CN106149570A - 一种步履式架桥机架设预制箱梁施工方法 - Google Patents
一种步履式架桥机架设预制箱梁施工方法 Download PDFInfo
- Publication number
- CN106149570A CN106149570A CN201510129471.7A CN201510129471A CN106149570A CN 106149570 A CN106149570 A CN 106149570A CN 201510129471 A CN201510129471 A CN 201510129471A CN 106149570 A CN106149570 A CN 106149570A
- Authority
- CN
- China
- Prior art keywords
- box beam
- support roller
- overhead traveling
- bridge
- traveling crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 27
- 210000001364 upper extremity Anatomy 0.000 claims description 19
- 239000000725 suspension Substances 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 4
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 230000001360 synchronised effect Effects 0.000 claims description 3
- 230000007547 defect Effects 0.000 abstract description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 3
- 238000009417 prefabrication Methods 0.000 abstract description 2
- 238000007689 inspection Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 230000004888 barrier function Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000008187 granular material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及桥梁施工领域,特别涉及一种步履式架桥机架设预制箱梁施工方法。它包括在架桥机后端起吊由运梁车运来的预制箱梁,调制架桥机前、后支腿及中、后托轮等构件,在保持架桥机自身重量平衡的同时推动架桥机前移,将架桥机前支腿纵移到前方待架跨桥墩盖梁上,后支腿支于已架箱梁前端顶面,从而达到过孔的目的,然后利用架桥机上的运梁天车进行箱梁的吊装。本发明解决了起重机需反复支设、挪移,施工效率低,风险系数高等缺陷。本发明既能保证工期,也保证了桥下道路的正常施工和车辆通行,同时降低施工成本,安全系数高,具有良好的社会效益和经济效益,宜在城市预制箱梁吊装工程中应用,特别适合水上桥梁,较高桥梁预制箱梁吊装。
Description
(一)
技术领域
本发明涉及桥梁施工领域,特别涉及一种步履式架桥机架设预制箱梁施工方法。
(二)
背景技术
预制箱梁吊装作为桥梁的主体工程,是整个桥梁施工领域的重点、难点,同时也存在众多的技术难题。目前的预制箱梁吊装施工工艺,采用起重机吊装需反复支设、挪移,施工效率低,风险系数高,并且需要采取一定的防护措施,一旦施工环境发生变化,施工条件复杂,施工工期较长,施工成本提高。
(三)
发明内容
本发明为了弥补现有技术的缺陷,提供了一种安全、高效的步履式架桥机架设预制箱梁施工方法。
本发明是通过如下技术方案实现的:
一种步履式架桥机架设预制箱梁施工方法,其特征是:包括以下步骤:
1)第一跨箱梁架设:
首先由运梁平车喂梁,启动运梁平车将箱梁运至中托轮处,使箱梁前吊点置于前天车下方,并将箱梁前端吊起;同时驱动前天车和运梁平车后轮,同步前进,使箱梁的后吊点位于正在中托轮处等待的后天车下方;接着后天车起吊,两个天车带着箱梁前进,直到箱梁达到两桥墩上方;将箱梁下落离盖梁5~15厘米;架桥机横移,前支腿和中托的轮箱同步沿着各自的横移轨道移动,到达梁位时落梁,下落在支座上,完成一片箱梁的安装。
2)过孔:
a:顶升后托轮及前支腿,用起吊天车将中托轮及中托轮横移轨道前移30米移至已吊装完成箱梁端部,将后托轮前移10米;
b:用运梁平车将箱梁运至中托轮偏后位置,并将两个起吊天车后退至中托轮后方,用后天车将箱梁前端吊起,前天车与中托轮联接;
c:收起前支腿、后支腿,启动中托轮组推动主梁架前移16米,箱梁不动;放下后支腿,用前天车将后托轮前移18米,同时箱梁与后天车跟进至后托轮偏后位置;
d:顶升后托轮,收起后支腿,启动中托轮组推动主梁架前移14米,箱梁不动;将前天车与后托轮解除联接,并起吊前支腿轨道前移至前一个盖梁处,铺设调平后,将前支腿架设至轨道上;
e:将后天车与箱梁解除联接,两天车移至中托轮偏后处,启动运梁平车将箱梁运至中托轮处,开始下一跨箱梁吊装。
3)梁体横移至就位位置:前支腿横移轮组和中托下横移轮组同时、同向、同速动作,驱动架桥机连带梁片横向移动。
4)落梁:将箱梁落到桥墩的支座上。
5)架桥机返回:首先起重小车横移:拆吊具,收起钢丝绳,两起重小车横移到天车梁中间;其次架桥机横移:横移架桥机到喂梁位置;最后是天车返回到后支腿位置,做好吊装下一片箱梁的准备。
本发明的有益效果是:
1、本发明解决了起重机需反复支设、挪移,施工效率低,风险系数高等缺陷。
2、本发明既能保证工期,也保证了桥下道路的正常施工和车辆通行,同时降低施工成本。
3、本发明在施工现场不会出现起重机,也就不会对周围行人和车辆造成伤害,因此具有良好的社会效益和经济效益,
在城市桥梁建设中有推广价值。
4、本发明的施工方法宜在城市预制箱梁吊装工程中应用,特别适合水上桥梁,较高桥梁预制箱梁吊装。
(四)
具体实施方式
在使用该种步履式架桥机架设预制箱梁施工方法进行施工前先做好施工准备:所有梁片由监理工程师及项目质检工程师检查合格后方可进行运输、安装,安装前要求检查梁体的外形尺寸、砼强度、预埋钢筋(件)尺寸及位置、吊装孔洞位置、泄水孔位置、张拉及压浆质量、砼外观质量、封端质量等,符合要求后方可安装。严格检查梁体各部位尺寸、外观质量、砼强度、张拉及压浆质量,检查预埋钢筋(件)位置、数量,严格检查需后浇砼连接部位的施工缝处理情况,必须将松散砼颗粒、浮浆全部凿除,以露出新鲜砼面为宜。
质检员负责收集架桥机及人员进场资料上报监理审核,包括机械合格证、桥机生产厂家资质以及人员身份信息、特种作业人员操作证。并做好桥机拼装、调试后报验工作。
完成架桥机的拼装并验收合格后再进行以下步骤:
1)第一跨箱梁架设:
首先由运梁平车喂梁,启动运梁平车将箱梁运至中托轮处,使箱梁前吊点置于前天车下方,并将箱梁前端吊起;同时驱动前天车和运梁平车后轮,同步前进,使箱梁的后吊点位于正在中托轮处等待的后天车下方;接着后天车起吊,两个天车带着箱梁前进,直到箱梁达到两桥墩上方;将箱梁下落离盖梁5~15厘米;架桥机横移,前支腿和中托的轮箱同步沿着各自的横移轨道移动,到达梁位时落梁,下落在支座上,完成一片箱梁的安装。
2)过孔:
a:顶升后托轮及前支腿,用起吊天车将中托轮及中托轮横移轨道前移30米移至已吊装完成箱梁端部,将后托轮前移10米;
b:用运梁平车将箱梁运至中托轮偏后位置,并将两个起吊天车后退至中托轮后方,用后天车将箱梁前端吊起,前天车与中托轮联接;
c:收起前支腿、后支腿,启动中托轮组推动主梁架前移16米,箱梁不动;放下后支腿,用前天车将后托轮前移18米,同时箱梁与后天车跟进至后托轮偏后位置;
d:顶升后托轮,收起后支腿,启动中托轮组推动主梁架前移14米,箱梁不动;将前天车与后托轮解除联接,并起吊前支腿轨道前移至前一个盖梁处,铺设调平后,将前支腿架设至轨道上;
e:将后天车与箱梁解除联接,两天车移至中托轮偏后处,启动运梁平车将箱梁运至中托轮处,开始下一跨箱梁吊装。
3)梁体横移至就位位置:前支腿横移轮组和中托下横移轮组同时、同向、同速动作,驱动架桥机连带梁片横向移动。
4)落梁:将箱梁落到桥墩的支座上。混凝土拆模时的强度不得低于设计强度的75%。为了保证颜色一致,拆模后应阴干半天,然后覆盖毛毡洒水养生。对箱梁混凝土进行全面检查,发现问题及时分析原因,及时纠正。
5)架桥机返回:首先起重小车横移:拆吊具,收起钢丝绳,两起重小车横移到天车梁中间;其次架桥机横移:横移架桥机到喂梁位置;最后是天车返回到后支腿位置,做好吊装下一片箱梁的准备。
吊装完成后,进行检查验收:根据支座中心线用直尺复核箱梁顺桥向位置是否准确,用全站仪测量顺桥纵轴线方向,偏差应控制在10mm以内。不合格的坚决返工,重新起吊安装,直至符合规范要求。保证桥梁线形美观。
质量标准:根据有关规范、图纸要求,质量标准如下:
前支腿、中托轮的横向运行轨道要求严格控制间距,二条轨道必须平行,架桥机轨距误差不超过2mm,相邻轨道接头高差不大于1mm。
顺桥纵轴线方向,偏差应控制在10mm以内。
除说明书所述技术特征外,其余技术特征均为本领域技术人员已知技术。
Claims (1)
1.一种步履式架桥机架设预制箱梁施工方法,其特征是:包括以下步骤:
1)第一跨箱梁架设:
首先由运梁平车喂梁,启动运梁平车将箱梁运至中托轮处,使箱梁前吊点置于前天车下方,并将箱梁前端吊起;同时驱动前天车和运梁平车后轮,同步前进,使箱梁的后吊点位于正在中托轮处等待的后天车下方;接着后天车起吊,两个天车带着箱梁前进,直到箱梁达到两桥墩上方;将箱梁下落离盖梁5~15厘米;架桥机横移,前支腿和中托的轮箱同步沿着各自的横移轨道移动,到达梁位时落梁,下落在支座上,完成一片箱梁的安装;
2)过孔:
a:顶升后托轮及前支腿,用起吊天车将中托轮及中托轮横移轨道前移30米移至已吊装完成箱梁端部,将后托轮前移10米;
b:用运梁平车将箱梁运至中托轮偏后位置,并将两个起吊天车后退至中托轮后方,用后天车将箱梁前端吊起,前天车与中托轮联接;
c:收起前支腿、后支腿,启动中托轮组推动主梁架前移16米,箱梁不动;放下后支腿,用前天车将后托轮前移18米,同时箱梁与后天车跟进至后托轮偏后位置;
d:顶升后托轮,收起后支腿,启动中托轮组推动主梁架前移14米,箱梁不动;将前天车与后托轮解除联接,并起吊前支腿轨道前移至前一个盖梁处,铺设调平后,将前支腿架设至轨道上;
e:将后天车与箱梁解除联接,两天车移至中托轮偏后处,启动运梁平车将箱梁运至中托轮处,开始下一跨箱梁吊装;
3)梁体横移至就位位置:前支腿横移轮组和中托下横移轮组同时、同向、同速动作,驱动架桥机连带梁片横向移动;
4)落梁:将箱梁落到桥墩的支座上;
5)架桥机返回:起重小车横移:拆吊具,收起钢丝绳,两起重小车横移到天车梁中间;
6)架桥机横移:横移架桥机到喂梁位置;
7)天车返回:天车返回到后支腿位置,做好吊装下一片箱梁的准备。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510129471.7A CN106149570A (zh) | 2015-03-24 | 2015-03-24 | 一种步履式架桥机架设预制箱梁施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510129471.7A CN106149570A (zh) | 2015-03-24 | 2015-03-24 | 一种步履式架桥机架设预制箱梁施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106149570A true CN106149570A (zh) | 2016-11-23 |
Family
ID=58063823
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510129471.7A Pending CN106149570A (zh) | 2015-03-24 | 2015-03-24 | 一种步履式架桥机架设预制箱梁施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106149570A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653104A (zh) * | 2018-12-26 | 2019-04-19 | 中国水利水电第四工程局有限公司 | 一种双线箱梁变跨架设施工方法 |
CN112575694A (zh) * | 2020-12-10 | 2021-03-30 | 江苏捷达交通工程集团有限公司 | 一种大跨径t梁安装施工工法 |
CN112663514A (zh) * | 2020-12-21 | 2021-04-16 | 中建八局第三建设有限公司 | 一种新型墩梁一体化架桥机 |
CN113202028A (zh) * | 2021-04-08 | 2021-08-03 | 中铁六局集团有限公司 | 上跨营业线铁路架桥机架设大跨度箱梁施工方法 |
CN113802467A (zh) * | 2021-10-27 | 2021-12-17 | 重庆城建控股(集团)有限责任公司 | 基于架桥机的大坡度架梁方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1609342A (zh) * | 2004-11-25 | 2005-04-27 | 中铁大桥局集团有限公司 | 下导梁式架桥机及其架梁方法 |
CN2878481Y (zh) * | 2005-12-09 | 2007-03-14 | 郑州力博桥梁机械制造有限公司 | 架桥机 |
CN102797226A (zh) * | 2012-07-26 | 2012-11-28 | 中铁六局集团有限公司 | 60米钢箱梁整体架设施工方法 |
CN103147398A (zh) * | 2013-02-04 | 2013-06-12 | 秦皇岛天业通联重工股份有限公司 | 一种架桥机及其实现桥间转移或穿过隧道的方法 |
-
2015
- 2015-03-24 CN CN201510129471.7A patent/CN106149570A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1609342A (zh) * | 2004-11-25 | 2005-04-27 | 中铁大桥局集团有限公司 | 下导梁式架桥机及其架梁方法 |
CN2878481Y (zh) * | 2005-12-09 | 2007-03-14 | 郑州力博桥梁机械制造有限公司 | 架桥机 |
CN102797226A (zh) * | 2012-07-26 | 2012-11-28 | 中铁六局集团有限公司 | 60米钢箱梁整体架设施工方法 |
CN103147398A (zh) * | 2013-02-04 | 2013-06-12 | 秦皇岛天业通联重工股份有限公司 | 一种架桥机及其实现桥间转移或穿过隧道的方法 |
Non-Patent Citations (1)
Title |
---|
杨小强: "杨小强", 《中国新技术新产品》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653104A (zh) * | 2018-12-26 | 2019-04-19 | 中国水利水电第四工程局有限公司 | 一种双线箱梁变跨架设施工方法 |
CN112575694A (zh) * | 2020-12-10 | 2021-03-30 | 江苏捷达交通工程集团有限公司 | 一种大跨径t梁安装施工工法 |
CN112663514A (zh) * | 2020-12-21 | 2021-04-16 | 中建八局第三建设有限公司 | 一种新型墩梁一体化架桥机 |
CN113202028A (zh) * | 2021-04-08 | 2021-08-03 | 中铁六局集团有限公司 | 上跨营业线铁路架桥机架设大跨度箱梁施工方法 |
CN113802467A (zh) * | 2021-10-27 | 2021-12-17 | 重庆城建控股(集团)有限责任公司 | 基于架桥机的大坡度架梁方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104790295B (zh) | 轮胎式龙门吊架梁施工工法 | |
CN107268463B (zh) | 一种连续梁拆除方法 | |
CN106149570A (zh) | 一种步履式架桥机架设预制箱梁施工方法 | |
CN104195952A (zh) | 应用于钢混混合梁斜拉桥钢箱梁架设方法 | |
CN104372743B (zh) | 栈桥快速施工方法 | |
CN105421249A (zh) | 一种拖吊结合式新型挂篮结构及施工方法 | |
JP2014066007A (ja) | 既設橋梁の撤去方法および既設橋梁の更新方法 | |
CN204510844U (zh) | 一种大跨度钢梁高空安装滑移装置 | |
CN107747282B (zh) | 上跨既有线旧桥梁体整体拆除方法 | |
CN105155417B (zh) | 一种攀爬式运梁跨车及基于其的隧道口桥梁运架方法 | |
KR101234090B1 (ko) | 철도 판형교의 거더 교체 방법 | |
CN104018426A (zh) | 一种钢桁梁安装方法 | |
CN106087768A (zh) | 一种在桥隧狭短过渡段上拼装移动模架的方法 | |
CN105544406B (zh) | 贝雷梁滑移式拆除装置及其拆除方法 | |
CN104179123A (zh) | 一种两孔连做节段拼装造桥机 | |
JP2019044453A (ja) | 架替工法及び架設機 | |
CN113279335A (zh) | 一种可用于跨山岭大吨位、宽幅度钢箱梁安装的装置及方法 | |
CN101481903A (zh) | 跨缆吊机倒退拼装架设山区悬索桥主桁方法 | |
CN108625270A (zh) | 导梁门吊安装桥梁预制箱梁施工方法 | |
CN103821084A (zh) | 梁底作业设备及梁底作业方法 | |
CN203767643U (zh) | 一种封闭式钢结构输送栈桥 | |
CN106192761B (zh) | 一种在桥隧狭短过渡段拆解移动模架的方法 | |
CN209338005U (zh) | 一种架梁施工用移动式高低腿龙门吊 | |
CN102535351B (zh) | 大风及高空条件下桥梁施工用腹板式造桥机及施工工艺 | |
JP2021050512A (ja) | 橋梁の架替工法および橋梁上部構造 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161123 |