[go: up one dir, main page]

CN110601090A - Pre-laying anchor cable auxiliary ship-moving method and system composition of long-distance sandbar section - Google Patents

Pre-laying anchor cable auxiliary ship-moving method and system composition of long-distance sandbar section Download PDF

Info

Publication number
CN110601090A
CN110601090A CN201910885948.2A CN201910885948A CN110601090A CN 110601090 A CN110601090 A CN 110601090A CN 201910885948 A CN201910885948 A CN 201910885948A CN 110601090 A CN110601090 A CN 110601090A
Authority
CN
China
Prior art keywords
cable
anchor
ship
laid
laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910885948.2A
Other languages
Chinese (zh)
Inventor
柴宝亮
董立军
潘洪海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Hai Xing Energy Technology Co Ltd
Original Assignee
Beijing Hai Xing Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Hai Xing Energy Technology Co Ltd filed Critical Beijing Hai Xing Energy Technology Co Ltd
Priority to CN201910885948.2A priority Critical patent/CN110601090A/en
Publication of CN110601090A publication Critical patent/CN110601090A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/10Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle in or under water

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

本发明涉及海底电缆铺设技术领域,公开了一种长距离沙洲段的预铺锚缆辅助行船方法及系统组成。其特征在于:在跨越沙洲区域预先布设两条预铺锚缆;在涨潮至水深条件满足行船要求时,启动绞磨机绞缆,铺缆船持续沿着电缆设计路由行船,同时边铺边埋电缆。预铺锚缆布设不占用主作业时间;当铺缆船穿越沙洲区域时,依靠绞磨机绞预铺锚缆提供前进动力。因此在一个高潮期间水深满足行船要求的条件下,可以不间断行船,达到最大限度的提高铺缆效率的目的;从而确保一次大潮汛铺缆船能够穿越沙洲段完成电缆铺设施工。

The invention relates to the technical field of submarine cable laying, and discloses a pre-laid anchor cable auxiliary navigation method and system composition for a long-distance sandbar section. It is characterized in that: two pre-laid anchor cables are pre-laid across the sandbar area; when the tide rises to the water depth and meets the sailing requirements, the winch mill is started to twist the cables, and the cable-laying ship continues to sail along the cable design route, while laying and burying. cable. The laying of pre-laid anchor cables does not take up the main operation time; when the cable-laying ship passes through the sandbar area, it relies on the winch mill to twist the pre-laid anchor cables to provide forward power. Therefore, under the condition that the water depth meets the requirements of sailing during a high tide, the ship can be sailed uninterruptedly to achieve the purpose of maximizing the efficiency of cable laying; thus ensuring that the cable laying ship can pass through the sandbar section to complete the cable laying construction during a large tide.

Description

一种长距离沙洲段的预铺锚缆辅助行船方法及系统组成A pre-laid anchor cable assisted sailing method and system composition for a long-distance sandbar section

技术领域technical field

本发明涉及海底电缆铺设技术领域,尤其是一种长距离沙洲段的预铺锚缆辅助行船方法及系统组成。The invention relates to the technical field of submarine cable laying, in particular to a pre-laid anchor cable auxiliary navigation method and system composition for a long-distance sandbar section.

背景技术Background technique

海底电缆是连通海上设施和陆地设施之间的重要电力传输和信号传输设施。随着海底电缆的直径增大,长距离海底电缆海上铺设施工的难度越来越大。因此需要根据海缆铺设施工环境条件,尤其是水深条件,因地制宜的选用适当的施工方法。Submarine cables are important power transmission and signal transmission facilities connecting offshore facilities and land facilities. As the diameter of submarine cables increases, the difficulty of laying long-distance submarine cables at sea becomes more and more difficult. Therefore, it is necessary to select appropriate construction methods according to local conditions according to the environmental conditions of submarine cable laying construction, especially the water depth conditions.

对于以高潮时有水、低潮时露滩为特征的长距离沙洲段,有两种备选的海缆铺设施工方法:第一种是利用高潮时段使用如锚艇之类的小船帮拖铺缆船行船,同时边铺边埋电缆;第二种是同时递交的专利申请《一种长距离沙洲段海缆铺设的铺缆船甲板布置及施工方法》所述的利用低潮露滩时起抛锚,利用高潮有水时绞缆行船,同时边铺边埋电缆。For long-distance sandbar sections characterized by water at high tide and exposed beaches at low tide, there are two alternative construction methods for submarine cable laying: the first is to use small boats such as anchor boats to tow and lay the cable during high tide periods The ship sails while laying and burying the cable; the second is to use the low-tide open beach to lift and drop anchor as described in the patent application "A Cable-laying Vessel Deck Layout and Construction Method for Laying Long-distance Sandbar Section Submarine Cables" submitted at the same time. Utilize the twisted cable to sail when there is water at high tide, and simultaneously lay and bury the cable.

对于第一种方法,由于如锚艇之类的小船同时提供铺缆船前进动力和控向动力,受沙洲区域水深条件所限,满足行船条件的小船吃水小、提供的动力有限,因此小船在海况较差的情况下动力明显不足,导致帮拖铺缆船时行船速度慢、铺缆效率较低。尤其是铺缆船在横风、横浪时,实际铺缆路由偏离电缆设计路由的可能性较大。For the first method, because small boats such as anchor boats provide both forward power and steering power for the cable-laying ship, limited by the water depth conditions in the sandbar area, small boats that meet the sailing conditions have small drafts and limited power. In the case of poor sea conditions, the power is obviously insufficient, resulting in slow sailing speed and low cable laying efficiency when helping tow the cable laying ship. Especially when the cable laying ship is in cross wind and waves, the actual cable laying route is more likely to deviate from the cable design route.

对于第二种方法,由于每次起抛锚时施放的锚缆长度有限,通常不大于500m,因此每次高潮时铺缆船行船的距离较短,通常不大于350m,因此铺缆船行船铺缆效率较低。For the second method, due to the limited length of the anchor cable that is released each time the anchor is lifted and dropped, usually not more than 500m, the distance that the cable-laying ship sails at each high tide is relatively short, usually not more than 350m, so the cable-laying ship sails and lays the cable less efficient.

综上所述,无论是第一种方法还是第二种方法,均存在行船铺缆的效率较低、施工周期较长的问题。长距离沙洲段海缆铺设施工,通常只有大潮汛的3-5天高潮时的水深条件,才满足行船要求。若不能在水深满足行船要求的3-5天内顺利通过沙洲段,完成电缆铺设施工,铺缆船将只能坐滩等待近半个月后的下一个大潮汛。待机期间的船舶安全、电缆安全将存在严重隐患。To sum up, both the first method and the second method have the problems of low efficiency of laying cables by boat and long construction period. For the construction of long-distance submarine cable laying in the sandbar section, usually only the water depth conditions at the high tide of 3-5 days during the big tide flood can meet the requirements for sailing. If the cable laying work cannot be completed within 3-5 days when the water depth meets the sailing requirements, the cable laying ship will have to sit on the beach and wait for the next big tide in nearly half a month. There will be serious hidden dangers to ship safety and cable safety during the standby period.

因此提高铺缆船行船铺缆效率,缩短施工周期,确保在一个大潮汛期间完成穿越长距离沙洲段海缆铺设施工,是业界亟待解决的技术问题。Therefore, it is an urgent technical problem to be solved in the industry to improve the efficiency of cable-laying ships, shorten the construction period, and ensure that the submarine cable laying construction across the long-distance sandbar section can be completed during a large tide.

发明内容Contents of the invention

为了提高长距离沙洲段海缆铺设的行船铺缆效率,确保在一个大潮汛期间完成穿越长距离沙洲段海缆铺设施工,本发明提出一种长距离沙洲段的预铺锚缆辅助行船方法及系统组成。In order to improve the cable laying efficiency of the long-distance sandbar section submarine cable laying and ensure that the submarine cable laying construction across the long-distance sandbar section is completed during a big tide, the present invention proposes a pre-laid anchor cable auxiliary sailing method for the long-distance sandbar section and system composition.

作为第一方面,本发明提出一种长距离沙洲段的预铺锚缆辅助行船方法,其特征在于,包括如下步骤:As a first aspect, the present invention proposes a pre-laid mooring cable-assisted sailing method for a long-distance sandbar section, which is characterized in that it includes the following steps:

1)在跨越沙洲区域的电缆设计路由两侧预先布设两条预铺锚缆;1) Pre-lay two pre-laid anchor cables on both sides of the cable design route across the sandbar area;

2)在铺缆船上预先布置安装两台绞磨机;2) Pre-arrange and install two winch mills on the cable-laying ship;

3)在大潮汛到来之前,铺缆船行船至预铺锚缆始端位置,打捞预铺锚缆的始端到铺缆船甲板,并接入绞磨机;3) Before the arrival of the big tide, the cable-laying ship sails to the beginning of the pre-laid anchor cable, salvages the beginning of the pre-laid anchor cable to the deck of the cable-laying ship, and connects it to the winch mill;

4)在涨潮至水深条件满足行船要求时,启动绞磨机绞缆,铺缆船持续沿着电缆设计路由行船,同时边铺边埋电缆;4) When the tide rises until the water depth meets the sailing requirements, start the winch mill to twist the cable, and the cable-laying ship continues to sail along the cable design route, while laying and burying the cable;

5)在落潮至水深条件不满足行船要求时,停止绞缆,铺缆船坐滩,等待下一次涨潮;5) When the ebb tide does not meet the requirements of sailing, stop the cable laying, and the cable laying ship sits on the beach and waits for the next high tide;

6)按照4、5步骤循环,在大潮汛期间,铺缆船利用高潮穿越长距离沙洲段铺缆施工完毕。6) Cycle according to steps 4 and 5. During the high tide, the cable laying ship will use the high tide to cross the long-distance sandbar section and complete the cable laying construction.

所述两台绞磨机,对于舷侧出缆的铺缆船,安装在铺缆船前进方向的船舷甲板上。The two winch mills are installed on the side deck of the cable-laying ship in the forward direction for the cable-laying ship with side outlet.

所述两台绞磨机,对于船艉出缆的铺缆船,安装在船头甲板上,并对称布置。The two winch mills are installed on the bow deck for the cable-laying ship that goes out from the stern, and are arranged symmetrically.

所述两条预铺锚缆的长度均足以穿越沙洲区域。The length of the two pre-laid anchor cables is sufficient to cross the sandbar area.

所述两条预铺锚缆平行于电缆设计路由,并保持100m-250m的距离。The two pre-laid anchor cables are parallel to the cable design route, and keep a distance of 100m-250m.

所述两条预铺锚缆接近始端的间距逐步变小,直到两条预铺锚缆始端的间距与铺缆船上两台绞磨机的间距大致相同。The distance between the two pre-laid anchor cables close to the starting ends is gradually reduced until the distance between the two pre-laid anchor cables is approximately the same as the distance between the two winches on the cable-laying ship.

作为第二方面,本发明提出一种长距离沙洲段的预铺锚缆系统组成,包括船锚、一端与船锚通过锚卸扣连接的锚缆,其特征在于,锚缆包括若干段第一钢丝绳索具、连接相邻两段第一钢丝绳索具的卸扣转环。As a second aspect, the present invention proposes a pre-laid anchor cable system for a long-distance sandbar section, including a ship anchor, and an anchor cable connected to the ship anchor through an anchor shackle at one end. It is characterized in that the anchor cable includes several sections of the first Steel wire rope slings and shackle swivels connecting two adjacent sections of the first steel wire rope slings.

所述锚缆的另一端与一条第二钢丝绳索具的一端通过普通卸扣连接。The other end of the anchor cable is connected to one end of a second wire rope sling through a common shackle.

所述第二钢丝绳索具的另一端与一个浮球组用尼龙绳连接。The other end of the second steel wire rope sling is connected with a floating ball group with a nylon rope.

所述第二钢丝绳索具的长度不小于高潮时水深与铺缆船干舷高度的总和,并留有适当余量。The length of the second wire rope sling is not less than the sum of the water depth at high tide and the freeboard height of the cable-laying ship, and an appropriate margin is left.

所述锚卸扣上连接一条锚头缆的一端;所述锚头缆的另一端与一个浮球组用尼龙绳连接。One end of an anchor cable is connected to the anchor shackle; the other end of the anchor cable is connected to a floating ball group with a nylon rope.

所述卸扣转环的位置附近用尼龙绳连接一个浮球;所述浮球上拴一个警示灯。A floating ball is connected with a nylon rope near the position of the shackle swivel; a warning light is fastened on the floating ball.

所述尼龙绳的连接长度按满足最高水位时浮球浮出水面三分之二体积以上确定。The connection length of the nylon rope is determined by more than two-thirds of the volume of the floating ball floating on the water surface when the highest water level is met.

所述浮球组由不少于两个浮球组成,各浮球分别涂上不同的颜色;所述浮球组上拴一个警示灯。The floating ball group is composed of no less than two floating balls, and each floating ball is painted with a different color; a warning light is attached to the floating ball group.

作为第三方面,本发明提出一种长距离沙洲段的预铺锚缆布设施工方法,其特征在于,包括如下步骤:As a third aspect, the present invention proposes a construction method for laying pre-laid anchor cables on a long-distance sandbar section, which is characterized in that it includes the following steps:

1)装船运输:在码头将包括船锚、第一钢丝绳索具、浮球组、浮球在内的预铺锚缆的各部分组件装载在起重船甲板上;第二挖掘机上船;然后起重船运输到海上安装位置附近;其中每条第一钢丝绳索具卷在一个滚筒,便于吊装、运输,及现场布设;1) Shipment and transportation: Load all parts of the pre-laid anchor cable including the anchor, the first wire rope sling, the float group, and the float on the deck of the crane ship at the dock; the second excavator boards the ship; Then the crane ship is transported to the vicinity of the offshore installation location; each of the first wire rope slings is wound on a drum, which is convenient for hoisting, transportation, and on-site layout;

2)起重船坐滩:起重船利用高潮时航行到电缆设计路由跨越沙洲段附近位置抛锚就位;落潮后,起重船坐滩;2) The crane ship is on the beach: the crane ship uses the high tide to sail to the position near the cable design route crossing the sandbar section and anchors in place; after the ebb tide, the crane ship is on the beach;

3)第二挖掘机下船:退潮露滩后,起重船吊机辅助下吊装搭设爬梯结构,第二挖掘机沿着爬梯结构下船;3) Disembarking of the second excavator: After the ebb tide and the beach, the lifting ladder structure is hoisted and erected with the assistance of the crane on the crane, and the second excavator disembarks along the ladder structure;

4)吊装船锚就位:起重船将船锚吊至起重船以外,由第二挖掘机吊起船锚,在GPS导航指引下运送到预铺锚缆的锚位,并放置在滩涂泥面上;4) Hoist the anchor in place: the crane ship lifts the anchor out of the crane ship, lifts the anchor by the second excavator, and transports it to the anchor position of the pre-laid anchor cable under the guidance of GPS navigation, and places it on the tidal flat mud surface;

5)第一钢丝绳索具布设:第二挖掘机回到起重船附近,将起重船吊下来的卷有第一钢丝绳索具的一个滚筒吊装到锚位附近;将第一钢丝绳索具的一端与船锚用锚卸扣连接;第二挖掘机吊着滚筒沿着预铺锚缆设计布设轨迹行驶,同时随着滚筒的转动布设第一钢丝绳索具,直到这段第一钢丝绳索具全部脱离滚筒;按照以上方法在布设第二段第一钢丝绳索具,并且将第二段第一钢丝绳索具和第一段第一钢丝绳索具用卸扣转环连接;按以上方法,直到整条预铺锚缆的各段第一钢丝绳索具全部布设连接完毕;5) The first wire rope rigging is laid: the second excavator returns to the vicinity of the crane ship, hoists a drum with the first wire rope sling that is hoisted by the crane ship near the anchor position; One end is connected to the ship anchor with an anchor shackle; the second excavator hoists the drum and travels along the designed laying track of the pre-laid anchor cable, and at the same time lays the first wire rope sling with the rotation of the drum until the first wire rope sling is completely Detach from the drum; according to the above method, lay the second section of the first steel wire rope sling, and connect the second section of the first steel wire rope sling and the first section of the first steel wire rope sling with a shackle swivel; follow the above method until the entire sling The first wire rope slings of each section of the pre-laid anchor cable are all laid and connected;

6)附件连接:在第二挖掘机辅助下,分别连接锚头缆、第二钢丝绳索具;然后在相应的位置用尼龙绳连接浮球、浮球组,连接警示灯;6) Accessory connection: With the assistance of the second excavator, connect the anchor head cable and the second wire rope sling respectively; then connect the floating ball and floating ball group with nylon rope at the corresponding position, and connect the warning light;

7)起重船撤离:当两条预铺锚缆全部布设完毕后,第二挖掘机回到起重船上;起重船在涨水后高潮时离开沙洲区域,返回码头。7) Crane boat evacuation: After the two pre-laid anchor cables are all laid, the second excavator returns to the crane boat; the crane boat leaves the sandbar area at high tide after rising water and returns to the dock.

以上4-6步骤,在低潮露滩时进行;涨潮前第二挖掘机撤回起重船待命;再次低潮露滩后下船继续施工。The above steps 4-6 are carried out at low tide and on the beach; before the high tide, the second excavator is withdrawn to the crane ship and is on standby; after the low tide is on the beach again, disembark and continue construction.

本发明的有益效果是:预铺锚缆布设可在电缆海上铺设施工前进行,不占用主作业时间;当铺缆船穿越沙洲段时,依靠绞磨机绞预铺锚缆提供铺缆船的前进动力,因此在一个高潮期间水深满足行船要求的条件下,可以不间断行船,达到最大限度的提高铺缆效率的目的;从而确保一次大潮汛铺缆船能够穿越沙洲段完成电缆铺设施工。The beneficial effects of the present invention are: the laying of the pre-laid anchor cables can be carried out before the laying of the cables at sea, without taking up the main operation time; Therefore, under the condition that the water depth meets the requirements of sailing during a high tide, the ship can be sailed uninterrupted to maximize the efficiency of cable laying; thus ensuring that the cable laying ship can cross the sandbar section to complete the cable laying construction during a big tide.

附图说明Description of drawings

以下结合附图及具体实施方式作进一步详细说明。Further details will be given below in conjunction with the accompanying drawings and specific embodiments.

图1为本发明实施例一的平面布置图;Fig. 1 is the plane layout diagram of Embodiment 1 of the present invention;

图2为实施例一的船舷出缆铺缆船布置图;Fig. 2 is the layout drawing of the cable-laying ship on the ship's side of the first embodiment;

图3为本发明实施例二的平面布置图;Fig. 3 is the plane layout drawing of the second embodiment of the present invention;

图4为实施例二的船艉出缆铺缆船布置图;Fig. 4 is the layout drawing of the cable-laying ship of the stern of the second embodiment;

图5为预铺锚缆组成连接示意图;Figure 5 is a schematic diagram of the composition and connection of pre-laid anchor cables;

图6为起重船装船布置图;Fig. 6 is the loading layout of the crane ship;

图7为起重船抛锚就位示意图;Fig. 7 is a schematic diagram of a crane ship anchored in place;

图8为第二挖掘机下船示意图;Fig. 8 is a schematic diagram of disembarking the second excavator;

图9为第二挖掘机运送船锚示意图;Fig. 9 is a schematic diagram of the second excavator transporting the anchor;

图10为第二挖掘机布设主钢丝绳示意图。Fig. 10 is a schematic diagram of laying the main wire rope by the second excavator.

其中:1-电缆设计路由;2-预铺锚缆;3-铺缆船;4-绞磨机;5-沙洲区域;6-主流向;7-电缆;8-小船;9-起重船;21-船锚;22-锚卸扣;23-锚缆;31-电动储缆盘;32-铺缆作业线;33-埋设犁;34-右舷锚缆;35-第一挖掘机;91-第二挖掘机;92-爬梯结构;231-第一钢丝绳索具;232-卸扣转环;233-第二钢丝绳索具;234-普通卸扣;235-浮球组;236-浮球;237-锚头缆;238-尼龙绳;239-警示灯;2311-滚筒。Among them: 1- cable design route; 2- pre-laid anchor cable; 3- cable laying ship; 4- winch mill; 5- sandbar area; 6- main direction; 7- cable; 8- small boat; 9- crane ship ;21-anchor; 22-anchor shackle; 23-anchor cable; 31-electric cable storage reel; 32-cable laying line; 33-buried plow; 34-starboard anchor cable; -Second excavator; 92-Ladder structure; 231-First wire rope rigging; 232-Shackle swivel; 233-Second wire rope rigging; 234-Ordinary shackle; ; 237-anchor head cable; 238-nylon rope; 239-warning light; 2311-roller.

具体实施方式Detailed ways

如图1、图3,一种长距离沙洲段的预铺锚缆2辅助行船方法,包括如下步骤:As shown in Fig. 1 and Fig. 3, a pre-laid anchor cable 2 assisted sailing method for a long-distance sandbar section includes the following steps:

1)在跨越沙洲区域5的电缆设计路由1两侧预先布设两条预铺锚缆2。1) Two pre-laid anchor cables 2 are pre-laid on both sides of the cable design route 1 across the sandbar area 5.

2)在铺缆船3上预先布置安装两台绞磨机4。2) Prearrange and install two winch mills 4 on the cable laying ship 3 .

3)在大潮汛到来之前,铺缆船3行船至预铺锚缆2始端位置时,打捞预铺锚缆2的始端到铺缆船3甲板,并接入绞磨机4。3) Before the arrival of the big tide, when the cable-laying ship 3 sails to the beginning of the pre-laid anchor cable 2, the beginning of the pre-laid anchor cable 2 is salvaged to the deck of the cable-laying ship 3, and connected to the winch 4.

4)在涨潮至水深条件满足行船要求时,启动绞磨机4绞缆,铺缆船3持续沿着电缆设计路1由行船,同时边铺边埋电缆。4) When the tide rises until the water depth meets the requirements for sailing, start the winch mill 4 to twist the cable, and the cable laying ship 3 continues to sail along the cable design route 1 while laying and burying the cable.

5)在落潮至水深条件不满足行船要求时,停止绞缆,铺缆船坐滩,等待下一次涨潮。5) When the ebb tide does not meet the requirements for sailing, stop the cable laying, and the cable laying ship sits on the beach and waits for the next high tide.

6)按照4、5步骤循环,在大潮汛期间,铺缆船3利用高潮穿越长距离沙洲区域5铺缆施工完毕。6) Cycle according to steps 4 and 5. During the flood season, the cable laying ship 3 uses the high tide to cross the long-distance sandbar area 5 and the cable laying construction is completed.

所述预铺锚缆2,其长度足以穿越沙洲区域5,两条预铺锚缆2平行于电缆设计路由1,并保持100m的距离。The length of the pre-laid anchor cables 2 is sufficient to cross the sandbar area 5, and the two pre-laid anchor cables 2 are parallel to the cable design route 1, and keep a distance of 100m.

所述两条预铺锚缆2接近始端的间距逐步变小,直到两条预铺锚缆2始端的间距与铺缆船3上两台绞磨机4的间距大致相同。The distance between the two pre-laid anchor cables 2 close to the starting ends is gradually reduced until the distance between the two pre-laid anchor cables 2 is approximately the same as the distance between the two winch mills 4 on the cable-laying ship 3 .

如图1、图2,实施例一:对于施工海域主流向6基本垂直于电缆设计路由1的情况,宜采用船舷出缆的铺缆船3。两台绞磨机4安装在铺缆船3左舷甲板上,来自电动储缆盘31的电缆7通过铺缆作业线32从右舷出缆,通过埋设犁33铺埋在海底以下。预铺锚缆2通过绞磨机4绞缆提供铺缆船3行船的持续动力,铺缆船3两条右舷锚缆34控制铺缆船3不过度偏离电缆设计路由1。右舷锚缆34的起抛锚在低潮露滩时由第一挖掘机35下船实施。As shown in Fig. 1 and Fig. 2, embodiment 1: for the situation that the main direction 6 of the construction sea area is substantially perpendicular to the cable design route 1, the cable laying ship 3 that goes out from the ship's side should be used. Two winch mills 4 are installed on the port deck of the cable laying ship 3, and the cables 7 from the electric cable storage reel 31 go out from the starboard side through the cable laying operation line 32, and are buried below the seabed by the laying plow 33. The pre-laid anchor cable 2 provides continuous power for the cable-laying ship 3 to sail through the twisted cable of the winch mill 4, and the two starboard anchor cables 34 of the cable-laying ship 3 control the cable-laying ship 3 not to deviate excessively from the cable design route 1. The anchor lifting and handling of the starboard anchor cable 34 is carried out by the first excavator 35 disembarking when the low tide is exposed.

铺缆船3船体大致顺流向,受流力较小,并由右舷锚缆34克服;铺缆船3行船依靠跨越沙洲区域5的预铺锚缆2提供动力,因此可充分利用高潮时满足行船水深条件的时间,电缆7铺埋的效率大幅度提高。The hull of the cable-laying ship 3 is generally along the flow direction, and the flow force is relatively small, which is overcome by the anchor cable 34 on the starboard side; In the time of water depth condition, the efficiency of laying and burying the cable 7 is greatly improved.

如图3、图4,实施例二:对于施工海域主流向6基本与电缆设计路由1走向一致的情况,宜采用船艉出缆的铺缆船3。两台绞磨机4安装在铺缆船3船头甲板上,并对称布置。来自电动储缆盘31的电缆7通过铺缆作业线32从船艉出缆,通过埋设犁33铺埋在海底以下。预铺锚缆2通过绞磨机4绞缆提供铺缆船3行船的持续动力,铺缆船3两舷各有一条小船8控制铺缆船3不过度偏离电缆设计路由1。As shown in Fig. 3 and Fig. 4, embodiment 2: for the situation that the main direction 6 of the construction sea area is basically consistent with the direction of the cable design route 1, it is advisable to use the cable laying ship 3 with the cable coming out from the stern. Two winch mills 4 are installed on the bow deck of the cable-laying ship 3 and arranged symmetrically. The cable 7 from the electric cable storage reel 31 goes out from the stern of the ship through the cable laying operation line 32, and is buried below the seabed by the embedding plow 33. The pre-laid anchor cable 2 provides continuous power for the cable-laying ship 3 to sail through the twisted cable of the winch mill 4. There is a small boat 8 on both sides of the cable-laying ship 3 to control the cable-laying ship 3 so as not to deviate excessively from the cable design route 1.

铺缆船3船体大致顺流向,受流力较小,并由两条小船8克服;铺缆船3行船依靠跨越沙洲区域5的预铺锚缆2提供动力,因此可充分利用高潮时满足行船水深条件的时间,电缆7铺埋的效率大幅度提高。The hull of the cable-laying ship 3 is generally along the flow direction, and the flow force is small, and is overcome by two small boats 8; the sailing of the cable-laying ship 3 relies on the pre-laid anchor cable 2 across the sandbar area 5 to provide power, so it can fully use the high tide to meet the requirements of sailing. In the time of water depth condition, the efficiency of laying and burying the cable 7 is greatly improved.

如图5,一种长距离沙洲段的预铺锚缆系统组成,包括船锚21、一端与船锚21通过锚卸扣22连接的锚缆23,其特征在于,锚缆23包括若干条第一钢丝绳索具231、连接相邻两条第一钢丝绳索具231的卸扣转环232。As shown in Figure 5, a pre-laid anchor cable system for a long-distance sandbar section consists of a ship anchor 21, an anchor cable 23 connected to the ship anchor 21 through an anchor shackle 22 at one end, and is characterized in that the anchor cable 23 includes several first A wire rope sling 231 and a shackle swivel 232 connecting two adjacent first wire rope slings 231 .

每条第一钢丝绳索具231缠绕在滚筒2311上,重量适当,便于使用第二挖掘机91吊运和第一钢丝绳索具231牵拉施放;使用卸扣转环232连接两条第一钢丝绳索具231,有利于在第一钢丝绳索具231牵拉施放的时候扭力得到释放。Each first steel wire rope rigging 231 is wound on the drum 2311, and the weight is appropriate, which is convenient to use the second excavator 91 to lift and the first steel wire rope rigging 231 to pull and release; use the shackle swivel 232 to connect the two first steel wire ropes The tool 231 is conducive to releasing the torsion force when the first wire rope rigging tool 231 is pulled and released.

所述锚缆23的另一端与一条第二钢丝绳索具233的一端通过普通卸扣234连接。所述第二钢丝绳索具233的另一端与一个浮球组235用尼龙绳238连接。所述第二钢丝绳索具233的长度不小于高潮时水深与铺缆船3干舷高度的总和,并留有适当余量。The other end of the anchor cable 23 is connected to one end of a second wire rope sling 233 through a common shackle 234 . The other end of the second wire rope rigging 233 is connected with a floating ball group 235 with a nylon rope 238 . The length of the second wire rope rigging 233 is not less than the sum of the water depth at high tide and the freeboard height of the cable-laying ship 3, and an appropriate margin is left.

所述锚卸扣22上连接一条锚头缆237的一端;所述锚头缆237的另一端与一个浮球组235用尼龙绳连接238。所述卸扣转环232的位置附近用尼龙绳238连接一个浮球236;所述浮球236上拴一个警示灯239。所述尼龙绳238的连接长度按满足最高水位时浮球236或浮球组235浮出水面三分之二体积以上确定。所述浮球组235由不少于两个浮球组成,各浮球分别涂上不同的颜色;所述浮球组235上拴一个警示灯239。One end of an anchor cable 237 is connected to the anchor shackle 22; the other end of the anchor cable 237 is connected 238 with a float group 235 by a nylon rope. A nylon rope 238 is used to connect a floating ball 236 near the position of the shackle swivel 232; a warning light 239 is fastened on the floating ball 236. The connection length of the nylon rope 238 is determined by more than two thirds of the volume of the floating ball 236 or the floating ball group 235 when the highest water level is met. The floating ball group 235 is composed of no less than two floating balls, and each floating ball is painted with a different color; a warning light 239 is tied to the floating ball group 235 .

浮球236、浮球组235在白天标识预铺锚缆2的位置,其上安装的警示灯239在夜间标识预铺锚缆2的位置,便于过往船舶观察和避让。The floating ball 236 and the floating ball group 235 mark the position of the pre-laid anchor cable 2 during the day, and the warning light 239 installed on it marks the position of the pre-laid anchor cable 2 at night, which is convenient for passing ships to observe and avoid.

如图6-图10,本发明提出一种长距离沙洲段的预铺锚缆2布设施工方法,包括如下步骤:As shown in Fig. 6-Fig. 10, the present invention proposes a kind of pre-laid anchor cable 2 laying construction method of long-distance sandbar section, comprises the following steps:

1)装船运输:在码头将包括船锚21、第一钢丝绳索具231、浮球组235、浮球236在内的预铺锚缆2的各部分组件全部装载在起重船9甲板上,第二挖掘机91上船,然后起重船9运输到海上安装位置附近;其中每条第一钢丝绳索具231卷在一个滚筒2311,便于吊装、运输,及现场布设;1) Shipment transportation: at the wharf, all parts of the pre-laid anchor cable 2 including the anchor 21, the first wire rope sling 231, the float group 235, and the float 236 are all loaded on the deck of the crane ship 9 , the second excavator 91 is boarded, and then the crane ship 9 is transported to the vicinity of the offshore installation location; wherein each first wire rope sling 231 is wound on a drum 2311, which is convenient for hoisting, transportation, and on-site layout;

2)起重船9坐滩:起重船9利用高潮时航行到电缆设计路由1跨越沙洲区域5附近位置抛锚就位;低潮后,起重船9坐滩;2) Crane ship 9 is on the beach: when the crane ship 9 sails to the cable design route 1 across the sandbar area 5 and anchors in place when it is at high tide; after low tide, the crane ship 9 is on the beach;

3)第二挖掘机91下船:退潮露滩后,起重船9的吊机辅助下吊装搭设爬梯结构92,第二挖掘机91沿着爬梯结构92下船;3) The second excavator 91 disembarks: after the ebb tide and the beach, the crane of the crane ship 9 assists in hoisting and erecting the ladder structure 92, and the second excavator 91 disembarks along the ladder structure 92;

4)吊装船锚21就位:起重船9将船锚21吊至起重船9以外,由第二挖掘机91吊起船锚21,在GPS导航指引下运送到预铺锚缆2的锚位,并放置在滩涂泥面上;4) hoisting the anchor 21 in place: the lifting ship 9 lifts the anchor 21 outside the lifting ship 9, lifts the anchor 21 by the second excavator 91, and transports it to the place where the anchor cable 2 is pre-laid under the guidance of GPS navigation. Anchor position, and placed on the tidal mud surface;

5)第一钢丝绳索具231布设:第二挖掘机91回到起重船9附近,将起重船9吊下来的卷有第一钢丝绳索具231的一个滚筒2311吊装到锚位附近;将第一钢丝绳索具231的一端与船锚21用锚卸扣22连接;第二挖掘机91吊着滚筒2311沿着预铺锚缆2设计布设轨迹行驶,同时随着滚筒2311的转动布设第一钢丝绳索具231,直到这段第一钢丝绳索具231全部脱离滚筒2311;按照以上方法在布设第二段第一钢丝绳索具231,并且将第二段第一钢丝绳索具231和第一段第一钢丝绳索具231用卸扣转环232连接;按以上方法,直到整条预铺锚缆2的各段第一钢丝绳索具231全部布设连接完毕;5) Laying of the first wire rope rigging 231: the second excavator 91 returns to the vicinity of the crane ship 9, hoists a drum 2311 with the first wire rope rigging 231 hoisted by the crane ship 9 to the vicinity of the anchor position; One end of the first wire rope sling 231 is connected with the ship anchor 21 with the anchor shackle 22; the second excavator 91 hangs the drum 2311 and travels along the pre-laid anchor cable 2 design laying track, and simultaneously lays the first anchor cable along with the rotation of the drum 2311. Wire rope sling 231, until this section of the first wire rope sling 231 all breaks away from the drum 2311; according to the above method, the second section of the first wire rope sling 231 is laid, and the second section of the first steel wire rope 231 and the first section of the first section A wire rope sling 231 is connected with a shackle swivel 232; according to the above method, until the first wire rope sling 231 of each section of the whole pre-laid anchor cable 2 is all laid and connected;

6)附件连接:在第二挖掘机91辅助下,分别连接锚头缆237、第二钢丝绳索具233;然后在相应的位置用尼龙绳238连接浮球236、浮球组235,连接警示灯239;6) Accessory connection: with the assistance of the second excavator 91, respectively connect the anchor head cable 237 and the second wire rope sling 233; then connect the floating ball 236 and the floating ball group 235 with a nylon rope 238 at the corresponding position, and connect the warning light 239;

7)起重船9撤离:当两条预铺锚缆2全部布设完毕后,第二挖掘机91回到起重船9上;起重船9在涨水后高潮时离开沙洲区域5,返回码头。7) Lifting ship 9 withdraws: after two pre-laid anchor cables 2 are all laid out, the second excavator 91 returns to the lifting ship 9; pier.

以上4-6步骤,在低潮露滩时进行;涨潮前第二挖掘机91撤回起重船9待命;再次低潮露滩后下船继续施工。The above 4-6 steps are carried out when the low tide is exposed; before the high tide, the second excavator 91 is withdrawn to the crane ship 9 and is on standby; after the low tide is exposed again, disembark to continue construction.

Claims (18)

1. A pre-laying anchor cable auxiliary ship-moving method for a long-distance sandbar section is characterized by comprising the following steps:
1) two pre-laid anchor cables are pre-laid on two sides of a cable design route spanning a sandbank area;
2) arranging and installing two winching machines on a cable laying ship in advance;
3) before a flood comes, a cable laying ship travels to the position of the starting end of the pre-laid anchor cable, the starting end of the pre-laid anchor cable is salvaged to a deck of the cable laying ship, and a winching machine is connected;
4) when the condition of rising tide to water depth meets the requirement of a traveling ship, starting a winch for stranding, and continuously traveling the ship along the cable design route by a cable laying ship while laying and burying the cable;
5) when the water depth condition from the tide to the water depth does not meet the requirement of sailing, stopping stranding, laying a cable boat and sitting on the beach, and waiting for the next tide rising;
6) and (5) circulating according to the steps 4 and 5, and finishing cable laying construction of the cable laying ship by utilizing high tide to pass through the long-distance sand continent section in the flood season of the flood tide.
2. The method for assisting the sailing of the pre-laid anchor cable across the long-distance sandbank section according to claim 1, wherein: and the two winching machines are arranged on the ship board deck in the advancing direction of the cable laying ship for the cable laying ship with the side cable outlet.
3. The method for assisting the sailing of the pre-laid anchor cable across the long-distance sandbank section according to claim 1, wherein: the two winching machines are arranged on a bow deck and symmetrically arranged for the cable laying ship with the stern cable outlet.
4. The method for assisting the sailing of the pre-laid anchor cable across the long-distance sandbank section according to claim 1, wherein: the two pre-laid anchor lines are of sufficient length to traverse the sandbar section.
5. The method for assisting the sailing of the pre-laid anchor cable across the long-distance sandbank section according to claim 1, wherein: the two pre-laid anchor cables are parallel to the cable design route and keep a distance of 100m-250 m.
6. The method for assisting the sailing of the pre-laid anchor cables across the long-distance sandbars according to claim 1, wherein the distance between the two pre-laid anchor cables near the beginning is gradually decreased until the distance between the beginning of the two pre-laid anchor cables is approximately the same as the distance between two winches on the cable-laying ship.
7. The pre-laid anchor cable system for the long-distance sandbar section comprises a ship anchor and an anchor cable, wherein one end of the anchor cable is connected with the ship anchor through an anchor shackle.
8. The pre-laid anchor line system composition for long-reach sandbars according to claim 7, wherein the other end of the anchor line is connected to one end of a second wire rope rigging by a conventional shackle.
9. The pre-laid anchor line system composition of claim 8, wherein the other end of the second wire rope rigging is connected to a buoyant ball group with nylon rope.
10. The pre-mooring anchor line system composition for long-distance sandbars according to claim 8, wherein the length of the second wire rope is not less than the sum of the water depth at high tide and the freeboard height of the mooring vessel, and a proper margin is left.
11. The pre-laid anchor line system assembly of claim 7, wherein the anchor shackle is connected to an end of an anchor line.
12. The pre-laid anchor line system composition for long-reach sandbars according to claim 11, wherein the other end of the anchor line is connected to a buoyant ball group with nylon rope.
13. The pre-laid anchor line system assembly of a long-haul sandbank section of claim 7, wherein a float ball is attached to the shackle near the location of the shackle.
14. The system of claim 9 or 12, wherein the floating ball group comprises at least two floating balls, and each floating ball is painted with different colors.
15. The pre-laid anchor line system composition of a long-reach sandbank section according to claim 9, 12 or 13, wherein the connection length of the nylon rope is determined by the volume of more than two thirds of the floating ball floating above the water surface when the highest water level is met.
16. A pre-laid anchor line system for long-haul sandbars as claimed in claim 9, 12 or 13 wherein a warning light is attached to said float ball or float ball set.
17. A pre-laid anchor cable laying construction method for a long-distance sandbar section is characterized by comprising the following steps:
1) shipping and transporting: loading each part assembly of a pre-laid anchor cable comprising a ship anchor, a first steel wire rope, a floating ball group and a floating ball on a deck of a crane ship at a wharf, loading a second excavator on the ship, and transporting the crane ship to the position near the offshore installation position; each first steel wire rope is wound on a roller, so that the hoisting, transportation and field laying are facilitated.
2) The crane ship sits on the beach: the crane ship sails to a position near a cable design route crossing sandbar section by utilizing high tide and is anchored in place; after the tide falls, the crane ship sits on the beach.
3) The second excavator is launched: after the tide is removed and the dew is exposed, the hoisting boat crane assists to hoist and set up the ladder stand structure, and the second excavator is driven to descend along the ladder stand structure.
4) Hoisting the ship anchor in place: the crane ship lifts the ship anchor out of the crane ship, the ship anchor is lifted by a second excavator, and the ship anchor is conveyed to an anchor position of a pre-laid anchor cable under the guidance of GPS navigation and is placed on the mud surface of the mud flat.
5) Laying a first steel wire rope rigging: the second excavator returns to the position near the crane ship, and a roller which is hung by the crane ship and is coiled with a first steel wire rope is hoisted to the position near the anchor position; connecting one end of a first steel wire rope tool with the anchor shackle for the ship anchor; the second excavator hangs the roller and runs along the designed laying track of the pre-laid anchor cable, and simultaneously a first steel wire rope rigging is laid along with the rotation of the roller until the first steel wire rope rigging is completely separated from the roller; laying a second section of first steel wire rope rigging according to the method, and connecting the second section of first steel wire rope rigging with the first section of first steel wire rope rigging by using a shackle swivel; according to the method, the first steel wire rope of each section of the whole pre-laid anchor cable is completely laid and connected.
6) Connecting accessories: under the assistance of a second excavator, an anchor head cable and a second steel wire rope rigging are respectively connected; then the nylon rope is used for connecting the floating ball and the floating ball group at corresponding positions and connecting the warning lamp.
7) And (3) evacuating the crane ship: after the two pre-laid anchor cables are completely laid, the second excavator returns to the crane ship; the crane ship leaves the sandbank area at the time of high water and high tide and returns to the wharf.
18. The construction method for laying anchor cables in advance for the long-distance sandbar according to claim 17, wherein the 4-6 steps are performed in low tide and open beach; before the flood tide, the second excavator withdraws the crane ship for standby; and taking the ship out for continuous construction after the tide is low again and the beach is exposed.
CN201910885948.2A 2019-09-11 2019-09-11 Pre-laying anchor cable auxiliary ship-moving method and system composition of long-distance sandbar section Pending CN110601090A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910885948.2A CN110601090A (en) 2019-09-11 2019-09-11 Pre-laying anchor cable auxiliary ship-moving method and system composition of long-distance sandbar section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910885948.2A CN110601090A (en) 2019-09-11 2019-09-11 Pre-laying anchor cable auxiliary ship-moving method and system composition of long-distance sandbar section

Publications (1)

Publication Number Publication Date
CN110601090A true CN110601090A (en) 2019-12-20

Family

ID=68861004

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910885948.2A Pending CN110601090A (en) 2019-09-11 2019-09-11 Pre-laying anchor cable auxiliary ship-moving method and system composition of long-distance sandbar section

Country Status (1)

Country Link
CN (1) CN110601090A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113594972A (en) * 2021-08-24 2021-11-02 广州南方卫星导航仪器有限公司 Offshore cable laying cooperative operation method and system based on multi-ship linkage

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0617970A (en) * 1992-07-02 1994-01-25 Furukawa Electric Co Ltd:The Construction method of burying long body in seabed
FR2781033A1 (en) * 1998-07-08 2000-01-14 Louis Dreyfus Communication Cable laying apparatus for burying cable in bed of watercourse comprising a towed sledge-mounted submerged mole-plough
JP2003319521A (en) * 2002-04-22 2003-11-07 Sumitomo Electric Ind Ltd Method of laying submarine cable
CN103247977A (en) * 2013-05-14 2013-08-14 国家电网公司 Multiphase submarine cable transversal arrangement circularly laying construction method
CN205418004U (en) * 2016-03-21 2016-08-03 江苏乾维海洋工程科技发展有限公司 Buoy mooring system
CN108216491A (en) * 2018-03-07 2018-06-29 南通力威机械有限公司 A kind of novel paving cable ship trailer system
JP2018167745A (en) * 2017-03-30 2018-11-01 株式会社関海事工業所 On-water work method
CN108755644A (en) * 2018-07-04 2018-11-06 天津立海兴海洋工程有限公司 Transfer platform and its installation method for intertidal zone land cable drawing
CN211405292U (en) * 2019-09-11 2020-09-01 北京海瑞兴能源科技有限责任公司 Pre-laying anchor cable system composition of long-distance sandbank section

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0617970A (en) * 1992-07-02 1994-01-25 Furukawa Electric Co Ltd:The Construction method of burying long body in seabed
FR2781033A1 (en) * 1998-07-08 2000-01-14 Louis Dreyfus Communication Cable laying apparatus for burying cable in bed of watercourse comprising a towed sledge-mounted submerged mole-plough
JP2003319521A (en) * 2002-04-22 2003-11-07 Sumitomo Electric Ind Ltd Method of laying submarine cable
CN103247977A (en) * 2013-05-14 2013-08-14 国家电网公司 Multiphase submarine cable transversal arrangement circularly laying construction method
CN205418004U (en) * 2016-03-21 2016-08-03 江苏乾维海洋工程科技发展有限公司 Buoy mooring system
JP2018167745A (en) * 2017-03-30 2018-11-01 株式会社関海事工業所 On-water work method
CN108216491A (en) * 2018-03-07 2018-06-29 南通力威机械有限公司 A kind of novel paving cable ship trailer system
CN108755644A (en) * 2018-07-04 2018-11-06 天津立海兴海洋工程有限公司 Transfer platform and its installation method for intertidal zone land cable drawing
CN211405292U (en) * 2019-09-11 2020-09-01 北京海瑞兴能源科技有限责任公司 Pre-laying anchor cable system composition of long-distance sandbank section

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
潘梦蕾;: "锚与锚链", 现代舰船, no. 04, 1 April 2008 (2008-04-01) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113594972A (en) * 2021-08-24 2021-11-02 广州南方卫星导航仪器有限公司 Offshore cable laying cooperative operation method and system based on multi-ship linkage

Similar Documents

Publication Publication Date Title
CN111645810B (en) Multifunctional work ship with buoyancy adjusting carrying platform and operation method thereof
US10150535B2 (en) Systems, methods and units for offloading or loading cargo at sea
JP2009533258A (en) Deep-sea ship
EP0653349B1 (en) Line fisher for use in anchor laying
WO2009070034A2 (en) Method for picking up and towing a structure under water
JP6820698B2 (en) How to add mooring lines, how to moor floating structures and how to construct floating offshore wind turbines
CN207060358U (en) Large Offshore Structures semi-submerged ship floats installing and applied
US7882792B2 (en) Auxiliary floating structure and procedure for descent of equipment into the sea
CN110601090A (en) Pre-laying anchor cable auxiliary ship-moving method and system composition of long-distance sandbar section
CN211405292U (en) Pre-laying anchor cable system composition of long-distance sandbank section
CN113879487B (en) Unloading method of non-self-floating sinking tube
JP6949690B2 (en) Floating body mooring method and floating body
JPH0656076A (en) Submarine cable laying construction method and laying work ship thereof
CN210529503U (en) A positioning device for a suspension bridge beam-carrying ship
EP3841007B1 (en) Mooring tensioning arrangement and a method for longitudinal cross tension of a mooring system
CN203714157U (en) Full-rotation tugboat with two anchor winches at fore body
CN113772044A (en) Offshore single-point mooring replacement and maintenance method
CN219406804U (en) Double deck ship anchoring system
CN112722161A (en) Low-cost launching construction process for jacket
CN110949612A (en) Single-point anchoring system suitable for deep open sea culture ship
CN107128459B (en) Large-scale marine structure semi-submerged ship floating installation
CN105059484B (en) It goes ashore on a kind of Large Offshore Structures operating type
CN221678929U (en) A bow anchoring device for offshore wind power operations
CN109422200B (en) Installation method of tensioning hydraulic cylinder of drilling platform marine riser
NL2004529C2 (en) Vessel and method for raising a load under water using the vessel.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination