[go: up one dir, main page]

CN109653240B - Urban residual mud and slag mound in ecological restoration project and its construction method - Google Patents

Urban residual mud and slag mound in ecological restoration project and its construction method Download PDF

Info

Publication number
CN109653240B
CN109653240B CN201811622515.XA CN201811622515A CN109653240B CN 109653240 B CN109653240 B CN 109653240B CN 201811622515 A CN201811622515 A CN 201811622515A CN 109653240 B CN109653240 B CN 109653240B
Authority
CN
China
Prior art keywords
retaining wall
layer
soil
slope
slag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811622515.XA
Other languages
Chinese (zh)
Other versions
CN109653240A (en
Inventor
余郁
陈晓飞
费康
李园
吴健翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzhou Municipal Construction Division
Yangzhou University
Original Assignee
Yangzhou Municipal Construction Division
Yangzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzhou Municipal Construction Division, Yangzhou University filed Critical Yangzhou Municipal Construction Division
Priority to CN201811622515.XA priority Critical patent/CN109653240B/en
Publication of CN109653240A publication Critical patent/CN109653240A/en
Application granted granted Critical
Publication of CN109653240B publication Critical patent/CN109653240B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/005Soil-conditioning by mixing with fibrous materials, filaments, open mesh or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Revetment (AREA)

Abstract

本发明提供了一种生态修复工程中城市余泥渣土堆筑体及其施工方法,堆筑体包括:设在基底上的堆筑体本体、设在堆筑体本体内的排水盲管、设在堆筑体本体至少一侧的侧面的挡墙组件和设在所述挡墙组件上方的土工格栅,其中,在细圆砾土层与基底层之间由下至上依次包括:土工布层和垫层,垫层的厚度为0.4‑0.8m,垫层由下至上依次为:中粗砂层、砂夹砾石层和碎石层,其中土工布层纵、横向抗拉断裂强度≥12KN/m,纵、横向撕破强力≥0.4KN,CBR顶破强力≥1.5KN,梯度比GR≤3。根据本发明的生态修复工程中城市余泥渣土堆筑体,整个堆筑体的稳定性大幅提高,合理得利用了建筑余土进行堆筑体建设,便于更有效地对了生态环境进行改造,具有良好的应用前景。

Figure 201811622515

The invention provides an urban residual mud and slag piling body and a construction method thereof in an ecological restoration project. The piling body comprises: a piling body body arranged on a base, a drainage blind pipe arranged in the piling body body, A retaining wall assembly arranged on at least one side of the stack body and a geogrid disposed above the retaining wall assembly, wherein, from bottom to top, between the fine round gravel soil layer and the base layer sequentially includes: geotextile Layer and cushion, the thickness of the cushion is 0.4-0.8m, and the cushion from bottom to top is: medium-coarse sand layer, sand and gravel layer and gravel layer, of which the longitudinal and transverse tensile fracture strength of geotextile layer is ≥12KN /m, longitudinal and transverse tearing strength ≥0.4KN, CBR bursting strength ≥1.5KN, gradient ratio GR≤3. According to the urban residual mud and slag pile in the ecological restoration project of the present invention, the stability of the entire pile is greatly improved, and the construction residual soil is reasonably used for the construction of the pile, which facilitates the more effective reconstruction of the ecological environment. , has a good application prospect.

Figure 201811622515

Description

生态修复工程中城市余泥渣土堆筑体及其施工方法Urban residual mud and slag mound in ecological restoration project and its construction method

技术领域technical field

本发明涉及园林建筑技术领域,具体而言,特别涉及一种生态修复工程中城市余泥渣土堆筑体堆筑体及其施工方法The invention relates to the technical field of garden architecture, in particular, to an urban residual mud and slag mound in an ecological restoration project and a construction method thereof

背景技术Background technique

随着经济的快速发展和城市规模不断扩大,城市用地紧张等问题的突显,城市地下空间的开发越来越受到重视。地下建筑物、构筑物、市政交通工程等的不断施工,与之而来的是越来越多的建筑余土,“渣土围城”成为很多城市的痛点,制约了城市的可持续发展。而现今生态环境的改造,生活环境的改善越来越被政府重视。未来城市建设理念的不断发展,如何通过“变废为宝”,采用城市建筑余土人工堆筑山体工程的应用前景也会越来越广泛。With the rapid development of the economy and the continuous expansion of the city scale, the shortage of urban land and other problems have become prominent, and the development of urban underground space has been paid more and more attention. The continuous construction of underground buildings, structures, municipal transportation projects, etc., is accompanied by more and more residual construction waste. "Scum siege" has become a pain point in many cities, restricting the sustainable development of cities. Nowadays, the transformation of the ecological environment and the improvement of the living environment are increasingly being valued by the government. With the continuous development of the concept of urban construction in the future, how to "turn waste into treasure" and use the residual soil of urban construction to artificially build mountain mass engineering will have more and more extensive application prospects.

发明内容SUMMARY OF THE INVENTION

本发明旨在至少在一定程度上解决现有技术中的上述技术问题之一。有鉴于此,本发明一方面提供一种易于实施、可靠性高的生态修复工程中城市余泥渣土堆筑体。本发明的另一方面提供一种生态修复工程中城市余泥渣土堆筑体的施工方法。The present invention aims to solve one of the above-mentioned technical problems in the prior art at least to a certain extent. In view of this, one aspect of the present invention provides an urban residual mud and slag mound in an ecological restoration project that is easy to implement and has high reliability. Another aspect of the present invention provides a construction method for an urban residual mud and slag mound in an ecological restoration project.

根据本发明的生态修复工程中城市余泥渣土堆筑体包括:设在基底上的堆筑体本体、设在所述堆筑体本体内的排水盲管、设在所述堆筑体本体至少一侧的侧面的挡墙组件和设在所述挡墙组件上方的土工格栅,所述挡墙组件包括:厚度为0.8m-1.2m的三七灰土层、设在所述三七灰土层上方的模块式加筋土挡墙、设在所述三七土层上并位于所述模块式加筋土挡墙外侧的卵石截洪沟、设在所述模块式加筋土挡墙与堆筑体本体之间的细圆砾土层、设在所述细圆砾土层上方的透水土工布和设在所述细圆砾土层与所述堆筑体本体之间的厚袋装砂砾石反滤层,其中,在所述细圆砾土层与所述基底层之间由下至上依次包括:土工布层和垫层,所述垫层的厚度为0.4-0.8m,所述垫层由下至上依次为:中粗砂层、砂夹砾石层和碎石层,其中所述土工布层纵、横向抗拉断裂强度≥12KN/m,纵、横向撕破强力≥0.4KN,CBR顶破强力≥1.5KN,梯度比GR≤3。According to the ecological restoration project of the present invention, the urban residual mud and slag soil stack includes: a stack body body arranged on the base, a drainage blind pipe arranged in the stack body body, and a stack body body arranged in the stack body body. At least one side retaining wall assembly and a geogrid disposed above the retaining wall assembly, the retaining wall assembly comprising: a Panax notoginseng lime soil layer with a thickness of 0.8m-1.2m, The modular reinforced soil retaining wall above the layer, the pebble flood intercepting ditch located on the Panax notoginseng soil layer and located outside the modular reinforced soil retaining wall, and the modular reinforced soil retaining wall and the The fine round gravel soil layer between the body of the stacking body, the permeable geotextile arranged above the fine round gravel soil layer, and the thick bagged bag set between the fine round gravel soil layer and the body of the stacking body Sand and gravel filter layer, wherein, from bottom to top, between the fine round gravel soil layer and the base layer sequentially includes: a geotextile layer and a cushion layer, the thickness of the cushion layer is 0.4-0.8m, the The cushion layers from bottom to top are: medium-coarse sand layer, sand sandwiched gravel layer and crushed stone layer, wherein the longitudinal and transverse tensile breaking strength of the geotextile layer is ≥12KN/m, and the longitudinal and transverse tearing strength is ≥0.4KN, CBR bursting strength≥1.5KN, gradient ratio GR≤3.

根据本发明的实施例的生态修复工程中城市余泥渣土堆筑体,整个堆筑体的稳定性大幅提高,合理得利用了建筑余土进行堆筑体建设,便于更有效地对了生态环境进行改造,具有良好的应用前景。In the ecological restoration project according to the embodiment of the present invention, the stability of the entire piled body is greatly improved, and the residual construction soil is reasonably used for the construction of the piled body, which is convenient for more effective ecological restoration. The environment is transformed, and it has a good application prospect.

另外,根据本发明上述实施例的生态修复工程中城市余泥渣土堆筑体还可以具有如下附加的技术特征:In addition, in the ecological restoration project according to the above-mentioned embodiment of the present invention, the urban residual mud and slag mound may also have the following additional technical features:

根据本发明的一个实施例,在所述细圆砾土层内设有多个土压力盒,在所述土工格栅上设有位移监测桩。According to an embodiment of the present invention, a plurality of earth pressure cells are arranged in the fine round gravel soil layer, and displacement monitoring piles are arranged on the geogrid.

根据本发明的一个实施例,所述模块式加筋土挡墙包括具有第一预定高度的第一模块式加筋土挡墙和具有第二预定高度的第二模块式加筋土挡墙,所述第一模块式加筋土挡墙和所述第二模块式加筋土挡墙之间构造成台阶形,以在所述第一模块式加筋土挡墙一侧形成一级挡墙组件和在所述第二模块式加筋土挡墙的一侧形成二级挡墙组件。According to an embodiment of the present invention, the modular reinforced soil retaining wall includes a first modular reinforced soil retaining wall with a first predetermined height and a second modular reinforced soil retaining wall with a second predetermined height, The first modular reinforced soil retaining wall and the second modular reinforced soil retaining wall are constructed in a stepped shape to form a first-level retaining wall on one side of the first modular reinforced soil retaining wall assembly and forming a secondary retaining wall assembly on one side of the second modular reinforced earth retaining wall.

根据本发明的一个实施例,在所述堆筑体本体内设有用于对所述基底沉降监测的沉降板。According to an embodiment of the present invention, a settling plate for monitoring the settlement of the base is provided in the stack body.

根据本发明的一个实施例,所述垫层被设置成台阶形。According to an embodiment of the present invention, the cushion layer is provided in a stepped shape.

根据上述生态修复工程中城市余泥渣土堆筑体的施工方法,包括以下步骤:According to the construction method of the urban residual mud and slag mound in the above-mentioned ecological restoration project, the following steps are included:

S1:对基底的表面进行处理,并在基底上设置高度小于0.6m、宽度大于1.0m的台阶,所述台阶与堆筑体本体的陡坡处对应;S1: The surface of the base is treated, and steps with a height of less than 0.6m and a width of greater than 1.0m are arranged on the base, and the steps correspond to the steep slope of the body of the stack;

S2:对所述堆筑体本体基底填土层进行压实,并在模块式加筋土挡墙的基底处换填三七灰土并压实,在基底的坡脚20m-25m范围以内先铺设一层土工布,再铺设垫层;S2: Compact the soil layer at the base of the body of the stack, replace with notoginseng lime soil at the base of the modular reinforced soil retaining wall and compact it, and lay it first within 20m-25m of the slope foot of the base A layer of geotextile, and then lay a cushion;

S3:对所述堆筑体本体分区分层填充、分层压实,且所述堆筑体本体采用粉土填充,所述堆筑体主峰周围采用黏土填筑,其中,所述粉土的压实系数K不小于0.9,地基系数K30不小于80MPa/m;所述黏土厚度为0.4m-0.6m,压实系数K不小于0.9,地基系数K30不小于80MPa/m,分层厚度为压实后0.3m一层,每压实一层后对地基的压实质量进行压实系数K和地基系数K30检验,检测数量为每2000m2不小于4处;S3: Filling and compacting the body of the stacked body in different zones and layers, and the body of the stacked body is filled with silt, and the surrounding of the main peak of the stacked body is filled with clay, wherein the silt is filled with clay. The compaction coefficient K is not less than 0.9, the foundation coefficient K30 is not less than 80MPa/m; the thickness of the clay is 0.4m-0.6m, the compaction coefficient K is not less than 0.9, the foundation coefficient K30 is not less than 80MPa/m, and the layer thickness is 0.3m layer after compaction, after each layer of compaction, the compaction coefficient K and foundation coefficient K30 of the foundation shall be inspected, and the number of inspections shall not be less than 4 per 2000m2;

S4:使用所述模块式加筋土挡墙进行收坡,且采用的所述模块式加筋土挡墙的高度为2.83m-7.02m;S4: Use the modular reinforced soil retaining wall for slope closing, and the height of the modular reinforced soil retaining wall used is 2.83m-7.02m;

S5:采用边坡包裹体对所述堆筑体陡于1:4的边坡进行加固,并在所述边坡包裹体下方设置碎石和浆砌片石基础;S5: Use side slope inclusions to reinforce the side slopes of the stacked body that are steeper than 1:4, and set up gravel and mortar rubble foundations below the side slope inclusions;

S6:在所述模块式加筋土挡墙下部设置排水盲管,并在所述排水盲管底部铺设复合土工膜。S6: A drainage dead pipe is arranged at the lower part of the modular reinforced earth retaining wall, and a composite geomembrane is laid on the bottom of the drainage dead pipe.

根据本发明的实施例的生态修复工程中城市余泥渣土堆筑体的施工方法,整个堆筑体的稳定性大幅提高,合理得利用了建筑余土进行堆筑体建设,便于更有效地对了生态环境进行改造,具有良好的应用前景。According to the construction method of the urban residual mud and slag pile in the ecological restoration project according to the embodiment of the present invention, the stability of the whole pile is greatly improved, and the construction of the pile can be reasonably made use of the construction residual soil, which is convenient for a more effective It has a good application prospect for the transformation of the ecological environment.

另外,根据本发明上述实施例的生态修复工程中城市余泥渣土堆筑体的施工方法还可以具有如下附加的技术特征:In addition, the construction method of the urban residual mud and slag pile in the ecological restoration project according to the above-mentioned embodiment of the present invention may also have the following additional technical features:

根据本发明的一个实施例,进一步包括以下步骤:S7:根据工程概况确定堆筑体X、Y、Z三个方向的尺寸,建立三维模型,对所述三维模型划分网格后,通过在三维模型中设置多个位移监测点、多个应力监测点对所述模块式加筋土挡墙的最高断面的受力、变形及稳定性进行分析。According to an embodiment of the present invention, it further includes the following steps: S7: Determine the dimensions of the stacking body in the three directions of X, Y, and Z according to the project overview, establish a three-dimensional model, and divide the three-dimensional model by meshing the three-dimensional model. Multiple displacement monitoring points and multiple stress monitoring points are set in the model to analyze the stress, deformation and stability of the highest section of the modular reinforced soil retaining wall.

根据本发明的一个实施例,对堆筑体进行沉降观测和水平位移观测,以在发生以下至少一种情况时发出报警:According to an embodiment of the present invention, settlement observation and horizontal displacement observation are carried out on the stack, so as to issue an alarm when at least one of the following conditions occurs:

边坡支护结构坡顶的最大水平位移已大于填土高度的1/500或20mm,以及水平位移速率已连续3天大于2mm/d;The maximum horizontal displacement of the slope top of the slope supporting structure has been greater than 1/500 or 20mm of the fill height, and the horizontal displacement rate has been greater than 2mm/d for 3 consecutive days;

填筑期地表沉降速率大于10mm/d;During the filling period, the surface settlement rate is greater than 10mm/d;

边坡底部或周围土体出现可能导致剪切破坏的迹象或其他可能影响安全的征兆;Signs that may lead to shear failure or other signs that may affect safety at the bottom of the slope or in the surrounding soil;

坡顶附近出现新裂缝;New cracks appear near the top of the slope;

根据经验判断认为,已出现其他必须报警的情况。Judging from experience, other situations have occurred that must be reported to the police.

根据本发明的一个实施例,,S4中,在所述模块式加筋土挡墙的面层布置混凝土预制模块,且相邻的所述混凝土预制块之间设有伸缩缝。According to an embodiment of the present invention, in S4, prefabricated concrete modules are arranged on the surface layer of the modular reinforced earth retaining wall, and expansion joints are provided between the adjacent prefabricated concrete blocks.

根据本发明的一个实施例,S5中:所述边坡包裹体包括双向拉伸土工格栅及土工布,所述双向拉伸土工格栅内填充炭黑量大于2%的聚丙烯:所述排水盲管呈梅花形布置,所述复合土工膜采用无纺土工布贴附加入炭黑的高密度聚乙烯膜,高密度聚乙烯膜的膜厚大于0.3mm。According to an embodiment of the present invention, in S5: the slope inclusion includes a biaxially oriented geogrid and a geotextile, and the biaxially oriented geogrid is filled with polypropylene with an amount of carbon black greater than 2%: the The blind drainage pipes are arranged in a plum blossom shape, and the composite geomembrane is made of non-woven geotextiles pasted with a high-density polyethylene film with carbon black added, and the film thickness of the high-density polyethylene film is greater than 0.3 mm.

本发明的附加方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本发明的实践了解到。Additional aspects and advantages of the present invention will be set forth, in part, from the following description, and in part will be apparent from the following description, or may be learned by practice of the invention.

附图说明Description of drawings

图1是根据本发明的一个实施例的生态修复工程中城市余泥渣土堆筑体的结构示意图。FIG. 1 is a schematic structural diagram of an urban residual mud and slag pile in an ecological restoration project according to an embodiment of the present invention.

图2是根据本发明的另一个实施例的生态修复工程中城市余泥渣土堆筑体的结构示意图;2 is a schematic structural diagram of an urban residual mud and slag pile in an ecological restoration project according to another embodiment of the present invention;

图3是图2中A处的放大示意图。FIG. 3 is an enlarged schematic view of A in FIG. 2 .

图4是根据本发明的一个实施例的生态修复工程中城市余泥渣土堆筑体的施工方法的流程图。Fig. 4 is a flow chart of a construction method of an urban residual mud and slag pile in an ecological restoration project according to an embodiment of the present invention.

具体实施方式Detailed ways

下面详细描述本发明的实施例,所述实施例的示例在附图中示出,其中自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。下面通过参考附图描述的实施例是示例性的,旨在用于解释本发明,而不能理解为对本发明的限制。The following describes in detail the embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein the same or similar reference numerals refer to the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary, and are intended to explain the present invention and should not be construed as limiting the present invention.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", " Rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", etc. The relationship is based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore It should not be construed as a limitation of the present invention.

此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In addition, the terms "first" and "second" are only used for descriptive purposes, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first" or "second" may expressly or implicitly include one or more of that feature. In the description of the present invention, "plurality" means two or more, unless otherwise expressly and specifically defined.

在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise expressly specified and limited, the terms "installed", "connected", "connected", "fixed" and other terms should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection , or integrated; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal connection of the two elements or the interaction relationship between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific situations.

在本发明中,除非另有明确的规定和限定,第一特征在第二特征之“上”或之“下”可以包括第一和第二特征直接接触,也可以包括第一和第二特征不是直接接触而是通过它们之间的另外的特征接触。而且,第一特征在第二特征“之上”、“上方”和“上面”包括第一特征在第二特征正上方和斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”包括第一特征在第二特征正下方和斜下方,或仅仅表示第一特征水平高度小于第二特征。In the present invention, unless otherwise expressly specified and limited, a first feature "on" or "under" a second feature may include the first and second features in direct contact, or may include the first and second features Not directly but through additional features between them. Also, the first feature being "above", "over" and "above" the second feature includes the first feature being directly above and obliquely above the second feature, or simply means that the first feature is level higher than the second feature. The first feature is "below", "below" and "below" the second feature includes the first feature being directly below and diagonally below the second feature, or simply means that the first feature has a lower level than the second feature.

如图1-3所示,根据本发明的实施例的生态修复工程中城市余泥渣土堆筑体100,包括:设在基底200上的堆筑体本体10、设在堆筑体本体10内的排水盲管11、设在堆筑体本体10至少一侧的侧面的挡墙组件和设在挡墙组件上方的土工格栅30。As shown in FIGS. 1-3 , the urban residual mud and slag soil stack 100 in the ecological restoration project according to the embodiment of the present invention includes: a stack body 10 provided on the base 200 , a stack body 10 provided on the stack body 10 The inner drainage blind pipe 11 , the retaining wall assembly arranged on at least one side of the stack body 10 , and the geogrid 30 disposed above the retaining wall assembly.

挡墙组件可以包括:厚度为0.8m-1.2m的三七灰土层21、设在三七灰土层21上方的模块式加筋土挡墙22、设在三七土层21上并位于模块式加筋土挡墙22外侧的卵石截洪沟23、设在模块式加筋土挡墙22与堆筑体本体10之间的细圆砾土层24、设在细圆砾土层24上方的透水土工布25和设在细圆砾土层24与堆筑体本体10之间的厚袋装砂砾石反滤层26。The retaining wall assembly may include: a Panax notoginseng lime soil layer 21 with a thickness of 0.8m-1.2m, a modular reinforced soil retaining wall 22 provided above the Panax notoginseng soil layer 21, a modular reinforced soil retaining wall 22 provided on the Panax notoginseng soil layer 21 and located in a modular The pebble flood intercepting ditch 23 outside the reinforced earth retaining wall 22, the fine round gravel soil layer 24 arranged between the modular reinforced earth retaining wall 22 and the stack body 10, the fine round gravel soil layer 24 arranged above the fine round gravel soil layer 24. The permeable geotextile 25 and the thick bagged sand and gravel filter layer 26 arranged between the fine round gravel soil layer 24 and the body 10 of the stacking body.

其中,在细圆砾土层24与基底200之间由下至上依次包括:土工布层27和垫层28,垫层28的厚度为0.4-0.8m,垫层28由下至上依次为:中粗砂层、砂夹砾石层和碎石层,其中土工布层27纵、横向抗拉断裂强度≥12KN/m,纵、横向撕破强力≥0.4KN,CBR顶破强力≥1.5KN,梯度比GR≤3。Among them, between the fine round gravel soil layer 24 and the base 200, from bottom to top, it includes: a geotextile layer 27 and a cushion layer 28, the thickness of the cushion layer 28 is 0.4-0.8m, and the cushion layer 28 from bottom to top is: Coarse sand layer, sand sandwiched gravel layer and gravel layer, of which the geotextile layer 27 has longitudinal and transverse tensile fracture strength ≥12KN/m, longitudinal and transverse tearing strength ≥0.4KN, CBR bursting strength ≥1.5KN, gradient ratio GR≤3.

如图3所示,模块式加筋土挡墙22可以包括具有第一预定高度的第一模块式加筋土挡墙221和具有第二预定高度的第二模块式加筋土挡墙222,第一模块式加筋土挡墙221和第二模块式加筋土挡墙222之间构造成台阶形,以在第一模块式加筋土挡墙一侧形成一级挡墙组件201和在第二模块式加筋土挡墙222的一侧形成二级挡墙组件202。As shown in FIG. 3 , the modular reinforced earth retaining wall 22 may include a first modular reinforced earth retaining wall 221 having a first predetermined height and a second modular reinforced earth retaining wall 222 having a second predetermined height, The first modular reinforced earth retaining wall 221 and the second modular reinforced earth retaining wall 222 are constructed in a stepped shape, so as to form the first-level retaining wall assembly 201 on one side of the first modular reinforced earth retaining wall and on the other side. One side of the second modular reinforced earth retaining wall 222 forms the secondary retaining wall assembly 202 .

根据本发明的实施例,通过设置一级挡墙组件201和二级挡墙组件202两级加筋土挡墙相比较于单级加筋土挡墙而言,主要有着结构差异、破坏模型差异和设计方法三方面的差异。According to the embodiment of the present invention, compared with the single-stage reinforced soil retaining wall, the two-stage reinforced soil retaining wall mainly has structural differences and damage model differences by setting the first-stage retaining wall assembly 201 and the second-stage retaining wall assembly 202 and three aspects of the design method.

结构差异:两级加筋土挡墙上下两级墙体之间的台阶与筋材、筋材与墙面板填料相互影响,一起组成两级加筋土挡墙的结构。在台阶作用下,下部墙体会受到挡墙上部荷载应力扩散的较大影响,比如当台阶宽度很大时,台阶作用比较明显;当台阶宽度较小时,两级挡墙也就可以视为单级挡墙来进行设计,台阶影响忽略不计。Structural difference: The steps between the two-level reinforced earth retaining wall and the lower and lower walls interact with the reinforcement, the reinforcement and the wall panel filler, and together form the structure of the two-level reinforced earth retaining wall. Under the action of the step, the lower wall will be greatly affected by the load stress diffusion on the upper part of the retaining wall. For example, when the step width is large, the step effect is more obvious; when the step width is small, the two-stage retaining wall can also be regarded as a single-stage retaining wall. Step retaining walls are used for design, and the influence of steps is ignored.

破坏模型差异:两级加筋土挡墙的破坏既相互独立,又相互联系。由于上墙基础设置在下墙的墙体之上,故下墙的承载力与稳定性直接关系到上墙的稳定与安全性,相比之下,上部墙体的变形破坏则对下部墙体的影响较小。Differences in failure models: The failures of two-level reinforced earth retaining walls are both independent and interrelated. Since the foundation of the upper wall is set on the wall of the lower wall, the bearing capacity and stability of the lower wall are directly related to the stability and safety of the upper wall. Less affected.

参见图1-3,可以理解的是,在对堆筑体100进行施工时,可以在堆筑体本体10的一侧设置模块式加筋土挡墙22进行收坡,模块式加筋土挡墙22的墙高可以为2.83m-7.02m。加筋土挡墙胸背坡坡比1:0.05。模块式加筋土挡墙22的加筋材料宜选用单向拉伸聚乙烯塑料土工格栅,炭黑量≥2%并均匀分布,土工格栅纵向极限抗拉强度≥120KN/m,纵向标称伸长率≤11.5%。土工格栅长7m-9m,竖向间距Sy=0.3m。土工格栅回折长不小于1.5m,幅间搭接0.1m,采用骑马钉按间距1m固定在填土上。加筋土挡墙填料采用洁净的级配良好的细圆砾土。Referring to FIGS. 1-3 , it can be understood that during the construction of the stack body 100 , a modular reinforced soil retaining wall 22 may be set on one side of the stack body 10 to close the slope. The wall height of the wall 22 may be 2.83m-7.02m. The slope ratio of the reinforced soil retaining wall between the chest and the back is 1:0.05. The reinforcement material of the modular reinforced earth retaining wall 22 should be uniaxially stretched polyethylene plastic geogrid, the amount of carbon black is ≥2% and evenly distributed, the longitudinal ultimate tensile strength of the geogrid is ≥120KN/m, and the longitudinal standard is ≥120KN/m. Said elongation ≤ 11.5%. The length of the geogrid is 7m-9m, and the vertical spacing Sy=0.3m. The folded length of the geogrid shall not be less than 1.5m, the overlap between the panels shall be 0.1m, and the backfill shall be fixed on the filling soil with a distance of 1m by using saddle tacks. Reinforced earth retaining wall fill is clean and well-graded fine round gravel soil.

进一步地,强降雨工况下,山体渗流对山体稳定性影响较大,为减小影响,宜减小山上地表水下渗,并加强山体内地下水排出。Further, under heavy rainfall conditions, the mountain seepage has a greater impact on the stability of the mountain. In order to reduce the impact, it is advisable to reduce the surface water seepage on the mountain and strengthen the discharge of groundwater in the mountain.

主峰范围内填高最大其安全稳定性最低,需重点设计,故增设防渗粘土层,减小地表水下渗,并将其引向安全区域。模块式加筋土挡墙22采用细圆砾土,墙背向山体内铺设梅花形布置的排水盲管,加强地下水排出。山体四周坡脚向山体内20m-30m范围内设排水垫层,加快地下水排出。The maximum filling height within the main peak range has the lowest safety and stability, and requires key design. Therefore, an anti-seepage clay layer is added to reduce surface water infiltration and lead it to a safe area. The modular reinforced soil retaining wall 22 is made of fine round gravel soil, and the plumb-shaped drainage blind pipes are laid in the back of the wall to enhance the drainage of groundwater. Drainage cushions are set up in the range of 20m-30m from the foot of the slope around the mountain to the mountain to speed up the drainage of groundwater.

排水盲管11适于设置在袋装砂砾石反滤层右侧垫层以上3m的位置处,排水盲管11截面采用0.3m*0.3m,纵向间距5m,呈梅花形布置。盲沟底部复合土工膜采用无纺布复合土工膜,二布一膜结构。复合土工膜纵、横向抗拉断裂强度≥20KN/m,CBR顶破强力≥2.5KN,垂直渗透系数≤1.0×10-11cm/s,膜材采用加入炭黑的高密度聚乙烯,膜厚≥0.3mm。The blind drainage pipe 11 is suitable for being arranged at a position 3m above the cushion layer on the right side of the bagged sand and gravel filter layer. The composite geomembrane at the bottom of the blind ditch adopts a non-woven composite geomembrane, with two fabrics and one membrane structure. Composite geomembrane longitudinal and transverse tensile breaking strength ≥ 20KN/m, CBR bursting strength ≥ 2.5KN, vertical permeability coefficient ≤ 1.0×10-11cm/s, the membrane material is high-density polyethylene with carbon black added, and the film thickness ≥ 0.3mm.

在堆筑体填筑期间和填筑完成后可以进行挡墙土压力、拉筋内力和山体沉降变形(含地基和本体)连续监测。通过对挡墙土压力、土工格栅拉力和沉降变形等进行系统的观测与分析评估,在填筑过程中,指导控制填土速率。具体地,根据本发明的一些实施例,在细圆砾土层24内设有多个土压力盒41,在土工格栅30上设有位移监测桩42。在堆筑体本体10内设有用于对基底200沉降监测的沉降板43。The earth pressure of retaining wall, internal force of tie bars and mountain settlement and deformation (including foundation and body) can be continuously monitored during and after the filling of the stack. Through systematic observation, analysis and evaluation of the earth pressure of the retaining wall, the tensile force of the geogrid and the settlement deformation, the filling rate is guided and controlled during the filling process. Specifically, according to some embodiments of the present invention, a plurality of earth pressure cells 41 are provided in the fine round gravel soil layer 24 , and displacement monitoring piles 42 are provided on the geogrid 30 . A settling plate 43 for monitoring the settlement of the base 200 is provided in the stack body 10 .

根据本发明的一个实施例,为了便于施工,垫层28可以被设置成台阶形。According to an embodiment of the present invention, in order to facilitate construction, the cushion layer 28 may be provided in a stepped shape.

根据本发明的实施例的生态修复工程中城市余泥渣土堆筑体100,整个堆筑体的稳定性高,合理得利用了建筑余土进行堆筑体建设,便于更有效地对了生态环境进行改造,具有良好的应用前景。In the ecological restoration project according to the embodiment of the present invention, the urban residual mud and slag pile 100 has high stability of the entire pile, and the construction waste can be reasonably used for the construction of the pile, which is convenient for more effective ecological restoration. The environment is transformed, and it has a good application prospect.

下面参考图4描述根据本发明的实施例的生态修复工程中城市余泥渣土堆筑体的施工方法,该施工方法,其特征在于,包括以下步骤:The following describes the construction method of the urban residual mud and slag pile in the ecological restoration project according to the embodiment of the present invention with reference to FIG. 4 . The construction method is characterized in that, it includes the following steps:

S1:对基底的表面进行处理,并在基底上设置高度小于0.6m、宽度大于1.0m的台阶,所述台阶与堆筑体本体的陡坡处对应;S1: The surface of the base is treated, and steps with a height of less than 0.6m and a width of greater than 1.0m are arranged on the base, and the steps correspond to the steep slope of the body of the stack;

S2:对所述堆筑体本体基底填土层进行压实,并在模块式加筋土挡墙的基底处换填三七灰土并压实,在基底的坡脚20m-25m范围以内先铺设一层土工布,再铺设垫层;S2: Compact the soil layer at the base of the body of the stack, replace with notoginseng lime soil at the base of the modular reinforced soil retaining wall and compact it, and lay it first within 20m-25m of the slope foot of the base A layer of geotextile, and then lay a cushion;

S3:对所述堆筑体本体分区分层填充、分层压实,且所述堆筑体本体采用粉土填充,所述堆筑体主峰周围采用黏土填筑,其中,所述粉土的压实系数K不小于0.9,地基系数K30不小于80MPa/m;所述黏土厚度为0.4m-0.6m,压实系数K不小于0.9,地基系数K30不小于80MPa/m,分层厚度为压实后0.3m一层,每压实一层后对地基的压实质量进行压实系数K和地基系数K30检验,检测数量为每2000m2不小于4处;S3: Filling and compacting the body of the stacked body in different zones and layers, and the body of the stacked body is filled with silt, and the surrounding of the main peak of the stacked body is filled with clay, wherein the silt is filled with clay. The compaction coefficient K is not less than 0.9, the foundation coefficient K30 is not less than 80MPa/m; the thickness of the clay is 0.4m-0.6m, the compaction coefficient K is not less than 0.9, the foundation coefficient K30 is not less than 80MPa/m, and the layer thickness is 0.3m layer after compaction, after each layer of compaction, the compaction coefficient K and foundation coefficient K30 of the foundation shall be inspected, and the number of inspections shall not be less than 4 per 2000m2;

S4:使用所述模块式加筋土挡墙进行收坡,且采用的所述模块式加筋土挡墙的高度为2.83m-7.02m;S4: Use the modular reinforced soil retaining wall for slope closing, and the height of the modular reinforced soil retaining wall used is 2.83m-7.02m;

S5:采用边坡包裹体对所述堆筑体陡于1:4的边坡进行加固,并在所述边坡包裹体下方设置碎石和浆砌片石基础;S5: Use side slope inclusions to reinforce the side slopes of the stacked body that are steeper than 1:4, and set up gravel and mortar rubble foundations below the side slope inclusions;

S6:在所述模块式加筋土挡墙下部设置排水盲管,并在所述排水盲管底部铺设复合土工膜。S6: A drainage dead pipe is arranged at the lower part of the modular reinforced earth retaining wall, and a composite geomembrane is laid on the bottom of the drainage dead pipe.

可以理解的是,在施工前,需要对基底(地基)做表层处理和加固处理,具体地:It is understandable that, before construction, the substrate (foundation) needs to be surface treated and reinforced, specifically:

地基表层处理:Ground surface treatment:

1)山体填筑施工前排水疏干地表,整平地面;原地面清除表土,按规定回填、压实,其标准同山体要求;1) Before the construction of mountain filling, drain the ground and level the ground; remove the topsoil from the original ground, backfill and compact according to the regulations, and the standards are the same as the mountain requirements;

2)山体地基横、纵向坡度陡于1:10地段,基底挖台阶,台阶高度不大于0.6m,台阶宽度不小于1.0m,台阶底设4%向外倾斜的坡度。2) The horizontal and vertical slopes of the mountain foundation are steeper than 1:10, and the base is dug with steps. The height of the steps is not more than 0.6m, the width of the steps is not less than 1.0m, and the bottom of the steps is set with a slope of 4% inclined outward.

地基加固处理:Ground reinforcement treatment:

1)沿省道山体边坡设置300m两级加筋挡土墙,一级加筋土挡墙基底挖除换填不小于1.0m厚的三七灰土+重型碾压。三七灰土采用挖除的原地基土,剔除碎砖后就地掺30%(配比按体积计)灰改良。三七灰土压实标准采用压实系数K不小于0.90,7d饱和无侧限抗压强度不小于300kPa。换填三七灰土后地基的地基承载力特征值达到180kPa。1) Set up a 300m two-level reinforced retaining wall along the mountain slope of the provincial road, and excavate and replace the base of the first-level reinforced soil retaining wall with not less than 1.0m thick Panax notoginseng soil + heavy rolling. Panax notoginseng lime soil adopts excavated original foundation soil, and after removing broken bricks, 30% (proportion by volume) ash is added on the spot to improve. The compaction standard of Panax notoginseng lime soil adopts the compaction coefficient K of not less than 0.90, and the 7d saturated unconfined compressive strength of not less than 300kPa. The characteristic value of the foundation bearing capacity of the foundation after replacement of Panax notoginseng lime soil reaches 180kPa.

2)山体基底填土层进行压实处理,其中填土层厚大于2.5m的地段基底采用冲击碾压压实,其它地段采用重型碾压,碾压后地基的压实系数不小于0.9。2) The mountain base fill layer shall be compacted. The base of the section with the fill layer thickness greater than 2.5m shall be compacted by impact rolling, and the other sections shall be compacted by heavy rolling. The compaction coefficient of the foundation after rolling shall not be less than 0.9.

3)山体南坡原地面以上,靠坡脚20~25m范围以内铺垫一层土工布+0.6m厚垫层(0.15m厚中粗砂+0.15m厚砂夹砾石+0.3m厚碎石),较陡地段需做台阶式垫层处理。3) Above the original ground on the southern slope of the mountain, lay a layer of geotextile + 0.6m thick cushion (0.15m thick medium and coarse sand + 0.15m thick sand with gravel + 0.3m thick gravel) within 20~25m of the foot of the slope, Steep sections need to be treated with stepped cushion.

在对堆筑体本体10进行填筑时,其填料可以分为两部分,山体本体粉土填筑和山体表层黏土填筑;施工前应严格控制填料的含水量,当填料的含水量大于最优含水量时,采用翻松、晾晒、风干或换土回填、均匀掺入干土等措施来降低含水量,若填料含水量过大夯实时产生橡皮土,应翻松晾干至最佳含水量时再填筑。若含水量偏低,可采用预先洒水润湿。严格控制填料的含水量,确保山体土方填筑质量;山体堆筑以冲击碾压为主,局部采用重型碾压;山体本体填筑粉土,压实系数K不小于0.9,地基系数K30不小于80MPa/m;山体表层填筑0.5m厚的黏土,压实系数K不小于0.9,地基系数K30不小于80MPa/m;填料采用推土机摊铺,16T以上压路机碾压6-8遍,分区分层压实,分层厚度为压实后0.3m一层,每压实一层后对地基的压实质量进行压实系数K和地基系数K30检验,检测数量为每2000m2不小于4处。山体表层按设计要求填筑0.5m粘土,填筑方法为每一区段15m-20m山体粉土填筑碾压完成后,由挖掘机进行修整,然后铺设粘土整平(分两层铺土碾压),最后采用压路机沿等高线压实(压路机倾斜不大于10度时),大于10度时采用上下坡碾压。When filling the body 10 of the stack, the filling can be divided into two parts, the mountain body silt filling and the mountain surface clay filling; the water content of the filling should be strictly controlled before construction, and when the water content of the filling is greater than the maximum When the water content is excellent, measures such as loosening, drying, air-drying or soil replacement and backfilling, and evenly mixing dry soil are used to reduce the water content. Refill when there is water. If the water content is low, it can be moistened with pre-sprinkling water. Strictly control the water content of the filler to ensure the quality of earthwork filling in the mountain; the mountain mass is mainly built by impact rolling, and heavy rolling is used locally; the mountain body is filled with silt, the compaction coefficient K is not less than 0.9, and the foundation coefficient K30 is not less than 80MPa/m; the surface of the mountain is filled with 0.5m thick clay, the compaction coefficient K is not less than 0.9, and the foundation coefficient K30 is not less than 80MPa/m; For compaction, the layer thickness is 0.3m after compaction. After each compaction layer, the compaction coefficient K and the foundation coefficient K30 of the foundation are tested for the compaction quality, and the number of inspections is not less than 4 per 2000m2. The surface of the mountain is filled with 0.5m of clay according to the design requirements. The filling method is that each section of 15m-20m of mountain silt is filled and rolled, and then trimmed by an excavator, and then laid with clay for leveling (divided into two layers of soil and rolling). Pressing), and finally use the road roller to compact along the contour line (when the road roller is inclined not more than 10 degrees), and when it is more than 10 degrees, it is rolled up and down.

在对堆筑体的边坡进行防护时,山体边坡采用土工格栅加固,宽度为6.0m,层间距0.6m。土工格栅采用双向拉伸塑料土工格栅,材质为加入炭黑的聚丙烯,炭黑含量≥2%并均匀分布,抗拉强度纵、横向抗拉强度不小于50kN/m,纵/横向标称伸长率≤15/13%。When protecting the slope of the stack, the slope of the mountain is reinforced with geogrids with a width of 6.0m and a layer spacing of 0.6m. The geogrid adopts biaxially stretched plastic geogrid, the material is polypropylene with carbon black added, the carbon black content is ≥2% and evenly distributed, the longitudinal and transverse tensile strengths are not less than 50kN/m, and the longitudinal/horizontal standard Said elongation ≤ 15/13%.

山体表面满铺设易降解的三维土工网垫,网垫幅宽不小于5.0m,材料基本性能满足相关要求。纵横向每隔1m左右用不短于15cm竹钉垂直打入边坡固定网垫;网垫搭接宽度不小于2cm,搭接部位适当加密竹钉。铺设完成后需对坡面夯拍一遍,使网垫与坡面密贴,在山体表面撒播草籽绿化。The surface of the mountain is covered with easily degradable three-dimensional geonet mats, the width of the mats is not less than 5.0m, and the basic properties of the materials meet the relevant requirements. Vertically and horizontally every 1m or so, use bamboo nails no shorter than 15cm to vertically drive into the slope to fix the mesh pad; the overlap width of the mesh pad is not less than 2cm, and the overlapping parts are properly encrypted with bamboo nails. After the laying is completed, it is necessary to ram the slope surface once, so that the mesh pad is closely attached to the slope surface, and grass seeds are sown on the mountain surface for greening.

坡脚加固:山体东、西、南坡设置卵石截洪沟和坡脚挡墙,坡脚挡墙上设置

Figure GDA0002500784600000121
排水管,山体雨水能顺利排入截洪沟内。Reinforcement at the foot of the slope: the east, west and south slopes of the mountain are set with pebble flood intercepting ditch and the retaining wall at the foot of the slope, and the retaining wall at the foot of the slope is set
Figure GDA0002500784600000121
Drainage pipes, the rainwater from the mountain can be smoothly discharged into the flood intercepting ditch.

排水盲管的设置,袋装砂砾石反滤层右侧垫层以上3m于适宜位置设纵向排水盲管,盲沟截面采用0.3m*0.3m,纵向间距5m,呈梅花形布置。盲沟底部复合土工膜采用无纺布复合土工膜,二布一膜结构。复合土工膜纵、横向抗拉断裂强度≥20KN/m,CBR顶破强力≥2.5KN,垂直渗透系数≤1.0×10-11cm/s,膜材采用加入炭黑的高密度聚乙烯,膜厚≥0.3mm。山体坡地面以上靠坡脚20~25m范围以内铺垫一层0.6m厚排水垫层,通过PVC泄水管排入卵石截洪沟中。For the setting of drainage blind pipes, vertical drainage blind pipes are set at suitable positions 3m above the right cushion of the bagged sand and gravel filter layer. The composite geomembrane at the bottom of the blind ditch adopts a non-woven composite geomembrane, with two fabrics and one membrane structure. Composite geomembrane longitudinal and transverse tensile breaking strength ≥ 20KN/m, CBR bursting strength ≥ 2.5KN, vertical permeability coefficient ≤ 1.0×10-11cm/s, the membrane material is high-density polyethylene with carbon black added, and the film thickness ≥ 0.3mm. A layer of drainage cushion with a thickness of 0.6m shall be laid within the range of 20-25m above the slope foot of the mountain slope, which shall be discharged into the pebble flood interception ditch through the PVC drainage pipe.

在对堆筑体进行检测时,山体西坡、南坡地面以上靠坡脚20~25m范围以内铺垫一层0.6m厚排水垫层,通过PVC泄水管排入卵石截洪沟中。边坡坡顶水平位移和垂直位移观测桩采用直径100mm的松原木制作,长1m,桩顶中心埋设一小钢钉。开始施工后即可布设坡脚和挡土墙外侧的位移观测桩,坡脚和挡土墙顶部位移观测桩待施工至相应高程后埋设,并测试其初读数。When testing the stack, a layer of 0.6m-thick drainage cushion should be laid within 20-25m above the ground on the west and south slopes of the mountain, and then drained into the pebble flood interception ditch through PVC drainage pipes. The horizontal and vertical displacement observation piles at the top of the slope are made of pine logs with a diameter of 100 mm and a length of 1 m. A small steel nail is embedded in the center of the top of the pile. The displacement observation piles at the toe of the slope and the outer side of the retaining wall can be laid out after the construction starts. The displacement observation piles at the toe of the slope and the top of the retaining wall shall be buried after the construction reaches the corresponding elevation, and the initial readings shall be tested.

本工程地基沉降和边坡坡顶位移按采用三等位移监测网的要求测量。采用裂缝计量测挡土墙顶部1.5H(H为边坡高度)范围内地表裂缝发展情况。监测精度不低于1mm。The foundation settlement and slope top displacement of this project shall be measured according to the requirements of the third-level displacement monitoring network. The crack measurement was used to measure the development of surface cracks within the range of 1.5H (H is the height of the slope) at the top of the retaining wall. The monitoring accuracy is not less than 1mm.

土压力传感器安装前应标定,安装时,将土压力盒受力膜(承压膜)面朝上,土压力盒底部填入约5cm中细砂压实垫平,用水平尺控制将土压力盒安装水平。安装好土压力盒后在其周围覆盖10cm厚的中细砂,压实。压力监测传感器(土压力盒)精度不宜大于5%FS(满量程);The earth pressure sensor should be calibrated before installation. When installing, put the stress-bearing membrane (pressure-bearing membrane) of the earth pressure box facing up, fill the bottom of the earth pressure box with about 5cm of medium-fine sand to compact it, and use a level ruler to control the earth pressure. The box is installed horizontally. After the earth pressure box is installed, cover it with 10cm thick medium-fine sand and compact it. The accuracy of the pressure monitoring sensor (earth pressure box) should not be greater than 5% FS (full scale);

柔性位移计安装前应标定,当土工隔栅下层填土碾压完成后,将土工隔栅按照设计长度铺设在填筑碾压完成的平面上,牢固安装柔性位移计,并用细砂将柔性位移计底部垫平、密实。在其周围覆盖20cm的细砂或中砂压实。柔性位移计测试精度不宜大于0.01m。The flexible displacement meter should be calibrated before installation. When the lower layer of the geogrid is filled and compacted, the geogrid should be laid on the flat surface after the filling and rolling according to the design length, and the flexible displacement meter should be firmly installed. The bottom of the meter is flat and dense. Cover it with 20cm of fine or medium sand for compaction. The test accuracy of the flexible displacement meter should not be greater than 0.01m.

监测频率、周期,所有元件埋设后,必须测试初始读数,在山体正式填筑前,必须对所有元件进行复测,作为正式初始读数。监测工程观测的频次应满足施工阶段要求,当外部环境条件(天气、施工等)发生变化时应及时观测。填筑完成沉降变形观测期不少于6个月,并应经过一个雨季。Monitor the frequency and period. After all components are buried, the initial reading must be tested. Before the mountain is officially filled, all components must be re-tested as the official initial reading. The frequency of monitoring engineering observation should meet the requirements of the construction stage, and should be observed in time when the external environmental conditions (weather, construction, etc.) change. The settlement and deformation observation period shall be no less than 6 months after the filling is completed, and a rainy season shall pass.

监测技术标准与警戒值,工作基准点按二等水准测量的要求进行精确测量,沉降观测和水平位移观测按三等水准测量的要求进行精确测量。若遇到下列可能影响基坑安全的情况之一时,应立即报警:Monitoring technical standards and warning values, working datum points shall be accurately measured according to the requirements of the second-class leveling survey, and settlement observation and horizontal displacement observation shall be accurately measured according to the requirements of the third-level leveling survey. If you encounter one of the following situations that may affect the safety of the foundation pit, you should immediately call the police:

边坡支护结构坡顶的最大水平位移已大于填土高度的1/500或20mm,以及水平位移速率已连续3天大于2mm/d;The maximum horizontal displacement of the slope top of the slope supporting structure has been greater than 1/500 or 20mm of the fill height, and the horizontal displacement rate has been greater than 2mm/d for 3 consecutive days;

填筑期地表沉降速率大于10mm/d;During the filling period, the surface settlement rate is greater than 10mm/d;

边坡底部或周围土体出现可能导致剪切破坏的迹象或其他可能影响安全的征兆(如少量流砂、涌土、隆起、陷落等);The bottom of the slope or the surrounding soil shows signs that may lead to shear failure or other signs that may affect safety (such as a small amount of quicksand, soil gushing, uplift, collapse, etc.);

坡顶附近出现新裂缝;New cracks appear near the top of the slope;

根据经验判断认为,已出现其他必须报警的情况。Judging from experience, other situations have occurred that must be reported to the police.

根据本发明的一个实施例,生态修复工程中城市余泥渣土堆筑体的施工方法,进一步包括以下步骤:S7:根据工程概况确定堆筑体X、Y、Z三个方向的尺寸,建立三维模型,对所述三维模型划分网格后,通过在三维模型中设置多个位移监测点、多个应力监测点对所述模块式加筋土挡墙的最高断面的受力、变形及稳定性进行分析。According to an embodiment of the present invention, the construction method of the urban residual mud and slag mound in the ecological restoration project further includes the following steps: S7: Determine the dimensions of the mound in the three directions of X, Y, and Z according to the general situation of the project, and establish Three-dimensional model, after dividing the three-dimensional model into a grid, by setting multiple displacement monitoring points and multiple stress monitoring points in the three-dimensional model, the stress, deformation and stability of the highest section of the modular reinforced soil retaining wall are sex analysis.

根据本发明的一个实施例,S4中,在所述模块式加筋土挡墙的面层布置混凝土预制模块,且相邻的所述混凝土预制块之间设有伸缩缝。According to an embodiment of the present invention, in S4, prefabricated concrete modules are arranged on the surface layer of the modular reinforced earth retaining wall, and expansion joints are provided between the adjacent prefabricated concrete blocks.

根据本发明的一个实施例,S5中:所述边坡包裹体包括双向拉伸土工格栅及土工布,所述双向拉伸土工格栅内填充炭黑量大于2%的聚丙烯:所述排水盲管呈梅花形布置,所述复合土工膜采用无纺土工布贴附加入炭黑的高密度聚乙烯膜,高密度聚乙烯膜的膜厚大于0.3mm。According to an embodiment of the present invention, in S5: the slope inclusion includes a biaxially oriented geogrid and a geotextile, and the biaxially oriented geogrid is filled with polypropylene with an amount of carbon black greater than 2%: the The blind drainage pipes are arranged in a plum blossom shape, and the composite geomembrane is made of non-woven geotextiles pasted with a high-density polyethylene film with carbon black added, and the film thickness of the high-density polyethylene film is greater than 0.3 mm.

可以理解的是,在S1中,对基底的表面进行处理,并在基底上设置台阶,台阶与堆筑体的陡坡处对应。S1可以理解为:对地基表层进行处理的步骤,具体地,在对堆筑体,例如为山体,填筑施工前应排水疏干地表,整平地面;地基不处理地段清除表土,按规定回填、压实,其标准同山体要求。山体地基横、纵向坡度陡于1:10地段,基底应挖台阶,台阶高度小于0.6m,台阶宽度大于1.0m,台阶底设4%向外倾斜的坡度。It can be understood that, in S1, the surface of the base is processed, and steps are provided on the base, and the steps correspond to the steep slope of the stack. S1 can be understood as: the steps of treating the surface of the foundation. Specifically, before the filling construction of a stacked body, such as a mountain, the surface should be drained and the ground should be leveled; , compaction, its standards are the same as the mountain requirements. The lateral and longitudinal slopes of the mountain foundation are steeper than 1:10, and the base should be dug with steps. The height of the steps should be less than 0.6m, the width of the steps should be greater than 1.0m, and the bottom of the steps should have a slope of 4% inclined outward.

S2中,对所述堆筑体基底填土层进行压实,并在模块式加筋土挡墙的基底处换填三七灰土并压实,在基底的坡脚20m-25m范围以内先铺设一层土工布,再铺设垫层,垫层可以被设置成台阶形。S2可理解为,对地基进行加固处理的步骤,具体地,可以在模块式加筋土挡墙基底挖除换填的三七灰土并采用重型碾压。三七灰土采用挖除的原地基土掺灰改良。三七灰土底面地基土碾压后的地基承载力特征值要求达到150kPa,换填三七灰土后地基的地基承载力特征值要求达到180kPa。山体基底填土层进行压实处理,其中填土层厚大于2.5m的地段基底采用冲击碾压压实,其它地段采用重型碾压,碾压后地基的压实系数不小于0.9。In S2, compaction is carried out on the base fill layer of the stacking body, and the base of the modular reinforced soil retaining wall is replaced with Panax notoginseng lime soil and compacted, and the base is first laid within the range of 20m-25m from the slope foot of the base. A layer of geotextile, and then laying a cushion, the cushion can be set into a step shape. S2 can be understood as the step of reinforcing the foundation. Specifically, the replaced Panax notoginseng lime soil can be excavated at the base of the modular reinforced soil retaining wall and heavy-duty rolling is used. Notoginseng lime soil was improved by mixing ash with the excavated original foundation soil. The characteristic value of the foundation bearing capacity of the foundation soil on the bottom surface of Panax notoginseng lime soil after rolling is required to reach 150kPa, and the characteristic value of the foundation bearing capacity of the foundation after replacement with notoginseng lime soil is required to reach 180kPa. The mountain base fill layer shall be compacted. The base of the section with the fill layer thickness greater than 2.5m shall be compacted by impact rolling, and the other sections shall be compacted by heavy rolling. The compaction coefficient of the foundation after rolling shall not be less than 0.9.

S3中,对堆筑体分区分层填充、分层压实,且堆筑体采用粉土填充,堆筑体主峰周围采用黏土填筑。S3可以理解为:对堆筑体进行填充的步骤,具体地,堆筑体可以理解为山体,山体主峰周围填筑厚度大于0.6m的黏土,压实系数K不小于0.9,地基系数K30建议不小于80MPa/m。山体可以采用粉土填筑,压实系数K不小于0.9,地基系数K30建议不小于80MPa/m。山体填料需分区分层填筑,分层压实,填料压实标准采用压实系数与地基系数结合作为控制指标。In S3, the stacked body is filled and compacted in layers, and the stacked body is filled with silt, and the surrounding of the main peak of the stacked body is filled with clay. S3 can be understood as: the step of filling the stack. Specifically, the stack can be understood as a mountain. The main peak of the mountain is filled with clay with a thickness of more than 0.6m, the compaction coefficient K is not less than 0.9, and the foundation coefficient K30 is not recommended. less than 80MPa/m. The mountain can be filled with silt, the compaction coefficient K is not less than 0.9, and the foundation coefficient K30 is recommended not to be less than 80MPa/m. The mountain filling needs to be filled in different layers and compacted. The compaction standard of the packing adopts the combination of the compaction coefficient and the foundation coefficient as the control index.

S4中,使用模块式加筋土挡墙进行收坡,且采用的模块式加筋土挡墙的高度为2.83m-7.02m。In S4, the modular reinforced soil retaining wall is used for slope closing, and the height of the adopted modular reinforced soil retaining wall is 2.83m-7.02m.

S5中,采用边坡包裹体对所述堆筑体陡于1:4的边坡进行加固,并在边坡包裹体下方设置碎石和浆砌片石基础;S5可以理解为:边坡防护的步骤,具体地,山体陡于1:4的边坡采用包裹体加固,每0.3m一层用土工格栅加土工布包裹,宽度不小于4.0m。In S5, slope inclusions are used to reinforce the side slopes of the stacked body that are steeper than 1:4, and gravel and mortar rubble foundations are set under the slope inclusions; S5 can be understood as: slope protection Steps, specifically, the slope of the mountain body steeper than 1:4 is reinforced with inclusions, and every 0.3m layer is wrapped with geogrid and geotextile, and the width is not less than 4.0m.

S6中,在模块式加筋土挡墙下部设置排水盲管,并在排水盲管底部铺设复合土工膜。S5可以理解为:山体排水工程的步骤。In S6, a drainage blind pipe is set at the lower part of the modular reinforced earth retaining wall, and a composite geomembrane is laid at the bottom of the drainage blind pipe. S5 can be understood as: the steps of the mountain drainage project.

根据本发明的实施例的堆筑体施工方法,整个堆筑体的稳定性大幅提高,合理得利用了建筑余土进行堆筑体建设,便于更有效地对了生态环境进行改造,具有良好的应用前景。According to the construction method of the stack body according to the embodiment of the present invention, the stability of the whole stack body is greatly improved, the residual construction soil is reasonably used for the stack body construction, the ecological environment can be transformed more effectively, and the application prospects.

根据本发明的一个实施例,在S2中山体基底在坡脚20m-25m范围以内铺垫一层的垫层,其中,中粗砂的厚度可以为0.15m,厚砂夹砾石的厚度可以为0.15m,厚碎石的厚度可以为0.3m,垫层表层铺设一层土工布,较陡地段需做台阶式垫层处理。According to an embodiment of the present invention, in S2, the mountain base is laid with a layer of cushion within the range of 20m-25m at the foot of the slope, wherein the thickness of medium and coarse sand can be 0.15m, and the thickness of thick sand with gravel can be 0.15m , The thickness of the thick gravel can be 0.3m, a layer of geotextile is laid on the surface of the cushion, and the steeper section needs to be treated with a stepped cushion.

根据本发明的一个实施例,例如,根据工程概况,加筋土挡墙墙高2.83-7.02m。选填土厚度较大,。整个模型宽度(X方向)取60m,挡墙底部以外取10.8m宽;竖直(Z方向)向模型底部标高为零;水平厚度(Y方向)取0.5m。According to one embodiment of the present invention, for example, according to the project overview, the height of the reinforced earth retaining wall is 2.83-7.02m. Choose a thicker fill. The width of the entire model (X direction) is 60m, and the width outside the bottom of the retaining wall is 10.8m; the vertical (Z direction) is zero to the bottom of the model; the horizontal thickness (Y direction) is 0.5m.

本数值计算可以应用FLAC3D快速拉格朗日差分分析软件。根据上述模型及各地质单元尺寸,借助ansys软件建立假三维模型,划分网格后导入FLAC3D进行计算及后处理。建好的模型如图2所示。单元类型为六面体单元,模型总计7836个节点,3796个单元。This numerical calculation can use the FLAC3D fast Lagrangian difference analysis software. According to the above model and the size of each geological element, a fake 3D model was established with the help of ansys software, and after dividing the mesh, it was imported into FLAC3D for calculation and post-processing. The built model is shown in Figure 2. The element type is hexahedral element, and the model has a total of 7836 nodes and 3796 elements.

根据边坡及加筋土挡墙特征,设置1、2、3共3个位移监测点,分别位于填土顶部、斜坡中部、加筋土挡墙顶部;设置1个测斜孔,位于斜坡中部,深度为10m;设置4、5、6共3个应力监测点,位于混凝土面板和填料接触界面,4号测点位于加筋土挡墙顶部往下2.5m,5号测点位于加筋土挡墙顶部往下5m,6号测点位于混凝土面板底部和加筋土挡墙填料交界处。土工格栅为结构单元,无法在其中布置监测点,其应力可以通过计算结果显示。According to the characteristics of the slope and the reinforced soil retaining wall, three displacement monitoring points 1, 2 and 3 are set up, which are located at the top of the fill, the middle of the slope, and the top of the reinforced soil retaining wall. , the depth is 10m; a total of 3 stress monitoring points 4, 5 and 6 are set, which are located at the contact interface between the concrete panel and the filler. The No. 4 measuring point is located 2.5m down from the top of the reinforced soil retaining wall, and the No. 5 measuring point is located in the reinforced soil. The top of the retaining wall is 5m down, and the No. 6 measuring point is located at the junction of the bottom of the concrete panel and the filling of the reinforced soil retaining wall. Geogrid is a structural unit, and monitoring points cannot be arranged in it, and its stress can be displayed by calculation results.

采用FLAC3D快速拉格朗日差分分析软件,以上述模型及材料参数进行以下工作:Using the FLAC3D fast Lagrangian differential analysis software, the following work is carried out with the above model and material parameters:

第一,初始应力场计算。该状态下采用弹性模型进行天然状态下初始应力场计算,地层在自重应力场下固结。通过计算结果,即应力场和位移场,可判断模型是否正常。First, the initial stress field calculation. In this state, the elastic model is used to calculate the initial stress field in the natural state, and the formation is consolidated under the self-weight stress field. Through the calculation results, namely stress field and displacement field, it can be judged whether the model is normal or not.

第二,加筋土挡墙的计算。清零前阶段产生的位移场,为该阶段计算做准备。该状态激活土工格栅结构单元geogrid。利用摩尔-库伦模型计算挡墙及边坡的变形及稳定性。Second, the calculation of the reinforced earth retaining wall. Clear the displacement field generated in the previous stage to prepare for the calculation of this stage. This state activates the geogrid structural element geogrid. The deformation and stability of retaining walls and slopes were calculated using the Moore-Coulomb model.

第三,分以下情况进行计算。Third, the calculation is carried out in the following cases.

(1)不同土工格栅弹性模量:10GPa、26GPa、52GPa、78GPa。(1) Elastic modulus of different geogrids: 10GPa, 26GPa, 52GPa, 78GPa.

(2)不同土工格栅间距:30cm、45cm、60cm、75cm。(2) Different geogrid spacing: 30cm, 45cm, 60cm, 75cm.

(3)不同加筋土挡墙填料粘聚力:0、0.1kPa、1kPa、10kPa。(3) Cohesion of different reinforced soil retaining wall fillers: 0, 0.1kPa, 1kPa, 10kPa.

(4)不同加筋土挡墙填料弹性模量:1MPa、10MPa、50MPa、100MPa。(4) Elastic modulus of different reinforced soil retaining wall fillers: 1MPa, 10MPa, 50MPa, 100MPa.

(5)不同加筋土挡墙填料摩擦角:20°、25°、30°、35°。(5) Friction angles of different reinforced soil retaining wall fillers: 20°, 25°, 30°, 35°.

根据本发明的一个实施例,数值模拟计算主要分析加筋土挡墙最高断面,该断面为整个加筋土挡墙边坡最危险断面,通过对该断面的受力、变形及稳定性分析,只要改断面的变形及稳定性满足安全要求,则整个加筋土挡墙边坡满足安全性要求。此外,考虑不同土工格栅强度参数、不同土工格栅间距、不同加筋土挡墙填料强度参数,分析这些参数对加筋土挡墙变形及稳定性的影响规律。由于稳定性安全系数计算采用的强度折减迭代方法计算时间较长,本次数值计算只对设采用的状态参数下的最不利断面的稳定性安全系数进行计算分析。According to an embodiment of the present invention, the numerical simulation calculation mainly analyzes the highest section of the reinforced soil retaining wall, which is the most dangerous section of the slope of the entire reinforced soil retaining wall. As long as the deformation and stability of the modified section meet the safety requirements, the entire reinforced earth retaining wall slope meets the safety requirements. In addition, considering different geogrid strength parameters, different geogrid spacing, and different reinforced soil retaining wall filler strength parameters, the influence of these parameters on the deformation and stability of the reinforced soil retaining wall was analyzed. Due to the long calculation time of the strength reduction iterative method used in the calculation of the stability safety factor, this numerical calculation only calculates and analyzes the stability safety factor of the most unfavorable section under the adopted state parameters.

因数值计算无法精确分层碾压过程中土层的施工变形,本次数值计算采用弹性模型计算使其平衡后位移场清零,再利用摩尔-库伦模型计算最终变形和稳定性。鉴于数值计算的目的和效果,位移场在定性上能反应变形趋势,在定量上可能和实际变形大学有一些误差,尤其是考虑荷载的情况下。和设计计算相比,数值计算稳定性安全系数计算过程采用强度折减法,因此更能反映边坡实际破坏过程,稳定性分析和设计计算相比较为可靠。最不利断面分析:对天然状态下初始应力场进行计算如果应力场呈层状均匀分布,无异常状态,随着地层越深应力越大。说明该数值计算模型无网格划分错误,可进行下一步计算。Because the numerical calculation cannot accurately calculate the construction deformation of the soil layer in the process of stratified rolling, the elastic model is used in this numerical calculation to clear the displacement field after equilibrium, and then the Moore-Coulomb model is used to calculate the final deformation and stability. In view of the purpose and effect of numerical calculation, the displacement field can qualitatively reflect the deformation trend, but quantitatively there may be some errors with the actual deformation, especially when considering the load. Compared with the design calculation, the numerical calculation stability safety factor calculation process adopts the strength reduction method, so it can better reflect the actual failure process of the slope, and the stability analysis is more reliable than the design calculation. The most unfavorable section analysis: Calculate the initial stress field in the natural state. If the stress field is uniformly distributed in layers, there is no abnormal state, and the stress increases with the deeper the formation. It shows that the numerical calculation model has no mesh division error, and the next calculation can be carried out.

无超载情况:No overload condition:

位移分析,位移较大区在加筋土挡墙及其后的边坡约30m范围内。加筋土挡墙的总位移在16mm-28mm范围内,由于承受挡墙的推力作用,挡墙底角前反压的土体位移最大,表现为隆起,最大隆起量35mm左右;挡墙后的土体位移最大部位在加筋土挡墙顶部背后的坡体表层,最大水平位移约12mm,最大沉降约20mm。加筋土挡墙的位移比墙后土体位移小,并且挡墙上下位移差异很小。位移矢量场显示坡体及挡墙的位移矢量场较均匀,没有出现位移突变的区域。如果挡墙和坡体随着计算过程位移变化曲线相近,都是随着计算过程不断增大,加筋土挡墙顶部的位移比坡体中部和坡体顶部大,为坡体中部和顶部的位移十分相近。开始时加筋土挡墙顶部的沉降十分缓慢,坡体的沉降比较突然,一定时间后挡墙沉降速率才变大,这是因为挡墙混凝土结构自身变形很小,当墙后和墙底的土体变形后才会引起挡墙变形。最终,墙顶的沉降量比坡体的沉降量小,监测点的沉降均小于9mm。Displacement analysis shows that the larger displacement area is within about 30m of the reinforced earth retaining wall and the slope behind it. The total displacement of the reinforced soil retaining wall is in the range of 16mm-28mm. Due to the thrust of the retaining wall, the soil displacement of the back pressure in front of the bottom corner of the retaining wall is the largest, which is manifested as uplift, and the maximum uplift is about 35mm; The largest position of soil displacement is on the slope surface layer behind the top of the reinforced earth retaining wall, the maximum horizontal displacement is about 12mm, and the maximum settlement is about 20mm. The displacement of the reinforced soil retaining wall is smaller than that of the soil behind the wall, and the difference between the upper and lower displacements of the retaining wall is small. The displacement vector field shows that the displacement vector field of the slope and retaining wall is relatively uniform, and there is no region with sudden displacement. If the displacement curves of the retaining wall and the slope body are similar with the calculation process, they are both increasing with the calculation process. The displacements are very close. At the beginning, the settlement of the top of the reinforced earth retaining wall is very slow, the settlement of the slope is relatively sudden, and the settlement rate of the retaining wall becomes larger after a certain period of time. This is because the deformation of the concrete structure of the retaining wall itself is very small. Deformation of the retaining wall occurs only after the soil is deformed. Finally, the settlement of the top of the wall is smaller than that of the slope, and the settlement of the monitoring points is less than 9mm.

受力分析,加筋土挡墙底部和挡墙中下部填土出现最大主应力集中。墙底应力集中是由于挡墙的推力造成,挡墙填土应力集中是由于坡体的下滑力作用于整个加筋土填料后部,说明加筋土挡墙对边坡起到很好的拦挡效果。加筋土挡墙的面板是小主应力集中区,由于挡墙后的土体推力作用,挡墙处理张拉趋势,并出现拉应力,但拉应力量值很小。The stress analysis shows that the maximum principal stress concentration occurs at the bottom of the reinforced soil retaining wall and the filling in the middle and lower parts of the retaining wall. The stress concentration at the bottom of the wall is caused by the thrust of the retaining wall, and the stress concentration of the retaining wall filling is due to the sliding force of the slope acting on the rear of the entire reinforced soil filling, indicating that the reinforced soil retaining wall plays a good role in blocking the slope. Effect. The panel of the reinforced soil retaining wall is a small principal stress concentration area. Due to the thrust of the soil behind the retaining wall, the retaining wall handles the tension trend and appears tensile stress, but the value of the tensile stress is small.

稳定性分析,加筋土挡墙以及边坡的未出现剪应变率明显增大区带,挡墙面层和填土间因为挤压作用其剪应变有所增大。挡墙底部前缘的地面剪应变率较大,由于该处地面隆起过大引起,因此应该采取重力反压措施。Stability analysis shows that the shear strain rate of the reinforced soil retaining wall and the slope does not appear to increase significantly, and the shear strain between the retaining wall layer and the filling increases due to the extrusion effect. The ground shear strain rate at the front edge of the bottom of the retaining wall is relatively large, which is caused by the excessive ground uplift there, so gravity backpressure measures should be taken.

根据本发明的一个实施例,砂加砾石用包裹体包装,包裹体为塑料编织袋,包裹体压载宽度大于0.5m。由此,可以便于施工,降低施工成本。According to an embodiment of the present invention, the sand and gravel are packed with inclusions, the inclusions are plastic woven bags, and the ballast width of the inclusions is greater than 0.5 m. Thereby, the construction can be facilitated and the construction cost can be reduced.

根据本发明的一个实施例,S4中,模块式加筋土挡墙包括炭黑量≥2%的单向拉伸聚乙烯塑料制成的土工格栅,所述土工格栅长7m-9m,竖向间距大于0.3m,所述土工格栅回折长大于1.5m,幅间搭接大于0.1m。优选地,模块式加筋土挡墙内的填料采用细圆砾土。优选地,S4中,在模块式加筋土挡墙的面层布置混凝土预制模块,且相邻的所述混凝土预制块之间设有伸缩缝。土工格栅采用双向拉伸塑料土工格栅,材质为加入炭黑的聚丙烯,炭黑含量大于等于2%并均匀分布,抗拉强度纵、横向抗拉强度不小于50kN/m,纵/横向标称伸长率小于等于15/13%。土工布采用无纺土工布,土工布纵、横向抗拉断裂强度大于等于12KN/m,纵、横向撕破强力大于等于0.4KN,CBR顶破强力大于等于1.5KN,梯度比GR小于等于3。包裹体下方设置碎石和浆砌片石基础,碎石基础断面尺寸为1.4*0.15m,浆砌片石基础断面尺寸为1.6*0.15m。可以理解的是,模块式加筋土挡墙的方案与对换填垫层加压实地基和水泥土挤密桩方案相比,前者属于比较简便的工艺技术和施工设备,耗费较少量的材料,施工周期短并且对管线工程影响小。由此,可以有效保证堆筑体的结构的稳定性,且这种结构更有利于推广和使用。According to an embodiment of the present invention, in S4, the modular reinforced earth retaining wall includes a geogrid made of uniaxially stretched polyethylene plastic with a carbon black content of ≥2%, and the geogrid is 7m-9m long, The vertical spacing is greater than 0.3m, the folded length of the geogrid is greater than 1.5m, and the overlap between the panels is greater than 0.1m. Preferably, the filler in the modular reinforced earth retaining wall adopts fine round gravel soil. Preferably, in S4, prefabricated concrete modules are arranged on the surface layer of the modular reinforced earth retaining wall, and expansion joints are provided between the adjacent prefabricated concrete blocks. The geogrid adopts biaxially stretched plastic geogrid, the material is polypropylene with carbon black added, the carbon black content is greater than or equal to 2% and evenly distributed, the longitudinal and transverse tensile strength is not less than 50kN/m, the longitudinal/transverse The nominal elongation is less than or equal to 15/13%. The geotextile is made of non-woven geotextile. The longitudinal and transverse tensile breaking strength of the geotextile is greater than or equal to 12KN/m, the longitudinal and transverse tearing strength is greater than or equal to 0.4KN, the bursting strength of CBR is greater than or equal to 1.5KN, and the gradient ratio GR is less than or equal to 3. The gravel and mortar rubble foundations are set below the inclusions. The section size of the gravel foundation is 1.4*0.15m, and the section size of the mortar rubble foundation is 1.6*0.15m. It can be understood that the scheme of modular reinforced soil retaining wall is a relatively simple process technology and construction equipment, and consumes less material, the construction period is short and the impact on pipeline engineering is small. Therefore, the stability of the structure of the stack can be effectively ensured, and this structure is more conducive to promotion and use.

可以理解的是,强降雨工况下,山体渗流对山体稳定性影响较大,为减小影响,宜减小山上地表水下渗,并加强山体内地下水排出。It is understandable that under heavy rainfall conditions, the mountain seepage has a great influence on the stability of the mountain. In order to reduce the impact, it is advisable to reduce the infiltration of the surface water on the mountain and strengthen the drainage of groundwater in the mountain.

主峰范围内填高最大其安全稳定性最低,需重点设计,故增设防渗粘土层,减小地表水下渗,并将其引向安全区域。模块式加筋土挡墙采用细圆砾土,墙背向山体内铺设梅花形布置的盲管,加强地下水排出。山体四周坡脚向山体内20-30m范围内设排水垫层,加快地下水排出。The maximum filling height within the main peak range has the lowest safety and stability, and requires key design. Therefore, an anti-seepage clay layer is added to reduce surface water infiltration and lead it to a safe area. The modular reinforced soil retaining wall is made of fine round gravel soil, and the back of the wall is laid with a plum-shaped blind pipe in the mountain to enhance the drainage of groundwater. Drainage cushions are set up in the 20-30m range from the foot of the slope around the mountain to the mountain to speed up the drainage of groundwater.

根据本发明的一个实施例,S5中:边坡包裹体包括双向拉伸土工格栅及土工布,双向拉伸土工格栅内填充有加入炭黑量大于2%的聚丙烯。具体地,土工格栅采用双向拉伸塑料土工格栅,材质为加入炭黑的聚丙烯,炭黑含量大于2%并均匀分布,抗拉强度纵、横向抗拉强度不小于50kN/m,纵/横向标称伸长率小于等于15/13%。土工布采用无纺土工布,土工布纵、横向抗拉断裂强度大于等于12KN/m,纵、横向撕破强力大于等于0.4KN,CBR顶破强力大于等于1.5KN,梯度比GR小于等于3。包裹体下方设置碎石和浆砌片石基础,碎石基础断面尺寸为1.4*0.15m,浆砌片石基础断面尺寸为1.6*0.15m。由此,可以提高堆筑体的整体稳定性。According to an embodiment of the present invention, in S5: the slope inclusion includes a biaxially oriented geogrid and a geotextile, and the biaxially oriented geogrid is filled with polypropylene with a carbon black content greater than 2%. Specifically, the geogrid is made of biaxially stretched plastic geogrid, the material is polypropylene with carbon black added, the carbon black content is greater than 2% and is evenly distributed, the longitudinal and transverse tensile strength / The nominal elongation in transverse direction is less than or equal to 15/13%. The geotextile is made of non-woven geotextile. The longitudinal and transverse tensile breaking strength of the geotextile is greater than or equal to 12KN/m, the longitudinal and transverse tearing strength is greater than or equal to 0.4KN, the bursting strength of CBR is greater than or equal to 1.5KN, and the gradient ratio GR is less than or equal to 3. The gravel and mortar rubble foundations are set below the inclusions. The section size of the gravel foundation is 1.4*0.15m, and the section size of the mortar rubble foundation is 1.6*0.15m. Thereby, the overall stability of the stack can be improved.

根据本发明的一个实施例,在S6中:所述排水盲管呈梅花形布置,所述复合土工膜采用无纺土工布贴附加入炭黑的高密度聚乙烯膜,高密度聚乙烯膜的膜厚大于0.3mm。具体地,袋装砂砾石反滤层右侧垫层以上3m于适宜位置设纵向排水盲管,盲沟截面采用0.3m*0.3m,纵向间距5m,呈梅花形布置,具体见详图。盲沟底部复合土工膜采用无纺布复合土工膜,二布一膜结构。复合土工膜纵、横向抗拉断裂强度大于等于20KN/m,CBR顶破强力大于等于2.5KN,垂直渗透系数小于等于1.0×10-11cm/s,膜材采用加入炭黑的高密度聚乙烯,膜厚大于等于0.3mm。土工布规格同边坡防护中的无纺土工布。According to an embodiment of the present invention, in S6: the drainage blind pipes are arranged in a plum blossom shape, and the composite geomembrane is made of non-woven geotextiles pasted with a high-density polyethylene film with carbon black added. The film thickness is greater than 0.3mm. Specifically, a vertical drainage blind pipe is set at a suitable position 3m above the cushion on the right side of the bagged sand and gravel filter layer. The section of the blind ditch is 0.3m*0.3m, and the longitudinal spacing is 5m, which is arranged in a plum blossom shape. The composite geomembrane at the bottom of the blind ditch adopts a non-woven composite geomembrane, with two fabrics and one membrane structure. The longitudinal and transverse tensile breaking strength of composite geomembrane is greater than or equal to 20KN/m, the bursting strength of CBR is greater than or equal to 2.5KN, and the vertical permeability coefficient is less than or equal to 1.0×10-11cm/s. The film thickness is greater than or equal to 0.3mm. Geotextile specifications are the same as non-woven geotextiles in slope protection.

在本说明书的描述中,参考术语“一个实施例”、“一些实施例”、“示例”、“具体示例”、或“一些示例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不必须针对的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任何的一个或多个实施例或示例中以合适的方式结合。此外,本领域的技术人员可以将本说明书中描述的不同实施例或示例进行接合和组合。In the description of this specification, description with reference to the terms "one embodiment," "some embodiments," "example," "specific example," or "some examples", etc., mean specific features described in connection with the embodiment or example , structure, material or feature is included in at least one embodiment or example of the present invention. In this specification, schematic representations of the above terms are not necessarily directed to the same embodiment or example. Furthermore, the particular features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, those skilled in the art may combine and combine the different embodiments or examples described in this specification.

尽管上面已经示出和描述了本发明的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本发明的限制,本领域的普通技术人员在本发明的范围内可以对上述实施例进行变化、修改、替换和变型。Although the embodiments of the present invention have been shown and described above, it should be understood that the above-mentioned embodiments are exemplary and should not be construed as limiting the present invention. Embodiments are subject to variations, modifications, substitutions and variations.

Claims (10)

1.一种生态修复工程中城市余泥渣土堆筑体,其特征在于,包括:设在基底上的堆筑体本体、设在所述堆筑体本体内的排水盲管、设在所述堆筑体本体至少一侧的侧面的挡墙组件和设在所述挡墙组件上方的土工格栅,所述挡墙组件包括:厚度为0.8m-1.2m的三七灰土层、设在所述三七灰土层上方的模块式加筋土挡墙、设在所述三七土层上并位于所述模块式加筋土挡墙外侧的卵石截洪沟、设在所述模块式加筋土挡墙与堆筑体本体之间的细圆砾土层、设在所述细圆砾土层上方的透水土工布和设在所述细圆砾土层与所述堆筑体本体之间的厚袋装砂砾石反滤层,其中,在所述细圆砾土层与所述基底层之间由下至上依次包括:土工布层和垫层,所述垫层的厚度为0.4-0.8m,所述垫层由下至上依次为:中粗砂层、砂夹砾石层和碎石层,其中所述土工布层纵、横向抗拉断裂强度≥12KN/m,纵、横向撕破强力≥0.4KN,CBR顶破强力≥1.5KN,梯度比GR≤3。1. an urban residual mud and slag mound in an ecological restoration project is characterized in that, comprising: the mound body that is arranged on the base, the drainage blind pipe that is positioned in the described mound body, the The retaining wall assembly on the side of at least one side of the stack body and the geogrid arranged above the retaining wall assembly, the retaining wall assembly includes: a Panax notoginseng lime soil layer with a thickness of 0.8m-1.2m, a The modular reinforced soil retaining wall above the Panax notoginseng soil layer, the pebble flood intercepting ditch located on the Panax notoginseng soil layer and located outside the modular reinforced soil retaining wall, and the The fine round gravel soil layer between the reinforced soil retaining wall and the body of the stack body, the permeable geotextile arranged above the fine round gravel soil layer, and the permeable geotextile provided between the fine round gravel soil layer and the body of the stack body The thick bagged sand and gravel filter layer between the layers, wherein, between the fine round gravel soil layer and the base layer, from bottom to top, it includes: a geotextile layer and a cushion layer, and the thickness of the cushion layer is 0.4- 0.8m, the cushion layers from bottom to top are: medium-coarse sand layer, sand sandwiched gravel layer and crushed stone layer, wherein the longitudinal and transverse tensile fracture strength of the geotextile layer is ≥12KN/m, and the longitudinal and transverse tearing Strength ≥0.4KN, CBR bursting strength ≥1.5KN, gradient ratio GR≤3. 2.根据权利要求1所述的生态修复工程中城市余泥渣土堆筑体,其特征在于,在所述细圆砾土层内设有多个土压力盒,在所述土工格栅上设有位移监测桩。2 . The urban residual mud and slag soil stack in the ecological restoration project according to claim 1 , wherein a plurality of earth pressure cells are arranged in the fine round gravel soil layer, and a plurality of earth pressure cells are arranged on the geogrid. Equipped with displacement monitoring piles. 3.根据权利要求1所述的生态修复工程中城市余泥渣土堆筑体,其特征在于,所述模块式加筋土挡墙包括具有第一预定高度的第一模块式加筋土挡墙和具有第二预定高度的第二模块式加筋土挡墙,所述第一模块式加筋土挡墙和所述第二模块式加筋土挡墙之间构造成台阶形,以在所述第一模块式加筋土挡墙一侧形成一级挡墙组件和在所述第二模块式加筋土挡墙的一侧形成二级挡墙组件。3 . The urban residual mud and slag building body in the ecological restoration project according to claim 1 , wherein the modular reinforced soil retaining wall comprises a first modular reinforced soil retaining wall with a first predetermined height. 4 . wall and a second modular reinforced earth retaining wall having a second predetermined height, the first modular reinforced earth retaining wall and the second modular reinforced earth retaining wall are configured in a stepped shape to A primary retaining wall assembly is formed on one side of the first modular reinforced earth retaining wall and a secondary retaining wall assembly is formed on one side of the second modular reinforced earth retaining wall. 4.根据权利要求1所述的生态修复工程中城市余泥渣土堆筑体,其特征在于,在所述堆筑体本体内设有用于对所述基底沉降监测的沉降板。4 . The urban residual mud and slag soil stack in an ecological restoration project according to claim 1 , wherein a settlement plate for monitoring the settlement of the base is provided in the body of the stack. 5 . 5.根据权利要求1所述的生态修复工程中城市余泥渣土堆筑体,其特征在于,所述垫层被设置成台阶形。5 . The urban residual mud and slag pile in the ecological restoration project according to claim 1 , wherein the cushion layer is arranged in a stepped shape. 6 . 6.根据权利要求1-5中任一项所述的生态修复工程中城市余泥渣土堆筑体的施工方法,其特征在于,包括以下步骤:6. according to the construction method of urban residual mud and slag mound in the ecological restoration project according to any one of claims 1-5, it is characterized in that, comprising the following steps: S1:对基底的表面进行处理,并在基底上设置高度小于0.6m、宽度大于1.0m的台阶,所述台阶与堆筑体本体的陡坡处对应;S1: The surface of the base is treated, and steps with a height of less than 0.6m and a width of greater than 1.0m are arranged on the base, and the steps correspond to the steep slope of the body of the stack; S2:对所述堆筑体本体基底填土层进行压实,并在模块式加筋土挡墙的基底处换填三七灰土并压实,在基底的坡脚20m-25m范围以内先铺设一层土工布,再铺设垫层;S2: Compact the soil layer at the base of the body of the stack, replace with notoginseng lime soil at the base of the modular reinforced soil retaining wall and compact it, and lay it first within 20m-25m of the slope foot of the base A layer of geotextile, and then lay a cushion; S3:对所述堆筑体本体分区分层填充、分层压实,且所述堆筑体本体采用粉土填充,所述堆筑体主峰周围采用黏土填筑,其中,所述粉土的压实系数K不小于0.9,地基系数K30不小于80MPa/m;所述黏土厚度为0.4m-0.6m,压实系数K不小于0.9,地基系数K30不小于80MPa/m,分层厚度为压实后0.3m一层,每压实一层后对地基的压实质量进行压实系数K和地基系数K30检验,检测数量为每2000m2不小于4处;S3: Filling and compacting the body of the stacked body in different zones and layers, and the body of the stacked body is filled with silt, and the surrounding of the main peak of the stacked body is filled with clay, wherein the silt is filled with clay. The compaction coefficient K is not less than 0.9, the foundation coefficient K30 is not less than 80MPa/m; the thickness of the clay is 0.4m-0.6m, the compaction coefficient K is not less than 0.9, the foundation coefficient K30 is not less than 80MPa/m, and the layer thickness is 0.3m layer after compaction, after each layer of compaction, the compaction coefficient K and foundation coefficient K30 of the foundation shall be inspected, and the number of inspections shall not be less than 4 per 2000m2; S4:使用所述模块式加筋土挡墙进行收坡,且采用的所述模块式加筋土挡墙的高度为2.83m-7.02m;S4: Use the modular reinforced soil retaining wall for slope closing, and the height of the modular reinforced soil retaining wall used is 2.83m-7.02m; S5:采用边坡包裹体对所述堆筑体陡于1:4的边坡进行加固,并在所述边坡包裹体下方设置碎石和浆砌片石基础;S5: Use side slope inclusions to reinforce the side slopes of the stacked body that are steeper than 1:4, and set up gravel and mortar rubble foundations below the side slope inclusions; S6:在所述模块式加筋土挡墙下部设置排水盲管,并在所述排水盲管底部铺设复合土工膜。S6: A drainage dead pipe is arranged at the lower part of the modular reinforced earth retaining wall, and a composite geomembrane is laid on the bottom of the drainage dead pipe. 7.根据权利要求6所述的生态修复工程中城市余泥渣土堆筑体的施工方法,其特征在于,进一步包括以下步骤:S7:根据工程概况确定堆筑体X、Y、Z三个方向的尺寸,建立三维模型,对所述三维模型划分网格后,通过在三维模型中设置多个位移监测点、多个应力监测点对所述模块式加筋土挡墙的最高断面的受力、变形及稳定性进行分析。7. The construction method of the urban residual mud and slag pile in the ecological restoration project according to claim 6, it is characterized in that, further comprises the following steps: S7: determine three piles X, Y, Z according to the general situation of the project The size of the direction, establish a three-dimensional model, after dividing the three-dimensional model into a grid, by setting a plurality of displacement monitoring points and a plurality of stress monitoring points in the three-dimensional model, the maximum section of the modular reinforced soil retaining wall is subjected to stress. Force, deformation and stability are analyzed. 8.根据权利要求6所述的生态修复工程中城市余泥渣土堆筑体的施工方法,其特征在于,对堆筑体进行沉降观测和水平位移观测,以在发生以下至少一种情况时发出报警:8. the construction method of the urban residual mud and slag mound in the ecological restoration project according to claim 6, is characterized in that, carry out settlement observation and horizontal displacement observation to the mound, so that when the following at least one situation occurs Send an alarm: 边坡支护结构坡顶的最大水平位移已大于填土高度的1/500或20mm,以及水平位移速率已连续3天大于2mm/d;The maximum horizontal displacement of the slope top of the slope supporting structure has been greater than 1/500 or 20mm of the fill height, and the horizontal displacement rate has been greater than 2mm/d for 3 consecutive days; 填筑期地表沉降速率大于10mm/d;During the filling period, the surface settlement rate is greater than 10mm/d; 边坡底部或周围土体出现可能导致剪切破坏的迹象或其他可能影响安全的征兆;Signs that may lead to shear failure or other signs that may affect safety at the bottom of the slope or in the surrounding soil; 坡顶附近出现新裂缝;New cracks appear near the top of the slope; 根据经验判断认为,已出现其他必须报警的情况。Judging from experience, other situations have occurred that must be reported to the police. 9.根据权利要求6所述的生态修复工程中城市余泥渣土堆筑体的施工方法,其特征在于,S4中,在所述模块式加筋土挡墙的面层布置混凝土预制模块,且相邻的所述混凝土预制块之间设有伸缩缝。9. The construction method of the urban residual mud and slag pile in the ecological restoration project according to claim 6, wherein in S4, prefabricated concrete modules are arranged on the surface layer of the modular reinforced soil retaining wall, And expansion joints are arranged between the adjacent concrete prefabricated blocks. 10.根据权利要求6所述的生态修复工程中城市余泥渣土堆筑体的施工方法,其特征在于,S5中:所述边坡包裹体包括双向拉伸土工格栅及土工布,所述双向拉伸土工格栅内填充炭黑量大于2%的聚丙烯:所述排水盲管呈梅花形布置,所述复合土工膜采用无纺土工布贴附加入炭黑的高密度聚乙烯膜,高密度聚乙烯膜的膜厚大于0.3mm。10. The construction method of the urban residual mud and slag pile in the ecological restoration project according to claim 6, wherein in S5: the side slope inclusion comprises a biaxially stretched geogrid and a geotextile, so the The biaxially oriented geogrid is filled with polypropylene with a carbon black content of more than 2%: the drainage blind pipes are arranged in a plum blossom shape, and the composite geomembrane is made of non-woven geotextiles pasted with high-density polyethylene film with carbon black added , the film thickness of high-density polyethylene film is greater than 0.3mm.
CN201811622515.XA 2018-12-28 2018-12-28 Urban residual mud and slag mound in ecological restoration project and its construction method Active CN109653240B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811622515.XA CN109653240B (en) 2018-12-28 2018-12-28 Urban residual mud and slag mound in ecological restoration project and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811622515.XA CN109653240B (en) 2018-12-28 2018-12-28 Urban residual mud and slag mound in ecological restoration project and its construction method

Publications (2)

Publication Number Publication Date
CN109653240A CN109653240A (en) 2019-04-19
CN109653240B true CN109653240B (en) 2020-07-07

Family

ID=66117972

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811622515.XA Active CN109653240B (en) 2018-12-28 2018-12-28 Urban residual mud and slag mound in ecological restoration project and its construction method

Country Status (1)

Country Link
CN (1) CN109653240B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119229A (en) * 2019-11-01 2020-05-08 中铁二院工程集团有限责任公司 Multi-stage reinforced retaining wall comprehensive protection system suitable for large-scale waste slag yard and stability checking and calculating method and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0765315B2 (en) * 1989-12-07 1995-07-19 清水建設株式会社 Embankment structure
US6079908A (en) * 1993-03-31 2000-06-27 Societe Civile Des Brevets Henri Vidal Stabilizing elements for mechanically stabilized earthen structure and mechanically stabilized earthen structure
CN203960883U (en) * 2014-02-20 2014-11-26 中铁第四勘察设计院集团有限公司 One both wired high embankment is helped wide ruggedized construction
CN107354911B (en) * 2017-08-31 2023-09-29 郑州大学 Construction method for ecological flexible geogrid reinforced wharf

Also Published As

Publication number Publication date
CN109653240A (en) 2019-04-19

Similar Documents

Publication Publication Date Title
Palmeira et al. Advances in geosynthetics materials and applications for soil reinforcement and environmental protection works
Liu et al. Field study of a retaining wall constructed with clay-filled soilbags
CN107354911B (en) Construction method for ecological flexible geogrid reinforced wharf
CN112921905B (en) Construction method of initial dam suitable for upstream type tailing pond
CN210104706U (en) A construction structure for deep soft foundation treated by vacuum combined piling load preloading
CN111119229A (en) Multi-stage reinforced retaining wall comprehensive protection system suitable for large-scale waste slag yard and stability checking and calculating method and construction method thereof
Xu et al. Earth reinforcement using soilbags
Bildik et al. Effect of geogrid reinforcement on soil-structure–pipe interaction in terms of bearing capacity, settlement and stress distribution
CN104846840A (en) Shallowly-buried soft soil integrated trench reinforcing device and construction method
CN111778793A (en) A cavity collapse prevention structure and construction method
CN112195965A (en) Expansive soil cutting retaining wall
Karpurapu The geosynthetics for sustainable construction of infrastructure projects
CN204676593U (en) A super-high integral steel-plastic grid reinforced earth abutment retaining wall structure
CN109653240B (en) Urban residual mud and slag mound in ecological restoration project and its construction method
CN207537975U (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN107503370B (en) Composite reinforced soil high retaining wall for manhole and its manufacturing method
Zornberg Ingenuity in geotechnical design using geosynthetics
CN106049413B (en) A kind of composite power drain consolidation system and construction method applied to deep layer foundation in saturated soft soil
CN212223948U (en) A comprehensive protection system for multi-level reinforced soil retaining walls suitable for large-scale spoil fields
CN108677999B (en) Silt bagged soil retaining wall structure and construction method
CN107700514A (en) A kind of processing method on weak base foundation selection structural shape
CN207244552U (en) A kind of ecology flexible geogrid reinforcement harbour
CN201762729U (en) Anti-seepage structure of solid waste landfill on high-steep side slope or strongly-weathered bedrock
CN110644529A (en) Reverse-wrapping type slag building geotextile bag retaining wall, construction method and application
CN215105430U (en) Tide-sensitive river section steel pipe pile anchor pulling combined cofferdam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant