[go: up one dir, main page]

CN114718585A - A shield construction method suitable for passing through tidal lakes - Google Patents

A shield construction method suitable for passing through tidal lakes Download PDF

Info

Publication number
CN114718585A
CN114718585A CN202210484068.6A CN202210484068A CN114718585A CN 114718585 A CN114718585 A CN 114718585A CN 202210484068 A CN202210484068 A CN 202210484068A CN 114718585 A CN114718585 A CN 114718585A
Authority
CN
China
Prior art keywords
tidal
shield
lake
grouting
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210484068.6A
Other languages
Chinese (zh)
Inventor
第五亚东
曾宇昕
田成名
冯骥蒙
卢志军
章新生
施成林
张俊儒
赵晓明
王辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fifth Engineering Co Ltd of CTCE Group
Original Assignee
Southwest Jiaotong University
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fifth Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University, China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Fifth Engineering Co Ltd of CTCE Group filed Critical Southwest Jiaotong University
Priority to CN202210484068.6A priority Critical patent/CN114718585A/en
Publication of CN114718585A publication Critical patent/CN114718585A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • E21D9/002Injection methods characterised by the chemical composition used
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • General Chemical & Material Sciences (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a shield construction method suitable for passing through a tidal lake, which comprises the following steps: firstly, carrying out real-site survey on a site, determining the range of unfavorable geology in a tidal lake region, and marking stratums in the range as grouting stratums; cofferdams are arranged in the grouting stratum in different areas to reduce the water level of the tidal lake, and grouting pipes are inserted in the cofferdams and used for injecting grout to reinforce the unfavorable geology in the tidal lake area; after grouting is finished, starting the shield machine to carry out tunneling work, setting the cofferdams again in different areas in the tunneling process to reduce the influence of tide water level change on the tunneling process of the shield machine, simultaneously adjusting the pressure in a front cabin of the shield according to the tide rule, increasing the pressure of a soil cabin when the tide rises, and reducing the pressure of the soil cabin when the tide falls. The technical problem of potential safety hazards existing when the shield passes through the tidal lake in the sea-filling area in the prior art is solved.

Description

一种适用于下穿潮汐湖的盾构施工方法A shield construction method suitable for passing through tidal lakes

技术领域technical field

本发明涉及盾构隧道施工技术领域,特别涉及一种适用于下穿潮汐湖的盾构施工方法。The invention relates to the technical field of shield tunnel construction, in particular to a shield construction method suitable for passing through a tidal lake.

背景技术Background technique

随着我国经济的快速发展和城市化进程的加快,城市人口的增加给城市交通带来的压力日渐明显,交通拥塞、城市环境日益恶化已成为各大城市普遍存在和亟待解决的重要问题。城市地铁作为一种安全、快捷、高效、环保的交通形式,迅速成为许多大城市解决交通问题的首要选择。在城市地铁建设过程中,地铁隧道大部分采用盾构法施工;由于城市水文地质特性及线路规划的必要性,在城市地铁盾构施工过程中,不可避免的需要穿越江河湖海。With the rapid development of my country's economy and the acceleration of urbanization, the increase of urban population has brought increasing pressure on urban traffic. Traffic congestion and the deteriorating urban environment have become common and urgent problems in major cities. As a safe, fast, efficient and environmentally friendly form of transportation, urban subway has quickly become the first choice for many large cities to solve traffic problems. In the process of urban subway construction, most subway tunnels are constructed by the shield method; due to the urban hydrogeological characteristics and the necessity of line planning, in the process of urban subway shield construction, it is inevitable to cross rivers, lakes and seas.

盾构穿越填海地区潮汐湖时,地质较为复杂,水位受潮汐影响,土压平衡盾构掘进期间土仓压力设置不当极易造成湖底沉降或隆起,使湖水与土仓联通,造成掘进风险;区间上方覆土自稳性较差,且区间范围内存在孤石及基岩突起,地层软硬不均,盾构机掘进速度不稳定,掘进困难,极易造成螺旋机喷涌,土仓压力不稳定,掘进掌子面失稳,湖面沉降隆起;填海地区孤石及基岩突起极易对盾构机刀具刀盘造成磨损,导致盾构机掘进无进尺,被动于湖底开仓,增大施工风险,严重危及盾构作业施工。When the shield tunnel passes through the tidal lake in the reclamation area, the geology is complicated, the water level is affected by the tide, and the improper setting of the soil pressure in the earth pressure balance shield during the excavation of the shield can easily cause the lake bottom to subsidence or uplift, so that the lake water and the soil warehouse are connected, resulting in excavation risks; The self-stability of the overlying soil above the interval is poor, and there are boulders and bedrock protrusions within the interval, the stratum is unevenly soft and hard, the tunneling speed of the shield machine is unstable, and it is difficult to drive, which is very likely to cause the screw machine to spout and the pressure of the soil bin is unstable. , the tunnel face is unstable, and the lake surface subsides and uplifts; the boulders and bedrock protrusions in the reclamation area can easily cause wear to the shield cutter cutter head, resulting in no footage of the shield tunneling machine, passively opening warehouses at the bottom of the lake, and increasing construction. Risk, seriously endanger the shield construction.

因此,现在亟需一种适用于下穿潮汐湖的盾构施工技术,保证施工过程及盾构掘进过程中的安全。Therefore, there is an urgent need for a shield construction technology suitable for passing through the tidal lake, so as to ensure the safety of the construction process and the shield tunneling process.

发明内容SUMMARY OF THE INVENTION

基于此,本发明的目的是提供一种适用于下穿潮汐湖的盾构施工方法,以解决现有技术中,盾构穿越填海地区潮汐湖时,存在安全隐患的技术问题。Based on this, the purpose of the present invention is to provide a shield construction method suitable for passing through tidal lakes, so as to solve the technical problem of potential safety hazards when shields pass through tidal lakes in reclamation areas in the prior art.

本发明提供一种适用于下穿潮汐湖的盾构施工方法,所述方法包括:The invention provides a shield construction method suitable for passing through a tidal lake, the method comprising:

先对现场进行实地勘察,确定潮汐湖区域不良地质的范围,并将所述范围内的地层标记为注浆地层;First conduct on-the-spot investigation to determine the range of unfavorable geology in the tidal lake area, and mark the strata within the range as grouting strata;

对注浆地层分区域设置围堰以降低潮汐湖的水位,并在所述围堰内插设注浆管,所述注浆管用于注入浆液,以对潮汐湖区域内的不良地质进行加固;Cofferdams are arranged for the grouting strata in different areas to lower the water level of the tidal lake, and a grouting pipe is inserted in the cofferdam, and the grouting pipe is used for injecting slurry to reinforce the poor geology in the tidal lake area;

待注浆完毕后,启用盾构机进行掘进工作,在掘进过程中,分区域再次设置围堰减少潮汐水位变化对盾构机掘进过程中的影响,同时根据潮汐的规律,调节盾构前方仓内压力,涨潮时提高土仓压力,落潮时降低土仓压力。After the grouting is completed, the shield machine is activated to carry out the excavation work. During the excavation process, cofferdams are set again in different areas to reduce the influence of tidal water level changes on the excavation process of the shield machine. The internal pressure increases the soil bin pressure during high tide, and reduces the soil bin pressure during ebb tide.

进一步地,所述适用于下穿潮汐湖的盾构施工方法,其中,所述浆液包括水泥和水玻璃,所述水泥和水玻璃的比例为1:1。Further, in the shield construction method suitable for passing through a tidal lake, the slurry includes cement and water glass, and the ratio of the cement and water glass is 1:1.

进一步地,所述适用于下穿潮汐湖的盾构施工方法,其中,所述围堰内注浆管的数量不少于3个/m2Further, in the shield construction method suitable for passing through a tidal lake, the number of grouting pipes in the cofferdam is not less than 3/m 2 .

进一步地,所述适用于下穿潮汐湖的盾构施工方法,其中,所述注浆管采用PVC管材。Further, in the shield construction method suitable for passing through a tidal lake, wherein the grouting pipe is made of PVC pipe.

进一步地,所述适用于下穿潮汐湖的盾构施工方法,其中,所述盾构机为土压平衡盾构,且选用辐条面板式刀盘。Further, in the shield construction method suitable for passing through a tidal lake, the shield machine is an earth pressure balance shield, and a spoke-panel cutter head is selected.

进一步地,所述适用于下穿潮汐湖的盾构施工方法,其中,当所述盾构机掘进至潮汐湖50m外时,降低掘进速度,以提高土仓压力。Further, in the shield construction method suitable for passing through the tidal lake, when the shield machine is excavated to 50m outside the tidal lake, the excavation speed is reduced to increase the pressure of the soil bunker.

进一步地,所述适用于下穿潮汐湖的盾构施工方法,其中,当盾构机通过后,进行盾构管片的背后注浆工作,同时监测管片的内力变化和渗漏水情况,并进一步做好补浆工作。Further, according to the shield construction method suitable for passing through the tidal lake, after the shield machine passes through, the back grouting work of the shield segment is performed, and the internal force change and leakage of the segment are monitored at the same time. And further do a good job of replenishing pulp.

进一步地,所述适用于下穿潮汐湖的盾构施工方法,其中,所述注浆地层内围堰数量至少为3个。Further, in the shield construction method suitable for passing through a tidal lake, the number of cofferdams in the grouting formation is at least three.

综上所述,与现有的技术相比,本发明具有的有益效果在于:通过对潮汐湖区域不良地质进行加固,使得盾构可在含有孤石、基岩突起、中砂等复合地层的潮汐湖区域下穿施工,大大改善了作业环境,大幅度降低了盾构下穿潮汐湖掘进施工风险,有效防止了湖面异常,涌沙涌水等风险,具有自动化程度高、施工安全质量整体较高的施工优势;并且在掘进过程中分区域再次设置围堰减少潮汐水位变化对盾构机掘进过程中的影响,同时根据潮汐的规律,调节盾构前方仓内压力,避免湖底开仓的高风险工况,解决了现有技术中,盾构穿越填海地区潮汐湖时,存在安全隐患的技术问题。To sum up, compared with the prior art, the present invention has the beneficial effect that: by reinforcing the unfavorable geology in the tidal lake area, the shield can be used in complex formations containing boulders, bedrock protrusions, medium sand, etc. The construction under the tidal lake area greatly improves the working environment, greatly reduces the construction risk of shield tunneling through the tidal lake, and effectively prevents the risks of abnormal lake surface, sand gushing and water gushing. It has a high degree of automation and overall high construction safety quality. In the process of excavation, cofferdams are set up again in different areas to reduce the impact of tidal water level changes on the excavation process of the shield machine. At the same time, according to the law of tides, the pressure in the warehouse in front of the shield machine is adjusted to avoid the high risk of opening warehouses at the bottom of the lake. The working condition solves the technical problem of potential safety hazards in the prior art when the shield passes through the tidal lake in the reclamation area.

附图说明Description of drawings

图1为本发明中适用于下穿潮汐湖的盾构施工方法的流程图;Fig. 1 is the flow chart of the shield construction method that is suitable for going down through the tidal lake in the present invention;

图2为本发明中注浆示意图;Fig. 2 is the schematic diagram of grouting in the present invention;

图3为本发明中盾构机掘进示意图;Fig. 3 is the tunneling schematic diagram of shield machine in the present invention;

如下具体实施方式将结合上述附图进一步说明本发明。The following specific embodiments will further illustrate the present invention with reference to the above drawings.

具体实施方式Detailed ways

为了便于理解本发明,下面将参照相关附图对本发明进行更全面的描述。附图中给出了本发明的若干实施例。但是,本发明可以以许多不同的形式来实现,并不限于本文所描述的实施例。相反地,提供这些实施例的目的是使对本发明的公开内容更加透彻全面。In order to facilitate understanding of the present invention, the present invention will be described more fully hereinafter with reference to the related drawings. Several embodiments of the invention are presented in the accompanying drawings. However, the present invention may be embodied in many different forms and is not limited to the embodiments described herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete.

需要说明的是,当元件被称为“固设于”另一个元件,它可以直接在另一个元件上或者也可以存在居中的元件。当一个元件被认为是“连接”另一个元件,它可以是直接连接到另一个元件或者可能同时存在居中元件。本文所使用的术语“垂直的”、“水平的”、“左”、“右”以及类似的表述只是为了说明的目的。It should be noted that when an element is referred to as being "fixed to" another element, it can be directly on the other element or intervening elements may also be present. When an element is referred to as being "connected" to another element, it can be directly connected to the other element or intervening elements may also be present. The terms "vertical," "horizontal," "left," "right," and similar expressions are used herein for illustrative purposes only.

除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施例的目的,不是旨在于限制本发明。本文所使用的术语“及/或”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terms used herein in the description of the present invention are for the purpose of describing specific embodiments only, and are not intended to limit the present invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.

请参阅图1,本发明第一实施例中的适用于下穿潮汐湖的盾构施工方法的流程图,包括以下步骤:Please refer to FIG. 1 , a flowchart of a shield construction method suitable for passing through a tidal lake in the first embodiment of the present invention, including the following steps:

步骤S101,先对现场进行实地勘察,确定潮汐湖区域不良地质的范围,并将所述范围内的地层标记为注浆地层;Step S101, first conduct on-the-spot investigation to determine the range of unfavorable geology in the tidal lake area, and mark the strata within the range as grouting strata;

具体地,施工前先对现场进行勘察,查看现场水文地质情况,选择、准备好合适的材料;根据图纸进行测量放样,确定围堰位置如何划分。Specifically, before construction, the site shall be surveyed, the hydrogeological conditions of the site shall be checked, suitable materials shall be selected and prepared;

步骤S102,对注浆地层分区域设置围堰以降低潮汐湖的水位,并在所述围堰内插设注浆管,所述注浆管用于注入浆液,以对潮汐湖区域内的不良地质进行加固;Step S102, setting cofferdams on the grouting formation sub-regions to lower the water level of the tidal lake, and inserting grouting pipes in the cofferdams, the grouting pipes are used for injecting slurry, so as to carry out the treatment of poor geology in the tidal lake area. reinforcement;

具体地,所述注浆地层内围堰数量至少为3个,一般分为3个区域,可根据实际情况调整,注浆完毕后,拆除围堰,其中,注浆管采用PVC管材,所述浆液包括水泥和水玻璃,所述水泥和水玻璃的比例为1:1,所述围堰内注浆管的数量不少于3个/m2Specifically, the number of cofferdams in the grouting formation is at least 3, which are generally divided into 3 areas, which can be adjusted according to actual conditions. After grouting is completed, the cofferdams are removed. The slurry includes cement and water glass, the ratio of the cement and water glass is 1:1, and the number of grouting pipes in the cofferdam is not less than 3/m 2 .

步骤S103,待注浆完毕后,启用盾构机进行掘进工作,在掘进过程中,分区域再次设置围堰减少潮汐水位变化对盾构机掘进过程中的影响,同时根据潮汐的规律,调节盾构前方仓内压力,涨潮时提高土仓压力,落潮时降低土仓压力。In step S103, after the grouting is completed, the shield machine is activated to carry out the excavation work. During the excavation process, cofferdams are set up again in different areas to reduce the influence of tidal water level changes on the excavation process of the shield machine, and at the same time, the shield is adjusted according to the law of tides. The pressure in the front silo is increased, the pressure of the soil bunker is increased when the tide is high, and the pressure of the soil bunker is reduced when the tide is low.

请参阅图2至图3,所示为本申请中的注浆示意图和盾构掘进示意图,其中,1为湖面、2为湖底、3为围堰、4为注浆管、5为浆液、6为土体加固区、7为盾构机。Please refer to FIG. 2 to FIG. 3, which show the schematic diagram of grouting and the schematic diagram of shield tunneling in the application, wherein 1 is the lake surface, 2 is the lake bottom, 3 is the cofferdam, 4 is the grouting pipe, 5 is the slurry, and 6 is the grouting pipe. 7 is the soil reinforcement area, and 7 is the shield machine.

为便于理解,以某工程建设的规划设计为例,筼筜湖属咸水性人工湖泊,水域面积约1.5平方公里,湖水与海水连通,水位受潮汐影响,勘察期间水面标高约在±0m左右,水深一般在2~6m范围;区间主要地质为:杂填土平均为2.3m、淤泥平均为1.8m、粉质粘土平均为7.7m、砾沙平均为2.5m、残积砂质性黏土平均为3m、全风化花岗岩平均为2.5m。For ease of understanding, taking the planning and design of a project as an example, Yundang Lake is a saline artificial lake with a water area of about 1.5 square kilometers. The lake water is connected to the sea water, and the water level is affected by the tide. The water depth is generally in the range of 2-6m; the main geology in the interval is: the average of the mixed fill is 2.3m, the average of the silt is 1.8m, the average of the silty clay is 7.7m, the average of the gravel is 2.5m, and the average of the residual sandy clay is 3m. , The average of all weathered granite is 2.5m.

总体施工方案:先实地勘察,明确注浆地层的范围,做好施工准备;按照图1所示,分区域设置围堰,降低水位后,采用PVC注浆管,浆液采用1:1的水泥和水玻璃双液注浆,注浆孔数量为不少于3个/m2,注浆完毕后,拆除围堰;做好盾构掘进前的准备工作,开始进行盾构机掘进工作,当所述盾构机掘进至潮汐湖50m外时,降低掘进速度,以提高土仓压力,在掘进过程中,分区域再次设置围堰减少潮汐水位变化对盾构掘进过程中的影响,且要根据潮汐的规律,调节盾构前方仓内压力,具体为:涨潮时提升土仓压力0.1MPa,落潮时降低土仓压力0.1MPa;盾构通过后,及时进行盾构管片的背后注浆工作,及时监测管片的内力变化和渗漏水情况,并进一步做好补浆工作。Overall construction plan: first conduct on-the-spot investigation, clarify the scope of grouting stratum, and prepare for construction; as shown in Figure 1, set up cofferdams in different areas, and use PVC grouting pipes after lowering the water level, and use 1:1 cement and Water glass double-liquid grouting, the number of grouting holes is not less than 3/m2, after the grouting is completed, remove the cofferdam; do the preparations before the shield tunneling, and start the shield tunneling work. When the shield tunneling machine is 50m away from the tidal lake, the tunneling speed is reduced to increase the pressure of the soil bunker. During the tunneling process, cofferdams are set up again in different areas to reduce the impact of tidal water level changes on the shield tunneling process. Regularly, adjust the pressure in the warehouse in front of the shield, specifically: increase the pressure of the soil warehouse by 0.1MPa during high tide, and reduce the pressure of the soil warehouse by 0.1MPa when the tide is low; after the shield passes, the back grouting work of the shield segment should be carried out in time, and timely monitoring Changes in the internal force of the segment and the situation of water leakage, and further do a good job of replenishing the slurry.

关键施工技术:Key construction techniques:

1、地层加固施工1. Ground reinforcement construction

施工前先对现场进行勘察,查看现场水文地质情况,选择、准备好合适的材料;根据图纸进行测量放样,确定围堰位置如何划分,之后再分区域设置围堰,降低水位后,用PVC注浆管,浆液采用1:1的水泥和水玻璃双液注浆进行注浆,注浆完毕后,拆除围堰。Investigate the site before construction, check the hydrogeological conditions of the site, select and prepare suitable materials; measure and stake out according to the drawings, determine how to divide the cofferdam position, and then set up cofferdams in different areas. After lowering the water level, use PVC injection molding. For the grout pipe, the grout is grouted with 1:1 cement and water glass double-liquid grouting. After the grouting is completed, the cofferdam is removed.

(1)地层加固处理范围(1) Scope of stratum reinforcement treatment

①砂层区①Sand area

加固长度:区间左线为ZDK3+910~978,长68m;区间右线为YDK3+895~YDK4+989,长94m。Reinforcement length: the left line of the interval is ZDK3+910~978, and the length is 68m; the right line of the interval is YDK3+895~YDK4+989, and the length is 94m.

加固宽度:区间隧道洞身及两侧各3m。Reinforcement width: 3m on each side of the tunnel body and on both sides.

加固深度:盾构开仓加固区域10m范围都按隧道顶部以上1m至隧道底部以下1m。砂层加固深度为砂层以上1m,至砂层以下1m。Reinforcement depth: The 10m range of the shield opening reinforcement area is from 1m above the top of the tunnel to 1m below the bottom of the tunnel. The reinforcement depth of the sand layer is 1m above the sand layer and 1m below the sand layer.

②孤石区(主动开仓点)②Boulder area (active opening point)

加固长度:区间左线里程ZDK3+910~ZDK3+920;ZDK3+997~ZDK3+999;Reinforcement length: ZDK3+910~ZDK3+920 on the left line of the interval; ZDK3+997~ZDK3+999;

加固宽度:为隧道洞身以外3m。Reinforcement width: 3m outside the tunnel body.

加固深度:隧道顶以上1m至隧底部以下1m。Reinforcement depth: 1m above the top of the tunnel to 1m below the bottom of the tunnel.

(2)注浆孔的布置(2) Arrangement of grouting holes

①砂层区:隧道洞身范围钻孔间距为3m,梅花型布置;洞身两侧布设单排钻孔,孔位距隧道轮廓边2m,孔间距为1.5m。① Sand layer area: The spacing between the boreholes in the tunnel body is 3m, with a plum-shaped arrangement; a single row of boreholes are arranged on both sides of the tunnel body, the holes are 2m away from the tunnel outline, and the hole spacing is 1.5m.

②孤石、基岩区:加固区四周采用单排钻孔,间距为1.5m,中间加固区钻孔间距为3m。②Boulder and bedrock areas: A single row of drilling holes is used around the reinforcement area with a spacing of 1.5m, and the drilling spacing in the middle reinforcement area is 3m.

对于取芯效果较差和盾构保压过程湖内出现冒泡的加固区域进行预埋管补注双液浆。预埋注浆管区域注浆顺序,由小里程至大里程,先左线后右线,先两侧边线再内部,先封闭区再填充区。For the reinforcement area with poor coring effect and bubbling in the lake during the shield pressure keeping process, the pre-buried pipe shall be filled with double-liquid slurry. The grouting sequence of the pre-embedded grouting pipe area is from small mileage to large mileage, first the left line, then the right line, first the side lines on both sides, then the interior, and the closed area first and then the filling area.

(3)地层加固处理完毕后的检测方法(3) Detection method after stratum reinforcement treatment is completed

①采用钻孔抽芯法,做抗压试验,要求28d无侧限抗压强度≥0.2MPa;①Use the drilling core-pulling method to do the compressive test, and the 28d unconfined compressive strength is required to be ≥0.2MPa;

②采用随机原位标贯试验,标贯击数应不小于10击。② The random in-situ standard penetration test shall be adopted, and the number of standard penetration strikes shall not be less than 10.

③按1%孔数抽查,质量检查孔的压水检查工作应在单元工程灌浆结束7d后进行。③Sample inspection according to 1% of the number of holes, and the pressurized water inspection of the quality inspection holes should be carried out 7 days after the completion of grouting in the unit project.

根据设计要求,以上方法可选择其一。According to the design requirements, one of the above methods can be selected.

2、盾构掘进施工控制2. Shield tunneling construction control

2.1、盾构机针对性设计2.1. Targeted design of shield machine

(1)刀盘的基本结构(1) The basic structure of the cutter head

刀盘的基本结构为辐条面板式,刀盘采用四牛腿,四主梁+四副梁结构形式,可安装滚刀,刀座可实现滚刀与撕裂刀互换,为复合式刀盘。刀盘开挖直径Φ6480mm,开口率34%,开口分布均匀,利于渣土流动,不易产生泥饼,同时具备中、微风化花岗岩掘进和黏土、砂层地层掘进功能。The basic structure of the cutter head is the spoke-panel type, the cutter head adopts the structure of four corbels, four main beams + four sub-beams, which can be installed with a hob, and the cutter seat can realize the exchange of the hob and the tearing knife, which is a composite cutter head . The excavation diameter of the cutterhead is Φ6480mm, the opening rate is 34%, and the openings are evenly distributed, which is conducive to the flow of muck and is not easy to produce mud cakes.

刀盘通过上软下硬地层时偏载力大,要求刀盘具有足够的刚度强度。根据本工程详勘报告揭露中风化花岗岩、微风化花岗岩的最大强度为43.5-104Mpa,由于刀盘结构复杂,受力计算需采用有限元方法进行受力分析。通过优化设计,刀盘受力可满足应力在150MPa以下的地层使用,本型式的刀盘具有足够的刚度强度,在上软下硬段偏载较大的条件下,刀盘变形在弹性变形范围以内。本型式的刀盘刚度、强度能够满足本工程需要。When the cutter head passes through the upper and lower hard formations, the eccentric load force is large, and the cutter head is required to have sufficient rigidity and strength. According to the detailed investigation report of this project, it is revealed that the maximum strength of medium-weathered granite and lightly-weathered granite is 43.5-104Mpa. Due to the complex structure of the cutter head, the force calculation needs to use the finite element method for force analysis. Through the optimized design, the force of the cutter head can be used in formations with a stress below 150MPa. This type of cutter head has sufficient rigidity and strength. Under the condition of large eccentric load on the upper soft and lower hard sections, the cutter head deforms within the elastic deformation range. within. The rigidity and strength of this type of cutter head can meet the needs of this project.

(2)刀具配置(2) Tool configuration

根据地层特点,岩层强度最大为104MPa,撕裂刀不能切削高强度岩石,因此需要配置滚刀,由于岩层强度不均匀,最小12.7MPa,最大104MPa,选用耐冲击的17寸滚刀,刀盘配有6把中心双联滚刀,35把单刃滚刀,43把正面刮刀,16把边缘刮刀,1把仿形刀。中心双联滚刀刀间距为90mm,单刃滚刀刀间距为75mm。其中有4把边刀高于前盾直径,最外两道轨迹各有2把边滚刀,可减少边刀换刀次数。另外,通过转换座可以实现滚刀和撕裂刀的互换,用以适应不同的地层。According to the characteristics of the stratum, the maximum strength of the rock formation is 104MPa, and the tearing knife cannot cut high-strength rock, so a hob needs to be equipped. Due to the uneven strength of the rock formation, the minimum 12.7MPa, the maximum 104MPa, the impact-resistant 17-inch hob is selected, and the cutter head is equipped with There are 6 center duplex reels, 35 single edge reels, 43 front scrapers, 16 edge scrapers, and 1 profiler. The center double hob cutter spacing is 90mm, and the single edge hob cutter spacing is 75mm. Among them, 4 side knives are higher than the diameter of the front shield, and each of the two outermost tracks has 2 side hob, which can reduce the number of side knives to change. In addition, the exchange of the hob and the tearing knife can be realized through the conversion seat to adapt to different formations.

刀盘面板上用焊接复合钢板和堆焊网格;在外圈梁焊采用复合钢板全覆盖+合金保护刀,增加耐磨性。刀盘配置油压式磨损检测装置,保护刀盘本体不被磨损。Welded composite steel plate and surfacing grid are used on the cutter head panel; the outer ring beam welding is fully covered by composite steel plate + alloy protection knife to increase wear resistance. The cutter head is equipped with a hydraulic wear detection device to protect the cutter head body from being worn.

2.2、盾构机主要配置参数2.2. Main configuration parameters of shield machine

盾构机型号为CTE6450,整机总长约86m,主机总长9600mm,总重(主机+后配套)约500T;盾构机开挖直径φ6480mm,刀盘转速0~3.7rpm;最大推进速度约80mm/min;最大推力3991T,适用管片规格(外径/内径-宽度/分度)Φ6200/5500~1200/22.5°。水平转弯半径250m;纵向爬坡能力±50‰。The model of the shield machine is CTE6450, the total length of the whole machine is about 86m, the total length of the main machine is 9600mm, and the total weight (main machine + rear support) is about 500T; the excavation diameter of the shield machine is φ6480mm, the speed of the cutter head is 0~3.7rpm; the maximum propulsion speed is about 80mm /min; maximum thrust 3991T, applicable to segment specifications (outer diameter/inner diameter-width/division) Φ6200/5500~1200/22.5°. The horizontal turning radius is 250m; the longitudinal climbing ability is ±50‰.

盾构采用液压驱动;盾体采用被动铰接;螺旋输送机为螺旋轴形式,最大出渣能力420m3/h;管片安装机为中心回转式;采用VMT导向系统。The shield adopts hydraulic drive; the shield body adopts passive hinge; the screw conveyor is in the form of a screw shaft, and the maximum slag discharge capacity is 420m3/h; the segment installation machine is a central rotary type; the VMT guiding system is adopted.

2.3、盾构掘进施工工艺要点2.3. Key points of shield tunneling construction technology

区间隧道采用土压平衡盾构掘进,土压平衡是利用盾构机切削的泥土充满密封仓并保持适当的土压力来平衡开挖面的土体,从而达到对盾构机前方开挖面进行支护的目的。因此,盾构掘进过程中,需根据地质差异、覆土厚度、地面建筑环境情况并结合地表隆陷监测结果及时调整设定土仓压力,保持推进速度稳定,控制纠偏量,减少对土体的扰动,为管片拼装创造良好的条件。将施工轴线与设计轴线的偏差及地层变形控制在允许的范围内。The interval tunnel is excavated with earth pressure balance shield. The earth pressure balance is to use the soil cut by the shield machine to fill the sealing chamber and maintain proper earth pressure to balance the soil on the excavation surface, so as to achieve the excavation surface in front of the shield machine. purpose of support. Therefore, in the process of shield tunneling, it is necessary to adjust and set the soil pressure in time according to the geological difference, the thickness of the covering soil, the ground construction environment and the monitoring results of the surface uplift, to keep the advancing speed stable, control the amount of correction, and reduce the disturbance to the soil. , to create good conditions for segment assembly. Control the deviation between the construction axis and the design axis and the formation deformation within the allowable range.

2.4、参数控制2.4, parameter control

①通过实际施工总结,下穿筼筜湖区域段及砂性地层中掘进时刀盘转速控制在1.0-1.2r/min、刀盘扭矩保持在1800KN.M以内、减少土层扰动,以免顶破湖底土体。掘进速度控制在40-60mm/min、总推力控制在17000KN以内,确保盾构机匀速、安全、连续通过。穿越期间同步注浆每环5~6m3,砂层区域对脱出盾尾6~7环位置每隔十环做一道止水环,同步注浆压力控制在2.5~3bar,二次注浆压力0.5Mpa~0.8Mpa。① According to the actual construction summary, the cutter head speed should be controlled within 1.0-1.2r/min, the cutter head torque should be kept within 1800KN.M, and the soil disturbance should be reduced to avoid burst Lake bottom soil. The tunneling speed is controlled within 40-60mm/min, and the total thrust is controlled within 17000KN to ensure uniform, safe and continuous passage of the shield machine. During the crossing period, the synchronous grouting shall be carried out at 5-6m 3 per ring. In the sand layer area, a water stop ring shall be made every ten rings at the position of the 6-7 ring of the shield tail. The synchronous grouting pressure shall be controlled at 2.5-3 bar, and the secondary grouting pressure shall be 0.5 Mpa~0.8Mpa.

②孤石区域掘进,已经探明孤石区域有两处,基岩突起一处,穿越期间主要参数控制:刀盘转速1.2r/min,土压力1.1bar,掘进速度10~30mm/min,总推力17000KN,刀盘扭矩2500KN.M,同步注浆量5~6m3②The boulder area is excavated. It has been proved that there are two boulder areas, one of the bedrock protrusions. During the crossing, the main parameters are controlled: the cutter head speed is 1.2r/min, the earth pressure is 1.1bar, the excavation speed is 10~30mm/min, the total The thrust is 17000KN, the cutter head torque is 2500KN.M, and the synchronous grouting volume is 5~6m 3 .

2.5、风险控制措施2.5. Risk control measures

①在下穿筼筜湖区域段掘进时,为避免出现喷涌现象,采用螺旋机双闸门控制,减缓喷涌压力,向螺旋机及土仓加入高分子聚合物进行渣土改良,增加渣土粘稠度及流塑性,减小或避免喷涌严重。利用盾构机配套二次注浆设备,及时于脱出盾尾第十环进行二次注浆封环,防止管片壁后地下水串通,流入土仓。①In order to avoid the gushing phenomenon when excavating through the Yundang Lake area, the screw machine double gate control is used to slow down the gushing pressure, and high molecular polymer is added to the screw machine and soil bin to improve the slag and increase the viscosity of the slag. And flow plasticity, reduce or avoid serious gushing. The shield machine is used with the secondary grouting equipment, and the secondary grouting sealing ring is carried out in time when the tenth ring of the shield tail is removed to prevent the groundwater from collusion behind the segment wall and flowing into the soil bin.

②根据进湖、湖底、出湖埋深不同,严格控制每一环土仓压力,避免土压过高顶破湖底。②According to the different burial depths of entering the lake, bottom of the lake, and exiting the lake, strictly control the pressure of each ring of soil silo to prevent the soil pressure from being too high and breaking the lake bottom.

③砂层以及下穿筼筜湖掘进,必须快速,稳定安全通过,因此必须做好盾构机后配套(各台车、电瓶车、龙门吊等设备)及盾构机自身的保养检修工作,确保盾构机于易喷涌区域及下穿筼筜湖期间快速稳定掘进通过,最大限度避免异常停机。③The sand layer and tunneling through the Yundang Lake must be passed quickly, stably and safely. Therefore, it is necessary to do a good job in the maintenance and repair work of the shield machine after the support (each vehicle, battery car, gantry crane, etc.) and the shield machine itself to ensure the shield machine. The mechanism quickly and stably excavates and passes through the area prone to spewing and when it passes through the Yundang Lake, avoiding abnormal downtime to the greatest extent.

④严密监控螺旋机出土口的出土情况和土仓的压力变化情况,若出现喷涌现象首先关闭螺旋机上下闸门,隔断水源,避免地下水、流砂或所添加泥浆的大量喷出,保证掘进安全,再向螺旋机及土仓注入高分子聚合物充分搅拌进行改良后继续出土。④Strictly monitor the excavation situation of the screw excavator and the pressure change of the soil bin. If there is a spouting phenomenon, first close the upper and lower gates of the screw machine to cut off the water source to avoid a large amount of groundwater, quicksand or added mud. The high molecular polymer was injected into the screw machine and the soil bin, and the excavation was continued after thorough stirring and improvement.

⑤洞内准备好聚氨酯,螺旋输送机改良系统连接好聚氨酯注入管路,发生螺旋机喷涌时直接注入聚氨酯,控制喷涌;⑤ Prepare polyurethane in the hole, connect the polyurethane injection pipeline to the screw conveyor improvement system, and inject polyurethane directly when the screw machine spews to control the spout;

⑥湖面准备好船只,将应急沙袋、水面隔离带等应急物资提前放置在船上,穿越筼筜湖期间24h专人值班巡视,发生冒顶现象,及时将沙袋放置在冒顶区域,避免该区域扩大。⑥ Prepare the boat on the lake surface, and place emergency sandbags, water surface isolation belts and other emergency supplies on the boat in advance. During the crossing of Yundang Lake, special personnel will be on duty for 24-hour inspections. If roof caving occurs, place sandbags in the roof caving area in time to avoid the expansion of the area.

⑦盾构机穿越前对湖底的地勘孔逐一注浆封堵,避免掘进时出现冒顶现象,导致掌子面与湖底连通,仓内进入大量湖水出现螺旋机喷涌;⑦Before the shield machine passes through, the geological exploration holes at the bottom of the lake are grouted and blocked one by one, so as to avoid the phenomenon of roof falling during the excavation, which will lead to the connection between the tunnel face and the bottom of the lake, and a large amount of lake water in the warehouse will cause the spiral machine to spout;

⑧若正面地下水过于丰富,可增加对螺旋输送机内注入的膨润土,以利于螺旋输送机形成土塞效应,涌水较大时,可注入高分子聚合物防止喷涌;同时加强渣土外运管理,保证渣土及时外运,确保下穿筼筜湖期间连续推进。⑧If the groundwater on the front is too rich, the bentonite injected into the screw conveyor can be increased to facilitate the screw conveyor to form a soil plug effect. When the water influx is large, high molecular polymers can be injected to prevent gushing; Ensure that the muck is shipped out in time, and ensure continuous advancement during the passage through the Yundang Lake.

⑨严格控制同步注浆和二次补浆压力及方量,同步注浆压力控制在0.25~0.3Mpa,每隔十环做一道双液浆止水环,二次补浆压力控制在0.8Mpa以内,避免由于注浆压力过大击穿湖底,造成盾尾出现渗漏水现象;⑨Strictly control the pressure and volume of synchronous grouting and secondary grouting, control the synchronous grouting pressure within 0.25~0.3Mpa, make a double-liquid water stop ring every ten rings, and control the secondary grouting pressure within 0.8Mpa , to avoid water seepage at the shield tail due to excessive grouting pressure penetrating the lake bottom;

⑩穿越筼筜湖期间渣土改良及泡沫系统使用优质油脂及泡沫。⑩ The muck improvement and foam system use high-quality grease and foam during the crossing of Yundang Lake.

综上,本发明上述实施例当中的适用于下穿潮汐湖的盾构施工方法,通过对潮汐湖区域不良地质进行加固,使得盾构可在含有孤石、基岩突起、中砂等复合地层的潮汐湖区域下穿施工,大大改善了作业环境,大幅度降低了盾构下穿潮汐湖掘进施工风险,有效防止了湖面异常,涌沙涌水等风险,具有自动化程度高、施工安全质量整体较高的施工优势;并且在掘进过程中分区域再次设置围堰减少潮汐水位变化对盾构机掘进过程中的影响,同时根据潮汐的规律,调节盾构前方仓内压力,避免湖底开仓的高风险工况,解决了现有技术中,盾构穿越填海地区潮汐湖时,存在安全隐患的技术问题。To sum up, in the above-mentioned embodiments of the present invention, the shield construction method suitable for penetrating tidal lakes, by strengthening the unfavorable geology in the tidal lake area, enables the shield to be used in composite strata containing boulders, bedrock protrusions, medium sand, etc. The construction under the tidal lake area greatly improves the working environment, greatly reduces the construction risk of shield tunneling through the tidal lake, effectively prevents the risks of abnormal lake surface, sand and water gushing, and has a high degree of automation and overall construction safety quality. In addition, cofferdams are set up again in different areas during the excavation process to reduce the impact of tidal water level changes on the excavation process of the shield machine. At the same time, according to the law of tides, the pressure in the warehouse in front of the shield machine is adjusted to avoid the height of the warehouse opening at the bottom of the lake. The risk condition solves the technical problem of potential safety hazards in the prior art when the shield passes through the tidal lake in the reclamation area.

在本说明书的描述中,参考术语“一个实施例”、“一些实施例”、“示例”、“具体示例”、或“一些示例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不一定指的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任何的一个或多个实施例或示例中以合适的方式结合。In the description of this specification, description with reference to the terms "one embodiment," "some embodiments," "example," "specific example," or "some examples", etc., mean specific features described in connection with the embodiment or example , structure, material or feature is included in at least one embodiment or example of the present invention. In this specification, schematic representations of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.

以上所述实施例仅表达了本发明的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对本发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only represent several embodiments of the present invention, and the descriptions thereof are specific and detailed, but should not be construed as a limitation on the scope of the patent of the present invention. It should be pointed out that for those of ordinary skill in the art, without departing from the concept of the present invention, several modifications and improvements can also be made, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention should be subject to the appended claims.

Claims (8)

1. A shield construction method suitable for passing through a tidal lake, the method comprising:
firstly, carrying out real-site survey on a site, determining the range of unfavorable geology in a tidal lake region, and marking stratums in the range as grouting stratums;
cofferdams are arranged in the grouting stratum in different areas to reduce the water level of the tidal lake, and grouting pipes are inserted in the cofferdams and used for injecting grout to reinforce the unfavorable geology in the tidal lake area;
after grouting is finished, starting the shield machine to carry out tunneling work, setting cofferdams again in different areas to reduce the influence of tide water level change on the tunneling process of the shield machine in the tunneling process, simultaneously adjusting the pressure in a front cabin of the shield according to the tide rule, increasing the pressure of a soil cabin when the tide rises, and reducing the pressure of the soil cabin when the tide falls.
2. The shield construction method suitable for going through a tidal lake according to claim 1, wherein the slurry comprises cement and water glass in a ratio of 1: 1.
3. The shield construction method suitable for downward crossing tidal lakes according to claim 1, wherein the number of grouting pipes in the cofferdam is not less than 3/m2
4. The shield construction method suitable for downward crossing of tidal lakes of claim 1, wherein the grouting pipe is a PVC pipe.
5. The shield construction method suitable for downward crossing of tidal lakes according to claim 1, wherein the shield machine is an earth pressure balance shield and a spoke panel type cutter head is selected.
6. The shield construction method suitable for downward crossing of a tidal lake according to claim 5, wherein when the shield machine tunnels to outside of the tidal lake by 50m, the tunneling speed is reduced to increase the earth pressure.
7. The shield construction method suitable for downward-crossing tidal lakes as claimed in claim 5, wherein after the shield machine passes through, the back grouting work of the shield segment is performed, and the internal force change and the water leakage condition of the segment are monitored, and the grouting work is further performed.
8. The shield construction method suitable for downward traversing a tidal lake of claim 1, wherein the number of cofferdams in the grouting formation is at least 3.
CN202210484068.6A 2022-05-06 2022-05-06 A shield construction method suitable for passing through tidal lakes Pending CN114718585A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210484068.6A CN114718585A (en) 2022-05-06 2022-05-06 A shield construction method suitable for passing through tidal lakes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210484068.6A CN114718585A (en) 2022-05-06 2022-05-06 A shield construction method suitable for passing through tidal lakes

Publications (1)

Publication Number Publication Date
CN114718585A true CN114718585A (en) 2022-07-08

Family

ID=82232287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210484068.6A Pending CN114718585A (en) 2022-05-06 2022-05-06 A shield construction method suitable for passing through tidal lakes

Country Status (1)

Country Link
CN (1) CN114718585A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117763985A (en) * 2023-12-11 2024-03-26 山东大学 Dynamic water grouting simulation method and system under tidal action

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2523641A1 (en) * 1982-03-18 1983-09-23 Sogelerg Structures Method of seating underwater tunnel - uses concrete sections made in trench and pushed forward through water
JPH11181811A (en) * 1997-12-24 1999-07-06 Kajima Corp Underwater tunnel
CN105781556A (en) * 2016-03-21 2016-07-20 中铁四局集团第五工程有限公司 Construction method for shield to penetrate through shallow-covered urban landscape lake downwards
CN207267975U (en) * 2017-06-30 2018-04-24 中国建筑第六工程局有限公司 A kind of bed stabilization structure for being used under shield tunnel wear river
CN109458184A (en) * 2018-11-22 2019-03-12 重庆大学 Shallow Section shield construction method under lake
CN112664221A (en) * 2020-12-29 2021-04-16 中交第三航务工程局有限公司 Pipe jacking construction method for complex geological formation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2523641A1 (en) * 1982-03-18 1983-09-23 Sogelerg Structures Method of seating underwater tunnel - uses concrete sections made in trench and pushed forward through water
JPH11181811A (en) * 1997-12-24 1999-07-06 Kajima Corp Underwater tunnel
CN105781556A (en) * 2016-03-21 2016-07-20 中铁四局集团第五工程有限公司 Construction method for shield to penetrate through shallow-covered urban landscape lake downwards
CN207267975U (en) * 2017-06-30 2018-04-24 中国建筑第六工程局有限公司 A kind of bed stabilization structure for being used under shield tunnel wear river
CN109458184A (en) * 2018-11-22 2019-03-12 重庆大学 Shallow Section shield construction method under lake
CN112664221A (en) * 2020-12-29 2021-04-16 中交第三航务工程局有限公司 Pipe jacking construction method for complex geological formation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张程: "盾构下穿潮汐河控制技术研究", 铁道建筑技术, no. 9, 30 September 2021 (2021-09-30), pages 124 - 127 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117763985A (en) * 2023-12-11 2024-03-26 山东大学 Dynamic water grouting simulation method and system under tidal action

Similar Documents

Publication Publication Date Title
CN108049878B (en) A kind of powder land floor shield cuts the construction method that stake is crossed the river
CN105804758B (en) Across constructing metro tunnel method on the rectangular top pipe of the shallow small spacing of earthing big cross section
CN100580221C (en) Construction method of shield tunnel passing through shallow soil-covered river bed
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN106638669B (en) Existing subway station building enclosure hardened system and method are worn under a kind of shield
CN112855188B (en) Subway engineering soft soil stratum earth pressure balance shield construction method
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN105804761A (en) Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum
WO2021098444A1 (en) Technique for controlling tunneling parameters of shielded tunneling machine for rocky region at shielded tunneling launch point
CN109386293A (en) The sealed reception construction method of large section rectangular top pipe
CN109113092A (en) Construction method is protected in underground large-diameter pipeline original position water flowing
CN110130909A (en) A Construction Method of Shield Tunneling Under the Existing Station in Powder Soil Stratum
AU2021101945A4 (en) A Construction Control Method for Shield Tunneling Through Existing Operating Lines
CN110985016B (en) Quick receiving method of shield machine suitable for hard rock stratum in mine tunnel
CN206467684U (en) Existing subway station building enclosure hardened system is worn under a kind of shield
CN113818889B (en) Construction method for crossing underground shield tunnel through civil air defense roadway
CN114718585A (en) A shield construction method suitable for passing through tidal lakes
CN109707394B (en) A construction method for the tunnel door at the receiving end of the shield tunnel of the subway tunnel
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure
CN113374496B (en) Upper Crossing Tunnel Structure and Construction Method
CN111156008A (en) Shield construction and monitoring method for dangerous source river electric power tunnel
Chen et al. Cutting, Wear and replacement of cutting tools during shield tunneling
CN115681613A (en) Pipe jacking construction method for silt silty clay layer construction
CN114542092A (en) Construction Method of Shield Tunnel Receiving without Bottom Plate Structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination