[go: up one dir, main page]

CN105625568B - Assembly concrete orthogonal spatial space lattice boxlike tube-in-tube structure - Google Patents

Assembly concrete orthogonal spatial space lattice boxlike tube-in-tube structure Download PDF

Info

Publication number
CN105625568B
CN105625568B CN201511013604.0A CN201511013604A CN105625568B CN 105625568 B CN105625568 B CN 105625568B CN 201511013604 A CN201511013604 A CN 201511013604A CN 105625568 B CN105625568 B CN 105625568B
Authority
CN
China
Prior art keywords
grid
concrete
tube
floor
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201511013604.0A
Other languages
Chinese (zh)
Other versions
CN105625568A (en
Inventor
马克俭
徐鹏强
吴刚
令狐延
赵勇
王丰娟
朱九洲
张华刚
吴京
林力勋
何永安
李�杰
房海
魏艳辉
陈志鹏
白蓉
刁川
宋金涛
王维奇
李莉
姜岚
陆红娜
陈靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Prosperous Large Building Science And Technology Ltd
Southeast University
Guizhou University
China Construction Fourth Engineering Division Corp Ltd
Weifang Changda Construction Group Ltd
No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Original Assignee
Prosperous Large Building Science And Technology Ltd
Southeast University
Guizhou University
China Construction Fourth Engineering Division Corp Ltd
Weifang Changda Construction Group Ltd
No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Prosperous Large Building Science And Technology Ltd, Southeast University, Guizhou University, China Construction Fourth Engineering Division Corp Ltd, Weifang Changda Construction Group Ltd, No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group filed Critical Prosperous Large Building Science And Technology Ltd
Priority to CN201511013604.0A priority Critical patent/CN105625568B/en
Publication of CN105625568A publication Critical patent/CN105625568A/en
Application granted granted Critical
Publication of CN105625568B publication Critical patent/CN105625568B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明涉及一种装配式混凝土正交正放空间网格盒式筒中筒结构,横向空腹楼盖的网格与竖向网格式框架的网格相等,且彼此在交汇处刚性连接;楼盖与中央的钢筋混凝土核芯筒周边剪力墙,在空腹楼盖位置为刚性连接,楼盖与中央核芯筒剪力墙及与竖向网格式框架分别两两刚性连接成网格式盒式结构,网格式盒式结构与中央混凝土核心筒组成正交正放盒式筒中筒结构,横向空腹楼盖与竖向网格式框架单元化预制后,再分层安装;拼装节点后浇注混凝土量占总量的5%以内,大幅度降低模板使用量及工时,提高施工进度,工程造价整体下降20%左右。

The invention relates to a prefabricated concrete orthogonal space grid box-type tube-in-tube structure, the grid of the horizontal fasting floor is equal to the grid of the vertical grid frame, and they are rigidly connected at the intersection; The shear walls around the central reinforced concrete core tube are rigidly connected at the position of the hollow floor, and the floor is rigidly connected with the central core tube shear wall and the vertical grid frame respectively to form a grid box structure. The grid box structure and the central concrete core tube form an orthogonal box-type tube-in-tube structure. After the horizontal hollow floor and the vertical grid frame are prefabricated in units, they are then installed in layers; the amount of concrete poured after assembling the nodes accounts for the total Within 5% of the total, the amount of formwork used and man-hours are greatly reduced, the construction progress is improved, and the overall project cost is reduced by about 20%.

Description

装配式混凝土正交正放空间网格盒式筒中筒结构Prefabricated Concrete Orthogonal Space Grid Box Tube-in-Tube Structure

技术领域technical field

本发明涉及一种高层与超高层混凝土结构,具体地说,涉及一种装配式整体式混凝土正交正放空间网格盒式筒中筒结构,属于建筑技术领域。The invention relates to a high-rise and super-high-rise concrete structure, in particular to a prefabricated monolithic concrete orthogonal space grid box-type tube-in-tube structure, which belongs to the technical field of construction.

技术背景technical background

2014年住房和城乡建设部发布《装配式混凝土结构技术规程》(JGJ1-2014),主要是针对传统的混凝土结构,如框架、框.剪、框.筒等结构体系,如图1所示为传统的混凝土框架.核芯筒结构,其中央核芯筒剪力墙现场浇制,周边框架柱、梁、次梁及板为预制装配式,它由下到上,一层又一层将预制柱、梁在节点处设制后浇区,将钢筋连接后二次浇制混凝土形成整体。对于高层与超高层建筑,周边的框架梁和柱,往往是肥梁胖柱,轻者几吨,重者十几吨,并均为单根,运输、安装、制作难度大,对于超高层建筑采用传统结构体系进行装配整体式施工,很难降低工程造价达到节能减排的功效。In 2014, the Ministry of Housing and Urban-Rural Development issued the "Technical Regulations for Prefabricated Concrete Structures" (JGJ1-2014), mainly for traditional concrete structures, such as frame, frame. shear, frame. tube and other structural systems, as shown in Figure 1. Traditional concrete frame and core tube structure, the central core tube shear wall is cast on site, and the surrounding frame columns, beams, secondary beams and slabs are prefabricated. It is prefabricated layer by layer from bottom to top. Post-cast areas are set at the joints of the columns and beams, and the concrete is poured twice after the steel bars are connected to form a whole. For high-rise and super high-rise buildings, the surrounding frame beams and columns are often fat beams and columns, the light ones are several tons, the heavy ones are more than ten tons, and they are all single. It is difficult to transport, install and manufacture. For super high-rise buildings, traditional It is difficult to reduce the project cost to achieve the effect of energy saving and emission reduction if the structural system is assembled in an integrated construction.

发明内容Contents of the invention

本发明要解决的问题是针对以上不足,提供一种装配式整体式混凝土正交正放空间网格盒式筒中筒结构及制作方法,采用该结构后及方法后,实现了以下目的:The problem to be solved by the present invention is to address the above deficiencies, and to provide a prefabricated integral concrete orthogonal space grid box-type tube-in-tube structure and manufacturing method. After adopting the structure and method, the following objectives are achieved:

1、建筑物实现单元化拼装。1. Buildings are unitized and assembled.

2、减少后浇混凝土工程量。2. Reduce the amount of post-cast concrete engineering.

3、提高施工质量,加快施工进度。3. Improve the construction quality and speed up the construction progress.

4、降低工程造价。4. Reduce project cost.

5、工厂预制,现场装配,文明施工。5. Factory prefabrication, on-site assembly, and civilized construction.

为解决以上技术问题,本发明采用以下技术方案:装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于:横向空腹楼盖的网格与竖向网格式框架的网格相等,且彼此在交汇处刚性连接;In order to solve the above technical problems, the present invention adopts the following technical solutions: prefabricated concrete orthogonal vertical space grid box-type tube-in-tube structure, characterized in that the grid of the horizontal hollow floor is equal to the grid of the vertical grid frame , and are rigidly connected to each other at the intersection;

横向空腹楼盖与竖向网格式框架单元化预制后,再分层安装。The horizontal hollow floor and the vertical grid frame are unitized and prefabricated, and then installed in layers.

一种优化方案,楼盖与中央的钢筋混凝土核芯筒周边剪力墙,在空腹楼盖位置为刚性连接。An optimized scheme, the floor and the shear wall around the central reinforced concrete core tube are rigidly connected at the location of the empty-web floor.

进一步地,楼盖与中央核芯筒剪力墙及与竖向网格式框架分别两两刚性连接成网格式盒式结构。Further, the floor is rigidly connected with the shear wall of the central core tube and the vertical grid frame respectively to form a grid box structure.

进一步地,网格式盒式结构与中央混凝土核心筒组成正交正放盒式筒中筒结构。Further, the grid box structure and the central concrete core tube form an orthogonal and positive box-type tube-in-tube structure.

基于以上装配式混凝土正交正放空间网格盒式筒中筒结构,该装配式混凝土正交正放空间网格盒式筒中筒结构的制作方法包括:Based on the above-mentioned prefabricated concrete orthogonally placed space grid box-type tube-in-tube structure, the manufacturing method of the fabricated concrete orthogonally placed space grid box-type tube-in-tube structure includes:

将竖向网格式框架和横向空腹网格楼盖分别划分为若干网格单元,然后预制成拼装单元,再在施工现场分层安装。Divide the vertical grid frame and the horizontal hollow grid floor into several grid units, and then prefabricate the assembled units, and then install them layer by layer at the construction site.

进一步地,预制工程量占总工程量的85%。Further, the prefabrication engineering volume accounts for 85% of the total engineering volume.

进一步地,在现场由下向上分层浇制中央混凝土核芯筒;Further, the central concrete core tube is poured layer by layer from bottom to top on site;

混凝土核芯筒内设置塔吊,作拼装单元吊装、安装使用。A tower crane is installed inside the concrete core tube for hoisting and installation of assembled units.

进一步地,核芯筒施工2-3层后,先将周边竖向网格式框架拼装单元进行安装,每一层网格框架柱在楼盖标高均预制45°拼装悬臂短梁,在此处与楼盖45°夹角空腹梁拼接,墙架安装时设置安装架;Furthermore, after the construction of 2-3 floors of the core tube, the surrounding vertical grid frame assembly units are installed first, and the grid frame columns of each floor are prefabricated at 45° to assemble short cantilever beams at the floor level. The 45° included angle of the floor is spliced with hollow beams, and the installation frame is installed when the wall frame is installed;

每一层周边网格式框架安装就位后,分层安装混凝土空腹网格预制单元,塔吊吊装就位后,设置支撑架在每一节位置支撑就位。After the surrounding grid frame of each layer is installed in place, the concrete hollow grid prefabricated units are installed layer by layer. After the tower crane is hoisted in place, the support frame is set to support in place at each section.

进一步地,在方形网格空腹楼盖支托处,安放四点支承钢筋桁架楼承板,仅在拼接位置设置模板。Further, a four-point-supported reinforced truss floor deck is placed at the support of the square grid hollow floor, and the formwork is only set at the splicing position.

进一步地,在节点位置剪力键纵筋及上弦上部钢筋均穿入预留箍筋内,再在网格四角支托位置搁置钢筋桁架楼承板,再将空腹梁上弦上部纵向钢筋设置预留箍筋内,拼装单元与拼装单元之间上、下弦杆拼接位置纵向钢筋连接,当上、下弦拼接位置模板安装后,拼接处及楼承板处一次性后浇高一级混凝土,空腹网格单元与楼承板二次浇制混凝土后形成楼盖整体,中部留出水平管线铺设的夹层,当竖向与横向混凝土网格拼接位置后浇混凝土养护完成,即形成混凝土正交正放空间网格盒式筒中筒结构。Further, at the node position, the longitudinal reinforcement of the shear key and the upper reinforcement of the upper chord are all penetrated into the reserved stirrups, and then the reinforced truss floor deck is placed at the support position of the four corners of the grid, and then the longitudinal reinforcement of the upper chord of the vierendeel beam is set to be reserved. Inside the stirrups, the upper and lower chord splicing positions between the assembled units are connected with longitudinal steel bars. After the formwork is installed at the upper and lower chord splicing positions, the joints and floor decks are poured with a one-time post-poured concrete, and the hollow grid After the unit and the floor deck are poured concrete twice, the floor is formed as a whole, and the interlayer for laying horizontal pipelines is left in the middle. When the vertical and horizontal concrete grids are spliced, the concrete is poured and cured, and the concrete is formed. Orthogonal space network Box-in-tube structure.

本发明采用以上技术方案,与现有技术相比,具有以下优点:The present invention adopts the above technical scheme, and compared with the prior art, has the following advantages:

1、本发明建筑结构的横向正交正放空腹楼盖的网格与竖向网格式框架网格相等,且彼此在交汇处刚性连接,形成空间网格盒式结构的力学模型,从而使结构体系的力学性能和抗侧刚度得到大幅度提升,从而实现将横向空腹楼盖与竖向网格式框架单元化预制后,再分层安装。1. The grid of the horizontally orthogonal and vertical hollow floor of the building structure of the present invention is equal to the grid of the vertical grid frame, and they are rigidly connected at the intersection to form a mechanical model of the space grid box structure, so that the structure The mechanical properties and lateral stiffness of the system have been greatly improved, so that the horizontal hollow floor and the vertical grid frame can be prefabricated and then installed in layers.

2、由于预制单元网格化后,构件截面尺寸小,自重轻,单元覆盖面积大,拼装节点后浇注混凝土量占总量的5%以内。2. After the prefabricated unit is meshed, the cross-sectional size of the component is small, the weight is light, and the unit coverage area is large. The amount of concrete poured after assembling the joints accounts for less than 5% of the total.

3、预制构件亦网格化,整体性和空间作用增强,装配构件覆盖建筑面积亦大,除中央核芯筒仍为现场浇制(15%),其余大面积(85%)构件均为预制装配式,在预制场制作,按国家行业标准(JGJ1-2014)进行预制装配整体式施工,在拼接部位等强连接钢筋后,二次浇注混凝土连为整体,大幅度减小现场浇注混凝土工作量,仅在拼接位置设置模板,大幅度降低模板使用量及工时,提高施工进度,节约模板促进建筑工业化的发展。3. The prefabricated components are also gridded, the integrity and spatial effect are enhanced, and the building area covered by the assembled components is also large. Except for the central core tube which is still cast on site (15%), the rest of the large-area (85%) components are prefabricated Prefabricated type, manufactured in the prefabrication field, prefabricated assembly integral construction according to the national industry standard (JGJ1-2014), after the splicing parts are strongly connected to the steel bars, the secondary pouring concrete is connected as a whole, which greatly reduces the workload of on-site pouring concrete , Only set the formwork at the splicing position, greatly reduce the amount of formwork usage and man-hours, improve the construction progress, save formwork and promote the development of construction industrialization.

4、工程造价整体下降20%左右。4. The overall project cost decreased by about 20%.

5、相比传统的混凝土框架、核芯筒结构体系抗侧刚度提高20%-25%。5. Compared with the traditional concrete frame and core tube structure system, the lateral stiffness is increased by 20%-25%.

6、减小了楼盖的厚度,在塔楼最大高度及楼层净高相同的条件下,降低了层高,增加了塔楼的层数。6. The thickness of the floor is reduced. Under the condition that the maximum height of the tower and the net height of the floors are the same, the storey height is reduced and the number of floors of the tower is increased.

7、楼盖厚度δ=(1/25-1/30)L(进深),室内房间可自由划分,不受“有墙必有梁”的限制,板中央空腹可穿越水平管线。7. The thickness of the floor δ=(1/25-1/30)L (depth), the indoor rooms can be divided freely, not subject to the restriction of "where there are walls, there must be beams", and the hollow center of the slab can pass through the horizontal pipeline.

下面结合附图和实施例对本发明作进一步说明。The present invention will be further described below in conjunction with drawings and embodiments.

附图说明Description of drawings

附图1为传统的高层与超高层写字楼建筑中混凝土框架核芯筒结构的标准层结构布置图;Accompanying drawing 1 is the standard floor structure layout diagram of concrete frame core tube structure in traditional high-rise and super high-rise office buildings;

附图2为本发明高层与超高层写字楼建筑中混凝土正交正放空间网格盒式筒中筒结构的标准层结构布置图;Accompanying drawing 2 is the standard floor structure layout diagram of the concrete orthogonally placed space grid box-type tube-in-tube structure in high-rise and super high-rise office buildings of the present invention;

附图3为图2中预制网格单元布置图,A1与A2单元几何尺寸相同,但配筋不同;Accompanying drawing 3 is the layout diagram of the prefabricated grid unit in Figure 2, A1 and A2 unit geometric dimensions are the same, but the reinforcement is different;

附图4为图3中预制混凝土A1、A2网格空腹单元平面几何尺寸图,支托为搁置钢筋桁架楼承板的支承点;Accompanying drawing 4 is the plane geometric dimension drawing of prefabricated concrete A1, A2 mesh fasting unit in Fig. 3, and the supporting bracket is the supporting point for laying down the steel bar truss floor deck;

附图5为本发明中楼盖每个网格的钢筋桁架楼承板平面及剖面图;Accompanying drawing 5 is the steel bar truss floor deck plane and the section view of each grid of the floor in the present invention;

附图6为图4中A单元正交的A节点细部构造;Accompanying drawing 6 is the detail structure of A node orthogonal to A unit in Fig. 4;

附图7为图6中A节点剖面构造,上弦箍筋在预制件上预留,楼承板安装并补扎钢筋后浇制高一级混凝土;Attached drawing 7 is the section structure of joint A in Figure 6, the upper chord stirrups are reserved on the prefabricated parts, the floor deck is installed and the steel bars are patched, and then the higher level concrete is poured;

附图8为本发明中混凝土空腹网格单元与楼承板二次浇制混凝土后形成的楼盖整体;Accompanying drawing 8 is the entire floor formed after the concrete hollow grid unit and the floor slab are poured concrete twice in the present invention;

附图9为附图8中A节点及B节点细部构造,用细点表示后浇混凝土部位,粗虚线为预制构件内钢筋;Accompanying drawing 9 is the detailed structure of A node and B node in Fig. 8, the post-cast concrete parts are indicated by thin dots, and the thick dotted line is the internal reinforcement of prefabricated components;

附图10为本发明中高层与超高层(100m≤H≤216m)装配整体式混凝土正交正放空间网格盒式筒中筒结构,外部网格式框架预制单元A、B布置简图;Accompanying drawing 10 is the middle and super high-rise (100m ≤ H ≤ 216m) assembled integral concrete orthogonal vertical space grid box-in-tube structure of the present invention, and a schematic layout diagram of the external grid frame prefabricated units A and B;

附图11为图10中预制混凝土网格A单元构造图。Accompanying drawing 11 is the structural diagram of unit A of prefabricated concrete grid in Fig. 10.

具体实施方式Detailed ways

实施例1,如图2所示,混凝土正交正放空间网格盒式结构筒中筒结构,若仍采用现场浇制,模板工作量大,虽然均是小构件,但节点数量大幅度增加,如图2每增楼盖混凝土节点量是图1所示结构3倍以上,若仍然采用现场浇制模板量大,耗工耗时,若采用预制装配整体式施工方法,将达到事半功倍的功效。Example 1, as shown in Figure 2, if the concrete is placed in a vertically spaced grid box-type tube-in-tube structure, if it is still cast on site, the workload of the formwork will be large. Although they are all small components, the number of nodes will increase significantly. As shown in Figure 2, the amount of concrete joints for each additional floor is more than three times that of the structure shown in Figure 1. If the site-cast formwork is still used, the amount of labor and time is large, and if the prefabricated assembly integral construction method is used, it will achieve twice the result with half the effort.

图2所示混凝土正交正放空间网格盒式筒中筒结构,其横向混凝土空腹楼盖为a×a=2.8m×2.8m=9.84m2正方形空腹网格,其空腹梁中上、下弦有1/3与核芯筒混凝土剪力墙刚性连接,另2/3空腹梁彼此正交刚性连接,而空腹梁与四周的竖向网格式框架柱均一一对应刚性连接,框架柱网尺寸与空腹网格相等,即竖向网格与和横向网格组成空间网格盒式结构整体,具有板的特性,由于网格化,结构每一层楼盖的节点比图1所示常规结构的节点成倍数增加,再用常规现场浇制费工、费时、费材,为此采用装配整体式工业化工序,具体实施方式如下:As shown in Figure 2, the concrete orthogonal space grid box-type tube-in-tube structure has a horizontal concrete hollow floor with a×a=2.8m×2.8m=9.84m 2 square fasting grid, and the upper and lower chords of the hollow beam 1/3 is rigidly connected to the concrete shear wall of the core tube, and the other 2/3 of the vierendeel beams are rigidly connected to each other orthogonally, and the vierendeel beams are rigidly connected to the surrounding vertical grid frame columns in one-to-one correspondence. The size of the frame column grid It is equal to the fasting grid, that is, the vertical grid and the horizontal grid form a space grid box structure as a whole, which has the characteristics of a plate. Due to the grid, the nodes of each floor of the structure are smaller than those of the conventional structure shown in Figure 1. The nodes are multiplied, and then conventional on-site casting is labor-intensive, time-consuming, and material-intensive. For this purpose, an integrated industrial process of assembly is adopted. The specific implementation method is as follows:

1)预制件制作:楼盖,周边网格式框架预制单元化,这些单元均在预制场预制,如图3所示,楼盖划分为A1单元8个,A2单元10个,网格式框架标准层每层A单元16个,B单元4个(每层角部共4个),如图11所示,这些预制网格混凝土单元,根据施工图要求由下向上,分批预制。1) Manufacture of prefabricated parts: the floor and the surrounding grid frame are prefabricated into units, and these units are prefabricated in the prefabrication yard. As shown in Figure 3, the floor is divided into 8 units of A 1 and 10 units of A 2 , and the grid frame There are 16 units A and 4 units B on each floor of the standard floor (a total of 4 corners on each floor), as shown in Figure 11. These prefabricated grid concrete units are prefabricated in batches from bottom to top according to the requirements of the construction drawing.

2)中央混凝土核芯筒在现场由下向上分层浇制,并注意每一层与楼盖拼接位置的构造,混凝土核芯筒内设置塔吊,作预制单元吊装、安装使用;2) The central concrete core tube is poured layer by layer from bottom to top on site, and attention should be paid to the structure of the splicing position of each floor and the floor. A tower crane is installed in the concrete core tube for hoisting and installation of prefabricated units;

3)核芯筒施工(2-3层)后,先将图10划分的网格A、B单元安装,图11墙架预制混凝土网格A单元,其每一层网格框架柱在楼盖标高均预制了45°拼装悬臂短梁,在此处与楼盖45°夹角空腹梁拼接,墙架安装时应有专门的安装架,确保结构安全架设和二次浇注混凝土并养护。每一层周边网格式框架安装就位后,分层安装图3所示预制混凝土空腹网格A1与A2单元,图4为预制混凝土网格A1(A2)单元平面图,此预制件覆盖楼盖平面面积35m2,自重不到3T,且整体性好,塔吊吊装就位后,应有专门的支撑架(可升降)在每一节位置支撑就位,如图5所示,在方形网格空腹楼盖支托处,安放四点支承钢筋桁架楼承板,仅在拼接位置设置模板,图6为预制A单元剪力键位置上弦节点构造,节点中央为剪力键箍筋及竖向钢筋,此钢筋上端90°弯折于预留的上弦箍筋内,图7为图6的A-A剖面,在节点位置剪力键纵筋及上弦上部钢筋均穿入预留箍筋内,再在网格四角支托位置搁置钢筋桁架楼承板,再按图9所示将空腹梁上弦上部纵向钢筋设置预留箍筋内,单元与单元之间上、下弦杆拼接位置纵向钢筋(下弦上、下两列,上弦只下部一列)等强连接,当上、下弦拼接位置模板安装后,拼接处及楼承板处一次性后浇高一级混凝土,如图9标注有黑色细点位置,塔楼楼盖即形成如图8的剖面构造,此处楼盖进深11200,空腹板厚度450(L/25),中部留出净空2.55m×0.1m,即为水平管线铺设的夹层,当竖向与横向混凝土网格拼接位置后浇混凝土养护完成,即形成“混凝土正交正放空间网格盒式筒中筒结构”。3) After the construction of the core tube (2-3 floors), first install the grid A and B units divided in Figure 10, and the prefabricated concrete grid unit A of the wall frame in Figure 11, and the grid frame columns of each layer are on the floor All elevations are prefabricated with short cantilever beams assembled at 45°, where they are spliced with the hollow beams at an angle of 45° to the floor. There should be special mounting brackets for the installation of wall frames to ensure the safe erection of the structure and the secondary pouring of concrete and maintenance. After the surrounding grid frame of each layer is installed in place, the precast concrete hollow grid A 1 and A 2 units shown in Figure 3 are installed layer by layer, and Figure 4 is the plan view of the precast concrete grid A 1 (A 2 ) unit. The plane area of the covered floor is 35m 2 , the self-weight is less than 3T, and the integrity is good. After the tower crane is hoisted in place, there should be a special support frame (which can be lifted) to support in place at each section, as shown in Figure 5. Place four-point supporting steel truss floor slabs at the supports of the hollow floor of the square grid, and only set the formwork at the splicing position. Figure 6 shows the structure of the upper chord node at the shear key position of the prefabricated unit A. The center of the node is the shear key stirrup and Vertical steel bar, the upper end of this steel bar is bent at 90° in the reserved upper chord stirrup. Fig. 7 is the AA section of Fig. 6. At the joint position, the longitudinal bar of the shear key and the upper part of the upper chord are all penetrated into the reserved stirrup. Then place the reinforced truss floor deck at the support positions of the four corners of the grid, and then set the longitudinal reinforcement on the upper chord of the vierendeel beam in the reserved stirrup as shown in Figure 9, and set the vertical reinforcement at the splicing position of the upper and lower chords between units (lower chord) The upper and lower columns, the upper chord is only the lower one) equal strong connection, when the upper and lower chord splicing position formwork is installed, the splicing place and the floor slab are poured with a one-time higher level of concrete, as shown in Figure 9 marked with black fine dots, The sectional structure of the tower floor is formed as shown in Figure 8. The depth of the floor here is 11200, the thickness of the hollow plate is 450 (L/25), and the clearance in the middle is 2.55 m × 0.1 m , which is the interlayer for laying horizontal pipelines. After the splicing position with the horizontal concrete grid is completed, the concrete curing is completed, and the "concrete orthogonal space grid box-type tube-in-tube structure" is formed.

本领域技术人员应该认识到,上述的具体实施方式只是示例性的,是为了使本领域技术人员能够更好的理解本发明内容,不应理解为是对本发明保护范围的限制,如拼装单元实现工业化进行量产,建筑单位只需要在现场从第二步开始中央混凝土核芯筒的浇制即可,只要是根据本发明技术方案所作的改进,均落入本发明的保护范围。Those skilled in the art should realize that the above-mentioned specific implementation is exemplary only, in order to enable those skilled in the art to better understand the contents of the present invention, and should not be interpreted as limiting the protection scope of the present invention, such as the realization of assembly units For industrialized mass production, the construction unit only needs to start the casting of the central concrete core tube from the second step on site. As long as it is improved according to the technical solution of the present invention, it all falls within the scope of protection of the present invention.

Claims (7)

1.装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于:横向空腹楼盖的网格与竖向网格式框架的网格相等,且彼此在交汇处刚性连接;1. Prefabricated concrete orthogonal space grid box-in-tube structure, characterized in that: the grid of the horizontal fasting floor is equal to the grid of the vertical grid frame, and they are rigidly connected at the intersection; 横向空腹楼盖与竖向网格式框架单元化预制后,再分层安装;The horizontal hollow floor and the vertical grid frame are unitized and prefabricated, and then installed in layers; 所述装配式混凝土正交正放空间网格盒式筒中筒结构的制作方法,包括:在现场由下向上分层浇制中央混凝土核芯筒;The manufacturing method of the prefabricated concrete orthogonal and vertical space grid box-type tube-in-tube structure includes: pouring the central concrete core tube layer by layer from bottom to top on site; 中央混凝土核芯筒内设置塔吊,作拼装单元吊装、安装使用;A tower crane is installed in the central concrete core tube for hoisting and installation of assembled units; 中央混凝土核芯筒施工2-3层后,先将周边竖向网格式框架拼装单元进行安装,每一层网格框架柱在横向空腹楼盖标高均预制45°拼装悬臂短梁,在此处与横向空腹楼盖45°夹角空腹梁拼接,墙架安装时设置安装架;After the construction of 2-3 floors of the central concrete core tube, the surrounding vertical grid frame assembly units are installed first, and the grid frame columns of each layer are prefabricated at 45° assembled cantilever short beams at the elevation of the horizontal vierendeel floor. Here It is spliced with the hollow beam at an angle of 45° to the horizontal hollow floor, and the installation frame is set when the wall frame is installed; 每一层周边网格式框架安装就位后,分层安装混凝土空腹网格预制单元,塔吊吊装就位后,设置支撑架在每一节位置支撑就位。After the surrounding grid frame of each layer is installed in place, the concrete hollow grid prefabricated units are installed layer by layer. After the tower crane is hoisted in place, the support frame is set to support in place at each section. 2.如权利要求1所述的装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于:横向空腹楼盖与中央混凝土核芯筒周边剪力墙在横向空腹楼盖位置为刚性连接。2. The prefabricated concrete orthogonal space grid box-in-tube structure as claimed in claim 1, characterized in that: the horizontal fasting floor and the shear wall around the central concrete core tube are at the position of the horizontal fasting floor Rigid connection. 3.如权利要求1所述的装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于:横向空腹楼盖与中央混凝土核芯筒剪力墙及与竖向网格式框架分别两两刚性连接成网格式盒式结构。3. The prefabricated concrete orthogonal space grid box-in-tube structure according to claim 1, characterized in that: the horizontal fasting floor and the central concrete core tube shear wall and the vertical grid frame are respectively Two by two are rigidly connected to form a grid-like box structure. 4.如权利要求1所述的装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于:网格式盒式结构与中央混凝土核心筒组成正交正放盒式筒中筒结构。4. The prefabricated concrete orthogonal and vertical space grid box-in-tube structure according to claim 1, characterized in that: the grid box structure and the central concrete core tube form an orthogonal and positive box-type tube-in-tube structure. 5.如权利要求1-4其中之一所述的装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于:制作方法包括:5. The prefabricated concrete orthogonal space grid box-type tube-in-tube structure according to any one of claims 1-4, characterized in that: the manufacturing method includes: 将竖向网格式框架和横向空腹楼盖分别划分为若干网格单元,然后预制成拼装单元,再在施工现场分层安装。Divide the vertical grid frame and the horizontal vierendeel floor into several grid units, and then prefabricate the assembled units, and then install them layer by layer at the construction site. 6.如权利要求5所述装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于,预制工程量占总工程量的85%。6. As claimed in claim 5, the prefabricated concrete orthogonal space grid box-type tube-in-tube structure is characterized in that the prefabricated engineering volume accounts for 85% of the total engineering volume. 7.如权利要求1所述装配式混凝土正交正放空间网格盒式筒中筒结构,其特征在于:在节点位置剪力键纵筋及上弦上部钢筋均穿入预留箍筋内,再在网格四角支托位置搁置钢筋桁架楼承板,再将空腹梁上弦上部纵向钢筋设置预留箍筋内,拼装单元与拼装单元之间上、下弦杆拼接位置纵向钢筋连接,当上、下弦拼接位置模板安装后,拼接处及钢筋桁架楼承板处一次性后浇高一级混凝土,混凝土空腹网格预制单元与钢筋桁架楼承板二次浇制混凝土后形成横向空腹楼盖整体,中部留出水平管线铺设的夹层,当竖向与横向混凝土网格拼接位置后浇混凝土养护完成,即形成混凝土正交正放空间网格盒式筒中筒结构。7. As claimed in claim 1, the prefabricated concrete orthogonal space grid box-in-tube structure is characterized in that: at the node position, the longitudinal reinforcement of the shear key and the upper reinforcement of the upper chord all penetrate into the reserved stirrup, and then The reinforced truss floor deck is placed at the four-corner support positions of the grid, and then the vertical steel bars on the upper chord of the vierendeel beam are set in the reserved stirrups, and the longitudinal steel bars at the splicing positions of the upper and lower chords between the assembled units are connected, as the upper and lower chords After the formwork at the splicing position is installed, the splicing place and the steel truss floor deck are poured with the first-grade concrete at one time, and the concrete hollow grid prefabricated unit and the steel truss floor deck are poured with concrete twice to form a whole horizontal hollow floor. Leave the interlayer for the laying of horizontal pipelines, and when the vertical and horizontal concrete grids are spliced, the concrete curing is completed, that is, the concrete orthogonal space grid box-type tube-in-tube structure is formed.
CN201511013604.0A 2015-12-31 2015-12-31 Assembly concrete orthogonal spatial space lattice boxlike tube-in-tube structure Expired - Fee Related CN105625568B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511013604.0A CN105625568B (en) 2015-12-31 2015-12-31 Assembly concrete orthogonal spatial space lattice boxlike tube-in-tube structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511013604.0A CN105625568B (en) 2015-12-31 2015-12-31 Assembly concrete orthogonal spatial space lattice boxlike tube-in-tube structure

Publications (2)

Publication Number Publication Date
CN105625568A CN105625568A (en) 2016-06-01
CN105625568B true CN105625568B (en) 2018-02-06

Family

ID=56040876

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511013604.0A Expired - Fee Related CN105625568B (en) 2015-12-31 2015-12-31 Assembly concrete orthogonal spatial space lattice boxlike tube-in-tube structure

Country Status (1)

Country Link
CN (1) CN105625568B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105951995A (en) * 2016-06-08 2016-09-21 潍坊昌大建设集团有限公司 Prefabricated concrete III orthogonal-diagonal space lattice box type tube-in-tube structure and manufacturing method thereof
CN106245772A (en) * 2016-08-03 2016-12-21 潍坊昌大建设集团有限公司 Assembly concrete orthogonal spatial space lattice boxlike bundled tube structure and manufacture method
CN106996147B (en) * 2017-03-31 2019-10-18 东南大学 Multi-layer and large-span assembly-type orthogonal and vertical assembly-type concrete space grid box structure and manufacturing method
CN107630509A (en) * 2017-09-21 2018-01-26 湖南金海钢结构股份有限公司 A kind of compound orthogonal-diagonal lattice space steel lattice boxlike tube-in-tube structure of assembled
CN107724536A (en) * 2017-09-21 2018-02-23 湖南金海钢结构股份有限公司 A kind of compound orthogonal spatial space steel lattice boxlike tube-in-tube structure of assembled
CN107989193A (en) * 2017-12-10 2018-05-04 湖南金海钢结构股份有限公司 Compound orthogonal spatial space lattice boxlike tube-in-tube structure and production method
CN108951643B (en) * 2018-09-06 2020-06-09 中国建筑第八工程局有限公司 Super high-rise deep foundation pit basement core tube large-span large-area support changing construction method
CN109403460A (en) * 2018-09-10 2019-03-01 湖南工业大学 Circular flat large span honeycomb type concrete space lattice box structure and preparation method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2625599A1 (en) * 1976-06-08 1977-12-22 Norbert Dr Ing Wackernell Lattice structure acting as fluid distribution system - has tubes screwed together at nodal points with joints sealed by socket inserts
CN202298892U (en) * 2011-10-02 2012-07-04 广州市城市规划勘测设计研究院 Composite structure system of steel frame-concrete tube
CN102454217B (en) * 2011-11-08 2014-06-04 浙江东南网架股份有限公司 Bunchy tube structure for concrete core tubes and integrally-assembled space steel grids
CN203977572U (en) * 2014-04-30 2014-12-03 王本淼 A kind of high-rise building that adopts cast-in-situ hollow building roof
CN104929290B (en) * 2015-04-29 2017-11-14 潍坊昌大建设集团有限公司 Large-span steel-reinforced concrete orthogonal-diagonal lattice hollow floor system and preparation method thereof
CN104988984A (en) * 2015-04-29 2015-10-21 潍坊昌大建设集团有限公司 U-shaped steel and concrete combined orthogonal-diagonal spatial grid box type structure and manufacturing method

Also Published As

Publication number Publication date
CN105625568A (en) 2016-06-01

Similar Documents

Publication Publication Date Title
CN105625568B (en) Assembly concrete orthogonal spatial space lattice boxlike tube-in-tube structure
CN105625566B (en) Assembly concrete orthogonal-diagonal lattice space lattice box structure tube-in-tube structure
US9340975B2 (en) Method of casting in-situ ferrocement ribbed slab with spliced rack and suspended formwork
CN105649360A (en) Integral assembling type building system and installing method
CN104652705B (en) Prefabricated and assembly type steel reinforced concrete column with high-performance concrete frame and construction method
CN106193292A (en) A kind of steel frame assembled integral reinforced concrete shear wall structure system
CN207553289U (en) A kind of assembled steel and concrete frame space modular structure and system
CN101691784A (en) Steel structured wide-bay energy-saving residential building with gypsum walls and on-site layering and sectioning manufacturing method
CN109083308B (en) Anti-seismic prefabricated assembly type wall and construction method thereof
CN102704569A (en) Multilayer large-span assembling integral type space steel grid building structure and manufacturing method
CN107989238A (en) A kind of cast-in-place sandwiched heat-preservation shear wall structure, assembled architecture and engineering method
CN111155680A (en) All-bolt connection multilayer prefabricated section steel concrete shear wall structure and preparation and construction method thereof
CN106996147A (en) Multilayer large-span assembled orthogonal spatial assembled concrete space lattice box structure and preparation method
CN109944324B (en) Composite steel-concrete frame column and reinforced concrete frame column combined assembly structure system
CN106121109A (en) Large span right hexagonal steel-concrete cellular hollow sandwich panel ceiling for storied building and manufacture method
CN106245772A (en) Assembly concrete orthogonal spatial space lattice boxlike bundled tube structure and manufacture method
CN205329970U (en) Precast concrete wallboard and wall panel structure system of dark frame in area of structure thereof
CN105649259B (en) A kind of wallboard structural system of the dark framework of band of precast concrete wall panel and its structure
CN210421568U (en) Assembled beam and plate structure
CN204919932U (en) Assemble integral non -reinforced concrete ribbed floor
CN111364642A (en) Assembled energy-consumption shear wall system and construction method thereof
CN108277904B (en) Assembled frame type light steel frame-reinforcing mesh-foamed concrete combined wall
CN115897787A (en) An assembled slab-column structure system
CN210049379U (en) Steel concrete combined frame column assembly type structure system
CN210049380U (en) Steel concrete combined frame column and reinforced concrete frame column combined assembly type structure system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180206

Termination date: 20211231

CF01 Termination of patent right due to non-payment of annual fee