CN112411894A - Improved structure and construction method for planting roof exhaust pipe - Google Patents

Improved structure and construction method for planting roof exhaust pipe Download PDF

Info

Publication number
CN112411894A
CN112411894A CN202011372163.4A CN202011372163A CN112411894A CN 112411894 A CN112411894 A CN 112411894A CN 202011372163 A CN202011372163 A CN 202011372163A CN 112411894 A CN112411894 A CN 112411894A
Authority
CN
China
Prior art keywords
exhaust pipe
pipe
waterproof
new
old
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011372163.4A
Other languages
Chinese (zh)
Other versions
CN112411894B (en
Inventor
崔喆林
李绪兵
李笑笑
刘琪琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoye Zhengzhou Construction Engineering Co ltd
Original Assignee
Baoye Zhengzhou Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoye Zhengzhou Construction Engineering Co ltd filed Critical Baoye Zhengzhou Construction Engineering Co ltd
Priority to CN202011372163.4A priority Critical patent/CN112411894B/en
Publication of CN112411894A publication Critical patent/CN112411894A/en
Application granted granted Critical
Publication of CN112411894B publication Critical patent/CN112411894B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D11/00Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
    • E04D11/02Build-up roofs, i.e. consisting of two or more layers bonded together in situ, at least one of the layers being of watertight composition
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/17Ventilation of roof coverings not otherwise provided for
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/254Roof garden systems; Roof coverings with high solar reflectance
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B80/00Architectural or constructional elements improving the thermal performance of buildings
    • Y02B80/32Roof garden systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Cultivation Of Plants (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The invention provides an exhaust pipe reconstruction structure for a planted roof and a construction method, wherein the reconstruction structure formed by the construction method comprises a roof concrete slab, a waterproof heat-insulating layer arranged above the roof concrete slab and an old exhaust pipe penetrating through the roof concrete slab and the waterproof heat-insulating layer, wherein a primary waterproof coiled material is wrapped on the periphery of the old exhaust pipe, a new exhaust pipe is sleeved on an extension section of the old exhaust pipe extending out of the waterproof heat-insulating layer, a newly-added waterproof coiled material is wrapped on the periphery of the new exhaust pipe, and the newly-added waterproof coiled material is attached to the primary waterproof coiled material below the new exhaust pipe; and a PVC pipe is arranged outside the new exhaust pipe, waterproof mortar is filled between the PVC pipe and the new exhaust pipe, planting soil is filled outside the PVC pipe, and the height of the waterproof mortar is higher than that of the top of the newly-added waterproof coiled material. The invention solves the problems that the time and labor are wasted in the process of dismounting and mounting the exhaust pipe structure again when the planted roof is transformed, and the leakage is easy to generate due to the insufficient protection of the exhaust pipe when the planted roof is used.

Description

Improved structure and construction method for planting roof exhaust pipe
Technical Field
The invention relates to the technical field of roof construction, in particular to a modified structure for planting a roof exhaust pipe and a construction method.
Background
Live in the roof or possess the owner of independent roofing and require to plant the roofing when reforming transform on the basis of former roofing, except that the conventional waterproof insulation layer of laying at the concrete roof surface, because the old blast pipe height of former roofing is lower, can bury old blast pipe mouth when the soil is laid in the later stage, this just need advance extension, fixed and waterproof etc. transformation to old blast pipe when reforming transform planting the roofing, avoid the laying of planting soil to exert an influence to building blast pipe.
Most of the traditional methods for modifying the planted roof are re-construction, the old exhaust pipe is dismantled and re-installed, labor and time are wasted, the construction cost is greatly increased, and the leakage hidden danger is easily caused by improper treatment of the waterproof coiled material joint of the re-installed exhaust pipe;
in addition, in the implementation process of the planted roof, if the exhaust pipe for the planted roof is not protected in place, the exhaust pipe of the roof is easy to damage, and the leakage and other consequences are caused, so that the exhaust pipe is difficult to strengthen and repair, the planted soil needs to be excavated, and the construction is inconvenient.
Disclosure of Invention
In order to solve the problems that the time and the labor are wasted when the exhaust pipe structure is dismantled again during the installation process and the leakage is easily caused when the exhaust pipe is not protected in place during the use of the planted roof in the prior art. The invention provides a modified structure for a planted roof exhaust pipe and a construction method.
An exhaust pipe transformation structure for a planted roof comprises a roof concrete slab, a waterproof heat-insulating layer arranged above the roof concrete slab and an old exhaust pipe penetrating through the roof concrete slab and the waterproof heat-insulating layer, wherein a raw waterproof coiled material wraps the periphery of the old exhaust pipe, a new exhaust pipe is sleeved on an extension section of the old exhaust pipe extending out of the waterproof heat-insulating layer, a newly-added waterproof coiled material wraps the periphery of the new exhaust pipe, and the newly-added waterproof coiled material is attached to the raw waterproof coiled material below the new exhaust pipe;
the novel exhaust pipe is externally provided with a PVC pipe, the bottom of the PVC pipe is in contact with the upper surface of the waterproof heat-insulating layer, waterproof mortar is filled between the PVC pipe and the novel exhaust pipe, planting soil is filled outside the PVC pipe, and the height of the waterproof mortar is higher than that of the top of the novel waterproof coiled material.
Further, the new exhaust pipe is sleeved with the old exhaust pipe at the position 1/2 of the extending section, and the sum of the radius of the old exhaust pipe and the thickness of the original waterproof roll is equal to the radius of the new exhaust pipe.
Further, the top of the new exhaust pipe is higher than the top of the PVC pipe, and a rain-shielding cap is arranged at the top of the new exhaust pipe.
Furthermore, the top of the newly-added waterproof roll is tightly bound with the new exhaust pipe through a galvanized iron wire.
Furthermore, an elastic sealant is coated at the joint of the top of the waterproof mortar and the new exhaust pipe.
Furthermore, a puncture-proof water storage layer is arranged between the planting soil and the waterproof heat-insulating layer, and the contact part of the puncture-proof water storage layer and the PVC pipe is in sealing connection.
A construction method for a transformation structure of a planted roof exhaust pipe comprises the following steps:
step 1, arranging the top of an old exhaust pipe into a vertical pipe orifice state, specifically comprising cutting off an elbow at the top of the old exhaust pipe or disassembling old rain shielding equipment;
step 2, sleeving the bottom end of the new exhaust pipe in the middle of the extending section of the old exhaust pipe and clamping and filling the raw waterproof coiled material between the old exhaust pipe and the new exhaust pipe;
step 3, wrapping the newly-added waterproof coiled material on the periphery of the new exhaust pipe, and tightly binding and fixing the top of the newly-added waterproof coiled material and the new exhaust pipe through a galvanized iron wire to prevent the newly-added waterproof coiled material from falling off;
step 4, vertically sleeving a PVC pipe on the periphery of the new exhaust pipe and sealing the bottom of the PVC pipe with the waterproof heat-insulating layer;
step 5, pouring waterproof mortar into the PVC pipe, coating an elastic sealant at a gap where the waterproof mortar is contacted with the new exhaust pipe after the waterproof mortar is solidified, and installing a rain-shielding cap at the top of the new exhaust pipe;
and 6, paving a puncture-proof water storage layer on the waterproof heat-insulating layer outside the PVC pipe, sealing the joint of the puncture-proof water storage layer and the PVC, and paving the planting soil on the puncture-proof water storage layer to complete transformation.
Compared with the prior art, the invention has the beneficial effects that:
the invention provides a modified structure and a construction method for planting a roof exhaust pipe, which are modified by sleeving a new exhaust pipe outside an old exhaust pipe, namely, old rain shielding equipment at the top of the old exhaust pipe is cut off or disassembled at the elbow part at the top of the old exhaust pipe, so that the top of the old exhaust pipe is vertical, a longer and thicker new exhaust pipe is sleeved outside the old exhaust pipe, and a raw waterproof coiled material is upwards connected with a newly-added waterproof coiled material outside the new exhaust pipe, so that the waterproofness of the modified exhaust pipe structure is enhanced;
secondly increase the protection of PVC pipe outside new blast pipe, both as the mould that waterproof mortar was pour, can reduce the destruction of long period plant roots to new blast pipe and old blast pipe basis again, fill waterproof mortar between PVC pipe and blast pipe, avoid the seepage hidden danger and play fixed effect to new blast pipe, make planting soil and heat preservation waterproof layer separate and make moisture not downward seepage and loss through the setting up of preventing the water storage layer of puncturing, the waterproof performance and the planting soil moisture retention ability of roofing structure have been guaranteed.
Drawings
Fig. 1 is a schematic diagram of the overall structure of the transformed structure of the exhaust pipe for the planted roof.
FIG. 2 is a schematic view of the top structure of the waterproof mortar for the modified structure of the planted roof exhaust pipe of the invention.
FIG. 3 is a schematic structural diagram I before the transformation of the transformed structure of the exhaust pipe for the planted roof.
FIG. 4 is a schematic structural diagram II of a modified structure of the exhaust pipe for the planted roof before modification.
The reference numeral is 1 for roofing concrete slab, 2 is waterproof heat preservation, 3 is old blast pipe, 4 is primary waterproofing membrane, 5 is new blast pipe, 6 is newly-increased waterproofing membrane, 7 is the PVC pipe, 8 is waterproof mortar, 9 is planting soil, 10 is the rain-proof cap, 11 is the elastic sealing agent, 12 is the reservoir stratum of preventing puncturing, 13 is the galvanized iron wire, 14 is the top elbow, 15 is old rain-proof equipment.
Detailed Description
The invention will be further explained with reference to the following figures and specific examples:
example one
As shown in fig. 1-2, an exhaust pipe reconstruction structure for a planted roof comprises a roof concrete slab 1, a waterproof insulation layer 2 arranged above the roof concrete slab 1, and an old exhaust pipe 3 penetrating through the roof concrete slab 1 and the waterproof insulation layer 2, wherein a primary waterproof roll material 4 is wrapped on the periphery of the old exhaust pipe 3, a new exhaust pipe 5 is sleeved on an extension section 301 of the old exhaust pipe 3 extending out of the waterproof insulation layer 2, a new waterproof roll material 6 is wrapped on the periphery of the new exhaust pipe 5, and the new waterproof roll material 6 is attached to the primary waterproof roll material 4 below the new exhaust pipe 5;
the novel exhaust pipe 5 is externally provided with a PVC pipe 7, the bottom of the PVC pipe 7 is in surface contact with the upper surface of the waterproof heat-insulating layer 2, waterproof mortar 8 is filled between the PVC pipe 7 and the novel exhaust pipe 5, planting soil 9 is filled outside the PVC pipe 7, and the height of the waterproof mortar 8 is higher than that of the top of the newly-added waterproof coiled material 6.
Through new blast pipe 5's setting, make old blast pipe 3 obtain the extension in length, the roofing of planting soil 9 can realize normal exhaust function when the packing, new waterproof coiled material 6's setting and new waterproof coiled material 6 and native waterproofing membrane 4's laminating are connected and are made new blast pipe 5 and the old blast pipe 3 condition of not producing the seepage after the registration, waterproof mortar 8's packing between PVC pipe 7 and new blast pipe 5, both play the fixed action to the connection of new blast pipe 5 and old blast pipe 3, prevent again that plant root system or moisture in the planting soil 9 from to the erosion of new blast pipe 5 and old blast pipe 3, good guard action has been played, make the blast pipe stable in structure of the planting roofing of reforming transform reliable.
The arrangement that the waterproof mortar 8 does not have the newly-added waterproof coiled material 6 enables the waterproof mortar 8 to form a certain degree of protection for the contact part of the newly-added waterproof coiled material 6 and the new exhaust pipe 5, and rainwater and the like are prevented from permeating from the upper part of the newly-added waterproof coiled material 6.
Specifically, the new exhaust pipe 5 is sleeved with the old exhaust pipe 3 at the position 1/2 of the protruding section 301, and the sum of the radius of the old exhaust pipe 3 and the thickness of the primary waterproof roll 4 is equal to the radius of the new exhaust pipe 5.
It can be understood that, the new exhaust pipe 5 and the protruding section 301 should ensure sufficient joint, and the length of the new exhaust pipe 5 should be shortened as much as possible to achieve the purpose of saving material, so that the new exhaust pipe 5 is sleeved at the position 1/2 of the protruding section 301 to save material and be reliably connected, when the new exhaust pipe 5 is sleeved with the old exhaust pipe 3, because the middle clamp is provided with the primary waterproof roll 4, for reliable sleeving, the radius of the new exhaust pipe 5 is required to be larger than the radius of the old exhaust pipe 3, and the difference value is the thickness of the primary waterproof roll 4.
As an embodiment, the top of the new exhaust pipe 5 is higher than the top of the PVC pipe 7 and the new exhaust pipe 5 is provided with a rain-shielding cap 10 at the top. The rain-proof cap 10 protects the pipe opening of the new exhaust pipe 5, and prevents rainwater or impurities from entering the room through the pipe opening of the new exhaust pipe 5.
As an implementation mode, the top of the newly added waterproof roll 6 is tightly bound with the new exhaust pipe 5 through galvanized iron wires 13. Through the tightening operation of the galvanized iron wires 13, the situation that the newly added waterproof coiled material 6 drops in the pouring process of the waterproof mortar 8 is avoided.
As an implementation mode, the joint between the top of the waterproof mortar 8 and the new exhaust pipe 5 is coated with an elastic sealant 11. The elastic sealant 11 seals the gap at the joint of the waterproof mortar 8 and the new exhaust pipe 5, and further ensures the waterproof performance.
As an implementation mode, a puncture-proof water storage layer 12 is arranged between the planting soil 9 and the waterproof heat-insulating layer 2, and the puncture-proof water storage layer 12 is hermetically connected with the contact part of the PVC pipe 7. It can be understood that the puncture-proof water storage layer 12 separates the planting soil 9 from the waterproof heat-insulating layer 2, and the waterproof performance of the roof structure and the water 9 retention capacity of the planting soil are ensured.
Example two
A construction method for a transformation structure of a planted roof exhaust pipe comprises the following steps:
step 1, the top of an old exhaust pipe 3 is arranged to be in a vertical pipe orifice state, and specifically the method comprises the steps of cutting off a top elbow 14 of an old exhaust pipe 5 or disassembling an old rain shielding device 15;
step 2, sleeving the bottom end of the new exhaust pipe 5 in the middle of the extending section 301 of the old exhaust pipe 3, and clamping and filling the primary waterproof coiled material 4 between the old exhaust pipe 3 and the new exhaust pipe 5;
step 3, wrapping the newly-added waterproof coiled material 6 at the periphery of the new exhaust pipe 5, and tightly binding and fixing the top of the newly-added waterproof coiled material 6 and the new exhaust pipe 5 through a galvanized iron wire 13 to prevent the newly-added waterproof coiled material 6 from falling off;
step 4, vertically sleeving a PVC pipe 7 on the periphery of the new exhaust pipe 5, and sealing the bottom of the PVC pipe 7 with the waterproof heat-insulating layer 2;
step 5, pouring waterproof mortar 8 into the PVC pipe 7, coating an elastic sealant 11 at a gap where the waterproof mortar 8 is contacted with the new exhaust pipe after the waterproof mortar 8 is solidified, and installing a rain-shielding cap 10 at the top of the new exhaust pipe 5;
and 6, paving a puncture-proof water storage layer 12 on the waterproof heat-insulating layer 2 outside the PVC pipe 7, sealing the joint of the puncture-proof water storage layer 12 and the PVC, and paving the planting soil 9 on the puncture-proof water storage layer 12 to complete the transformation.
As shown in fig. 3 and 4, which are schematic structural diagrams of an old exhaust pipe before modification, the construction method wholly adopts a mode that a new exhaust pipe 5 is sleeved outside an old exhaust pipe 3 to modify, when the construction is carried out, an old rain shielding device 15 at the top of the old exhaust pipe 3 is cut off or disassembled at the top elbow 14 part of the old exhaust pipe 3, so that the top of the old exhaust pipe 3 is vertical, a longer and thicker new exhaust pipe 5 is sleeved outside the old exhaust pipe 3, and a raw waterproof coiled material 4 is upwards connected with a newly-added waterproof coiled material 6 outside the new exhaust pipe 5, so that the waterproofness of the modified exhaust pipe structure is enhanced;
secondly increase the protection of PVC pipe 7 outside new blast pipe 5, both as the mould that waterproof mortar 8 was pour, can reduce the destruction of long period plant roots to new blast pipe 5 and old blast pipe 3 basis again, waterproof mortar 8 pour avoid the seepage hidden danger and play fixed effect to new blast pipe 5, make planting soil 9 separate with heat preservation waterproof layer 2 and make moisture not downward seepage and loss through the setting up of preventing puncturing water storage layer 12, the waterproof performance and the planting soil moisture retention ability of roofing structure have been guaranteed.
The modified structure formed by the construction method is the modified structure of the exhaust pipe described in the first embodiment, and is not described again here.
The above-described embodiments are merely preferred embodiments of the present invention, and not intended to limit the scope of the invention, so that equivalent changes or modifications in the structure, features and principles described in the present invention should be included in the claims of the present invention.

Claims (7)

1. The utility model provides an exhaust pipe transformation structure for planting roofing, includes roofing concrete slab (1), sets up waterproof insulation layer (2) and pass roofing concrete slab (1) and waterproof insulation layer (2) old blast pipe (3) above roofing concrete slab (1), its characterized in that, native waterproofing membrane (4) have been wrapped up in old blast pipe (3) periphery, and new blast pipe (5) have been registrated on the section (301) that stretches out of waterproof insulation layer (2) of old blast pipe (3), new waterproofing membrane (6) have been wrapped up in new blast pipe (5) periphery, newly-increased waterproofing membrane (6) and native waterproofing membrane (4) laminating under new blast pipe (5);
new blast pipe (5) are provided with PVC pipe (7) and PVC pipe (7) bottom and waterproof heat preservation (2) upper surface contact outward, it has waterproof mortar (8) and PVC pipe (7) outside packing to fill between PVC pipe (7) and new blast pipe (5) has planting soil (9), the top of newly-increased waterproofing membrane (6) is highly submerged in waterproof mortar (8).
2. The exhaust pipe reforming structure for the planted roof as claimed in claim 1, wherein the new exhaust pipe (5) is sleeved with the old exhaust pipe (3) at 1/2 of the protruding section (301), and the sum of the radius of the old exhaust pipe (3) and the thickness of the primary waterproof roll (4) is equal to the radius of the new exhaust pipe (5).
3. The exhaust pipe reforming structure for the planted roof as claimed in claim 1, wherein the top of the new exhaust pipe (5) is higher than the top of the PVC pipe (7) and a rain-shielding cap (10) is arranged on the top of the new exhaust pipe (5).
4. The exhaust pipe reconstruction structure for the planted roof is characterized in that the top of the newly added waterproof roll (6) is tightly bound with the new exhaust pipe (5) through galvanized iron wires (13).
5. The exhaust pipe reforming structure for the planted roof as claimed in claim 1, wherein an elastic sealant (11) is coated at the joint of the top of the waterproof mortar (8) and the new exhaust pipe (5).
6. The improved structure for the planted roof exhaust pipe according to claim 1, wherein a puncture-proof water storage layer (12) is arranged between the planting soil (9) and the waterproof heat-insulating layer (2), and the puncture-proof water storage layer (12) is hermetically connected with a contact part of the PVC pipe (7).
7. A construction method for a transformation structure of a planted roof exhaust pipe is characterized by comprising the following steps:
step 1, the top of an old exhaust pipe (3) is arranged to be in a vertical pipe orifice state, and specifically the method comprises the steps of cutting off a top elbow (14) of the old exhaust pipe (5) or disassembling old rain shielding equipment (15);
step 2, sleeving the bottom end of the new exhaust pipe (5) in the middle of the extending section (301) of the old exhaust pipe (3) and clamping and filling the primary waterproof coiled material (4) between the old exhaust pipe (3) and the new exhaust pipe (5);
step 3, wrapping a newly-added waterproof coiled material (6) at the periphery of the new exhaust pipe (5), and tightly binding the top of the newly-added waterproof coiled material (6) with the new exhaust pipe (5) through a galvanized iron wire (13) to prevent the newly-added waterproof coiled material (6) from falling off;
step 4, vertically sleeving a PVC pipe (7) on the periphery of the new exhaust pipe (5) and sealing the bottom of the PVC pipe (7) with the waterproof heat-insulating layer (2);
step 5, pouring waterproof mortar (8) into the PVC pipe (7), after the waterproof mortar (8) is solidified, coating an elastic sealant (11) at a gap where the waterproof mortar (8) is contacted with the new exhaust pipe, and installing a rain-shielding cap (10) at the top of the new exhaust pipe (5);
and 6, paving a puncture-preventing water storage layer (12) on the waterproof heat-insulating layer (2) outside the PVC pipe (7), sealing the joint of the puncture-preventing water storage layer (12) and the PVC, and paving the planting soil (9) on the puncture-preventing water storage layer (12) to complete transformation.
CN202011372163.4A 2020-11-30 2020-11-30 Transformation structure for planting roof exhaust pipe and construction method Active CN112411894B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011372163.4A CN112411894B (en) 2020-11-30 2020-11-30 Transformation structure for planting roof exhaust pipe and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011372163.4A CN112411894B (en) 2020-11-30 2020-11-30 Transformation structure for planting roof exhaust pipe and construction method

Publications (2)

Publication Number Publication Date
CN112411894A true CN112411894A (en) 2021-02-26
CN112411894B CN112411894B (en) 2024-09-06

Family

ID=74828840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011372163.4A Active CN112411894B (en) 2020-11-30 2020-11-30 Transformation structure for planting roof exhaust pipe and construction method

Country Status (1)

Country Link
CN (1) CN112411894B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2032986A (en) * 1978-08-18 1980-05-14 Bolton & Hayes Ltd A method of roofing
CN101831994A (en) * 2010-04-30 2010-09-15 唐山德生防水材料有限公司 Double-layer waterproof and double-layer water exhaust structure of heat insulation house surface and construction method thereof
US9228689B1 (en) * 2013-09-13 2016-01-05 Roger Cline System and method for in-place vent pipe restoration
CN106996165A (en) * 2017-05-10 2017-08-01 中建局集团建设发展有限公司 Planted roof waterproof heat-preservation exhaust system and construction method with exhaust apparatus
CN206784763U (en) * 2017-03-26 2017-12-22 中国建筑第六工程局有限公司 A kind of device for roof vent pipe detailed treatment
CN108797904A (en) * 2017-05-05 2018-11-13 五冶集团上海有限公司 A kind of accessible roof secretly buries discharge duct construction method
CN214658301U (en) * 2020-11-30 2021-11-09 宝冶(郑州)建筑工程有限公司 A reform transform structure for planting roofing blast pipe

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2032986A (en) * 1978-08-18 1980-05-14 Bolton & Hayes Ltd A method of roofing
CN101831994A (en) * 2010-04-30 2010-09-15 唐山德生防水材料有限公司 Double-layer waterproof and double-layer water exhaust structure of heat insulation house surface and construction method thereof
US9228689B1 (en) * 2013-09-13 2016-01-05 Roger Cline System and method for in-place vent pipe restoration
CN206784763U (en) * 2017-03-26 2017-12-22 中国建筑第六工程局有限公司 A kind of device for roof vent pipe detailed treatment
CN108797904A (en) * 2017-05-05 2018-11-13 五冶集团上海有限公司 A kind of accessible roof secretly buries discharge duct construction method
CN106996165A (en) * 2017-05-10 2017-08-01 中建局集团建设发展有限公司 Planted roof waterproof heat-preservation exhaust system and construction method with exhaust apparatus
CN214658301U (en) * 2020-11-30 2021-11-09 宝冶(郑州)建筑工程有限公司 A reform transform structure for planting roofing blast pipe

Also Published As

Publication number Publication date
CN112411894B (en) 2024-09-06

Similar Documents

Publication Publication Date Title
CN106149764B (en) A kind of precast assembly pipe gallery bell and spigot waterproof construction
CN206917119U (en) One kind goes out roof pipeline waterproof construction
CN214658301U (en) A reform transform structure for planting roofing blast pipe
CN206319642U (en) Plus the binding structure of build-up layers wall
CN112411894A (en) Improved structure and construction method for planting roof exhaust pipe
CN206971581U (en) A kind of water-proofing treatment system of joint of plate perforating pipe position
CN106381853A (en) Combined type irrigation and drainage channel and construction method thereof
CN215669707U (en) Basement outer wall expansion joint waterproof construction
CN112281860B (en) Inner lining wall structure and construction method thereof
CN208396162U (en) A kind of thermal isolation by water storage roofing
CN214941725U (en) Passive house roof rainwater collecting port part heat-insulated bridge node structure
CN217128772U (en) Inverted roof drainage structure
CN206784448U (en) A kind of filleting antipriming pipe for tunnel structure
CN215483689U (en) Roof deformation joint structure
CN105756293B (en) A kind of Green Roof structure and its construction method
CN205476117U (en) Structure that passive form building parapet bears down on one
CN212388765U (en) Water stop deformation joint structure
CN209082847U (en) A kind of newly-built equipment base water-tight device of roofing
CN114351947B (en) Concealed heat-insulating roof steam exhaust system and construction method thereof
CN215367861U (en) Building node waterproof construction
CN216893170U (en) U-shaped waterproof structure with inverted deformation joint of planted roof
CN206015921U (en) Drain pipe waterproof construction
CN217500838U (en) Sloping tile roofing pipe shaft structure
CN222207354U (en) A roof waterproofing and leak-proofing structure
CN218346585U (en) Novel planting roofing movement joint node

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant