CN107143338A - A kind of coal mine roadway driving and method for protecting support - Google Patents
A kind of coal mine roadway driving and method for protecting support Download PDFInfo
- Publication number
- CN107143338A CN107143338A CN201710512244.1A CN201710512244A CN107143338A CN 107143338 A CN107143338 A CN 107143338A CN 201710512244 A CN201710512244 A CN 201710512244A CN 107143338 A CN107143338 A CN 107143338A
- Authority
- CN
- China
- Prior art keywords
- channel
- roof
- support
- passage
- coal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000003245 coal Substances 0.000 title claims abstract description 69
- 238000000034 method Methods 0.000 title claims abstract description 40
- 238000009412 basement excavation Methods 0.000 claims abstract description 35
- 238000010276 construction Methods 0.000 claims description 21
- 239000000463 material Substances 0.000 claims description 16
- 229910000831 Steel Inorganic materials 0.000 claims description 15
- 239000010959 steel Substances 0.000 claims description 15
- 239000002184 metal Substances 0.000 claims description 13
- 238000005520 cutting process Methods 0.000 claims description 11
- 230000008569 process Effects 0.000 claims description 11
- 238000005516 engineering process Methods 0.000 claims description 9
- 230000002787 reinforcement Effects 0.000 claims description 9
- 238000005728 strengthening Methods 0.000 claims description 3
- 238000011084 recovery Methods 0.000 claims description 2
- 239000011435 rock Substances 0.000 abstract description 25
- 230000005641 tunneling Effects 0.000 abstract description 8
- 230000000694 effects Effects 0.000 description 13
- 238000010586 diagram Methods 0.000 description 6
- 230000015572 biosynthetic process Effects 0.000 description 5
- 238000005755 formation reaction Methods 0.000 description 5
- 239000011440 grout Substances 0.000 description 5
- 238000005065 mining Methods 0.000 description 5
- 238000009792 diffusion process Methods 0.000 description 4
- 238000005553 drilling Methods 0.000 description 4
- 238000004088 simulation Methods 0.000 description 4
- 238000004873 anchoring Methods 0.000 description 3
- 239000011152 fibreglass Substances 0.000 description 3
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 238000005422 blasting Methods 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 229920001971 elastomer Polymers 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 230000036316 preload Effects 0.000 description 2
- 239000000243 solution Substances 0.000 description 2
- 239000000126 substance Substances 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 229910010272 inorganic material Inorganic materials 0.000 description 1
- 239000011147 inorganic material Substances 0.000 description 1
- 229920000592 inorganic polymer Polymers 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 229920000620 organic polymer Polymers 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 229920003023 plastic Polymers 0.000 description 1
- 239000002861 polymer material Substances 0.000 description 1
- 229920002635 polyurethane Polymers 0.000 description 1
- 239000004814 polyurethane Substances 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000001739 rebound effect Effects 0.000 description 1
- 229920005989 resin Polymers 0.000 description 1
- 239000011347 resin Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 238000009987 spinning Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/155—Laggings made of strips, slats, slabs or sheet piles
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明公开了一种煤矿井下巷道掘进及支护方法,主要是为了解决三软厚煤层回采工作面切眼掘进时,顶板围岩松软破碎,巷道成型困难,进而影响掘进安全和速度等难题。本发明方法是将整个切眼空间挖掘分为破顶形成第一通道、卧底形成第二通道和向待采煤体侧扩帮形成第三通道共三个阶段,本发明能够很好的适应顶板极为松软破碎的厚煤层工作面大断面切眼顶板软弱破碎的特点,有效防止顶板冒顶事故的发生。
The invention discloses a tunneling and supporting method for an underground roadway in a coal mine, which is mainly aimed at solving problems such as that the surrounding rock of the roof is soft and broken and the roadway is difficult to form, which further affects the safety and speed of the tunneling, etc. The method of the present invention divides the excavation of the entire cut-out space into three stages: the first passage is formed by breaking the roof, the second passage is formed under the undercover, and the third passage is formed by expanding the side of the coal body to be mined. The present invention can well adapt to the roof The extremely soft and broken thick coal seam working face has the characteristics of a large cross-section cut-out roof, which is weak and broken, and effectively prevents the occurrence of roof fall accidents.
Description
技术领域technical field
本发明涉及一种煤矿巷道掘进及支护方法,适应顶板极为松软破碎的厚煤层工作面大断面切眼掘进和支护。The invention relates to a coal mine roadway excavation and support method, which is suitable for excavation and support of large cross-section cutting holes in thick coal seam working faces with extremely soft and broken roofs.
背景技术Background technique
我国煤矿开采机械化程度和应用范围逐步提高,工作面切眼高度和宽度不断增大,一般采用导硐扩帮二次成巷的掘进方式,二次扩帮成巷中易造成切眼冒顶事故,尤其是在顶板极为松软破碎的厚煤层工作面切眼中冒顶事故频发。因此,保证顶板极为松软破碎的厚煤层工作面切眼的安全掘进和围岩稳定具有重大经济意义和社会意义。The degree of mechanization and the scope of application of coal mining in my country are gradually increasing, and the height and width of the cutout in the working face are increasing. Generally, the excavation method of tunnel expansion and secondary roadway formation is adopted. In the secondary expansion of the roadway, it is easy to cause the cutout and roof fall accidents. Especially in the cut eye of the thick coal seam working face with very soft and broken roof, roof fall accidents occur frequently. Therefore, it is of great economic and social significance to ensure the safety of excavation and the stability of the surrounding rock in thick coal seam working faces with extremely soft and broken roofs.
目前,掘进工作面切眼的主要方法是导硐扩帮二次成巷法,使用该方法掘进切眼时,虽然先掘进一个断面较小的导硐,然后再进行大深度的扩帮形成切眼,但仍未彻底消除切眼冒顶的安全隐患。其中一个主要原因是:由于切眼宽度往往较大,宽度成为切眼围岩稳定的主控因素,目前的导硐扩帮二次成巷法只是推迟了大宽度形成的时间,没有考虑消除大宽度切眼的挠曲和压曲效应,二次扩帮切眼形成后,导致切眼顶板软弱破碎煤岩体冒落。煤岩体注浆加固是解决巷道顶板煤岩体有效手段之一,但受限制于切眼预注浆工程量大、顶板注浆效果差、成本高等因素,未能大范围推广应用。综上,现有的切眼掘进方法表现出以下几个问题:1)现有切眼掘进技术不能达到很好的防止顶板软弱破碎煤岩体冒顶的目的;2)现有切眼预注浆技术工程量大、安全隐患大、顶板注浆效果差、成本高;3)二次扩帮过程中,顶板支护难度大,安全隐患严重,切眼掘进速度慢;4)无法消除切眼顶板挠曲效应和大跨度压曲效应,始终存在冒顶的隐患。At present, the main method of tunneling in the excavation working face is the secondary tunneling method of tunnel expansion. eye, but still not completely eliminate the potential safety hazard of eye-cutting and roof fall. One of the main reasons is that because the width of the cut hole is often large, the width becomes the main controlling factor for the stability of the surrounding rock of the cut hole. The current secondary tunneling method of expanding the side of the guide tunnel only delays the time for the formation of the large width, and does not consider eliminating the large width. The deflection and buckling effect of the width cut hole, after the formation of the second side expansion cut hole, leads to the weak and broken coal and rock mass caving of the cut hole roof. Coal rock mass grouting reinforcement is one of the effective means to solve the roadway roof coal rock mass, but it has not been widely used due to the large amount of pre-grouting work, poor roof grouting effect, and high cost. To sum up, the existing hole-cutting tunneling methods show the following problems: 1) the existing hole-cutting tunneling technology can not achieve the purpose of preventing the roof from falling of the weak and broken coal and rock mass; 2) the existing hole-cutting pre-grouting Large technical engineering volume, large safety hazards, poor roof grouting effect, and high cost; 3) During the second side expansion process, the roof support is difficult, serious safety hazards, and the excavation speed of the cut hole is slow; 4) The cut hole roof cannot be eliminated Due to deflection effect and large-span buckling effect, there is always a hidden danger of roof fall.
发明内容Contents of the invention
本发明的目的在于提供一种煤矿巷道掘进及支护方法,以克服现有技术中的问题,本发明能够很好的适应顶板极为松软破碎的厚煤层工作面大断面切眼顶板软弱破碎的特点,有效防止顶板冒顶事故的发生。The purpose of the present invention is to provide a coal mine roadway excavation and support method to overcome the problems in the prior art. The present invention can well adapt to the characteristics of the weak and broken roof of the thick coal seam working face with a large section cut hole that is extremely soft and broken. , Effectively prevent the occurrence of roof fall accidents.
为达到上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:
一种煤矿巷道掘进及支护方法,将整个切眼施工分为破顶形成第一通道、卧底形成第二通道以及向待采煤体侧扩帮形成第三通道三个阶段,具体包括以下步骤:A coal mine roadway excavation and support method, which divides the entire eye-cutting construction into three stages: breaking the roof to form the first passage, forming the second passage under the undercover, and expanding the side of the coal body to be mined to form the third passage. Specifically, it includes the following steps :
步骤一:以距离煤层底板高度H的通道分界面为第一通道的底面基础,超挖部分煤层顶板,掘进形成第一通道,掘进过程中对第一通道进行支护,其中H为第二通道的高度;Step 1: Take the channel interface at a height H from the coal seam floor as the bottom foundation of the first channel, over-excavate part of the coal seam roof, and excavate to form the first channel, and support the first channel during the excavation process, where H is the second channel the height of;
步骤二:对第一通道待采煤体侧的巷道帮部进行注浆加固和加强支护;Step 2: Carry out grouting reinforcement and strengthening support to the side of the roadway on the side of the coal body to be mined in the first passage;
步骤三:以煤层底板为底面基础,以通道分界面为顶面边界掘进第二通道,并对第二通道两帮进行支护;Step 3: taking the coal seam floor as the bottom foundation, taking the passage interface as the top boundary to excavate the second passage, and supporting the two sides of the second passage;
步骤四:对第二通道待采煤体侧进行扩帮,即掘进形成第三通道,并对第三通道进行联合支护,即形成由第一通道、第二通道和第三通道组成的切眼。Step 4: Expand the side of the coal body to be mined in the second channel, that is, excavate to form the third channel, and carry out joint support for the third channel, that is, form a cutting channel composed of the first channel, the second channel and the third channel. Eye.
进一步地,步骤一中超挖部分煤层顶板具体为:将煤层上方赋存的伪顶和软弱直接顶挖除,以稳定直接顶作为第一通道的顶板。Further, the over-excavation part of the coal seam roof in step 1 specifically includes: excavating the false roof and the weak direct roof existing above the coal seam, so as to stabilize the direct roof as the roof of the first channel.
进一步地,步骤一中对第一通道进行支护具体为:对第一通道顶板总体采用锚杆、锚索、金属网以及钢带联合支护技术;对第一通道两帮总体采用锚杆、锚索、金属网以及钢筋梯子梁联合支护技术,其中锚索紧跟掘进迎头施工。Further, the support for the first channel in step 1 is specifically: the joint support technology of anchor rods, anchor cables, metal mesh and steel belts is adopted for the roof of the first channel as a whole; The combined support technology of anchor cables, metal mesh and reinforced ladder beams, in which the anchor cables closely follow the excavation and head-on construction.
进一步地,步骤二中注浆材料为超聚混凝土,加强支护方式为补打锚索进行加强支护。Further, the grouting material in step 2 is super-polymeric concrete, and the reinforced support method is to add anchor cables for reinforced support.
进一步地,步骤三中对第二通道两帮进行锚网支护,其中待采煤体侧帮采用可回收锚杆进行支护。Further, in step 3, anchor mesh support is carried out on the two sides of the second channel, wherein the side walls of the coal body to be mined are supported by recoverable anchor rods.
进一步地,步骤四中对第三通道进行联合支护前,先对第三通道的顶板进行注浆加固,并对第三通道的侧方和下方进行锚索补强支护。Further, before the combined support of the third channel in step 4, the roof of the third channel is reinforced by grouting, and the side and bottom of the third channel are reinforced and supported by anchor cables.
进一步地,步骤四中对第三通道的待采煤体侧帮采用锚杆及双抗网进行联合支护,第三通道的顶板采用锚杆、锚索、金属网以及钢带进行联合支护,其中锚索紧跟掘进迎头施工。Further, in step 4, the side of the coal body to be mined in the third channel is jointly supported by anchor rods and double-resistance nets, and the roof of the third channel is jointly supported by anchor rods, anchor cables, metal mesh and steel belts , wherein the anchor cable follows the head-on construction of the excavation.
与现有技术相比,本发明具有以下有益的技术效果:Compared with the prior art, the present invention has the following beneficial technical effects:
本发明针对顶板极为松软破碎的厚煤层工作面大断面切眼顶板自稳性能差、承载能力差和跨度大等特点,采用一种新的巷道掘进及支护方法。该方法可以大大降低不稳定大跨度顶板的挠曲效应和压曲效应,从根本上改善了顶板的受力状态;该巷道掘进技术沿煤层底板掘进,较沿煤层顶板布置切眼方式,解决了回采过程中工作面需多个循环逐步下扎的过程,以及两巷端头与工作面标高不一的支护难题,不留底煤三角区,提高了煤炭采出率;相比较切眼掘前超前预注浆技术,该技术各工序相互交叉影响小,多工序可平行作业,施工速度快且安全可靠。本发明设计合理、安全可靠、施工速度快、推过应用前景广泛,可以大幅度提高顶板极为松软破碎的厚煤层工作面大断面切眼的安全水平和技术经济效益。The invention adopts a new roadway excavation and support method aiming at the characteristics of poor self-stability, poor bearing capacity and large span of the large-section cut-out roof of the thick coal seam working face with extremely soft and broken roof. This method can greatly reduce the deflection effect and buckling effect of the unstable long-span roof, and fundamentally improve the stress state of the roof; In the process of mining, the working face needs multiple cycles to gradually lower the process, and the support problem of the different elevations between the ends of the two roadways and the working face does not leave the bottom coal triangle area, which improves the coal recovery rate; Advanced pre-grouting technology, each process of this technology has little interaction with each other, multiple processes can be operated in parallel, and the construction speed is fast and safe and reliable. The invention is reasonable in design, safe and reliable, fast in construction speed and broad in application prospect, and can greatly improve the safety level and technical and economic benefits of large-section cutouts in thick coal seam working faces with extremely soft and broken roofs.
进一步地,采用注化学浆液在侧面对第三通道顶板加固可以显著提高注浆效果,增强破碎煤岩层的整体稳定性,为工作面回采设备安装空间提供了成型基础和安全保障,具有显著的加固效果;在第三通道顶板锚网支护的基础上对其进行锚索补强支护,同时在其一侧也有锚索补强支护,整体加固效果好,围岩强度高。Furthermore, using chemical grout to reinforce the roof of the third channel on the side can significantly improve the grouting effect, enhance the overall stability of the broken coal strata, and provide a forming foundation and safety guarantee for the installation space of the mining equipment in the working face, which has significant reinforcement Effect: On the basis of the anchor net support of the roof of the third channel, it is reinforced with anchor cables, and at the same time, there is also an anchor cable reinforcement support on one side, the overall reinforcement effect is good, and the strength of the surrounding rock is high.
附图说明Description of drawings
图1为第一通道支护断面图;Fig. 1 is a sectional view of the first channel support;
图2为注浆锚杆结构示意图;Fig. 2 is the schematic diagram of grouting bolt structure;
图3为注浆系统设备布置示意图;Figure 3 is a schematic diagram of the equipment layout of the grouting system;
图4为注浆施工工艺流程图;Fig. 4 is a flow chart of the grouting construction process;
图5为第二通道支护断面图;Fig. 5 is a sectional view of the second channel support;
图6为自旋锚杆结构示意图;Fig. 6 is a structural schematic diagram of a spin anchor;
图7为第三通道支护断面图;Figure 7 is a sectional view of the third channel support;
图中:1—第一通道;2—第二通道;3—第三通道;4—通道分界面;5—煤层底板;6—煤层顶板;7—螺纹钢锚杆;8—锚索;9—注浆锚杆;10—圆锥形端头;11—注浆锚杆杆体;12—出浆孔;13—挡圈;14—A组物料;15—B组物料;16—注浆泵;17—高压橡胶管;18—注射枪;19—封口器;20—可回收锚杆;21—挤压旋进锥头;22—自旋锚杆杆体;23—旋丝;24—预紧螺母;25—碟形托盘;26—围岩表面;27—玻璃钢锚杆。In the figure: 1—first channel; 2—second channel; 3—third channel; 4—channel interface; 5—coal seam floor; 6—coal seam roof; 7—rebar anchor rod; 8—anchor cable; 9 — grouting anchor; 10—conical end; 11—grouting anchor body; 12—grouting hole; 13—retaining ring; 14—A group of materials; 15—B group of materials; 16—grouting pump; 17—high-pressure rubber tube; 18—injection gun; 19—sealer; 20—recoverable anchor rod; 21—squeezing and screwing in the cone head; 22—spinning anchor rod body; ; 25—disc-shaped tray; 26—surrounding rock surface; 27—glass fiber reinforced plastic bolt.
具体实施方式detailed description
下面结合附图对本发明作进一步详细描述:Below in conjunction with accompanying drawing, the present invention is described in further detail:
参见图1至图7,本发明的一种煤矿井下巷道掘进及支护方法,主要是为了解决三软厚煤层回采工作面切眼掘进时,顶板围岩松软破碎,巷道成型困难,进而影响掘进安全和速度等难题。本发明方法是将整个切眼空间挖掘分为破顶形成第一通道1、卧底形成第二通道2和向待采煤体侧扩帮形成第三通道3共三个阶段,包括以下步骤:Referring to Fig. 1 to Fig. 7, a coal mine underground roadway excavation and support method according to the present invention is mainly to solve the problem that the surrounding rock of the roof is soft and broken, and the roadway is difficult to form, which in turn affects the tunneling problems such as security and speed. The method of the present invention divides the excavation of the entire cut-out space into three stages: breaking the roof to form the first passage 1, forming the second passage 2 undercover, and expanding the side of the coal body to be mined to form the third passage 3, which includes the following steps:
步骤一:以距离煤层底板5一定距离(一定距离指第二通道2的高度)的通道分界面4为第一通道1的底面基础,超挖部分煤层顶板6,破除伪顶,掘进形成第一通道1,即将煤层上方赋存的伪顶和软弱直接顶挖除,以稳定性较好的直接顶为第一通道1的顶板,掘进过程中及时对第一通道1进行支护,顶板采用锚杆+锚索+金属网+钢带联合支护技术,两帮采用锚杆+锚索+金属网+钢筋梯子梁联合支护技术,均分步骤实施联合支护,其中锚索紧跟掘进迎头施工;Step 1: take the channel interface 4 at a certain distance from the coal seam floor 5 (a certain distance refers to the height of the second channel 2) as the bottom foundation of the first channel 1, over-excavate part of the coal seam roof 6, break the false roof, and excavate to form the first channel 1. Passage 1 is to excavate the false roof and weak direct roof existing above the coal seam, and use the direct roof with better stability as the roof of the first passage 1. During the excavation process, the first passage 1 shall be supported in time, and the roof shall be anchored Combined support technology of rod + anchor cable + metal mesh + steel belt, the two sides adopt the combined support technology of anchor rod + anchor cable + metal mesh + steel ladder beam, and the joint support is implemented in steps, in which the anchor cable closely follows the head of the excavation construction;
步骤二:对第一通道1的工作面推进方向侧的巷道帮部进行注浆加固和加强支护,注浆材料为超聚混凝土,超聚混凝土由A组物料14和B组物料15组成,A组物料14和B组物料15均以无机材料为骨料,以多种树脂为黏结材料,兼具无机与有机高分子材料的特点,具有黏结性好、早期强度高、固化时间可调、安全性能高、成本低等优点,详见专利CNCN201110207625.1,加强支护方式为补打锚索8加强支护;其中化学注浆采用理论计算和数值模拟相结合的方法初步确定出注浆的各项参数,包括注浆孔的深度、注浆压力、注浆扩散半径、注浆时间、注浆孔间排距、注浆顺序和注浆锚杆单孔注浆量等,然后根据现场工程实践效果进行反馈分析,可对各项注浆参数进行优化;Step 2: Carry out grouting reinforcement and reinforced support to the side of the roadway on the side of the advancing direction of the working face of the first passage 1. The grouting material is superpolymer concrete, and the superpolymer concrete is composed of group A material 14 and group B material 15. Group A material 14 and B group material 15 both use inorganic materials as aggregates and a variety of resins as bonding materials. They have the characteristics of both inorganic and organic polymer materials, with good adhesion, high early strength, adjustable curing time, For the advantages of high safety performance and low cost, please refer to the patent CNCN201110207625.1 for details. The reinforced support method is to add anchor cables 8 to strengthen the support; the chemical grouting adopts the method of combining theoretical calculation and numerical simulation to preliminarily determine the grouting value. Various parameters, including depth of grouting hole, grouting pressure, grouting diffusion radius, grouting time, row spacing between grouting holes, grouting sequence and single hole grouting amount of grouting anchor, etc., and then according to the site engineering Feedback analysis of practical effects can optimize various grouting parameters;
步骤三:以煤层底板5为底面基础,以通道分界面4为顶面边界掘进第二通道2,并及时对两帮进行锚网支护,其中待采煤体侧帮选用可回收锚杆10进行支护;Step 3: Take the coal seam floor 5 as the bottom foundation, and take the passage interface 4 as the top boundary to excavate the second passage 2, and carry out anchor mesh support for the two sides in time, and select the recoverable anchor rod 10 for the side of the coal body to be mined support;
步骤四:对第二通道2待采煤体侧进行扩帮,即掘进形成第三通道3,在对第三通道3顶板进行注浆加固的基础上,从侧方和下方对其进行锚索补强支护,然后对第三通道3及时进行联合支护,其中待采煤体侧帮采用锚杆+双抗网进行支护,顶板采用锚杆+锚索+金属网+钢带进行支护,其中锚索紧跟掘进迎头施工,第二通道2和第三通道3共同构成了切眼回采设备安装的空间,至此切眼已形成,即由第一通道1、第二通道2和第三通道3组成。Step 4: Expand the side of the coal body to be mined in the second channel 2, that is, excavate to form the third channel 3, and on the basis of grouting and strengthening the roof of the third channel 3, anchor cables to it from the side and below Reinforce the support, and then carry out combined support for the third channel 3 in time, in which the side of the coal body to be mined is supported by bolts + double-resistant nets, and the roof is supported by bolts + anchor cables + metal mesh + steel belts The anchor cable is closely followed by the head-on construction of the excavation. The second channel 2 and the third channel 3 together constitute the space for the installation of the cutting hole mining equipment. Three channels are composed of 3.
本发明优先掘进第一通道1为工作面回采设备安装空间顶板的极软弱破碎围岩注浆提供了条件,在上述极软弱破碎围岩的侧面注浆,一方面保证了注浆工程空间的安全,另一方面较直接在软弱围岩下方空间进行注浆围岩加固效果更好。The present invention preferentially excavates the first channel 1 to provide conditions for the grouting of the extremely weak and broken surrounding rock on the roof of the mining equipment installation space of the working face. Grouting the side of the above-mentioned extremely weak and broken surrounding rock ensures the safety of the grouting project space on the one hand. On the other hand, it is better to strengthen the surrounding rock by grouting directly in the space under the weak surrounding rock.
注浆时采用的注浆锚杆9的直径为Φ20mm~Φ25mm。钻孔深度的确定是采用数值模拟来确定第一通道1形成后围岩塑性区的范围作为确定注浆孔深度的参考依据。注浆时间的确定是通过数值模拟得出工作面随注浆时间变化的浆液渗透范围图和孔隙压力扩散云图,浆液扩散速度很慢且趋于稳定时即为合适的注浆时间。注浆顺序是由下向上,即先注帮脚,再注中间和帮顶,采用间隔跳孔的注浆方式。The diameter of the grouting anchor rod 9 adopted during grouting is Φ20mm~Φ25mm. The determination of the drilling depth is to use numerical simulation to determine the range of the plastic zone of the surrounding rock after the formation of the first channel 1 as a reference basis for determining the depth of the grouting hole. The determination of grouting time is to obtain the grout penetration range map and pore pressure diffusion cloud map of the working face with the grouting time through numerical simulation. The grouting time is suitable when the grouting diffusion speed is very slow and tends to be stable. The grouting sequence is from bottom to top, that is, the side foot is injected first, and then the middle and top side are injected, and the grouting method of skipping holes at intervals is adopted.
工作面切眼扩巷二次成巷时顶板的稳定性,是影响切眼施工速度和保证安全掘巷的关键因素。本发明将工作面切眼空间分解成三个通道分阶段进行开挖,通过掘进第一通道1为顶板煤岩层注浆工程提供了空间,同时施工帮部锚索加强支护,进一步增强了其稳定性。工人技术水平、施工组织等条件允许时,可在滞后第一通道1适当距离施工第二通道2;若设备机具允许,还可同时施工第二通道2和第三通道3。The stability of the roof during the secondary roadway forming of the cut-out and widening of the working face is the key factor affecting the construction speed of the cut-out and ensuring the safety of the roadway. The present invention decomposes the cutting hole space of the working face into three passages for excavation in stages, and provides space for the roof coal and rock layer grouting project through the excavation of the first passage 1. At the same time, the anchor cables of the construction side are strengthened and supported, which further enhances its stability. When the technical level of workers, construction organization and other conditions permit, the second passage 2 can be constructed at an appropriate distance behind the first passage 1; if the equipment and tools allow, the second passage 2 and the third passage 3 can also be constructed at the same time.
下面结合实施例对本发明的操作过程做详细描述:The operation process of the present invention is described in detail below in conjunction with embodiment:
本发明所述的一种煤矿巷道掘进及支护方法,将整个切眼施工分为破顶形成第一通道1、卧底形成第二通道2和扩帮形成第三通道3三个阶段,包括步骤:A coal mine roadway excavation and support method according to the present invention divides the entire eye-cutting construction into three stages: breaking the roof to form the first passage 1, forming the second passage 2 under the undercover, and forming the third passage 3 by expanding the side, including the steps :
步骤一、以两巷与工作面切眼连通的任意一端为起点,以距离煤层底板5一定距离的通道分界面4为第一通道1的底基础,超挖部分煤层顶板6,破除伪顶,采用掘进机或者爆破方式掘进第一通道1,该第一通道1是连通回风巷和进风巷的巷道。Step 1. Starting from any end where the two lanes are connected to the cut hole of the working face, taking the channel interface 4 at a certain distance from the coal seam floor 5 as the bottom foundation of the first channel 1, over-excavating part of the coal seam roof 6, and removing the false roof. The first passage 1 is excavated by a roadheader or blasting, and the first passage 1 is a roadway connecting the air return lane and the air inlet lane.
步骤二、为保证第一通道1围岩的稳定性,对顶板进行锚杆+锚索+金属网+钢带支护,其中锚索与锚杆相间布置,锚索紧跟掘进迎头施工。螺纹钢锚杆7长度为2.4m,间排距为900×800mm;锚索8选用七股预应力钢绞线,规格为Φ17.8×6000mm,间排距为1400×1600mm,锚杆配合300×300×10mm鼓型托盘,锚索配合钢带加垫400×400×12mm平托盘。Step 2. In order to ensure the stability of the surrounding rock of the first channel 1, the roof is supported by bolts + anchor cables + metal mesh + steel belts, in which the anchor cables are arranged alternately with the anchor bolts, and the anchor cables are closely followed by the head-on construction. The length of threaded steel anchor rod 7 is 2.4m, and the distance between rows is 900×800mm; the anchor cable 8 is made of seven prestressed steel strands, the specification is Φ17.8×6000mm, the distance between rows is 1400×1600mm, and the anchor rod is matched with 300 ×300×10mm drum-shaped pallet, anchor cable with steel belt and padded 400×400×12mm flat pallet.
两帮用锚杆+金属+钢筋梯子梁+锚索进行支护,为避免后期对第三通道3顶板支护造成影响,锚索与锚杆布置在同一断面上,且锚索滞后掘进迎头30m施工。锚杆间排距为800×800mm,锚索间排距为1600×1600mm,帮脚锚杆距底板距离不大于300mm,滞后第一通道1掘进迎头一定距离上对第一通道1工作面侧帮进行锚索8补强支护,间排距为1600×1600mm,托盘等参数同顶板支护,支护断面图如图1所示。煤层和岩层中螺纹钢锚杆预紧力矩不小于200N·m和250N·m,锚索预紧力不小于8T,并且施工完7天后对锚杆、索预紧力(矩)进行二次预紧,以消除预紧力(矩)的回弹影响。The two gangs are supported by anchor rods + metal + reinforced ladder beams + anchor cables. In order to avoid the impact on the roof support of the third channel 3 in the later stage, the anchor cables and the anchor rods are arranged on the same section, and the anchor cables lag behind the excavation head by 30m construction. The row spacing between the anchor rods is 800×800mm, the row spacing between the anchor cables is 1600×1600mm, the distance between the anchor bolts of the support foot and the bottom plate is not more than 300mm, lagging behind the first channel 1 excavation and facing the side support of the first channel 1 working face at a certain distance Carry out reinforcement support with 8 anchor cables, the spacing between rows is 1600×1600mm, and the parameters of the pallet are the same as the roof support. The cross-sectional view of the support is shown in Figure 1. The pre-tightening torque of threaded steel bolts in coal seams and rock formations is not less than 200N m and 250N m, and the pre-tightening force of anchor cables is not less than 8T, and the pre-tightening force (moment) of anchor rods and cables should be pre-tightened twice after 7 days of construction. Tighten to eliminate the rebound effect of preload (moment).
步骤三、对第一通道1工作面侧巷道帮部进行注浆。注浆参数应根据理论计算、数值模拟初步确定,并根据现场实施效果进一步优化,主要参数包括注浆压力、浆液扩散半径、注浆时间、注浆孔间排距、注浆顺序等。Step 3: Grouting the side roadway side of the working face of the first passage 1. Grouting parameters should be preliminarily determined based on theoretical calculations and numerical simulations, and further optimized based on on-site implementation results. The main parameters include grouting pressure, grout diffusion radius, grouting time, row spacing between grouting holes, and grouting sequence.
注浆锚杆9安装在第一通道1的待采煤体侧帮部。注浆锚杆9外露长度100mm,采用Φ26钻头钻孔至设计深度,孔深2.2m。将注浆锚杆9放入钻孔中,然后沿锚杆杆径放入中空环形水泥卷或者用浸沾水泥浆的纱布封堵。注浆材料选用波雷因,波雷因是一种双液型改性聚氨酯注浆材料,由A组物料14和B组物料15两种液体组份组成,施工时按重量比1:1进行混合。同一断面内由下向上注浆,即先注帮脚,再注帮中,最后注帮顶;不同断面分组间隔注浆,每8排为一组,即先进行1、3、5、7单排注浆,再进行2、4、6、8双排注浆,依次交替进行。注浆压力不大于3Mpa。单孔注浆时间为10~13min。为保证注浆能将裂隙充填密实,原则上应注到不明显吃浆为止。注浆完成后,在注浆锚杆外露端加垫托盘,并用螺母预紧,预紧力矩不小于150N·m。The grouting anchor rod 9 is installed on the side of the coal body to be mined in the first channel 1 . The exposed length of the grouting anchor rod 9 is 100mm, and the hole is drilled to the design depth with a Φ26 drill bit, and the hole depth is 2.2m. Put the grouting anchor rod 9 into the borehole, then put into the hollow annular cement roll along the anchor rod diameter or block with gauze soaked in cement slurry. The grouting material is Bolein, which is a two-liquid modified polyurethane grouting material, which is composed of two liquid components, Group A material 14 and Group B material 15, and the weight ratio is 1:1 during construction. mix. Grouting from bottom to top in the same section, i.e. injecting the foot of the side first, then the center of the side, and finally the top of the side; different sections are grouped and spaced for grouting, and each 8 rows is a group, that is, first, 1, 3, 5, 7 singles Row grouting, and then 2, 4, 6, 8 double row grouting, alternately. The grouting pressure is not greater than 3Mpa. The grouting time for a single hole is 10-13 minutes. In order to ensure that the grouting can fill the cracks tightly, in principle, it should be injected until the grouting is not obvious. After the grouting is completed, add a pallet to the exposed end of the grouting anchor rod, and pre-tighten it with nuts, and the pre-tightening torque is not less than 150N·m.
注浆锚杆9结构示意图如图2所示。注浆锚杆9前端为圆锥形端头10,长度K为200mm,并焊接牢固。注浆锚杆杆体11布置Φ8mm出浆孔12,孔距d=200mm,呈五花状排列,杆体外直径D=22mm,壁厚3mm,杆体后端L=500mm内不设出浆孔,螺纹段S=100mm,挡圈13高5mm。如围岩极为破碎致使钻孔无法成孔,则可选用自钻式注浆锚杆。注浆系统设备布置示意图如图3所示。The structural diagram of the grouting anchor 9 is shown in FIG. 2 . The front end of the grouting anchor rod 9 is a conical end 10, the length K is 200mm, and it is firmly welded. The grouting anchor body 11 is arranged with Φ8mm grout holes 12, the hole distance d=200mm, arranged in a five-flower shape, the outer diameter of the rod is D=22mm, the wall thickness is 3mm, there is no grout hole in the rear end of the rod body L=500mm, and the screw thread Segment S=100mm, the high 5mm of retaining ring 13. If the surrounding rock is so broken that the hole cannot be drilled, a self-drilling grouting bolt can be used. The schematic diagram of the equipment layout of the grouting system is shown in Figure 3.
注浆施工工艺流程图如图4所示。打钻孔→安装注浆锚杆9→安装封孔器19→高压橡胶管17连接注射枪18和注浆泵16→将两根管分别连接至A组物料14和B组物料15中→开启注浆泵16→达到注浆要求→关闭注浆泵16→拆卸注射枪18。The flow chart of the grouting construction process is shown in Figure 4. Drill holes → install grouting bolt 9 → install hole sealer 19 → connect injection gun 18 and grouting pump 16 with high-pressure rubber pipe 17 → connect the two pipes to group A material 14 and group B material 15 → open Grouting pump 16 → meet the grouting requirements → close the grouting pump 16 → disassemble the injection gun 18 .
每个注浆班使用注浆泵之前,均应通过用泵吸排清水的方式,检查设备是否正常工作,包括注浆管路、压力表等。Before using the grouting pump in each grouting class, check whether the equipment is working properly, including grouting pipelines, pressure gauges, etc., by pumping and draining clean water.
步骤四、掘进第二通道2。采用掘进机或者炮掘方式对第一通道1卧底至煤层底板5之间掘进形成第二通道2,并对两帮进行锚杆+金属网+钢筋梯子梁支护,间排距为800×800mm,待采煤体侧帮用可回收预应力锚杆20进行支护,可回收锚杆20选用螺旋式可回收锚杆,即利用自旋锚杆杆体22上的旋丝23和紧固件提供的摩擦力和预紧力对围岩进行支护。其余参数同第一通道1要求,支护断面如图5所示。Step 4, excavate the second channel 2. Use roadheader or gun excavation to excavate the first channel 1 undercover to the coal seam floor 5 to form the second channel 2, and support the two sides with anchor rods + metal mesh + steel ladder beams, and the distance between rows is 800×800mm , the side of the coal body to be mined is supported with a retrievable prestressed bolt 20, and the retrievable bolt 20 is a spiral retrievable bolt, which is provided by the screw 23 and the fastener on the spin bolt body 22. The friction and preload force support the surrounding rock. The remaining parameters are the same as the requirements of the first channel 1, and the support section is shown in Figure 5.
可回收锚杆20,即可回收预应力锚杆结构示意图如图6所示。可回收锚杆20前端为挤压旋进锥头21,长度N=50mm,自旋锚杆杆体22直径为20mm,自旋锚杆杆体22上布满旋丝23,旋丝间距M为30~40mm,旋丝高度为4~7mm。后端通过对预紧螺母24施加扭矩将碟形托盘25紧贴围岩表面26,达到对可回收锚杆20施加预紧力的作用。该锚杆为钻锚一体化锚杆,即无需使用锚固剂,依靠以及软弱围岩的初期变形快以及钻孔孔径与杆体公称直径相近的特点实现预紧力和保证锚固力。The structural schematic diagram of the recoverable anchor 20 , that is, the recoverable prestressed anchor is shown in FIG. 6 . The front end of the recoverable bolt 20 is an extruded screw-in cone head 21, the length N=50mm, the diameter of the spin bolt body 22 is 20mm, and the spin bolt body 22 is covered with spiral threads 23, and the distance between the spiral bolts M is 30~ 40mm, the screw height is 4~7mm. The rear end exerts a torque on the pre-tightening nut 24 to make the dish-shaped tray 25 close to the surface 26 of the surrounding rock, so as to exert a pre-tightening force on the recoverable bolt 20 . The anchor rod is an integrated anchor rod for drilling and anchoring, that is, no anchoring agent is used, and the pre-tightening force and anchoring force are realized by relying on the characteristics of fast initial deformation of the weak surrounding rock and the similar diameter of the drilled hole to the nominal diameter of the rod body.
步骤五、掘进第三通道3。采用掘进机或者炮掘方式对第二通道2待采煤体侧帮进行扩帮形成第三通道3,对顶板进行锚杆+锚索+金属网+钢带联合支护,顶板锚杆和锚索布置在同一断面内,且与第一通道1帮部支护锚杆、索所在断面错开半个排距,即400mm,其中锚索紧跟掘进迎头施工。顶板三根锚索间排距为1500×1600mm,其余参数同第一通道1顶板支护要求。Step five, excavate the third passage 3. The side of the coal body to be mined in the second channel 2 is expanded to form the third channel 3 by means of a roadheader or blasting, and the roof is supported by bolts + anchor cables + metal mesh + steel belts, and the roof bolts and anchors are combined. The cables are arranged in the same section, and are staggered from the section where the first channel 1 side support anchor rod and cables are located by half a row distance, that is, 400mm, and the anchor cables are closely followed by the head-on construction of the excavation. The spacing between the three anchor cables on the roof is 1500×1600mm, and the other parameters are the same as the roof support requirements of the first channel 1.
待采煤体侧帮用锚杆+双抗网支护,锚杆选用玻璃钢锚杆27,玻璃钢托盘选用球壳厚度和高度分别为7mm和18mm的托盘。支护断面如图7所示。The side of the coal body to be mined is supported by anchor rods + double-resistant nets. The anchor rods are made of glass fiber reinforced plastic anchor rods 27, and the glass fiber reinforced plastic pallets are made of pallets with a spherical shell thickness and height of 7mm and 18mm respectively. The support section is shown in Figure 7.
步骤六、对注浆工程加固效果进行检查,可采用对第三通道3顶板岩层进行钻孔窥视检查的方法,观察顶板岩层裂隙充填情况;对支护参数进行优化分析,主要是通过对顶板岩层离层进行监测,查看顶板整体的稳定性,调整支护参数。Step 6. Check the reinforcement effect of the grouting project. You can use the method of drilling and peeking at the roof rock layer of the third channel 3 to observe the filling of the cracks in the roof rock layer; optimize and analyze the support parameters, mainly through the roof rock layer. Monitor the separation layer, check the overall stability of the roof, and adjust support parameters.
以上所述,仅是本发明的较佳实施例,并非对本发明的任何限制,凡是根据本发明的技术实质对以上实施例所做的任何简单的修改变更以及等效结构变化,均属于本发明的技术方案的保护范围内。The above description is only a preferred embodiment of the present invention, and does not limit the present invention. Any simple modification and equivalent structural changes made to the above embodiments according to the technical essence of the present invention belong to the present invention. within the scope of protection of the technical solution.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710512244.1A CN107143338B (en) | 2017-06-28 | 2017-06-28 | A kind of coal mine roadway driving and method for protecting support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710512244.1A CN107143338B (en) | 2017-06-28 | 2017-06-28 | A kind of coal mine roadway driving and method for protecting support |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107143338A true CN107143338A (en) | 2017-09-08 |
CN107143338B CN107143338B (en) | 2018-12-25 |
Family
ID=59784334
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710512244.1A Active CN107143338B (en) | 2017-06-28 | 2017-06-28 | A kind of coal mine roadway driving and method for protecting support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107143338B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107654247A (en) * | 2017-09-22 | 2018-02-02 | 中国矿业大学 | A kind of sliding structure area pole loose thick coal layer coal roadway tunneling is met head on anti-top coal leakage method for leakage |
CN108035742A (en) * | 2017-11-16 | 2018-05-15 | 河南理工大学 | A kind of passive harmonious method for protecting support of extreme rockburst tunnel master |
CN109958459A (en) * | 2019-03-05 | 2019-07-02 | 辽宁工程技术大学 | A method of excavating along the bottom of a soft and thick coal seam |
CN111663945A (en) * | 2020-05-27 | 2020-09-15 | 山东黄金矿业(莱州)有限公司三山岛金矿 | Open roof cutting roadway type upward wide drift filling mining method |
CN112664248A (en) * | 2020-12-25 | 2021-04-16 | 国家能源集团宁夏煤业有限责任公司 | Soft rock water spraying roadway supporting method |
CN113153315A (en) * | 2021-04-26 | 2021-07-23 | 中国矿业大学 | Deep large-section hole-cutting roadway-forming mode and method for determining supporting time |
CN113914867A (en) * | 2021-10-12 | 2022-01-11 | 国能神东煤炭集团有限责任公司 | A roof reinforcement method for excavating lower layer cut holes under upper layer goaf |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2001023711A1 (en) * | 1998-07-16 | 2001-04-05 | Kfc Ltd. | Ground reinforcing method |
CN102305074A (en) * | 2011-08-15 | 2012-01-04 | 鞍钢集团矿业公司 | Flat-bottomed pillar sublevel caving method of reinforced concrete structure artificial roof |
CN102390952A (en) * | 2011-07-22 | 2012-03-28 | 安徽佳泰矿业科技有限公司 | Super-polymerized concrete composite material and preparation method thereof |
CN104141496A (en) * | 2014-06-21 | 2014-11-12 | 西安科技大学 | Rectangular roadway surrounding rock deformation and failure control method |
CN105525919A (en) * | 2014-09-29 | 2016-04-27 | 四川省华蓥山煤业股份有限公司绿水洞煤矿 | Steeply inclined fully-mechanized mining face open-off cut enlarging and equipment installation crossing operation method |
CN105781597A (en) * | 2014-12-16 | 2016-07-20 | 淮南矿业(集团)有限责任公司 | Method for performing anchoring and grouting reinforcement inside deep well soft rock gob-side entry retaining |
CN106351663A (en) * | 2016-09-29 | 2017-01-25 | 淮南矿业(集团)有限责任公司 | Retrograde brush expansion process for cut construction |
-
2017
- 2017-06-28 CN CN201710512244.1A patent/CN107143338B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2001023711A1 (en) * | 1998-07-16 | 2001-04-05 | Kfc Ltd. | Ground reinforcing method |
CN102390952A (en) * | 2011-07-22 | 2012-03-28 | 安徽佳泰矿业科技有限公司 | Super-polymerized concrete composite material and preparation method thereof |
CN102305074A (en) * | 2011-08-15 | 2012-01-04 | 鞍钢集团矿业公司 | Flat-bottomed pillar sublevel caving method of reinforced concrete structure artificial roof |
CN104141496A (en) * | 2014-06-21 | 2014-11-12 | 西安科技大学 | Rectangular roadway surrounding rock deformation and failure control method |
CN105525919A (en) * | 2014-09-29 | 2016-04-27 | 四川省华蓥山煤业股份有限公司绿水洞煤矿 | Steeply inclined fully-mechanized mining face open-off cut enlarging and equipment installation crossing operation method |
CN105781597A (en) * | 2014-12-16 | 2016-07-20 | 淮南矿业(集团)有限责任公司 | Method for performing anchoring and grouting reinforcement inside deep well soft rock gob-side entry retaining |
CN106351663A (en) * | 2016-09-29 | 2017-01-25 | 淮南矿业(集团)有限责任公司 | Retrograde brush expansion process for cut construction |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107654247A (en) * | 2017-09-22 | 2018-02-02 | 中国矿业大学 | A kind of sliding structure area pole loose thick coal layer coal roadway tunneling is met head on anti-top coal leakage method for leakage |
CN108035742A (en) * | 2017-11-16 | 2018-05-15 | 河南理工大学 | A kind of passive harmonious method for protecting support of extreme rockburst tunnel master |
CN108035742B (en) * | 2017-11-16 | 2023-04-14 | 河南理工大学 | A method of active and passive harmonious support for extremely weak coal seam roadway |
CN109958459A (en) * | 2019-03-05 | 2019-07-02 | 辽宁工程技术大学 | A method of excavating along the bottom of a soft and thick coal seam |
CN109958459B (en) * | 2019-03-05 | 2021-07-23 | 辽宁工程技术大学 | A method of excavating along the bottom of a soft and thick coal seam |
CN111663945A (en) * | 2020-05-27 | 2020-09-15 | 山东黄金矿业(莱州)有限公司三山岛金矿 | Open roof cutting roadway type upward wide drift filling mining method |
CN112664248A (en) * | 2020-12-25 | 2021-04-16 | 国家能源集团宁夏煤业有限责任公司 | Soft rock water spraying roadway supporting method |
CN113153315A (en) * | 2021-04-26 | 2021-07-23 | 中国矿业大学 | Deep large-section hole-cutting roadway-forming mode and method for determining supporting time |
CN113914867A (en) * | 2021-10-12 | 2022-01-11 | 国能神东煤炭集团有限责任公司 | A roof reinforcement method for excavating lower layer cut holes under upper layer goaf |
Also Published As
Publication number | Publication date |
---|---|
CN107143338B (en) | 2018-12-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107143338A (en) | A kind of coal mine roadway driving and method for protecting support | |
Yang et al. | Failure mechanism and control technology of water-immersed roadway in high-stress and soft rock in a deep mine | |
CN112855223B (en) | Coal roadway-advanced curtain space integrated grouting method after penetrating goaf wall | |
CN103089275B (en) | Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections | |
CN103233740B (en) | Top-cutting roadway coal-pillar-free mining method of close-range thin coal seam | |
CN102937030B (en) | Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock | |
CN109209392B (en) | Full-ring excavation method suitable for IV-V-grade surrounding rock of large-section tunnel | |
CN104929666A (en) | Top breaking gob-side entry retaining method for tender roofs | |
CN102877858B (en) | Reinforcing method for crushed top plate of coal face | |
CN106884655B (en) | A two-way reinforcement method for coal pillars in gob-side roadway | |
CN108316941B (en) | Broken surrounding rock and soft rock roadway U-shaped steel canopy supporting method | |
CN103195426A (en) | Steep-coal-seam long wall face non-pillar coal mining method | |
CN109989777B (en) | Method for controlling initial support large deformation of tunnel small-mileage extrusion deformation section | |
CN111535817A (en) | Working face double-lane tunneling small coal pillar reinforcement construction method | |
CN105927243B (en) | A kind of underground country rock tomography suspension device and method for protecting support | |
CN108035742B (en) | A method of active and passive harmonious support for extremely weak coal seam roadway | |
CN108775252A (en) | The supporting construction and method for protecting support in Deep Soft Rock tunnel | |
CN113605893B (en) | Control method for pre-filling full gob-side entry driving surrounding rock | |
WO2016150188A1 (en) | Method for fracturing filler wall left behind in adjacent coal-mining face | |
CN105863700B (en) | A kind of roadside support method of shallow coal level lane | |
CN102425155B (en) | A superficial reinforcement method of overlying rock mass in goaf | |
Li et al. | Trial of small gateroad pillar in top coal caving longwall mining of large mining height | |
CN103806917A (en) | Vertical strip roadway tunneling method | |
CN110552731A (en) | top coal caving stoping roadway grouting anchor cable supporting structure and advanced supporting method thereof | |
CN119122523A (en) | A kind of gob-side tunnel top cutting pressure relief support structure and support method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |