CN108999407A - A kind of constructional column concreting top uses the construction method of funnel - Google Patents

A kind of constructional column concreting top uses the construction method of funnel Download PDF

Info

Publication number
CN108999407A
CN108999407A CN201811150495.0A CN201811150495A CN108999407A CN 108999407 A CN108999407 A CN 108999407A CN 201811150495 A CN201811150495 A CN 201811150495A CN 108999407 A CN108999407 A CN 108999407A
Authority
CN
China
Prior art keywords
constructional column
funnel
steel
concreting
steel funnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811150495.0A
Other languages
Chinese (zh)
Inventor
纪磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN201811150495.0A priority Critical patent/CN108999407A/en
Publication of CN108999407A publication Critical patent/CN108999407A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A kind of constructional column concreting top uses the construction method of funnel, belongs to building construction secondary structure constructional column concreting technical field.Step: installation binding constructional column steel bar framework, and support template stay concreting mouth at the 200mm apart from top plate;To constructional column steel bar framework first time casting concrete until concreting mouth position after support template;Steel funnel is made according to the size of constructional column concreting mouth, keeps steel funnel cross-sectional width consistent with concreting mouth width dimensions, steel funnel is mounted on constructional column concreting mouth position, steel funnel is fixed with lower face die plate;After steel funnel fixes, by steel funnel inlet to second of casting concrete is carried out at the top of constructional column, until closely knit with top plate;Form removal and steel funnel after concrete reaches intensity requirement reject the prominent concrete in steel funnel position, and Constructional Col-umn Construction is completed.The advantage is that it is easy to operate, guarantee constructional column top concrete pouring quality, reduces constructional column concrete and reprocess, reduce construction cost.

Description

A kind of constructional column concreting top uses the construction method of funnel
Technical field
The invention belongs to building construction secondary structure constructional column concreting technical fields, in particular, provide a kind of structure Make the construction method that funnel is used at the top of column concreting.
Background technique
Building construction secondary structure constructional column concreting pours the stage finally, since top concrete pours mouth Reason, after vibrating, concrete overflow cannot complete concreting well at the top of constructional column, cause to go out at the top of constructional column Existing gap and concrete misrun and other issues, will also largely repair top after constructional column demoulding, make construction cost It increases.
Summary of the invention
The purpose of the present invention is to provide the construction methods that funnel is used at the top of a kind of constructional column concreting, to refining In iron master control room secondary structure constructional column pouring construction, it is mounted with funnel at the top of constructional column, by funnel, makes at the top of constructional column Concreting is closely knit, and achieves success, and this method not only ensure that constructional column top concrete pouring quality, and significantly Reprocessing after reducing constructional column demoulding, saves manpower and material resources, reduces construction cost, has accumulated treasured for similar construction later Expensive experience.
The present invention makes funnel cross-sectional width and mixes according to the good steel funnel (steel plate thickness 4mm) of live constructional column dimensioned It is consistent that solidifying soil pours mouthful width dimensions, and steel funnel, funnel bottom are installed when constructional column concreting is to apart from top plate 200mm It is fixed with template, side is fixed with building block.Then by funnel again to residual concrete is poured at the top of constructional column, until coagulation Soil presses closer vibration compacting with top plate, after constructional column demoulding, rejects to the slightly prominent concrete in constructional column funnel position, constructional column Construction is completed, and is met the requirements.Specific step is as follows:
The first step, installation binding constructional column steel bar framework 2, and support template 4, stay coagulation at the 200mm apart from top plate 1 Soil pours mouth 3 (see Fig. 1);
Second step, to constructional column steel bar framework first time casting concrete 5 until concreting mouth 3 after support template 4 Position (see Fig. 2);
Third step, making steel funnel 6 according to the size of constructional column concreting mouth 3, (steel plate of production steel funnel is thick Degree is 4mm), keep steel funnel cross-sectional width consistent with 3 width dimensions of concreting mouth, and steel funnel 6 is mounted on constructional column 3 position of concreting mouth, steel funnel 6 and lower face die plate 4 are fixed (see Fig. 3-Fig. 6);
4th step after steel funnel 6 fixes, continues to pour constructional column top for the second time by 6 entrance of steel funnel Concrete seven, until closely knit (see Fig. 7) with top plate 1;
5th step, form removal 4 and steel funnel 6 after concrete reaches intensity requirement are slightly prominent mixed to 6 position of steel funnel Solidifying soil is rejected, and (see Fig. 8) is completed in the construction of constructional column 8.
This method is easy to operate, not only ensure that constructional column top concrete pouring quality, and greatly reduce construction Column concrete is reprocessed, and construction cost is reduced, and achieves good economic benefit for company.
Detailed description of the invention
Fig. 1 is that constructional column ties up muscle formwork figure (cross-section diagram).
Fig. 2 is constructional column first time concreting figure (cross-section diagram).
Fig. 3 is the main view of steel funnel.
Fig. 4 is the vertical view of steel funnel.
Fig. 5 is the side view of steel funnel.
Fig. 6 is to install steel crater blasting (cross-section diagram) at the top of constructional column.
Fig. 7 is second of concreting figure (cross-section diagram) of constructional column
Fig. 8 is that figure is completed in constructional column demoulding construction
In figure, top plate 1, constructional column steel bar framework 2, concreting mouth 3, template 4, first time casting concrete 5, steel leakage Bucket 6, second of casting concrete 7, constructional column 8.
Specific embodiment
Fig. 1-Fig. 8 is a kind of specific embodiment of the invention.Specific embodiment is as follows:
The first step, installation binding constructional column steel bar framework 2, and support template 4, stay coagulation at the 200mm apart from top plate 1 Soil pours mouth 3 (see Fig. 1);
Second step, to constructional column steel bar framework first time casting concrete 5 until concreting mouth 3 after support template 4 Position (see Fig. 2);
Third step makes steel funnel 6 (steel plate thickness 4mm) according to the size of constructional column concreting mouth 3, makes funnel Cross-sectional width is consistent with 3 width dimensions of concreting mouth, and steel funnel 6 is mounted on 3 position of constructional column concreting mouth, Steel funnel 6 and lower face die plate 4 are fixed (see Fig. 3-Fig. 6);
4th step after steel funnel 6 fixes, continues to pour constructional column top for the second time by 6 entrance of steel funnel Concrete seven, until closely knit (see Fig. 7) with top plate 1;
5th step, form removal 4 and steel funnel 6 after concrete reaches intensity requirement are slightly prominent mixed to 6 position of steel funnel Solidifying soil is rejected, and (see Fig. 8) is completed in the construction of constructional column 8.

Claims (2)

1. using the construction method of funnel at the top of a kind of constructional column concreting, which is characterized in that specific step is as follows:
The first step, installation binding constructional column steel bar framework (2), and support template (4), are stayed mixed at the 200mm apart from top plate (1) Solidifying soil pours mouth (3);
Second step, to constructional column steel bar framework first time casting concrete (5) until concreting mouth after support template (4) (3) position;
Third step makes steel funnel (6) according to the size of constructional column concreting mouth (3), make steel funnel cross-sectional width with Concreting mouth (3) width dimensions are consistent, and steel funnel (6) is mounted on constructional column concreting mouth (3) position, steel leakage It struggles against (6) and lower face die plate (4) is fixed;
4th step after steel funnel (6) fixes, continues to pour constructional column top for the second time by steel funnel (6) entrance Concrete (7), until closely knit with top plate (1);
5th step, form removal (4) and steel funnel (6) after concrete reaches intensity requirement are prominent to steel funnel (6) position mixed Solidifying soil is rejected, and constructional column (8) construction is completed.
2. using the construction method of funnel at the top of constructional column concreting according to claim 1, which is characterized in that system The steel plate thickness for making steel funnel is 4mm.
CN201811150495.0A 2018-09-29 2018-09-29 A kind of constructional column concreting top uses the construction method of funnel Pending CN108999407A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811150495.0A CN108999407A (en) 2018-09-29 2018-09-29 A kind of constructional column concreting top uses the construction method of funnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811150495.0A CN108999407A (en) 2018-09-29 2018-09-29 A kind of constructional column concreting top uses the construction method of funnel

Publications (1)

Publication Number Publication Date
CN108999407A true CN108999407A (en) 2018-12-14

Family

ID=64589552

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811150495.0A Pending CN108999407A (en) 2018-09-29 2018-09-29 A kind of constructional column concreting top uses the construction method of funnel

Country Status (1)

Country Link
CN (1) CN108999407A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111188461A (en) * 2020-02-24 2020-05-22 中国二十二冶集团有限公司 Secondary constructional column of heat-insulation integrated column and construction method of heat-insulation integrated column

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331425A (en) * 1997-06-04 1998-12-15 Nkk Corp Construction method for steel-pipe reinforced concrete column
CN203129605U (en) * 2013-02-26 2013-08-14 中国建筑第七工程局有限公司 Concrete pouring hopper for construction column
CN205400043U (en) * 2016-03-04 2016-07-27 中国建筑第五工程局有限公司 Constructional column is funnel combination tool for concreting
CN106760503A (en) * 2016-11-22 2017-05-31 江苏大学 A kind of constructional column based on standard knot combination is poured uses template
CN206233596U (en) * 2016-10-26 2017-06-09 中国建筑第八工程局有限公司 Building block exterior wall constructional column concrete casting device
CN206681361U (en) * 2017-03-03 2017-11-28 上海二十冶建设有限公司 Template assembly for constructional column one-time cast-forming

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331425A (en) * 1997-06-04 1998-12-15 Nkk Corp Construction method for steel-pipe reinforced concrete column
CN203129605U (en) * 2013-02-26 2013-08-14 中国建筑第七工程局有限公司 Concrete pouring hopper for construction column
CN205400043U (en) * 2016-03-04 2016-07-27 中国建筑第五工程局有限公司 Constructional column is funnel combination tool for concreting
CN206233596U (en) * 2016-10-26 2017-06-09 中国建筑第八工程局有限公司 Building block exterior wall constructional column concrete casting device
CN106760503A (en) * 2016-11-22 2017-05-31 江苏大学 A kind of constructional column based on standard knot combination is poured uses template
CN206681361U (en) * 2017-03-03 2017-11-28 上海二十冶建设有限公司 Template assembly for constructional column one-time cast-forming

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111188461A (en) * 2020-02-24 2020-05-22 中国二十二冶集团有限公司 Secondary constructional column of heat-insulation integrated column and construction method of heat-insulation integrated column
CN111188461B (en) * 2020-02-24 2024-04-19 中国二十二冶集团有限公司 Secondary constructional column of heat-insulating integrated column and construction method of heat-insulating integrated column

Similar Documents

Publication Publication Date Title
CN106592426A (en) Prefabricated template system for transverse pre-stress overall width reinforced concrete bridge deck and construction method
CN207616844U (en) Foundation platform precast concrete side form and molding machine
CN105804395B (en) Stair continuously poured in one molding construction method based on monoblock type typified form
CN210658959U (en) Constructional column concrete placement construction structures of smashing
CN105128131A (en) Method for manufacturing prestressed hollow slab beam through polystyrene foam
CN104532754B (en) A kind of prestressed concrete box girder end-blocking template construction method
CN108999407A (en) A kind of constructional column concreting top uses the construction method of funnel
CN102383598A (en) Method for section construction of building project constructional column
CN108638322B (en) Prefabricated post concreting method in a kind of assembled architecture
CN109910142A (en) Integral reinforced concrete hollowed-out tire seat template with prefabricated bearing bridge deck
CN105908883A (en) Construction method for preventing upward floating of composite floor system lightweight core formwork
CN110468744B (en) Channel bridge reinforcement construction method
CN209538013U (en) A kind of end template for the construction of Thin-wall Hollow Pier pier top solid-section
CN205735443U (en) A kind of template containing joint production for precast assembly
CN105984036A (en) Bubble control technique for producing PC (polycarbonate) boards with modular molds
CN108748614A (en) Mobile press-down type band shear key laminated floor slab making apparatus structure and production method
CN109577641A (en) Prefabricated shear wall pours constrained edge template and its installation method with after
CN201962948U (en) Concrete beam pouring template with embedded part at top
CN209397710U (en) Novel pre-fabricated one
CN208934250U (en) A kind of assembled exempts to tear round beam column concrete blinding open
CN208717969U (en) A kind of novel alter-pouring strips mould plate installs structure
CN207934255U (en) A kind of prefabricated composite wallboard for exempting from formwork
CN208163916U (en) A kind of producing device of hybrid beam
CN106638672B (en) A kind of construction method effectively reducing piping lane haunch area concrete formation bubble
CN206477251U (en) Transverse prestress overall with reinforced concrete bridge deck plate prefab-form system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181214