CN109898819A - A kind of the overhanging tool type scaffold system and its installation method of foldable telescopic - Google Patents

A kind of the overhanging tool type scaffold system and its installation method of foldable telescopic Download PDF

Info

Publication number
CN109898819A
CN109898819A CN201910086572.9A CN201910086572A CN109898819A CN 109898819 A CN109898819 A CN 109898819A CN 201910086572 A CN201910086572 A CN 201910086572A CN 109898819 A CN109898819 A CN 109898819A
Authority
CN
China
Prior art keywords
frame body
main frame
steel girder
cantilever steel
adjustable cantilever
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910086572.9A
Other languages
Chinese (zh)
Other versions
CN109898819B (en
Inventor
苏国活
周子璐
黄硕
管聪聪
程昌宏
郭奇
张伊菡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Original Assignee
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd filed Critical Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority to CN201910086572.9A priority Critical patent/CN109898819B/en
Publication of CN109898819A publication Critical patent/CN109898819A/en
Application granted granted Critical
Publication of CN109898819B publication Critical patent/CN109898819B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/25Greenhouse technology, e.g. cooling systems therefor

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The invention discloses the overhanging tool type scaffold systems and its installation method of a kind of foldable telescopic, the main frame body required including constituting outer edge protection when the huge column of pattern profile line super high-rise building is constructed, adjustable cantilever steel girder, it installs the operating platform, wall-connecting piece and floor, main frame body includes top cross-bar, off-load wirerope, upright bar, hound, platform board, turnover panel, stair and building enclosure, the bottom end of crossbeam is fixedly connected by bolt with the overhanging end of adjustable cantilever steel girder, adjustable cantilever steel girder includes folded section, telescopic segment, anchoring piece and folded piece, the both ends of folded piece are flexibly connected with two folded sections respectively, one end of folded section is connected with telescopic segment, the control of the distance between main frame body and main body is controlled by adjustable cantilever steel girder, realize the alien invasion protection of special-shaped outer contour building, it is practical, together When could be applicable to the super high-rise building of high, the different huge column type formula of different layer.

Description

A kind of the overhanging tool type scaffold system and its installation method of foldable telescopic
Technical field
The present invention relates to connection system for guide rail, the overhanging tool type scaffold system and its peace of specially a kind of foldable telescopic Dress method.
Background technique
With the high speed development of China's economy and science and technology, super high-rise building has been shown as the terrestrial reference in modern city Outstanding effect is increasingly becoming the symbol of countries and cities Musculature stab.Novel facade, need more to innovate applies Work technology is realized.Super High king-tower building structure type generallys use the huge rod structure of Core Walls Structure-outline border, wherein the outline border in king-tower building Difficulty of construction is big for huge column, then it is particularly important to face side operation safety protection problem for the huge column of outline border.
In order to solve the problems, such as the huge column construction safety protection of super high-rise building outline border, the prior art is usually by using climbing The facilities such as frame are protected.But these facilities are climbed extremely difficult, after needing to remove transhipment certainly when facing special-shaped outer contour It assembles again, so efficiency just greatly reduces.
Summary of the invention
The purpose of the present invention is to provide the overhanging tool type scaffold system and its installation method of a kind of foldable telescopic, To solve the above technical problems.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of overhanging tool type scaffold system of foldable telescopic, including main frame body, adjustable cantilever steel girder, installation behaviour Make platform, wall-connecting piece and floor, main frame body includes top cross-bar, off-load wirerope, upright bar, hound, platform board, turnover panel, building Ladder and building enclosure, the bottom end of crossbeam are fixedly connected by bolt with the overhanging end of adjustable cantilever steel girder, and the top of crossbeam is set It is equipped with off-load wirerope, the bottom end vertical welding of crossbeam is fixed with several upright bars, fixes between several upright bars by bolt level There are several platform boards, several hounds are diagonally installed between several platform boards, one end of several platform boards is welded and fixed Have turnover panel, and it is detachable between several platform boards stair are installed, empty three sides of facing of main frame body are equipped with building enclosure, enclose Protection structure is welded and fixed with main frame body;
Adjustable cantilever steel girder includes folded section, telescopic segment, anchoring piece and folded piece, the both ends of folded piece respectively with two Folded section is flexibly connected, and one end of folded section is connected with telescopic segment, is installed the operating platform including railing and springboard, railing by Several plates are welded, and the bottom end of railing is fixedly connected by bolt in adjustable cantilever steel girder, and springboard is laid on adjustable On formula cantilever steel girder;
Wall-connecting piece includes embedded steel tube, horizontal steel tube, the logical crossover sub in side and fastener, and one end of the logical crossover sub in side passes through Bolt is fixedly connected with upright bar, and the other end of the logical crossover sub in side is provided with horizontal steel tube, the equal tight fit in the both ends of horizontal steel tube Fastener is installed, two fasteners pass through bolt respectively and are fixedly connected with the logical crossover sub in side and embedded steel tube.
The quantity of several upright bars is no less than four, and the angle between stair and platform board is 45-60 degree.
The rectangular steel pipe that folded section is 150 × 250 × 10 × 10 by two sections, to fold, is stretched by folded piece doubling The rectangular steel pipe that the section Duan Weiyi is 120 × 200 × 14 × 14, and 120 × 200 × 14 × 14 rectangular steel pipe is to be inserted into 150 × 250 × 10 × 10 rectangular steel pipes are realized flexible.
One end of adjustable cantilever steel girder is anchored at the top of floor, the other end of adjustable cantilever steel girder by bolt with The crossbeam on main frame body top is fixedly connected, and main frame body is connect by wall-connecting piece with main structure.
Main frame body is fixedly connected with adjustable cantilever steel girder by the way that bolt is detachable.
The installation method of the scaffold specifically comprises the following steps:
Main frame body is completed by the first step on ground;
Adjustable cantilever steel girder is fixedly mounted on the top of floor, and the top paving of adjustable cantilever steel girder by second step If installing the operating platform;
The main frame body being completed, is hoisted to the lower section of adjustable cantilever steel girder by third step, and by the top of main frame body It is fixedly connected by bolt with adjustable cantilever steel girder;
One end of wall-connecting piece is fixedly mounted on master after the completion of fixed on adjustable cantilever steel girder by the 4th step, main frame body The other end of one end of frame body, wall-connecting piece is fixedly mounted on the body construction;
One end of off-load wirerope is fixed on the fixed point on crossbeam, off-load steel after the completion of wall-connecting piece is fixed by the 5th step The other end of cord is fixed on the fixed point on next level plate;
6th step, turnover panel is overturn, and is overlapped on floor;
7th step, after This floor construction, dismantling wall-connecting piece, off-load wirerope and main frame body and adjustable overhang steel The supreme work layer flooring of main frame body integral hoisting is repeated second step to the 6th step and operated with week by the connection bolt between beam Turn to use.
Beneficial effects of the present invention:
1, a kind of overhanging tool type scaffold system of foldable telescopic of the present invention is controlled by adjustable cantilever steel girder and is led The alien invasion protection of special-shaped outer contour building is realized in the control of the distance between frame body and main body, practical, while can also be fitted The super high-rise building of high, different huge column type formulas for different layers.
2, a kind of overhanging tool type scaffold system of foldable telescopic of the present invention, can cover three operations after the installation is completed Layer, meets three work layers while constructing, improve work efficiency, reduce costs, while also reducing the work of construction personnel Make intensity.
3, a kind of overhanging tool type scaffold system of foldable telescopic of the present invention, stabilized structure is highly-safe, ties up simultaneously It is also very convenient that shield is got up, and either suffers from very strong superiority from security standpoint or economic angle.
Detailed description of the invention
In order to facilitate the understanding of those skilled in the art, the present invention will be further described below with reference to the drawings.
Fig. 1 is a kind of overhanging tool type scaffold system structure diagram of foldable telescopic of the present invention.
Fig. 2 is a kind of overhanging tool type scaffold system front view of foldable telescopic of the present invention.
Fig. 3 is a kind of overhanging tool type scaffold system right view of foldable telescopic of the present invention.
Fig. 4 is the adjustable overhanging steel beam structure schematic diagram of the present invention.
Fig. 5 is wall-connecting piece structural schematic diagram of the present invention.
In figure: 1, main frame body;101, crossbeam;102, off-load wirerope;103, upright bar;104, hound;105, platform board; 106, turnover panel;107, stair;108, building enclosure;2, adjustable cantilever steel girder;201, folded section;202, telescopic segment;203, anchor Firmware;204, folded piece;3, it installs the operating platform;301, railing;302, springboard;4, wall-connecting piece;401, embedded steel tube;402, water Flat steel pipe;403, the logical crossover sub in side;404, fastener;5, floor.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with embodiment, it is clear that described reality Applying example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is general Logical technical staff all other embodiment obtained without creative efforts belongs to what the present invention protected Range.
Referring to Figure 1, the overhanging tool type scaffold system of a kind of foldable telescopic, including main frame body 1, adjustable overhanging Girder steel 2 installs the operating platform 3, wall-connecting piece 4 and floor 5, constitutes and can satisfy the huge column construction of pattern profile line super high-rise building When outer edge protection requirement, while for huge column construct constructing operation face is provided.
Fig. 2-4 is referred to, main frame body 1 includes top cross-bar 101, off-load wirerope 102, upright bar 103, hound 104, puts down The bottom end of platen 105, turnover panel 106, stair 107 and building enclosure 108, crossbeam 101 passes through bolt and adjustable cantilever steel girder 2 Overhanging end is fixedly connected, and the top of crossbeam 101 is provided with off-load wirerope 102, if the bottom end vertical welding of crossbeam 101 is fixed with Dry upright bar 103, the quantity of several upright bars 103 are no less than four, and are horizontally fixed between several upright bars 103 by bolt several Platform board 105, several hounds 104 are diagonally equipped between several platform boards 105, and several hounds 104 are several flat Platen 105 provides support force, prevents several platform boards 105 from causing to deform because stress is excessive, one end welding of several platform boards 105 Be fixed with turnover panel 106, and it is detachable between several platform boards 105 stair 107 are installed, stair 107 and platform board 105 it Between angle be 45-60 degree, empty three sides of facing of main frame body 1 are equipped with building enclosure 108, and building enclosure 108 and main frame body 1 weld It is fixed.
Adjustable cantilever steel girder 2 includes folded section 201, telescopic segment 202, anchoring piece 203 and folded piece 204, wherein is folded Section 201 realizes folding, folded piece by 204 doubling of folded piece by the rectangular steel pipe that two sections are 150 × 250 × 10 × 10 204 both ends are flexibly connected with two folded sections 201 respectively, and one end of folded section 201 is connected with telescopic segment 202, are stretched The rectangular steel pipe that section 202 is 120 × 200 × 14 × 14 for a section, and 120 × 200 × 14 × 14 rectangular steel pipe can be inserted It is flexible to enter the realization of 150 × 250 × 10 × 10 rectangular steel pipes.
Installing the operating platform 3 includes railing 301 and springboard 302, and railing 301 is welded by several plates, railing 301 Bottom end is fixedly connected by bolt in adjustable cantilever steel girder 2, and springboard 302 is laid on adjustable cantilever steel girder 2.
Fig. 5 is referred to, wall-connecting piece 4 includes embedded steel tube 401, horizontal steel tube 402, the logical crossover sub 403 in side and fastener 404, one end of the logical crossover sub 403 in side is fixedly connected by bolt with upright bar 103, and the other end of the logical crossover sub 403 in side is set It is equipped with horizontal steel tube 402, the equal tight fit in the both ends of horizontal steel tube 402 is equipped with fastener 404, and two fasteners 404 pass through spiral shell respectively Bolt is fixedly connected with square logical crossover sub 403 and embedded steel tube 401, so that horizontal steel tube 402 is in horizontally disposed, and side leads to conversion Connector 403 and embedded steel tube 401 are that horizontal steel tube 402 provides support force.
One end of adjustable cantilever steel girder 2 is anchored at the top of floor 5, and the other end of adjustable cantilever steel girder 2 passes through spiral shell Bolt is fixedly connected with the crossbeam 101 on 1 top of main frame body, and main frame body 1 is connect by wall-connecting piece 4 with main structure.
Main frame body 1 is fixedly connected with adjustable cantilever steel girder 2 by the way that bolt is detachable, and main frame body 1 can pass through tower Whole promotion is hung, adjustable cantilever steel girder 2 can be transported by construction elevator to next construction layer.
By adjusting the overhanging end length of adjustable cantilever steel girder 2, realize that protective frame, can with respect to the distance at building edge Mode cantilever steel girder 2 adjusts overhanging segment length problem by way of folding and stretching, while also solving the transport of cantilever steel girder Problem.
The installation method of the scaffold specifically comprises the following steps:
Main frame body 1 is completed by the first step on ground;
Adjustable cantilever steel girder 2 is fixedly mounted on the top of floor 5, and the top of adjustable cantilever steel girder 2 by second step Laying installs the operating platform 3;
The main frame body 1 being completed, is hoisted to the lower section of adjustable cantilever steel girder 2 by third step, and by the top of main frame body 1 End is fixedly connected by bolt with adjustable cantilever steel girder 2;
One end of wall-connecting piece 4 is fixedly mounted on by the 4th step, main frame body 1 after the completion of fixed on adjustable cantilever steel girder 2 The other end of one end of main frame body 1, wall-connecting piece 4 is fixedly mounted on the body construction;
One end of off-load wirerope 102 is fixed on the fixation on crossbeam 101 after the completion of wall-connecting piece 4 is fixed by the 5th step Point, the other end of off-load wirerope 102 are fixed on the fixed point on next level plate 5;
6th step overturns turnover panel 106, and is overlapped on floor 5;
7th step, after This floor construction, dismantling wall-connecting piece 4, off-load wirerope 102 and main frame body 1 with it is adjustable The supreme work layer flooring of 1 integral hoisting of main frame body is repeated second step to the 6th step by the connection bolt between cantilever steel girder 2 Operation, is used in turn to fast implement.
In the use of the present invention, folded section 201 passes through folding by the rectangular steel pipe that two sections are 150 × 250 × 10 × 10 204 doubling of overlapping piece, which is realized, to be folded, and the both ends of folded piece 204 are flexibly connected with two folded sections 201 respectively, and the one of folded section 201 It holds and is connected with telescopic segment 202, the rectangular steel pipe that telescopic segment 202 is 120 × 200 × 14 × 14 for a section, and 120 × 200 × 14 × 14 rectangular steel pipe be inserted into 150 × 250 × 10 × 10 rectangular steel pipes realize it is flexible, and then by adjusting can The overhanging end length of mode cantilever steel girder 2 realizes distance of the protective frame with respect to building edge.Adjustable cantilever steel girder 2 passes through It folds and flexible mode adjusts overhanging segment length problem, while also solving the transportation problem of cantilever steel girder.
Present invention disclosed above preferred embodiment is only intended to help to illustrate the present invention.There is no detailed for preferred embodiment All details are described, are not limited the invention to the specific embodiments described.Obviously, according to the content of this specification, It can make many modifications and variations.These embodiments are chosen and specifically described to this specification, is in order to better explain the present invention Principle and practical application, so that skilled artisan be enable to better understand and utilize the present invention.The present invention is only It is limited by claims and its full scope and equivalent.

Claims (6)

1. a kind of overhanging tool type scaffold system of foldable telescopic, including main frame body (1), adjustable cantilever steel girder (2), peace Fill operating platform (3), wall-connecting piece (4) and floor (5), main frame body (1) include top cross-bar (101), off-load wirerope (102), Upright bar (103), hound (104), platform board (105), turnover panel (106), stair (107) and building enclosure (108), crossbeam (101) bottom end is fixedly connected by bolt with the overhanging end of adjustable cantilever steel girder (2), and the top of crossbeam (101) is provided with Off-load wirerope (102), the bottom end vertical welding of crossbeam (101) are fixed with several upright bars (103), between several upright bars (103) It is horizontally fixed with several platform boards (105) by bolt, several hounds is diagonally installed between several platform boards (105) (104), one end of several platform boards (105) is welded with turnover panel (106), and detachable between several platform boards (105) Be equipped with stair (107), empty three sides of facing of main frame body (1) are equipped with building enclosure (108), building enclosure (108) and body frame Body (1) is welded and fixed;
Adjustable cantilever steel girder (2) includes folded section (201), telescopic segment (202), anchoring piece (203) and folded piece (204), folding The both ends of overlapping piece (204) are flexibly connected with two folded sections (201) respectively, and one end of folded section (201) is connected with flexible Section (202), installing the operating platform (3) includes railing (301) and springboard (302), and railing (301) is welded by several plates, The bottom end of railing (301) is fixedly connected by bolt in adjustable cantilever steel girder (2), and springboard (302) is laid on adjustable suspension It chooses on girder steel (2);
Wall-connecting piece (4) includes embedded steel tube (401), horizontal steel tube (402), side logical crossover sub (403) and fastener (404), side The one end of logical crossover sub (403) is fixedly connected by bolt with upright bar (103), and the other end of side logical crossover sub (403) is set It is equipped with horizontal steel tube (402), the equal tight fit in both ends of horizontal steel tube (402) is equipped with fastener (404), two fasteners (404) point Not Tong Guo bolt be fixedly connected with side logical crossover sub (403) and embedded steel tube (401).
2. a kind of overhanging tool type scaffold system of foldable telescopic according to claim 1, which is characterized in that several The quantity of the upright bar (103) is no less than four, and the angle between stair (107) and platform board (105) is 45-60 degree.
3. a kind of overhanging tool type scaffold system of foldable telescopic according to claim 1, which is characterized in that described The rectangular steel pipe that folded section (201) section You Lianggen is 150 × 250 × 10 × 10, to fold, is stretched by folded piece (204) doubling Contracting section (202) be a section be 120 × 200 × 14 × 14 rectangular steel pipe, and 120 × 200 × 14 × 14 rectangular steel pipe with It is inserted into 150 × 250 × 10 × 10 rectangular steel pipes and realizes and stretch.
4. a kind of overhanging tool type scaffold system of foldable telescopic according to claim 1, which is characterized in that described One end of adjustable cantilever steel girder (2) is anchored at the top of floor (5), and the other end of adjustable cantilever steel girder (2) passes through bolt It is fixedly connected with the crossbeam (101) on main frame body (1) top, main frame body (1) is connect by wall-connecting piece (4) with main structure.
5. a kind of overhanging tool type scaffold system of foldable telescopic according to claim 1, which is characterized in that described Main frame body (1) is fixedly connected with adjustable cantilever steel girder (2) by the way that bolt is detachable.
6. a kind of installation method of the overhanging tool type scaffold system of foldable telescopic, which is characterized in that the installation of the system Method specific steps include:
Main frame body (1) is completed by the first step on ground;
Adjustable cantilever steel girder (2) is fixedly mounted on the top of floor (5), and the top of adjustable cantilever steel girder (2) by second step End is laid with and installs the operating platform (3);
The main frame body being completed (1), is hoisted to the lower section of adjustable cantilever steel girder (2) by third step, and by main frame body (1) Top is fixedly connected by bolt with adjustable cantilever steel girder (2);
One end of wall-connecting piece (4) is fixedly mounted after the completion of fixed on adjustable cantilever steel girder (2) for 4th step, main frame body (1) In one end of main frame body (1), the other end of wall-connecting piece (4) is fixedly mounted on the body construction;
One end of off-load wirerope (102) is fixed on the fixation on crossbeam (101) after the completion of wall-connecting piece (4) is fixed by the 5th step Point, the other end of off-load wirerope (102) are fixed on the fixed point on next level plate (5);
Turnover panel (106) are overturn, and are overlapped on floor (5) by the 6th step;
7th step, after This floor construction, dismantling wall-connecting piece (4), off-load wirerope (102) and main frame body (1) with it is adjustable The supreme work layer flooring of main frame body (1) integral hoisting is repeated second step extremely by the connection bolt between formula cantilever steel girder (2) 6th step is operated to be used in turn.
CN201910086572.9A 2019-01-29 2019-01-29 Foldable telescopic overhanging tool type scaffold system and installation method thereof Active CN109898819B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910086572.9A CN109898819B (en) 2019-01-29 2019-01-29 Foldable telescopic overhanging tool type scaffold system and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910086572.9A CN109898819B (en) 2019-01-29 2019-01-29 Foldable telescopic overhanging tool type scaffold system and installation method thereof

Publications (2)

Publication Number Publication Date
CN109898819A true CN109898819A (en) 2019-06-18
CN109898819B CN109898819B (en) 2023-08-18

Family

ID=66944406

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910086572.9A Active CN109898819B (en) 2019-01-29 2019-01-29 Foldable telescopic overhanging tool type scaffold system and installation method thereof

Country Status (1)

Country Link
CN (1) CN109898819B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359693A (en) * 2019-06-24 2019-10-22 中国五冶集团有限公司 A kind of boat scaffold structure
CN110792251A (en) * 2019-10-28 2020-02-14 山东天成钢结构有限公司 Remove convenient work platform that encorbelments
CN111502227A (en) * 2020-04-30 2020-08-07 江苏中南建筑产业集团有限责任公司 Operating platform and construction method for building peripheral constructional column construction
CN112779986A (en) * 2020-12-30 2021-05-11 浙江新曙光建设有限公司 Cantilever frame structure and mounting method thereof
CN113928505A (en) * 2021-12-06 2022-01-14 江南造船(集团)有限责任公司 Reversible platform for ship building
CN113944313A (en) * 2021-11-03 2022-01-18 上海建工五建集团有限公司 Overhanging section steel jacking limiting device, overhanging steel platform and construction method thereof
CN114482515A (en) * 2022-01-10 2022-05-13 中国建筑第八工程局有限公司 Comprehensive attachment device for nonstandard super high floors of super high-rise building
CN114737738A (en) * 2022-03-22 2022-07-12 天长市安骄金属制品科技有限公司 Sliding type extensible operating table for scaffold
CN114809699A (en) * 2022-05-11 2022-07-29 北京市第三建筑工程有限公司 Construction method of assembly type outer facade enclosure system for reconstruction of upper part of super high-rise building
CN115977373A (en) * 2022-12-27 2023-04-18 上海建工五建集团有限公司 Enclosure structure and construction method of a ring-type scaffolding

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0419250A2 (en) * 1989-09-20 1991-03-27 John Clement Preston A construction landing platform for installation in a building under construction
JP2010090546A (en) * 2008-10-03 2010-04-22 Asahi Kasei Homes Co Suspended working floor
CN201865325U (en) * 2010-08-31 2011-06-15 龙海燕 Foldable scaffold for decoration
CN105239765A (en) * 2015-10-26 2016-01-13 中国建筑股份有限公司 Foldable multifunctional overhanging unloading platform
CN205558329U (en) * 2016-04-13 2016-09-07 上海建工二建集团有限公司 Foldable throwing of prefabricated assembly type structure net
CN206108786U (en) * 2016-08-31 2017-04-19 江苏能建机电实业集团有限公司 Boiler furnace maintenance platform of hoisting point is strengthened to aluminium system of adoption
CN210002931U (en) * 2019-01-29 2020-01-31 中建四局第六建筑工程有限公司 tool type protection system for telescopic adjustment of construction of super high-rise outer frame column

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0419250A2 (en) * 1989-09-20 1991-03-27 John Clement Preston A construction landing platform for installation in a building under construction
JP2010090546A (en) * 2008-10-03 2010-04-22 Asahi Kasei Homes Co Suspended working floor
CN201865325U (en) * 2010-08-31 2011-06-15 龙海燕 Foldable scaffold for decoration
CN105239765A (en) * 2015-10-26 2016-01-13 中国建筑股份有限公司 Foldable multifunctional overhanging unloading platform
CN205558329U (en) * 2016-04-13 2016-09-07 上海建工二建集团有限公司 Foldable throwing of prefabricated assembly type structure net
CN206108786U (en) * 2016-08-31 2017-04-19 江苏能建机电实业集团有限公司 Boiler furnace maintenance platform of hoisting point is strengthened to aluminium system of adoption
CN210002931U (en) * 2019-01-29 2020-01-31 中建四局第六建筑工程有限公司 tool type protection system for telescopic adjustment of construction of super high-rise outer frame column

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
应惠清: "土木工程施工 上 第3版", 上海:同济大学出版社, pages: 207 - 208 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359693B (en) * 2019-06-24 2024-04-09 中国五冶集团有限公司 Suspension type scaffold structure
CN110359693A (en) * 2019-06-24 2019-10-22 中国五冶集团有限公司 A kind of boat scaffold structure
CN110792251A (en) * 2019-10-28 2020-02-14 山东天成钢结构有限公司 Remove convenient work platform that encorbelments
CN111502227A (en) * 2020-04-30 2020-08-07 江苏中南建筑产业集团有限责任公司 Operating platform and construction method for building peripheral constructional column construction
CN112779986A (en) * 2020-12-30 2021-05-11 浙江新曙光建设有限公司 Cantilever frame structure and mounting method thereof
CN113944313A (en) * 2021-11-03 2022-01-18 上海建工五建集团有限公司 Overhanging section steel jacking limiting device, overhanging steel platform and construction method thereof
CN113928505A (en) * 2021-12-06 2022-01-14 江南造船(集团)有限责任公司 Reversible platform for ship building
CN114482515A (en) * 2022-01-10 2022-05-13 中国建筑第八工程局有限公司 Comprehensive attachment device for nonstandard super high floors of super high-rise building
CN114737738B (en) * 2022-03-22 2023-09-01 天长市安骄金属制品科技有限公司 Sliding extensible operation table for scaffold
CN114737738A (en) * 2022-03-22 2022-07-12 天长市安骄金属制品科技有限公司 Sliding type extensible operating table for scaffold
CN114809699A (en) * 2022-05-11 2022-07-29 北京市第三建筑工程有限公司 Construction method of assembly type outer facade enclosure system for reconstruction of upper part of super high-rise building
CN114809699B (en) * 2022-05-11 2023-11-17 北京市第三建筑工程有限公司 Construction method of assembled outer elevation enclosure system for transformation of upper part of super high-rise building
CN115977373A (en) * 2022-12-27 2023-04-18 上海建工五建集团有限公司 Enclosure structure and construction method of a ring-type scaffolding

Also Published As

Publication number Publication date
CN109898819B (en) 2023-08-18

Similar Documents

Publication Publication Date Title
CN109898819A (en) A kind of the overhanging tool type scaffold system and its installation method of foldable telescopic
CN104196222B (en) The suspension scaffold of tools type section steel builder's jack
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN101397844B (en) Construction method of special section steel concrete composite structure inclined wall mould base engineering
CN103362297B (en) A kind of attached lift scaffold constructure scheme
CN206513052U (en) A kind of spring layer support and hydraulic pressure spring layer climbing system
CN210002931U (en) tool type protection system for telescopic adjustment of construction of super high-rise outer frame column
CN103741964A (en) Rake type lifting frame and dismantling method for reinforced concrete groove-shaped roof boards
CN209568359U (en) A kind of falsework for the construction of outer-enwraped type Guard fence base
CN208363666U (en) It is a kind of for build face side construction safety protection frame
CN206987431U (en) One kind enters to cheat assembled ladder cage
CN117052099A (en) Assembled steel ladder operation scaffold and construction process thereof
CN201065638Y (en) Suspended steel structure lower hanging handling frame
CN212613654U (en) Curtain wall construction system suitable for high-rise building with special-shaped giant columns
CN204850515U (en) Steel construction faces limit protector
CN104818859B (en) The installation method of orbit traffic overhead station operation platform
CN204038917U (en) Detachable external hanging type operating platform
CN203394008U (en) Suspension type hanging bracket used on plane truss
CN104195954B (en) Overhead column erection without scaffolding platform and erection method thereof
CN103306202B (en) Steel panel used in fabricated Bailey truss in matching manner
CN206189834U (en) Double -deck integrally lift up formula operation platform of elevartor shaft
CN207794582U (en) A kind of hanging large span combination support for shuttering
CN205822800U (en) High-altitude concrete conveying device
CN207003972U (en) Movable construction operation platform
CN207314793U (en) Operating platform between a kind of regularization precast stair

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 230000 building 3, 262 Heping Road, Yaohai District, Hefei City, Anhui Province

Patentee after: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau

Address before: 20th Floor, Zhongjian Building, No. 263 Heping Road, Yaohai District, Hefei City, Anhui Province, 230000

Patentee before: CHINA CONSTRUCTION 4TH ENGINEERING BUREAU, 6TH Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231020

Address after: 5th Floor, Building B, Guangzhou Information Port, No. 16 Keyun Road, Tianhe District, Guangzhou City, Guangdong Province, 510630

Patentee after: CHINA CONSTRUCTION FOURTH ENGINEERING DIVISION CORP.,LTD.

Patentee after: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau

Address before: 230000 building 3, 262 Heping Road, Yaohai District, Hefei City, Anhui Province

Patentee before: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau