[go: up one dir, main page]

CN114810098A - Multi-cabin pipe gallery underground excavation construction method - Google Patents

Multi-cabin pipe gallery underground excavation construction method Download PDF

Info

Publication number
CN114810098A
CN114810098A CN202210679035.7A CN202210679035A CN114810098A CN 114810098 A CN114810098 A CN 114810098A CN 202210679035 A CN202210679035 A CN 202210679035A CN 114810098 A CN114810098 A CN 114810098A
Authority
CN
China
Prior art keywords
cabin
excavation
support structure
excavated
vault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210679035.7A
Other languages
Chinese (zh)
Inventor
刘佳杰
郭俊
宁伟
刘志成
吴雷明
安红卫
刘晓飞
王振
胡振涛
张磊
李博森
韩国辉
杨志平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Road and Bridge Co Ltd
Original Assignee
Beijing Municipal Road and Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Road and Bridge Co Ltd filed Critical Beijing Municipal Road and Bridge Co Ltd
Priority to CN202210679035.7A priority Critical patent/CN114810098A/en
Publication of CN114810098A publication Critical patent/CN114810098A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Soil Sciences (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a multi-cabin pipe gallery underground excavation construction method which is characterized in that vertical two lining structures which are independently arranged between adjacent cabins are combined into a common vertical two lining structure to serve as a common intermediate wall between the adjacent cabins of an underground excavation pipe gallery. Among the preliminary bracing structure, the vertical preliminary bracing structure of sharing that plays supporting role between adjacent cabins is replaced by two vertical lining structures of sharing, makes two lining structures of undercut piping lane form a continuous outsourcing preliminary bracing structure outward. On the premise of meeting the underground excavation supporting conditions, the shared intermediate wall between the adjacent cabins of the underground excavation pipe gallery and the shared intermediate wall between the adjacent cabins of the open excavation pipe gallery can be kept consistent, so that the multi-cabin pipe gallery constructed by the open excavation method is directly connected with the multi-cabin pipe gallery constructed by the underground excavation method, and an intermediate wall thickness transition section is not required to be arranged.

Description

一种多舱室管廊暗挖施工方法A construction method for underground excavation of multi-chamber pipe gallery

技术领域technical field

本发明涉及一种管廊暗挖施工方法,特别涉及一种应用于多舱室管廊,减少相邻舱室间中隔墙厚度的暗挖施工方法。The invention relates to a construction method for underground excavation of a pipe gallery, in particular to a construction method for undercover excavation applied to a multi-cabin pipe gallery to reduce the thickness of a partition wall between adjacent cabins.

背景技术Background technique

管廊施工中,一般采用明挖法和暗挖法相结合的施工方案。在施工条件满足的情况下,一般采用明挖法施工,即开挖基坑,在基坑内进行管廊施工,基坑内管廊施工完成后,按要求回填基坑;当管廊与既有建筑物、结构物或管线相交时,一般采用暗挖法下穿既有建筑物、结构物或管线。In the construction of the pipe gallery, the construction scheme combining the open-cut method and the under-cut method is generally adopted. When the construction conditions are met, the open-cut method is generally used, that is, the foundation pit is excavated, and the pipe gallery construction is carried out in the foundation pit. After the construction of the pipe gallery in the foundation pit is completed, the foundation pit is backfilled as required; When the buildings, structures or pipelines intersect, the undercut method is generally used to penetrate the existing buildings, structures or pipelines.

请参照图2所示的以三舱室管廊为例,采用明挖法施工的多舱室管廊截面图,采用明挖法施工的多舱室管廊中,相邻舱室间设置的明挖管廊相邻舱室间共用中隔墙厚度一般为0.2m~0.5m。采用暗挖法施工的多舱室管廊中,为了确保管廊结构的稳定性,管廊结构主要包括初期支结构及二衬结构。请参照图3所示的以三舱室管廊为例,采用一般暗挖法施工的多舱室管廊截面图,一般暗挖施工方法中,每个舱室都有独立的二衬结构,相邻舱室间竖向二衬结构之间设置一般暗挖管廊共用竖向初期支护结构,相邻舱室间之间的一般暗挖管廊相邻舱室间共用中隔墙由相邻舱室间各自独立设置的竖向二衬结构及一般暗挖管廊共用竖向初期支护结构组成,其厚度一般为0.8m~1.2m。Please refer to the cross-sectional view of the multi-cabin pipe gallery constructed by the open-cut method using the three-cabin pipe gallery as an example shown in Figure 2. Among the multi-cabin pipe gallery constructed by the open-cut method, the open-cut pipe gallery set between adjacent cabins The thickness of the common partition wall between adjacent cabins is generally 0.2m~0.5m. In the multi-chamber pipe gallery constructed by the underground excavation method, in order to ensure the stability of the pipe gallery structure, the pipe gallery structure mainly includes the initial support structure and the secondary lining structure. Please refer to the cross-sectional view of the multi-compartment pipe gallery with the three-chamber pipe gallery as an example shown in Figure 3. In the general underground excavation method, each cabin has an independent secondary lining structure, and the adjacent cabins Between the two vertical lining structures, the general underground excavation pipe gallery is set to share the vertical initial support structure, and the general underground excavation pipe gallery between the adjacent cabins The common partition wall between the adjacent cabins is set independently by the adjacent cabins The vertical secondary lining structure and the general underground pipe gallery share the vertical initial support structure, and the thickness is generally 0.8m~1.2m.

由于明挖管廊相邻舱室间共用中隔墙厚度与一般暗挖管廊相邻舱室间共用中隔墙厚度不一致,当明挖法施工的多舱室管廊与一般暗挖法施工的多舱室管廊相接时,需要在明挖法施工的多舱室管廊设置中隔墙厚度过渡段,使明挖管廊相邻舱室间共用中隔墙厚度逐步过渡到与一般暗挖管廊相邻舱室间共用中隔墙一致,确保明挖法施工的多舱室管廊各舱室与一般暗挖法施工的多舱室管廊各舱室一一对应,便于明挖法施工的多舱室管廊与一般暗挖法施工的多舱室管廊相接。Since the thickness of the common partition wall between the adjacent cabins of the cut-and-cover pipe gallery is inconsistent with the thickness of the common partition wall between the adjacent cabins of the general open-cut pipe gallery, when the multi-compartment pipe gallery constructed by the cut-and-cover method is different from that of the multi-compartment constructed by the general open-cut method When the pipe galleries are connected, it is necessary to set up the thickness transition section of the partition wall in the multi-chamber pipe galleries constructed by the cut-and-cover method, so that the thickness of the common partition wall between the adjacent cabins of the open-cut pipe galleries gradually transitions to that adjacent to the general open-cut pipe galleries. The common partition wall between the cabins is consistent to ensure that the multi-compartment pipe gallery constructed by the open-cut method is in one-to-one correspondence with the multi-compartment pipe gallery of the general open-cut method, which is convenient for the open-cut method. The multi-chamber pipe gallery constructed by the excavation method is connected.

明挖法施工的多舱室管廊设置的共用中隔墙厚度过渡段施工过程较为复杂,质量控制难度大,施工难度大。The construction process of the thickness transition section of the common partition wall set in the multi-chamber pipe gallery constructed by the open-cut method is relatively complicated, the quality control is difficult, and the construction is difficult.

发明内容SUMMARY OF THE INVENTION

本发明的目的是解决上述问题而提供一种多舱室管廊暗挖施工方法,所述多舱室管廊暗挖施工方法是将相邻舱室间各自独立设置的竖向二衬结构合并成一个共用竖向二衬结构作为暗挖管廊相邻舱室间共用中隔墙,所述共用竖向二衬结构与拱顶二衬结构、竖向二衬结构(或其他共用竖向二衬结构)及底板二衬结构形成闭合的管廊舱室二衬结构;初期支护结构中,相邻舱室间起到支撑作用的共用竖向初期支护结构由共用竖向二衬结构代替,使暗挖管廊二衬结构外形成一个连续的外包初期支护结构,本发明在满足暗挖支护条件的前提下,可以使暗挖管廊相邻舱室间共用中隔墙与明挖管廊相邻舱室间共用中隔墙保持一致,使明挖法施工的多舱室管廊与暗挖法施工的多舱室管廊直接相接,不用设置中隔墙厚度过渡段。The purpose of the present invention is to solve the above problems and provide a multi-chamber pipe gallery underground excavation construction method. The vertical secondary lining structure is used as the common partition wall between the adjacent cabins of the underground tunnel. The second lining structure of the bottom plate forms a closed second lining structure of the pipe gallery cabin; in the initial support structure, the common vertical initial supporting structure that plays a supporting role between adjacent cabins is replaced by the common vertical second lining structure, so that the underground excavation pipe gallery A continuous outsourcing initial support structure is formed outside the secondary lining structure. On the premise of satisfying the conditions of undercut support, the invention can make the adjacent cabins of the undercut pipe gallery share the partition wall and the adjacent cabins of the open cut pipe gallery. The shared middle partition wall is kept the same, so that the multi-chamber pipe gallery constructed by the cut-and-cover method and the multi-chamber tube gallery constructed by the undercut method are directly connected, and there is no need to set the transition section of the thickness of the middle partition wall.

本发明主要通过以下技术方案实现上述目的:The present invention mainly realizes above-mentioned purpose through following technical scheme:

一种多舱室管廊暗挖施工方法,其特征主要在于:A construction method for underground excavation of a multi-chamber pipe gallery, which is mainly characterized in that:

步骤1:暗挖管廊初期支护结构加工及二衬结构钢筋加工。Step 1: Processing of the initial support structure of the underground tunnel and the processing of the secondary lining structural steel bar.

初期支护结构材料和结构形式根据实际地质和设计要求情况确定,可以是工字钢或钢筋格栅等。初期支护结构和二衬结构钢筋根据设计图纸进行预先加工。The material and structural form of the initial support structure are determined according to the actual geology and design requirements, which can be I-beam or steel grating. The initial support structure and secondary lining structural steel bars are pre-processed according to the design drawings.

进行初期支护结构体系转换施工时,后开挖舱室拱顶初期支护结构及后开挖舱室底板初期支护结构需要与其相邻的先开挖舱室拱顶初期支护结构及先开挖舱室底板初期支护结构连接。During the conversion of the initial support structure system, the initial support structure of the rear-excavated cabin dome and the initial support structure of the rear-excavated cabin floor need to be adjacent to the first-excavated cabin vault initial support structure and the first-excavated cabin. The initial support structure of the base plate is connected.

进一步的,加工先开挖舱室拱顶初期支护结构时,在先开挖舱室拱顶初期支护结构靠近后开挖舱室侧的拱脚处附近设置拱顶初期支护结构预埋钢板,用于后开挖舱室拱顶初期支护结构与相邻先开挖舱室拱顶初期支护结构连接。Further, when processing the initial support structure of the dome of the first excavation cabin, the pre-buried steel plate of the initial support structure of the dome is set near the arch foot of the first excavation cabin vault near the side of the back excavation cabin. The initial support structure of the vault of the cabin excavated after the excavation is connected with the initial support structure of the vault of the adjacent first excavated cabin.

进一步的,加工先开挖舱室底板初期支护结构时,在先开挖舱室底板初期支护结构靠近后开挖舱室侧设置底板初期支护结构预埋钢板,用于后开挖舱室底板初期支护结构与相邻先开挖舱室底板初期支护结构连接。Further, when processing the initial support structure of the first excavation cabin bottom plate, the pre-embedded steel plate of the bottom plate initial support structure is arranged on the side of the first excavated cabin bottom plate close to the rear excavation cabin, which is used for the initial support of the rear excavation cabin bottom plate. The protective structure is connected with the initial supporting structure of the adjacent first excavated cabin floor.

进一步的,加工先开挖舱室拱顶二衬结构钢筋时,在先开挖舱室拱顶二衬结构钢筋靠近后开挖舱室侧的拱脚处附近设置拱顶二衬结构钢筋预埋钢板,用于后开挖舱室拱顶二衬结构钢筋与相邻先开挖舱室拱顶二衬结构钢筋连接。Further, when processing the structural steel bars for the second lining of the cabin dome excavation first, the pre-buried steel plates for the second lining structural steel bar of the dome roof shall be set near the arch foot of the second excavated cabin side near the side of the second lining of the cabin excavated first. The second lining structural steel bar of the cabin dome of the rear excavated cabin is connected with the second lining structural steel bar of the adjacent first excavated cabin roof.

进一步的,加工先开挖舱室底板二衬结构钢筋时,在先开挖舱室底板二衬结构钢筋靠近后开挖舱室侧设置底板二衬结构钢筋预埋钢板,用于后开挖舱室底板二衬结构钢筋与相邻先开挖舱室底板二衬结构钢筋连接。Further, when processing the structural steel bars for the second lining of the cabin floor excavated first, the pre-embedded steel plates for the structural steel bars of the second lining of the second lining of the cabin floor of the first excavated cabin are set near the side of the rear excavated cabin, which are used for the second lining of the second lining of the bottom excavated cabin. The structural steel bars are connected with the second lining structural steel bars of the adjacent first excavated cabin floor.

进一步的,还需加工后开挖舱室的拱顶初期支护结构、后开挖舱室的底板初期支护结构、后开挖舱室的拱顶二衬支护钢筋、后开挖舱室的底板二衬支护钢筋、竖向二衬结构钢筋及二衬结构纵向钢筋和箍筋、竖向初期支护结构。Further, it is necessary to process the initial support structure of the dome of the rear excavation cabin, the initial support structure of the bottom plate of the rear excavation cabin, the second lining of the dome of the rear excavated cabin, and the second lining of the bottom plate of the rear excavated cabin. Supporting steel bars, vertical secondary lining structural steel bars and secondary lining structural longitudinal steel bars and stirrups, and vertical initial support structures.

进一步的,由于先后开挖舱室间竖向初期支护结构在后开挖舱室施工过程中将被拆除,因此,先后开挖舱室间竖向初期支护结构需要单独设置,便于后期拆除。Further, since the vertical initial support structure between successively excavated cabins will be dismantled during the construction of the post-excavation cabin, the vertical initial support structure between successively excavated cabins needs to be set up separately to facilitate later dismantling.

需要说明的是,将暗挖管廊中包含的所有舱室从任意一端向另一端依次进行编号:01号舱室、02号舱室、03号舱室……N号舱室;其中,编号为奇数的舱室为先开挖舱室,编号为偶数的舱室为后开挖舱室。对于末尾编号舱室,当暗挖管廊包含舱室数为奇数时,末尾编号舱室为先开挖舱室;当暗挖管廊包含舱室数为偶数时,末尾编号舱室为后开挖舱室,另命名为末尾后开挖舱室。所述先开挖舱室为暗挖管廊施工中,首先进行开挖施工的舱室;所述后开挖舱室为先开挖舱室完成一定深度开挖、初期支护结构及二衬结构施工后,再开挖的舱室。先开挖舱室相邻舱室为后开挖舱室。当暗挖管廊包含舱室数为偶数时,末尾编号舱室为末尾后开挖舱室。It should be noted that all the cabins included in the tunnel tunnel are numbered sequentially from either end to the other end: No. 01 cabin, No. 02 cabin, No. 03 cabin... No. N cabin; among them, the odd-numbered cabins are The cabins are excavated first, and the cabins with even numbers are excavated later. For the last numbered cabins, when the number of cabins contained in the tunnel tunnel is odd, the last numbered cabin is the first excavation cabin; when the number of cabins contained in the tunnel tunnel is even, the last numbered cabin is the rear excavation cabin, which is also named as Excavate the cabin after the end. The first excavation cabin is the first excavation cabin in the construction of the underground excavation pipe gallery; the post excavation cabin is the first excavation cabin after completion of a certain depth excavation, initial support structure and secondary lining structure construction, Re-excavated cabin. The adjacent cabins of the first excavation cabin are the latter excavation cabins. When the number of cabins contained in the underground excavation pipe gallery is even, the last numbered cabin is the last excavated cabin.

步骤2:暗挖管廊舱室开挖前,加固开挖土体。Step 2: Reinforce the excavated soil before excavating the cabin of the underground tunnel.

进一步的,开挖土体加固时,开挖土体加固措施根据开挖土体的稳定性,可以采用超前管棚、超前小导管注浆、深孔注浆或不进行开挖土体加固。Further, when the excavated soil is reinforced, the reinforcement measures of the excavated soil can be based on the stability of the excavated soil, and can adopt advanced pipe shed, advanced small pipe grouting, deep hole grouting or no excavation soil reinforcement.

优选的,应加固暗挖管廊所有舱室开挖土体,确保开挖时土体的稳定性。Preferably, the excavated soil in all cabins of the tunnel tunnel should be reinforced to ensure the stability of the soil during excavation.

步骤3:先开挖舱室处土体开挖及初期支护结构安装施工。Step 3: First excavate the soil at the cabin and install the initial support structure.

进一步的,先开挖舱室进行土体开挖时,先开挖舱室土体开挖方法根据开挖土体稳定性确定,可以采用全断面开挖、台阶法、预留核心土法等。Further, when excavating the cabin first for soil excavation, the method of excavating the cabin soil first is determined according to the stability of the excavated soil, and can adopt the full-section excavation, the step method, and the reserved core soil method.

进一步的,随着先开挖舱室开挖,根据设计初期支护结构间距的要求及时安装先开挖舱室拱顶初期支护结构、先后开挖舱室间竖向初期支护结构及竖向初期支护结构,并采用锁脚锚杆临时加固先后开挖舱室间竖向初期支护结构及竖向初期支护结构,在纵向相邻的先开挖舱室拱顶初期支护结构间、先后开挖舱室间竖向初期支护结构间及竖向初期支护结构间安装钢筋网片并喷射先开挖舱室拱顶初期支护结构、先后开挖舱室间竖向初期支护结构及竖向初期支护结构混凝土。Further, with the excavation of the first excavation cabin, according to the requirements of the initial support structure spacing in the design, the initial support structure of the first excavation cabin dome, the vertical initial support structure and the vertical initial support structure between the cabins were excavated in time. The vertical initial support structure and the vertical initial support structure between the cabins are excavated successively, and the vertical initial support structure of the adjacent longitudinally excavated cabin vaults is excavated successively. Install reinforced mesh between the vertical primary supporting structures and between the vertical primary supporting structures and excavate the primary supporting structures of the cabin vaults by spraying first, excavate successively the vertical primary supporting structures and vertical primary supporting structures between the chambers Structural concrete.

进一步的,待先开挖舱室拱顶初期支护结构、先后开挖舱室间竖向初期支护结构及竖向初期支护结构混凝土达到设计要求后,安装先开挖舱室底板初期支护结构,在纵向相邻的先开挖舱室底板初期支护结构间安装钢筋网片并喷射先开挖舱室底板初期支护结构混凝土。Further, after excavating the initial support structure of the cabin dome, excavating the vertical initial support structure between the cabins successively and the concrete of the vertical initial support structure to meet the design requirements, install the preliminary support structure of the cabin floor by excavating first. Install reinforced mesh between the longitudinally adjacent initial support structures of the first-excavated cabin floor and spray concrete for the initial support structure of the first-excavated cabin floor.

优选的,先开挖舱室中,先开挖舱室拱顶初期支护结构、先后开挖舱室间竖向初期支护结构、竖向初期支护结构及先开挖舱室底板初期支护结构之间采用螺栓连接。Preferably, in the first excavation of the cabin, first excavate the initial support structure of the cabin dome, successively excavate the vertical initial support structure between the cabins, the vertical initial support structure and the first excavation between the initial support structure of the cabin bottom plate Bolted connection.

步骤4:整平先后开挖舱室间竖向初期支护结构靠近后开挖舱室侧的混凝土表面。Step 4: Level the concrete surface of the vertical initial support structure between the successive excavated cabins close to the side of the later excavated cabin.

需要说明的是,整平先后开挖舱室间竖向初期支护结构靠近后开挖舱室侧的混凝土表面的目的是先后开挖舱室间竖向初期支护结构拆除后,先开挖舱室和后开挖舱室共用二衬结构(即暗挖管廊相邻舱室间共用中隔墙)面向后开挖舱室的混凝土表面平整,保证后开挖舱室二衬结构外观质量达到要求。It should be noted that the purpose of leveling the concrete surface of the vertical initial support structure between the successive excavation cabins close to the side of the rear excavation cabin is to excavate the vertical initial support structure between the cabins successively, and then excavate the cabin and the rear. The common secondary lining structure of the excavated cabins (that is, the common partition wall between the adjacent cabins of the underground excavation pipe gallery) faces the concrete surface of the rear excavated cabin to be flat, so as to ensure that the appearance quality of the secondary lining structure of the rear excavated cabin meets the requirements.

步骤5:铺设安装先开挖舱室防水层并预留用于与相邻后开挖舱室防水层搭接的预留搭接防水层。Step 5: Lay and install the pre-excavated cabin waterproof layer and the reserved overlap waterproof layer reserved for overlapping with the adjacent post-excavated cabin waterproof layer.

进一步的,需要在先开挖舱室拱顶防水层在靠近后开挖舱室侧预留用于与相邻后开挖舱室拱顶防水层搭接的拱顶预留搭接防水层。Further, it is necessary to reserve an overlap waterproof layer on the vault of the first excavated cabin on the side close to the rear excavated cabin for overlapping with the adjacent rear excavated cabin dome roof waterproof layer.

进一步的,需要在先开挖舱室底板防水层在靠近后开挖舱室侧预留用于与相邻后开挖舱室底板防水层搭接的底板预留搭接防水层。Further, it is necessary to reserve an overlapping waterproof layer on the bottom plate for overlapping with the waterproof layer of the bottom plate of the adjacent rear excavation cabin on the side close to the rear excavation cabin before the waterproof layer of the bottom plate of the first excavated cabin.

优选的,拱顶预留搭接防水层及底板预留搭接防水层长度为0.4m~0.8m。Preferably, the length of the reserved overlapping waterproof layer for the vault and the reserved overlapping waterproof layer for the bottom plate is 0.4m~0.8m.

优选的,为节省防水材料,不铺设后续施工需要拆除的先后开挖舱室间竖向初期支护结构处的防水层。Preferably, in order to save waterproof materials, the waterproof layer at the vertical initial support structure between the successively excavated cabins that needs to be removed in the subsequent construction is not laid.

步骤6:在先后开挖舱室间竖向初期支护结构靠近后开挖舱室侧的混凝土表面均匀涂抹脱模剂。Step 6: Apply mold release agent evenly on the concrete surface of the vertical initial support structure between successive excavation cabins close to the side of the rear excavated cabin.

需要说明的是,在先后开挖舱室间竖向初期支护结构靠近后开挖舱室侧的混凝土表面均匀涂抹脱模剂的目的是便于拆除分离先后开挖舱室间竖向初期支护结构。It should be noted that the purpose of evenly applying mold release agent to the concrete surface of the vertical initial support structure between the successive excavation cabins near the rear excavation cabin is to facilitate the removal and separation of the vertical initial support structure between the successive excavation cabins.

步骤7:先开挖舱室二衬结构钢筋安装及二衬结构混凝土浇筑。Step 7: First excavate the secondary lining structure of the cabin to install the reinforcement and pour the concrete of the secondary lining structure.

进一步的,安装先开挖舱室拱顶二衬结构钢筋、竖向二衬结构钢筋、先后开挖舱室共用竖向二衬结构钢筋、先开挖舱室底板二衬结构钢筋及二衬结构纵向钢筋和箍筋。Further, install the first excavation cabin dome second lining structural steel bar, vertical second lining structural steel bar, successively excavate the cabin common vertical second lining structural steel bar, first excavate the cabin bottom second lining structural steel bar and the second lining structure longitudinal steel bar and stirrups.

架设安先开挖舱室装拱顶二衬结构、竖向二衬结构及先后开挖舱室共用竖向二衬结构模板,浇筑先开挖舱室装拱顶二衬结构、竖向二衬结构及先后开挖舱室共用竖向二衬结构混凝土;待先开挖舱室装拱顶二衬结构、竖向二衬结构及先后开挖舱室共用竖向二衬结构混凝土达到设计要求后,拆除先开挖舱室装拱顶二衬结构、竖向二衬结构及先后开挖舱室共用竖向二衬结构模板,然后浇筑先开挖舱室底板二衬结构混凝土,并整平先开挖舱室底板二衬结构混凝土表面。Erection of the first excavation cabin with dome double lining structure, vertical double lining structure and the common vertical double lining structure formwork for successive excavation cabins, pouring first excavation cabin with vault double lining structure, vertical double lining structure and successive excavation cabins. The excavated cabins share the vertical secondary lining structural concrete; after the first excavated cabins are installed with the vaulted secondary lining structure, the vertical secondary lining structure, and the successively excavated cabins share the vertical secondary lining structural concrete to meet the design requirements, the first excavated cabins will be removed. Install the dome-top two-lining structure, the vertical two-lining structure, and excavate the cabins to share the vertical two-lining structure formwork, and then pour the first-excavated cabin floor second-lining structure concrete, and level the first-excavated cabin bottom second-lining structure concrete surface .

优选的,先开挖舱室中,先开挖舱室拱顶二衬结构钢筋、竖向二衬结构钢筋、先后开挖舱室共用竖向二衬结构钢筋及先开挖舱室底板二衬结构钢筋之间采用焊接连接。Preferably, in the first excavation of the cabin, first excavate the cabin dome second lining structural steel bar, the vertical second lining structural steel bar, excavate the cabin shared vertical second lining structural steel bar first, and first excavate the cabin floor between the second lining structural steel bar Use welded connections.

步骤8:后开挖舱室处土体开挖及初期支护结构安装施工。Step 8: Soil excavation at the rear excavation cabin and installation of the initial support structure.

进一步的,后开挖舱室采用上下台阶法施工,上下台阶错开距离为3.0m~6.0m。Further, the rear excavation cabin is constructed by the upper and lower steps method, and the staggered distance between the upper and lower steps is 3.0m~6.0m.

当暗挖管廊舱室个数为奇数时:When the number of cabins in the underground tunnel is odd:

进一步的,上台阶开挖深度为3.0m~6.0m时,凿除与后开挖舱室相邻先开挖舱室拱顶初期支护结构预埋钢板处的混凝土保护层,使拱顶初期支护结构预埋钢板全部漏出,并确保拱顶初期支护结构预埋钢板表面干净无杂物;Further, when the excavation depth of the upper step is 3.0m~6.0m, the concrete protective layer at the pre-embedded steel plate of the initial support structure of the dome of the first excavation cabin adjacent to the rear excavation cabin is removed, so that the initial support of the dome can be eliminated. All the embedded steel plates of the structure leak out, and ensure that the surface of the embedded steel plates of the initial supporting structure of the vault is clean and free of debris;

然后,将后开挖舱室拱顶初期支护结构与相邻先开挖舱室拱顶支护结构预埋钢板连接,在纵向相邻后开挖舱室拱顶初期支护结构间安装钢筋网片并喷射后开挖舱室拱顶初期支护结构混凝土。Then, connect the initial support structure of the rear-excavated cabin vault with the pre-embedded steel plate of the adjacent first-excavated cabin vault support structure, and install steel mesh between the longitudinally adjacent rear-excavated cabin vault initial support structures and After spraying, excavate the concrete for the initial support structure of the cabin vault.

进一步的,后开挖舱室拱顶初期支护结构混凝土施工完成后,进行下台阶开挖,凿除与后开挖舱室相邻先开挖舱室底板初期支护结构预埋钢板处的混凝土保护层,使底板初期支护结构预埋钢板全部漏出,并确保底板初期支护结构预埋钢板表面干净无杂物;Further, after the concrete construction of the initial support structure of the rear excavation cabin vault is completed, the lower steps are excavated, and the concrete protection layer at the pre-embedded steel plate of the initial support structure of the first excavation cabin bottom adjacent to the rear excavation cabin is removed. , so that all the embedded steel plates of the initial supporting structure of the bottom plate leak out, and ensure that the surface of the embedded steel plates of the initial supporting structure of the bottom plate is clean and free of debris;

然后,将后开挖舱室底板初期支护结构与相邻先开挖舱室底板支护结构预埋钢板连接,在纵向相邻后开挖舱室底板初期支护结构间安装钢筋网片并喷射后开挖舱室底板初期支护结构混凝土。Then, connect the initial support structure of the back excavation cabin floor with the pre-embedded steel plate of the adjacent first excavated cabin floor support structure, install steel mesh between the initial support structures of the longitudinal adjacent back excavation cabin floor and spray the back excavation. Excavate the concrete for the initial support structure of the cabin floor.

当暗挖管廊舱室个数为偶数时:When the number of tunnel tunnels is an even number:

除末尾后开挖舱室外,其他后开挖舱室均按上述当暗挖管廊舱室个数为奇数时的施工方法施工。Except for the rear excavation cabins at the end, the other rear excavation cabins shall be constructed according to the construction method mentioned above when the number of underground excavation pipe gallery cabins is odd.

进一步的,末尾后开挖舱室进行土体开挖时,末尾后开挖舱室土体开挖方法根据开挖土体稳定性确定,可以采用全断面开挖、台阶法、预留核心土法等。Further, when excavating the cabin after the end for soil excavation, the soil excavation method for the cabin after the end is determined according to the stability of the excavated soil, and can adopt the full-section excavation, step method, reserved core soil method, etc. .

随着末尾后开挖舱室开挖,根据设计初期支护结构间距的要求及时安装末尾后开挖舱室拱顶初期支护结构及竖向初期支护结构。With the excavation of the post-excavation cabin, the initial support structure and vertical initial support structure of the dome of the post-excavation cabin should be installed in time according to the requirements of the initial support structure spacing in the design.

进一步的,末尾后开挖舱室拱顶初期支护结构一侧与相邻先开挖舱室拱顶初期支护结构预埋钢板连接,另一侧与竖向初期支护结构上部连接。采用锁脚锚杆临时加固竖向初期支护结构。在纵向相邻末尾后开挖舱室拱顶初期支护结构间及竖向初期支护结构间安装钢筋网片并喷射末尾后开挖舱室拱顶初期支护结构混凝土及竖向初期支护结构混凝土。Further, one side of the initial support structure of the dome of the cabin excavated after the end is connected with the embedded steel plate of the initial support structure of the adjacent dome of the first excavated cabin, and the other side is connected with the upper part of the vertical initial support structure. The vertical primary support structure is temporarily reinforced by locking foot anchors. Install reinforced mesh between the initial support structure of the cabin vault and the vertical initial support structure after the longitudinal adjacent end, and spray the concrete for the initial support structure of the cabin vault and the concrete for the initial vertical support structure after the end .

进一步的,待末尾后开挖舱室拱顶初期支护结构及竖向初期支护结构混凝土达到设计要求后,安装末尾后开挖舱室底板初期支护结构,末尾后开挖舱室底板初期支护结构一侧与相邻先开挖舱室底板初期支护结构预埋钢板连接,另一侧与竖向初期支护结构下部连接,在纵向相邻的末尾后开挖舱室底板初期支护结构间安装钢筋网片并喷射末尾后开挖舱室底板初期支护结构混凝土。Further, after the initial support structure of the cabin vault and the initial vertical support structure concrete meet the design requirements after the end of the excavation, install the initial support structure of the cabin bottom excavated after the end, and excavate the initial support structure of the cabin bottom after the end. One side is connected to the pre-embedded steel plate of the initial support structure of the adjacent first excavated cabin floor, the other side is connected to the lower part of the vertical initial support structure, and the steel bars are installed between the initial support structures of the cabin floor after excavation at the end of the longitudinal adjacent end. Excavate the initial supporting structure concrete of the cabin floor after the mesh and spray the end.

优选的,后开挖舱室拱顶初期支护结构及末尾后开挖舱室拱顶初期支护结构分别与拱顶初期支护结构预埋钢板的连接方式可以是焊接连接或螺栓连接。Preferably, the connection between the initial support structure of the rear excavation cabin vault and the initial support structure of the rear excavation cabin vault and the embedded steel plate of the initial support structure of the vault may be welding connection or bolt connection.

优选的,后开挖舱室底板初期支护结构及末尾后开挖舱室底板初期支护结构分别与底板初期支护结构预埋钢板的连接方式可以是焊接连接或螺栓连接。Preferably, the connection between the initial support structure of the rear excavation cabin floor and the initial support structure of the rear excavation cabin floor and the embedded steel plate of the initial support structure of the floor can be welding connection or bolt connection.

优选的,相邻先开挖舱室开挖深达到10.0m~15.0m后,开始后开挖舱室开挖及末尾后开挖舱室的开挖。Preferably, after the excavation depth of the adjacent first-excavated cabin reaches 10.0m~15.0m, the excavation of the post-excavation cabin is started and the excavation of the post-excavation cabin is completed.

步骤9:拆除先后开挖舱室间竖向初期支护结构。Step 9: Remove the vertical initial support structure between the successively excavated cabins.

需要说明的是,拆除先后开挖舱室间竖向初期支护结构的目的是使暗挖管廊初期支护结构形成一个连续的整体初期支护结构。It should be noted that the purpose of removing the vertical initial support structure between successively excavated cabins is to form a continuous overall initial support structure for the initial support structure of the underground excavation pipe gallery.

拆除先后开挖舱室间竖向初期支护结构过程中应注意不能破坏已完成的先开挖舱室拱顶初期支护结构、先开挖舱室底板初期支护结构、先后开挖舱室共用竖向二衬结构(即暗挖管廊相邻舱室间共用中隔墙)、拱顶预留搭接防水层及底板预留搭接防水层。During the process of dismantling the vertical initial support structure between the successively excavated cabins, care should be taken not to damage the completed initial support structure of the dome roof of the first excavated cabin, the initial support structure of the first excavated cabin bottom plate, and the common vertical two The lining structure (that is, the common partition wall between the adjacent cabins of the underground tunnel), the lapped waterproof layer reserved for the vault and the lapped waterproof layer reserved for the bottom plate.

步骤10:铺设安装后开挖舱室防水层。Step 10: Lay and excavate the waterproof layer of the cabin after installation.

进一步的,铺设安装后开挖舱室防水层时,须使后开挖舱室拱顶防水层与拱顶预留搭接防水层有效搭接,确保防水效果。Further, when laying and installing the waterproof layer of the excavated cabin after installation, the waterproof layer of the dome roof of the rear excavation cabin must be effectively overlapped with the reserved overlapping waterproof layer of the vault to ensure the waterproof effect.

进一步的,铺设安装后开挖舱室防水层时,须使后开挖舱室底板防水层与底板预留搭接防水层有效搭接,确保防水效果。Further, when laying and installing the waterproof layer of the excavated cabin after installation, the waterproof layer of the bottom plate of the rear excavated cabin must be effectively overlapped with the reserved lap waterproof layer of the bottom plate to ensure the waterproof effect.

步骤11:后开挖舱室二衬结构钢筋安装及二衬结构混凝土浇筑。Step 11: Reinforcement installation of the secondary lining structure of the rear excavation cabin and concrete pouring of the secondary lining structure.

当暗挖管廊舱室个数为奇数时:When the number of cabins in the underground tunnel is odd:

进一步的,凿除与后开挖舱室相邻先开挖舱室拱顶二衬结构钢筋预埋钢板处的混凝土保护层,使拱顶二衬结构钢筋预埋钢板全部漏出,并确保拱顶二衬结构钢筋预埋钢板表面干净无杂物;Further, the concrete protective layer at the pre-embedded steel steel plate of the second lining structure of the dome of the first excavation cabin adjacent to the rear excavation cabin is removed, so that all the steel embedded steel plates of the second lining structure of the dome roof leak out, and ensure the second lining of the dome roof. The surface of the structural steel embedded steel plate is clean and free of debris;

然后,将后开挖舱室拱顶二衬结构钢筋与其相邻先开挖舱室拱顶二衬结构钢筋预埋钢板连接,并安装二衬结构纵向钢筋和箍筋,架设安装后开挖舱室拱顶二衬结构模板,浇筑后开挖舱室拱顶二衬结构混凝土;待后开挖舱室拱顶二衬结构混凝土达到设计要求后,拆除后开挖舱室拱顶二衬结构模板。Then, connect the second lining structural steel bar of the rear excavation cabin with the pre-embedded steel plate of the second lining structural steel bar of the adjacent first excavated cabin dome, install the longitudinal steel bars and stirrups of the second lining structure, and erect and install the rear excavation cabin vault The secondary lining structural formwork, excavate the secondary lining structural concrete of the cabin vault after pouring; after the secondary lining structural concrete of the secondary lining of the secondary lining of the post excavation cabin roof meets the design requirements, remove the secondary lining structural formwork of the secondary lining of the post excavation cabin vault.

进一步的,凿除与后开挖舱室相邻先开挖舱室底板二衬结构钢筋预埋钢板处的混凝土保护层,使底板二衬结构钢筋预埋钢板全部漏出,并确保底板二衬结构钢筋预埋钢板表面干净无杂物;Further, the concrete protective layer at the pre-embedded steel plate of the second lining structural steel bar on the bottom plate of the first excavation cabin adjacent to the rear excavation cabin is removed, so that all the embedded steel steel plate of the second lining structural steel bar on the bottom floor is leaked, and the pre-embedded steel steel plate of the second lining structure on the bottom floor is ensured. The surface of the buried steel plate is clean and free of debris;

然后,将后开挖舱室底板二衬结构钢筋与其相邻先开挖舱室底板二衬结构钢筋预埋钢板连接,并安装二衬结构纵向钢筋和箍筋,浇筑后开挖舱室底板二衬结构混凝土,并整平后开挖舱室底板二衬结构混凝土表面。Then, connect the secondary lining structural steel bars of the rear excavated cabin floor with the pre-embedded steel plates adjacent to the secondary lining structural steel bars of the first excavated cabin floor, install the longitudinal steel bars and stirrups of the secondary lining structure, and excavate the secondary lining structural concrete of the cabin floor after pouring. , and excavate the second-lined structural concrete surface of the cabin floor after leveling.

当暗挖管廊舱室个数为偶数时:When the number of tunnel tunnels is an even number:

除末尾后开挖舱室外,其他后开挖舱室均按上述当暗挖管廊舱室个数为奇数时的施工方法施工。Except for the rear excavation cabins at the end, the other rear excavation cabins shall be constructed according to the construction method mentioned above when the number of underground excavation pipe gallery cabins is odd.

进一步的,安装末尾后开挖舱室拱顶二衬结构钢筋、竖向二衬结构钢筋、末尾后开挖舱室底板二衬结构钢筋及二衬结构纵向钢筋和箍筋。Further, install the secondary lining structural steel bar and vertical secondary lining structural steel bar of the rear excavation cabin at the end, the secondary lining structural steel bar and the secondary lining structural longitudinal steel bar and stirrup of the rear excavation cabin bottom plate.

末尾后开挖舱室拱顶二衬结构钢筋一侧与相邻先开挖舱室拱顶二衬结构钢筋预埋钢板连接,另一侧与竖向二衬结构钢筋连接;末尾后开挖舱室底板二衬结构钢筋一侧与相邻先开挖舱室底板二衬结构钢筋预埋钢板连接,另一侧与竖向二衬结构钢筋连接。At the end of the excavation, one side of the second lining structural steel bar of the cabin vault is connected with the pre-buried steel plate of the adjacent second lining structural steel bar of the first excavation cabin, and the other side is connected with the vertical second lining structural steel bar; One side of the lining structural steel bar is connected with the pre-embedded steel plate for the second lining structural steel bar on the bottom of the adjacent first excavated cabin, and the other side is connected with the vertical second lining structural steel bar.

架设安装末尾后开挖舱室拱顶二衬结构模板及竖向二衬结构模板,浇筑末尾后开挖舱室拱顶二衬结构混凝土及竖向二衬结构混凝土;待末尾后开挖舱室拱顶二衬结构混凝土及竖向二衬结构混凝土达到设计要求后,拆除末尾后开挖舱室拱顶二衬结构模板及竖向二衬结构模板。After erection and installation, excavate the cabin dome secondary lining structural formwork and vertical secondary lining structural formwork, excavate the cabin dome secondary lining structural concrete and vertical secondary lining structural concrete after the end of pouring; After the lining structural concrete and the vertical secondary lining structural concrete meet the design requirements, the secondary lining structural formwork and the vertical secondary lining structural formwork of the cabin vault shall be excavated at the end of the excavation.

然后,浇筑末尾后开挖舱室底板二衬结构混凝土,并整平末尾后开挖舱室底板二衬结构混凝土表面。Then, excavate the secondary lining structural concrete of the cabin floor after the end of pouring, and level the surface of the secondary lining structural concrete of the cabin floor after the end of the excavation.

优选的,后开挖舱室拱顶二衬结构钢筋及末尾后开挖舱室拱顶二衬结构钢筋分别与拱顶二衬结构钢筋预埋钢板的连接方式为焊接连接。Preferably, the second lining structural steel bar of the rear excavation cabin and the second rear lining structural steel bar of the rear excavation cabin are respectively connected with the pre-embedded steel plate of the second lining structural steel roof of the dome by welding connection.

优选的,后开挖舱室底板二衬结构钢筋及末尾后开挖舱室底板二衬结构钢筋分别与底板二衬结构钢筋预埋钢板的连接方式为焊接连接。Preferably, the second lining structural steel bars of the rear excavation cabin floor and the second lining structural steel bars of the rear excavation cabin floor at the end are respectively connected with the pre-embedded steel plates of the second floor lining structural steel bars by welding connection.

上述施工方法中省略了本领域技术人员熟知的前期常规施工前准备、施工过程中必要的安全措施、质量要求、基本技术及操作规程等。The above-mentioned construction method omits the pre-conventional pre-construction preparations, necessary safety measures, quality requirements, basic techniques and operating rules during construction, which are well known to those skilled in the art.

本发明至少具有如下优点或有益效果:The present invention has at least the following advantages or beneficial effects:

本发明提供一种多舱室管廊暗挖施工方法,所述多舱室管廊暗挖施工方法有效的减小了暗挖管廊相邻舱室间共用中隔墙的厚度,本发明在满足暗挖支护条件的前提下,可以使暗挖管廊相邻舱室间共用中隔墙与明挖管廊相邻舱室间共用中隔墙保持一致,使明挖法施工的多舱室管廊与暗挖法施工的多舱室管廊直接相接,不用设置中隔墙厚度过渡段。The invention provides a multi-cabin pipe gallery underground excavation construction method, which effectively reduces the thickness of the common partition wall between adjacent cabins of the undercover pipe gallery. Under the premise of supporting conditions, the common partition wall between the adjacent cabins of the open-cut pipe gallery can be kept consistent with the common partition wall between the adjacent cabins of the open-cut pipe gallery, so that the multi-cabin pipe gallery constructed by the open-cut method can be compared with the open-cut pipe gallery. The multi-chamber pipe gallery constructed by the method is directly connected, and there is no need to set the thickness transition section of the middle partition wall.

附图说明Description of drawings

为了更清楚地说明本发明的技术方案,下面将对本发明所需要使用的附图作简单地介绍,应当理解,以下附图不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to illustrate the technical solution of the present invention more clearly, the following will briefly introduce the drawings required for the present invention. It should be understood that the following drawings should not be regarded as a limitation of the scope. In other words, on the premise of no creative work, other related drawings can also be obtained from these drawings.

图1为所述多舱室管廊暗挖施工方法流程图;Fig. 1 is described multi-chamber pipe gallery underground excavation construction method flow chart;

图2为以三舱室管廊为例,采用明挖法施工的多舱室管廊截面图;Figure 2 is a cross-sectional view of the multi-cabin pipe gallery constructed by the open-cut method, taking the three-cabin pipe gallery as an example;

图3为以三舱室管廊为例,采用一般暗挖法施工的多舱室管廊截面图;Figure 3 is a cross-sectional view of a multi-chamber pipe gallery constructed by a general underground excavation method, taking the three-cabin pipe gallery as an example;

图4为实施例1暗挖管廊初期支护结构截面图;Fig. 4 is the sectional view of the initial support structure of the underground excavation pipe gallery in Example 1;

图5为实施例1暗挖管廊二衬结构及二衬结构钢筋布置截面图;5 is a cross-sectional view of the secondary lining structure of the underground excavation pipe gallery and the arrangement of the reinforcement bars of the secondary lining structure in Embodiment 1;

图6为实施例1先开挖舱室初期支护结构、二衬结构及防水层示意图;6 is a schematic diagram of the initial support structure, secondary lining structure and waterproof layer of the first excavated cabin in Example 1;

图7为实施例1后开挖舱室初期支护结构、二衬结构及防水层示意图;7 is a schematic diagram of the initial support structure, secondary lining structure and waterproof layer of the excavated cabin after Example 1;

图8为实施例2先开挖舱室初期支护结构、二衬结构及防水层示意图;8 is a schematic diagram of the initial support structure, secondary lining structure and waterproof layer of the first excavated cabin in Example 2;

图9为实施例2后开挖舱室及末尾后开挖舱室初期支护结构、二衬结构及防水层示意图。9 is a schematic diagram of the initial support structure, the secondary lining structure and the waterproof layer of the post-excavation cabin and the final post-excavation cabin in Example 2.

图标:1-先开挖舱室;11-先开挖舱室拱顶初期支护结构;111-拱顶初期支护结构预埋钢板;12-先开挖舱室底板初期支护结构;121-底板初期支护结构预埋钢板;13-先开挖舱室拱顶二衬结构;131-先开挖舱室拱顶二衬结构钢筋;1311-拱顶二衬结构钢筋预埋钢板;14-先开挖舱室底板二衬结构;141-先开挖舱室底板二衬结构钢筋;1411-底板二衬结构钢筋预埋钢板;15-先开挖舱室防水层;151-先开挖舱室拱顶防水层;1511-拱顶预留搭接防水层;152-先开挖舱室底板防水层;1521-底板预留搭接防水层;2-后开挖舱室;21-后开挖舱室拱顶初期支护结构;22-后开挖舱室底板初期支护结构;23-后开挖舱室拱顶二衬结构;231-后开挖舱室拱顶二衬结构钢筋;24-后开挖舱室底板二衬结构;241-后开挖舱室底板二衬结构钢筋;25-后开挖舱室防水层;251-后开挖舱室拱顶防水层;252-后开挖舱室底板防水层;26-末尾后开挖舱室;261-末尾后开挖舱室拱顶初期支护结构;262-末尾后开挖舱室底板初期支护结构;263-末尾后开挖舱室拱顶二衬结构;264-末尾后开挖舱室底板二衬结构;31-初期支护结构;311-一般暗挖管廊共用竖向初期支护结构;312-先后开挖舱室间竖向初期支护结构;313-竖向初期支护结构;41-二衬结构;411-二衬结构钢筋;412-竖向二衬结构;4121-竖向二衬结构钢筋;413-二衬结构纵向钢筋和箍筋;414-先后开挖舱室共用竖向二衬结构;4141-先后开挖舱室共用竖向二衬结构钢筋;51-明挖管廊相邻舱室间共用中隔墙。Icons: 1- Excavate the cabin first; 11- Excavate the initial support structure of the cabin vault first; 111- Pre-embedded steel plate for the initial support structure of the vault; 12- Excavate the initial support structure of the cabin bottom plate first; 121- The initial stage of the bottom plate Pre-embedded steel plate for supporting structure; 13- First excavation of the second lining structure of the cabin dome; 131- First excavation of the second lining structure of the cabin dome; 1311 - Pre-embedded steel plate of the second lining structure of the vault; 14- First excavation of the cabin Bottom two lining structure; 141- First excavation cabin bottom two lining structural steel bars; 1411- Bottom two bottom lining structural steel bars pre-embedded steel plate; 15- First excavating cabin waterproof layer; 151- First excavating cabin dome waterproof layer; 1511- 152- First-excavation cabin bottom waterproof layer; 1521- Bottom plate reserved lap waterproof layer; 2- Rear excavation cabin; 21- Rear excavation cabin vault initial support structure; 22 - Initial support structure of the rear excavation cabin floor; 23- The second lining structure of the rear excavation cabin vault; 231- The second lining structure of the rear excavation cabin dome; 24- The second lining structure of the rear excavation cabin floor; 241 - The rear 25- Rear excavation cabin waterproof layer; 251- Rear excavation cabin dome waterproof layer; 252- Rear excavation cabin floor waterproof layer; 26- Rear excavation cabin; 261- End 262-Initial support structure of the rear excavation cabin vault; 262-Initial support structure of the rear excavation cabin bottom plate; 263-The second lining structure of the rear excavation cabin dome; 264-The second lining structure of the rear excavation cabin bottom plate;31 -Initial support structure; 311- Vertical initial support structure shared by general underground tunnels; 312- Vertical initial support structure between successively excavated cabins; 313-Vertical initial support structure; 41- Secondary lining structure; 411- Secondary lining structural steel bar; 412-Vertical secondary lining structure; 4121-Vertical secondary lining structural steel bar; 413- Secondary lining structural longitudinal steel bar and stirrup; The cabins excavated successively share the vertical secondary lining structural steel bars; the adjacent cabins of the 51-cut and cut pipe gallery share the middle partition wall.

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚,下面将结合本发明实施例的附图,对本发明施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。In order to make the purpose, technical solutions and advantages of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are the present invention. Some examples, but not all examples.

因此,以下对在附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的发明的范围,而是仅仅表示本发明的选定实施例。基于本发明的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明的范围。Thus, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts shall fall within the scope of the present invention.

应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。It should be noted that like numerals and letters refer to like items in the following figures, so once an item is defined in one figure, it does not require further definition and explanation in subsequent figures.

在本发明实施例的描述中,需要说明的是,若出现术语“中心”、“上”、“下”、“左”、“右”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该发明中惯常摆放的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对发明的限制。此外,术语“第一”、“第二”、“第三”等仅用于区分描述,而不能理解为指示或暗示相对重要性。In the description of the embodiments of the present invention, it should be noted that if the terms "center", "upper", "lower", "left", "right", "inner", "outer", etc. indicate the orientation or position The relationship is based on the orientation or positional relationship shown in the drawings, or the orientation or positional relationship that is conventionally placed in the invention, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must be It has a specific orientation, is constructed and operates in a specific orientation, and therefore should not be construed as a limitation of the invention. Furthermore, the terms "first", "second", "third", etc. are only used to differentiate the description and should not be construed as indicating or implying relative importance.

在本发明实施例的描述中,还需要说明的是,除非另有明确的规定和限定,若出现术语“设置”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是焊接连接等;可以是直接相连,也可以通过中间媒介间接相连。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the description of the embodiments of the present invention, it should also be noted that, unless otherwise expressly specified and limited, the terms "set", "installed", "connected" and "connected" should be understood in a broad sense. It can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or a welding connection; it can be directly connected or indirectly connected through an intermediate medium. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific situations.

实施例1Example 1

实施例1基本情况,某3舱管廊为干线综合管廊,是连接市区和机场的重要市政通道。该管廊需下穿某一级公路,暗挖段长度为30.0m。管廊两侧舱室为电力舱及热力舱,舱室宽均为2.0m;中舱室为水信舱,舱室宽为3.9m;该管廊高度为5.0m。该管廊初期支护结构(31)为钢筋格栅,初期支护结构(31)混凝土厚度为0.25m;二衬结构(41)厚度为0.4m,与明挖管廊相邻舱室间共用中隔墙(51)厚度一致。The basic situation of Example 1, a certain 3-cabin pipe gallery is a trunk line integrated pipe gallery, which is an important municipal passage connecting the urban area and the airport. The pipe gallery needs to pass through a certain level of road, and the length of the undercut section is 30.0m. The cabins on both sides of the pipe gallery are power cabins and thermal cabins, and the width of the cabins is 2.0m; the middle cabin is the water signal cabin, and the width of the cabin is 3.9m; the height of the pipe gallery is 5.0m. The initial support structure (31) of the pipe gallery is a steel grating, and the concrete thickness of the initial support structure (31) is 0.25m; the thickness of the secondary lining structure (41) is 0.4m, which is shared with the adjacent cabins of the cut-and-cover pipe gallery. The thickness of the partition wall (51) is the same.

请参照图1及图4~图7所示。实施例1中,两侧舱室为先开挖舱室(1),中舱室为后开挖舱室(2),所述多舱室管廊暗挖施工方法如下:Please refer to Figure 1 and Figure 4 to Figure 7. In Embodiment 1, the cabins on both sides are the first excavation cabin (1), the middle cabin is the rear excavation cabin (2), and the construction method of the multi-chamber pipe gallery underground excavation is as follows:

步骤1:暗挖管廊初期支护结构(31)加工及二衬结构钢筋(411)加工。Step 1: Processing of the initial support structure (31) of the buried pipe gallery and the processing of the secondary lining structural steel bar (411).

实施例1中,初期支护结构(31)为钢筋格栅。初期支护结构(31)和二衬结构钢筋(411)根据设计图纸进行预先加工。In Embodiment 1, the initial support structure (31) is a steel grating. The primary support structure (31) and the secondary lining structural steel bar (411) are pre-processed according to the design drawings.

加工先开挖舱室拱顶初期支护结构(11)时,在先开挖舱室拱顶初期支护结构(11)靠近后开挖舱室(2)侧的拱脚处附近设置拱顶初期支护结构预埋钢板(111),用于后开挖舱室拱顶初期支护结构(21)与相邻先开挖舱室拱顶初期支护结构(11)连接。When processing the preliminary support structure (11) of the first excavation cabin dome, the preliminary support structure of the first excavation cabin (11) is set near the arch foot of the back excavation cabin (2) side. The structural pre-embedded steel plate (111) is used to connect the initial support structure (21) of the dome of the rear excavation cabin with the initial support structure (11) of the adjacent first excavated cabin dome.

加工先开挖舱室底板初期支护结构(12)时,在先开挖舱室底板初期支护结构(12)靠近后开挖舱室(2)侧设置底板初期支护结构预埋钢板(121),用于后开挖舱室底板初期支护结构(22)与相邻先开挖舱室底板初期支护结构(12)连接。When processing the preliminary support structure (12) of the first excavation cabin floor, the pre-embedded steel plate (121) of the bottom preliminary support structure is arranged on the side of the first excavated cabin bottom preliminary support structure (12) close to the rear excavation cabin (2). It is used for connecting the initial support structure (22) of the bottom of the cabin after excavation with the preliminary support structure (12) of the bottom of the adjacent first excavated cabin.

加工先开挖舱室拱顶二衬结构钢筋(131)时,在先开挖舱室拱顶二衬结构钢筋(131)靠近后开挖舱室(2)侧的拱脚处附近设置拱顶二衬结构钢筋预埋钢板(1311),用于后开挖舱室拱顶二衬结构钢筋(231)与相邻先开挖舱室拱顶二衬结构钢筋(131)连接。When the structural steel bar (131) for the second lining of the cabin dome is excavated first, the second lining structure of the dome is set near the arch foot of the first excavated cabin dome second lining structural steel bar (131) near the side of the second excavated cabin (2). The steel pre-embedded steel plate (1311) is used for connecting the second lining structural steel bar (231) of the cabin dome of the rear excavation with the second lining structural steel bar (131) of the adjacent first excavated cabin dome.

加工先开挖舱室底板二衬结构钢筋(141)时,在先开挖舱室底板二衬结构钢筋(141)靠近后开挖舱室(2)侧设置底板二衬结构钢筋预埋钢板(1411),用于后开挖舱室底板二衬结构钢筋(241)与相邻先开挖舱室底板二衬结构钢筋(141)连接。When processing the second lining structural steel bar (141) of the first excavation cabin floor, the pre-embedded steel plate (1411) of the second floor second lining structural steel bar is set on the side of the first excavating cabin floor second lining structural steel bar (141) close to the rear excavation cabin (2). It is used for connecting the second lining structural steel bar (241) of the bottom excavated cabin floor with the second lining structural steel bar (141) of the adjacent first excavated cabin bottom floor.

还需加工后开挖舱室的拱顶初期支护结构(21)、后开挖舱室的底板初期支护结构(22)、后开挖舱室的拱顶二衬支护钢筋(231)、后开挖舱室的底板二衬支护钢筋(241)、竖向二衬结构钢筋(4121)及二衬结构纵向钢筋和箍筋(413)、竖向初期支护结构(313)。It is also necessary to process the initial support structure (21) of the dome of the rear excavation cabin, the initial support structure of the bottom plate of the rear excavation cabin (22), the second lining supporting steel bar of the dome of the rear excavation cabin (231), and the rear excavation cabin. The bottom plate of the excavated cabin is lined with a second lining supporting steel bar (241), a vertical second lining structural steel bar (4121), a second lining structure longitudinal steel bar and stirrups (413), and a vertical initial support structure (313).

由于先后开挖舱室间竖向初期支护结构(312)在后开挖舱室(2)施工过程中将被拆除,因此,先后开挖舱室间竖向初期支护结构(312)需要单独设置,便于后期拆除。Since the vertical initial support structure (312) between the successively excavated cabins will be removed during the construction of the later excavated cabin (2), the vertical initial support structure (312) between the successively excavated cabins needs to be set separately. Easy to dismantle later.

步骤2:暗挖管廊舱室开挖前,加固开挖土体。Step 2: Reinforce the excavated soil before excavating the cabin of the underground tunnel.

开挖土体加固时,开挖土体加固措施根据开挖土体的稳定性,实施例1中,全断面开挖土体加固采用深孔注浆,深孔注浆使用水泥浆液进行注浆,水灰比为1:1,一次注浆深度为10.0m,注浆半径不小于1.5m,确保土体开挖前,完成暗挖管廊所有舱室开挖土体的加固。When the excavated soil is reinforced, the reinforcement measures of the excavated soil are based on the stability of the excavated soil. In Example 1, deep-hole grouting is used for the reinforcement of the full-section excavated soil, and cement slurry is used for grouting in the deep-hole. , the water-cement ratio is 1:1, the depth of one grouting is 10.0m, and the grouting radius is not less than 1.5m, so as to ensure that the soil reinforcement of all cabins of the underground tunnel is completed before the soil is excavated.

步骤3:先开挖舱室(1)处行土体开挖及初期支护结构(31)安装施工。Step 3: First excavate the cabin (1) for soil excavation and installation of the initial support structure (31).

实施例1中,先开挖舱室(1)采用台阶法进行土体开挖,上下台阶错开4.0m~5.0m。In Example 1, the cabin (1) was excavated first by adopting the step method for soil excavation, and the upper and lower steps were staggered by 4.0m to 5.0m.

随着先开挖舱室(1)开挖,根据设计初期支护结构(31)间距的要求及时安装先开挖舱室拱顶初期支护结构(11)、先后开挖舱室间竖向初期支护结构(312)及竖向初期支护结构(313),并采用锁脚锚杆临时加固先后开挖舱室间竖向初期支护结构(312)及竖向初期支护结构(313),在纵向相邻的先开挖舱室拱顶初期支护结构(11)间、先后开挖舱室间竖向初期支护结构(312)间及竖向初期支护结构(313)间安装钢筋网片并喷射先开挖舱室拱顶初期支护结构(11)、先后开挖舱室间竖向初期支护结构(312)及竖向初期支护结构(313)混凝土。With the excavation of the first excavation cabin (1), according to the requirements of the initial design support structure (31) spacing, install the first excavation cabin dome preliminary support structure (11) in time, and successively excavate the vertical preliminary support between the cabins The structure (312) and the vertical initial support structure (313) are temporarily reinforced with locking anchor rods. Reinforcement mesh is installed and sprayed between the adjacent first-excavated cabin vault initial support structures (11), the successively excavated vertical initial support structures (312) and vertical initial support structures (313) First, excavate the initial support structure (11) of the cabin vault, and then excavate the concrete of the vertical initial support structure (312) and the vertical initial support structure (313) between the cabins successively.

待先开挖舱室拱顶初期支护结构(11)、先后开挖舱室间竖向初期支护结构(312)及竖向初期支护结构(313)混凝土达到设计要求后,安装先开挖舱室底板初期支护结构(12),在纵向相邻的先开挖舱室底板初期支护结构(12)间安装钢筋网片并喷射先开挖舱室底板初期支护结构(12)混凝土。After excavating the preliminary support structure (11) of the cabin vault, excavating the vertical preliminary support structure (312) and vertical preliminary support structure (313) between the cabins successively to meet the design requirements, the first excavation cabin is installed. As for the initial support structure (12) of the bottom plate, a steel mesh sheet is installed between the longitudinally adjacent preliminary support structures (12) of the cabin bottom plate which are excavated first, and concrete is sprayed for the preliminary support structure (12) of the first excavated cabin bottom plate.

先开挖舱室(1)中,先开挖舱室拱顶初期支护结构(11)、先后开挖舱室间竖向初期支护结构(312)、竖向初期支护结构(313)及先开挖舱室底板初期支护结构(12)之间采用螺栓连接。In the first excavation of the cabin (1), the preliminary support structure (11) of the cabin dome is excavated first, the vertical preliminary support structure (312), the vertical preliminary support structure (313), and the Bolt connection is adopted between the initial support structures (12) of the bottom plate of the excavated cabin.

步骤4:整平先后开挖舱室间竖向初期支护结构(312)靠近后开挖舱室(2)侧的混凝土表面。Step 4: Leveling the concrete surface of the vertical initial support structure (312) between the successive excavation cabins close to the side of the rear excavation cabin (2).

步骤5:铺设安装先开挖舱室防水层(15)并预留用于与相邻后开挖舱室防水层(25)搭接的预留搭接防水层。Step 5: Lay and install a pre-excavated cabin waterproof layer (15) and a reserved overlap waterproof layer reserved for overlapping with the adjacent rear-excavated cabin waterproof layer (25).

需要在先开挖舱室拱顶防水层(151)在靠近后开挖舱室(2)侧预留用于与相邻后开挖舱室拱顶防水层(251)搭接的拱顶预留搭接防水层(1511)。It is necessary to reserve the lap joint of the vault on the side close to the rear excavation cabin (2) for overlapping with the vault waterproof layer (251) of the adjacent rear excavation cabin. Waterproof layer (1511).

需要在先开挖舱室底板防水层(152)在靠近后开挖舱室(2)侧预留用于与相邻后开挖舱室底板防水层(252)搭接的底板预留搭接防水层(1521)。It is necessary to reserve the lap waterproof layer ( 1521).

拱顶预留搭接防水层(1511)及底板预留搭接防水层(1521)长度为0.5m~0.6m。The length of the reserved overlapping waterproof layer (1511) for the vault and the reserved overlapping waterproof layer (1521) for the bottom plate is 0.5m~0.6m.

为节省防水材料,不铺设后续施工需要拆除的先后开挖舱室间竖向初期支护结构(312)处的防水层。In order to save waterproof materials, the waterproof layer at the vertical initial support structure (312) between the successive excavation cabins that needs to be removed in the subsequent construction is not laid.

步骤6:在先后开挖舱室间竖向初期支护结构(312)靠近后开挖舱室(2)侧的混凝土表面均匀涂抹脱模剂。Step 6: Evenly apply release agent on the concrete surface of the vertical initial support structure (312) between the successive excavation cabins near the side of the rear excavation cabin (2).

步骤7:先开挖舱室二衬结构钢筋(411)安装及二衬结构(41)混凝土浇筑。Step 7: First, excavate the reinforcement bars (411) of the cabin secondary lining structure and install the concrete for the secondary lining structure (41).

安装先开挖舱室拱顶二衬结构钢筋(131)、竖向二衬结构钢筋(4121)、先后开挖舱室共用竖向二衬结构钢筋(4141)、先开挖舱室底板二衬结构钢筋(141)及二衬结构纵向钢筋和箍筋(413)。Install the double lining structural steel bar (131) for the first excavation of the cabin dome, the vertical second lining structural steel bar (4121), the common vertical second lining structural steel bar (4141) for excavating the cabin first, and the second lining structural steel bar for the second lining of the cabin floor ( 141) and the longitudinal reinforcement and stirrups (413) of the secondary lining structure.

架设安先开挖舱室装拱顶二衬结构(13)、竖向二衬结构(412)及先后开挖舱室共用竖向二衬结构(414)模板,浇筑先开挖舱室装拱顶二衬结构(13)、竖向二衬结构(412)及先后开挖舱室共用竖向二衬结构(414)混凝土;待先开挖舱室装拱顶二衬结构(13)、竖向二衬结构(412)及先后开挖舱室共用竖向二衬结构(414)混凝土达到设计要求后,拆除先开挖舱室装拱顶二衬结构(13)、竖向二衬结构(412)及先后开挖舱室共用竖向二衬结构(414)模板,然后浇筑先开挖舱室底板二衬结构(14)混凝土,并整平先开挖舱室底板二衬结构(14)混凝土表面。Erection the first-excavated cabin with dome secondary lining structure (13), the vertical secondary lining structure (412), and the successively excavated cabins share the vertical secondary lining structure (414) formwork, and pour the first-excavated cabin with vaulted secondary lining Structure (13), vertical secondary lining structure (412) and successively excavated cabins share vertical secondary lining structure (414) concrete; 412) and successively excavated cabins sharing the vertical secondary lining structure (414) After the concrete meets the design requirements, dismantle the first excavated cabin to install the dome secondary lining structure (13), the vertical secondary lining structure (412) and the successively excavated cabins The vertical secondary lining structure (414) formwork is shared, and then the concrete of the secondary lining structure (14) of the cabin floor is excavated first, and the concrete surface of the secondary lining structure (14) of the cabin floor is leveled.

先开挖舱室(1)中,先开挖舱室拱顶二衬结构钢筋(131)、竖向二衬结构钢筋(4121)、先后开挖舱室共用竖向二衬结构钢筋(4141)及先开挖舱室底板二衬结构钢筋(141)之间采用焊接连接。In the first excavation of the cabin (1), the second lining structural steel bar (131) and the vertical second lining structural steel bar (4121) of the cabin dome are excavated first. Welding connection is adopted between the second lining structural steel bars (141) of the bottom plate of the excavated cabin.

步骤8:后开挖舱室(2)处土体开挖及初期支护结构(31)安装施工。Step 8: The soil excavation at the rear excavation cabin (2) and the installation and construction of the initial support structure (31).

实施例1中,后开挖舱室(2)采用上下台阶法施工,上下台阶错开距离为4.0m~5.0m。In Example 1, the rear excavation cabin (2) is constructed by the upper and lower steps method, and the staggered distance between the upper and lower steps is 4.0m~5.0m.

实施例1中,暗挖管廊舱室个数为3,是奇数。In Example 1, the number of cabins in the underground tunnel is 3, which is an odd number.

上台阶开挖深度为4.0m~5.0m时,凿除与后开挖舱室(2)相邻先开挖舱室(1)拱顶初期支护结构预埋钢板(111)处的混凝土保护层,使拱顶初期支护结构预埋钢板(111)全部漏出,并确保拱顶初期支护结构预埋钢板(111)表面干净无杂物;When the excavation depth of the upper step is 4.0m~5.0m, the concrete protective layer at the pre-embedded steel plate (111) of the initial support structure of the vault shall be removed by chiseling and removing the adjacent first-excavated cabin (1) to the rear-excavated cabin (2). Make all the embedded steel plates (111) of the initial support structure of the vault leak out, and ensure that the surface of the embedded steel plates (111) of the initial support structure of the vault is clean and free of debris;

然后,将后开挖舱室拱顶初期支护结构(21)与相邻先开挖舱室(1)拱顶支护结构预埋钢板连接(111),在纵向相邻后开挖舱室拱顶初期支护结构(21)间安装钢筋网片并喷射后开挖舱室拱顶初期支护结构(21)混凝土。Then, connect (111) the initial support structure (21) of the vault of the rear-excavated cabin with the embedded steel plate of the adjacent first-excavated cabin (1) vault support structure, and at the initial stage of the vault of the adjacent rear-excavated cabin in the longitudinal direction Reinforcing steel mesh sheets are installed between the supporting structures (21) and the concrete for the initial supporting structure (21) of the cabin vault is excavated after spraying.

后开挖舱室拱顶初期支护结构(21)混凝土施工完成后,进行下台阶开挖,凿除与后开挖舱室(2)相邻先开挖舱室(1)底板初期支护结构预埋钢板(121)处的混凝土保护层,使底板初期支护结构预埋钢板(121)全部漏出,并确保底板初期支护结构预埋钢板(121)表面干净无杂物;After the concrete construction of the initial support structure (21) of the vault of the rear excavation cabin is completed, the lower step excavation is carried out, and the first excavation cabin (1) adjacent to the rear excavation cabin (2) is removed and the initial support structure of the bottom plate is pre-buried The concrete protective layer at the steel plate (121) makes all the embedded steel plates (121) of the initial support structure of the base plate leak out, and ensures that the surface of the embedded steel plates (121) of the initial support structure of the base plate is clean and free of debris;

然后,将后开挖舱室底板初期支护结构(22)与相邻先开挖舱室(1)底板支护结构预埋钢板(121)连接,在纵向相邻后开挖舱室底板初期支护结构(22)间安装钢筋网片并喷射后开挖舱室底板初期支护结构(22)混凝土。Then, connect the initial support structure (22) of the bottom plate of the rear excavation cabin to the pre-embedded steel plate (121) of the bottom support structure of the adjacent first excavated cabin (1). (22) Install reinforcement mesh and excavate the initial support structure (22) concrete of the cabin floor after spraying.

后开挖舱室拱顶初期支护结构(21)与拱顶初期支护结构预埋钢板(111)的连接方式是焊接连接。The connection method between the initial support structure (21) of the rear excavation cabin vault and the embedded steel plate (111) of the initial support structure of the vault is welding connection.

后开挖舱室底板初期支护结构(22)与底板初期支护结构预埋钢板(121)的连接方式是焊接连接。The connection between the initial support structure (22) of the bottom plate of the rear excavation cabin and the embedded steel plate (121) of the initial support structure of the bottom plate is a welding connection.

相邻先开挖舱室(1)开挖深达到12.0m后,开始后开挖舱室(2)的开挖。After the adjacent first excavation cabin (1) reaches a depth of 12.0m, the excavation of the rear excavation cabin (2) starts.

步骤9:拆除先后开挖舱室间竖向初期支护结构(312)。Step 9: Remove the vertical initial support structure (312) between the successively excavated cabins.

步骤10:铺设安装后开挖舱室防水层(25)。Step 10: Lay the waterproof layer (25) of the excavated cabin after installation.

铺设安装后开挖舱室防水层(25)时,须使后开挖舱室拱顶防水层(251)与拱顶预留搭接防水层(1511)有效搭接,确保防水效果。When laying and installing the post-excavation cabin waterproof layer (25), the post-excavation cabin dome waterproof layer (251) must be effectively overlapped with the dome reserved lap waterproof layer (1511) to ensure the waterproof effect.

铺设安装后开挖舱室防水层(25)时,须使后开挖舱室底板防水层(252)与底板预留搭接防水层(1521)有效搭接,确保防水效果。When laying the waterproof layer (25) of the excavated cabin after installation, the waterproof layer (252) of the bottom plate of the rear excavated cabin must be effectively overlapped with the reserved lap waterproof layer (1521) of the bottom plate to ensure the waterproof effect.

步骤11:后开挖舱室二衬结构钢筋(411)安装及二衬结构(41)混凝土浇筑。Step 11: Installation of the rebar (411) for the secondary lining structure of the rear excavation cabin and concrete pouring for the secondary lining structure (41).

实施例1中,暗挖管廊舱室个数为3,是奇数。In Example 1, the number of cabins in the underground tunnel is 3, which is an odd number.

凿除与后开挖舱室(2)相邻先开挖舱室(1)拱顶二衬结构钢筋预埋钢板(1311)处的混凝土保护层,使拱顶二衬结构钢筋预埋钢板(1311)全部漏出,并确保拱顶二衬结构钢筋预埋钢板(1311)表面干净无杂物;Chisel off the concrete protective layer at the first excavated cabin (1) adjacent to the rear excavation cabin (2) at the pre-buried steel steel plate (1311) of the secondary lining structure of the vault, so that the pre-buried steel steel plate (1311) of the secondary lining structure of the vault will be removed. All leakage, and ensure that the surface of the embedded steel plate (1311) of the second lining structure of the vault is clean and free of debris;

然后,将后开挖舱室拱顶二衬结构钢筋(231)与其相邻先开挖舱室(1)拱顶二衬结构钢筋预埋钢板(1311)连接,并安装二衬结构纵向钢筋和箍筋(413),架设安装后开挖舱室拱顶二衬结构(23)模板,浇筑后开挖舱室拱顶二衬结构(23)混凝土;待后开挖舱室拱顶二衬结构(23)混凝土达到设计要求后,拆除后开挖舱室拱顶二衬结构(23)模板。Then, connect the rebar (231) of the second lining structure of the rear excavated cabin with the pre-embedded steel plate (1311) of the second lining structural steel of the adjacent first excavated cabin (1), and install the longitudinal steel bars and stirrups of the second lining structure (413), erect and install the template of the second lining structure (23) of the excavated cabin dome, pour the concrete of the second lining structure of the second lining of the cabin dome (23) after pouring; After the design requirements are met, the template for the second lining structure (23) of the cabin dome is removed and excavated.

凿除与后开挖舱室(2)相邻先开挖舱室(1)底板二衬结构钢筋预埋钢板(1411)处的混凝土保护层,使底板二衬结构钢筋预埋钢板(1411)全部漏出,并确保底板二衬结构钢筋预埋钢板(1411)表面干净无杂物;Chisel off the concrete protective layer at the first excavation cabin (1) adjacent to the rear excavation cabin (2) at the pre-embedded steel plate (1411) of the second floor lining structure, so that all the pre-buried steel plates (1411) of the second floor lining structure are leaked , and ensure that the surface of the pre-embedded steel plate (1411) for the second lining structure of the bottom plate is clean and free of debris;

然后,将后开挖舱室底板二衬结构钢筋(241)与其相邻先开挖舱室(1)底板二衬结构钢筋预埋钢板(1411)连接,并安装二衬结构纵向钢筋和箍筋(413),浇筑后开挖舱室底板二衬结构(24)混凝土,并整平后开挖舱室底板二衬结构(24)混凝土表面。Then, connect the secondary lining structural steel bars (241) of the rear excavated cabin with the pre-embedded steel plates (1411) of the adjacent first excavated cabin (1) floor, and install the secondary lining structural longitudinal steel bars and stirrups (413). ), excavate the concrete of the secondary lining structure (24) of the cabin floor after pouring, and excavate the concrete surface of the secondary lining structure (24) of the cabin floor after leveling.

后开挖舱室拱顶二衬结构钢筋(231)与拱顶二衬结构钢筋预埋钢板(1311)的连接方式为焊接连接。The connection mode of the second lining structural steel bar (231) of the rear excavation cabin and the pre-embedded steel plate (1311) of the second lining structural steel bar of the vault is the welding connection.

后开挖舱室底板二衬结构钢筋(241)与底板二衬结构钢筋预埋钢板(1411)的连接方式为焊接连接。The connection mode of the second lining structural steel bar (241) of the rear excavation cabin and the pre-embedded steel plate (1411) of the second lining structural steel reinforcing bar of the floor is welding connection.

实施例2Example 2

实施例2基本情况,某4舱管廊下穿某河道,4个舱室宽度均为2.0m,其中包含2个电力舱、1个水信舱及1个备用舱,该暗挖管廊高4.5m。该管廊初期支护结构为工字钢,初期支护结构(31)混凝土厚度为0.3m;二衬结构厚度为0.4m,与明挖管廊相邻舱室间共用中隔墙(51)厚度一致。该暗挖管廊总长为50.0m。开挖土体加固措施采用超前管棚。The basic situation of Example 2, a 4-cabin pipe gallery passes through a certain river, and the width of the 4 cabins is 2.0m, including 2 power cabins, 1 water signal cabin and 1 spare cabin, and the height of the buried pipe gallery is 4.5m . The initial supporting structure of the pipe gallery is I-beam, the concrete thickness of the initial supporting structure (31) is 0.3m; the thickness of the secondary lining structure is 0.4m, and the thickness of the partition wall (51) is shared with the adjacent cabins of the cut-and-cut pipe gallery. Consistent. The total length of the underground tunnel is 50.0m. The excavation soil reinforcement measures adopt advanced pipe shed.

请参照图1及图8~图9所示。实施例2中,将暗挖管廊中包含的所有舱室从左端向右端依次编号为01号舱室、02号舱室、03号舱室及04号舱室,其中,01号舱室及03号舱室为先开挖舱室(1),02号舱室为后开挖舱室(2),04号舱室为末尾后开挖舱室(26)。所述多舱室管廊暗挖施工方法如下:Please refer to Figure 1 and Figure 8 to Figure 9. In Example 2, all the cabins included in the underground excavation pipe gallery are sequentially numbered from the left end to the right end as No. 01 cabin, No. 02 cabin, No. 03 cabin and No. 04 cabin, wherein, No. 01 cabin and No. 03 cabin are opened first. The excavation cabin (1), the No. 02 cabin is the rear excavation cabin (2), and the 04 cabin is the rear excavation cabin (26). The construction method for underground excavation of the multi-cabin pipe gallery is as follows:

01号舱室、02号舱室及03号舱室的施工方法请参照实施例1中所述施工方法。其中各步骤中不同参数有:Please refer to the construction method described in Example 1 for the construction methods of No. 01 cabin, No. 02 cabin and No. 03 cabin. The different parameters in each step are:

步骤1:暗挖管廊初期支护结构(31)加工及二衬结构钢筋(411)加工。Step 1: Processing of the initial support structure (31) of the buried pipe gallery and the processing of the secondary lining structural steel bar (411).

实施例2中,初期支护结构(31)为工字钢。In Example 2, the initial support structure (31) is an I-beam.

步骤2:暗挖管廊舱室开挖前,加固开挖土体。Step 2: Reinforce the excavated soil before excavating the tunnel cabin.

实施例2中,全断面开挖土体加固采用超前管棚。In Example 2, the full-section excavated soil was reinforced with an advanced pipe shed.

步骤3:先开挖舱室(1)处土体开挖及初期支护结构(31)安装施工。Step 3: First excavate the soil at the cabin (1) and install the initial support structure (31).

实施例2中,先开挖舱室(1)采用台阶法进行土体开挖,上下台阶错开3.0m~4.0m。In Example 2, the cabin (1) was excavated first by adopting the step method for soil excavation, and the upper and lower steps were staggered by 3.0m to 4.0m.

步骤5:铺设安装先开挖舱室防水层(15)并预留用于与相邻后开挖舱室防水层(25)搭接的预留搭接防水层。Step 5: Lay and install a pre-excavated cabin waterproof layer (15) and a reserved overlap waterproof layer reserved for overlapping with the adjacent rear-excavated cabin waterproof layer (25).

实施例2中,拱顶预留搭接防水层(1511)及底板预留搭接防水层(1521)长度为0.6m~0.7m。In Embodiment 2, the length of the reserved overlapping waterproof layer (1511) for the vault and the reserved overlapping waterproof layer (1521) for the bottom plate is 0.6 m to 0.7 m.

步骤8:后开挖舱室(2)处土体开挖及初期支护结构(31)安装施工。Step 8: The soil excavation at the rear excavation cabin (2) and the installation and construction of the initial support structure (31).

实施例2中,后开挖舱室(2)采用上下台阶法施工,上下台阶错开距离为3.0m~4.0m。In Example 2, the rear excavation cabin (2) is constructed by using the upper and lower steps method, and the staggered distance between the upper and lower steps is 3.0m~4.0m.

实施例2中,后开挖舱室拱顶初期支护结构(21)与拱顶初期支护结构预埋钢板(111)的连接方式是螺栓连接。In Embodiment 2, the connection method between the initial support structure (21) of the rear-excavated cabin dome and the embedded steel plate (111) of the initial support structure of the dome is bolt connection.

实施例2中,后开挖舱室底板初期支护结构(22)与底板初期支护结构预埋钢板(121)的连接方式是螺栓连接。In Embodiment 2, the connection mode of the initial support structure (22) of the back excavation cabin floor and the embedded steel plate (121) of the initial support structure of the floor is bolt connection.

实施例2中,相邻先开挖舱室(1)开挖深达到10.0m后,开始后开挖舱室(2)的开挖。In Example 2, after the excavation depth of the adjacent first excavation cabin (1) reaches 10.0 m, the excavation of the rear excavation cabin (2) is started.

由于实施例2暗挖管廊舱室个数为4,是偶数,因此,对于末尾后开挖舱室(26),步骤8及步骤11包括以一下内容:Since the number of cabins in the underground excavation pipe gallery in Example 2 is 4, which is an even number, for the rear excavation cabin (26) at the end, steps 8 and 11 include the following contents:

步骤8:后开挖舱室(2)处土体开挖及初期支护结构(31)安装施工。Step 8: The soil excavation at the rear excavation cabin (2) and the installation and construction of the initial support structure (31).

实施例2中,暗挖管廊舱室个数为4,是偶数。In Example 2, the number of cabins in the underground tunnel is 4, which is an even number.

末尾后开挖舱室(26)进行土体开挖采用台阶法。随着末尾后开挖舱室(26)开挖,根据设计初期支护结构间距的要求及时安装末尾后开挖舱室拱顶初期支护结构(261)及竖向初期支护结构(313)。After the end of the excavation of the cabin (26), the soil excavation adopts the step method. Following the excavation of the post-excavation cabin (26), install the post-excavation cabin dome preliminary support structure (261) and vertical preliminary support structure (313) in time according to the requirements of the initial design support structure spacing.

末尾后开挖舱室拱顶初期支护结构(261)一侧与相邻先开挖舱室(1)拱顶初期支护结构预埋钢板(111)连接,另一侧与竖向初期支护结构(313)上部连接。采用锁脚锚杆临时加固竖向初期支护结构(313)。在纵向相邻末尾后开挖舱室拱顶初期支护结构(261)间及竖向初期支护结构(313)间安装钢筋网片并喷射末尾后开挖舱室拱顶初期支护结构(261)混凝土及竖向初期支护结构(313)混凝土。One side of the preliminary support structure (261) of the dome of the cabin excavated after the end is connected with the embedded steel plate (111) of the preliminary support structure of the adjacent first excavated cabin (1), and the other side is connected with the vertical preliminary support structure (313) Upper connection. The vertical primary support structure (313) is temporarily reinforced with locking foot anchors. Install steel mesh between the initial support structure (261) and vertical initial support structure (313) of the cabin vault after the longitudinal adjacent end and excavate the initial support structure (261) of the cabin vault after spraying the end. Concrete and vertical primary support structure (313) Concrete.

待末尾后开挖舱室拱顶初期支护结构(261)及竖向初期支护结构(313)混凝土达到设计要求后,安装末尾后开挖舱室底板初期支护结构(262),末尾后开挖舱室底板初期支护结构(262)一侧与相邻先开挖舱室(1)底板初期支护结构预埋钢板(121)连接,另一侧与竖向初期支护结构(313)下部连接,在纵向相邻的末尾后开挖舱室底板初期支护结构(262)间安装钢筋网片并喷射末尾后开挖舱室底板初期支护结构(262)混凝土。After the end of the excavation, the initial support structure (261) and vertical initial support structure (313) of the cabin dome meet the design requirements, and then the initial support structure (262) of the cabin bottom plate will be excavated after the end of installation, and then excavated after the end of the installation. One side of the preliminary support structure (262) of the cabin floor is connected with the embedded steel plate (121) of the preliminary support structure of the adjacent first excavated cabin (1), and the other side is connected with the lower part of the vertical preliminary support structure (313). Install reinforced mesh between the longitudinally adjacent initial support structures (262) of the rear excavation cabin floor and spray concrete for the initial support structure (262) of the rear end excavation cabin floor.

末尾后开挖舱室拱顶初期支护结构(261)与拱顶初期支护结构预埋钢板(111)的连接方式是螺栓连接。The connection method of the initial support structure (261) of the cabin vault after the end of the excavation and the embedded steel plate (111) of the initial support structure of the vault is bolt connection.

末尾后开挖舱室底板初期支护结构(262)与底板初期支护结构预埋钢板(121)的连接方式是螺栓连接。The connection method between the initial support structure (262) of the cabin floor after the end excavation and the embedded steel plate (121) of the initial support structure of the floor is bolt connection.

步骤11:后开挖舱室(2)二衬结构钢筋(411)安装及二衬结构(41)混凝土浇筑。Step 11: Reinforcement (411) of the secondary lining structure is installed in the rear excavation cabin (2) and concrete is poured for the secondary lining structure (41).

实施例2中,暗挖管廊舱室个数为4,是偶数。In Example 2, the number of cabins in the underground tunnel is 4, which is an even number.

安装末尾后开挖舱室拱顶二衬结构(263)钢筋、竖向二衬结构钢筋(4121)、末尾后开挖舱室底板二衬结构(264)钢筋及二衬结构纵向钢筋和箍筋(413)。Install the rear excavation cabin dome secondary lining structure (263) steel bar, vertical secondary lining structural steel bar (4121), the end rear excavation cabin bottom secondary lining structure (264) steel bar and the secondary lining structure longitudinal steel bar and stirrup (413) ).

末尾后开挖舱室拱顶二衬结构(263)钢筋一侧与相邻先开挖舱室(1)拱顶二衬结构钢筋预埋钢板(1311)连接,另一侧与竖向二衬结构钢筋(4121)连接;末尾后开挖舱室底板二衬结构(264)钢筋一侧与相邻先开挖舱室(1)底板二衬结构钢筋预埋钢板(1411)连接,另一侧与竖向二衬结构钢筋(4121)连接。At the end of the excavation cabin dome secondary lining structure (263), one side of the steel bar is connected with the pre-embedded steel plate (1311) of the adjacent first excavated cabin (1) dome secondary lining structural steel bar, and the other side is connected with the vertical secondary lining structural steel bar (4121) Connection; at the end, the second lining structure of the cabin bottom excavated at the end (264) One side of the steel bar is connected with the pre-embedded steel plate (1411) of the second lining structure of the adjacent first excavation cabin (1), and the other side is connected with the vertical two Lining structural steel bar (4121) connection.

架设安装末尾后开挖舱室拱顶二衬结构(263)模板及竖向二衬结构(412)模板,浇筑末尾后开挖舱室拱顶二衬结构(263)混凝土及竖向二衬结构(412)混凝土;待末尾后开挖舱室拱顶二衬结构(263)混凝土及竖向二衬结构(412)混凝土达到设计要求后,拆除末尾后开挖舱室拱顶二衬结构(263)模板及竖向二衬结构(412)模板。After erection and installation, excavate the formwork of the secondary lining structure of the cabin dome (263) and the formwork of the vertical secondary lining structure (412), and excavate the secondary lining structure of the cabin dome after the pouring (263) Concrete and vertical secondary lining structure (412) ) concrete; after the final excavation of the secondary lining structure of the cabin dome (263) and the concrete of the vertical secondary lining structure (412) meet the design requirements, remove the formwork and vertical secondary lining structure (263) of the secondary lining structure of the dome excavated after the end of the excavation To the second liner structure (412) template.

然后,浇筑末尾后开挖舱室底板二衬结构(264)混凝土,并整平末尾后开挖舱室底板二衬结构(264)混凝土表面。Then, the concrete of the secondary lining structure ( 264 ) of the second lining structure of the cabin bottom excavated after the end is poured, and the concrete surface of the secondary lining structure ( 264 ) of the second lining structure of the second lining structure of the cabin floor after the final excavation is leveled.

末尾后开挖舱室拱顶二衬结构(263)钢筋与拱顶二衬结构钢筋预埋钢板(1311)的连接方式为焊接连接。The connection between the rebar of the second lining structure of the dome (263) and the pre-embedded steel plate (1311) of the second lining structure of the dome after the excavation at the end is by welding.

末尾后开挖舱室底板二衬结构(264)钢筋与底板二衬结构钢筋预埋钢板(1411)的连接方式为焊接连接。The connection between the steel bars of the second lining structure (264) of the cabin floor after the end excavation and the pre-embedded steel plates (1411) of the second lining structure of the floor is welded connection.

上述实施例1及实施例2中省略了本领域技术人员熟知的前期常规施工前准备、施工过程中必要的安全措施、质量要求、基本技术及操作规程等。The above-mentioned embodiment 1 and embodiment 2 omit the pre-conventional pre-construction preparations, necessary safety measures, quality requirements, basic technology and operation rules in the construction process that are well known to those skilled in the art.

以上仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (5)

1. A multi-cabin pipe gallery underground excavation construction method is characterized by comprising the following main construction steps:
step 1: processing a preliminary bracing structure (31) of the underground excavated pipe gallery and processing a secondary lining structural steel bar (411);
step 2: before the underground pipe gallery cabin is excavated, reinforcing an excavated soil body;
and step 3: firstly, excavating soil at the excavation cabin (1) and installing and constructing a primary supporting structure (31);
and 4, step 4: leveling the concrete surface of the vertical primary supporting structure (312) between the successively excavated cabins, which is close to the side of the rear excavated cabin (2);
and 5: paving and installing a pre-excavated cabin waterproof layer (15) and reserving a reserved lapping waterproof layer for lapping with an adjacent post-excavated cabin waterproof layer (25);
step 6: uniformly smearing a release agent on the concrete surface of the vertical primary support structure (312) between the successively excavated cabins, which is close to the rear excavated cabin (2);
and 7: firstly, excavating a cabin second lining structural steel bar (411) for installation and pouring concrete of a second lining structure (41);
and 8: excavating soil at the rear excavation cabin (2) and installing and constructing a primary supporting structure (31);
and step 9: dismantling a vertical primary supporting structure (312) between successively excavated cabins;
step 10: a cabin waterproof layer (25) is excavated after the installation;
step 11: and (3) installing second lining structural steel bars (411) of the rear excavation cabin and pouring concrete of the second lining structure (41).
2. The multi-cabin pipe gallery underground excavation construction method according to claim 1, wherein in the step 1:
arranging a pre-buried steel plate (111) of the arch crown primary support structure near an arch foot of the side of the rear excavation cabin (2) of the first excavation cabin arch crown primary support structure (11), and connecting the rear excavation cabin arch crown primary support structure (21) with the adjacent first excavation cabin arch crown primary support structure (11);
arranging a bottom plate primary supporting structure embedded steel plate (121) on the side, close to the rear excavation cabin (2), of the front excavation cabin bottom plate primary supporting structure (12), and connecting the rear excavation cabin bottom plate primary supporting structure (22) with the adjacent front excavation cabin bottom plate primary supporting structure (12);
arranging a vault secondary lining structural steel bar embedded steel plate (1311) near an arch foot of the side of the back excavation cabin (2) close to the vault secondary lining structural steel bar (131) of the vault of the first excavation cabin, and connecting the vault secondary lining structural steel bar (231) of the back excavation cabin with the adjacent vault secondary lining structural steel bar (131) of the first excavation cabin;
arranging a bottom plate secondary lining structural steel bar embedded steel plate (1411) at the side of the primary excavation cabin bottom plate secondary lining structural steel bar (141) close to the secondary excavation cabin (2), wherein the bottom plate secondary lining structural steel bar (241) is used for connecting the secondary excavation cabin bottom plate secondary lining structural steel bar (141) with the adjacent primary excavation cabin bottom plate secondary lining structural steel bar (141);
vertical primary supporting structures (312) among the successively excavated cabins need to be arranged independently, and later-stage dismantling is facilitated.
3. The multi-cabin pipe gallery underground excavation construction method according to claim 1, wherein in the step 5:
a vault reserved lapping waterproof layer (1511) for lapping with an adjacent back excavation cabin vault waterproof layer (251) is reserved on the side, close to the back excavation cabin (2), of the first excavation cabin vault waterproof layer (151);
a bottom plate reserved lapping waterproof layer (1521) for lapping with an adjacent rear excavation cabin bottom plate waterproof layer (252) is reserved on the side, close to the rear excavation cabin (2), of the first excavation cabin bottom plate waterproof layer (152);
waterproof layers which need to be dismantled in subsequent construction and are arranged at the vertical primary supporting structures (312) between the excavated cabins are not laid.
4. The method for multi-cabin pipe gallery underground excavation construction according to claim 1, wherein in the step 8:
the rear excavation cabin (2) is constructed by adopting an up-and-down step method;
when the secretly dig piping lane cabin number is the odd:
when the excavation depth of the upper step is 3.0-6.0 m, chiseling a concrete protective layer at the pre-buried steel plate (111) of the arch crown primary support structure of the pre-excavated cabin (1) adjacent to the post-excavated cabin (2), so that all the pre-buried steel plates (111) of the arch crown primary support structure are leaked out, and the surface of the pre-buried steel plates (111) of the arch crown primary support structure is clean and free of impurities;
then, connecting (111) the post-excavation cabin vault primary support structure (21) with the pre-buried steel plates of the vault support structures of the adjacent pre-excavation cabins (1), installing reinforcing steel meshes between the longitudinally adjacent post-excavation cabin vault primary support structures (21), and excavating the cabin vault primary support structure (21) concrete after spraying;
after the concrete construction of the post-excavation cabin vault primary support structure (21) is completed, performing lower bench excavation, chiseling a concrete protective layer at a position, adjacent to the post-excavation cabin (2), of a pre-embedded steel plate (121) of a bottom plate primary support structure of the pre-excavation cabin (1), so that the pre-embedded steel plate (121) of the bottom plate primary support structure is completely leaked out, and the surface of the pre-embedded steel plate (121) of the bottom plate primary support structure is ensured to be clean and free of impurities;
then, connecting the post-excavation cabin bottom plate primary supporting structures (22) with the embedded steel plates (121) of the bottom plate supporting structures of the adjacent pre-excavation cabins (1), installing reinforcing steel meshes between the longitudinally adjacent post-excavation cabin bottom plate primary supporting structures (22), and excavating the cabin bottom plate primary supporting structures (22) after spraying concrete;
when the secretly dig piping lane cabin number is the even number:
except the rear excavation cabins (26) at the end, constructing other rear excavation cabins (2) according to the construction method when the number of the underground excavation pipe gallery cabins is odd;
installing a final excavation cabin vault primary support structure (261) and a vertical primary support structure (313) in time according to the requirement of the designed primary support structure distance along with the final excavation cabin (26) excavation;
one side of the post-excavation cabin vault primary support structure (261) is connected with the embedded steel plate (111) of the vault primary support structure of the adjacent pre-excavation cabin (1), and the other side of the post-excavation cabin vault primary support structure is connected with the upper part of the vertical primary support structure (313); a vertical primary supporting structure (313) is temporarily reinforced by adopting a locking pin anchor rod; installing reinforcing mesh sheets between primary supporting structures (261) of the excavated cabin vault after the longitudinal adjacent tail and between primary vertical supporting structures (313), and spraying concrete of the primary supporting structures (261) of the excavated cabin vault after the tail and concrete of the primary vertical supporting structures (313);
after the tail excavation cabin vault primary support structure (261) and the vertical primary support structure (313) reach the design requirements, the cabin bottom plate primary support structure (262) is excavated after the installation tail, one side of the cabin bottom plate primary support structure (262) is connected with the embedded steel plate (121) of the primary support structure of the bottom plate of the adjacent first excavation cabin (1), the other side of the cabin bottom plate primary support structure is connected with the lower part of the vertical primary support structure (313), and reinforcing mesh sheets are installed between the longitudinally adjacent tail excavation cabin bottom plate primary support structures (262) and the cabin bottom plate primary support structure (262) is excavated after the spraying tail.
5. The method for multi-cabin pipe gallery underground excavation construction according to claim 1, wherein in the step 11:
when the secretly dig piping lane cabin number is the odd:
chiseling a concrete protective layer at a vault secondary-lining structure steel bar embedded steel plate (1311) of a vault of a first excavation cabin (1) adjacent to a later excavation cabin (2), so that the vault secondary-lining structure steel bar embedded steel plate (1311) is completely leaked out, and the surface of the vault secondary-lining structure steel bar embedded steel plate (1311) is ensured to be clean and free of impurities;
secondly, connecting the post-excavation cabin vault secondary lining structure steel bars (231) with the adjacent pre-embedded steel plates (1311) of the pre-excavation cabin (1) vault secondary lining structure steel bars, installing secondary lining structure longitudinal steel bars and stirrups (413), erecting a post-excavation cabin vault secondary lining structure (23) template, and excavating cabin vault secondary lining structure (23) concrete after pouring; after the concrete of the secondary lining structure (23) of the arch top of the excavated cabin reaches the design requirement, removing the template of the secondary lining structure (23) of the arch top of the excavated cabin;
chiseling a concrete protective layer at a position, adjacent to the rear excavation cabin (2), of a pre-excavation cabin (1) and a pre-buried steel plate (1411) of a second-lining structural steel bar of a bottom plate, so that the pre-buried steel plate (1411) of the second-lining structural steel bar of the bottom plate is completely leaked out, and the surface of the pre-buried steel plate (1411) of the second-lining structural steel bar of the bottom plate is clean and free of impurities;
secondly, connecting the post-excavation cabin bottom plate secondary lining structural steel bars (241) with the adjacent pre-embedded steel plates (1411) of the pre-excavation cabin (1) bottom plate secondary lining structural steel bars, installing the secondary lining structural longitudinal steel bars and the stirrups (413), excavating the cabin bottom plate secondary lining structure (24) concrete after pouring, and excavating the concrete surface of the cabin bottom plate secondary lining structure (24) after leveling;
when the secretly dig piping lane cabin number is the even number:
except the rear excavation cabins (26) at the end, constructing other rear excavation cabins (2) according to the construction method when the number of the underground excavation pipe gallery cabins is odd;
mounting reinforcing steel bars of a post-ending excavated cabin vault secondary lining structure (263), vertical secondary lining structural reinforcing steel bars (4121), post-ending excavated cabin base plate secondary lining structure (264) reinforcing steel bars, longitudinal reinforcing steel bars of the secondary lining structure and stirrups (413);
one side of a steel bar of a post-tail excavation cabin vault secondary lining structure (263) is connected with an adjacent pre-excavation cabin (1) vault secondary lining structure steel bar embedded steel plate (1311), and the other side of the steel bar is connected with a vertical secondary lining structure steel bar (4121); after the end, one side of the steel bar of the two-lining structure (264) of the bottom plate of the excavated cabin is connected with the embedded steel plate (1411) of the two-lining structure steel bar of the bottom plate of the adjacent excavated cabin (1) firstly, and the other side of the steel bar is connected with the two vertical-lining structure steel bar (4121).
CN202210679035.7A 2022-06-16 2022-06-16 Multi-cabin pipe gallery underground excavation construction method Pending CN114810098A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210679035.7A CN114810098A (en) 2022-06-16 2022-06-16 Multi-cabin pipe gallery underground excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210679035.7A CN114810098A (en) 2022-06-16 2022-06-16 Multi-cabin pipe gallery underground excavation construction method

Publications (1)

Publication Number Publication Date
CN114810098A true CN114810098A (en) 2022-07-29

Family

ID=82521131

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210679035.7A Pending CN114810098A (en) 2022-06-16 2022-06-16 Multi-cabin pipe gallery underground excavation construction method

Country Status (1)

Country Link
CN (1) CN114810098A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120175374A (en) * 2025-05-22 2025-06-20 长江勘测规划设计研究有限责任公司 Double-arch multi-hole tunnel with multi-compartment integrated pipeline corridor function and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060135592A (en) * 2006-12-12 2006-12-29 윤석렬 Intermediate wall of two arch tunnel
CN110005416A (en) * 2019-04-30 2019-07-12 北京万兴建筑集团有限公司 A kind of branch line piping lane tunnel interface section constructing method
CN110094212A (en) * 2019-04-28 2019-08-06 北京万兴建筑集团有限公司 A kind of structure more cabins pipe gallery tunnel arranged side by side and its construction method independently of each other
CN112647973A (en) * 2020-10-30 2021-04-13 北京市政路桥股份有限公司 Template for ensuring flatness of side face of partition wall soil body in primary support in pipe gallery underground excavation construction and using method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060135592A (en) * 2006-12-12 2006-12-29 윤석렬 Intermediate wall of two arch tunnel
CN110094212A (en) * 2019-04-28 2019-08-06 北京万兴建筑集团有限公司 A kind of structure more cabins pipe gallery tunnel arranged side by side and its construction method independently of each other
CN110005416A (en) * 2019-04-30 2019-07-12 北京万兴建筑集团有限公司 A kind of branch line piping lane tunnel interface section constructing method
CN112647973A (en) * 2020-10-30 2021-04-13 北京市政路桥股份有限公司 Template for ensuring flatness of side face of partition wall soil body in primary support in pipe gallery underground excavation construction and using method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王伟威: "大跨度城市地下综合管廊穿越城市主干路初支联立二衬独立法施工技术", 2021年全国土木工程施工技术交流会论文集(上册), 10 June 2021 (2021-06-10), pages 96 - 99 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120175374A (en) * 2025-05-22 2025-06-20 长江勘测规划设计研究有限责任公司 Double-arch multi-hole tunnel with multi-compartment integrated pipeline corridor function and construction method

Similar Documents

Publication Publication Date Title
CN110630283B (en) A three-layer support structure suitable for double-arch tunnel and construction method
CN108412501B (en) Under wear oil pipeline shallow depth loess tunnels construction method
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN205742213U (en) Foundation pit supporting construction
CN111365018B (en) A method of strengthening and reinforcing sleeve arch suitable for small tunnel clearance
CN204729099U (en) Rock quality layer tunneling three layers of subway station canopy structure
CN105781582A (en) Novel shallow-buried tunnel support structure applicable to urban sensitive areas and construction method of novel shallow-buried tunnel support structure applicable to urban sensitive areas
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN116816397A (en) A construction method for ultra-shallow burial and long-span underground excavation subway stations
CN112012762B (en) Construction method of double-layer secondary lining multi-arch tunnel structure
CN112012761B (en) Construction method of anti-disturbance double-arch tunnel structure
CN115875051A (en) A three-layer thin-walled straight middle wall structure and construction method of multi-arch tunnel
CN102777066B (en) Spiral-tunneling reverse construction method of bucket-shaped screw-type underground garage
CN111502691A (en) Anti-slip tunnel structure and construction method thereof
CN113898007B (en) Semi-inverse construction method for long-span corridor structure along street
CN114810098A (en) Multi-cabin pipe gallery underground excavation construction method
CN112610222B (en) Karst cave backfilling method and tunnel construction method
CN112012763B (en) Construction method of double-layer primary support multi-arch tunnel structure
CN118745738A (en) A steel joint support system for deep foundation pits to avoid pipelines and its construction method
CN215906845U (en) Large-span vestibule mounting structure in foundation pit
CN116464060A (en) A construction method for accelerating high-span area structures at high-span areas of basement floors
CN115341910A (en) A tunnel construction method with complex geological conditions under expressway and tunnel
CN111042214A (en) Anti-floating structure of shallow-soil-covered underground structure and construction method thereof
CN115478872B (en) M-CRD excavation supporting and excavating method for multi-arch tunnel
CN119435012B (en) A method for concealed excavation of a three-layer six-hole subway station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination