CN103741964A - Rake type lifting frame and dismantling method for reinforced concrete groove-shaped roof boards - Google Patents

Rake type lifting frame and dismantling method for reinforced concrete groove-shaped roof boards Download PDF

Info

Publication number
CN103741964A
CN103741964A CN201310752178.7A CN201310752178A CN103741964A CN 103741964 A CN103741964 A CN 103741964A CN 201310752178 A CN201310752178 A CN 201310752178A CN 103741964 A CN103741964 A CN 103741964A
Authority
CN
China
Prior art keywords
roof panel
roof
rake
row
supports
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310752178.7A
Other languages
Chinese (zh)
Other versions
CN103741964B (en
Inventor
陈超
吴荣善
曾元智
陈梦逢
潘子祥
涂修利
付强
李刚
周俐
吴大顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pangang Group Engineering Technology Co Ltd
Original Assignee
Pangang Group Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Engineering Technology Co Ltd filed Critical Pangang Group Engineering Technology Co Ltd
Priority to CN201310752178.7A priority Critical patent/CN103741964B/en
Publication of CN103741964A publication Critical patent/CN103741964A/en
Application granted granted Critical
Publication of CN103741964B publication Critical patent/CN103741964B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a rake type lifting frame and a dismantling method for reinforced concrete groove-shaped roof boards. The dismantling method for the reinforced concrete groove-shaped roof boards can conveniently dismantle the roof boards. The rake type lifting frame comprises two base supports, two inclined supports, two vertical supports and a plurality of horizontal supports; the two base supports which are horizontally arranged in a mutually parallel mode are arranged on external side at opposite two ends in the length direction of the roof boards to be dismantled; one ends of the two inclined supports and one ends of the two base supports are fixed; one ends of the two inclined supports upwardly extend obliquely in a mutually parallel mode; the length of the two vertical supports is identical; the two vertical supports are fixedly connected between the fixed base supports and inclined supports to support the inclined supports; the plurality of horizontal supports are connected between the two base supports and the two inclined supports; portions of the two inclined supports, which upwardly extend obliquely from connecting points of the vertical supports, are provided with two manual hoists which are used for lifting the roof boards; the horizontal distance between the two manual hoists which are arranged on the same inclined support is less than the width of the rood boards.

Description

耙式吊装架和钢筋混凝土槽形屋面板的拆除方法Dismantling method of rake hoisting frame and reinforced concrete trough roof panel

技术领域technical field

本发明涉及屋面板拆除施工领域,具体地说,本发明涉及一种耙式吊装架和利用该耙式吊装架进行的钢筋混凝土槽形屋面板的拆除方法。The invention relates to the field of roof panel removal construction, in particular to a rake-type hoisting frame and a method for removing reinforced concrete trough-shaped roof panels using the rake-type hoisting frame.

背景技术Background technique

目前,在对钢筋混凝土屋面板进行拆除时,主要采用直接破碎方式或者自行式吊车配合方式拆除。这两种拆除的方式都需要停产,屋面附件的生产设备需要停机,并且将这些生产设备移走,以避免影响屋面板的正常拆除或者遭到破坏,使得屋面板的拆除过程复杂,且耗时较长。At present, when removing reinforced concrete roof slabs, direct crushing or self-propelled cranes are mainly used for demolition. These two demolition methods need to stop production, and the production equipment of the roof accessories needs to be shut down, and these production equipment should be removed to avoid affecting the normal demolition or damage of the roof panels, making the roof panel removal process complicated and time-consuming longer.

在某些情况下,受到现场施工条件或工艺的限制,可能大型的汽车吊和塔吊等吊装设备无法设置,导致屋面板的拆除较为困难。In some cases, due to the limitation of on-site construction conditions or workmanship, it may not be possible to set up large-scale truck cranes and tower cranes and other hoisting equipment, making it difficult to remove the roof panels.

发明内容Contents of the invention

本发明的目的在于提供一种耙式吊装架和钢筋混凝土槽形屋面板的拆除方法,以在施工场地受限的情况下,完成屋面板的拆除,并减少拆除时间,提高作业效率。The object of the present invention is to provide a method for dismantling a rake hoisting frame and a reinforced concrete trough roof panel, so as to complete the dismantling of the roof panel when the construction site is limited, reduce the demolition time, and improve the working efficiency.

为了实现上述目的,根据本发明的一方面,提供了一种耙式吊装架,用于拆除钢筋混凝土槽形屋面板,所述耙式吊装架包括:两个底支架,彼此平行地水平设置,并且所述两个底支架位于待拆除的屋面板的长度方向的相对两端的外侧;两个斜支架,所述两个斜支架的一端分别与所述两个底支架的一端固定,并且彼此平行地倾斜地向上延伸;两个竖直支架,长度相同,并且分别固定地连接在相固定的底支架和斜支架之间,以支撑所述斜支架;多个横支架,连接在所述两个底支架之间以及所述两个斜支架之间。其中,在每个斜支架的从与各自竖直支架的连接点处斜向上延伸的部分上均设置有两个手动葫芦,用于吊装在屋面板的四个角处,以提升屋面板,并且被设置在同一斜支架上的两个手动葫芦之间的水平距离均小于屋面板的宽度。优选地,所述斜支架与水平面之间的角度为30°-50°。In order to achieve the above object, according to one aspect of the present invention, a rake-type hoisting frame is provided for removing reinforced concrete trough-shaped roof panels, the rake-type hoisting frame includes: two bottom brackets, horizontally arranged parallel to each other, And the two bottom brackets are located outside the opposite ends of the length direction of the roof panel to be removed; two oblique brackets, one end of the two oblique brackets are respectively fixed to one end of the two bottom brackets, and parallel to each other Extend upward obliquely; two vertical supports have the same length and are respectively fixedly connected between the fixed bottom support and the inclined support to support the inclined support; a plurality of horizontal supports are connected between the two between the bottom brackets and between the two inclined brackets. Wherein, two manual hoists are arranged on the part extending obliquely upward from the connection point with the respective vertical support of each inclined support, for hoisting at the four corners of the roof panel to lift the roof panel, and The horizontal distance between the two manual hoists arranged on the same inclined support is smaller than the width of the roof panel. Preferably, the angle between the inclined support and the horizontal plane is 30°-50°.

优选地,所述底支架、所述竖直支架和所述斜支架均为工字钢。Preferably, the bottom bracket, the vertical bracket and the oblique bracket are all I-shaped steel.

根据本发明的另一方面,还提供了一种钢筋混凝土槽形屋面板的拆除方法,所述拆除方法包括:在待拆除的屋面上安装一列龙门吊装架,在所述一列龙门吊装架的顶支架上安装沿所述一列龙门吊装架延伸的轨道梁,在所述轨道梁上安装卷扬机和电动葫芦;对所述一列龙门吊装架与屋面之间的连接处进行包边焊接;拆除屋面的一块待拆除屋面板上的防水层、找平层、天窗挡水窗,并清除屋面板之间的填料;切割屋面板与屋架梁之间的钢结构连接件;将上述耙式吊装架安装在屋面板处;在耙式吊装架下方铺设滑道,所述滑道与所述一列龙门吊装架垂直并延伸至所述一列龙门吊装架下方;利用耙式吊装架的四个手动葫芦提升屋面板;调节四个手动葫芦,将屋面板放置到滑道上;利用卷扬机将屋面板沿滑道牵引到所述一列龙门吊装架下方;利用所述一列龙门吊装架将屋面板沿滑道牵引至所述一列龙门吊装架的一端;利用电动葫芦将屋面板放置到预定位置。According to another aspect of the present invention, there is also provided a method for removing reinforced concrete trough roof panels, the removal method comprising: installing a row of gantry hoisting frames on the roof to be removed; A track beam extending along the row of gantry hoisting frames is installed on the bracket, and a hoist and an electric hoist are installed on the track beam; edge welding is performed on the connection between the row of gantry hoisting frames and the roof; a piece of the roof is removed The waterproof layer, leveling layer and skylight water retaining window on the roof slab are to be removed, and the filler between the roof slabs is removed; the steel structure connectors between the roof slab and the roof truss beam are cut; the above-mentioned rake hoisting frame is installed on the roof slab place; lay a slideway under the rake-type hoisting frame, the slideway is perpendicular to the row of gantry hoisting frames and extends to the bottom of the row of gantry hoisting frames; use four manual hoists of the rake-type hoisting frame to lift the roof panel; adjust Four manual hoists, place the roof panel on the slideway; use the winch to pull the roof panel along the slideway to the bottom of the row of gantry hoisting frames; use the row of gantry hoisting frames to pull the roof panel along the slideway to the row of gantry cranes One end of the rack; use the electric hoist to place the roof panel to the predetermined position.

优选地,利用四个手动葫芦将屋面板提升一段距离,缓慢放下前方两个手动葫芦同时缓慢提升后方两个手动葫芦,使得屋面板朝向耙式吊装架下方的滑道转移,当屋面板的至少2/3投影在滑道上时,利用所述四个手动葫芦将屋面板放置在滑道上。Preferably, use four manual hoists to lift the roof panel for a certain distance, slowly lower the front two manual hoists while slowly lifting the rear two manual hoists, so that the roof panel moves towards the slideway below the rake hoisting frame, when the roof panel is at least When 2/3 is projected on the slideway, utilize the four manual hoists to place the roof panel on the slideway.

优选地,在屋面板的后部开设有牵引孔,以与卷扬机的牵引绳连接而使得屋面板被卷扬机牵引至所述一列龙门吊装架下方。Preferably, a traction hole is opened at the rear of the roof panel to connect with the traction rope of the hoist so that the roof panel is pulled by the hoist to the bottom of the row of gantry hoisting frames.

优选地,所述一列龙门吊装架的相邻两个龙门吊装架之间的距离大于屋面板的长度。Preferably, the distance between two adjacent gantry hoisting frames of the row of gantry hoisting frames is greater than the length of the roof panel.

通过本发明所提供的耙式吊装架和拆除方法,能够在屋面拆除场地较小并受限,使得大型吊车无法利用的情况下,完成钢筋混凝土槽形屋面板的拆除作业,并且能够缩短拆除时间,提高作业效率和安全性。With the rake-type hoisting frame and removal method provided by the present invention, the demolition of reinforced concrete trough-shaped roof panels can be completed and the demolition time can be shortened when the roof demolition site is small and limited so that large cranes cannot be used , Improve work efficiency and safety.

附图说明Description of drawings

图1是根据本发明的实施例的耙式吊装架的结构示意图;Fig. 1 is the structural representation of the rake type suspension frame according to the embodiment of the present invention;

图2是根据本发明的实施例的龙门吊装架的结构示意图;Fig. 2 is a schematic structural view of a gantry hoisting frame according to an embodiment of the present invention;

图3是根据本发明的实施例的龙门吊装架与屋面之间的焊接状态示意图;Fig. 3 is a schematic diagram of the welding state between the gantry hoisting frame and the roof according to an embodiment of the present invention;

图4是根据本发明的实施例的耙式吊装架和一列龙门吊装架的布置示意图;Fig. 4 is a schematic layout diagram of a rake type hoisting frame and a column of gantry hoisting frames according to an embodiment of the present invention;

图5是根据本发明的实施例的利用耙式吊装架提升屋面板的状态示意图;Fig. 5 is a schematic diagram of the state of using a rake hoisting frame to lift a roof panel according to an embodiment of the present invention;

图6是根据本发明的实施例的利用耙式吊装架将屋面板放置到滑道上的状态示意图;Fig. 6 is a schematic diagram of the state of placing the roof panel on the slideway using a rake hoisting frame according to an embodiment of the present invention;

图7是根据本发明的实施例的屋面板平面牵引过程的示意图。Fig. 7 is a schematic diagram of the plane pulling process of the roof panel according to the embodiment of the present invention.

具体实施方式Detailed ways

为了使本领域技术人员能够更好的理解本发明,下面结合附图对本发明的具体实施例进行详细描述。In order to enable those skilled in the art to better understand the present invention, specific embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings.

图1是根据本发明的实施例的耙式吊装架的结构示意图。Fig. 1 is a schematic structural view of a rake hoisting frame according to an embodiment of the present invention.

参照图1,根据本发明的一方面,提供了一种用于拆除钢筋混凝土槽形屋面板(以下,简称屋面板)的耙式吊装架10,该耙式吊装架10包括:两个底支架101,彼此平行地水平设置,并且这两个底支架101位于待拆除的屋面板W的长度方向(与底支架101垂直)的相对两端的外侧,即,两个底支架101之间的距离要稍长于屋面板W的长度;两个斜支架102,两个斜支架102的一端分别与两个底支架101的一端固定,并且彼此平行地倾斜地向上延伸;两个竖直支架103,长度相同,并且分别固定地连接在相固定的底支架101和斜支架102之间,以支撑斜支架102;多个横支架104,连接在两个底支架101之间以及两个斜支架102之间,以加强耙式吊装架10的强度。此外,在两个底支架101和两个斜支架102之间还可以连接多个支架,以进一步加强耙式吊装架10的强度。Referring to Fig. 1, according to one aspect of the present invention, a rake-type hoisting frame 10 for removing reinforced concrete trough roof panels (hereinafter referred to as roof panels) is provided, and the rake-type hoisting frame 10 includes: two bottom brackets 101, arranged horizontally parallel to each other, and these two bottom brackets 101 are located outside the opposite ends of the length direction (perpendicular to the bottom brackets 101) of the roof panel W to be removed, that is, the distance between the two bottom brackets 101 should be Slightly longer than the length of the roof panel W; two oblique brackets 102, one end of the two oblique brackets 102 are respectively fixed to one end of the two bottom brackets 101, and extend upwards obliquely parallel to each other; two vertical brackets 103, the same length , and are respectively fixedly connected between the fixed bottom bracket 101 and the oblique bracket 102 to support the oblique bracket 102; a plurality of horizontal brackets 104 are connected between the two bottom brackets 101 and the two oblique brackets 102, To strengthen the intensity of the rake type suspension frame 10. In addition, multiple brackets can be connected between the two bottom brackets 101 and the two oblique brackets 102 to further strengthen the strength of the rake suspension frame 10 .

在每个斜支架102的从与各自竖直支架103的连接点处斜向上延伸的部分上均设置有两个手动葫芦105(见图5、图6),用于吊装在屋面板W的四个角处,以提升屋面板W,并且被设置在同一斜支架102上的两个手动葫芦105之间的水平距离均小于屋面板的宽度,如图6所示。具体地,在每个斜支架102上,两个手动葫芦105可分别连接在斜支架102的延伸出去的一端以及该斜支架102与竖直支架103的连接处。Two manual hoists 105 (see Fig. 5 and Fig. 6 ) are arranged on the part of each oblique support 102 that extends obliquely upward from the connection point with the respective vertical support 103, for hoisting on the four sides of the roof panel W. corner, to lift the roof panel W, and the horizontal distance between the two manual hoists 105 arranged on the same inclined support 102 is less than the width of the roof panel, as shown in Figure 6. Specifically, on each slanting support 102 , two manual hoists 105 can be respectively connected to the extended end of the slanting support 102 and the joint between the slanting support 102 and the vertical support 103 .

斜支架102的与水平面之间的倾斜角度可以大约为30°-50°,优选地,可大约为45°。The inclination angle between the inclined bracket 102 and the horizontal plane may be approximately 30°-50°, preferably approximately 45°.

耙式吊装架10上的每个支架均可以采用工字钢制成。例如,可以采用I25#工字钢制成。此外,对于底支架101、竖直支架103和斜支架102而言,由于在起吊屋面板W时,其受到的拉力较大,这些支架可以采用强度更大的工字钢制成,以避免支架在起吊时发生弯曲变形或者倾斜。Each support on the rake type suspension frame 10 can adopt I-beam to make. For example, it can be made of I25 # I-beam. In addition, for the bottom bracket 101, the vertical bracket 103 and the oblique bracket 102, since the roof panel W is subjected to a relatively large tensile force when lifting the roof panel W, these brackets can be made of stronger I-beams to avoid the Bending deformation or tilting occurs during lifting.

根据本发明的另一方面,还提供了一种钢筋混凝土槽形屋面板的拆除方法,下面参照图2至图7对本发明的拆除方法进行详细描述。According to another aspect of the present invention, a method for dismantling a reinforced concrete channel roof panel is also provided, and the dismantling method of the present invention will be described in detail below with reference to FIGS. 2 to 7 .

在待拆除的屋面(即,屋顶)上安装一列龙门吊装架20,该一列龙门吊装架20由多个龙门吊装架按排布置而成。每个龙门吊装架均包括两个立柱203和连接在两个立柱203之间的顶支架202,如图2所示,在所有龙门吊装架的顶支架202上贯穿地连接有轨道梁70,在该轨道梁70上挂设有电动葫芦201和卷扬机204,该电动葫芦201和卷扬机204可以沿轨道梁70运动,以便运送屋面板W。当然,卷扬机204也可以采用其他方式安装,例如,如图7中所示,只要能够牵引屋面板W即可。A row of gantry hoisting frames 20 is installed on the roof to be removed (that is, the roof), and the row of gantry hoisting frames 20 is formed by arranging a plurality of gantry hoisting frames in a row. Each gantry hoisting frame all comprises two columns 203 and the top bracket 202 that is connected between the two columns 203, as shown in Figure 2, on the top bracket 202 of all gantry hoisting frames, is connected with track beam 70 penetratingly, in An electric hoist 201 and a hoist 204 are hung on the track beam 70 , and the electric hoist 201 and the hoist 204 can move along the track beam 70 to transport the roof panel W. Of course, the hoist 204 can also be installed in other ways, for example, as shown in FIG. 7 , as long as it can pull the roof panel W.

例如,在本发明的实施例中,对于跨距为30m的屋面,可每隔6m便设置一个龙门吊装架,一共设置72个龙门吊装架,从屋面的一端延伸至另一端。此外,可以采用I16#工字钢制作立柱203,采用I25a#工字钢做顶支架202,采用I32a#工字钢作为轨道梁70,所挂设的电动葫芦201为5t电动葫芦,卷扬机204可以为1t卷扬机。For example, in the embodiment of the present invention, for a roof with a span of 30m, a gantry hoisting frame can be provided every 6m, and a total of 72 gantry hoisting frames are provided, extending from one end of the roof to the other end. In addition, I16 # I-beam can be used to make the column 203, I25a # I-beam can be used as the top bracket 202, and I32a # I-beam can be used as the track beam 70. The electric hoist 201 hung is a 5t electric hoist, and the hoist 204 can be It is a 1t hoist.

需要说明的是,为了方便后续屋面板被牵引至该列龙门吊装架20之下,相邻两个龙门吊装架20之间的距离最好大于每个屋面板的长度,以避免在牵引过程中对屋面板的角度进行调节,节省拆除时间。It should be noted that, in order to facilitate subsequent roof panels to be pulled under the row of gantry hoisting frames 20, the distance between two adjacent gantry hoisting frames 20 is preferably greater than the length of each roof panel, so as to avoid the Adjust the angle of the roof panel to save demolition time.

所述一列龙门吊装架20可以安装在屋面边缘,在进行安装时,可对每个龙门吊装架与屋面之间进行包边焊接30,如图3所示,以加强每个龙门吊装架与屋面之间的连接强度,防止龙门吊装架20在进行作业时移动或倾翻,并且能够起到保护屋架梁的作用。例如,可以采用δ=20mm包边焊接。The row of gantry hoisting frames 20 can be installed on the edge of the roof. During installation, edge welding 30 can be performed between each gantry hoisting frame and the roof, as shown in Figure 3, to strengthen the connection between each gantry hoisting frame and the roof. The strength of the connection between them prevents the gantry hoisting frame 20 from moving or tipping when performing operations, and can play a role in protecting the roof truss beams. For example, δ=20mm wrap welding can be used.

接下来,针对屋面上即将拆除的一块呈长方形的屋面板W,进行处理。具体地,拆除该屋面板W上的防水层、找平层、天窗挡水窗,并清除屋面板W之间的填料。然后,切割屋面板W与屋架梁之间的钢结构连接件,以将该屋面板W独立出来,进行后续针对该屋面板W进行移除。Next, process a rectangular roof panel W that is about to be removed on the roof. Specifically, remove the waterproof layer, leveling layer, and skylight water blocking window on the roof panel W, and remove the filler between the roof panels W. Then, cutting the steel structure connecting piece between the roof panel W and the roof truss beams, so as to separate the roof panel W, and remove the roof panel W subsequently.

将耙式吊装架10安装在屋面板W处,具体地,该耙式吊装架10的两个底支架101应该位于屋面板W的长度方向的两侧处,且横支架104不会位于屋面板W之上而是位于屋面板W之后,斜支架102上的四个手动葫芦105的正投影应该大体上位于屋面板W上。Install the rake type suspension frame 10 at the roof panel W, specifically, the two bottom brackets 101 of the rake type suspension frame 10 should be located at both sides of the length direction of the roof panel W, and the cross brackets 104 should not be located on the roof panel W. Above W but behind the roof panel W, the orthographic projections of the four hand hoists 105 on the inclined bracket 102 should be located substantially on the roof panel W.

利用两根直径大约为17.5mm的钢绳做封绳40,连接在耙式吊装架10和所述一列龙门吊装架之间,并可用3t手动滑车将两根封绳40张紧。Utilize two steel ropes with a diameter of about 17.5mm to make the sealing rope 40, connect between the rake type hoisting frame 10 and the gantry hoisting frame of the row, and the two sealing ropes 40 can be tensioned by a 3t manual block.

然后,在耙式吊装架10下方铺设滑道50,该滑道50与所述一列龙门吊装架20垂直,并延伸至所述一列龙门吊装架20下方,如图4所示。该滑道50同样可采用强度足够的两根平行设置的工字钢制成,例如,25a#工字钢。此外,该滑道50的跨距要小于耙式吊装架10的两个底支架101之间的距离以及屋面板W的长度。Then, a slideway 50 is laid under the rake-type hoisting frame 10 , the slideway 50 is perpendicular to the row of gantry hoisting frames 20 , and extends to the bottom of the row of gantry hoisting frames 20 , as shown in FIG. 4 . The slideway 50 can also be made of two parallel I-beams with sufficient strength, for example, 25a # I-beams. In addition, the span of the slideway 50 is smaller than the distance between the two bottom brackets 101 of the rake suspension frame 10 and the length of the roof panel W.

在屋面板W的大体四个角处开设吊孔,将耙式吊装架10的四个手动葫芦105吊装在该四个吊孔处。启动手动葫芦105,将屋面板W向上提升一段距离,如图5所示。在这个提升的过程中,屋面板W的上升路径可能并不是竖直的,但是最好使得屋面板W保持水平地上升。此外,由于同一斜支架102上的两个手动葫芦105之间的水平距离小于屋面板W的宽度,所以,这两个手动葫芦105的拉绳在提升屋面板W时均不是竖直的,如图6中虚线示出的手动葫芦105,这时,后方的两个手动葫芦105受力大于前方两个手动葫芦105的受力。Hanging holes are provided at approximately four corners of the roof panel W, and the four manual hoists 105 of the rake lifting frame 10 are hoisted at the four hanging holes. Start the manual hoist 105 to lift the roof panel W up a certain distance, as shown in FIG. 5 . During this lifting process, the rising path of the roof panel W may not be vertical, but it is better to keep the roof panel W rising horizontally. In addition, since the horizontal distance between the two manual hoists 105 on the same inclined support 102 is smaller than the width of the roof panel W, the pull ropes of the two manual hoists 105 are not vertical when lifting the roof panel W, as For the manual hoists 105 shown by dotted lines in FIG. 6 , at this moment, the force of the two manual hoists 105 at the rear is greater than that of the two front manual hoists 105 .

随后,调节这四个手动葫芦105,将屋面板W放置到滑道50上。Subsequently, the four manual hoists 105 are adjusted to place the roof panel W on the slideway 50 .

具体地,在四个手动葫芦105将屋面板W起吊一段距离后,例如,起吊大约400mm-500mm,缓慢地放下前方两个手动葫芦同时缓慢地提升后方两个手动葫芦,使得屋面板朝向耙式吊装架10下方的滑道50转移,如图6所示,当屋面板W的至少2/3正投影在滑道50上时,再利用这四个手动葫芦105将屋面板W放置在滑道50上,如图6中实线示出的手动葫芦105。Specifically, after the four manual hoists 105 have lifted the roof panel W for a certain distance, for example, about 400mm-500mm, slowly put down the front two manual hoists while slowly lifting the rear two manual hoists, so that the roof panel faces the rake. The slideway 50 below the hoisting frame 10 is transferred, as shown in Figure 6, when at least 2/3 of the roof panel W is orthographically projected on the slideway 50, the four manual hoists 105 are used to place the roof panel W on the slideway 50, the manual hoist 105 shown in solid line in FIG. 6 .

然后,将所述一列龙门吊装架20上的卷扬机204的牵引绳60连接在屋面板W后部事先开设的牵引孔上(其中,该牵引孔可以为多个),将屋面板W沿滑道50缓慢地牵引到所述一列龙门吊装架20下方,如图7所示,这个过程为平面移动。Then, connect the traction rope 60 of the hoist 204 on the row of gantry hoisting frames 20 to the pre-opened traction hole at the rear of the roof panel W (wherein there may be multiple traction holes), and pull the roof panel W along the slideway. 50 is slowly drawn to below the row of gantry hoisting frames 20, as shown in Figure 7, this process is plane movement.

需要注意的是,在平面移动的过程中,屋面板W的角度可能会发生偏转,而导致屋面板W在靠近龙门吊装架20时可能会与龙门吊装架20发生碰撞,如图7中所示,这时,需要事先对屋面板W的角度进行调节,以保证屋面板W能够被顺利地牵引至龙门吊装架20下方。It should be noted that during the plane movement, the angle of the roof panel W may be deflected, causing the roof panel W to collide with the gantry hoisting frame 20 when approaching the gantry hoisting frame 20, as shown in FIG. 7 , at this time, the angle of the roof panel W needs to be adjusted in advance to ensure that the roof panel W can be smoothly pulled to the bottom of the gantry hoisting frame 20 .

然后,利用所述一列龙门吊装架20上的电动葫芦201将屋面板W沿轨道梁70起吊地运送至所述一列龙门吊装架20的一端。然后,再利用该电动葫芦201将屋面板W放置到预定位置,例如,将屋面板W降落至地面。Then, use the electric hoist 201 on the row of gantry hoisting frames 20 to hoist the roof panel W along the track beam 70 to one end of the row of gantry hoisting frames 20 . Then, the electric hoist 201 is used to place the roof panel W to a predetermined position, for example, to lower the roof panel W to the ground.

在拆除完与所述一列龙门吊装架垂直的一列屋面板之后,针对相邻的另一列屋面板进行拆除时,可将耙式吊装架移动至该列屋面板的最前方的一个屋面板处,进行拆除。即,在拆除其中一个屋面板,只要将耙式吊装架移动至该屋面板处即可。After removing a row of roof panels perpendicular to the row of gantry hoisting frames, when removing another row of adjacent roof panels, the rake-type hoisting frame can be moved to the frontmost roof panel of the row of roof panels, to dismantle. That is, when one of the roof panels is removed, it is only necessary to move the rake lifting frame to the roof panel.

通过本发明所提供的耙式吊装架和拆除方法,能够在屋面拆除场地较小并受限,使得大型吊车无法利用的情况下,完成钢筋混凝土槽形屋面板的拆除作业,并且能够缩短拆除时间,提高作业效率和安全性。此外,在利用该耙式吊装架和拆除方法对屋面板进行拆除时,厂房内的施工或者地面上的施工设备可不停止,从而能够更进一步地提高作业效率。With the rake-type hoisting frame and removal method provided by the present invention, the demolition of reinforced concrete trough-shaped roof panels can be completed and the demolition time can be shortened when the roof demolition site is small and limited so that large cranes cannot be used , Improve work efficiency and safety. In addition, when the roof panel is removed by using the rake-type hoisting frame and the removal method, the construction in the factory building or the construction equipment on the ground do not need to stop, so that the working efficiency can be further improved.

此外,还可以对以上所提供的耙式吊装架进行各种改进和完善,例如,在耙式吊装架上再焊接各种加强肋或加强梁,以提高强度。也可以对龙门吊装架或者龙门吊装架与耙式吊装架之间的连接进行改进和完善,例如,可以在龙门吊装架之下也铺设沿龙门吊装架延伸的辅助滑道,可以在保持屋面板位于该辅助滑道上的情况下,利用电动葫芦将屋面板牵引至龙门吊装架的一端,这有助于减小电动葫芦的受力。或者,对于上述拆除方法也可以进行改进和完善,例如,可以在屋架梁下弦上挂设保护棚和安全网,以避免影响厂房内的正常施工,提高安全性。此外,该拆除方法的进行时序也不必完全按照以上所描述的进行。除此以外,以上提供的耙式吊装架和拆除方法还可以应用于其他拆除施工。In addition, various improvements and improvements can be made to the rake hanger provided above, for example, various reinforcing ribs or beams are welded on the rake hanger to increase the strength. It is also possible to improve and perfect the connection between the gantry hoisting frame or the gantry hoisting frame and the rake hoisting frame. When located on the auxiliary slideway, the electric hoist is used to pull the roof panel to one end of the gantry hoisting frame, which helps to reduce the force on the electric hoist. Alternatively, the above demolition method can also be improved and perfected. For example, a protective shed and a safety net can be hung on the lower chord of the roof truss beam to avoid affecting the normal construction in the factory building and improve safety. In addition, the timing of the dismantling method does not have to be exactly as described above. In addition, the rake hoisting frame and demolition method provided above can also be applied to other demolition constructions.

上面对本发明的具体实施方式进行了详细描述,虽然已表示和描述了一些实施例,但本领域技术人员应该理解,在不脱离由权利要求及其等同物限定其范围的本发明的原理和精神的情况下,可以对这些实施例进行修改和完善,这些修改和完善也应在本发明的保护范围内。The specific embodiments of the present invention have been described in detail above. Although some embodiments have been shown and described, those skilled in the art should understand that without departing from the principle and spirit of the present invention whose scope is defined by the claims and their equivalents Under the circumstances, these embodiments can be modified and improved, and these modifications and improvements should also be within the protection scope of the present invention.

Claims (7)

1.一种耙式吊装架,用于拆除钢筋混凝土槽形屋面板,其特征在于,所述耙式吊装架包括:1. A rake-type hoisting frame for removing reinforced concrete trough roof panels, characterized in that, the rake-type hoisting frame comprises: 两个底支架,彼此平行地水平设置,并且所述两个底支架位于待拆除的屋面板的长度方向的相对两端的外侧;Two bottom brackets are horizontally arranged parallel to each other, and the two bottom brackets are located outside the opposite ends of the length direction of the roof panel to be removed; 两个斜支架,所述两个斜支架的一端分别与所述两个底支架的一端固定,并且彼此平行地倾斜地向上延伸;Two oblique brackets, one end of the two oblique brackets is respectively fixed to one end of the two bottom brackets, and extends obliquely upward parallel to each other; 两个竖直支架,长度相同,并且分别固定地连接在相固定的底支架和斜支架之间,以支撑所述斜支架;two vertical supports with the same length, and are respectively fixedly connected between the fixed bottom support and the oblique support to support the oblique support; 多个横支架,连接在所述两个底支架之间以及所述两个斜支架之间,a plurality of horizontal brackets connected between the two bottom brackets and between the two oblique brackets, 其中,在每个斜支架的从与各自竖直支架的连接点处斜向上延伸的部分上均设置有两个手动葫芦,用于吊装在屋面板的四个角处,以提升屋面板,并且被设置在同一斜支架上的两个手动葫芦之间的水平距离均小于屋面板的宽度。Wherein, two manual hoists are arranged on the part extending obliquely upward from the connection point with the respective vertical support of each inclined support, for hoisting at the four corners of the roof panel to lift the roof panel, and The horizontal distance between the two manual hoists arranged on the same inclined support is smaller than the width of the roof panel. 2.根据权利要求1所述的耙式吊装架,其特征在于,所述斜支架与水平面之间的角度为30°-50°。2. The rake-type hoisting frame according to claim 1, characterized in that, the angle between the inclined bracket and the horizontal plane is 30°-50°. 3.根据权利要求1所述的耙式吊装架,其特征在于,所述底支架、所述竖直支架和所述斜支架均为工字钢。3. The rake-type hoisting frame according to claim 1, characterized in that, the bottom bracket, the vertical bracket and the inclined bracket are all I-beams. 4.一种钢筋混凝土槽形屋面板的拆除方法,其特征在于,包括:4. A method for removing a reinforced concrete trough roof panel, characterized in that it comprises: 在待拆除的屋面上安装一列龙门吊装架,在所述一列龙门吊装架的顶支架上安装沿所述一列龙门吊装架延伸的轨道梁,在所述轨道梁上安装卷扬机和电动葫芦;Install a row of gantry hoisting frames on the roof to be removed, install a rail beam extending along the row of gantry hoisting frames on the top bracket of the row of gantry hoisting frames, and install hoist and electric hoist on the rail beams; 对所述一列龙门吊装架与屋面之间的连接处进行包边焊接;Carry out hemming welding at the junction between the row of gantry hoisting frames and the roof; 拆除屋面的一块待拆除屋面板上的防水层、找平层、天窗挡水窗,并清除屋面板之间的填料;Remove the waterproof layer, leveling layer, skylight water retaining window on a roof panel to be removed on the roof, and remove the filler between the roof panels; 切割屋面板与屋架梁之间的钢结构连接件;Cut the steel structure connection between the roof panel and the roof truss beam; 将如权利要求1至3任意一项所述的耙式吊装架安装在屋面板处;Installing the rake type hoisting frame as described in any one of claims 1 to 3 at the roof panel; 在耙式吊装架下方铺设滑道,所述滑道与所述一列龙门吊装架垂直并延伸至所述一列龙门吊装架下方;A slideway is laid below the rake-type hoisting frame, and the slideway is perpendicular to the row of gantry hoisting frames and extends to below the row of gantry hoisting frames; 利用耙式吊装架的四个手动葫芦提升屋面板;Lifting of the roof panels with four hand hoists of the rake hoisting frame; 调节四个手动葫芦,将屋面板放置到滑道上;Adjust the four manual hoists to place the roof panels on the slides; 利用卷扬机将屋面板沿滑道牵引到所述一列龙门吊装架下方;Utilize the hoist to pull the roof panel to the bottom of the row of gantry hoisting frames along the slideway; 利用所述一列龙门吊装架将屋面板沿滑道牵引至其一端;Utilize the row of gantry hoisting frames to pull the roof panel to one end along the slideway; 利用电动葫芦将屋面板放置到预定位置。Use the electric hoist to place the roof panel to the predetermined position. 5.根据权利要求4所述的拆除方法,其特征在于,利用四个手动葫芦将屋面板提升一段距离,缓慢放下前方两个手动葫芦同时缓慢提升后方两个手动葫芦,使得屋面板朝向耙式吊装架下方的滑道转移,当屋面板的至少2/3投影在滑道上时,利用所述四个手动葫芦将屋面板放置在滑道上。5. The demolition method according to claim 4, characterized in that four manual hoists are used to lift the roof panel for a certain distance, and the two front manual hoists are slowly lowered while the rear two manual hoists are slowly lifted, so that the roof panel faces the rake type. The slideway below the hoisting frame is transferred, and when at least 2/3 of the roof panel is projected on the slideway, the four manual hoists are used to place the roof panel on the slideway. 6.根据权利要求4所述的拆除方法,其特征在于,在屋面板的后部开设有牵引孔,以与卷扬机的牵引绳连接而使得屋面板被卷扬机牵引至所述一列龙门吊装架下方。6. The demolition method according to claim 4, characterized in that, a traction hole is opened at the rear of the roof panel to connect with the traction rope of the hoist so that the roof panel is pulled by the hoist to the bottom of the row of gantry hoisting frames. 7.根据权利要求4所述的拆除方法,其特征在于,所述一列龙门吊装架的相邻两个龙门吊装架之间的距离大于屋面板的长度。7. The removal method according to claim 4, wherein the distance between two adjacent gantry hoisting frames of the row of gantry hoisting frames is greater than the length of the roof panel.
CN201310752178.7A 2013-12-31 2013-12-31 The method for dismounting of rake mast-up and armored concrete channel roof slab Expired - Fee Related CN103741964B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310752178.7A CN103741964B (en) 2013-12-31 2013-12-31 The method for dismounting of rake mast-up and armored concrete channel roof slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310752178.7A CN103741964B (en) 2013-12-31 2013-12-31 The method for dismounting of rake mast-up and armored concrete channel roof slab

Publications (2)

Publication Number Publication Date
CN103741964A true CN103741964A (en) 2014-04-23
CN103741964B CN103741964B (en) 2016-06-29

Family

ID=50499021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310752178.7A Expired - Fee Related CN103741964B (en) 2013-12-31 2013-12-31 The method for dismounting of rake mast-up and armored concrete channel roof slab

Country Status (1)

Country Link
CN (1) CN103741964B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109989590A (en) * 2019-04-09 2019-07-09 中建一局集团建设发展有限公司 For the auxiliary fixing device of roof overlength steel girder erection and the hanging method of girder steel
CN110965803A (en) * 2019-11-29 2020-04-07 中冶天工集团有限公司 Underground diaphragm wall dismantling construction device and construction method thereof
CN111852063A (en) * 2020-06-22 2020-10-30 北京建工集团有限责任公司 Construction method for renovating and reforming large building roof
CN112081250A (en) * 2020-08-03 2020-12-15 上海建工一建集团有限公司 House integral lifting system and house integral lifting method
CN112081249A (en) * 2020-08-03 2020-12-15 上海建工一建集团有限公司 Roof integral jacking system and roof integral jacking method
CN113390263A (en) * 2021-06-15 2021-09-14 攀钢集团工程技术有限公司 Method for dismantling collapsed plate blank of heating furnace

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10225183A1 (en) * 2001-06-06 2003-02-06 Michael Barnsteiner Demolition machine for especially walls has transporting device mounted on top of wall and movable along it, and means to support transporting device on wall and which are brought into engagement with sides of wall
CN101078300A (en) * 2007-05-22 2007-11-28 佛山市工程承包总公司 Heritage building ridge holistic hoisting method
JP2012136936A (en) * 2012-03-16 2012-07-19 Total Kankyo:Kk Method for demolishing cleaning factory
CN202530775U (en) * 2012-02-03 2012-11-14 上海庞源机械租赁股份有限公司 Structure for dismounting inner climbing tower crane by using roof crane

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10225183A1 (en) * 2001-06-06 2003-02-06 Michael Barnsteiner Demolition machine for especially walls has transporting device mounted on top of wall and movable along it, and means to support transporting device on wall and which are brought into engagement with sides of wall
CN101078300A (en) * 2007-05-22 2007-11-28 佛山市工程承包总公司 Heritage building ridge holistic hoisting method
CN202530775U (en) * 2012-02-03 2012-11-14 上海庞源机械租赁股份有限公司 Structure for dismounting inner climbing tower crane by using roof crane
JP2012136936A (en) * 2012-03-16 2012-07-19 Total Kankyo:Kk Method for demolishing cleaning factory

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
陶福保: "马钢三钢轧总厂炼钢厂房屋盖系统改造安全技术管理", 《安徽冶金科技职业学院学报》, vol. 23, no. 1, 31 January 2013 (2013-01-31) *
黄俊宇等: "闹市区钢筋混凝土排架厂房拆除方案设计", 《江苏建筑》, no. 5, 31 October 2013 (2013-10-31), pages 59 - 61 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109989590A (en) * 2019-04-09 2019-07-09 中建一局集团建设发展有限公司 For the auxiliary fixing device of roof overlength steel girder erection and the hanging method of girder steel
CN109989590B (en) * 2019-04-09 2024-01-23 中建一局集团建设发展有限公司 Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam
CN110965803A (en) * 2019-11-29 2020-04-07 中冶天工集团有限公司 Underground diaphragm wall dismantling construction device and construction method thereof
CN110965803B (en) * 2019-11-29 2024-03-26 中冶天工集团有限公司 Underground diaphragm wall dismantling construction device and construction method thereof
CN111852063A (en) * 2020-06-22 2020-10-30 北京建工集团有限责任公司 Construction method for renovating and reforming large building roof
CN112081250A (en) * 2020-08-03 2020-12-15 上海建工一建集团有限公司 House integral lifting system and house integral lifting method
CN112081249A (en) * 2020-08-03 2020-12-15 上海建工一建集团有限公司 Roof integral jacking system and roof integral jacking method
CN113390263A (en) * 2021-06-15 2021-09-14 攀钢集团工程技术有限公司 Method for dismantling collapsed plate blank of heating furnace

Also Published As

Publication number Publication date
CN103741964B (en) 2016-06-29

Similar Documents

Publication Publication Date Title
LU102302B1 (en) Steel reinforcement cage for use in ventilation shaft diaphragm wall, and usage method
CN103741964B (en) The method for dismounting of rake mast-up and armored concrete channel roof slab
CN103015325B (en) Construction method of cast-in-place concrete crash barrier with eaves
CN102661054B (en) Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method
CN109898819A (en) A kind of the overhanging tool type scaffold system and its installation method of foldable telescopic
WO2022252829A1 (en) Liftable scaffold, lifting and installation methods thereof, and construction method for prefabricated building
CN111255217A (en) A kind of elevator shaft stereotyped operation platform and operation method thereof
KR101118526B1 (en) Construction method of steel tower of bridge and dismantling method of lifting frame
CN105019664A (en) High-altitude sliding installation method for box room type electric room
CN104234447A (en) Tool-type suspension staircase for deep foundation pit
CN108277994B (en) Method for quickly dismantling safety protection shed of overhead high-speed rail operation line
CN106522566A (en) Roof steel truss slipping rail and dismounting and installing method thereof
CN104110002A (en) Method for replacing bridge deck slabs of steel truss girder bridge
JP2010242308A (en) Method for demolishing high-rise building of concrete slab structure, and concrete slab demolition equipment
CN202899639U (en) Concrete column structure
CN108505539A (en) A kind of beam outrigger platform and its erection method
JP3242893U (en) Portable Safe Operation Platform for High-Rise Building Elevator Shafts
CN203361170U (en) Supporting upright column pile for building foundation pit support
CN207377576U (en) Simple walking trolley suitable for limited space
CN113802478B (en) An arch bridge deck structure dismantling device based on arch rib support
CN206636168U (en) Overhanging type scaffold system
CN117005664A (en) Electric translation type hanging basket
CN215669490U (en) Cantilever type tubular pile hanging and striking positioning support
CN204754950U (en) It puts force piece to combine to adopt to combine
CN203924652U (en) The operation platform of periphery shear wall between a kind of precast stair

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160629

Termination date: 20161231

CF01 Termination of patent right due to non-payment of annual fee