CN110145315A - A kind of driving method weakening city shallow tunnel concussion of blasting - Google Patents

A kind of driving method weakening city shallow tunnel concussion of blasting Download PDF

Info

Publication number
CN110145315A
CN110145315A CN201910392462.5A CN201910392462A CN110145315A CN 110145315 A CN110145315 A CN 110145315A CN 201910392462 A CN201910392462 A CN 201910392462A CN 110145315 A CN110145315 A CN 110145315A
Authority
CN
China
Prior art keywords
predicament
top bar
blasting
concussion
embarrassing situation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910392462.5A
Other languages
Chinese (zh)
Inventor
马栋
田小路
杨彦岭
张红伟
刘学文
孟凡文
王金阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN201910392462.5A priority Critical patent/CN110145315A/en
Publication of CN110145315A publication Critical patent/CN110145315A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of driving method for weakening city shallow tunnel concussion of blasting, include the following steps: that broken digging machine or cantilever excavator is selected to carry out cold digging operation to top bar rock mass according to section size;Top bar dregs is slagged tap;Top bar erects steel arch-shelf and sets anchor pole;Top bar pneumatically placed concrete;It gets out of a predicament or an embarrassing situation Blasting Excavation;Dregs of getting out of a predicament or an embarrassing situation is slagged tap;It gets out of a predicament or an embarrassing situation and erects steel arch-shelf and set anchor pole;Pneumatically placed concrete of getting out of a predicament or an embarrassing situation closing;Inverted arch applies.Tunnel top bar of the present invention is got out of a predicament or an embarrassing situation and inverted arch step excavation, each workspace process independently carry out, and be independent of each other interference, and speed of application is significantly improved;Tunnel inverted arch just props up quickly closure in time, closely follows face, and effective deformation controlling for rock surrounding gateways guarantees the quality and safety of constructing tunnel;Biggish shock insulation band and free face are provided after the cold digging of top bar, get out of a predicament or an embarrassing situation explosion when so that concussion of blasting reduces, mitigate influence of the explosion to resident.

Description

A kind of driving method weakening city shallow tunnel concussion of blasting
Technical field
The present invention relates to technical field of tunnel construction, it particularly relates to a kind of decrease city shallow tunnel concussion of blasting Driving method.
Background technique
At present hard, generally use compared with soft rock tunnel drilling and blasting method excavation.When being in complex environment, city is especially passed through When, upper part often there are many buildings or structures, scenic spots and historical sites etc., concussion of blasting in construction to the structures of buildings or structures and The resident of periphery life can have an adverse effect.Therefore, it is necessary to take glissando or use damping excavation technology.
Summary of the invention
For above-mentioned technical problem in the related technology, the present invention proposes a kind of to weaken city shallow tunnel concussion of blasting Driving method can overcome the above-mentioned deficiency of the prior art.
To realize the above-mentioned technical purpose, the technical scheme of the present invention is realized as follows:
A kind of driving method weakening city shallow tunnel concussion of blasting, includes the following steps:
S1: broken digging machine or cantilever excavator is selected to carry out cold digging operation to top bar rock mass according to section size;
S2: top bar dregs is slagged tap;
S3: top bar erects steel arch-shelf and sets anchor pole, specifically:
S3.1: the loose slag of top bar face arch springing or corner position is cleaned out;
S3.2: using the first branch rack of face, the arch clipping room determined according to design drawing is away from installation steel arch-shelf;
S3.3: being welded to connect muscle and reinforced mesh, installs lock foot anchoring stock and system anchor bolt;
S4: top bar pneumatically placed concrete;
S5: Blasting Excavation of getting out of a predicament or an embarrassing situation;
S6: dregs of getting out of a predicament or an embarrassing situation is slagged tap;
S7: getting out of a predicament or an embarrassing situation and erect steel arch-shelf and set anchor pole, specifically:
S7.1: steel arch-shelf is installed after the loose slag of arch springing position is cleaned out;
S7.2: up/down steps steel arch-shelf is connected using bolt;
S7.3: being welded to connect muscle and reinforced mesh, installs lock foot anchoring stock and system anchor bolt;
S8: pneumatically placed concrete of getting out of a predicament or an embarrassing situation closing;
After S9: inverted arch applies, and supporting in the early stage all closes cyclization, lining construction operation is carried out.
Further, in step S1, the cold every cyclic advance for digging operation is determined according to country rock situation, generally no greater than 2 Pin Steelframe spacing.
Preferably, step S2 specifically: in top bar digging process, face is crushed dregs using mini-excavator It takes off and is transported to rear, then the dregs at rear is transported to outside hole using transport vehicle.
Preferably, it in step S3.2, is attached between steel arch-shelf each unit using steel plate, angle steel and bolt.
Preferably, in step S4, top bar pneumatically placed concrete uses wet spraying process, and spraying operation segmentation, fragment, layering, From bottom to top, spiral successively carries out.
Preferably, it when in top bar pneumatically placed concrete if any larger calixconcavity, is first filled and led up, guarantees that preliminary bracing and scar are close Patch makes steel arch-shelf and spray anchor at supporting entirety stress, to inhibit surrouding rock deformation.
Preferably, in step S5, Blasting Excavation of getting out of a predicament or an embarrassing situation takes the construction principle of " more perforatings, few powder charge, be segmented " more, and According to the country rock situation that every circulation face discloses, borehole arrangement parameter is adjusted in time, optimizes Blasting Excavation scheme.
Preferably, step S6 specifically: excavate face rear portion getting out of a predicament or an embarrassing situation using mini-excavator or rollover loading machine Operation of slagging tap is carried out, and dregs is transported to outside hole using transport vehicle.
Preferably, in step S8, pneumatically placed concrete of getting out of a predicament or an embarrassing situation uses wet spraying process, and spraying operation segmentation, fragment, layering, From bottom to top, spiral successively carries out.
Beneficial effects of the present invention: the present invention has the advantage that as follows with effect:
1, tunnel top bar, get out of a predicament or an embarrassing situation and inverted arch step excavation, each workspace process independently carry out, be independent of each other interference, applies Work speed is significantly improved.
2, tunnel inverted arch just props up quickly closure in time, closely follows face, and effective deformation controlling for rock surrounding gateways guarantees constructing tunnel Quality and safety.
3, biggish shock insulation band and free face are provided after the cold digging of top bar, get out of a predicament or an embarrassing situation explosion when so that concussion of blasting drop It is low, mitigate influence of the explosion to resident.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is the schematic diagram of the benching tunnelling method section excavation described according to embodiments of the present invention;
In figure: 1, top bar excavates the soil body;2, it gets out of a predicament or an embarrassing situation and excavates the soil body;3, inverted arch excavates the soil body;4, inverted arch has been applied.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected Range.
The driving method of a kind of decrease city shallow tunnel concussion of blasting according to embodiments of the present invention, including it is as follows Step:
S1: broken digging machine or cantilever excavator is selected to carry out cold digging operation to top bar rock mass according to section size;
S2: top bar dregs is slagged tap;
S3: top bar erects steel arch-shelf and sets anchor pole, specifically:
S3.1: the loose slag of top bar face arch springing or corner position is cleaned out;
S3.2: using the first branch rack of face, the arch clipping room determined according to design drawing is away from installation steel arch-shelf;
S3.3: being welded to connect muscle and reinforced mesh, installs lock foot anchoring stock and system anchor bolt;
S4: top bar pneumatically placed concrete;
S5: Blasting Excavation of getting out of a predicament or an embarrassing situation;
S6: dregs of getting out of a predicament or an embarrassing situation is slagged tap;
S7: getting out of a predicament or an embarrassing situation and erect steel arch-shelf and set anchor pole, specifically:
S7.1: steel arch-shelf is installed after the loose slag of arch springing position is cleaned out;
S7.2: up/down steps steel arch-shelf is connected using bolt;
S7.3: being welded to connect muscle and reinforced mesh, installs lock foot anchoring stock and system anchor bolt;
S8: pneumatically placed concrete of getting out of a predicament or an embarrassing situation closing;
After S9: inverted arch applies, and supporting in the early stage all closes cyclization, lining construction operation is carried out.
Wherein, in step S1, the cold every cyclic advance for digging operation is determined according to country rock situation, generally no greater than 2 Pin steelframes Spacing.
Wherein, step S2 specifically: in top bar digging process, face is crushed dregs using mini-excavator and is taken off It is transported to rear, then the dregs at rear is transported to outside hole using transport vehicle.
Wherein, it in step S3.2, is attached between steel arch-shelf each unit using steel plate, angle steel and bolt.
Wherein, in step S4, top bar pneumatically placed concrete uses wet spraying process, and spraying operation segmentation, fragment, layering, by On down, spiral is successively carried out.
Wherein, it when in top bar pneumatically placed concrete if any larger calixconcavity, is first filled and led up, guarantees that preliminary bracing and scar are close Patch makes steel arch-shelf and spray anchor at supporting entirety stress, to inhibit surrouding rock deformation.
Wherein, in step S5, Blasting Excavation of getting out of a predicament or an embarrassing situation takes the construction principle of " more perforatings, few powder charge, be segmented ", and root more According to the country rock situation that every circulation face discloses, borehole arrangement parameter is adjusted in time, optimizes Blasting Excavation scheme.
Wherein, step S6 specifically: using mini-excavator or rollover loading machine get out of a predicament or an embarrassing situation excavate face rear portion into Capable operation of slagging tap, and dregs is transported to outside hole using transport vehicle.
Wherein, in step S8, pneumatically placed concrete of getting out of a predicament or an embarrassing situation uses wet spraying process, and spraying operation segmentation, fragment, layering, by On down, spiral is successively carried out.
In order to facilitate understanding above-mentioned technical proposal of the invention, below by way of in specifically used mode to of the invention above-mentioned Technical solution is described in detail.
It is according to the present invention it is a kind of weaken city shallow tunnel concussion of blasting driving method, include as shown in Figure 1: It excavates the soil body 1 to top bar to excavate, top bar, which is excavated, uses cold digging method, and top bar dregs is slagged tap, and erects steel arch-shelf and beats If anchor pole, top bar pneumatically placed concrete;Then it excavates the soil body 2 to getting out of a predicament or an embarrassing situation and excavates, excavation of getting out of a predicament or an embarrassing situation is left office using blasting procedure Rank dregs is slagged tap, and is erected steel arch-shelf and is set anchor pole, pneumatically placed concrete of getting out of a predicament or an embarrassing situation;The soil body 3 finally is excavated to inverted arch to excavate, and is applied Inverted arch 4 has been applied as inverted arch, has such as needed to be backfilled calixconcavity in top bar pneumatically placed concrete, has needed to carry out calixconcavity backfill.
In conclusion tunnel top bar of the present invention, get out of a predicament or an embarrassing situation and inverted arch step excavation, each workspace process it is independent into Row, be independent of each other interference, and speed of application is significantly improved;Tunnel inverted arch just props up quickly closure in time, closely follows face, effectively Deformation controlling for rock surrounding gateways guarantees the quality and safety of constructing tunnel;Biggish shock insulation band and free face are provided after the cold digging of top bar, Get out of a predicament or an embarrassing situation explosion when so that concussion of blasting reduces, mitigate influence of the explosion to resident.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (9)

1. a kind of driving method for weakening city shallow tunnel concussion of blasting, which comprises the steps of:
S1: broken digging machine or cantilever excavator is selected to carry out cold digging operation to top bar rock mass according to section size;
S2: top bar dregs is slagged tap;
S3: top bar erects steel arch-shelf and sets anchor pole, specifically:
S3.1: the loose slag of top bar face arch springing or corner position is cleaned out;
S3.2: using the first branch rack of face, the arch clipping room determined according to design drawing is away from installation steel arch-shelf;
S3.3: being welded to connect muscle and reinforced mesh, installs lock foot anchoring stock and system anchor bolt;
S4: top bar pneumatically placed concrete;
S5: Blasting Excavation of getting out of a predicament or an embarrassing situation;
S6: dregs of getting out of a predicament or an embarrassing situation is slagged tap;
S7: getting out of a predicament or an embarrassing situation and erect steel arch-shelf and set anchor pole, specifically:
S7.1: steel arch-shelf is installed after the loose slag of arch springing position is cleaned out;
S7.2: up/down steps steel arch-shelf is connected using bolt;
S7.3: being welded to connect muscle and reinforced mesh, installs lock foot anchoring stock and system anchor bolt;
S8: pneumatically placed concrete of getting out of a predicament or an embarrassing situation closing;
After S9: inverted arch applies, and supporting in the early stage all closes cyclization, lining construction operation is carried out.
2. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 1, which is characterized in that step In rapid S1, the cold every cyclic advance for digging operation is determined according to country rock situation, generally no greater than 2 Pin steelframe spacing.
3. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 2, which is characterized in that step Rapid S2 specifically: in top bar digging process, face is crushed dregs using mini-excavator takes off and be transported to rear, then make The dregs at rear is transported to outside hole with transport vehicle.
4. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 3, which is characterized in that step In rapid S3.2, it is attached between steel arch-shelf each unit using steel plate, angle steel and bolt.
5. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 4, which is characterized in that step In rapid S4, top bar pneumatically placed concrete uses wet spraying process, and spraying operation segmentation, fragment, layering, from bottom to top, spiral, Successively carry out.
6. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 5, which is characterized in that on It when in step pneumatically placed concrete if any larger calixconcavity, is first filled and led up, guarantees that preliminary bracing is closely connected with scar, make steel arch-shelf and spray anchor Supporting entirety stress is formed, to inhibit surrouding rock deformation.
7. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 5, which is characterized in that step In rapid S5, Blasting Excavation of getting out of a predicament or an embarrassing situation takes the construction principle of " more perforatings, few powder charge, be segmented " more, and according to every circulation face The country rock situation of announcement adjusts borehole arrangement parameter in time, optimizes Blasting Excavation scheme.
8. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 7, which is characterized in that step Rapid S6 specifically: excavate face rear portion using mini-excavator or rollover loading machine and carry out operation of slagging tap getting out of a predicament or an embarrassing situation, and make Dregs is transported to outside hole with transport vehicle.
9. a kind of driving method for weakening city shallow tunnel concussion of blasting according to claim 8, which is characterized in that step In rapid S8, pneumatically placed concrete of getting out of a predicament or an embarrassing situation uses wet spraying process, and spraying operation segmentation, fragment, layering, from bottom to top, spiral, Successively carry out.
CN201910392462.5A 2019-05-13 2019-05-13 A kind of driving method weakening city shallow tunnel concussion of blasting Pending CN110145315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910392462.5A CN110145315A (en) 2019-05-13 2019-05-13 A kind of driving method weakening city shallow tunnel concussion of blasting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910392462.5A CN110145315A (en) 2019-05-13 2019-05-13 A kind of driving method weakening city shallow tunnel concussion of blasting

Publications (1)

Publication Number Publication Date
CN110145315A true CN110145315A (en) 2019-08-20

Family

ID=67595289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910392462.5A Pending CN110145315A (en) 2019-05-13 2019-05-13 A kind of driving method weakening city shallow tunnel concussion of blasting

Country Status (1)

Country Link
CN (1) CN110145315A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113513323A (en) * 2021-08-17 2021-10-19 中铁二局第四工程有限公司 Non-blasting and shock-absorbing blasting combined construction method
CN113565514A (en) * 2021-07-20 2021-10-29 贵州大学 Construction method of railway running under shallow buried subway tunnel in mountainous city

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2515759C1 (en) * 2012-12-13 2014-05-20 федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Южно-Российский государственный технический университет (Новочеркасский политехнический институт)" Heading blast digger
KR20160047228A (en) * 2014-10-22 2016-05-02 박재현 Cross-Section Tunnel Construction Method Using Rock Mass Quality Rating
CN106285691A (en) * 2016-08-05 2017-01-04 中铁工程装备集团有限公司 The method for tunnel construction that a kind of shield formula multi-arm development machine combines with New Austrian Tunneling Method
CN107725057A (en) * 2017-10-24 2018-02-23 济南城建集团有限公司 Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method
KR20180105100A (en) * 2018-09-04 2018-09-27 서동현 Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel
CN109339797A (en) * 2018-09-04 2019-02-15 贵州省公路工程集团有限公司 A kind of shock absorption construction method for tunnel exit with extremely small clear distance
CN109594995A (en) * 2019-01-31 2019-04-09 长安大学 A kind of Support System in Soft Rock Tunnels micro-disturbance machinery branch driving engineering method
CN109611102A (en) * 2019-01-11 2019-04-12 北京市政路桥股份有限公司 A construction method of cold excavation underpass overpass

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2515759C1 (en) * 2012-12-13 2014-05-20 федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Южно-Российский государственный технический университет (Новочеркасский политехнический институт)" Heading blast digger
KR20160047228A (en) * 2014-10-22 2016-05-02 박재현 Cross-Section Tunnel Construction Method Using Rock Mass Quality Rating
CN106285691A (en) * 2016-08-05 2017-01-04 中铁工程装备集团有限公司 The method for tunnel construction that a kind of shield formula multi-arm development machine combines with New Austrian Tunneling Method
CN107725057A (en) * 2017-10-24 2018-02-23 济南城建集团有限公司 Cities and towns Shi Zhi tunnels cantilever tunneling construction engineering method
KR20180105100A (en) * 2018-09-04 2018-09-27 서동현 Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel
CN109339797A (en) * 2018-09-04 2019-02-15 贵州省公路工程集团有限公司 A kind of shock absorption construction method for tunnel exit with extremely small clear distance
CN109611102A (en) * 2019-01-11 2019-04-12 北京市政路桥股份有限公司 A construction method of cold excavation underpass overpass
CN109594995A (en) * 2019-01-31 2019-04-09 长安大学 A kind of Support System in Soft Rock Tunnels micro-disturbance machinery branch driving engineering method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
师延仿: "《高速公路隧道施工技术及控制要点分析》", 《青海交通科技》 *
杨汉勇: "《武广客运专线浏阳河隧道综合施工技术》", 《铁道标准设计》 *
杭甬铁路客运专线有限责任公司: "《杭甬铁路客运专线工程总结(下册)》", 31 December 2014 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113565514A (en) * 2021-07-20 2021-10-29 贵州大学 Construction method of railway running under shallow buried subway tunnel in mountainous city
CN113513323A (en) * 2021-08-17 2021-10-19 中铁二局第四工程有限公司 Non-blasting and shock-absorbing blasting combined construction method

Similar Documents

Publication Publication Date Title
CN110318770A (en) A kind of hazy start tunneling method of vcehicular tunnel
CN109209391A (en) Tiny step excavation method suitable for IV-V grade of country rock of large cross-section tunnel
CN106246201A (en) The excavation in tunnel and karst cave treatment method when small-sized solution cavity is positioned at tunneling surrounding
CN110093928A (en) A kind of foundation pit supporting construction and earth excavation construction method
CN106555593B (en) A kind of big cross section soft rock tunnel is got out of a predicament or an embarrassing situation the construction method of excavation synchronous with inverted arch
CN110318762A (en) Advanced support method in hole at shallow buried covered excavation unsymmetrial loading tunnel roof fall
CN104847362B (en) Ground consisting of hard rock construction method across underground digging in subway station greatly
CN108286442A (en) Excavation method suitable for a Support System in Soft Rock Tunnels quick closure cyclization of two steps
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN102071947A (en) Construction method for soft surrounding rock section of large-span tunnel portal
CN104329095B (en) A kind of existing tunnel Widening Construction method
CN103643958B (en) Hydraulic breaking hammer excavation Modelling of Tunnel Excavation in Soft Rock method
CN110130922A (en) A kind of construction method of line tunnel portal
CN109209392A (en) Loopful excavation method suitable for IV-V grade of country rock of large cross-section tunnel
CN105604576A (en) Soft rock stratum underground excavation large-section tunnel construction method and supporting system
CN109853399A (en) Big section for arch bridge tilts tunnel type skewback structure and its construction method
CN109736827A (en) Excavation method of high-pressure gas expansion-induced cracking in the connection channel of urban subway hard rock strata
CN107975383A (en) Underground chamber tee T intersection excavation supporting construction method
CN103939115B (en) A kind of method of half shallow mining method hangar tunnel and structure
CN110145315A (en) A kind of driving method weakening city shallow tunnel concussion of blasting
CN109057801B (en) Construction Method for Excavation and Support of Double Side Wall Pilot Pit Composite Step Large Section Tunnel
CN109594989A (en) A kind of double trestle rapid constructing methods of three step of Support System in Soft Rock Tunnels detonation simultaneously
JP2001032673A (en) Tunnel work execution method
CN203716156U (en) Pit-in-pit city gate hole type excavation construction structure in deep foundation pit
JP3677698B2 (en) Construction method of tunnel junction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190820

RJ01 Rejection of invention patent application after publication