CN105863245A
CN105863245A CN201610336370.1A CN201610336370A CN105863245A CN 105863245 A CN105863245 A CN 105863245A CN 201610336370 A CN201610336370 A CN 201610336370A CN 105863245 A CN105863245 A CN 105863245A
Authority
CN
China
Prior art keywords
positioning sleeve
vertical rod
type scaffold
cross bar
inserted block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610336370.1A
Other languages
Chinese (zh)
Inventor
朱强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yeqiang Scaffold Science & Technology Development Co Ltd
Original Assignee
Jiangsu Yeqiang Scaffold Science & Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yeqiang Scaffold Science & Technology Development Co Ltd filed Critical Jiangsu Yeqiang Scaffold Science & Technology Development Co Ltd
Priority to CN201610336370.1A priority Critical patent/CN105863245A/en
Publication of CN105863245A publication Critical patent/CN105863245A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/20Stiff scaffolding clamps for connecting scaffold members of common shape for ends of members only, e.g. for connecting members in end-to-end relation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/22Stiff scaffolding clamps for connecting scaffold members of common shape for scaffold members in end-to-side relation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The invention discloses a straight inserting type scaffold, which is characterized by comprising a transverse rod and a vertical rod, wherein the two ends of the transverse rod are provided with arc-shaped inserting blocks fit in with the vertical rod; the upper end of the vertical rod is provided with an upper positioning sleeve; the lower end of the vertical rod is provided with a lower positioning sleeve; a cavity is arranged between the upper and lower positioning sleeves and the vertical rod; the arc-shaped inserting blocks can be inserted into the cavity; arc-shaped notches matched with the transverse rod are formed in the upper positioning sleeve and the lower positioning sleeve. The straight inserting type scaffold has the advantages that the safety is greatly enhanced; the installation convenience is ensured; meanwhile, the safety performance is improved.

Description

A kind of direct plugging type scaffold
Technical field
The present invention relates to building implement field, especially relate to a kind of direct plugging type scaffold.
Background technology
Scaffold refers to that job site is operative and solves vertically and horizontally to transport the various supports set up.The generic term on building circle, refers to be used in the higher place that cannot directly construct of exterior wall, inside fitting or floor height on construction site.Working up and down mainly for workmen or perimeter security net is gone along with sb. to guard him and high-altitude installation component etc., build a framework the most exactly, scaffold makes material generally to be had: bamboo and wood, steel pipe or synthetic material etc..Some engineering also uses when template with scaffold, and the department such as this external advertising, municipal administration, traffic road and bridge, mine is the most extensively used.
The steel pipe scaffold that traditional pin hand cradle uses in a large number mainly has fastener type and the big class of bowl fastening type two, but owing to the reasons such as design principle, geometry, material selection and manufacturing process exist many weak points, such as overlap, to dismantle speed slow, low in conjunction with rigidity, safety and stability is poor, and spare and accessory parts easily lose damage.
It is more convenient that the direct plugging type scaffold of prior art makes scaffold install by the cooperation of wheel disc and plug, but the direct plugging type scaffold of prior art lacks safety, complete consolidating by scaffold own wt guarantee scaffold, there is severe compromise.
Summary of the invention
Problem to be solved by this invention is, for above-mentioned shortcoming of the prior art, proposes innovation scheme, especially a kind of direct plugging type scaffold.
For solving the problems referred to above, the scheme that the present invention uses is as follows: a kind of direct plugging type scaffold, it is characterised in that include that cross bar and vertical rod, the two ends of described cross bar are provided with the arc inserted block suited with vertical rod;The upper end of described vertical rod is provided with positioning sleeve;The lower end of described vertical rod is provided with lower positioning sleeve;Described upper positioning sleeve and lower be provided with cavity between positioning sleeve and vertical rod;Described arc inserted block is inserted in cavity;Described upper positioning sleeve and lower positioning sleeve are equipped with the arc notch mated with cross bar.
Further, according to direct plugging type scaffold described in above-mentioned design, described upper positioning sleeve highlights vertical rod upper end one segment length a;Prominent lower positioning sleeve one segment length b in the lower end of described vertical rod;Described length a is identical with length b.
Further, according to direct plugging type scaffold described in above-mentioned design, described arc inserted block is threadeded with cross bar.
Further, according to direct plugging type scaffold described in above-mentioned design, the indent side of described arc inserted block is provided with damping pad.
Further, according to direct plugging type scaffold described in above-mentioned design, described damping pad is rubber sheet gasket.
Further, according to direct plugging type scaffold described in above-mentioned design, described damping pad is connected by adhesion agent and arc inserted block are fixing.
Further, according to direct plugging type scaffold described in above-mentioned design, the two ends up and down of described vertical rod are provided with the toothing being mutually matched.
The technique effect of the present invention is as follows: the direct plugging type scaffold of the present invention is provided with positioning sleeve at the two ends of vertical rod, cavity is formed between positioning sleeve and vertical rod, for placing the arc inserted block at cross bar two ends, and the upper positioning sleeve cooperation of the rainy positioning sleeve vertical rod upper end of the lower end of vertical rod is utilized to be fixed by cross bar.
Accompanying drawing explanation
Fig. 1 is direct plugging type scaffold link position structural representation.
Fig. 2 is direct plugging type scaffold link position decomposing schematic representation.
Fig. 3 is cross bar front view and top view.
Fig. 4 is vertical rod sectional view.
Wherein, 1 is vertical rod;2 is cross bar;3 is upper positioning sleeve;4 is lower positioning sleeve;5 is arc inserted block;6 is arc notch.
Detailed description of the invention
Below in conjunction with the accompanying drawings the present invention is described in further details.
Embodiment 1: a kind of direct plugging type scaffold, including cross bar 2 and vertical rod 1, the two ends of described cross bar 2 are provided with the arc inserted block 5 suited with vertical rod 1;The upper end of described vertical rod 1 is provided with positioning sleeve 3;The lower end of described vertical rod 1 is provided with lower positioning sleeve 4;It is provided with cavity between described upper positioning sleeve 3 and lower positioning sleeve 4 and vertical rod 1;Described arc inserted block 5 is inserted in cavity;Described upper positioning sleeve 3 and lower positioning sleeve 4 are equipped with the arc notch 6 mated with cross bar 2.
Embodiment 2: a kind of direct plugging type scaffold, including cross bar 2 and vertical rod 1, the two ends of described cross bar 2 are provided with the arc inserted block 5 suited with vertical rod 1;The upper end of described vertical rod 1 is provided with positioning sleeve 3;The lower end of described vertical rod 1 is provided with lower positioning sleeve 4;It is provided with cavity between described upper positioning sleeve 3 and lower positioning sleeve 4 and vertical rod 1;Described arc inserted block 5 is inserted in cavity;Described upper positioning sleeve 3 and lower positioning sleeve 4 are equipped with the arc notch 6 mated with cross bar 2, and described upper positioning sleeve 3 highlights vertical rod 1 upper end one segment length a;Prominent lower positioning sleeve 4 one segment length b in the lower end of described vertical rod 1;Described length a is identical with length b.
Embodiment 3: a kind of direct plugging type scaffold, including cross bar 2 and vertical rod 1, the two ends of described cross bar 2 are provided with the arc inserted block 5 suited with vertical rod 1;The upper end of described vertical rod 1 is provided with positioning sleeve 3;The lower end of described vertical rod 1 is provided with lower positioning sleeve 4;It is provided with cavity between described upper positioning sleeve 3 and lower positioning sleeve 4 and vertical rod 1;Described arc inserted block 5 is inserted in cavity;Described upper positioning sleeve 3 and lower positioning sleeve 4 are equipped with the arc notch 6 mated with cross bar 2, and described arc inserted block 5 is threadeded with cross bar 2.
Embodiment 4: a kind of direct plugging type scaffold, including cross bar 2 and vertical rod 1, the two ends of described cross bar 2 are provided with the arc inserted block 5 suited with vertical rod 1;The upper end of described vertical rod 1 is provided with positioning sleeve 3;The lower end of described vertical rod 1 is provided with lower positioning sleeve 4;It is provided with cavity between described upper positioning sleeve 3 and lower positioning sleeve 4 and vertical rod 1;Described arc inserted block 5 is inserted in cavity;Described upper positioning sleeve 3 and lower positioning sleeve 4 are equipped with the arc notch 6 mated with cross bar 2, and the indent side of described arc inserted block 5 is provided with damping pad.
Embodiment 5: a kind of direct plugging type scaffold, including cross bar 2 and vertical rod 1, the two ends of described cross bar 2 are provided with the arc inserted block 5 suited with vertical rod 1;The upper end of described vertical rod 1 is provided with positioning sleeve 3;The lower end of described vertical rod 1 is provided with lower positioning sleeve 4;It is provided with cavity between described upper positioning sleeve 3 and lower positioning sleeve 4 and vertical rod 1;Described arc inserted block 5 is inserted in cavity;Described upper positioning sleeve 3 and lower positioning sleeve 4 are equipped with the arc notch 6 mated with cross bar 2, and the indent side of described arc inserted block 5 is provided with damping pad, and described damping pad is connected by adhesion agent is fixing with arc inserted block 5.

Claims (7)

1. a direct plugging type scaffold, it is characterised in that include that cross bar and vertical rod, the two ends of described cross bar are provided with the arc inserted block suited with vertical rod;The upper end of described vertical rod is provided with positioning sleeve;The lower end of described vertical rod is provided with lower positioning sleeve;Described upper positioning sleeve and lower be provided with cavity between positioning sleeve and vertical rod;Described arc inserted block is inserted in cavity;Described upper positioning sleeve and lower positioning sleeve are equipped with the arc notch mated with cross bar.
Direct plugging type scaffold the most according to claim 1, it is characterised in that described upper positioning sleeve highlights vertical rod upper end one segment length a;Prominent lower positioning sleeve one segment length b in the lower end of described vertical rod;Described length a is identical with length b.
Direct plugging type scaffold the most according to claim 1, it is characterised in that described arc inserted block is threadeded with cross bar.
Direct plugging type scaffold the most according to claim 1, it is characterised in that the indent side of described arc inserted block is provided with damping pad.
Direct plugging type scaffold the most according to claim 4, it is characterised in that described damping pad is rubber sheet gasket.
Direct plugging type scaffold the most according to claim 4, it is characterised in that described damping pad is connected by adhesion agent and arc inserted block are fixing.
Direct plugging type scaffold the most according to claim 1, it is characterised in that the two ends up and down of described vertical rod are provided with the toothing being mutually matched.
CN201610336370.1A 2016-05-20 2016-05-20 Straight inserting type scaffold Pending CN105863245A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610336370.1A CN105863245A (en) 2016-05-20 2016-05-20 Straight inserting type scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610336370.1A CN105863245A (en) 2016-05-20 2016-05-20 Straight inserting type scaffold

Publications (1)

Publication Number Publication Date
CN105863245A true CN105863245A (en) 2016-08-17

Family

ID=56634417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610336370.1A Pending CN105863245A (en) 2016-05-20 2016-05-20 Straight inserting type scaffold

Country Status (1)

Country Link
CN (1) CN105863245A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854704A (en) * 2021-03-22 2021-05-28 王泽伟 Quick-insertion combined scaffold for building engineering

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2527711A1 (en) * 1982-05-28 1983-12-02 Select Etem Sa Scaffolding connection point - has locating rings welded on posts with locations for the cross members
CN1043764A (en) * 1988-12-28 1990-07-11 小野辰雄 The method and the support system that connect supporting mass
CN2190680Y (en) * 1994-03-29 1995-03-01 北京市比尔特施工新技术研究所 Wedge fastening joint of scaffold
CN1202590A (en) * 1997-06-12 1998-12-23 日钢计划株式会社 Pipe connecting joint
CN1388296A (en) * 2001-05-29 2003-01-01 于杰 Fast butt joint fastener
CN2793215Y (en) * 2005-01-26 2006-07-05 董国荣 Safety butt buckle of scaffold with steel pipe
CN205742975U (en) * 2016-05-20 2016-11-30 江苏业强脚手架科技发展有限公司 A kind of direct plugging type scaffold

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2527711A1 (en) * 1982-05-28 1983-12-02 Select Etem Sa Scaffolding connection point - has locating rings welded on posts with locations for the cross members
CN1043764A (en) * 1988-12-28 1990-07-11 小野辰雄 The method and the support system that connect supporting mass
CN2190680Y (en) * 1994-03-29 1995-03-01 北京市比尔特施工新技术研究所 Wedge fastening joint of scaffold
CN1202590A (en) * 1997-06-12 1998-12-23 日钢计划株式会社 Pipe connecting joint
CN1388296A (en) * 2001-05-29 2003-01-01 于杰 Fast butt joint fastener
CN2793215Y (en) * 2005-01-26 2006-07-05 董国荣 Safety butt buckle of scaffold with steel pipe
CN205742975U (en) * 2016-05-20 2016-11-30 江苏业强脚手架科技发展有限公司 A kind of direct plugging type scaffold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854704A (en) * 2021-03-22 2021-05-28 王泽伟 Quick-insertion combined scaffold for building engineering

Similar Documents

Publication Publication Date Title
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN205742975U (en) A kind of direct plugging type scaffold
CN203821821U (en) Crossed connecting piece for steel pipe scaffold
CN102995916A (en) Safe and practical tread board for realizing simple and convenient disassembly and assembly of temporary staircase in construction site
CN105863245A (en) Straight inserting type scaffold
CN205025081U (en) Take formula that cut straightly scaffold of safety lock
CN104372923B (en) Scaffolding
CN205063333U (en) Modular bathroom falls board and hangs mould device
CN204608833U (en) Municipal administration manhole
CN204023417U (en) For building the bearing pin bracket of high pier 0# block concrete
CN204152527U (en) The combined type preliminary bracing system of wall multiple-arch tunnel in implicit expression
CN204023422U (en) A kind of assembling Coping Construction operating platform
CN204960291U (en) Bracing piece of scaffold and fixed connection structure and scaffold between connecting rod
CN206220649U (en) Construction guard fender
CN105863247A (en) Direct-plug type scaffold with locking block
CN205637554U (en) Construction scaffold puts up connection structure
CN204282817U (en) Door-window opening mould plate installs structure
CN204370828U (en) Tool-type protective screening
CN204082181U (en) A kind of mine support
CN203008409U (en) Safe and practical tread board for realizing simple and convenient disassembly and assembly of temporary staircase in construction site
CN205604841U (en) Railing
CN205025080U (en) Formula anti -drop scaffold cut straightly
CN203977857U (en) Concrete plate surface reserved holes of pipes capping tools formula erecting device
CN204152195U (en) A kind of scaffold fastenings
CN206174341U (en) Stair are support for guardrail

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication