CN107724706A - A kind of Cracks On Concrete Floors reinforcement process - Google Patents

A kind of Cracks On Concrete Floors reinforcement process Download PDF

Info

Publication number
CN107724706A
CN107724706A CN201711000946.8A CN201711000946A CN107724706A CN 107724706 A CN107724706 A CN 107724706A CN 201711000946 A CN201711000946 A CN 201711000946A CN 107724706 A CN107724706 A CN 107724706A
Authority
CN
China
Prior art keywords
cracks
concrete floors
reinforcement process
floor slab
process according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711000946.8A
Other languages
Chinese (zh)
Inventor
关庆焕
邓金成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Guangda Construction Group Co Ltd
Original Assignee
Guangdong Guangda Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Guangda Construction Group Co Ltd filed Critical Guangdong Guangda Construction Group Co Ltd
Priority to CN201711000946.8A priority Critical patent/CN107724706A/en
Publication of CN107724706A publication Critical patent/CN107724706A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a kind of Cracks On Concrete Floors reinforcement process, belong to floor field of reinforcement, its step includes:Construction hole is drilled through in cracks on floor slab;Back and forth washed by water to construction hole again;In construction hole site installation grout nipple;In cracks on floor slab surface smear sealing compound;Grouter connection grout nipple carries out pouring into cement mortar.This kind of Cracks On Concrete Floors reinforcement process, mixed mud cracks on floor slab can be sealed and reinforced.

Description

A kind of Cracks On Concrete Floors reinforcement process
Technical field
The present invention relates to floor field of reinforcement, more particularly to a kind of Cracks On Concrete Floors reinforcement process.
Background technology
Concrete cracking is a world-famous puzzle, and wanting not ftracture is nearly impossible, and cracking has on a variety of floors There is surface crack to also have through crack, as long as it is all acceptable that country is required of surface crack no more than 0.3mm now, If this factor of through crack just has, it is enough.Needed in raw material water it is bigger easily cracking, mainly powder, cement, Miberal powder, flyash etc., also there is certain relation with sandstone;Additive also has a powder, the larger easy cracking of self-constriction, such as Red flyash and sandstone;Middle modulus of fineness also easily ftractureing less than 2.6, additive usage is larger also easy to produce cracking; Also the ratio of mud also has an impact, especially summer because moisture loss influence it is bigger;In addition also have and construct, such as pump When add water, vibration is insufficient, and the unreasonable late maintaining of molding not enough can all cause to ftracture, and design aspect design portion is rationally led Cause cracking.
The content of the invention
It is above-mentioned to solve the problems, such as, the invention provides a kind of Cracks On Concrete Floors reinforcement process, mixed mud can be sealed Tulou plank split is reinforced.
The technical solution used in the present invention is:A kind of Cracks On Concrete Floors reinforcement process, its step include:In floor Crack drills through construction hole;Back and forth washed by water to construction hole again;In construction hole site installation grout nipple;Sealed in cracks on floor slab surface smear Chewing-gum;Grouter connection grout nipple carries out pouring into cement mortar.
In above-mentioned technical proposal, before cracks on floor slab drills through construction hole, first cracks on floor slab is dug into V-groove, ensures grouting Stability.
In above-mentioned technical proposal, construction hole drill fetch bit is setting at the wider place, staggered place, end of cracks on floor slab or running through Place, to ensure to reduce to cracks on floor slab destruction and ensure consolidation effect.
In above-mentioned technical proposal, every cracks on floor slab is at least provided with two construction holes, to install grout nipple and be used as exhaust.
In above-mentioned technical proposal, the spacing in hole of constructing ensure that the density in construction hole, grouting effect between 35cm-40cm Fruit is more preferable.
In above-mentioned technical proposal, the width of sealing compound ensures that the sealing of sealing compound is imitated relative to the wide 1-3cm of cracks on floor slab Fruit.
In above-mentioned technical proposal, the grouting pressure that grouter connection grout nipple is in the milk is gradually risen by low, to ensure The stability of grouting.
In above-mentioned technical proposal, the grouting pressure that grouter connection grout nipple is in the milk is 0.2 to 0.4Mpa, ensures to fill Starch effect and cracks on floor slab structure will not be deteriorated simultaneously.
In above-mentioned technical proposal, when grout nipple is in the milk, when the midge rate of grouter is less than 0.1L/ minutes, then Constant pressure stops slip casting after grouting 3-8 minutes, ensure filling full water mud.
In above-mentioned technical proposal, after the completion of grouter grouting, grout nipple is blocked;Again after cement slurry sets, it will be in the milk Mouth takes out, and is filled and led up with sealing compound at grouting, seals the cracks on floor slab after reinforcing.
The beneficial effects of the invention are as follows:This kind of Cracks On Concrete Floors reinforcement process, back and forth wash by water, can remove to construction hole Impurity in cracks on floor slab, the cement mortar in grouting is set to be sufficient filling with and not influence cement mortar structure, and moisture content moistening floor Behind crack, cement mortar and cracks on floor slab combine more preferably, and consolidation effect is more preferably.
Embodiment
A kind of Cracks On Concrete Floors reinforcement process, its step include:
First to clearing away impurity at cracks on floor slab, the impurity generally refers to unconsolidated formation existing for cracks on floor slab, dust dirt Etc.;Surface concrete is cut to cracks on floor slab, until cracks on floor slab exposes solid internal layer, and by cracks on floor slab chisel into V-groove, Ensure the stability of grouting;
Construction hole is drilled through in cracks on floor slab;Construct hole drill fetch bit setting at the wider place, staggered place, end of cracks on floor slab or Through part, to ensure to reduce to cracks on floor slab destruction and ensure consolidation effect;The spacing in construction hole is protected between 35cm-40cm The density in construction hole is demonstrate,proved, grouting effect is more preferable;Every cracks on floor slab is at least provided with two construction holes, to install grout nipple and work For exhaust;
It is put into high-pressure water pipe to construction hole again back and forth wash by water to construction hole, the delivery port of high-pressure water pipe is in water pipe main body Side, do not stop rotatably to wash away the hole wall in hole of constructing, and ceaselessly change high-pressure water pipe up and down in construction hole Depth position, the silt in construct hole and crack is cleared up and prevents sediment deposition;
In the bottom spreading glue of grout nipple base, grout nipple is pasted on construction hole, with the installation grouting of construction hole Mouth;And the centre bore of grout nipple need to be directed at crack, glue is avoided to block the slurry hole of grout nipple;
In cracks on floor slab surface smear sealing compound, the width of sealing compound ensures sealing compound relative to the wide 1-3cm of cracks on floor slab Sealing effectiveness;After adhesive curing, cracks on floor slab is sprayed into from grout nipple with air gun, to examine cracks on floor slab insertion situation and sealing The sealing situation of glue;
Grouter connection grout nipple carries out pouring into cement mortar;The grouting pressure that grouter connection grout nipple is in the milk is by low Gradually rise, to ensure the stability of grouting;The grouting pressure that grouter connection grout nipple is in the milk is 0.2 to 0.4Mpa, Ensure grouting effect and cracks on floor slab structure will not be deteriorated simultaneously;When grout nipple is in the milk, when the midge rate of grouter is small When 0.1L/ minutes, then stop slip casting after constant pressure grouting 3-8 minutes, ensure filling full water mud.
After the completion of grouter grouting, grout nipple is blocked;Again after cement slurry sets, grout nipple is taken out, uses sealing compound Fill and lead up at grouting, seal the cracks on floor slab after reinforcing.
Embodiment above is merely illustrative and not limiting to the invention, therefore all according to described in present patent application scope The equivalent change or modification done of method, be included in the range of present patent application.

Claims (10)

1. a kind of Cracks On Concrete Floors reinforcement process, it is characterised in that its step includes:Construction hole is drilled through in cracks on floor slab; Back and forth washed by water to construction hole again;In construction hole site installation grout nipple;In cracks on floor slab surface smear sealing compound;Grouter connects Grout nipple carries out pouring into cement mortar.
A kind of 2. Cracks On Concrete Floors reinforcement process according to claim 1, it is characterised in that:Drilled through in cracks on floor slab Construct before hole, first dig cracks on floor slab into V-groove.
A kind of 3. Cracks On Concrete Floors reinforcement process according to claim 1, it is characterised in that:Construction hole drill fetch bit is put At the wider place of cracks on floor slab, staggered place, end or through part.
A kind of 4. Cracks On Concrete Floors reinforcement process according to claim 1 or 3, it is characterised in that:Every floor splits Seam is at least provided with two construction holes.
A kind of 5. Cracks On Concrete Floors reinforcement process according to claim 1 or 3, it is characterised in that:Between construction hole Away between 35cm-40cm.
A kind of 6. Cracks On Concrete Floors reinforcement process according to claim 1 or 2, it is characterised in that:The width of sealing compound Degree is relative to the wide 1-3cm of cracks on floor slab.
A kind of 7. Cracks On Concrete Floors reinforcement process according to claim 1, it is characterised in that:Grouter connection grouting The grouting pressure that mouth is in the milk is gradually risen by low.
A kind of 8. Cracks On Concrete Floors reinforcement process according to claim 1 or 7, it is characterised in that:Grouter connects The grouting pressure that grout nipple is in the milk is 0.2 to 0.4Mpa.
A kind of 9. Cracks On Concrete Floors reinforcement process according to claim 1 or 7, it is characterised in that:Enter in grout nipple During row grouting, when the midge rate of grouter is less than 0.1L/ minutes, then stop slip casting after constant pressure grouting 3-8 minutes.
A kind of 10. Cracks On Concrete Floors reinforcement process according to claim 1 or 2, it is characterised in that:Grouter is in the milk After the completion of, grout nipple is blocked;Again after cement slurry sets, grout nipple is taken out, filled and led up with sealing compound at grouting.
CN201711000946.8A 2017-10-24 2017-10-24 A kind of Cracks On Concrete Floors reinforcement process Pending CN107724706A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711000946.8A CN107724706A (en) 2017-10-24 2017-10-24 A kind of Cracks On Concrete Floors reinforcement process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711000946.8A CN107724706A (en) 2017-10-24 2017-10-24 A kind of Cracks On Concrete Floors reinforcement process

Publications (1)

Publication Number Publication Date
CN107724706A true CN107724706A (en) 2018-02-23

Family

ID=61213298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711000946.8A Pending CN107724706A (en) 2017-10-24 2017-10-24 A kind of Cracks On Concrete Floors reinforcement process

Country Status (1)

Country Link
CN (1) CN107724706A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0194567A2 (en) * 1985-03-06 1986-09-17 Friedrich Maurer Söhne GmbH & Co. KG Device for bridging expansion joints, particularly in bridges, road sections or the like
CN2771389Y (en) * 2005-03-02 2006-04-12 武汉武大巨成加固实业有限公司 Direct-insertion type concrete crack grouting nozzle
CN1888354A (en) * 2006-07-14 2007-01-03 山东省建筑科学研究院 Self-pressing crack treating device and construction technique
CN101736908A (en) * 2008-11-04 2010-06-16 唐益龙 Method for preventing and treating concrete surface crack
CN101942905A (en) * 2010-09-09 2011-01-12 新蒲建设集团有限公司 Method for treating assembly-type floorslab cracks
CN103452332A (en) * 2013-09-11 2013-12-18 中建中东有限责任公司 Method for repairing construction engineering floor slab crack
CN107023176A (en) * 2017-03-29 2017-08-08 中铁十九局集团有限公司 Method and device for repairing crack of low-pressure concrete structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0194567A2 (en) * 1985-03-06 1986-09-17 Friedrich Maurer Söhne GmbH & Co. KG Device for bridging expansion joints, particularly in bridges, road sections or the like
CN2771389Y (en) * 2005-03-02 2006-04-12 武汉武大巨成加固实业有限公司 Direct-insertion type concrete crack grouting nozzle
CN1888354A (en) * 2006-07-14 2007-01-03 山东省建筑科学研究院 Self-pressing crack treating device and construction technique
CN101736908A (en) * 2008-11-04 2010-06-16 唐益龙 Method for preventing and treating concrete surface crack
CN101942905A (en) * 2010-09-09 2011-01-12 新蒲建设集团有限公司 Method for treating assembly-type floorslab cracks
CN103452332A (en) * 2013-09-11 2013-12-18 中建中东有限责任公司 Method for repairing construction engineering floor slab crack
CN107023176A (en) * 2017-03-29 2017-08-08 中铁十九局集团有限公司 Method and device for repairing crack of low-pressure concrete structure

Similar Documents

Publication Publication Date Title
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
CN101260672B (en) Grouting method for rocky slope with weak surface and anchor pipe used for grouting
CN108517899A (en) Mouth high-pressure grouting leak stopping processing method is buried in the leakage drilling of deep basal pit diaphram wall
CN101413245B (en) Rotary spray drill bit and treatment method for emptying treatment of concrete floor slab bottom
CN106381840A (en) Leaking stoppage grouting method for cracks under high pressure flowing water state
KR100973745B1 (en) Grouting tip device and ground improvement method using same
CN205558920U (en) Fissured repair structure of last lining cutting of tunnel wall
CN105178858B (en) A kind of drilling tool for two-tube high-pressure rotary-spray technique
CN106284295A (en) Multichannel high-pressure vibro-grouting jet groutinl construction method
CN113774970A (en) Cast-in-place pile socketed section defect repairing construction method
CN110195444A (en) Basement leakage back side processing method
CN110130325B (en) Construction method for rock drilling and grouting
CN101929343B (en) Profile steel pulling and grouting method of SMW (Soil Mixing Wall) process
NO180042B (en) Method of injecting a mortar material
KR20090002833A (en) Construction device that fills the ground gap by spraying sand at the same time as H-beam drawing
CN107604903A (en) A kind of miniature steel pipe isolation pile reinforced construction method
CN1380470A (en) Impervious wall construction and soilslip-resisting and leakage-blocking process
CN106147732A (en) A kind of compound rapid hardening silicate leak stopping slurry and blocking method thereof
CN107724706A (en) A kind of Cracks On Concrete Floors reinforcement process
CN114483063A (en) Construction method for slurry shield river channel
CN108149637A (en) A kind of vertical bank revetment structure and its construction method
CN105781580A (en) Tunnel crack repair method
CN105863665B (en) A kind of processing method of stone matter tunnel inverted arch scum silica frost

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180223