CN106493144A - A kind of refuse disposal installation and installation method for gaolu wetland - Google Patents
A kind of refuse disposal installation and installation method for gaolu wetland Download PDFInfo
- Publication number
- CN106493144A CN106493144A CN201610846487.4A CN201610846487A CN106493144A CN 106493144 A CN106493144 A CN 106493144A CN 201610846487 A CN201610846487 A CN 201610846487A CN 106493144 A CN106493144 A CN 106493144A
- Authority
- CN
- China
- Prior art keywords
- plate
- rubbish
- collection box
- garbage collection
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B09—DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
- B09B—DISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
- B09B1/00—Dumping solid waste
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B09—DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
- B09B—DISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
- B09B5/00—Operations not covered by a single other subclass or by a single other group in this subclass
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B15/00—Cleaning or keeping clear the surface of open water; Apparatus therefor
- E02B15/04—Devices for cleaning or keeping clear the surface of open water from oil or like floating materials by separating or removing these materials
- E02B15/10—Devices for removing the material from the surface
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Processing Of Solid Wastes (AREA)
Abstract
The invention discloses a kind of refuse disposal installation and installation method for gaolu wetland, the refuse disposal installation includes rubbish bleeder, separator frame, the first garbage collection box, garbage separator, the second garbage collection box, body and water circle device.Installation method includes:A in () lake, rubbish bleeder is installed;The side concreting of (b) loke shore;C () body is installed;D () water circle device is installed;E () the first garbage collection box and separator frame are installed;F () location-plate and deflector are installed;G () the second garbage collection box and garbage separator are installed;H () outlet pipe is laid;I () soil is backfilled.Rubbish on lake surface can be collected by the present invention, play the effect of cleaning rubbish, the larger rubbish of volume is collected in the first garbage collection box simultaneously, the rubbish of small volume is collected in the second garbage collection box, accomplish to process refuse classification, and can carry out processing Posterior circle utilization, quality of increasing water quality by part lake water.
Description
Technical field
The invention belongs to gaolu wetland construction technique field, and in particular to a kind of refuse disposal installation for gaolu wetland
And installation method.
Background technology
At present, for the improvement of " black smelly " water body, a lot of gaolu wetland variation technology have been occurred in that, artificial gaolu is wet
Ground is the combination process that a kind of natural purification is combined with artificial-strengthening, can take suitable scale according to the size of sewage quantity
Adapt to therewith, the water quality for improving water body using the catharsis of gaolu wetland, and then eliminate black smelly.Artificial gaolu wetland and tradition
Secondary biochemical treatment compare, with building and operating cost is low, it is good to safeguard simple, effluent quality and to load variations adaptation energy
The advantages of power is strong, it is not the very less cities and towns of high, scale or rural sewage disposal to be relatively more suitable for technology management level.Promoting
On the premise of entering the benign cycle of Pollutants in Wastewater matter, the productive potentialities of resource can be given full play to, the recontamination of environment is prevented, from
And acquisition sewage disposal and the optimum efficiency of resource, obtain more and more extensive research and apply.
At present the rubbish at loke shore is cleared up, the effect of the water quality for improving water body is reached, main using artificial salvaging
To be purged to rubbish, although remove rubbish, but be the increase in labour cost, salvaging difficulty is there is also.
Content of the invention
Present invention aim at solve above-mentioned technical problem present in prior art, there is provided a kind of for gaolu wetland
Rubbish on lake surface can be collected by refuse disposal installation and installation method, the refuse disposal installation, play cleaning rubbish
Effect, while carrying out categorised collection to rubbish, the larger rubbish of volume is collected in the first garbage collection box, small volume
Rubbish is collected in the second garbage collection box, is accomplished to process refuse classification, and can be followed after part lake water is processed
Ring is utilized, quality of increasing water quality;In the refuse disposal installation installation process, first highly whole according to the porousness and lake water of soil
Body installs rubbish bleeder in lake, and the rational height further according to rubbish bleeder installs body, thus can be by rubbish
The position of reason is determined, and is easy to install one by one, and the position of associated components is aligned up and down, accelerates installation rate, carries
High installation accuracy.
In order to solve above-mentioned technical problem, the present invention is adopted the following technical scheme that:
A kind of refuse disposal installation for gaolu wetland, it is characterised in that:Including rubbish bleeder, separator frame,
One garbage collection box, garbage separator, the second garbage collection box, body and water circle device;Rubbish bleeder includes entering
Plate, the first installing plate and rubbish flow direction controller, the both sides for entering plate are provided with the first mounting bracket, enter to be provided with plate and enter
Mouthful, two rubbish flow direction controllers are installed on the first installing plate, the direction of rotation of two rubbish flow direction controllers is contrary;Separate
Frame includes that the first guide plate, separating plate and the second guide plate, the both sides of the first guide plate are provided with the second installing plate, the second installing plate
It is fixed on and enters between plate and body, the first guide plate is inclined located at row porch;First garbage collection box is fixed in body,
The end of the second guide plate is passed in the first garbage collection box, and the side of the first garbage collection box is provided with rubbish conveying end;Rubbish
Rubbish separator includes suction bucket, driver and water-supply-pipe, and the second garbage collection box is located at the lower section of separating plate, the second refuse collection
The second mounting bracket is provided with case, and the second mounting bracket fixes suction bucket;Location-plate is provided with body, and one end of location-plate is provided with
Positioning discharging opening, positioning discharging opening are located between separating plate and the second garbage collection box, and location-plate is fixedly connected with driver;Water
EGR includes that spray equipment and water treatment facilities, water-supply-pipe connect spray equipment, and one end of location-plate is provided with deflector, leads
Located at the lower section of spray equipment, the end of deflector is passed in water treatment facilities stream plate, and the bottom of water treatment facilities is provided with out
Water pipe.
Further, rubbish flow direction controller includes that motor and rotation dish, motor drive rotation dish rotation, rotation dish to be provided with
Rotatable lamella, motor drive turn disc so that rotatable lamella activity in lake water, accelerate lake water mobility, are easy to arrange rubbish
Enter.
Further, the first mounting bracket includes installing mobile jib and connection cross bar, installs mobile jib and is fixedly connected with plate is entered, even
The bottom for connecing cross bar is provided with least three insertion rods, and three insertion rods are arranged vertically upward, and connection cross bar can install mobile jib
Upper appropriate adjustment position, so when insertion rod is inserted in soil, staff can continue to exert a force on connection cross bar, insertion
Bar can be inserted downwardly in soil again, increase the fastness that installs.
Further, the inclination angle of the first guide plate is 5 °~15 °, and the plate face of the second guide plate is arc surface, and first is oriented to
Plate and the second guide plate play a part of guiding, and the first guide plate arranges generally 10 ° or so of inclination angle, unsuitable excessive, so
Separating plate is played to the detached effect of rubbish.
Further, the top of the first garbage collection box is provided with baffle plate, and baffle plate can carry out barrier effect to rubbish, by rubbish quilt
Collect in the first garbage collection box.
Further, the bottom of the second garbage collection box is provided with leveling support, and the second garbage collection box can be entered by leveling support
Row leveling is acted on, and then ensures that garbage separator arranges plane for horizontal plane, plays the effect of garbage separator normal operation.
Further, outlet pipe includes that arm and supervisor, arm are connected with supervisor, and arm is located at the bottom of water treatment facilities,
It is easy to the control to flow.
A kind of installation method of the refuse disposal installation for gaolu wetland, it is characterised in that comprise the steps:
A in () lake, rubbish bleeder is installed:Two the first mounting brackets are kept same rational height on the ground first,
A connecting rod is welded between two the first mounting brackets again, and then between two the first mounting brackets, bolt fixation is entered
Plate, then the first installing plate and rubbish flow direction controller are installed at the top for entering plate, then according to the soil at loke shore side
Porousness and lake water height, pull out control datum line in lake, then the first mounting bracket be inserted in soil, and controlled
In lake water, control enters mouth at lake surface to rubbish flow direction controller, then accesses floating plate in the bottom for entering plate, so
Surrounding in the first mounting bracket sets up spud pile afterwards, and connects spud pile and the first mounting bracket with iron wire;
The side concreting of (b) loke shore;
C () body is installed:According to the installation site of rubbish bleeder, the installation of body is drawn on concrete with pencil
Position, further according to setting-out position, builds supporting plank in installed position, then snaps in body between supporting plank, and
The bottom casting concrete overcoat of body, the height of concrete shield are controlled in 10~20mm;
D () water circle device is installed;
E () the first garbage collection box and separator frame are installed:First according to being put into the first refuse collection at the rubbish taking-up of body
Case, and the contact portion by the first garbage collection box with body welded, then separator frame is put into the first garbage collection box
In, then the end of the first guide plate is kept flushing with the end face for entering mouth, and is welded, then the end in the second installing plate
Portion is passed into and enters in mouth, then moves laterally into the other end of the second installing plate, by the second installing plate and body, separator frame
Contact with each other, then the second installing plate is welded respectively with plate, body, separator frame is entered;
F () location-plate and deflector are installed:According to the set location of separator frame, location-plate is welded in body, in welding
During, it is held in position discharging opening and is aligned with separating plate up and down, then one end of deflector is passed in water treatment facilities, while
End of the other end of deflector with separating plate is welded, then deflector is bolted on body;
G () the second garbage collection box and garbage separator are installed:By the second garbage collection box installed in positioning discharging opening
Lower section, further according to the position of suction bucket, adjusts the vertical height of the second garbage collection box, and by the second garbage collection box leveling,
Second mounting bracket is installed in the second garbage collection box again, then the second mounting bracket is welded with suction bucket, while
Driver is integrally provided in location-plate, and is welded, then water-supply-pipe is connected with spray equipment, then twined in junction
Upper adhesive plaster;
H () outlet pipe is laid;
I () soil is backfilled:Soil is inserted in the surrounding of body, soil is covered outlet pipe, then soil is compacted,
The cover height of soil is consistent with the height of concrete shield.
The present invention is had the advantages that as a result of above-mentioned technical proposal:
1st, when to lake surface garbage disposal, two rubbish flow direction controllers accelerate lake to a mouthful phase despining is entered to the present invention
Water is taken advantage of a situation to mouth flowing, the rubbish at loke shore is entered, and reduces the rubbish on lake surface, so can be by lake surface
Rubbish is collected, and plays the effect of cleaning rubbish.The larger rubbish of volume cannot be separated by separating plate simultaneously, led along first
It is collected in the first garbage collection box to the guide effect of plate and the second guide plate, the rubbish of small volume is by separating plate point
From, positioning discharging opening guide effect under be collected in the second garbage collection box, while lake water also drops onto the second rubbish
Collecting box, staff are periodically processed to the first garbage collection box and the second garbage collection box, accomplish to receive refuse classification
Collection process.
And the present invention, under driver effect, suction bucket carries out suction, lake to the bottom of the second garbage collection box
Water is inhaled in suction bucket, and the second garbage collection box is dropped by the filter screen isolation of suction bucket, and lake water is passed into by water-supply-pipe
In spray equipment, shower nozzle on spray equipment sprays lake water on deflector, and deflector is shunted to lake water and removal of impurities
Effect, then lake water enters into water treatment facilities and carries out physics and chemical treatment, purifies water, and increases the dissolved oxygen of lake water, only
Lake water after change is drained in lake again by outlet pipe, so part lake water is carried out processing Posterior circle utilization, is increased water quality
Quality, strengthens improvement of the ecological environment.
2nd, in the refuse disposal installation installation process in the present invention, first overall according to the porousness and lake water height of soil
Rubbish bleeder in lake is installed, is easy to control the rational height for entering plate, and is discharged into plate keep horizontal, and entering
Floating plate is accessed in the bottom of plate, then sets up spud pile in the surrounding of the first mounting bracket, and with iron wire by spud pile and the first peace
Dress support connection, improves the stability of rubbish bleeder installation.Rational height fitting machine further according to rubbish bleeder
Body, needs to build supporting plank in installation process, improves the accuracy that body is installed, and the bottom casting concrete protection in body
Layer, increases the stability of body.Then according to the command range entered between plate and body, to the first garbage collection box and separation
Frame is installed, and according to the set location of separator frame, welds location-plate in body, and positioning discharging opening is right up and down with separating plate
Standard, further according to the position of positioning discharging opening, installs the second garbage collection box, further according to the position of suction bucket, adjusts the second rubbish
The vertical height of collecting box, and by the second garbage collection box leveling, by separating plate, positioning discharging opening and the second garbage collection box
Lower alignment is installed, and thus can be determined the position of garbage disposal, is easy to install one by one, and the position of associated components is entered
Row is aligned up and down, accelerates installation rate, improves installation accuracy.
Description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is a kind of structural representation of the refuse disposal installation for gaolu wetland in the present invention;
Fig. 2 be Fig. 1 in A to structural representation;
Fig. 3 be Fig. 1 in B to structural representation;
Fig. 4 is the structural representation of rubbish flow direction controller in the present invention;
Fig. 5 is the structural representation of rubbish bleeder in the present invention;
Fig. 6 is the structural representation arranged between separator frame and the first garbage collection box in the present invention;
Fig. 7 is the structural representation arranged between garbage separator in the present invention, the second garbage collection box and water circle device
Figure;
Fig. 8 is the structural representation of spray equipment in the present invention;
Fig. 9 is the structural representation of garbage separator in the present invention;
Figure 10 is the structural representation of body in the present invention;
Figure 11 is the structural representation in the present invention after a kind of refuse disposal installation installation for gaolu wetland.
Specific embodiment
As shown in Figure 1 to 11, it is a kind of refuse disposal installation for gaolu wetland in the present invention, enters including rubbish
Device 1, separator frame 2, the first garbage collection box 3, garbage separator 4, the second garbage collection box 5, body 6 and water circle device 7.
Rubbish bleeder 1 includes entering plate 8, the first installing plate 9 and rubbish flow direction controller 10.Enter the both sides of plate 8
The first mounting bracket 11 is provided with, is entered to be provided with plate 8 and is entered mouth 12, can be adjusted according to the size of rubbish and lake surface SEA LEVEL VARIATION situation
The size of entire row entrance 12.Two rubbish flow direction controllers 10, two rubbish flow direction controllers 10 are installed on first installing plate 9
Direction of rotation conversely, main rotate to entering mouth 12.Rubbish flow direction controller 10 includes motor 28 and rotation dish 29, motor 28
Rotation dish 29 is driven to rotate.Rotation dish 29 is provided with rotatable lamella 30, and motor 28 drives rotation dish 29 to rotate so that rotatable lamella 30 exists
Activity in lake water, accelerates lake water mobility, is easy to enter rubbish.First mounting bracket 11 includes installing mobile jib 31 and connection is horizontal
Bar 32, connection cross bar 32 can install 31 activity of mobile jib, install mobile jib 31 and are fixedly connected with plate 8 is entered.The bottom of connection cross bar 32
Portion is provided with least three insertion rods 33, and three insertion rods 33 are arranged vertically upward, and connection cross bar 32 can be on mobile jib 31 be installed
Appropriate adjustment position, so when insertion rod 33 is inserted in soil, staff can continue to exert a force on connection cross bar 32, insert
Enter bar 33 to be inserted downwardly in soil again, increase the fastness that installs.
Separator frame 2 includes that the first guide plate 13, separating plate 14 and the second guide plate 15, the both sides of the first guide plate 13 are provided with
Second installing plate 16, the second installing plate 16 are fixed on and enter between plate 8 and body 6, and the first guide plate 13 is inclined to be located at and enters mouth
At 12.The inclination angle of the first guide plate 13 is 5 °~15 °, and the plate face of the second guide plate 15 is arc surface, 13 He of the first guide plate
Second guide plate 15 plays a part of guiding, and the first guide plate 13 arranges generally 10 ° or so of inclination angle, unsuitable excessive, so
Separating plate 14 is played to the detached effect of rubbish.
First garbage collection box 3 is fixed in body 6, and the end of the second guide plate 15 is passed into the first garbage collection box 3
In, the side of the first garbage collection box 3 is provided with rubbish conveying end 17, and staff opens rubbish conveying end 17, just can process the
Rubbish in one garbage collection box 3.The top of the first garbage collection box 3 is provided with baffle plate 34, and baffle plate 34 can stop to rubbish
Effect, rubbish is collected in the first garbage collection box 3.
Garbage separator 4 includes that suction bucket 18, driver 19 and water-supply-pipe 20, the second garbage collection box 5 are located at separating plate
14 lower section.It is provided with the second mounting bracket 21 in second garbage collection box 5, the second mounting bracket 21 fixes suction bucket 18, second
Mounting bracket 21 is A-frame.The bottom of the second garbage collection box 5 is provided with leveling support 35, and leveling support 35 can be by the second rubbish
Rubbish collecting box 5 carries out leveling effect, and then ensures that garbage separator 4 arranges plane for horizontal plane, plays garbage separator 4 normal
The effect of running.
Location-plate 22 is provided with body 6, and one end of location-plate 22 is provided with positioning discharging opening 23, and positioning discharging opening 23 is located at and divides
Between plate 14 and the second garbage collection box 5, location-plate 22 is fixedly connected with driver 19, and positioning discharging opening 23 plays installation position
The effect that puts positioning and rubbish is oriented to.
Water circle device 7 includes that spray equipment 24 and water treatment facilities 25, water-supply-pipe 20 connect spray equipment 24.Location-plate
22 one end is provided with deflector 26, and located at the lower section of spray equipment 24, the end of deflector 26 is passed into water process to deflector 26
In device 25.The bottom of water treatment facilities 25 is provided with outlet pipe 27, and outlet pipe 27 includes arm 36 and supervisor 37, arm 36 and master
Pipe 37 connects, and arm 36 is easy to the control to flow located at the bottom of water treatment facilities 25.
The present invention when to lake surface garbage disposal, accelerate to 12 phase despining of mouth is entered by two rubbish flow direction controllers 10
Lake water flows to mouth 12 is entered, and the rubbish at loke shore is taken advantage of a situation, and reduces the rubbish on lake surface, so can be by lake
Rubbish on face is collected, and plays the effect of cleaning rubbish.The larger rubbish of volume cannot be separated by separating plate 14 simultaneously, suitable
The guide effect for the first guide plate 13 and the second guide plate 15 is collected in the first garbage collection box 3, the rubbish of small volume
Rubbish is separated by separating plate 14, is collected in the second garbage collection box 5, while lake water under the guide effect of positioning discharging opening 23
Also drop onto the second garbage collection box 5, staff periodically to the first garbage collection box 3 and the second garbage collection box 5 at
Reason, accomplishes to process separate waste collection.
And the present invention, under the effect of driver 19, the bottom of 18 pairs of the second garbage collection box 5 of suction bucket carries out suction work
With lake water is inhaled in suction bucket 18, and the second garbage collection box 5 is dropped by the filter screen isolation of suction bucket 18, and lake water is by defeated
Water pipe 20 is passed in spray equipment 24, and the shower nozzle on spray equipment 24 sprays lake water on deflector 26, deflector 26 pairs
Lake water carries out shunting the effect with removal of impurities, and then lake water enters into water treatment facilities 25 and carries out physics and chemical treatment, purified water
Matter, increases the dissolved oxygen of lake water, and the lake water after purification is drained in lake again by outlet pipe 27, so part lake water is carried out
Process Posterior circle to utilize, quality of increasing water quality strengthens improvement of the ecological environment.
A kind of installation method of the refuse disposal installation for gaolu wetland, comprises the steps:
A in () lake, rubbish bleeder 1 is installed:Two the first mounting brackets 11 are kept same on the ground first height is set
Spend, then a connecting rod is welded between two the first mounting brackets 11, then bolt between two the first mounting brackets 11
Fixation enters plate 8, then installs the first installing plate 9 and rubbish flow direction controller 10 at the top for entering plate 8, then according near lake
The porousness of the soil at bank and lake water height, pull out control datum line in lake, then the first mounting bracket 11 are inserted
To in soil, and rubbish flow direction controller 10 is controlled in lake water, control enters mouth 12 at lake surface, is then entering plate
Floating plate is accessed in 8 bottom, and then the surrounding in the first mounting bracket 11 sets up spud pile, and with iron wire by spud pile and first
Mounting bracket 11 connects.As lake surface water level changes constantly, when rubbish bleeder 1 is arranged, lake surface is typically calculated
The scope of SEA LEVEL VARIATION, then from larger enter mouth 12 enter plate 8, it is to avoid shadow of the lake surface SEA LEVEL VARIATION to garbage disposal
Ring.
The side concreting of (b) loke shore:First debris are purged, basic unit is flattened, then microlith is used at basic unit
Sand is inserted, and flattens compacting, then inserts stone in microlith sand, then carries out concreting, conserves 10~15d after pouring.
C () body 6 is installed:According to the installation site of rubbish bleeder 1, on concrete, body 6 is drawn with pencil
Installation site, further according to setting-out position, builds supporting plank in installed position, then snaps in body 6 between supporting plank,
And the bottom casting concrete overcoat in body 6, the height control of concrete shield is in 10~20mm.
D () water circle device 7 is installed.
E () first garbage collection box 3 and separator frame 2 are installed:Elder generation is received according to the first rubbish is put at the rubbish taking-up of body 6
Header 3, and the contact portion by the first garbage collection box 3 with body 6 welded, then separator frame 2 is put into the first rubbish
In collecting box 3, then the end of the first guide plate 13 is kept flushing with the end face for entering mouth 12, and is welded, then the
The end of two installing plates 16 is passed into and enters in mouth 12, then moves laterally into the other end of the second installing plate 16, by second
Installing plate 16 is contacted with each other with body 6, separator frame 2, is then distinguished the second installing plate 16 with plate 8, body 6, separator frame 2 is entered
Welded.
F () location-plate 22 and deflector 26 are installed:According to the set location of separator frame 2, location-plate is welded in body 6
22, in welding process, it is held in position discharging opening 23 and is aligned about 14 with separating plate, then one end of deflector 26 is passed into water
In processing meanss 25, while the end by the other end of deflector 26 with separating plate 14 is welded, then that 26 bolt of deflector is solid
Determine on body 6.
G () second garbage collection box 5 and garbage separator 4 are installed:By the second garbage collection box 5 installed in positioning discharging opening
23 lower section, further according to the position of suction bucket 18, adjusts the vertical height of the second garbage collection box 5, and by the second refuse collection
5 leveling of case, then the second mounting bracket 21 is installed in the second garbage collection box 5, then by the second mounting bracket 21 and suction bucket
18 are welded, while driver 19 is integrally provided in location-plate 22, and are welded, then by water-supply-pipe 20 and spray
Device 24 is connected, then is wrapped with adhesive plaster in junction.
H () outlet pipe 27 is laid.
I () soil is backfilled:Soil is inserted in the surrounding of body 6, soil is covered outlet pipe 27, then soil is pressed
Real, the cover height of soil is consistent with the height of concrete shield.
In refuse disposal installation installation process in the present invention, first pacified according to the porousness and lake water height entirety of soil
Rubbish bleeder 1 in dress lake, is easy to the rational height for controlling to enter plate 8, and is discharged into plate 8 keep horizontal, and in row
Floating plate is accessed in the bottom for entering plate 8, then sets up spud pile in the surrounding of the first mounting bracket 11, and with iron wire by spud pile and the
One mounting bracket 11 connects, and improves the stability of the installation of rubbish bleeder 1.Setting further according to rubbish bleeder 1 is high
Degree installs body 6, needs to build supporting plank in installation process, improves the accuracy that body 6 is installed, and pour in the bottom of body 6
Concrete shield is built, increases the stability of body 6.Then according to the command range entered between plate 8 and body 6, to first
Garbage collection box 3 and separator frame 2 are installed, and according to the set location of separator frame 2, weld location-plate 22, positioning in body 6
Discharging opening 23 is aligned about 14 with separating plate, further according to the position of positioning discharging opening 23, installs the second garbage collection box 5, then root
According to the position of suction bucket 18, the vertical height of the second garbage collection box 5 is adjusted, and by 5 leveling of the second garbage collection box, will be separated
Plate 14, positioning discharging opening 23 are directed at installation with the second garbage collection box about 5, thus can carry out really the position of garbage disposal
Fixed, it is easy to install one by one, and the position of associated components is aligned up and down, accelerate installation rate, improves installation accuracy.
The specific embodiment of the present invention is these are only, but the technical characteristic of the present invention is not limited thereto.Any with this
Based on bright, it is to solve essentially identical technical problem, realizes essentially identical technique effect, done simple change, etc.
With replacement or modification etc., all it is covered by among protection scope of the present invention.
Claims (8)
1. a kind of refuse disposal installation for gaolu wetland, it is characterised in that:Including rubbish bleeder, separator frame, first
Garbage collection box, garbage separator, the second garbage collection box, body and water circle device;The rubbish bleeder includes arranging
Enter plate, the first installing plate and rubbish flow direction controller, the both sides for entering plate are provided with the first mounting bracket, described enter in plate
It is provided with and enters mouth, two rubbish flow direction controllers, two rubbish traffic organisings is installed on first installing plate
The direction of rotation of device is contrary;The separator frame includes the first guide plate, separating plate and the second guide plate, first guide plate
Both sides are provided with the second installing plate, second installing plate be fixed on described enter between plate and the body, described first is oriented to
Plate is inclined and is located at the row porch;First garbage collection box is fixed in the body, the end of second guide plate
Portion is passed in first garbage collection box, and the side of first garbage collection box is provided with rubbish conveying end;The rubbish
Separator includes suction bucket, driver and water-supply-pipe, second garbage collection box located at the lower section of the separating plate, described the
The second mounting bracket is provided with two garbage collection box, and second mounting bracket fixes the suction bucket;It is provided with the body
Location-plate, one end of the location-plate are provided with positioning discharging opening, and the positioning discharging opening is located at the separating plate and described second
Between garbage collection box, the location-plate is fixedly connected with the driver;The water circle device includes spray equipment and water
Processing meanss, the water-supply-pipe connect the spray equipment, and one end of the location-plate is provided with deflector, and the deflector is located at
The lower section of the spray equipment, the end of the deflector are passed in the water treatment facilities, the bottom of the water treatment facilities
Portion is provided with outlet pipe.
2. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that:The waste flow
Include that motor and rotation dish, the motor drive the rotation disc spins, the rotation dish to be provided with rotatable lamella to controller.
3. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that:First peace
Dress support includes installing mobile jib and connection cross bar, and the installation mobile jib is fixedly connected with the plate that enters, the connection cross bar
Bottom is provided with least three insertion rods, and three insertion rods are arranged vertically upward.
4. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that:Described first leads
It it is 5 °~15 ° to the inclination angle of plate, the plate face of second guide plate is arc surface.
5. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that:First rubbish
The top of rubbish collecting box is provided with baffle plate.
6. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that:Second rubbish
The bottom of rubbish collecting box is provided with leveling support.
7. a kind of refuse disposal installation for gaolu wetland according to claim 1, it is characterised in that:The outlet pipe
Including arm and supervisor, the arm is connected with the supervisor, and the arm is located at the bottom of the water treatment facilities.
8. a kind of installation method of the refuse disposal installation for gaolu wetland based on described in claim 1, it is characterised in that
Comprise the steps:
A in () lake, rubbish bleeder is installed:Two the first mounting brackets are kept same rational height on the ground first, then
A connecting rod is welded between two the first mounting brackets, and then between two the first mounting brackets, bolt is fixed and enters plate,
The first installing plate and rubbish flow direction controller are installed at the top for entering plate again, then dredging according to the soil at loke shore side
Loose degree and lake water height, pull out control datum line in lake, then the first mounting bracket are inserted in soil, and control rubbish
In lake water, control enters mouth at lake surface to flow direction controller, then accesses floating plate, Ran Hou in the bottom for entering plate
The surrounding of the first mounting bracket sets up spud pile, and connects spud pile and the first mounting bracket with iron wire;
The side concreting of (b) loke shore;
C () body is installed:According to the installation site of rubbish bleeder, the installation position of body is drawn on concrete with pencil
Put, further according to setting-out position, supporting plank is built in installed position, then snap in body between supporting plank, and in machine
The bottom casting concrete overcoat of body, the height of concrete shield are controlled in 10~20mm;
D () water circle device is installed;
E () the first garbage collection box and separator frame are installed:First according to being put into the first garbage collection box at the rubbish taking-up of body, and
Contact portion of first garbage collection box with body is welded, then separator frame is put in the first garbage collection box, so
Afterwards the end of the first guide plate is kept flushing with the end face for entering mouth, and is welded, then led in the end of the second installing plate
Enter to entering in mouth, then the other end of the second installing plate is moved laterally into, will be mutual with body, separator frame for the second installing plate
Then second installing plate is welded respectively by contact with plate, body, separator frame is entered;
F () location-plate and deflector are installed:According to the set location of separator frame, location-plate is welded in body, in welding process
In, it is held in position discharging opening and is aligned with separating plate up and down, then one end of deflector is passed in water treatment facilities, while will leads
The other end of stream plate is welded with the end of separating plate, and then deflector is bolted on body;
G () the second garbage collection box and garbage separator are installed:By the second garbage collection box installed in the lower section of positioning discharging opening,
Further according to the position of suction bucket, the vertical height of the second garbage collection box is adjusted, and by the second garbage collection box leveling, then the
Second mounting bracket is installed in two garbage collection box, then the second mounting bracket is welded with suction bucket, while will drive
Device is integrally provided in location-plate, and is welded, and is then connected water-supply-pipe with spray equipment, then is wrapped with glue in junction
Cloth;
H () outlet pipe is laid;
I () soil is backfilled:Soil is inserted in the surrounding of body, soil is covered outlet pipe, then soil is compacted, soil
Cover height be consistent with the height of concrete shield.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610846487.4A CN106493144B (en) | 2016-09-23 | 2016-09-23 | A kind of refuse disposal installation and installation method for gaolu wetland |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610846487.4A CN106493144B (en) | 2016-09-23 | 2016-09-23 | A kind of refuse disposal installation and installation method for gaolu wetland |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106493144A true CN106493144A (en) | 2017-03-15 |
CN106493144B CN106493144B (en) | 2019-04-26 |
Family
ID=58290813
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610846487.4A Active CN106493144B (en) | 2016-09-23 | 2016-09-23 | A kind of refuse disposal installation and installation method for gaolu wetland |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106493144B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110667794A (en) * | 2019-11-16 | 2020-01-10 | 华北水利水电大学 | Water surface floating sundry cleaning boat |
CN110904931A (en) * | 2019-11-19 | 2020-03-24 | 江苏科技大学 | Water surface garbage fishing device |
CN112813943A (en) * | 2021-01-04 | 2021-05-18 | 赖亮明 | Environment-friendly treatment equipment for cleaning river pollutants |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2707738Y (en) * | 2004-04-15 | 2005-07-06 | 刘晓虹 | Device for sucking and removing sewage on the water |
US7465843B2 (en) * | 2002-02-18 | 2008-12-16 | E.E.R. Environmental Energy Resources (Israe) Ltd. | Recycling system for a waste processing plant |
CN202644506U (en) * | 2012-05-29 | 2013-01-02 | 范福军 | Water surface sewage collecting device |
CN203546690U (en) * | 2013-11-13 | 2014-04-16 | 张楠 | River surface garbage fishing tool |
CN203715335U (en) * | 2013-11-01 | 2014-07-16 | 北京北科欧远科技有限公司山西分公司 | Device for removing light-weight suspended solids out of sewage |
CN204486451U (en) * | 2015-02-14 | 2015-07-22 | 宁德师范学院 | A kind of refuse disposal installation of deodorization |
CN204551405U (en) * | 2015-03-31 | 2015-08-12 | 徐卫东 | A kind of river surface rubbish fishing device efficiently |
CN105544639A (en) * | 2016-01-25 | 2016-05-04 | 天津汇康田科技研发有限公司 | Underwater waste collection system |
-
2016
- 2016-09-23 CN CN201610846487.4A patent/CN106493144B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7465843B2 (en) * | 2002-02-18 | 2008-12-16 | E.E.R. Environmental Energy Resources (Israe) Ltd. | Recycling system for a waste processing plant |
CN2707738Y (en) * | 2004-04-15 | 2005-07-06 | 刘晓虹 | Device for sucking and removing sewage on the water |
CN202644506U (en) * | 2012-05-29 | 2013-01-02 | 范福军 | Water surface sewage collecting device |
CN203715335U (en) * | 2013-11-01 | 2014-07-16 | 北京北科欧远科技有限公司山西分公司 | Device for removing light-weight suspended solids out of sewage |
CN203546690U (en) * | 2013-11-13 | 2014-04-16 | 张楠 | River surface garbage fishing tool |
CN204486451U (en) * | 2015-02-14 | 2015-07-22 | 宁德师范学院 | A kind of refuse disposal installation of deodorization |
CN204551405U (en) * | 2015-03-31 | 2015-08-12 | 徐卫东 | A kind of river surface rubbish fishing device efficiently |
CN105544639A (en) * | 2016-01-25 | 2016-05-04 | 天津汇康田科技研发有限公司 | Underwater waste collection system |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110667794A (en) * | 2019-11-16 | 2020-01-10 | 华北水利水电大学 | Water surface floating sundry cleaning boat |
CN110904931A (en) * | 2019-11-19 | 2020-03-24 | 江苏科技大学 | Water surface garbage fishing device |
CN110904931B (en) * | 2019-11-19 | 2021-04-27 | 江苏科技大学 | Surface garbage salvage device |
CN112813943A (en) * | 2021-01-04 | 2021-05-18 | 赖亮明 | Environment-friendly treatment equipment for cleaning river pollutants |
Also Published As
Publication number | Publication date |
---|---|
CN106493144B (en) | 2019-04-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206784757U (en) | A kind of device for recycling rainwater | |
CN203174656U (en) | Channel cleanout device | |
CN103205991A (en) | Channel cleanout device and method thereof | |
CN104631547A (en) | Rainwater collecting system | |
CN208934081U (en) | A kind of sponge cell rainwater utilization intelligent management system | |
CN106493144B (en) | A kind of refuse disposal installation and installation method for gaolu wetland | |
CN113216358B (en) | BIM-based drainage pipeline and construction method thereof | |
CN204530842U (en) | Rain water collecting system | |
CN206109974U (en) | Bridge drainage system | |
CN106436668B (en) | A kind of river garbage automatic cleaning method | |
CN205307897U (en) | A central transmission inhales mud scraper for two heavy ponds | |
CN215858110U (en) | Rain and sewage flow dividing device for building engineering | |
CN206591571U (en) | A kind of gardens rain collector | |
CN214972378U (en) | Construction effluent treatment plant | |
CN214460930U (en) | Environment-friendly sponge city's rainwater circulation system | |
CN104371911A (en) | Biogas fermentation tank deposit cleaning apparatus system and cleaning construction process | |
CN210987483U (en) | Viaduct greening irrigation system | |
CN210238633U (en) | Rainwater recycling system | |
CN106759766B (en) | A kind of urban road rainwater retention purification system and construction method | |
CN104727366B (en) | What a kind of belt edge table rushed function rushes suction dredge | |
CN212051031U (en) | Dredging sludge treatment system | |
CN118373510B (en) | Sponge urban rainwater collection and treatment system | |
CN217419195U (en) | Road rainwater super-seepage collecting and recycling system | |
CN114508160B (en) | Ecological regulation and control and landscaping construction method for water resources in garden lake center area | |
CN218249231U (en) | Temporary dustproof device for road engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |