CN106120811A - 一种基坑周边预防变形和纠偏施工方法 - Google Patents
一种基坑周边预防变形和纠偏施工方法 Download PDFInfo
- Publication number
- CN106120811A CN106120811A CN201610711033.6A CN201610711033A CN106120811A CN 106120811 A CN106120811 A CN 106120811A CN 201610711033 A CN201610711033 A CN 201610711033A CN 106120811 A CN106120811 A CN 106120811A
- Authority
- CN
- China
- Prior art keywords
- slip casting
- grouting
- grouting pipe
- row
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本发明涉及一种基坑周边预防变形和纠偏施工方法,包括如下步骤:定位放线、钻孔、预埋注浆管、封孔、制备浆液、注浆。本发明方法具有工期短、造价低、加固、纠偏效果好等特点,通过在基坑维护结构与被保护建(构)筑物之间设置三排注浆管,靠近建(构)筑物第一排注浆管用于开挖前土体加固;第二排注浆管用于开挖过程中纠偏,第三排注浆管用于开挖过程中应急使用;有效避免了由于基坑变形对建(构)筑物的影响。本发明方法注浆施工范围影响小、处理扩散范围大、加固、纠偏效果明显,且由于注浆是从被加固土体内部处理,具有改善土体内部的密实性和强度,达到纠偏补强的效果。
Description
技术领域
本发明属于建筑领域,尤其是一种基坑周边预防变形和纠偏施工方法。
背景技术
深基坑施工过程中,涉及周边邻近构筑物较近情况,尤其涉及老旧小区、地下构筑物等结构体系,需要进行较严格的设计及施工,避免施工过程中基坑变形。如果处理不得当或未经重视,造成不均匀沉降使构筑物受力变化、裂缝倒塌、引起工程事故。
深基坑施工为避免基坑变形,往往采取H型钢、重力式挡土墙、灌注桩、地连墙等竖向防护体系与水平混凝土、钢结构支撑体系配合使用,但这些方法均为施工前防护,对于施工过程中造成的基坑变形则无法进行弥补、修复。
发明内容
本发明的目的在于克服现有技术的不足,提供一种基坑周边预防变形和纠偏施工方法,该方法施工简单、加固效果好、具有纠偏功能。
本发明的方案是这样实现的:
一种基坑周边预防变形和纠偏施工方法,包括如下步骤:
步骤一、定位放线
根据设计图纸,在对应构筑物的深基坑边角处,利用经纬仪、钢卷尺进行桩位定位放样布三排且呈直角结构的钻孔,钻孔位置采用交错布置放线,相邻三个钻孔采用正三角结构布置,如图2、图3所示;
步骤二、钻孔
采用钻机制作注浆孔,按设置图纸制作三排注浆孔,注浆孔的孔深超过被保护构筑物基底一段距离;
步骤三、预埋注浆管
注浆孔内预埋注浆管,注浆管的下端部至注浆孔的底部,最上节注浆管应保护好丝扣以便于与注浆枪连接;
步骤四、封孔
注浆管应露出地面15cm左右,并将注浆管的顶部进行封口,防止异物进入;
步骤五、制备浆液
利用砂浆搅拌机拌制浆液,浆液必须经过搅拌机充分搅拌均匀后(不少于3min)才能开始压注,并应在搅拌过程中不停顿缓慢搅拌,搅拌时间应不大于浆液初凝时间;
步骤六、注浆
(1)注浆前,应对搅拌罐、注浆泵、注浆管等进行检验;
(2)大面积注浆施工前根据“试注浆”所取得的注浆量、注浆压力、注浆时间、水灰比等参数调整设计;
(3)注浆时,搅拌罐和注浆泵、水泥等均置于施工区域外;
(4)注浆采用分段注浆,即注浆阀下到设计深度后开始注浆,达到设计要求后上提注浆阀深度开始第二段注浆,以此类推至顶部。
而且,所述步骤四钻孔完成后,在注浆孔的外围制出沉积坑。
而且,注浆孔的孔深超过被保护构筑物基底5m。
而且,所述步骤六(4)中,分段注浆采用1.0m至2.0m为一段,从下向上注浆。
本发明的优点和积极效果是:
1、本发明方法具有工期短、造价低、加固、纠偏效果好等特点,通过在基坑维护结构与被保护建(构)筑物之间设置三排注浆管,有效避免了由于基坑变形对建(构)筑物的影响。
2、本发明方法注浆施工范围影响小、处理扩散范围大、加固、纠偏效果明显,且由于注浆是从被加固土体内部处理,具有改善土体内部的密实性和强度,达到纠偏补强的效果。
附图说明
图1是本发明的工作流程图;
图2是本发明钻孔布置图;
图3是本发明平面布置示意图;
图4是本发明土体加固剖面示意图。
具体实施方式
下面结合附图并通过具体实施例对本发明作进一步详述。
一种基坑周边预防变形和纠偏施工方法,如图1所示,包括如下步骤:
步骤一、定位放线
根据设计图纸,在对应构筑物的深基坑边角处,利用经纬仪、钢卷尺进行桩位定位放样布三排且呈直角结构的钻孔,钻孔位置采用交错布置放线,相邻三个钻孔采用正三角结构布置,如图2、图3所示;
步骤二、钻孔
如图3所示,制作三排注浆孔1,注浆孔的孔深超过被保护建(构)筑物基底A为5m;
步骤三、预埋注浆管
注浆孔内预埋注浆管,注浆管的下端部至注浆孔的底部,最上节注浆管应保护好丝扣以便于与注浆枪连接,如图3所示;
步骤四、封孔
注浆管应露出地面15cm左右,并将注浆管的顶部进行封口,防止异物进入;
步骤五、制备浆液
利用砂浆搅拌机拌制浆液,严格按照设计认可的配合比拌制水泥浆,配备浆液的所有组分必须经过计量,浆液必须经过搅拌机充分搅拌均匀后(不少于3min)才能开始压住,并应在搅拌过程中不停顿缓慢搅拌,搅拌时间应不大于浆液初凝时间;
步骤六、注浆
(1)注浆前,应对搅拌罐、注浆泵、注浆管等进行检验;将吸浆管放入储浆池,检查各管路连接好后,开动注浆泵,缓缓加压,增大进浆量,注意压力变化。在注浆过程中,应设立专人不断搅动储浆池中的浆液,密切注意压力表、吸浆量及孔口周围情况的变化,一旦出现堵管现象,应立即停止注浆,清洗疏通注浆管后再注;
(2)大面积注浆施工前应根据“试注浆”所取得的注浆量、注浆压力、注浆时间、水灰比等参数调整设计,指导本工程的施工。
(3)注浆时,搅拌罐和注浆泵、水泥等均置于施工区域外;
(4)注浆采用分段注浆,一般采用1.0m~2.0m一段,原则上从下向上注浆,即注浆阀下到设计深度后开始注浆,达到设计要求后上提注浆阀深度开始第二段注浆,以此类推至顶部。
本实施例中,在完成步骤四的钻孔后,可在注浆孔的外围制出沉积坑2,防止多余的浆液外流;
三排注浆管注浆分三种情况,靠近建(构)筑物第一排注浆管用于开挖前土体加固;第二排注浆管用于开挖过程中纠偏,第三排注浆管用于开挖过程中应急使用;
本发明的注浆顺序及注浆终止条件
施工顺序应遵循先施工加固区外排的注浆孔即沉积坑(起挡墙作用)、后逐步施工中部注浆孔的施工顺序;靠近建(构)筑物第一排注浆管用于开挖前土体加固,第二排注浆管用于开挖过程中纠偏,第三排注浆管用于开挖过程中应急使用;同排注浆孔采取间隔跳跃式进行注浆;注浆以注浆孔喷浆、达到注浆压力值、达到注浆量或注浆压力突增作为该孔停注的标准;注浆顺序为由下向上注浆,注浆孔的注浆提距为1.0m~2.0m。
安全措施
1、建立健全各种岗位责任制,严格执行现场交接制度。
2、钻机注浆泵及高压管路必须试运转,确认机械性能和各种阀门管路,压力表完好后,方准施工。
3、每次注浆前,要认真检查安全阀、压力表的灵敏度,并调整到规定注浆压力位置。
4、安装高压管路和泵头各部件时,各丝扣的联接必须拧紧,确保联接完好。
5、注浆过程中,禁止现场人员在注浆孔附近停留,防止密封胶冲式阀门破裂伤人。
6、注浆时不得随意停水停电,必要时必须事先通知,待注浆完成并冲洗后方可停水停电。
7、注浆施工期间,必须有专门机电修理工,以便出现机械和电器故障时能及时处理。
8、注浆现场操作人员必须佩戴安全帽、防护眼镜、口罩和手套等劳保用品,方可进行注浆施工。
需要强调的是,本发明所述的实施例是说明性的,而不是限定性的,因此本发明包括并不限于具体实施方式中所述的实施例,凡是由本领域技术人员根据本发明的技术方案得出的其他实施方式,同样属于本发明保护的范围。
Claims (4)
1.一种基坑周边预防变形和纠偏施工方法,其特征在于:包括如下步骤:
步骤一、定位放线
根据设计图纸,在对应构筑物的深基坑边角处,利用经纬仪、钢卷尺进行桩位定位放样布三排且呈直角结构的钻孔,钻孔位置采用交错布置放线,相邻三个钻孔采用正三角结构布置;
步骤二、钻孔
采用钻机制作注浆孔,按设置图纸制作三排注浆孔,注浆孔的孔深超过被保护构筑物基底一段距离;
步骤三、预埋注浆管
注浆孔内预埋注浆管,注浆管的下端部至注浆孔的底部,最上节注浆管应保护好丝扣以便于与注浆枪连接;
步骤四、封孔
注浆管应露出地面15cm左右,并将注浆管的顶部进行封口,防止异物进入;
步骤五、制备浆液
利用砂浆搅拌机拌制浆液,浆液必须经过搅拌机充分搅拌均匀后(不少于3min)才能开始压注,并应在搅拌过程中不停顿缓慢搅拌,搅拌时间应不大于浆液初凝时间;
步骤六、注浆
(1)注浆前,应对搅拌罐、注浆泵、注浆管等进行检验;
(2)大面积注浆施工前根据“试注浆”所取得的注浆量、注浆压力、注浆时间、水灰比等参数调整设计;
(3)注浆时,搅拌罐和注浆泵、水泥等均置于施工区域外;
(4)注浆采用分段注浆,即注浆阀下到设计深度后开始注浆,达到设计要求后上提注浆阀深度开始第二段注浆,以此类推至顶部。
2.根据权利要求1所述的一种基坑周边预防变形和纠偏施工方法,其特征在于:所述步骤四钻孔完成后,在注浆孔的外围制出沉积坑。
3.根据权利要求1所述的一种基坑周边预防变形和纠偏施工方法,其特征在于:注浆孔的孔深超过被保护构筑物基底5m。
4.根据权利要求1所述的一种基坑周边预防变形和纠偏施工方法,其特征在于:所述步骤六(4)中,分段注浆采用1.0m至2.0m为一段,从下向上注浆。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610711033.6A CN106120811A (zh) | 2016-08-24 | 2016-08-24 | 一种基坑周边预防变形和纠偏施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610711033.6A CN106120811A (zh) | 2016-08-24 | 2016-08-24 | 一种基坑周边预防变形和纠偏施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106120811A true CN106120811A (zh) | 2016-11-16 |
Family
ID=57273782
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610711033.6A Pending CN106120811A (zh) | 2016-08-24 | 2016-08-24 | 一种基坑周边预防变形和纠偏施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106120811A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836323A (zh) * | 2017-01-21 | 2017-06-13 | 叶长青 | 条形基础砖混建筑物的纠偏施工方法 |
CN110984145A (zh) * | 2019-12-06 | 2020-04-10 | 江苏长江机械化基础工程有限公司 | 管桩施工监测方法和监测设备 |
CN114232598A (zh) * | 2021-11-23 | 2022-03-25 | 广州市市政工程机械施工有限公司 | 一种保护既有建筑物/构筑物基础的注浆隔绝墙 |
CN116537159A (zh) * | 2023-04-21 | 2023-08-04 | 中建八局浙江建设有限公司 | 临近基坑的管道加固防沉降方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19935366A1 (de) * | 1998-07-29 | 2000-02-03 | Zueblin Ag | Wasserrückhaltende Baugrubenumschließung |
CN102433884A (zh) * | 2011-10-17 | 2012-05-02 | 同济大学建筑设计研究院(集团)有限公司 | 一种采用树根桩及桩侧挤密注浆的系统及设计方法 |
CN104074195A (zh) * | 2014-07-21 | 2014-10-01 | 浙江华展工程研究设计院有限公司 | 一种通过水平注浆控制基坑外地面沉降的方法 |
CN105862874A (zh) * | 2016-04-14 | 2016-08-17 | 浙江科技学院 | 一种控制临近基坑建构筑物变形的防护方法 |
-
2016
- 2016-08-24 CN CN201610711033.6A patent/CN106120811A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19935366A1 (de) * | 1998-07-29 | 2000-02-03 | Zueblin Ag | Wasserrückhaltende Baugrubenumschließung |
CN102433884A (zh) * | 2011-10-17 | 2012-05-02 | 同济大学建筑设计研究院(集团)有限公司 | 一种采用树根桩及桩侧挤密注浆的系统及设计方法 |
CN104074195A (zh) * | 2014-07-21 | 2014-10-01 | 浙江华展工程研究设计院有限公司 | 一种通过水平注浆控制基坑外地面沉降的方法 |
CN105862874A (zh) * | 2016-04-14 | 2016-08-17 | 浙江科技学院 | 一种控制临近基坑建构筑物变形的防护方法 |
Non-Patent Citations (3)
Title |
---|
夏明耀: "《地下工程设计施工手册》", 31 July 1999, 中国建筑工业出版社 * |
李连营等: "《新填土注浆加固处理实录》", 《施工技术》 * |
赵凤珍: "《深基坑周边建筑物地基的注浆加固技术》", 《铁道建筑》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836323A (zh) * | 2017-01-21 | 2017-06-13 | 叶长青 | 条形基础砖混建筑物的纠偏施工方法 |
CN106836323B (zh) * | 2017-01-21 | 2018-09-18 | 叶长青 | 条形基础砖混建筑物的纠偏施工方法 |
CN110984145A (zh) * | 2019-12-06 | 2020-04-10 | 江苏长江机械化基础工程有限公司 | 管桩施工监测方法和监测设备 |
CN110984145B (zh) * | 2019-12-06 | 2021-06-01 | 中煤长江基础建设有限公司 | 管桩施工监测方法和监测设备 |
CN114232598A (zh) * | 2021-11-23 | 2022-03-25 | 广州市市政工程机械施工有限公司 | 一种保护既有建筑物/构筑物基础的注浆隔绝墙 |
CN116537159A (zh) * | 2023-04-21 | 2023-08-04 | 中建八局浙江建设有限公司 | 临近基坑的管道加固防沉降方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105155569B (zh) | 一种后打桩海上风机基础的施工装置及施工方法 | |
CN110821503B (zh) | 一种超深盾构区间风井先隧后主体施工方法 | |
CN204491626U (zh) | 拉森钢板桩与预应力锚杆组合的基坑围护结构 | |
CN110700293B (zh) | 深水斜岩环境下旋挖引孔钢板桩围堰施工方法 | |
CN101691842B (zh) | 三臂液压凿岩台车及隧道钻孔注浆施工方法 | |
CN110005442A (zh) | 下穿既有建筑城市地下暗挖区间围岩加固工艺 | |
CN205172598U (zh) | 管幕旋喷桩支护结构 | |
CN110359467A (zh) | 一种基坑工程高压旋喷桩加固的施工方法 | |
CN104631470A (zh) | 高水位大粒径砂砾石地质深基坑组合支护施工方法 | |
CN104631475A (zh) | 一种下穿河流浅埋暗挖隧道的安全快速施工方法 | |
CN106120811A (zh) | 一种基坑周边预防变形和纠偏施工方法 | |
CN103410522A (zh) | 浅埋暗挖法连续近距离下穿铁路桥的施工方法 | |
CN104018512A (zh) | 对环境微扰动的沉井下沉施工方法 | |
CN106120797B (zh) | 富水区连续钢构渡槽墩地基灌浆施工方法 | |
CN109898521A (zh) | 一种用于基坑阳角的桩锚支护结构及施工方法 | |
CN106245655A (zh) | 利用微型钢管桩的深基坑支护施工方法 | |
CN102220764B (zh) | 深基坑支护体系的施工方法 | |
CN103174135B (zh) | 不达标后注浆灌注桩的修补方法 | |
CN105220719A (zh) | 深厚软土地区桥梁灌注桩纠偏方法 | |
CN103343534A (zh) | 基坑施工封闭降水方法 | |
CN103114602B (zh) | 渗透浸渍聚凝粘结体二次融补的基坑止水帷幕及构建方法 | |
CN111560964B (zh) | 一种基坑后防渗体系施工方法 | |
CN205000332U (zh) | 一种后打桩海上风机基础施工装置与桩套管连接结构 | |
CN108894247A (zh) | 一种地铁联络通道周边土体高压旋喷加固结构及施工方法 | |
CN204825955U (zh) | 一种后打桩海上风机基础的施工装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161116 |
|
RJ01 | Rejection of invention patent application after publication |