CN107060786A - A kind of Shield Construction Method Used method that groups of building are worn under karst region - Google Patents
A kind of Shield Construction Method Used method that groups of building are worn under karst region Download PDFInfo
- Publication number
- CN107060786A CN107060786A CN201710464609.8A CN201710464609A CN107060786A CN 107060786 A CN107060786 A CN 107060786A CN 201710464609 A CN201710464609 A CN 201710464609A CN 107060786 A CN107060786 A CN 107060786A
- Authority
- CN
- China
- Prior art keywords
- karst
- grouting
- building
- shield
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 82
- 238000000034 method Methods 0.000 title claims abstract description 48
- 230000002787 reinforcement Effects 0.000 claims abstract description 58
- 238000001514 detection method Methods 0.000 claims abstract description 28
- 230000005641 tunneling Effects 0.000 claims abstract description 25
- 238000012544 monitoring process Methods 0.000 claims abstract description 22
- 230000001360 synchronised effect Effects 0.000 claims abstract description 16
- 238000012360 testing method Methods 0.000 claims abstract description 9
- 238000011835 investigation Methods 0.000 claims abstract description 5
- 239000002002 slurry Substances 0.000 claims description 67
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 claims description 65
- 235000019353 potassium silicate Nutrition 0.000 claims description 64
- 239000004568 cement Substances 0.000 claims description 60
- 238000005553 drilling Methods 0.000 claims description 60
- 239000000243 solution Substances 0.000 claims description 57
- 239000011440 grout Substances 0.000 claims description 48
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 30
- 239000002689 soil Substances 0.000 claims description 25
- 239000007788 liquid Substances 0.000 claims description 19
- 239000000203 mixture Substances 0.000 claims description 13
- 230000000694 effects Effects 0.000 claims description 12
- 239000000463 material Substances 0.000 claims description 12
- 230000003014 reinforcing effect Effects 0.000 claims description 12
- 230000009977 dual effect Effects 0.000 claims description 9
- 238000007689 inspection Methods 0.000 claims description 9
- 239000006260 foam Substances 0.000 claims description 5
- 238000002347 injection Methods 0.000 claims description 5
- 239000007924 injection Substances 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 238000005056 compaction Methods 0.000 claims description 4
- 229910052738 indium Inorganic materials 0.000 claims description 4
- APFVFJFRJDLVQX-UHFFFAOYSA-N indium atom Chemical compound [In] APFVFJFRJDLVQX-UHFFFAOYSA-N 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000005187 foaming Methods 0.000 claims description 3
- 238000011065 in-situ storage Methods 0.000 claims description 3
- 230000002093 peripheral effect Effects 0.000 claims description 3
- 239000000126 substance Substances 0.000 claims description 3
- 238000007569 slipcasting Methods 0.000 claims 17
- 238000012545 processing Methods 0.000 claims 7
- 239000011083 cement mortar Substances 0.000 claims 6
- 230000006641 stabilisation Effects 0.000 claims 5
- 238000011105 stabilization Methods 0.000 claims 5
- 239000013049 sediment Substances 0.000 claims 3
- 238000000280 densification Methods 0.000 claims 2
- 238000003672 processing method Methods 0.000 claims 2
- 239000004115 Sodium Silicate Substances 0.000 claims 1
- 238000007596 consolidation process Methods 0.000 claims 1
- 239000004088 foaming agent Substances 0.000 claims 1
- 238000005259 measurement Methods 0.000 claims 1
- 229910052751 metal Inorganic materials 0.000 claims 1
- 239000002184 metal Substances 0.000 claims 1
- 210000004911 serous fluid Anatomy 0.000 claims 1
- 229910052911 sodium silicate Inorganic materials 0.000 claims 1
- 235000019994 cava Nutrition 0.000 abstract description 28
- 238000009412 basement excavation Methods 0.000 abstract description 25
- 239000012530 fluid Substances 0.000 description 12
- JEGUKCSWCFPDGT-UHFFFAOYSA-N h2o hydrate Chemical compound O.O JEGUKCSWCFPDGT-UHFFFAOYSA-N 0.000 description 10
- 238000011161 development Methods 0.000 description 9
- 230000035699 permeability Effects 0.000 description 6
- 238000010586 diagram Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 4
- 230000009191 jumping Effects 0.000 description 3
- 230000002159 abnormal effect Effects 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 2
- 238000005065 mining Methods 0.000 description 2
- 230000035515 penetration Effects 0.000 description 2
- 238000002203 pretreatment Methods 0.000 description 2
- 238000011160 research Methods 0.000 description 2
- 238000005488 sandblasting Methods 0.000 description 2
- 238000007711 solidification Methods 0.000 description 2
- 230000008023 solidification Effects 0.000 description 2
- 239000011550 stock solution Substances 0.000 description 2
- 238000009792 diffusion process Methods 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 239000011521 glass Substances 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
- E21D9/0607—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本发明公开了一种城市地铁隧道施工技术领域,特别是一种在岩溶区下穿建筑群的盾构掘进施工方法。该种方法主要施工步骤有:(a)建筑物安全现状调查及监测系统布设;(b)岩溶预探测及预处理;(c)盾构试掘进,确定施工参数和渣土改良工艺参数;(d)正式掘进施工,并予以渣土改良、同步注浆及二次补强注浆;(e)盾构掘进过程中岩溶探测及处理;(f)隧道壁后岩溶探测及处理;(g)先行洞探查及处理后行洞溶洞。本施工方法通过在盾构掘进路段进行地面岩溶探测及预处理,在盾构掘进过程中予以渣土改良、同步注浆、二次补强注浆,并在盾构掘进下穿建筑物段在隧道洞内辅以岩溶探明及处理等措施确保岩溶区隧道盾构掘进顺利下穿建筑群。
The invention discloses the technical field of urban subway tunnel construction, in particular to a shield tunneling construction method for passing through building groups in karst areas. The main construction steps of this method are: (a) building safety status investigation and monitoring system layout; (b) karst pre-detection and pretreatment; (c) shield tunneling test, to determine the construction parameters and dreg improvement process parameters; ( d) Formal excavation construction, and muck improvement, synchronous grouting and secondary reinforcement grouting; (e) Karst detection and treatment during shield excavation; (f) Karst detection and treatment behind the tunnel wall; (g) Exploration and treatment of caves in the first cave and karst caves in the latter cave. In this construction method, ground karst detection and pretreatment are carried out in the shield excavation section, muck improvement, synchronous grouting, and secondary reinforcement grouting are carried out during the shield excavation process, and the building section under the shield excavation is The tunnel is supplemented by measures such as karst exploration and treatment to ensure that the shield tunneling in the karst area passes smoothly under the building complex.
Description
技术领域technical field
本发明涉及城市隧道施工技术领域,特别涉及一种在岩溶区下穿建筑群的盾构掘进施工方法。The invention relates to the technical field of urban tunnel construction, in particular to a shield tunneling construction method for passing through building groups in karst areas.
背景技术Background technique
随着我国经济水平的不断提高,大量农村人口涌入城市,推动城市发展的同时也给城市带来沉重的交通负担,城市轨道交通由于其方面快捷且不占用地面空间而得到了迅猛发展。在现行轨道施工技术中,通常采用盾构机进行隧道掘进,而在我国南方地区进行城市轨道施工时经常需要在岩溶区下穿建筑群,现行施工技术中,通常通过地面钻孔对溶洞进行灌浆压密来提高土体强度。With the continuous improvement of my country's economic level, a large number of rural populations are pouring into cities, which promotes urban development and also brings heavy traffic burdens to cities. Urban rail transit has developed rapidly due to its fast and non-occupied ground space. In the current track construction technology, the shield machine is usually used for tunnel excavation, and in the urban track construction in southern my country, it is often necessary to pass through the building complex in the karst area. In the current construction technology, the karst cave is usually grouted through ground drilling compaction to increase soil strength.
当盾构隧道下穿建筑物时,若没有地面钻孔施工条件,将无法继续利用上述施工方法对岩溶进行探测及处理,同时由于建筑物的存在,对地表变形要求更加严格,城市轨道施工将面临盾构掘进过程中岩溶探测和处理及控制建筑物变形的双重挑战。When the shield tunnel passes through the building, if there is no ground drilling construction conditions, it will not be possible to continue to use the above construction methods to detect and deal with karst. At the same time, due to the existence of buildings, the requirements for surface deformation are more stringent, urban rail construction will Faced with the dual challenges of karst detection and treatment and control of building deformation during shield tunneling.
发明内容Contents of the invention
本发明的目的在于:盾构隧道在岩溶区下穿建筑群而部分区域缺乏地面钻孔施工条件,同时建筑物变形要求严格时,提供一种在岩溶区下穿建筑群的盾构掘进施工方法。该方法通过对具有地面钻孔施工工作面的岩溶区进行钻孔探测及处理,对无法进行地面钻孔施工的区域采用超前钻、地质雷达扫描及隧道洞内钻孔的方式探测盾构掘进区域内岩溶发育状况,并通过加密超前钻钻孔及隧道洞内钻孔对已探明溶洞予以注浆加固,同时在施工过程中加强地面和建筑物变形监测,及时反馈监测信息并积极调整施工参数,确保隧道盾构掘进顺利下穿岩溶区建筑群。The object of the present invention is to provide a shield tunneling construction method for tunneling under the building group in the karst area when the shield tunnel passes through the building group in the karst area and there is no ground drilling construction condition in some areas, and the building deformation requirements are strict. . The method detects and processes the karst area with the ground drilling construction face, and uses advanced drilling, geological radar scanning and tunnel drilling to detect the shield excavation area in the area where the ground drilling construction cannot be carried out. The development of karst in the interior, and the proven karst caves are reinforced by grouting through advanced drilling and tunnel drilling. At the same time, the deformation monitoring of the ground and buildings is strengthened during the construction process, and the monitoring information is fed back in time and the construction parameters are actively adjusted. , to ensure that the shield excavation of the tunnel passes smoothly through the building complex in the karst area.
为了实现上述发明目的,本发明提供了以下技术方案:In order to realize the above-mentioned purpose of the invention, the present invention provides the following technical solutions:
一种在岩溶区下穿建筑群的盾构掘进施工方法,包括以下步骤:A shield tunneling construction method for passing through building groups in a karst area, comprising the following steps:
a、建筑物安全现状调查及监测系统布设;a. Building safety status investigation and monitoring system layout;
b、岩溶预探测及预处理;b. Karst pre-detection and pre-treatment;
c、盾构试掘进,确定施工参数和渣土改良工艺参数;c. Shield tunneling test, to determine the construction parameters and dregs improvement process parameters;
d、正式掘进施工,并予以渣土改良、同步注浆及二次补强注浆;d. Formal excavation construction, and muck improvement, synchronous grouting and secondary reinforcement grouting;
e、盾构掘进过程中岩溶探测及处理;e. Karst detection and treatment during shield excavation;
f、隧道壁后岩溶探测及处理;f. Karst detection and treatment behind the tunnel wall;
g、先行洞探查及处理后行洞溶洞。g. Exploration and treatment of caves in advance and karst caves in subsequent caves.
上述施工步骤中,通过对盾构下穿区建筑物利用精密水准仪和铟钢尺测量建筑物既有沉降和相对倾斜,并根据建筑物类型确定其安全现状和剩余结构变形能力,为后续岩溶加固处理及隧道盾构下穿提供安全依据。In the above construction steps, the existing settlement and relative inclination of the building are measured by using a precision level and an indium steel ruler in the shield passing area, and its safety status and remaining structural deformation capacity are determined according to the type of building, so as to prepare for the subsequent karst reinforcement. Handling and tunnel shield underpassing provide safety basis.
对岩溶进行注浆加固处理及采用盾构法施工隧道必然对沿线地表环境产生影响,为确保工程安全,并保护周围环境,需要在施工全过程中进行监测,通过布设沉降、相对倾斜及裂缝监测系统,实时监测建筑物因施工而产生的变形,并根据监测结果,在施工过程中积极改进施工工艺和施工参数,最大限度减小周边地表、建筑物等的变形。The grouting reinforcement treatment of karst and the construction of tunnels using the shield method will inevitably have an impact on the surface environment along the line. In order to ensure project safety and protect the surrounding environment, it is necessary to monitor during the entire construction process, through the monitoring of settlement, relative inclination and cracks The system monitors the deformation of the building due to construction in real time, and according to the monitoring results, actively improves the construction process and construction parameters during the construction process to minimize the deformation of the surrounding ground and buildings.
上述施工步骤b中,在对岩溶区进行预处理前须判明岩溶预处理范围及岩溶发育状况。所述岩溶处理范围须根据建筑物类型、岩溶形态与大小、岩溶与建筑物相对位置关系评估盾构掘进过程中岩溶对建筑物影响,进而确定岩溶处理范围。In the above construction step b, the karst pretreatment range and karst development status must be identified before the karst area is pretreated. The scope of karst treatment must be based on the type of building, the shape and size of karst, and the relative positional relationship between karst and buildings to evaluate the impact of karst on buildings during shield tunneling, and then determine the scope of karst treatment.
上述施工步骤中,所述探明岩溶发育状况即利用地面垂直钻孔与倾斜钻孔获得芯样判明溶洞大小及充填情况。In the above construction steps, the verification of the karst development status is to obtain core samples by using the vertical and inclined boreholes on the ground to determine the size and filling status of the karst caves.
由于建筑物存在而无法进行地面垂直钻孔施工的隧道盾构掘进区域,选用矿研多功能快速钻机进行斜向钻孔探测溶洞,并根据隧道埋深,房屋基础位置确定钻孔平面位置及角度。In the tunnel shield excavation area where the ground vertical drilling cannot be carried out due to the existence of buildings, the multifunctional fast drilling rig of Mining Research Institute is used to conduct oblique drilling to detect karst caves, and the drilling plane position and angle are determined according to the buried depth of the tunnel and the position of the foundation of the house. .
岩溶预处理须根据已探明单个溶洞大小及充填情况选择相应加固方法,可归纳如下:For karst pretreatment, the corresponding reinforcement method must be selected according to the proven individual cave size and filling conditions, which can be summarized as follows:
(1)全充填溶洞:采用袖阀管对溶洞内充填物进行分层压密注浆。(1) Full filling of caves: Sleeve valve tubes are used to perform layered compaction grouting on the fillings in the caves.
(2)半填充和未填充溶洞:采用吹砂+化学灌浆的方法。(2) Semi-filled and unfilled caves: sand blasting + chemical grouting.
(3)注浆顺序:由外向内进行,先对溶洞边界予以双液浆充填,阻断浆液漏失通道后,再逐步向内用水泥浆对溶洞区中部灌浆压密;(3) Grouting sequence: from the outside to the inside, first fill the boundary of the cave with double-liquid grout, block the leakage channel of the grout, and then gradually grout and compact the middle of the cave area with cement grout;
(4)为防止邻孔串浆降低注浆效果,注浆须跳孔进行。(4) In order to prevent grouting from adjacent holes and reduce the grouting effect, grouting must be performed by jumping holes.
在对溶洞进行预处理时,注浆顺序须遵循由外向内的原则,即先对溶洞边界予以双液浆充填,阻断浆液漏失通道后,再逐步向内用水泥浆进行溶洞区中部的灌浆压密;同时由于钻孔注浆浆液扩散半径较大,对土体扰动较大,且浆液凝固时间较长,当按钻孔顺序进行喷浆加固时容易造成邻孔串浆而影响加固效果,故须予以跳孔注浆加固。When pretreating the cave, the grouting sequence must follow the principle from the outside to the inside, that is, first fill the cave boundary with double-liquid grout, block the leakage channel of the grout, and then gradually use the grouting grouting pressure in the middle of the cave area. At the same time, due to the large diffusion radius of the drilling grouting grout, the disturbance to the soil is large, and the grout solidification time is long, when the grouting reinforcement is carried out according to the drilling sequence, it is easy to cause grouting in adjacent holes and affect the reinforcement effect. It must be strengthened by jumping hole grouting.
岩溶预处理加固中,注浆加固区外围可用双液浆封闭,防止浆液漏失,内部采用纯水泥浆填充;所述双液浆浆材为水泥浆与水玻璃溶液,其中水泥浆成分包括水泥和水,水灰比为0.5:1~1:1,水玻璃溶液包括水玻璃和水,水玻璃溶液浓度为30~40°Be',水泥浆和水玻璃溶液配合为4:1~6:1;纯水泥浆成分包括水泥和水,水灰比为0.5:1~1:1,具体配合比应根据现场试验确定。In the karst pretreatment reinforcement, the periphery of the grouting reinforcement area can be closed with double-liquid slurry to prevent the leakage of the grout, and the interior is filled with pure cement slurry; the material of the double-liquid slurry is cement slurry and water glass solution, and the cement slurry components include cement and Water, the water-cement ratio is 0.5:1~1:1, the water glass solution includes water glass and water, the concentration of the water glass solution is 30~40°Be', and the ratio of cement slurry and water glass solution is 4:1~6:1 ; The components of pure cement slurry include cement and water, and the water-cement ratio is 0.5:1 to 1:1. The specific mixing ratio should be determined according to field tests.
岩溶预处理加固中,对于加固区外围,为使浆液快速凝固并有效阻止浆液漏失,注浆应以相对小压力、多次数、较大量控制,注浆压力0.4~0.7MPa,注浆次数3~4次;对于加固区中部,注浆压力为0~0.7MPa,注浆压力由0逐步提高,达到注浆终压并继续注浆10min以上,压浆3次,注浆速度30~50L/min;每次注浆间歇时间对于加固区外围取30min,对于加固区中部取6~10h,采用间歇注浆旨在多次填充挤压土体,使土体强度得到最大限度提高并有效降低土体渗透系数。In the karst pretreatment reinforcement, for the periphery of the reinforcement area, in order to make the grout solidify quickly and effectively prevent the grout from leaking, the grouting should be controlled with a relatively small pressure, multiple times, and relatively large quantities. The grouting pressure is 0.4-0.7 MPa, and the grouting frequency is 3-3 4 times; for the middle part of the reinforcement area, the grouting pressure is 0-0.7MPa, and the grouting pressure is gradually increased from 0 to the final grouting pressure, and the grouting is continued for more than 10 minutes, the grouting is 3 times, and the grouting speed is 30-50L/min ; The intermittent time of each grouting is 30 minutes for the periphery of the reinforcement area, and 6-10 hours for the middle of the reinforcement area. Intermittent grouting is used to fill the extruded soil multiple times, so that the strength of the soil can be maximized and the soil can be effectively reduced. permeability coefficient.
上述施工步骤中,岩溶预处理完后,须对注浆效果进行检验,检验方法为钻孔抽芯法结合随机原位标贯试验,检测数量为注浆孔数量的1%,且每个溶洞检测数量不少于1个检测钻孔。注浆加固区土体应满足钻孔芯样28d无侧限抗压强度值≥0.5MPa;加固体渗透系数不大于1×10-5cm/s;对于随机原位标贯试验,标准贯入度不小于10击。In the above construction steps, after the karst pretreatment, the grouting effect must be inspected. The inspection method is the drilling core-pulling method combined with the random in-situ standard penetration test. The number of inspections is 1% of the number of grouting holes, and each The number of inspections shall not be less than one inspection drill hole. The soil in the grouting reinforcement area should meet the 28d unconfined compressive strength value of the borehole core sample ≥ 0.5MPa; the permeability coefficient of the reinforcement body should not be greater than 1×10 -5 cm/s; The speed is not less than 10 hits.
在岩溶区盾构正式掘进前应根据试掘进确定施工参数,所述施工参数包括总推力、推进速度、刀盘扭矩、土仓压力和同步注浆参数。其中:总推力为1300~1600t,推进速度为5~10mm/min,刀盘扭矩为3.0~3.5MN·m,土仓压力为1.2~1.4Bar,同步注浆率为300%,同步注浆压力为2.0~4.0Bar间。在盾构正式掘进过程中应根据建筑物实时沉降、变形监测数据及盾构机前方土体性质而调整施工参数。Before the formal excavation of the shield tunneling in the karst area, the construction parameters should be determined according to the trial excavation. The construction parameters include total thrust, advancing speed, cutter head torque, soil chamber pressure and synchronous grouting parameters. Among them: the total thrust is 1300-1600t, the propulsion speed is 5-10mm/min, the cutterhead torque is 3.0-3.5MN·m, the soil bin pressure is 1.2-1.4Bar, the synchronous grouting rate is 300%, the synchronous grouting pressure Between 2.0 and 4.0 Bar. During the formal tunneling process of the shield machine, the construction parameters should be adjusted according to the real-time settlement and deformation monitoring data of the building and the properties of the soil in front of the shield machine.
上述施工步骤中,为防止刀盘渣土改良喷口阻塞,同时对刀盘刀具进行润滑及降温,应使用泡沫剂进行渣土改良,其中,泡沫原液浓度为3~5%,发泡率为10~20倍,注入率为5~10%。该渣土改良工艺参数须根据实时工况予以调整。In the above construction steps, in order to prevent the clogging of the cutter head dregs improvement nozzle, and at the same time lubricate and cool the cutter head cutter, a foam agent should be used for dregs improvement, wherein the concentration of the foam stock solution is 3 to 5%, and the foaming rate is 10% ~20 times, the injection rate is 5~10%. The parameters of the muck improvement process must be adjusted according to real-time working conditions.
上述施工步骤中,同步注浆浆液选用双液浆,所述双液浆浆材为水泥浆和水玻璃溶液,其中,水泥浆成分为水泥和水,水灰比为1:1;所述水玻璃溶液成分为水玻璃和水,水玻璃浓度为30~40°Be',其体积配合比为水玻璃:水=1:1~1:2;所述水泥浆和水玻璃溶液体积配合比为4:1~6:1;浆液配比应在现用配比基础上进行现场试配确定,并根据现场掘进条件予以调整和优化。In the above construction steps, the synchronous grouting slurry is selected from double-liquid slurry, and the material of the double-liquid slurry is cement slurry and water glass solution, wherein the cement slurry is composed of cement and water, and the water-cement ratio is 1:1; the water Glass solution composition is water glass and water, and water glass concentration is 30~40 ° Be ', and its volume mixing ratio is water glass: water=1:1~1:2; Described cement slurry and water glass solution volume mixing ratio are 4:1 to 6:1; the grout ratio should be determined on the basis of the current ratio through on-site trial matching, and adjusted and optimized according to the on-site excavation conditions.
上述施工步骤中,盾构机通过后,应在成型隧道纵向布置地质雷达测线扫描管片壁后空洞情况,并对存在松散、空洞、松散异常的位置立即组织二次双液浆补强注浆,达到加固土体和加固充填空洞的目的。In the above construction steps, after the shield machine passes through, a geological radar survey line should be arranged longitudinally in the forming tunnel to scan the cavity behind the segment wall, and a second double-liquid slurry reinforcement injection should be immediately organized for the positions where looseness, cavity, and looseness are abnormal. slurry to achieve the purpose of reinforcing the soil and reinforcing the filling cavity.
二次补强注浆浆液为双液浆,所述双液浆浆材为水泥浆和水玻璃溶液,其中,水泥浆成分为水泥和水,水灰比为1:1;所述水玻璃溶液成分为水玻璃和水,水玻璃浓度为30~40°Be',其体积配合比为水玻璃:水=1:1~1:2;所述水泥浆和水玻璃溶液体积配合比为4:1~6:1。The secondary reinforcing grouting grout is double-fluid grout, and the material of the double-fluid grout is cement slurry and water glass solution, wherein, the cement slurry components are cement and water, and the water-cement ratio is 1:1; the water glass solution The composition is water glass and water, the concentration of water glass is 30~40°Be', its volume mixing ratio is water glass: water=1:1~1:2; the volume mixing ratio of described cement slurry and water glass solution is 4: 1~6:1.
上述施工步骤中,在无法实施地面钻孔探测地段应运用盾构机前端超前钻设施探明隧道掘进方向内岩溶发育状况,运用地质雷达扫描辅以隧道内钻孔探明已成型隧道管片壁后溶洞,并通过加密钻孔对已探明溶洞予以注浆加固处理。其中岩溶处理范围须根据建筑物类型、岩溶形态与大小、岩溶与建筑物相对位置关系来评估盾构掘进过程中岩溶对建筑物影响而获得。In the above-mentioned construction steps, in the areas where ground drilling cannot be carried out, the advanced drilling facilities at the front end of the shield machine should be used to find out the karst development in the direction of tunnel excavation, and the geological radar scanning and drilling in the tunnel should be used to find out the formed tunnel segment wall After the karst caves, the proven karst caves were grouted and reinforced through intensified drilling. The scope of karst treatment must be obtained by evaluating the impact of karst on buildings during shield excavation based on building type, karst shape and size, and relative positional relationship between karst and buildings.
盾构掘进过程中岩溶处理即运用超前钻器具及隧道内钻孔对隧道掘进方向及已成型隧道周边已探明溶洞予以注浆加固处理。注浆加固方法可归纳如下:The karst treatment in the shield excavation process is to use the advanced drilling equipment and the boreholes in the tunnel to grout the tunnel excavation direction and the proven karst caves around the formed tunnel. The grouting reinforcement methods can be summarized as follows:
(1)为保证建筑物安全,对已探明须处理岩溶,无论溶洞大小与充填情况均采用双液浆予以加固;(1) In order to ensure the safety of the building, for the proven karst that needs to be dealt with, regardless of the size of the cave and the filling condition, it is reinforced with double liquid slurry;
(2)注浆顺序:由外向内进行,先对溶洞边界予以双液浆充填,阻断浆液漏失通道后,再逐步向内对溶洞区中部灌浆压密;(2) Grouting sequence: from outside to inside, first fill the boundary of the cave with double-liquid grout, block the leakage channel of the grout, and then gradually grout and compact the middle of the cave area inward;
(3)为防止邻孔串浆影响注浆效果,注浆须跳孔进行。(3) In order to prevent grouting in adjacent holes from affecting the grouting effect, grouting must be carried out by skipping holes.
超前钻及隧道内钻孔注浆加固浆液均为为双液浆,双液浆浆材为水泥浆与水玻璃溶液,其中水泥浆水灰比为0.5:1~1:1,水玻璃溶液成分包括水玻璃和水,水玻璃溶液浓度为30~40°Be',水泥浆和水玻璃溶液配合为4:1~6:1。Both advanced drilling and tunnel drilling and grouting reinforcement are double-fluid slurry, and the double-fluid slurry material is cement slurry and water glass solution. Including water glass and water, the concentration of water glass solution is 30-40°Be', and the ratio of cement slurry and water glass solution is 4:1-6:1.
对于岩溶加固区外围注浆,以相对小压力、多次数、较大量控制,注浆压力0.4~0.7MPa,注浆3~4次,每次注浆间歇时间可取30min;对于加固区中部,注浆压力可取0~0.4MPa,达到注浆终压并继续注浆10min以上,压浆4~5次,注浆速度20~30L/min,,每次注浆间歇时间取30min。For the grouting around the karst reinforcement area, the grouting pressure is 0.4-0.7MPa, the grouting time is 3-4 times, and the interval between each grouting is 30 minutes; for the middle part of the reinforcement area, grouting The grouting pressure can be 0~0.4MPa, reach the final grouting pressure and continue grouting for more than 10min, grouting 4~5 times, the grouting speed is 20~30L/min, and the interval time of each grouting is 30min.
在无法实施地面钻孔探测的下穿建筑物段,通过在先行洞隧道相应范围增加地质雷达测线并辅以隧道内钻孔的方式探明另一条隧道未施工段地质情况。若探明另一条隧道相应区域有溶洞,则可从已施工一侧隧道管片处加密钻孔进行注浆处理。In the section under the building where the ground drilling detection cannot be implemented, the geological situation of the unconstructed section of the other tunnel is proved by adding the geological radar survey line in the corresponding range of the tunnel ahead and supplemented by drilling in the tunnel. If it is found that there is a karst cave in the corresponding area of the other tunnel, the tunnel segment of the constructed side can be intensified and drilled for grouting.
上述施工步骤中,对另一侧隧道下穿建筑物区域内岩溶进行注浆加固处理时,浆液采用双液浆,双液浆浆材为水泥浆与水玻璃溶液,其中,水泥浆成分为水泥和水,水灰比为1:1;水玻璃溶液成分为水玻璃和水,水玻璃浓度为30~40°Be',其体积配合比为水玻璃:水=1:1~1:2;所述水泥浆和水玻璃溶液体积配合比为4:1~6:1。In the above construction steps, when performing grouting reinforcement treatment on the karst in the area where the tunnel passes under the building on the other side, the grout adopts double-fluid grout, and the double-fluid grout material is cement slurry and water glass solution, wherein the cement grout is composed of cement and water, the water-cement ratio is 1:1; the composition of water glass solution is water glass and water, the concentration of water glass is 30-40°Be', and its volume mixing ratio is water glass: water = 1:1-1:2; The volume ratio of the cement slurry to the water glass solution is 4:1-6:1.
对另一侧隧道下穿建筑物区域内岩溶进行注浆加固处理时,对于岩溶加固区外围注浆,以相对小压力、多次数、较大量控制,注浆压力0.4~0.7MPa,注浆3~4次,每次注浆间歇时间可取30min;对于加固区中部,注浆压力可取0~0.4MPa,达到注浆终压并继续注浆10min以上,压浆4~5次,注浆速度20~30L/min,,每次注浆间歇时间取30min。When performing grouting reinforcement treatment on the karst in the area where the tunnel passes under the building on the other side, for the peripheral grouting of the karst reinforcement area, the grouting pressure should be controlled at a relatively small pressure, multiple times, and a relatively large amount. ~ 4 times, the intermittent time of each grouting can be 30min; for the middle part of the reinforcement area, the grouting pressure can be 0-0.4MPa, reach the final grouting pressure and continue grouting for more than 10min, grouting 4-5 times, the grouting speed is 20 ~30L/min, the interval time between each grouting is 30min.
附图说明Description of drawings
图1为本发明岩溶区下穿建筑群的盾构掘进施工方法流程图。Fig. 1 is the flow chart of the construction method of shield tunneling under the building complex in the karst area of the present invention.
图2为地面斜孔探测溶洞示意图。Figure 2 is a schematic diagram of the detection of karst caves by oblique holes on the ground.
图3为隧道内超前钻探测溶洞剖面示意图。Fig. 3 is a schematic diagram of the section of the karst cave detected by advanced drilling in the tunnel.
图4为隧道内地质雷达及钻孔探测溶洞示意图。Figure 4 is a schematic diagram of geological radar and borehole detection of karst caves in the tunnel.
图5为先行洞探查后行洞溶洞示意图。Fig. 5 is a schematic diagram of the karst cave after the first cave exploration.
图中标记:1—建筑物,2—地表,3—地面斜孔探测,4—溶洞,5—拟建隧道,6—超前钻探测,7—已建成隧道,8—盾构机,9—隧道洞内钻孔探测,10—地质雷达探测,11—先行洞内钻孔探测后行洞溶洞。Marks in the figure: 1—building, 2—ground surface, 3—ground inclined hole detection, 4—karst cave, 5—planned tunnel, 6—advanced drilling detection, 7—completed tunnel, 8—shield machine, 9— Borehole detection in the tunnel, 10—Georadar detection, 11—Drill hole detection in the first cave, and then the karst cave.
具体实施方式detailed description
下面结合试验例及具体实施方式对本发明做进一步的详细描述。但不应将此理解为本发明上述主题的范围仅限于以下的实施例,凡基于本发明内容所实现的技术均属于本发明的范围。The present invention will be further described in detail below in conjunction with test examples and specific embodiments. However, it should not be understood that the scope of the above subject matter of the present invention is limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.
实施例Example
本实施例用于在岩溶区下穿建筑群的盾构掘进施工场合。This embodiment is used in the construction occasion of shield tunneling under the building group in the karst area.
在如图1所示,在岩溶区下穿建筑群的盾构掘进施工方法,包括以下步骤:As shown in Figure 1, the shield tunneling construction method for passing through the building complex in the karst area includes the following steps:
a、建筑物安全现状调查及监测系统布设;a. Building safety status investigation and monitoring system layout;
b、岩溶预探测及预处理;b. Karst pre-detection and pre-treatment;
c、盾构试掘进,确定施工参数和渣土改良工艺参数;c. Shield tunneling test, to determine the construction parameters and dregs improvement process parameters;
d、正式掘进施工,并予以渣土改良、同步注浆及二次补强注浆;d. Formal excavation construction, and muck improvement, synchronous grouting and secondary reinforcement grouting;
e、盾构掘进过程中岩溶探测及处理;e. Karst detection and treatment during shield excavation;
f、隧道壁后岩溶探测及处理;f. Karst detection and treatment behind the tunnel wall;
g、先行洞探查及处理后行洞溶洞。g. Exploration and treatment of caves in advance and karst caves in subsequent caves.
上述施工步骤中,通过对盾构下穿区建筑物区域内建筑物利用精密水准仪和铟钢尺测量建筑物既有沉降和相对倾斜,并根据建筑物类型确定其安全现状和剩余结构变形能力,为后续岩溶加固处理及隧道盾构下穿提供了安全依据。In the above construction steps, the existing settlement and relative inclination of the building are measured by using a precision level and an indium steel ruler in the building area of the shield tunneling area, and its safety status and remaining structural deformation capacity are determined according to the type of building. It provides a safety basis for subsequent karst reinforcement treatment and tunnel shield tunneling.
通过布设沉降、相对倾斜及裂缝监测系统,实时监测建筑物因施工而产生的变形,并根据监测结果,在施工过程中积极改进施工工艺和施工参数,可最大限度减小周边地表、建筑物等的变形。By laying out settlement, relative inclination and crack monitoring systems, real-time monitoring of the deformation of buildings due to construction, and according to the monitoring results, during the construction process, the construction process and construction parameters are actively improved to minimize the surrounding surface, buildings, etc. deformation.
上述施工步骤中,通过在岩溶处理范围内,利用地面垂直钻孔与倾斜钻孔获得芯样判明溶洞大小及充填情况,为后续岩溶处理提供依据。In the above-mentioned construction steps, within the scope of karst treatment, the core samples were obtained by using the vertical drilling and inclined drilling on the ground to determine the size and filling of the cave, so as to provide a basis for subsequent karst treatment.
岩溶处理范围须根据建筑物类型、岩溶形态与大小、岩溶与建筑物相对位置关系来评估盾构掘进过程中岩溶对建筑物影响而获得。The scope of karst treatment must be obtained by evaluating the impact of karst on buildings during shield excavation based on building type, karst shape and size, and relative positional relationship between karst and buildings.
如图2所示,在无地面垂直钻孔工作面时,可使用矿研多功能快速钻机进行斜向钻孔探测并处理溶洞,根据隧道埋深、房屋基础位置确定钻孔平面位置及角度。As shown in Figure 2, when there is no vertical drilling face on the ground, the mining research multifunctional fast drilling rig can be used to detect and process karst caves by oblique drilling, and the plane position and angle of the drilling can be determined according to the buried depth of the tunnel and the position of the foundation of the house.
上述施工步骤中,根据溶洞大小及充填情况,岩溶处理方法可归纳如下:In the above construction steps, according to the cave size and filling conditions, the karst treatment methods can be summarized as follows:
(1)全充填溶洞:采用袖阀管对溶洞内充填物进行分层压密注浆。(1) Full filling of caves: Sleeve valve tubes are used to perform layered compaction grouting on the fillings in the caves.
(2)半填充和未填充溶洞:采用吹砂+化学灌浆的方法。(2) Semi-filled and unfilled caves: sand blasting + chemical grouting.
(3)注浆顺序:由外向内进行,先对溶洞边界予以双液浆充填,阻断浆液漏失通道后,再逐步向内用水泥浆对溶洞区中部灌浆压密;(3) Grouting sequence: from the outside to the inside, first fill the boundary of the cave with double-liquid grout, block the leakage channel of the grout, and then gradually grout and compact the middle of the cave area with cement grout;
(4)为防止邻孔串浆降低注浆效果,注浆须跳孔进行。(4) In order to prevent grouting from adjacent holes and reduce the grouting effect, grouting must be performed by jumping holes.
为使浆液逐步挤压充填土体,从而最大限度提高土体强度,降低土体渗透系数,为后续盾构掘进施工提供保障,在对溶洞进行预处理注浆加固时,注浆顺序采用由外向内的原则,先对溶洞边界予以双液浆充填,阻断浆液漏失通道后,再逐步向内用水泥浆进行溶洞区中部的灌浆压密;同时由于钻孔注浆浆液扩散半径较大,对土体扰动较大,且浆液凝固时间较长,当按钻孔顺序进行喷浆加固时容易造成邻孔串浆而影响加固效果,故须予以跳孔注浆加固。In order to make the grout gradually squeeze the filling soil, thereby maximizing the strength of the soil, reducing the permeability coefficient of the soil, and providing guarantee for the subsequent shield tunneling construction, when pretreatment and grouting reinforcement of the cave, the grouting sequence is from outward to Based on the internal principle, first fill the boundary of the cave with double-fluid grout to block the passage of grout leakage, and then gradually use cement slurry inward to compact the grouting in the middle of the cave area; The disturbance of the body is large, and the solidification time of the grout is long. When the grouting reinforcement is carried out according to the drilling sequence, it is easy to cause the grouting in the adjacent holes and affect the reinforcement effect, so the grouting reinforcement must be skipped.
岩溶预处理加固中,注浆加固区外围可用双液浆封闭,防止浆液漏失,内部采用纯水泥浆填充;所述双液浆浆材为水泥浆与水玻璃溶液,其中水泥浆成分包括水泥和水,水灰比为0.5:1~1:1,水玻璃溶液包括水玻璃和水,水玻璃溶液浓度为30~40°Be',水泥浆和水玻璃溶液配合为4:1~6:1;纯水泥浆成分包括水泥和水,水灰比为0.5:1~1:1,具体配合比应根据现场试验确定。In the karst pretreatment reinforcement, the periphery of the grouting reinforcement area can be closed with double-liquid slurry to prevent the leakage of the grout, and the interior is filled with pure cement slurry; the material of the double-liquid slurry is cement slurry and water glass solution, and the cement slurry components include cement and Water, the water-cement ratio is 0.5:1~1:1, the water glass solution includes water glass and water, the concentration of the water glass solution is 30~40°Be', and the ratio of cement slurry and water glass solution is 4:1~6:1 ; The components of pure cement slurry include cement and water, and the water-cement ratio is 0.5:1 to 1:1. The specific mixing ratio should be determined according to field tests.
岩溶预处理加固中,对于加固区外围,为使浆液快速凝固并有效阻止浆液漏失,注浆应以相对小压力、多次数、较大量控制,注浆压力0.4~0.7MPa,注浆次数3~4次;对于加固区中部,注浆压力为0~0.7MPa,注浆压力由0逐步提高,达到注浆终压并继续注浆10min以上,压浆3次,注浆速度30~50L/min;每次注浆间歇时间对于加固区外围取30min,对于加固区中部取6~10h,采用间歇注浆旨在多次填充挤压土体,使土体强度得到最大限度提高并有效降低土体渗透系数。In the karst pretreatment reinforcement, for the periphery of the reinforcement area, in order to make the grout solidify quickly and effectively prevent the grout from leaking, the grouting should be controlled with a relatively small pressure, multiple times, and relatively large quantities. The grouting pressure is 0.4-0.7 MPa, and the grouting frequency is 3-3 4 times; for the middle part of the reinforcement area, the grouting pressure is 0-0.7MPa, and the grouting pressure is gradually increased from 0 to the final grouting pressure, and the grouting is continued for more than 10 minutes, the grouting is 3 times, and the grouting speed is 30-50L/min ; The intermittent time of each grouting is 30 minutes for the periphery of the reinforcement area, and 6-10 hours for the middle of the reinforcement area. Intermittent grouting is used to fill the extruded soil multiple times, so that the strength of the soil can be maximized and the soil can be effectively reduced. permeability coefficient.
上述施工步骤中,岩溶预处理完后,须对注浆效果进行检验,检验方法为钻孔抽芯法结合随机原位标贯试验,检测数量为注浆孔数量的1%,且每个溶洞检测数量不少于1个检测钻孔。注浆加固区土体应满足钻孔芯样28d无侧限抗压强度值≥0.5MPa;加固体渗透系数不大于1×10-5cm/s;对于随机原位标贯试验,标准贯入度不小于10击。In the above construction steps, after the karst pretreatment, the grouting effect must be inspected. The inspection method is the drilling core-pulling method combined with the random in-situ standard penetration test. The number of inspections is 1% of the number of grouting holes, and each The number of inspections shall not be less than one inspection drill hole. The soil in the grouting reinforcement area should meet the 28d unconfined compressive strength value of the borehole core sample ≥ 0.5MPa; the permeability coefficient of the reinforcement body should not be greater than 1×10 -5 cm/s; The speed is not less than 10 hits.
在岩溶区盾构正式掘进前应根据试掘进确定施工参数,所述施工参数包括总推力、推进速度、刀盘扭矩、土仓压力和同步注浆参数。其中:总推力为1300~1600t,推进速度为5~10mm/min,刀盘扭矩为3.0~3.5MN·m,土仓压力为1.2~1.4Bar,同步注浆率为300%,同步注浆压力为2.0~4.0Bar间。在盾构正式掘进过程中应根据建筑物实时沉降、变形监测数据及盾构机前方土体性质而调整施工参数。Before the formal excavation of the shield tunneling in the karst area, the construction parameters should be determined according to the trial excavation. The construction parameters include total thrust, advancing speed, cutter head torque, soil chamber pressure and synchronous grouting parameters. Among them: the total thrust is 1300-1600t, the propulsion speed is 5-10mm/min, the cutterhead torque is 3.0-3.5MN·m, the soil bin pressure is 1.2-1.4Bar, the synchronous grouting rate is 300%, the synchronous grouting pressure Between 2.0 and 4.0 Bar. During the formal tunneling process of the shield machine, the construction parameters should be adjusted according to the real-time settlement and deformation monitoring data of the building and the properties of the soil in front of the shield machine.
为防止刀盘渣土改良喷口阻塞,同时对刀盘刀具进行润滑及降温,应使用泡沫剂进行渣土改良,其中,泡沫原液浓度为3~5%,发泡率为10~20倍,注入率为5~10%。该渣土改良工艺参数须根据实时工况予以调整。In order to prevent clogging of the cutterhead dregs improvement nozzle, and at the same time lubricate and cool down the cutterhead cutter, a foam agent should be used for dregs improvement. The concentration of the foam stock solution is 3-5%, and the foaming rate is 10-20 times. The rate is 5-10%. The parameters of the muck improvement process must be adjusted according to the real-time working conditions.
上述施工步骤中,同步注浆浆液选用双液浆,所述双液浆浆材为水泥浆和水玻璃溶液,其中,水泥浆水灰比为1:1;所述水玻璃溶液成分为水玻璃和水,水玻璃浓度为30~40°Be',其体积配合比为水玻璃:水=1:1~1:2;所述水泥浆和水玻璃溶液体积配合比为4:1~6:1;浆液配比应在现用配比基础上进行现场试配确定,并根据现场掘进条件予以调整和优化。In the above-mentioned construction steps, the synchronous grouting slurry is selected from double-liquid slurry, and the material of the double-liquid slurry is cement slurry and water glass solution, wherein the water-cement ratio of the cement slurry is 1:1; the composition of the water glass solution is water glass And water, water glass concentration is 30~40 ° Be ', and its volume mixing ratio is water glass: water=1:1~1:2; Described cement slurry and water glass solution volume mixing ratio are 4:1~6: 1. The grout ratio should be determined on the basis of the current ratio, and be adjusted and optimized according to the on-site excavation conditions.
上述施工步骤中,盾构机通过后,应在成型隧道纵向布置测线,采用地质雷达扫描管片壁后空洞情况,并对存在松散、空洞、松散异常的位置立即组织二次双液浆补强注浆,达到加固土体和加固充填空洞的目的。In the above construction steps, after the shield machine passes through, the survey line should be arranged longitudinally in the forming tunnel, the cavity behind the segment wall should be scanned by geological radar, and the second double-fluid slurry repair should be organized immediately for the loose, cavity and loose abnormal positions. Strong grouting to achieve the purpose of reinforcing the soil and filling the void.
二次补强注浆浆液为双液浆,所述双液浆浆材为水泥浆和水玻璃溶液,其中,水泥浆成分为水泥和水,水灰比为1:1;所述水玻璃溶液成分为水玻璃和水,水玻璃浓度为30~40°Be',其体积配合比为水玻璃:水=1:1~1:2;所述水泥浆和水玻璃溶液体积配合比为4:1~6:1。The secondary reinforcing grouting grout is double-fluid grout, and the material of the double-fluid grout is cement slurry and water glass solution, wherein, the cement slurry components are cement and water, and the water-cement ratio is 1:1; the water glass solution The composition is water glass and water, the concentration of water glass is 30~40°Be', its volume mixing ratio is water glass: water=1:1~1:2; the volume mixing ratio of described cement slurry and water glass solution is 4: 1~6:1.
如图3、图4所示,下穿建筑物段岩溶探明即在无法实施地面钻孔探测地段运用超前钻、已成型隧道洞内地质雷达扫描辅以隧道内钻孔的方式探明隧道前方及周边岩溶发育状况。所述超前钻即在盾构停机安装管片间隙使用布置于盾构机前方的超前钻器具探明隧道前方岩溶发育状况,其中,超前钻钻机可打设与隧道轴线平行钻孔及与隧道轴线具有一定夹角钻孔;所述地质雷达扫描辅以隧道呢钻孔即在已成型隧道洞内通过发射并接收电磁波探明管片壁后岩溶发育状况并通过隧道内钻孔进一步确认隧道周边岩溶发育状况。As shown in Figure 3 and Figure 4, the karst detection of the section under the building is to use advanced drilling in the area where ground drilling cannot be implemented, and the geological radar scanning in the formed tunnel hole is supplemented by drilling in the tunnel to prove the front of the tunnel. and surrounding karst development. The advanced drilling is to use the advanced drilling equipment arranged in front of the shield machine to find out the karst development situation in front of the tunnel when the shield machine is shut down to install the segments. Drilling with a certain included angle; the geological radar scanning is supplemented by tunnel drilling, that is, the karst development status behind the wall of the segment is detected by transmitting and receiving electromagnetic waves in the formed tunnel hole, and the karst around the tunnel is further confirmed by drilling in the tunnel developmental status.
上述施工步骤中,下穿建筑物段岩溶处理即运用超前钻器具与隧道内钻孔对隧道掘进方向及已成型隧道周边已探明岩溶予以注浆加固处理。其中,超前钻器具可用于隧道前方岩溶处理,隧道内钻孔可对管片壁后岩溶予以处理。注浆加固方法可归纳如下:In the above-mentioned construction steps, the karst treatment of the underpassing building section is to use the advanced drilling equipment and the boreholes in the tunnel to perform grouting reinforcement treatment on the tunneling direction and the proven karst around the formed tunnel. Among them, the advanced drilling equipment can be used for karst treatment in front of the tunnel, and the drilling in the tunnel can be used for karst treatment behind the segment wall. The grouting reinforcement methods can be summarized as follows:
(1)为保证建筑物安全,无论溶洞大小与充填情况均采用双液浆予以加固;(1) In order to ensure the safety of the building, regardless of the size of the cave and the filling condition, it is reinforced with double liquid slurry;
(2)注浆顺序:由外向内进行,先对溶洞边界予以双液浆充填,阻断浆液漏失通道后,再逐步向内对溶洞区中部灌浆压密;(2) Grouting sequence: from outside to inside, first fill the boundary of the cave with double-liquid grout, block the leakage channel of the grout, and then gradually grout and compact the middle of the cave area inward;
(3)为防止邻孔串浆影响注浆效果,注浆须跳孔进行。(3) In order to prevent grouting in adjacent holes from affecting the grouting effect, grouting must be carried out by skipping holes.
下穿建筑物段岩溶注浆加固浆液为双液浆,双液浆浆材为水泥浆与水玻璃溶液,其中水泥浆成分包括水泥和水,水灰比为0.5:1~1:1,水玻璃溶液成分包括水玻璃和水,水玻璃溶液浓度为30~40°Be',水泥浆和水玻璃溶液配合为4:1~6:1;纯水泥浆成分包括水泥和水,水灰比为0.5:1~1:1。The karst grouting reinforcement in the building section below is a double-liquid slurry, and the double-liquid slurry material is cement slurry and water glass solution. The cement slurry includes cement and water. The composition of glass solution includes water glass and water, the concentration of water glass solution is 30-40°Be', the ratio of cement slurry and water glass solution is 4:1-6:1; the composition of pure cement slurry includes cement and water, and the water-cement ratio is 0.5:1~1:1.
下穿建筑物段,对于岩溶加固区外围注浆,以相对小压力、多次数、较大量控制,注浆压力0.4~0.7MPa,注浆3~4次,每次注浆间歇时间可取30min;对于加固区中部,注浆压力可取0~0.4MPa,达到注浆终压并继续注浆10min以上,压浆4~5次,注浆速度20~30L/min,,每次注浆间歇时间取30min。Under the building section, grouting around the karst reinforcement area should be controlled with relatively small pressure, multiple times, and relatively large quantities. The grouting pressure is 0.4-0.7MPa, and the grouting is 3-4 times. The interval between each grouting is preferably 30 minutes; For the middle part of the reinforcement area, the grouting pressure can be 0-0.4MPa, reach the final grouting pressure and continue grouting for more than 10 minutes, grouting 4-5 times, the grouting speed is 20-30L/min, and the interval time of each grouting is taken as 30min.
如图5所示,在无法实施地面钻孔探测的下穿建筑物段,通过在先行洞隧道相应范围增加地质雷达测线,扫描另一条隧道未施工段地质情况并予以处理。若探明另一条隧道下穿区域有溶洞,则可从已施工一侧隧道加密钻孔对溶洞进行注浆处理,其中,隧道内钻孔通过管片预留注浆孔实现,并可任意角度打设。As shown in Figure 5, in the underpass building section where the ground drilling detection cannot be implemented, the geological radar survey line is added in the corresponding range of the leading tunnel tunnel, and the geological conditions of the unconstructed section of the other tunnel are scanned and processed. If it is found that there is a karst cave in the underpass area of another tunnel, the karst cave can be grouted from the intensified drilling of the tunnel on the side that has already been constructed. set up.
上述施工步骤中,对另一侧隧道下穿建筑物区域内岩溶进行注浆加固处理时,浆液采用双液浆,双液浆浆材为水泥浆与水玻璃溶液,其中,水泥浆成分为水泥和水,水灰比为1:1;水玻璃溶液成分为水玻璃和水,水玻璃浓度为30~40°Be',其体积配合比为水玻璃:水=1:1~1:2;所述水泥浆和水玻璃溶液体积配合比为4:1~6:1。In the above construction steps, when performing grouting reinforcement treatment on the karst in the area where the tunnel passes under the building on the other side, the grout adopts double-fluid grout, and the double-fluid grout material is cement slurry and water glass solution, wherein the cement grout is composed of cement and water, the water-cement ratio is 1:1; the composition of water glass solution is water glass and water, the concentration of water glass is 30-40°Be', and its volume mixing ratio is water glass: water = 1:1-1:2; The volume ratio of the cement slurry to the water glass solution is 4:1-6:1.
对另一侧隧道下穿建筑物区域内岩溶进行注浆加固处理时,对于岩溶加固区外围注浆,以相对小压力、多次数、较大量控制,注浆压力0.4~0.7MPa,注浆3~4次,每次注浆间歇时间可取30min;对于加固区中部,注浆压力可取0~0.4MPa,达到注浆终压并继续注浆10min以上,压浆4~5次,注浆速度20~30L/min,,每次注浆间歇时间取30min。When performing grouting reinforcement treatment on the karst in the area where the tunnel passes under the building on the other side, for the peripheral grouting of the karst reinforcement area, the grouting pressure should be controlled at a relatively small pressure, multiple times, and a relatively large amount. ~ 4 times, the intermittent time of each grouting can be 30min; for the middle part of the reinforcement area, the grouting pressure can be 0-0.4MPa, reach the final grouting pressure and continue grouting for more than 10min, grouting 4-5 times, the grouting speed is 20 ~30L/min, the interval time between each grouting is 30min.
本实施例通过调查评估岩溶区建筑物安全现状及预设沉降、相对倾斜与裂缝监测系统,判明施工对建筑物影响规律,并通过反馈监测信息指导施工;同时在盾构掘进施工前,对岩溶区予以预探测,对已探明溶洞按不同方式进行注浆加固处理,并在无地面钻孔条件下运用超前钻、地质雷达扫描与已成型隧道内钻孔技术探测建筑物下方岩溶发育状况,从而对隧道周边溶洞打加密钻孔进行注浆加固,并从先行洞打设钻孔探明并处理后行洞隧道周边溶洞;对已探明溶洞予以注浆加固可提高土体强度,降低土体渗透系数,确保盾构掘进施工顺利下穿岩溶区建筑群。In this embodiment, through the investigation and evaluation of the safety status of buildings in karst areas and the preset settlement, relative inclination and crack monitoring system, the law of the impact of construction on buildings is identified, and the construction is guided by feedback monitoring information; The pre-detection of the area is carried out, and the proven karst caves are treated with grouting reinforcement in different ways, and the advanced drilling, geological radar scanning and borehole technology in the formed tunnel are used to detect the development of karst under the building without ground drilling. In this way, the karst caves around the tunnel are densely drilled for grouting reinforcement, and the karst caves around the tunnel are drilled from the first hole to prove and deal with the karst caves around the tunnel; the grouting reinforcement of the proven karst caves can increase the strength of the soil and reduce the soil strength. The body permeability coefficient ensures that the shield excavation construction smoothly passes through the building complex in the karst area.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710464609.8A CN107060786A (en) | 2017-06-19 | 2017-06-19 | A kind of Shield Construction Method Used method that groups of building are worn under karst region |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710464609.8A CN107060786A (en) | 2017-06-19 | 2017-06-19 | A kind of Shield Construction Method Used method that groups of building are worn under karst region |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107060786A true CN107060786A (en) | 2017-08-18 |
Family
ID=59594954
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710464609.8A Pending CN107060786A (en) | 2017-06-19 | 2017-06-19 | A kind of Shield Construction Method Used method that groups of building are worn under karst region |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107060786A (en) |
Cited By (25)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108222954A (en) * | 2017-12-14 | 2018-06-29 | 上海隧道工程有限公司 | The construction method of shield crossing sand material back filled region |
CN108303729A (en) * | 2018-02-27 | 2018-07-20 | 中南大学 | Shield tunnel influence area Karst method under building |
CN108397201A (en) * | 2018-01-31 | 2018-08-14 | 中铁二十二局集团第工程有限公司 | The safe construction method of rock tunnel(ling) machine |
CN108564268A (en) * | 2018-04-09 | 2018-09-21 | 中铁十二局集团第二工程有限公司 | Building risk management method is worn under water conservancy tunnel |
CN108643937A (en) * | 2018-04-27 | 2018-10-12 | 中铁十二局集团有限公司 | The prevention restoration methods of residential area are worn under hydraulic tunnel |
CN108868789A (en) * | 2018-07-05 | 2018-11-23 | 成都天佑智隧科技有限公司 | A kind of stratum active support and change method suitable for shield construction tunnel |
CN108999181A (en) * | 2018-08-15 | 2018-12-14 | 广州地铁设计研究院有限公司 | Molten, soil cave injecting treatment construction method and its application |
CN109736830A (en) * | 2019-01-10 | 2019-05-10 | 中铁建南方建设投资有限公司 | The implementation method of lateral sealing in a kind of TBM tunnel construction |
CN110130936A (en) * | 2019-06-06 | 2019-08-16 | 中铁十一局集团城市轨道工程有限公司 | It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack |
CN110359921A (en) * | 2019-08-13 | 2019-10-22 | 中铁十一局集团城市轨道工程有限公司 | Wear the construction method of building in a kind of shield short distance side |
CN111075460A (en) * | 2019-12-30 | 2020-04-28 | 中铁二十二局集团轨道工程有限公司 | Shield construction and monitoring method for urban dense building |
CN111502750A (en) * | 2020-06-09 | 2020-08-07 | 中铁四局集团有限公司 | Method for processing karst tunnel bottom large-scale karst cave |
CN111608688A (en) * | 2020-05-27 | 2020-09-01 | 中铁建大桥工程局集团第二工程有限公司 | A kind of reinforcement method of shield tunnel passing through building ground |
CN111852485A (en) * | 2020-07-27 | 2020-10-30 | 中交第二公路工程局有限公司 | Construction method for shield tunnel downward-penetrating sensitive building group in shallow-buried weak stratum |
CN111878084A (en) * | 2020-07-15 | 2020-11-03 | 中铁十八局集团有限公司 | Rapid treatment method for controlling surface subsidence by using large-diameter shield construction in case of meeting stratum funnel |
CN112922607A (en) * | 2021-02-25 | 2021-06-08 | 中铁九局集团第四工程有限公司 | Advance grouting reinforcement construction method in foundation tunnel of underground building penetrated by earth pressure balance shield |
CN113075744A (en) * | 2021-03-15 | 2021-07-06 | 华南理工大学 | Karst detection system for shield tunnel affected area under building |
CN113417644A (en) * | 2021-05-31 | 2021-09-21 | 中铁十六局集团北京轨道交通工程建设有限公司 | A method for detecting karst caves during shield construction |
CN113609714A (en) * | 2021-10-08 | 2021-11-05 | 湖南大学 | Method for determining radial displacement of wall surrounding rock in construction process of vertical shaft heading machine |
CN113981938A (en) * | 2021-11-15 | 2022-01-28 | 贵州省交通规划勘察设计研究院股份有限公司 | Method for preventing road surface from sinking in construction of karst mountain urban underground engineering |
CN114183170A (en) * | 2021-11-01 | 2022-03-15 | 中铁二十局集团有限公司 | Karst grouting construction method |
CN114737979A (en) * | 2022-03-14 | 2022-07-12 | 中铁十一局集团有限公司 | Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region |
CN115075827A (en) * | 2022-07-06 | 2022-09-20 | 中铁工程装备集团有限公司 | Method and structure for advanced processing of main line tunnel influence area based on small-section tunnel |
CN115163080A (en) * | 2022-05-24 | 2022-10-11 | 广州地铁设计研究院股份有限公司 | A non-stop construction survey method for tunnels under the airport flight area |
CN117107745A (en) * | 2023-10-24 | 2023-11-24 | 中铁三局集团广东建设工程有限公司 | Ground grouting construction process |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000147137A (en) * | 1998-11-05 | 2000-05-26 | Kyushu Electric Power Co Inc | Underground radar apparatus of underground excavator |
CN105840235A (en) * | 2016-05-09 | 2016-08-10 | 湖南大学 | Exploration and draining method for pressure-bearing karstic water in tunneling process |
CN106372297A (en) * | 2016-08-29 | 2017-02-01 | 上海交通大学 | Method for determining safe vertical distance between shield and karst cave in sand karst stratum |
-
2017
- 2017-06-19 CN CN201710464609.8A patent/CN107060786A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000147137A (en) * | 1998-11-05 | 2000-05-26 | Kyushu Electric Power Co Inc | Underground radar apparatus of underground excavator |
CN105840235A (en) * | 2016-05-09 | 2016-08-10 | 湖南大学 | Exploration and draining method for pressure-bearing karstic water in tunneling process |
CN106372297A (en) * | 2016-08-29 | 2017-02-01 | 上海交通大学 | Method for determining safe vertical distance between shield and karst cave in sand karst stratum |
Non-Patent Citations (3)
Title |
---|
ZHANGXUE9899: "溶洞处理技术交底1", 《豆丁网》 * |
毛贤等: "盾构机超前钻探与溶洞处理", 《铁道建筑技术》 * |
王余良: "岩溶区双模式盾构下穿建筑群的施工风险控制", 《建筑机械化》 * |
Cited By (33)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108222954B (en) * | 2017-12-14 | 2020-05-05 | 上海隧道工程有限公司 | Construction method for shield to penetrate through sandstone material backfill area |
CN108222954A (en) * | 2017-12-14 | 2018-06-29 | 上海隧道工程有限公司 | The construction method of shield crossing sand material back filled region |
CN108397201A (en) * | 2018-01-31 | 2018-08-14 | 中铁二十二局集团第工程有限公司 | The safe construction method of rock tunnel(ling) machine |
CN108303729A (en) * | 2018-02-27 | 2018-07-20 | 中南大学 | Shield tunnel influence area Karst method under building |
CN108564268A (en) * | 2018-04-09 | 2018-09-21 | 中铁十二局集团第二工程有限公司 | Building risk management method is worn under water conservancy tunnel |
CN108643937A (en) * | 2018-04-27 | 2018-10-12 | 中铁十二局集团有限公司 | The prevention restoration methods of residential area are worn under hydraulic tunnel |
CN108643937B (en) * | 2018-04-27 | 2020-01-31 | 中铁十二局集团有限公司 | Prevention and recovery method of hydraulic tunnel passing through residential area |
CN108868789A (en) * | 2018-07-05 | 2018-11-23 | 成都天佑智隧科技有限公司 | A kind of stratum active support and change method suitable for shield construction tunnel |
CN108999181A (en) * | 2018-08-15 | 2018-12-14 | 广州地铁设计研究院有限公司 | Molten, soil cave injecting treatment construction method and its application |
CN109736830A (en) * | 2019-01-10 | 2019-05-10 | 中铁建南方建设投资有限公司 | The implementation method of lateral sealing in a kind of TBM tunnel construction |
CN110130936A (en) * | 2019-06-06 | 2019-08-16 | 中铁十一局集团城市轨道工程有限公司 | It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack |
CN110359921A (en) * | 2019-08-13 | 2019-10-22 | 中铁十一局集团城市轨道工程有限公司 | Wear the construction method of building in a kind of shield short distance side |
CN110359921B (en) * | 2019-08-13 | 2024-05-07 | 中铁十一局集团城市轨道工程有限公司 | Construction method for shield close-range side-penetrating building |
CN111075460A (en) * | 2019-12-30 | 2020-04-28 | 中铁二十二局集团轨道工程有限公司 | Shield construction and monitoring method for urban dense building |
CN111608688A (en) * | 2020-05-27 | 2020-09-01 | 中铁建大桥工程局集团第二工程有限公司 | A kind of reinforcement method of shield tunnel passing through building ground |
CN111608688B (en) * | 2020-05-27 | 2022-05-17 | 中铁建大桥工程局集团第二工程有限公司 | Method for reinforcing ground of shield underpass building |
CN111502750A (en) * | 2020-06-09 | 2020-08-07 | 中铁四局集团有限公司 | Method for processing karst tunnel bottom large-scale karst cave |
CN111878084A (en) * | 2020-07-15 | 2020-11-03 | 中铁十八局集团有限公司 | Rapid treatment method for controlling surface subsidence by using large-diameter shield construction in case of meeting stratum funnel |
CN111878084B (en) * | 2020-07-15 | 2022-09-13 | 中铁十八局集团有限公司 | Rapid treatment method for controlling surface subsidence by using large-diameter shield construction in case of meeting stratum funnel |
CN111852485A (en) * | 2020-07-27 | 2020-10-30 | 中交第二公路工程局有限公司 | Construction method for shield tunnel downward-penetrating sensitive building group in shallow-buried weak stratum |
CN111852485B (en) * | 2020-07-27 | 2022-03-11 | 中交第二公路工程局有限公司 | Construction method for shield tunnel downward-penetrating sensitive building group in shallow-buried weak stratum |
CN112922607A (en) * | 2021-02-25 | 2021-06-08 | 中铁九局集团第四工程有限公司 | Advance grouting reinforcement construction method in foundation tunnel of underground building penetrated by earth pressure balance shield |
CN113075744A (en) * | 2021-03-15 | 2021-07-06 | 华南理工大学 | Karst detection system for shield tunnel affected area under building |
CN113417644A (en) * | 2021-05-31 | 2021-09-21 | 中铁十六局集团北京轨道交通工程建设有限公司 | A method for detecting karst caves during shield construction |
CN113417644B (en) * | 2021-05-31 | 2024-04-30 | 中铁十六局集团北京轨道交通工程建设有限公司 | Karst cave detection method in shield construction process |
CN113609714B (en) * | 2021-10-08 | 2021-12-21 | 湖南大学 | A method for determining the radial displacement of the surrounding rock of the shaft wall during the construction of the shaft boring machine |
CN113609714A (en) * | 2021-10-08 | 2021-11-05 | 湖南大学 | Method for determining radial displacement of wall surrounding rock in construction process of vertical shaft heading machine |
CN114183170A (en) * | 2021-11-01 | 2022-03-15 | 中铁二十局集团有限公司 | Karst grouting construction method |
CN113981938A (en) * | 2021-11-15 | 2022-01-28 | 贵州省交通规划勘察设计研究院股份有限公司 | Method for preventing road surface from sinking in construction of karst mountain urban underground engineering |
CN114737979A (en) * | 2022-03-14 | 2022-07-12 | 中铁十一局集团有限公司 | Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region |
CN115163080A (en) * | 2022-05-24 | 2022-10-11 | 广州地铁设计研究院股份有限公司 | A non-stop construction survey method for tunnels under the airport flight area |
CN115075827A (en) * | 2022-07-06 | 2022-09-20 | 中铁工程装备集团有限公司 | Method and structure for advanced processing of main line tunnel influence area based on small-section tunnel |
CN117107745A (en) * | 2023-10-24 | 2023-11-24 | 中铁三局集团广东建设工程有限公司 | Ground grouting construction process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107060786A (en) | A kind of Shield Construction Method Used method that groups of building are worn under karst region | |
Kang et al. | Improved compound support system for coal mine tunnels in densely faulted zones: a case study of China's Huainan coal field | |
CN104265307B (en) | Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method | |
CN101761346B (en) | Method for constructing metamorphic rock confined water tunnel | |
CN101994513B (en) | Method for constructing tunnel by finishing full section curtain grouting from upper-half section | |
Li et al. | Using grouting of shield tunneling to reduce settlements of overlying tunnels: case study in Shenzhen metro construction | |
CN106837351A (en) | Tunnel karst water detection and treatment method | |
Zhang et al. | An incident of water and soil gushing in a metro tunnel due to high water pressure in sandy silt | |
CN106089217B (en) | Major long tunnel rapid constructing method under complex geological condition | |
CN106837353A (en) | Filling karst tunnel construction treatment method | |
CN104408277B (en) | Method for predicting, preventing and controlling earth surface residual movement and deformation caused by newly-built building in mine lot | |
CN104196537A (en) | Construction method of three parallel metro tunnels with ultra-small clear distance | |
CN101566063A (en) | Method of reinforcing soil body for inlet and outlet cave mouths of tunnel shield | |
CN113186924A (en) | Subway foundation pit deep-buried karst cave treatment method | |
Arroyo et al. | Design of jet-grouting for tunnel waterproofing | |
CN103711492A (en) | Pipe-jacking type cable sleeve passage construction method | |
CN112983456A (en) | Water-rich sand layer multi-row pipe jacking surface deformation control method | |
CN110130936A (en) | It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack | |
CN104452793A (en) | Construction technology for foam concrete treatment of abandoned sewage pipeline at urban overpass foundation | |
CN111075460A (en) | Shield construction and monitoring method for urban dense building | |
CN112576265A (en) | Sedimentation control method for old villages penetrated by shield | |
CN107587512A (en) | The construction method of foundation pit enclosure structure under a kind of karst and/or cranny development stratum | |
CN113818889A (en) | Construction method for subway shield tunnel to cross and penetrate civil air defense tunnel | |
CN116104502B (en) | Method for reinforcing mountain tunnel crossing coal mine goaf | |
CN110067561A (en) | Under wear both wired Urban Underground mining sectbn construction methods |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170818 |