行焊接,安装完成后采用混凝土对安装孔的空余空间进行填塞处理。In this step, the retaining
S4、从上部开设固化土输送通道,所述固化土输送通道连通至人防洞的待处理段内;S4. Open a solidified soil conveying channel from the top, and the solidified soil conveying channel is connected to the waiting section of the air defense tunnel;
本步骤中,所述固化土输送通道开设在待处理段的中间位置,在后面的固化土6输送过程中,让固化土6自然流洞其待处理段的其他位置。In this step, the solidified soil conveying channel is opened in the middle of the section to be treated, and the solidified
S5、设置固化土搅拌场7,并通过开设的固化土输送通道向人防洞的待处理段内输送固化土,如图3所示;S5, the solidified
本步骤中,在施工现场设置固化土搅拌场7,所述固化土搅拌场分为材料存放区、原土输送区、拌和区和固化土存储输送区,且搅拌场的底部采用设定厚度的混凝土进行硬化,由中间向四周找坡,并设置排水系统。所述固化土6由土壤固化剂与原生土混拌制得,所述土壤固化剂的含量为12%。所述原生土直接在施工现场附近进行采集,制得的固化土6为泥浆状态,浇筑固化土时应分层浇筑,单层浇注高度不超过2m,上层浇筑时应在下层浇筑终凝后进行。In this step, a solidified
如图5所示,固化土输送管8的末端设置有导流组件,所述导流组件包括弯头9和导槽10,所述弯头9固定连接在固化土输送管8的端部,所述导槽10为半管结构,所述导槽10与弯头9之间转动连接,且导槽10与弯头9之间设置有弹簧11,当弹簧11处于自然状态时,所述导槽10的长度方向沿弯头的出料方向,导流组件的设置主要是为了避免在垂直输送至,由于自身重力和输送压力一起作用,导致具有较高的动能,在达到浇筑面时,会出现一定的离析现象,通过设置导流组件降低这种现象的发生,但是直接设置弯管会影响其通过固化土输送通道,在本方案中,只要弯头9只要能通过固化土输送通道即可。As shown in Figure 5, the end of the solidified soil delivery pipe 8 is provided with a guide assembly, the guide assembly includes an elbow 9 and a
S6、待固定化龄期达到设定时间后进行建筑基础的正常施工,施工效果如图4所示。S6. After the immobilization age reaches the set time, carry out the normal construction of the building foundation. The construction effect is shown in Figure 4.
以上所述实施例仅是为充分说明本发明而所举的较佳的实施例,本发明的保护范围不限于此。本技术领域的技术人员在本发明基础上所作的等同替代或变换,均在本发明的保护范围之内。本发明的保护范围以权利要求书为准。The above-mentioned embodiments are only preferred embodiments for fully illustrating the present invention, and the protection scope of the present invention is not limited thereto. Equivalent substitutions or transformations made by those skilled in the art on the basis of the present invention are all within the protection scope of the present invention. The protection scope of the present invention shall be determined by the claims.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211515980.XA CN116084443A (en) | 2022-11-30 | 2022-11-30 | Construction method for building foundation on underground civil air defense hole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211515980.XA CN116084443A (en) | 2022-11-30 | 2022-11-30 | Construction method for building foundation on underground civil air defense hole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN116084443A true CN116084443A (en) | 2023-05-09 |
Family
ID=86200016
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211515980.XA Pending CN116084443A (en) | 2022-11-30 | 2022-11-30 | Construction method for building foundation on underground civil air defense hole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN116084443A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2461745Y (en) * | 2001-02-14 | 2001-11-28 | 长沙中联重工科技发展股份有限公司 | Cloth isolating-proof device for concrete |
JP2003147782A (en) * | 2001-11-09 | 2003-05-21 | Tenox Corp | Foundation structure for constructing new building on existing basement and its construction method |
CN103603508A (en) * | 2013-11-19 | 2014-02-26 | 中国建筑第二工程局有限公司 | Plugging, pouring and reinforcing construction method of pile foundation in underground air-raid shelter |
CN104099943A (en) * | 2014-06-30 | 2014-10-15 | 中铁四局集团第四工程有限公司 | Underground diaphragm wall and deserted underground civil air defense engineering intersection processing method |
CN205112078U (en) * | 2015-07-30 | 2016-03-30 | 中建七局安装工程有限公司 | Isolating -proof device for concrete |
CN206545399U (en) * | 2017-02-17 | 2017-10-10 | 广州市第二市政工程有限公司 | A kind of anti-segregating concrete conduit |
CN108316346A (en) * | 2018-03-07 | 2018-07-24 | 宁波工程学院 | A kind of green processing method in discarded underground people's air defense hole |
CN214658906U (en) * | 2021-05-17 | 2021-11-09 | 中国十七冶集团有限公司 | Anti chute that educes |
CN215801064U (en) * | 2021-07-12 | 2022-02-11 | 中交路桥华南工程有限公司 | Anti-segregation string barrel |
-
2022
- 2022-11-30 CN CN202211515980.XA patent/CN116084443A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2461745Y (en) * | 2001-02-14 | 2001-11-28 | 长沙中联重工科技发展股份有限公司 | Cloth isolating-proof device for concrete |
JP2003147782A (en) * | 2001-11-09 | 2003-05-21 | Tenox Corp | Foundation structure for constructing new building on existing basement and its construction method |
CN103603508A (en) * | 2013-11-19 | 2014-02-26 | 中国建筑第二工程局有限公司 | Plugging, pouring and reinforcing construction method of pile foundation in underground air-raid shelter |
CN104099943A (en) * | 2014-06-30 | 2014-10-15 | 中铁四局集团第四工程有限公司 | Underground diaphragm wall and deserted underground civil air defense engineering intersection processing method |
CN205112078U (en) * | 2015-07-30 | 2016-03-30 | 中建七局安装工程有限公司 | Isolating -proof device for concrete |
CN206545399U (en) * | 2017-02-17 | 2017-10-10 | 广州市第二市政工程有限公司 | A kind of anti-segregating concrete conduit |
CN108316346A (en) * | 2018-03-07 | 2018-07-24 | 宁波工程学院 | A kind of green processing method in discarded underground people's air defense hole |
CN214658906U (en) * | 2021-05-17 | 2021-11-09 | 中国十七冶集团有限公司 | Anti chute that educes |
CN215801064U (en) * | 2021-07-12 | 2022-02-11 | 中交路桥华南工程有限公司 | Anti-segregation string barrel |
Non-Patent Citations (1)
Title |
---|
刘海林等: "中心城区深基坑遇废弃防空洞处理方法研究", 南昌工程学院学报, vol. 39, no. 6, 31 December 2020 (2020-12-31), pages 48 - 53 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112502777B (en) | Method for treating tunnel inrush roof collapse and door closing | |
CN101215834A (en) | Construction Method of Outrigger Type Diaphragm Wall | |
CN100513705C (en) | Underground Beam-Pile Frame Structure for Slope Reinforcement | |
CN108797641A (en) | A kind of structure and its construction method of Underground Subway Station construction period full station sealing | |
CN101343869A (en) | Underground continuous wall construction method of city-across pipeline | |
CN110864162A (en) | Construction process of argillaceous sandstone geological pipe jacking | |
CN110344394A (en) | A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method | |
CN109898556A (en) | A kind of underground pipe gallery structure and sunk type construction method | |
CN104264683A (en) | Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building | |
CN206736963U (en) | Ditch millet section high water level district lid tunnel stagnant water structure | |
CN104929142A (en) | Combined cofferdam structure and building construction method thereof | |
CN113529830B (en) | Shallow Buried Tunnel Adjacent Building Isolation-Underpinning Combination Reinforcement Structure and Its Construction Technology | |
CN212104124U (en) | Landslide prevention and control building unit and system | |
CN211038701U (en) | Mine method subway interval air shaft with shield first and well second | |
CN216407913U (en) | A water intake pipe jacking structure crossing the Linjiang Railway | |
CN116084443A (en) | Construction method for building foundation on underground civil air defense hole | |
CN107940102B (en) | Underground raw water pipeline protection construction method | |
CN110512594A (en) | The simple and easy method of churning driven opportunity cavity pore-forming | |
Dann et al. | Unlined Tunnels of the Snowy Mountains Hydro-Electric Authority, Australia | |
CN209760248U (en) | Composite submerged foundation pit enclosure structure | |
CN209816867U (en) | A supporting construction for peripheral foundation ditch of existing building | |
CN207143970U (en) | A kind of foundation pit enclosure stake | |
CN106193744B (en) | The round prefabricated assembled underground granary of equal steel plated inside and outside one kind | |
CN217974507U (en) | Protection system of subway tunnel structure crouches down during soft soil foundation ditch excavation | |
CN113931228B (en) | Material platform construction method for basement construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20230509 |