[go: up one dir, main page]

CN101761346B - Method for constructing metamorphic rock confined water tunnel - Google Patents

Method for constructing metamorphic rock confined water tunnel Download PDF

Info

Publication number
CN101761346B
CN101761346B CN200910261828A CN200910261828A CN101761346B CN 101761346 B CN101761346 B CN 101761346B CN 200910261828 A CN200910261828 A CN 200910261828A CN 200910261828 A CN200910261828 A CN 200910261828A CN 101761346 B CN101761346 B CN 101761346B
Authority
CN
China
Prior art keywords
water
construction
excavation
tunnel
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910261828A
Other languages
Chinese (zh)
Other versions
CN101761346A (en
Inventor
王利民
赵香萍
谷孝军
张朝亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority to CN200910261828A priority Critical patent/CN101761346B/en
Publication of CN101761346A publication Critical patent/CN101761346A/en
Application granted granted Critical
Publication of CN101761346B publication Critical patent/CN101761346B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及隧道工程施工领域,具体为一种变质岩承压水隧道的施工方法,解决现有方法易引发地质灾害、开挖轮廓难以控制、初期支护变形开裂以及易塌方等问题,包括初步预测围岩级别和地下水发育情况、超前探孔准确预报地质情况和地下水发育情况、超前钻孔泄水降压、超前小导管注浆固结围岩并堵水、选择洞身开挖方式并确定初期支护形式、施做径向小导管、开挖仰拱并浇筑仰拱混凝土、施做二次衬砌等步骤。采取本工法施工后,开挖轮廓得到了有效控制,掉块坍塌降低了发生频率缩小了规模,初期支护变形开裂得到了有效控制,再未进行过二次换拱,基本避免了隧道塌方;降低了费用,而且有效地提高了施工质量和施工安全,从而也创造了良好的社会效益。

Figure 200910261828

The invention relates to the field of tunnel engineering construction, in particular to a construction method of a metamorphic rock pressurized water tunnel, which solves problems such as geological disasters easily caused by existing methods, difficulty in controlling excavation contours, initial support deformation and cracking, and easy landslides, etc., including preliminary Predict the level of surrounding rock and the development of groundwater, accurately predict the geological situation and groundwater development in advance, drill in advance to release water and reduce pressure, advance small conduit grouting to consolidate surrounding rock and block water, select the excavation method of the cave body and determine Initial support form, construction of small radial conduits, excavation of inverted arches and pouring of inverted arch concrete, and application of secondary linings. After adopting this construction method, the excavation profile has been effectively controlled, the frequency of block collapse has been reduced and the scale has been reduced, the deformation and cracking of the initial support have been effectively controlled, and no secondary arch replacement has been performed, basically avoiding tunnel collapse; The cost is reduced, and the construction quality and construction safety are effectively improved, thereby creating good social benefits.

Figure 200910261828

Description

一种变质岩承压水隧道的施工方法Construction method of a metamorphic rock confined water tunnel

技术领域 technical field

本发明涉及隧道工程施工领域,具体为一种变质岩承压水隧道的施工方法。The invention relates to the field of tunnel engineering construction, in particular to a construction method for a metamorphic rock pressurized water tunnel.

背景技术 Background technique

变质岩承压水隧道围岩特点是节理裂隙发育,节理面密集、光滑,岩石呈块状或碎块状压碎结构,岩石单体强度高,且夹杂薄层软弱充填物,围岩整体性差,自稳能力弱,多层承压水造成洞身开挖后就出水并逐渐变大或开挖后当时没水过几天出水并逐渐变大。不出水,支护结构稳定安全,一旦出水,裂隙中的填充物就会软化随水流失,使围岩的整体性和稳定性变差,对支护体系压力增大,导致出水部位及其附近支护开裂、钢架变形、折断。The surrounding rocks of metamorphic rock confined water tunnels are characterized by the development of joints and fissures, the joint surfaces are dense and smooth, and the rocks are in the form of massive or fragmented crushed structures. , Weak self-stabilization ability, multi-layer pressurized water causes water to flow out of the cave body after excavation and gradually become larger, or water will flow out and gradually become larger after a few days of no water after excavation. The support structure is stable and safe when no water comes out. Once the water comes out, the filling in the crack will soften and be lost with the water, which will deteriorate the integrity and stability of the surrounding rock, increase the pressure on the support system, and cause the water outlet part and its vicinity to be damaged. The support is cracked, the steel frame is deformed and broken.

目前,在变质岩承压水地段进行隧道施工,由于对变质岩岩体特征认识不深,对承压水的危害作用估计不足,在施工时没有合理的针对性施工方案,仍按传统施工方案进行施工,容易引发突水、突泥、塌方等地质灾害,开挖轮廓难以控制,超挖严重,掉块坍塌时有发生,易发生初期支护变形开裂,钢架扭曲、折断,初期支护侵入限界,甚至出现塌方。此外在承压水条件下作业难度大,喷射混凝土来不及凝固就被冲散,焊接作业时焊液来不及焊粘就被冷凝,钻爆作业时炮孔来不及堵塞药卷就被冲出,注浆时浆液来不及凝固就被冲走,施工质量难以保证,支护体系受力复杂极易发生变形开裂。防水层不仅铺设焊接难度大,而且极易遭到承压水破坏造成二次衬砌渗漏水。At present, tunnel construction is carried out in the metamorphic rock confined water section. Due to the lack of deep understanding of the characteristics of the metamorphic rock mass and the underestimation of the harmful effects of the confined water, there is no reasonable and targeted construction plan during construction, and the traditional construction plan is still used. During construction, it is easy to cause geological disasters such as water inrush, mud inrush, and landslides. The excavation contour is difficult to control, over-excavation is serious, and block collapse occurs from time to time. It is easy to cause deformation and cracking of the primary support. The steel frame is twisted and broken. Invasion of the boundary, and even landslides. In addition, it is very difficult to work under the condition of pressurized water. The shotcrete will be washed away before it solidifies. During the welding operation, the welding fluid will be condensed before it can be welded. The grout is washed away before it solidifies, making it difficult to guarantee the construction quality, and the support system is easily deformed and cracked due to complex forces. The waterproof layer is not only difficult to lay and weld, but also easily damaged by pressurized water, resulting in water leakage from the secondary lining.

发明内容Contents of the invention

本发明为了解决现有变质岩承压水隧道采用传统隧道施工方法,存在易引发地质灾害、开挖轮廓难以控制、初期支护变形开裂以及易塌方、施工作业难度大等问题,提供一种变质岩承压水隧道的施工方法。In order to solve the problems of existing metamorphic rock confined water tunnels using traditional tunnel construction methods, such problems as geological disasters are easily caused, excavation contours are difficult to control, initial support deformation and cracking are easy to collapse, and construction operations are difficult, etc., the present invention provides a metamorphic tunnel. Construction method of rock-confined water tunnel.

本发明是采用如下技术方案实现的:一种变质岩承压水隧道的施工方法,包括以下步骤:A初步预测围岩级别和地下水发育情况;B超前探孔准确预报地质情况和地下水发育情况:依据初步预测结论,针对有承压水或富水地段以及地质复杂地段采取水平钻机进行超前钻孔探测,通过岩芯取样准确判定围岩岩性、结构特征,通过探孔出水量准确判定地下水发育情况及其压力状况,超前探孔采用RPD-150C钻探机Φ110mm钻头进行钻探,每50m钻探一次,每次钻探60m;C超前钻孔泄水降压:依据超前钻孔探测结果对富水及承压水地段采取超前钻孔泄水降压,超前泄水孔采用XY-2PC钻探机Φ91mm钻头进行钻孔,每25m钻孔一次,钻孔深度30m,每次钻孔3~7个;D超前小导管注浆固结围岩并堵水:在洞身拱部120°~180°范围内沿隧道开挖轮廓线施做超前小导管,注水泥-水玻璃双液浆,水泥-水玻璃双液浆参数∶水泥浆液水灰重量比为1∶1,灰浆水玻璃体积比为1∶0.8,水玻璃模数m=2.4~3.4,浓度Be=30~40,注浆压力控制在0.5~1.0MPa,浆液扩散半径不小于30cm;E选择洞身开挖方式并确定初期支护形式:经过超前钻孔泄水和小导管超前注浆,变质岩承压水隧道按三台阶法或上弧导预留核心土三台阶法进行施工,同时施作相应形式的初期支护;E施做径向小导管:在初期支护施做完毕后施做径向小导管;G开挖仰拱并浇筑仰拱混凝土:洞身开挖支护完成后,即时进行仰拱E施工,仰拱施工一次开挖和浇筑混凝土长度不得超过6m;H施做二次衬砌:仰拱施工完毕衬砌前,通过小导管灌注步骤D中所述的水泥-水玻璃双液浆。所述洞身开挖时所采用的三台阶法或上弧导预留核心土三台阶法均为本领域普通技术人员所熟知的,在隧道施工领域均有成熟的施工规范,初期支护应严格按设计或规范要求施作。The present invention is realized by adopting the following technical scheme: a construction method of a metamorphic rock confined water tunnel, comprising the following steps: A. Preliminary prediction of surrounding rock level and groundwater development; According to the preliminary prediction conclusion, horizontal drilling rigs are used for advanced drilling detection in areas with confined water or water-rich areas and areas with complex geology. The lithology and structural characteristics of surrounding rocks can be accurately determined through core sampling, and the development of groundwater can be accurately determined through the water output of exploration holes. conditions and pressure conditions, the advanced exploration hole is drilled with the RPD-150C drilling machine Φ110mm drill bit, drilling once every 50m, and each drilling is 60m; The pressurized water section adopts advanced drilling to relieve water and reduce pressure, and the advanced drainage hole is drilled with a Φ91mm drill bit of the XY-2PC drilling machine, drilling once every 25m, the drilling depth is 30m, and 3 to 7 holes are drilled each time; Small conduit grouting to consolidate the surrounding rock and block water: within the range of 120°-180° of the arch of the tunnel body, a small conduit is constructed along the contour line of the tunnel excavation, and the cement-sodium silicate double slurry is injected, and the cement-sodium silicate double slurry is injected. Slurry parameters: cement slurry water-cement weight ratio is 1:1, mortar water glass volume ratio is 1:0.8, water glass modulus m=2.4~3.4, concentration Be=30~40, grouting pressure is controlled at 0.5~1.0 MPa, the grout diffusion radius is not less than 30cm; E selects the excavation method of the cave body and determines the initial support form: through advanced drilling and small conduits for advanced grouting, the metamorphic rock confined water tunnel is guided by the three-step method or the upper arc guide Reserve the core soil for construction with the three-step method, and at the same time apply the corresponding form of initial support; E is to make a small radial conduit: after the initial support is completed, a radial small conduit is used; G excavates the inverted arch and pours it Inverted arch concrete: After the excavation and support of the cave body is completed, the inverted arch E construction shall be carried out immediately. The length of excavation and concrete pouring for the inverted arch construction shall not exceed 6m at one time; the secondary lining for H: before the construction of the inverted arch is completed, the construction of the inverted arch shall be carried out through small The cement-water glass double slurry described in step D is poured into the conduit. The three-step method used in the excavation of the tunnel body or the three-step method of the upper arc guide to reserve the core soil are well known to those skilled in the art, and there are mature construction specifications in the field of tunnel construction. The initial support should be Strictly follow the design or specification requirements.

在施工中,变质岩承压水隧道很难控制开挖轮廓,极易发生掉块、坍塌,本发明所述的变质岩承压水隧道采用三台阶微震动控制爆破法开挖,钻爆设计时,沿开挖轮廓线布置的所有周边眼采用导爆索串联,周边眼采用间隔装药形式(即一个炮眼装药,与其相邻的两个炮眼只放导爆索);上弧导爆破时,根据上弧导断面轮廓形式布置掏槽眼。采用本发明的钻爆设计,与传统的钻爆设计(所有周边眼均装药,上弧导掏槽眼采用长方形布置,而未按上弧导断面轮廓形式布置)相比,传统爆破一立方米断面,需要1.2-2.4Kg炸药,而本发明仅需要0.6Kg,大大减少了炸药的用量,而且可以有效降低爆破波对围岩的扰动,有效控制超欠挖,减少掉块、坍塌。本发明采用短进尺、多钻眼、少装药的微震动控制爆破开挖,在实际施工中依据围岩节理产状,软弱程度及时调整隧道爆破参数,取得了最佳爆破效果。During construction, it is difficult to control the excavation profile of the metamorphic rock confined water tunnel, and it is very easy to lose blocks and collapse. The metamorphic rock confined water tunnel described in the present invention is excavated by the three-step micro-vibration controlled blasting method, and the drill and blast design , all peripheral holes arranged along the excavation contour line shall be connected in series with detonating cords, and the peripheral holes shall be in the form of interval charge (i.e., one blasthole is charged, and the two adjacent blastholes are only equipped with detonating cords); , the cutting holes are arranged according to the profile of the upper arc guide section. Adopting the drill-and-blast design of the present invention, compared with the traditional drill-and-blast design (all peripheral holes are filled with explosives, and the upper arc-guided cutting holes are arranged in a rectangle instead of being arranged according to the profile of the upper-arc-guided cross-section), the traditional blasting of one cubic meter 1.2-2.4Kg of explosives is needed for a section of 1.5 meters, but the present invention only needs 0.6Kg, which greatly reduces the amount of explosives, and can effectively reduce the disturbance of blasting waves to surrounding rocks, effectively control over-under-excavation, and reduce block loss and collapse. The present invention adopts micro-vibration controlled blasting excavation with short footage, multiple drill holes, and less powder charge. In actual construction, the tunnel blasting parameters are adjusted in time according to the occurrence and weakness of surrounding rock joints, and the best blasting effect is achieved.

本发明在变质岩承压水隧道施工时,仔细分析设计提供的地质资料,结合超前地质预报资料,初步判定掌子面前方围岩级别和地下水发育情况,为超前钻孔探测提供指导意见;依据初步判定结果,有针对性采用超前钻孔,进行准确预报;超前钻孔探测后,依据水量大小,超前钻进泄水孔,使前方承压水提前得到释放,降低水压,为后面施工降低难度;洞身开挖前使用小导管超前注浆加固围岩,形成注浆固结圈,提高围岩自稳能力,将拱顶大部分地下水堵到开挖轮廓线以外,为施工作业提供便利条件;采取短进尺、多钻眼、少装药的微震动控制爆破开挖,降低爆破冲击波对围岩的扰动,改善开挖效果,减少掉块、坍塌;初期支护施做完毕后,施做径向小导管,前期用做泄水孔泄水,减缓承压水对初期支护的破坏作用,一旦初期支护变形开裂或即将衬砌前,则通过径向小导管进行径向注浆加固围岩并再次堵水。During the construction of the metamorphic rock confined water tunnel, the present invention carefully analyzes the geological data provided by the design, and combines the advanced geological forecast data to preliminarily determine the level of surrounding rock and the development of groundwater in front of the tunnel face, and provide guidance for advanced drilling detection; Preliminary judgment results, targeted use of advanced drilling for accurate forecasting; after advanced drilling detection, according to the amount of water, advanced drilling into the drain hole, so that the front of the pressurized water can be released in advance, reduce the water pressure, and reduce the pressure for subsequent construction. Difficulty; before the excavation of the cave body, small conduits are used to reinforce the surrounding rock with advanced grouting, forming a grouting consolidation ring, improving the self-stability of the surrounding rock, blocking most of the groundwater in the vault beyond the excavation contour line, and providing convenience for construction operations Conditions: adopt short footage, more drilling holes, and less explosives to control the blasting excavation by micro-vibration, reduce the disturbance of the blasting shock wave to the surrounding rock, improve the excavation effect, and reduce the loss of blocks and collapse; after the initial support is completed, the construction Make radial small conduits and use them as weep holes to drain water in the early stage to slow down the destructive effect of confined water on the initial support. Once the initial support deforms and cracks or is about to be lined, radial grouting reinforcement will be carried out through radial small conduits Surrounding rock and blocked water again.

总之,本发明针对承压水的特点采取“探—泄—堵—排—堵”系列措施,有效控制了承压水的危害及破坏作用,改善了施工条件,确保了施工质量和施工安全,提高了施工进度;同时本方法针对变质岩的岩性特点采取小导管超前注浆和小导管径向注浆加固围岩,有效地改善了岩体结构,提高了围岩自稳能力;采取短进尺、多钻眼、少装药的微震动控制爆破,有效地降低了爆破冲击波对围岩的扰动,改善了开挖效果,减少了掉块、坍塌。采取本工法施工后,开挖轮廓得到了有效控制,掉块坍塌降低了发生频率缩小了规模,初期支护变形开裂得到了有效控制,再未进行过二次换拱,基本避免了隧道塌方。采取本工法后平均每延米减少超挖4m3,减少超挖喷射混凝土4m3,减少费用约3500元;每延米平均减少处理掉块坍塌和初期支护变形开裂及塌方费用约3000元;每延米平均增加费用约5000;合计每延米平均减少费用约1500元,采取本工法不仅降低了费用,而且有效地提高了施工质量和施工安全,从而也创造了良好的社会效益,适用于所有变质岩承压水隧道施工。In a word, the present invention adopts a series of measures of "exploring-releasing-blocking-draining-blocking" for the characteristics of confined water, effectively controlling the hazards and destructive effects of confined water, improving construction conditions, ensuring construction quality and construction safety, and improving At the same time, according to the lithological characteristics of metamorphic rock, this method adopts small conduit advance grouting and small conduit radial grouting to strengthen the surrounding rock, which effectively improves the rock mass structure and improves the self-stabilization ability of the surrounding rock; Micro-vibration controlled blasting with footage, more drilling, and less charge can effectively reduce the disturbance of the blasting shock wave to the surrounding rock, improve the excavation effect, and reduce the loss of blocks and collapse. After adopting this construction method, the excavation profile has been effectively controlled, the frequency of block collapse has been reduced and the scale has been reduced, the deformation and cracking of the primary support have been effectively controlled, and there has been no secondary arch replacement, basically avoiding tunnel collapse. After adopting this construction method, an average of 4m 3 of over-excavation and 4m 3 of over-excavation shotcrete are reduced per linear meter, and the cost is reduced by about 3,500 yuan; the average cost of dealing with block collapse, primary support deformation, cracking and landslide is reduced by about 3,000 yuan per linear meter; The average cost increase per linear meter is about 5,000; the total average cost reduction per linear meter is about 1,500 yuan. The adoption of this construction method not only reduces the cost, but also effectively improves the construction quality and construction safety, thereby creating good social benefits. It is suitable for All metamorphic rock confined water tunnel construction.

附图说明 Description of drawings

图1为本发明的施工工艺流程方框图;Fig. 1 is a block diagram of construction technological process of the present invention;

图2为本发明所述的变质岩承压水隧道三台阶法施工工序图;Fig. 2 is the three-step construction process diagram of the metamorphic rock confined water tunnel of the present invention;

图3为本发明超前探孔及超前泄水孔布置示意图;Fig. 3 is a schematic diagram of the layout of the advanced detection hole and the advanced drainage hole of the present invention;

图4为本发明监控量测测点布置图;Fig. 4 is a layout diagram of the monitoring measurement points of the present invention;

图5为本发明变质岩承压水隧道开挖面的钻爆设计图Fig. 5 is the drilling and blasting design drawing of the excavation face of the metamorphic rock confined water tunnel of the present invention

图6为图5中的周边眼装药结构示意图;Fig. 6 is a schematic diagram of the structure of the peripheral eye charge in Fig. 5;

图中:1-超前探孔;2-超前泄水孔;3-隧道开挖轮廓线;4-超前小导管;5-径向小导管;6-周边眼;7-导爆索;8-上弧导;9-掏槽眼;10-中导A;11-中导B;12-下导C;13-下导D;14-仰拱E;15-半卷乳化炸药;16-炮泥;17-非电毫秒雷管。In the figure: 1-advance probe hole; 2-advance drain hole; 3-tunnel excavation contour line; 4-advance small duct; 5-radial small duct; 6-peripheral eye; 7-detonating cord; 8- Upper arc guide; 9-cut hole; 10-middle guide A; 11-middle guide B; 12-down guide C; 13-down guide D; 14-inverted arch E; mud; 17 - non-electric millisecond detonator.

具体实施方式 Detailed ways

一种变质岩承压水隧道的施工方法,如图1所示,包括以下步骤:A construction method of a metamorphic rock confined water tunnel, as shown in Figure 1, comprises the following steps:

A初步预测围岩级别和地下水发育情况:大的或特殊地质构造以及基本地质情况一般都会在设计提供的地质资料上标明,通过TSP203地质预报系统对隧道地质分段及时预测,可以相对准确地预测到即将施工段落地质结构及地下水发育情况。通过仔细分析设计地质资料和TSP系统预报资料得出初步结论,并为下一步是否实施或在哪一段采取超前探孔预测提供指导意见。由于变质岩承压水隧道节理密集、围岩破碎富含裂隙水,TSP系统预测范围有限,为了提高预报准确性,要求每80m预测一次;A Preliminary prediction of surrounding rock level and groundwater development: large or special geological structures and basic geological conditions are generally marked on the geological data provided by the design, and the tunnel geological segment can be predicted in time through the TSP203 geological prediction system, which can be predicted relatively accurately The geological structure and groundwater development of the upcoming construction section. Preliminary conclusions can be drawn through careful analysis of design geological data and TSP system forecast data, and guidance will be provided for whether to implement or in which section to adopt advanced sounding prediction in the next step. Due to the dense joints of the metamorphic rock confined water tunnel and the broken surrounding rock rich in fissure water, the prediction range of the TSP system is limited. In order to improve the accuracy of the prediction, it is required to make a prediction every 80m;

B超前探孔准确预报地质情况和地下水发育情况:依据初步预测结论,针对有承压水或富水地段以及地质复杂地段采取水平钻机进行超前钻孔探测,通过岩芯取样准确判定围岩岩性、结构特征,通过探孔出水量准确判定地下水发育情况及其压力状况,从而为隧道采取何种施工方法、何种支护形式和支护参数以及是否采取超前钻孔泄水作出准确判定,超前探孔1采用RPD-150C钻探机Φ110mm钻头进行钻探,每50m钻探一次,每次钻探60m,所述RPD-150C钻探机为现有公知设备;B. Preliminary exploration to accurately predict geological conditions and groundwater development: According to preliminary prediction conclusions, horizontal drilling rigs are used for advanced drilling detection in areas with confined water or water-rich areas and areas with complex geology, and the lithology of surrounding rocks can be accurately determined through core sampling , structural characteristics, accurately determine the development of groundwater and its pressure status through the water output of the probe hole, so as to make an accurate judgment for the construction method, support form and support parameters of the tunnel, and whether to adopt advanced drilling to discharge water. Exploration hole 1 is drilled with the RPD-150C drilling machine Φ110mm drill bit, drilling once every 50m, and drilling 60m each time. The RPD-150C drilling machine is an existing known equipment;

C超前钻孔泄水降压:依据超前钻孔探测结果对富水及承压水地段采取超前钻孔泄水降压,也可进一步探明地质情况为施工提供指导依据,超前泄水孔2采用XY-2PC钻探机Φ91mm钻头进行钻孔,每25m钻孔一次,钻孔深度30m,每次钻孔3~7个,超前探孔及超前泄水孔布置位置布置见图3,依据泄水孔出水量和水压决定泄水孔个数,起初可先钻3个孔,如果出水量大的话,再接着钻4个孔,所述XY-2PC钻探机为现有公知设备;C. Advanced drilling for drainage and depressurization: According to the results of advanced drilling detection, advanced drilling for drainage and depressurization of water-rich and confined water areas can also be used to further ascertain the geological conditions to provide guidance for construction. Advanced drainage hole 2 XY-2PC drilling machine Φ91mm drill bit is used for drilling, drilling once every 25m, the drilling depth is 30m, and 3 to 7 holes each time. The water output and water pressure of the holes determine the number of drain holes. At first, 3 holes can be drilled, and if the water output is large, then 4 holes can be drilled. The XY-2PC drilling machine is an existing known equipment;

D超前小导管注浆固结围岩并堵水:在洞身拱部120~180范围内沿隧道开挖轮廓线3施做超前小导管4,注水泥-水玻璃双液浆,一方面固结围岩提高围岩自稳能力,另为形成注浆固结圈可将拱部大部分地下水堵到开挖轮廓线以外,为下步施工作业提供便利条件。超前注浆小导管采用Φ42*4无缝钢管加工成锥形花管,长度不小于250cm,环向间距30cm,环与环水平搭接不小于100cm。水泥-水玻璃双液浆参数∶水泥浆液水灰重量比为1∶1,灰浆水玻璃体积比为1∶0.8,水玻璃模数m=2.4~3.4,浓度Be=30~40,注浆压力控制在0.5~1.0MPa,浆液扩散半径不小于30cm;上述浆液配比及注浆参数是申请人经过长期工程实践及经验总结所得来的,保证了注浆效果,围岩固结及堵水效果很好;D. Advance small conduit grouting to consolidate the surrounding rock and block water: within the range of 120-180° of the tunnel body arch, along the tunnel excavation contour line 3, advance small conduit 4, inject cement-water glass double slurry, on the one hand, solidify Consolidating the surrounding rock improves the self-stabilizing ability of the surrounding rock. In addition, to form a grouting consolidation circle, most of the groundwater in the arch can be blocked beyond the excavation contour line, providing convenient conditions for the next construction operation. The small duct for advance grouting is processed into a tapered flower tube with Φ42*4 seamless steel pipe, the length is not less than 250cm, the circumferential distance is 30cm, and the horizontal overlap between rings is not less than 100cm. Cement-water glass double slurry parameters: cement slurry water-cement weight ratio is 1:1, mortar water glass volume ratio is 1:0.8, water glass modulus m=2.4~3.4, concentration Be=30~40, grouting pressure It is controlled at 0.5-1.0MPa, and the grout diffusion radius is not less than 30cm; the above-mentioned grout ratio and grouting parameters are obtained by the applicant through long-term engineering practice and experience summary, which ensures the effect of grouting, surrounding rock consolidation and water blocking effect very good;

E选择洞身开挖方式并确定初期支护形式:经过超前钻孔泄水和小导管超前注浆,变质岩承压水隧道按三台阶法或上弧导预留核心土三台阶法进行施工,同时进行相应形式的初期支护;初期支护采用I18以上型钢钢架,间距80~100cm;系统锚杆采用长度不小于

Figure G2009102618281D00061
中空注浆锚杆,80×80cm梅花形布置;
Figure G2009102618281D00062
连接筋环向间距100cm,沿钢架内外两侧交错布置;钢筋网采用
Figure G2009102618281D00063
钢筋加工,网格15×15cm;采用C25喷射混凝土,厚度不小于20cm。初期支护参数也可按设计标准施做,但不得低于上述指标。开挖和支护要严格按照规范要求进行施做,确保施工质量。E Select the excavation method of the tunnel body and determine the initial support form: after the advance drilling and drainage and the small conduit advance grouting, the construction of the metamorphic rock confined water tunnel is carried out according to the three-step method or the three-step method with the core soil reserved on the upper arc guide At the same time, the corresponding form of initial support is carried out; the initial support adopts I18 steel frame with a distance of 80-100cm; the length of the anchor rod of the system is not less than
Figure G2009102618281D00061
Hollow grouting anchor rod, 80×80cm plum blossom arrangement;
Figure G2009102618281D00062
The circumferential spacing of the connecting bars is 100cm, and they are arranged staggered along the inner and outer sides of the steel frame; the steel mesh adopts
Figure G2009102618281D00063
Reinforcement processing, grid 15×15cm; C25 sprayed concrete, thickness not less than 20cm. Initial support parameters can also be implemented according to design standards, but not lower than the above indicators. Excavation and support shall be carried out in strict accordance with the specification requirements to ensure the construction quality.

上述三台阶法施工工序如下,如图2所示:The construction process of the above-mentioned three-step method is as follows, as shown in Figure 2:

a、当小导管超前预注浆强度达到后,按“短进尺、强支护”的施工原则,开挖上弧导8,并施做初期支护I部,循环进尺80~100cm;a. When the pre-grouting strength of the small conduit is reached, according to the construction principle of "short footage, strong support", the upper arc guide 8 is excavated, and the initial support I is applied, and the circular footage is 80-100cm;

b、上弧导超前3~5m开始中导施工,交错开挖中导A和中导B,并施做中导初期支护II部和III部,左右两部先后交错不得小于2m,每次施工长度不得超过两榀拱架(160~200cm);b. Start the construction of the intermediate guide 3~5m ahead of the upper arc guide, excavate the intermediate guide A and the intermediate guide B alternately, and implement the initial support of the intermediate guide Part II and Part III. The construction length shall not exceed two arches (160-200cm);

c、中导超前3~5m开始下导施工,交错开挖下导C和下导D,并施做中导初期支护IV部和V部,左右两部先后交错不得小于2m,每次施工长度不得超过两榀拱架(160~200cm);c. Start the down-guiding construction 3-5m ahead of the medium guide, excavate the down-guiding C and down-guiding D alternately, and implement the initial support of the medium-guiding part IV and V, and the left and right parts should not be less than 2m apart. The length shall not exceed two arches (160-200cm);

F施做径向小导管:为了防止初期支护将出水通道封住,使水压增大,造成初期支护变形开裂,在初期支护施做完毕后施做径向小导管5;径向小导管采用Φ42*4无缝钢管加工成锥形花管,长度不小于250cm,2.5×2.5m梅花形布置。径向小导管前期作为泄水孔泄水,初期支护一旦开裂或即将衬砌,则通过小导管注水泥-水玻璃双液浆,进一步加固围岩并堵水,浆液配合比及注浆压力按超前小导管预注浆执行;F: Make small radial conduits: in order to prevent the initial support from sealing the water outlet channel, increase the water pressure, and cause deformation and cracking of the initial support, make radial small conduits 5 after the initial support is completed; The small conduit is processed into a tapered flower tube with Φ42*4 seamless steel pipe, the length is not less than 250cm, and it is arranged in a quincunx shape of 2.5×2.5m. The radial small conduit is used as a weep hole in the early stage to discharge water. Once the initial support cracks or is about to be lined, the cement-sodium silicate double slurry is injected through the small conduit to further strengthen the surrounding rock and block water. Advance small catheter pre-grouting execution;

G开挖仰拱并浇筑仰拱混凝土:洞身开挖支护完成后,即时进行仰拱E(14)施工,仰拱施工一次开挖和浇筑混凝土VI长度不得超过6m,仰拱初期支护、仰拱和仰拱填充混凝土要分层整幅浇筑,仰拱各项施工工艺和技术指标必须满足设计或规范要求;G Excavate the inverted arch and pour the inverted arch concrete: After the excavation and support of the cave body is completed, the inverted arch E (14) construction will be carried out immediately. 1. Inverted arches and inverted arches shall be filled with concrete layered and poured in layers, and the construction techniques and technical indicators of inverted arches must meet the design or specification requirements;

H施做二次衬砌VII:仰拱施工完毕衬砌前,通过小导管灌注步骤D中所述的水泥-水玻璃双液浆,进一步加固围岩并堵水。铺防水板前对渗水量大的部位采取铺挂PE排水板和排水盲管进行集中引排。防水板采用厚度不小于1.5mm的PVC复合防水板,严格控制防水板施工工艺,严防钢筋等尖锐物件刺破防水板,确保防水板施工质量,严防二次衬砌渗漏水。二次衬砌混凝土采用全断面液压衬砌台车整体浇筑。衬砌各项施工工艺和技术指标必须满足设计或规范要求;H to do the secondary lining VII: before the construction of the inverted arch is completed and the lining is completed, the cement-sodium silicate double slurry described in step D is poured through the small conduit to further strengthen the surrounding rock and block the water. Before laying the waterproof board, the parts with large water seepage shall be paved and hung with PE drainage board and blind drainage pipe for centralized drainage. The waterproof board adopts a PVC composite waterproof board with a thickness of not less than 1.5mm. The construction process of the waterproof board is strictly controlled to prevent sharp objects such as steel bars from piercing the waterproof board, so as to ensure the construction quality of the waterproof board and prevent water leakage from the secondary lining. The secondary lining concrete is integrally poured with a full-section hydraulic lining trolley. The construction techniques and technical indicators of the lining must meet the design or specification requirements;

I爆破开挖:变质岩承压水隧道开挖面采用三台阶微震动控制爆破法(即按照上弧导、中导、下导三个台阶)开挖,钻爆设计时,沿开挖轮廓线布置的所有周边眼6采用导爆索7串联,周边眼采用间隔装药形式,如图5所示,标有13的周边眼装药,不标数字的周边眼只放导爆索,周边眼按照图6所示进行装药,按照上述钻爆设计图的装药表如下表1所示;上弧导8爆破时,根据上弧导断面轮廓形式布置掏槽眼9,如图5所示,标有数字3、5、7的炮眼为掏槽眼,由图可知,其布置形式以上弧导中心的空眼为中心、向其两侧分散对称布置,并且由内向外以3个掏槽眼、2两个掏槽眼和1个掏槽眼的排列形式布置,形成与上弧导断面轮廓相吻合的形状,采用此种钻爆设计,既可降低用药量,降低爆破波对围岩的扰动,又能取得最佳爆破效果。I blasting excavation: The excavation surface of the metamorphic rock confined water tunnel is excavated by the three-step micro-vibration control blasting method (that is, according to the three steps of upper arc guide, middle guide and lower guide). All the peripheral eyes 6 arranged in the line are connected in series with detonating cord 7, and the peripheral eyes adopt the form of interval charging, as shown in Figure 5, the peripheral eyes marked with 13 are charged, and the peripheral eyes without numbers are only equipped with detonating cords. The hole is charged as shown in Figure 6, and the charge table according to the above-mentioned drilling and blasting design drawing is shown in Table 1 below; when the upper arc guide 8 is blasted, the cutting hole 9 is arranged according to the outline of the upper arc guide section, as shown in Figure 5 It shows that the blast holes marked with numbers 3, 5, and 7 are cut holes. It can be seen from the figure that the arrangement form is centered on the hollow hole in the center of the arc guide, distributed symmetrically to both sides, and three cut holes are formed from the inside to the outside. The slot hole, two cut holes and one cut hole are arranged in an arrangement form to form a shape that matches the profile of the upper arc guide section. Adopting this drilling and blasting design can not only reduce the dosage of chemicals, but also reduce the impact of blasting waves on the surrounding area. Rock disturbance, and can achieve the best blasting effect.

表1Table 1

Figure G2009102618281D00081
Figure G2009102618281D00081

Figure G2009102618281D00091
Figure G2009102618281D00091

在上述工艺过程中,监控测量工作必须紧跟开挖、支护作业进行布点和监测,量测数据运用工程类比法及时分析、反馈,调整支护参数,以保证施工和结构安全,具体做法如下:In the above-mentioned process, the monitoring and measurement work must follow the excavation and support operations for point layout and monitoring. The measurement data shall be analyzed and fed back in time using the engineering analogy method, and the support parameters shall be adjusted to ensure the safety of construction and structure. The specific methods are as follows :

在变质岩承压水隧道施工时每隔10m布一组量测断面,每个断面布置一个拱顶下沉量测点和两条水平净空收敛量测基线。测点布置如图4所示,其中a为拱顶下沉量测点,b、c分别为两条水平净空收敛量测基线。During the construction of the metamorphic rock confined water tunnel, a group of measurement sections is arranged every 10m, and each section is arranged with a vault sinking measurement point and two horizontal clearance convergence measurement baselines. The layout of the measuring points is shown in Figure 4, where a is the measuring point for the vault sinking, and b and c are the two baselines for measuring the convergence of the horizontal clearance.

净空水平收敛量测和拱顶下沉量测采用相同的量测频率,量测频率见表2,实际量测频率从表中根据变形速度和距开挖工作面距离选择较高的一个量测频率。水平收敛量测采用激光断面仪进行量测,开挖后按要求迅速安装测点并编号,在开挖后12h内读取初读数。拱顶下沉量测采用激光断面仪和精密水准仪、收敛计、铟瓦尺进行量测,喷射混凝土后迅速在拱顶设点。The same measurement frequency is used for the headroom level convergence measurement and the vault sinking measurement. The measurement frequency is shown in Table 2. The actual measurement frequency is selected from the table according to the deformation speed and the distance from the excavation face. frequency. The horizontal convergence measurement is carried out with a laser profiler. After the excavation, the measuring points are quickly installed and numbered as required, and the initial reading is taken within 12 hours after the excavation. The sinking of the vault is measured with a laser profiler, a precision level, an extensometer, and an indium tile ruler, and points are quickly set on the vault after spraying the concrete.

表2Table 2

Figure G2009102618281D00092
Figure G2009102618281D00092

为了进一步证明该施工方法的有益效果,申请人列举以下工程实例加以证明:In order to further prove the beneficial effect of this construction method, the applicant cites the following engineering examples to prove it:

张集铁路旧堡隧道位于阴山东西复杂构造带南部,中朝准地台燕山沉降带与内蒙古地轴分界处。在地质历史上经历了前震旦纪、中生代及新生代三期较明显的构造运动,多期构造运动的叠加造成地质构造极其复杂。洞身范围均为太古界变质岩,以麻粒岩和浅粒岩为主,局部侵入花岗伟晶岩及辉绿岩岩脉。因原岩成分的差异及遭受多期构造运动的影响,致使构造节理裂隙发育程度不同,加之多期岩脉的侵入和断裂的切割阻隔作用,形成了部分地段和层位含水及隔水构造,从而形成了承压含水层。隧道围岩特点是节理裂隙发育,节理面密集、光滑,岩石呈块状或碎块状压碎结构,岩石单体强度高,且夹杂薄层软弱充填物,围岩整体性差,自稳能力弱,多层承压水造成洞身开挖后就出水并逐渐变大或开挖后当时没水过几天出水并逐渐变大。The Jiubao Tunnel of the Zhangji Railway is located in the south of the complex east-west structural belt of the Yinshan Mountains, at the boundary between the Yanshan subsidence zone of the Sino-Korean quasi-platform and the Inner Mongolia axis. In the geological history, it has experienced three periods of obvious tectonic movements: Pre-Sinian, Mesozoic and Cenozoic. The superposition of multi-stage tectonic movements has made the geological structure extremely complex. The scope of the cave body is all Archean metamorphic rocks, mainly granulite and shallow grainstone, and partially intruded into granitic pegmatite and diabase dikes. Due to the difference in the composition of the original rock and the influence of multi-stage tectonic movements, the development of structural joints and fissures is different. In addition, the intrusion of multi-stage dikes and the cutting and blocking of faults have formed water-bearing and water-resistant structures in some sections and layers. Confined aquifers are formed. The surrounding rock of the tunnel is characterized by the development of joints and fissures, the joint surface is dense and smooth, the rock is in the form of massive or fragmented crushed structures, the strength of the rock itself is high, and it is mixed with thin layers of weak fillings, the integrity of the surrounding rock is poor, and the self-stabilization ability is weak , multi-layer pressurized water causes water to flow out of the cave body after excavation and gradually become larger, or there is no water at that time after excavation, and water will flow out and gradually become larger after a few days.

上述张集铁路旧堡隧道为变质岩承压水隧道,在施工过程中采用传统施工方法,存在本发明背景技术中所记载的问题。而采用本发明所述的方法后,开挖轮廓得到了有效控制,掉块坍塌降低了发生频率缩小了规模,初期支护变形开裂得到了有效控制,再未进行过二次换拱,基本避免了隧道塌方。张集铁路旧堡隧道按本工法组织施工的变质岩承压水隧道累计长度为5385m,累计减少费用约807万元。The above-mentioned Jiubao Tunnel of Zhangji Railway is a metamorphic rock-bearing water tunnel, and traditional construction methods are used in the construction process, which has the problems recorded in the background technology of the present invention. However, after adopting the method described in the present invention, the excavation profile is effectively controlled, the occurrence frequency of falling block collapse is reduced and the scale is reduced, the deformation and cracking of the initial support are effectively controlled, and no secondary arch change is performed, basically avoiding The tunnel collapsed. The accumulative length of the metamorphic rock confined water tunnel constructed according to this construction method in the Jiubao Tunnel of Zhangji Railway is 5385m, and the accumulative cost reduction is about 8.07 million yuan.

Claims (2)

1.一种变质岩承压水隧道的施工方法,其特征是包括以下步骤: 1. A construction method of a metamorphic rock confined water tunnel is characterized in that it comprises the following steps: A 初步预测围岩级别和地下水发育情况; A Preliminary prediction of surrounding rock grade and groundwater development; B 超前探孔准确预报地质情况和地下水发育情况:依据初步预测结论,针对有承压水或富水地段以及地质复杂地段采取水平钻机进行超前钻孔探测,通过岩芯取样准确判定围岩岩性、结构特征,通过探孔出水量准确判定地下水发育情况及其压力状况,超前探孔(1)采用RPD-150C钻探机Φ110mm钻头进行钻探,每50m钻探一次,每次钻探60m; B Accurately predict the geological conditions and groundwater development in advance: according to the preliminary prediction conclusion, use horizontal drilling rigs for advanced drilling detection in areas with confined water or water-rich areas and areas with complex geology, and accurately determine the lithology of surrounding rocks through core sampling , Structural characteristics, accurately determine the development of groundwater and its pressure status through the water output of the probe hole, the advanced probe hole (1) uses the RPD-150C drilling machine Φ110mm drill bit to drill, drill once every 50m, and drill 60m each time; C 超前钻孔泄水降压:依据超前钻孔探测结果对富水及承压水地段采取超前钻孔泄水降压,超前泄水孔(2)采用XY-2PC钻探机Φ91mm钻头进行钻孔,每25m钻孔一次,钻孔深度30m,每次钻孔3~7个; C Advanced drilling for drainage and pressure reduction: According to the detection results of advanced drilling, advanced drilling is used for drainage and pressure reduction in water-rich and confined water sections. The advanced drainage hole (2) is drilled with XY-2PC drilling machine Φ91mm drill bit , drilling once every 25m, drilling depth 30m, 3 to 7 holes each time; D 超前小导管注浆固结围岩并堵水:在洞身拱部顶端两侧各60°范围内沿隧道开挖轮廓线(3)施做超前小导管(4),注水泥-水玻璃双液浆,水泥-水玻璃双液浆参数:水泥浆液水灰重量比为1∶1,灰浆水玻璃体积比为1∶0.8,水玻璃模数m=2.4~3.4,浓度Be=30~40,注浆压力控制在0.5~1.0MPa,浆液扩散半径不小于30cm; D Consolidate the surrounding rock by grouting and block water in small conduits in advance: within the range of 60° on both sides of the top of the arch of the tunnel body, construct small conduits in advance (4) along the tunnel excavation contour line (3), and inject cement-sodium silicate Double slurry, cement-water glass double slurry parameters: cement slurry water-cement weight ratio is 1:1, mortar water glass volume ratio is 1:0.8, water glass modulus m=2.4~3.4, concentration Be=30~40 , the grouting pressure is controlled at 0.5-1.0MPa, and the grout diffusion radius is not less than 30cm; E 选择洞身开挖方式并确定初期支护形式:经过超前钻孔泄水和小导管超前注浆,变质岩承压水隧道按三台阶法或上弧导预留核心土三台阶法进行施工,同时进行相应形式的初期支护; E Select the excavation method of the tunnel body and determine the initial support form: After the advance drilling and drainage and the small conduit advance grouting, the construction of the metamorphic rock confined water tunnel is carried out according to the three-step method or the three-step method of the upper arc guide with the core soil reserved , and at the same time carry out corresponding forms of primary support; F 施做径向小导管:在初期支护施做完毕后施做径向小导管(5); F Apply small radial catheters: after the initial support is completed, small radial catheters (5) are applied; G 开挖仰拱并浇筑仰拱混凝土:洞身开挖支护完成后,即时进行仰拱施工,仰拱施工一次开挖和浇筑混凝土长度不得超过6m; G Excavate the inverted arch and pour the inverted arch concrete: After the excavation and support of the cave body is completed, the inverted arch construction will be carried out immediately, and the length of excavation and pouring concrete for the inverted arch construction shall not exceed 6m; H 施做二次衬砌:仰拱施工完毕衬砌前,通过小导管灌注步骤D中所述的水泥-水玻璃双液浆。 H Apply the secondary lining: before the construction of the inverted arch is completed and the lining is completed, the cement-sodium silicate double slurry described in step D is poured through the small conduit. 2.根据权利要求1所述的一种变质岩承压水隧道的施工方法,其特征是变质岩承压水隧道开挖面采用三台阶微震动控制爆破法开挖,钻爆设计时,沿开挖轮廓线布置的所有周边眼(6)采用导爆索(7)串联,周边眼采用间隔装药形式;上弧导(8)爆破时,根据上弧导断面轮廓形式布置掏槽眼(9)。  2. The construction method of a metamorphic rock confined water tunnel according to claim 1, characterized in that the excavation surface of the metamorphic rock confined water tunnel adopts three-step micro-vibration control blasting method for excavation, and during drilling and blasting design, along the All the peripheral eyes (6) arranged in the excavation contour line are connected in series by detonating cord (7), and the peripheral eyes are in the form of interval charges; when the upper arc guide (8) is blasted, the cutting eyes are arranged according to the profile of the upper arc guide section ( 9). the
CN200910261828A 2009-12-30 2009-12-30 Method for constructing metamorphic rock confined water tunnel Expired - Fee Related CN101761346B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910261828A CN101761346B (en) 2009-12-30 2009-12-30 Method for constructing metamorphic rock confined water tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910261828A CN101761346B (en) 2009-12-30 2009-12-30 Method for constructing metamorphic rock confined water tunnel

Publications (2)

Publication Number Publication Date
CN101761346A CN101761346A (en) 2010-06-30
CN101761346B true CN101761346B (en) 2012-10-03

Family

ID=42492715

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910261828A Expired - Fee Related CN101761346B (en) 2009-12-30 2009-12-30 Method for constructing metamorphic rock confined water tunnel

Country Status (1)

Country Link
CN (1) CN101761346B (en)

Families Citing this family (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101922302A (en) * 2010-08-30 2010-12-22 中铁第四勘察设计院集团有限公司 Fault processing method of high pressure water enrichment area
CN102080568B (en) * 2010-11-19 2012-10-31 河北联合大学 Method for reducing water pressure of covering layer of mine transferred from opencast mine to underground mine
CN102128035B (en) * 2011-04-29 2012-12-26 重庆大学 Construction method of bilateral biased small-clear distance tunnel
CN102251783B (en) * 2011-05-10 2014-05-28 北京城建亚泰建设集团有限公司 Tunnel two-lining structure back grouting device, and grouting method thereof
CN103089280B (en) * 2011-11-01 2015-02-04 北京市政建设集团有限责任公司 Grouting water sealing and reinforcement construction process capable of realizing draining and plugging combined effect for underground water in tunnel
CN103089301B (en) * 2011-11-01 2015-02-04 北京市政建设集团有限责任公司 Grouting reinforcement construction process capable of realizing draining and plugging combined effect for underground water in vertical shaft
CN102493822B (en) * 2011-12-29 2014-04-02 中铁二十三局集团有限公司 Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN102606162B (en) * 2012-02-08 2014-09-17 中铁四局集团第二工程有限公司 Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN102606173B (en) * 2012-04-01 2014-12-10 中铁十二局集团有限公司 Construction method for treating tunnel deformation segment and accelerating tunneling
CN103089275B (en) * 2013-01-16 2013-12-04 山东大学 Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN103410516B (en) * 2013-05-08 2017-07-11 浙江广川工程咨询有限公司 Minor diameter tunnel full face tunneling surrouding rock deformation early warning engineering method
CN103233742A (en) * 2013-05-11 2013-08-07 中煤科工集团武汉设计研究院 Treatment measure of bad geological section for long distance pipeline coal conveying
CN103334770B (en) * 2013-06-09 2015-08-12 中铁隧道集团有限公司 One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN104453921B (en) * 2014-12-15 2016-06-08 中铁二十局集团有限公司 A kind of Soft Rock Tunnel Excavation construction technology
CN106193046B (en) * 2016-07-06 2018-08-07 中国电建集团华东勘测设计研究院有限公司 Weak counter-tilt slope discharges allowing for surrouding rock deformation and presses construction method in advance
CN106089217B (en) * 2016-07-22 2018-04-17 中铁建大桥工程局集团第五工程有限公司 Major long tunnel rapid constructing method under complex geological condition
CN106194195A (en) * 2016-07-22 2016-12-07 中铁建大桥工程局集团第五工程有限公司 Collapsible Loess District large cross-section tunnel three step is without remaining core soil in advance construction method
CN107288656B (en) * 2017-06-20 2019-12-13 清华大学 construction method of water seal cave depot surrounding rock active bearing system
CN108518229A (en) * 2018-04-24 2018-09-11 中铁五局集团第五工程有限责任公司 Large deformation weak broken wall rock outsized section tunnel excavation supporting structure and construction method
CN108590671A (en) * 2018-05-14 2018-09-28 姚晓宁 A kind of five steps, 14 excavation methods under advanced strong supporting system
CN108798718B (en) * 2018-07-09 2020-11-10 中铁十七局集团第四工程有限公司 Tunnel front-bearing subsequent grouting method
CN108915766B (en) * 2018-07-10 2020-09-29 河北煤炭科学研究院 Method for exploring deep hidden water guide channel of working surface
CN108959803B (en) * 2018-07-23 2020-06-05 北京交通大学 A collaborative design method and system for a tunnel support structure system
CN109736796B (en) * 2019-03-04 2022-09-13 中铁十六局集团有限公司 Advanced detection mechanism for deepening blast hole and prediction method thereof
CN110617067B (en) * 2019-09-02 2021-01-15 中铁十八局集团有限公司 Low-risk construction method for full-section boundary advanced pipe shed of extremely-soft surrounding rock tunnel
CN111023930B (en) * 2019-12-30 2022-12-27 中交路桥华南工程有限公司 Tunnel step excavation method
CN111219183B (en) * 2020-01-21 2023-07-04 中国铁建重工集团股份有限公司 Water volume and water pressure detection device
CN111350510B (en) * 2020-03-09 2021-06-04 中交第四公路工程局有限公司 Micro-step one-time blasting construction method for medium-section karst tunnel
CN111472815A (en) * 2020-05-29 2020-07-31 广西路桥工程集团有限公司 Rock mass tunnel pipe shed structure and construction method thereof
CN111810199A (en) * 2020-08-31 2020-10-23 中铁十六局集团有限公司 Tunnel water inrush disaster prevention treatment method
CN112796769B (en) * 2020-12-24 2023-05-05 中铁十八局集团第五工程有限公司 Construction method of water-rich weak surrounding rock stratum tunnel
CN113006825B (en) * 2021-04-09 2022-10-21 中铁六局集团太原铁路建设有限公司 Arch changing construction method for tunnel collapse position
CN113700490A (en) * 2021-09-17 2021-11-26 哈尔滨工业大学 Integrated freezing injury-water injury prevention and control method for tunnel construction and maintenance

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
丁常国.高压富水铁路隧道综合施工技术.《地下空间与工程学报》.2005,第1卷(第6期),435-448. *
史振宇.包家山特长隧道富水千枚岩地段快速施工技术.《隧道建设》.2009,第29卷(第1期),72-75. *
李雷.齐岳山隧道高压富水破碎带段施工技术.《建井技术》.2008,第29卷(第4期),36-39. *
陈丽萍.霞浦隧道穿过富水破碎F1断层的综合治理措施.《国防交通工程与技术》.2009,第7卷(第2期),38-41. *

Also Published As

Publication number Publication date
CN101761346A (en) 2010-06-30

Similar Documents

Publication Publication Date Title
CN101761346B (en) Method for constructing metamorphic rock confined water tunnel
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN104265307B (en) Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method
CN105422170B (en) Middle deep goaf grouting reinforcing and processing method under a kind of building foundation
CN102900441B (en) Based on country rock be badly deformed control China tunnel construction method
CN101994513B (en) Method for constructing tunnel by finishing full section curtain grouting from upper-half section
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN108678776B (en) Sandy clay geological tunnel roof collapse treatment method
CN110735653A (en) A deep hole retreat grouting water plugging construction method for igneous rock water-rich faults
CN104695963B (en) The construction method of subway tunnel crossing building in fragmentation rock stratum
CN203961994U (en) Under balancing earth-pressure shielding machine, wear the concealed tunneling structure of having runed shield tunnel
CN106089217A (en) Major long tunnel rapid constructing method under complex geological condition
CN105804761A (en) Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN113153307A (en) Tunnel construction method suitable for water-rich fractured rock mass
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN107339108A (en) The layer of sand location subway pipe shed construction method of underground water enrichment
CN102425155B (en) A superficial reinforcement method of overlying rock mass in goaf
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN108397199A (en) The method for tunnel construction in water hole is connected under a kind of short distance
CN114320360A (en) A construction method of TRD and surface deep hole half-section grouting combined with advanced water-stop curtain
CN114198124A (en) Construction method for grouting and water plugging of roof fall area of inclined shaft of coal mine
Liu et al. Characteristics analysis of roof overburden fracture in thick coal seam in deep mining and engineering application of super high water material in backfill mining
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121003

CF01 Termination of patent right due to non-payment of annual fee