CN101260672B - Grouting method for rocky slope with weak surface and anchor pipe used for grouting - Google Patents
Grouting method for rocky slope with weak surface and anchor pipe used for grouting Download PDFInfo
- Publication number
- CN101260672B CN101260672B CN2008100309289A CN200810030928A CN101260672B CN 101260672 B CN101260672 B CN 101260672B CN 2008100309289 A CN2008100309289 A CN 2008100309289A CN 200810030928 A CN200810030928 A CN 200810030928A CN 101260672 B CN101260672 B CN 101260672B
- Authority
- CN
- China
- Prior art keywords
- grouting
- anchor
- hole
- grout
- rock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域technical field
本发明涉及岩土工程中的岩体内部加固方法及其所用装置,特别涉及弱面夹层类的岩质边坡的注浆加固方法及其所用注浆装置。 The invention relates to a rock mass internal reinforcement method and a device used in geotechnical engineering, in particular to a grouting reinforcement method and a grouting device used for rock slopes with weak interlayers. the
背景技术Background technique
岩土工程中,含弱面夹层类的岩质边坡在降雨和地下水作用下很容易滑坡。目前,为了防止弱面夹层岩石边坡的水蚀管涌而导致的浅层滑坡,采用的加固方法有主要有两种:一种是锚杆加固岩层与喷射混凝土封闭坡面的联合方法;另一种是岩层高压注浆充填溶洞、断层、弱面夹层和节理裂隙。 In geotechnical engineering, rocky slopes with weak interlayers are prone to landslides under the action of rainfall and groundwater. At present, in order to prevent shallow landslides caused by water erosion piping on weak interlayer rock slopes, there are mainly two reinforcement methods used: one is the combined method of bolt reinforcement rock formation and shotcrete sealing slope surface; the other It is used for high-pressure grouting in rock formations to fill karst caves, faults, weak interlayers and joint fissures. the
锚杆与喷混联合加固方法存在着严重的缺点:大气和岩层之间的温差使坡面混凝土壳臌胀产生裂隙和离层,导致封闭失效,雨水下渗;锚杆注浆不能充满弱面夹层,渗水腐蚀锚杆杆体,缩短锚杆使用寿命,留下了安全隐患。 There are serious shortcomings in the joint reinforcement method of anchor bolt and spray mix: the temperature difference between the atmosphere and the rock layer causes the concrete shell on the slope to swell and produce cracks and separation layers, resulting in sealing failure and rainwater infiltration; the anchor bolt grouting cannot fill the weak surface Interlayer, water seepage corrodes the anchor rod body, shortens the service life of the anchor rod, and leaves a safety hazard. the
岩层高压注浆的注浆工具有自钻式锚杆和双层管(或双重管)。自钻式锚杆通常用于风化岩、碎石层、回填层、砂砾层和卵石层等难以成孔地层。自钻式锚杆要提供注浆中空通道以及钢钎扭力矩两种性能,采用的特殊钢材增加了锚杆的成本;自钻式锚杆只有一个注浆通道,只能用于压入式注浆。双层式或者双重式注浆管用于同时注入两种不同性质浆液的深层定位注浆,由于管材特殊,结构复杂、成本昂贵,也只能压入式注浆且不能作为锚杆加固岩层。 The grouting tools for rock formation high-pressure grouting include self-drilling bolts and double-layer pipes (or double-layer pipes). Self-drilling bolts are usually used in difficult-to-pore formations such as weathered rocks, gravel layers, backfill layers, gravel layers, and pebble layers. The self-drilling bolt should provide two performances of grouting hollow channel and steel brazing torque, and the special steel used increases the cost of the bolt; the self-drilling bolt has only one grouting channel, which can only be used for press-in grouting. pulp. Double-layer or dual-type grouting pipes are used for deep positioning grouting where two kinds of grout with different properties are injected at the same time. Due to the special pipe material, complex structure and high cost, it can only be press-in grouting and cannot be used as an anchor to strengthen the rock formation. the
而压入式注浆是借助于外加压力推挤浆液压迫夹层充填物、充填岩层裂隙的一种注浆方法。压入式注浆工艺用于浅层注浆存在三个缺点:一是边坡浅层注浆没有覆土压浆层,如果不能调节灌浆压力将造成坡面跑浆、冒浆,且边坡裂隙充填不满;二是浅层坡面岩层失水严重,浆液在锚孔和岩层的流动过程中损失水分,流动性变差而堵塞渗浆通道;三是停注时浆液不能回流,堵塞锚孔,导致不能反复灌注。 The press-in grouting is a grouting method that pushes the grout to force the interlayer filling and fill the rock formation fissures by means of external pressure. The press-in grouting process has three disadvantages in shallow grouting: First, there is no soil-covering grouting layer for shallow grouting on the slope. If the grouting pressure cannot be adjusted, the slope will run out of grout, and the slope will crack. The filling is not enough; the second is that the shallow slope rock layer loses water seriously, and the grout loses water in the flow process of the anchor hole and the rock layer, and the fluidity becomes poor, which blocks the grouting channel; the third is that the grout cannot return when the injection is stopped, and the anchor hole is blocked. Resulting in the inability to reperfuse. the
发明内容Contents of the invention
本发明的目的在于解决弱面浅层岩体注浆容易跑浆,以及裂隙充填不满 的问题,提供一种用于弱面岩质边坡浅层岩体的锚固注浆一体化的循环注浆方法,并提供一种用于循环注浆的锚管。 The purpose of the present invention is to solve the problem that the grouting of the weak surface shallow rock mass is easy to run out of grout and the filling of the cracks is not enough. method, and provide an anchor pipe for circulating grouting. the
本发明用于弱面岩质边坡浅层岩体的循环注浆方法的详细技术方案为:钻凿锚孔,锚孔直径比锚管管体外径大100mm;在锚孔内对中放入锚管,在锚孔孔口填塞混凝土;用注浆泵将双层搅拌机中的悬浮浆液压入锚管注浆;注浆过程中根据岩层稳定性通过注浆阀和回浆阀调节注浆流量和注浆压力;当输浆流量大于岩石吸浆流量或者注浆压力大于浅层岩体裂隙充填物的抗剪强度时,启动回浆阀使孔内浆液通过回浆管返回搅拌机的储浆桶,循环注浆。 The detailed technical scheme of the present invention for the circulating grouting method of the shallow rock mass of the weak surface rock slope is as follows: drill the anchor hole, the diameter of the anchor hole is 100mm larger than the outer diameter of the anchor pipe; Anchor pipe, fill concrete in the anchor hole orifice; use a grouting pump to hydraulically inject the suspended grout in the double-layer mixer into the anchor pipe for grouting; during the grouting process, adjust the grouting flow through the grouting valve and the grouting valve according to the stability of the rock formation and grouting pressure; when the grouting flow rate is greater than the rock grouting flow rate or the grouting pressure is greater than the shear strength of shallow rock fissure fillings, start the grout return valve to return the grout in the hole to the slurry storage tank of the mixer through the grout return pipe , cyclic grouting. the
上述方法中所用的锚管由锚头、锚管体和锚管体上的注浆孔组成,在锚头部分设置垫板和螺母作为预应力施加装置,距垫板600mm~1000mm处设置止浆塞,止浆塞下部连接回浆管入口,出口延伸至锚孔外连接双层搅拌机的储浆桶。 The anchor pipe used in the above method is composed of an anchor head, an anchor pipe body and a grouting hole on the anchor pipe body. A backing plate and a nut are arranged on the anchor head as a prestressing device, and a grout stopper is set at a distance of 600mm to 1000mm from the backing plate. The lower part of the stopper is connected to the inlet of the slurry return pipe, and the outlet extends to the outside of the anchor hole to connect to the slurry storage barrel of the double-layer mixer. the
使用本发明的锚管,在锚孔内形成循环注浆通道,注浆时既可有效保持浆液的含水量,又可通过调节注浆压力和流量,降低了对坡体岩层的扰动。特别是在无上覆土层出现坡面跑浆需要处理时,可以注入清水冲洗锚孔,防止浆液凝固堵塞锚孔,不仅为后序段反复注浆保留了通道,而且利用劈裂注浆封闭坡面裂隙,为后序段注浆提高压力创造了条件,从而有效地解决了传统压入式注浆跑浆、以及裂隙充填不满,不能适用于浅层加固的难题。且本发明的锚管采用普通中空钢就可以制成,结构简单,易于制作,成本低廉。 Using the anchor pipe of the present invention, a circulating grouting channel is formed in the anchor hole, which can not only effectively maintain the water content of the grout during grouting, but also reduce the disturbance to the slope rock formation by adjusting the grouting pressure and flow rate. Especially when there is no overlying soil layer and the grout on the slope needs to be treated, clean water can be injected to flush the anchor hole to prevent the grout from solidifying and blocking the anchor hole. This not only reserves the channel for repeated grouting in the subsequent stages, but also seals the slope by splitting grouting. The cracks on the surface create conditions for the post-sequence grouting to increase the pressure, thus effectively solving the problems of traditional press-in grouting, grout running out, and crack filling dissatisfaction, which cannot be applied to shallow reinforcement. Moreover, the anchor pipe of the present invention can be made of ordinary hollow steel, has a simple structure, is easy to manufacture, and has low cost. the
与现有边坡加固注浆方法相比,本发明所采用的循环注浆方法既保持了传统锚固施工简便可行的特点,又通过提高开灌压力实现夹层粘土劈裂注浆封闭坡面裂隙,为反复注浆提高注浆压力创造了条件;通过后续注浆控制注浆压力和流量,扩大了注浆范围,提高了单孔浆液注入率。采用本发明的循环注浆方法,能有效增强边坡夹层的抗水渗、水蚀能力,提高边坡整体的稳定能力。 Compared with the existing slope reinforcement grouting method, the circulating grouting method adopted in the present invention not only maintains the simple and feasible characteristics of traditional anchoring construction, but also realizes the splitting grouting of interlayer clay to close the slope cracks by increasing the opening grouting pressure, Create conditions for repeated grouting to increase the grouting pressure; control the grouting pressure and flow through subsequent grouting, expand the grouting range, and increase the single-hole grouting injection rate. Adopting the circulating grouting method of the present invention can effectively enhance the water seepage resistance and water erosion resistance of the slope interlayer, and improve the overall stability of the slope. the
该发明不仅为交通、水利、能源和建筑等行业弱面夹层岩质边坡和软岩、破碎岩体、砂砾卵石互层边坡提供了一种从岩体内部浅层加固、整治地质灾害的锚注方法,而且为坡面生态防护和消除岩土工程人工施工痕迹创造了条件,也消除了因锚杆锈蚀使加固工程提前失效的隐患。 This invention not only provides a method of strengthening and remediating geological disasters from the shallow layer inside the rock mass for weak interlayer rock slopes and soft rock, broken rock mass, and gravel and pebble interbedded slopes in industries such as transportation, water conservancy, energy, and construction. The anchor injection method not only creates conditions for slope ecological protection and eliminates the traces of artificial construction in geotechnical engineering, but also eliminates the hidden danger of early failure of reinforcement projects due to anchor corrosion. the
附图说明Description of drawings
图1:本发明的锚管结构示意图; Fig. 1: schematic diagram of anchor pipe structure of the present invention;
图2:用本发明的锚管进行循环式注浆的剖面结构图; Fig. 2: the sectional structural diagram that carries out circulating type grouting with the anchor pipe of the present invention;
图3:实施例2循环注浆方法的工艺流程图。 Fig. 3: Process flow chart of embodiment 2 circulation grouting method. the
具体实施方式Detailed ways
实施例1 Example 1
采用 的普通直缝焊管制作锚管体(6),自孔底20cm处钻凿第一排注浆孔(8),焊接孔底对中支架(7),每隔20钻凿注浆孔(8),并在锚管体(6)上段和中段分别焊接对中支架(7)。在锚头(1)部分设置垫板和螺母(2)作为预应力施加装置,距垫板(3)800mm处设置止浆塞(4),止浆塞下部连接回浆管(5)入口,回浆管出口延伸至锚孔外。 use The anchor pipe body (6) is made of ordinary straight seam welded pipe, the first row of grouting holes (8) is drilled from the hole bottom 20cm, the centering bracket (7) is welded at the bottom of the hole, and the grouting holes are drilled every 20 (8 ), and respectively weld the centering bracket (7) on the upper section and the middle section of the anchor pipe body (6). Set a backing plate and nut (2) on the anchor head (1) as a prestressing device, set a stopper (4) at a distance of 800mm from the backing plate (3), and the lower part of the stopper is connected to the inlet of the grout return pipe (5). The grout return pipe outlet extends out of the anchor hole.
实施例2 Example 2
某高速公路路段左边坡为粘土夹层破碎灰岩边坡。坡面长240m,最大高度39.6m,为顺向边坡。边坡共分四级,每级边坡高10m,坡比1∶0.75~1∶1。该边坡被四组节理和数条断层切割,坡顶自然边坡地下水渗透到断层和裂隙中,造成夹层粘土软化和流失,出现浅层岩层顺层滑移。高速公路业主要求坡面进行生态防护,不能喷射混凝土,要求对边坡进行浅层加固。采用图3所示的工艺流程实施循环注浆。 The left slope of an expressway section is a broken limestone slope with clay interlayer. The slope is 240m long and the maximum height is 39.6m, which is a forward slope. The slope is divided into four levels, each level of slope is 10m high, and the slope ratio is 1:0.75~1:1. The slope is cut by four groups of joints and several faults, and the groundwater of the natural slope at the top of the slope penetrates into the faults and fissures, causing the interlayer clay to soften and lose, and shallow rock strata to slip along the bed. The owner of the expressway requires ecological protection on the slope, no shotcrete, and shallow reinforcement of the slope. The process flow shown in Figure 3 is used to implement circular grouting. the
如图2所示,清理边坡后,钻凿直径54mm,孔深4~6m的锚孔,锚孔直径比锚管体(6)外径大100mm。用高压水清洗孔内岩渣,放入实施例1制作的锚管,在锚孔孔口深度600mm位置安装止浆塞(4),然后填塞混凝土(9)。锚头(1)与边坡平齐部分的位置安装垫板(3)和螺母(2)。采用标号52.5普通硅酸盐水泥、粘性土、粉煤灰作为悬浮浆液的浆材,利用双层砂浆搅拌机搅拌配制悬浮浆液。用注浆泵将悬浮浆液压入锚管,锚管入口处设压力表(12)和注浆阀(10)。悬浮浆液经过注浆孔(8)进入锚孔,孔内的一部分浆液挤压进弱面夹层裂隙中。注浆过程中,根据岩层稳定性及压力表,通过调节注浆流量和注浆压力。当输浆流量大于岩石吸浆流量或者注浆压力大于浅层岩体裂隙充填物的抗剪强度时,启动回浆管(5)上的回浆阀(11),使孔内浆液返回搅拌机的储浆桶,实现循环注浆。待孔内浆液结石体干缩后进行补浆,浇注混凝土格梁。当格梁强度达到设计强度的70%后,拧紧螺母(2)施加预应力。 As shown in Figure 2, after cleaning the side slope, the anchor hole with a diameter of 54 mm and a depth of 4 to 6 m is drilled, and the diameter of the anchor hole is 100 mm larger than the outer diameter of the anchor pipe body (6). Clean the slag in the hole with high-pressure water, put the anchor pipe made in embodiment 1, install the grout stopper (4) at the position of the depth of 600mm in the anchor hole opening, and then fill the concrete (9). A backing plate (3) and a nut (2) are installed at the position where the anchor head (1) is flush with the side slope. 52.5 ordinary Portland cement, cohesive soil, and fly ash are used as slurry materials for the suspension slurry, and the suspension slurry is prepared by stirring with a double-layer mortar mixer. Use a grouting pump to hydraulically inject the suspended grout into the anchor pipe, and set a pressure gauge (12) and a grouting valve (10) at the entrance of the anchor pipe. The suspended grout enters the anchor hole through the grouting hole (8), and a part of the grout in the hole is squeezed into the interlayer crack of the weak surface. During the grouting process, the grouting flow rate and the grouting pressure are adjusted according to the stability of the rock formation and the pressure gauge. When the slurry delivery flow rate is greater than the rock slurry suction flow rate or the grouting pressure is greater than the shear strength of the shallow rock mass fissure filling, start the slurry return valve (11) on the slurry return pipe (5) to return the slurry in the hole to the mixer. The grout storage tank realizes circulating grouting. After the grout stone body in the hole shrinks, the grout is replenished and the concrete lattice beam is poured. After the lattice beam strength reaches 70% of the design strength, tighten the nut (2) to apply prestress. the
对用本发明的方法注浆后的边坡岩体采用声波检测和钻孔取岩心样,结果显示:在距锚孔中心1.9m范围内岩体声波波速提高了10%~27%,6m浅孔低压循环式注浆半径超过1.9m。该边坡四年后稳定状况良好,相邻未注浆边坡出现多处局部滑坡。 The slope rock mass after grouting with the method of the present invention adopts acoustic detection and drilling to get core samples, and the results show that the sound wave velocity of the rock mass has increased by 10% to 27% in the range of 1.9m away from the center of the anchor hole. The radius of the hole low-pressure circulation grouting exceeds 1.9m. After four years, the stability of the slope was good, and there were many local landslides in the adjacent non-grouting slope. the
在同一边坡将压入式注浆和循环式注浆进行对比试验,结果显示: On the same slope, the press-in grouting and circulation grouting were compared and tested, and the results showed that:
①压入式注浆法采用水灰比2∶1或1.5∶1浆液开灌,在水灰比1.5∶1和最大注浆压力1.6Mpa以上条件下,正常灌浆可持续时间25~30min。循环式注浆法采用注浆压力0.05MPa水灰比2∶1浆液开灌就能获得较大的进浆流量,当采用水灰比0.8∶1和最大注浆压力1.0Mpa条件下正常灌浆可持续时间40min。 ① The press-in grouting method uses a water-cement ratio of 2:1 or 1.5:1 to start grouting. Under the conditions of a water-cement ratio of 1.5:1 and a maximum grouting pressure of 1.6Mpa or more, normal grouting can last for 25 to 30 minutes. The circulating grouting method can obtain a large grouting flow rate by using a grouting pressure of 0.05MPa and a water-cement ratio of 2:1. Duration 40min. the
②节理不发育区域注浆压力达到1.6MPa时,出现浅层裂隙水力劈裂跑浆;节理发育区域当注浆压力达到0.2MPa时就可能产生浆液的劈裂作用,引起地表冒浆。 ② When the grouting pressure reaches 1.6 MPa in the area with no joints, the hydraulic splitting and running of shallow fissures will occur; in the area with developed joints, when the grouting pressure reaches 0.2 MPa, the grouting may split and cause the surface to erupt. the
③使用循环注浆法锚孔比压入式注浆法锚孔的单孔多注入固料200L。 ③Anchor holes using circulating grouting method are injected with 200L more solid material than single holes using press-in grouting method. the
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100309289A CN101260672B (en) | 2008-03-27 | 2008-03-27 | Grouting method for rocky slope with weak surface and anchor pipe used for grouting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100309289A CN101260672B (en) | 2008-03-27 | 2008-03-27 | Grouting method for rocky slope with weak surface and anchor pipe used for grouting |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101260672A CN101260672A (en) | 2008-09-10 |
CN101260672B true CN101260672B (en) | 2011-04-27 |
Family
ID=39961341
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008100309289A Expired - Fee Related CN101260672B (en) | 2008-03-27 | 2008-03-27 | Grouting method for rocky slope with weak surface and anchor pipe used for grouting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101260672B (en) |
Families Citing this family (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101956560B (en) * | 2009-07-11 | 2013-02-20 | 北京中煤矿山工程有限公司 | Stop-grouting plug safety separation device for subvertical ground pre-grouting engineering |
CN102182191B (en) * | 2011-04-19 | 2013-03-20 | 中水东北勘测设计研究有限责任公司 | Impermeable choking and grouting method for rock plug truncated cone shell in deepwater |
WO2014127680A1 (en) * | 2013-02-19 | 2014-08-28 | Pei Chunguang | Scissor-type expansion bolt and use thereof |
CN103643977B (en) * | 2013-11-21 | 2015-08-19 | 中国矿业大学 | A kind of full anchor subregion is by pressure grouting anchor pole and using method thereof |
CN103669363B (en) * | 2013-12-31 | 2016-01-13 | 青建集团股份公司 | Anti-floating anchor rod pressure grouting device |
CN104832199A (en) * | 2015-04-30 | 2015-08-12 | 广西大学 | Anchor rod and anchoring method adopting anchor rod |
CN105019458A (en) * | 2015-07-30 | 2015-11-04 | 中铁五局(集团)有限公司 | Deep and thick sand layer covered karst cave grouting system device and construction method |
CN105862990B (en) * | 2016-03-24 | 2019-05-24 | 上海市机械施工集团有限公司 | A kind of prefabrication and assembly construction shaft wall structure and its construction method |
CN107675696A (en) * | 2017-08-23 | 2018-02-09 | 中铁二十二局集团有限公司 | A kind of Intelligent deep hole orientation slip casting and monitoring system |
CN108061687B (en) * | 2017-12-06 | 2020-02-14 | 中南大学 | Geotechnical engineering simulation test platform for researching potential failure surface |
CN108104474A (en) * | 2018-01-05 | 2018-06-01 | 广州华土建筑工程技术有限公司 | A kind of high-pressure grouting construction method expected using steel construction and CGM |
CN109162660A (en) * | 2018-10-30 | 2019-01-08 | 中国电建集团成都勘测设计研究院有限公司 | Interior anchor formula orifice closing device |
CN111636910A (en) * | 2020-07-02 | 2020-09-08 | 攀钢集团工程技术有限公司 | A grouting method and a press-in type hollow grouting anchor pipe |
CN112647499A (en) * | 2021-01-12 | 2021-04-13 | 中国电建集团中南勘测设计研究院有限公司 | Deepwater ground anchor grouting method |
CN114352328B (en) * | 2022-01-06 | 2024-10-18 | 徐州徐工基础工程机械有限公司 | Drilling and grouting anchor trolley grouting system and control method thereof |
CN114718060B (en) * | 2022-05-05 | 2024-09-27 | 湖南科技大学 | Winged inflatable anchor pipe and construction method thereof |
-
2008
- 2008-03-27 CN CN2008100309289A patent/CN101260672B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN101260672A (en) | 2008-09-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101260672B (en) | Grouting method for rocky slope with weak surface and anchor pipe used for grouting | |
CN110230309B (en) | Karst area bridge karst cave pile foundation construction method | |
CN104453913B (en) | A kind of Shaft Stopes front pre-grouting method | |
CN1193141C (en) | Combined grouting construction process of reinforcing foundation | |
CN114233385B (en) | Treatment method for mud-bursting water of inclined shaft | |
CN108678772A (en) | A kind of multilevel hierarchy suspension device and its construction method for rich water sandy gravel stratum tunnel | |
CN104612134A (en) | Cast-in place pile post-grouting construction method for pouring construction | |
CN101929340A (en) | Construction technology of pre-grouting and advance support for pipe shed in horizontal inclined roadway in coal mine | |
CN113529721B (en) | Combined drilling and grouting pipe for grouting reinforcement of island reef weak stratum and construction method | |
CN104846810A (en) | Self-circulating posterior grouting bored pile construction method | |
CN107513995A (en) | A kind of bridge struction pile post grouting construction method | |
CN103806479A (en) | Pile foundation combined grouting reinforcement construction method combining waterproof curtain | |
CN110965595A (en) | Raft foundation building lifting reinforcement structure and method under corrosive geological environment | |
CN102877470B (en) | Combined soil nailing construction method for supporting | |
CN111519618A (en) | Post-grouting device for prestressed pipe pile and construction method thereof | |
CN112610249B (en) | Method for preventing and controlling water damage of mine floor under high-pressure-bearing flowing water condition | |
CN102174818A (en) | Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system | |
CN110397056A (en) | A kind of deep building pit piping method for blocking | |
CN205369234U (en) | Freeze high pressure jet grouting pile | |
CN1380470A (en) | Impervious wall construction and soilslip-resisting and leakage-blocking process | |
CN207862925U (en) | A kind of slip casting casing device | |
CN206144587U (en) | Odd -shaped cross section cavity self -drilling stock | |
CN206256920U (en) | Deformed steel bar high-pressure slip casting stock | |
CN113445527A (en) | Method for treating leakage of grouting waterproof curtain in underground platform of rail transit | |
CN108571330A (en) | Method for treating leakage water of post-cast strip of subway bottom plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110427 Termination date: 20120327 |