CN105442395B - A pre-buried channel of contact rail for magnetic levitation engineering - Google Patents
A pre-buried channel of contact rail for magnetic levitation engineering Download PDFInfo
- Publication number
- CN105442395B CN105442395B CN201510987872.6A CN201510987872A CN105442395B CN 105442395 B CN105442395 B CN 105442395B CN 201510987872 A CN201510987872 A CN 201510987872A CN 105442395 B CN105442395 B CN 105442395B
- Authority
- CN
- China
- Prior art keywords
- channel
- contact rail
- engineering
- buried channel
- buried
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000005339 levitation Methods 0.000 title claims abstract description 14
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 25
- 239000010959 steel Substances 0.000 claims abstract description 25
- 238000009434 installation Methods 0.000 claims abstract description 24
- 239000000725 suspension Substances 0.000 claims abstract description 4
- 238000009415 formwork Methods 0.000 claims description 10
- 229910001335 Galvanized steel Inorganic materials 0.000 claims description 3
- 230000004323 axial length Effects 0.000 claims description 3
- 239000008397 galvanized steel Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 8
- 238000010276 construction Methods 0.000 abstract description 3
- 239000000463 material Substances 0.000 abstract description 3
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical group [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 6
- 229910052782 aluminium Inorganic materials 0.000 description 6
- 238000005260 corrosion Methods 0.000 description 3
- 238000005553 drilling Methods 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 229910000838 Al alloy Inorganic materials 0.000 description 1
- 229910000746 Structural steel Inorganic materials 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005246 galvanizing Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B25/00—Tracks for special kinds of railways
- E01B25/30—Tracks for magnetic suspension or levitation vehicles
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Railway Tracks (AREA)
Abstract
本发明公开了一种磁悬浮工程接触轨预埋槽道,该接触轨预埋槽道用于预埋在轨道梁中从而安装磁悬浮工程接触轨,包括两个并排安装的槽道本体,槽道本体通过连接钢筋相互连接,每个槽道本体上均设置有安装孔,这些安装孔的位置一一对应,用于安装固定件与轨道梁固定相连。本发明通过对其关键组件的结构及其设置方式、材料等进行改进,与现有技术相比能够有效解决磁悬浮工程中接触轨预埋槽道的问题,并且该接触轨预埋槽道能够很好的与轨道梁的施工相配合,实现接触轨预埋槽道、以及磁悬浮工程接触轨的精确安装。
The invention discloses a pre-embedded channel of a magnetic suspension engineering contact rail. The pre-embedded channel of the contact rail is used for pre-embedding in a track beam to install a magnetic suspension engineering contact rail. It includes two channel bodies installed side by side, and the channel body The connecting steel bars are connected to each other, and each channel body is provided with installation holes, and the positions of these installation holes correspond to each other, and are used for fixing the fixing parts and the track beams to be fixedly connected. Compared with the prior art, the present invention can effectively solve the problem of the pre-buried channel of the contact rail in the magnetic levitation project by improving the structure of its key components, its setting method, materials, etc., and the pre-buried channel of the contact rail can be easily Cooperate well with the construction of the track beam to realize the precise installation of the pre-buried channel of the contact rail and the contact rail of the magnetic levitation project.
Description
技术领域technical field
本发明属于轨道交通运输领域,更具体地,涉及一种磁悬浮工程接触轨预埋槽道。The invention belongs to the field of rail transportation, and more specifically relates to a pre-buried channel of a contact rail for a magnetic levitation engineering.
背景技术Background technique
接触轨需要在轨道梁两侧安装,现有的接触轨预埋槽道,其槽道类型多、铆钉形式所占空间较大,目前还没有一种比较适合磁悬浮工程(例如中低速磁浮工程)接触轨安装预埋槽道方式。磁悬浮工程槽道类型和尺寸较多,需要综合考虑各种槽道类型及其尺寸的影响,使选择的槽道方式适合于磁浮工程接触轨的安装;铆钉形式所占空间较大,一般槽道采用扁形钢结构,横向空间较大,预埋时容易和轨道梁钢筋冲突。另外,接触轨预埋槽道还需要考虑其与预制轨道梁模板固定方式,即该接触轨预埋槽道需要能够支持与磁浮工程预制轨道梁结构模板匹配的固定方式。The contact rail needs to be installed on both sides of the track beam. The existing contact rail pre-buried channels have many types of channels and rivets occupy a large space. At present, there is no one that is more suitable for maglev projects (such as medium and low speed maglev projects) The contact rail is installed in the embedded channel way. There are many types and sizes of channels in maglev engineering, and it is necessary to comprehensively consider the influence of various channel types and their sizes, so that the selected channel method is suitable for the installation of contact rails in maglev engineering; the rivet form occupies a large space, and the general channel The flat steel structure is adopted, and the horizontal space is large, so it is easy to conflict with the track beam reinforcement during pre-embedding. In addition, the busbar pre-buried channel also needs to consider its fixing method with the prefabricated track beam formwork, that is, the busbar embedded channel needs to be able to support the fixing method that matches the prefabricated track beam structural formwork of the maglev project.
发明内容Contents of the invention
针对现有技术的以上缺陷或改进需求,本发明的目的在于提供磁悬浮工程接触轨预埋槽道,其中通过对其关键组件的结构及其设置方式、材料等进行改进,与现有技术相比能够有效解决磁悬浮工程中接触轨预埋槽道的问题,并且该接触轨预埋槽道能够很好的与轨道梁的施工相配合,实现接触轨预埋槽道、以及磁悬浮工程接触轨的精确安装。In view of the above defects or improvement needs of the prior art, the purpose of the present invention is to provide the pre-buried channel of the magnetic levitation engineering contact rail, wherein by improving the structure of its key components and its setting method, materials, etc., compared with the prior art It can effectively solve the problem of the pre-buried channel of the contact rail in the magnetic levitation project, and the pre-buried channel of the contact rail can be well matched with the construction of the track beam, and realize the precise positioning of the pre-buried channel of the contact rail and the contact rail of the maglev project. Install.
为实现上述目的,按照本发明的一个方面,提供了一种磁悬浮工程接触轨预埋槽道,其特征在于,该接触轨预埋槽道用于预埋在轨道梁中从而安装磁悬浮工程接触轨,优选包括两个并排安装的槽道本体,所述槽道本体通过连接钢筋相互连接,每个所述槽道本体上均设置有安装孔,这些安装孔的位置一一对应,用于安装固定件与所述轨道梁固定相连。In order to achieve the above object, according to one aspect of the present invention, a maglev engineering contact rail embedded channel is provided. , preferably including two channel bodies installed side by side, the channel bodies are connected to each other through connecting steel bars, each of the channel bodies is provided with mounting holes, and the positions of these mounting holes correspond one-to-one for installation and fixing The parts are fixedly connected with the track beams.
作为本发明的进一步优选,所述槽道本体均为中空结构,每个所述槽道本体均包括顶面、两侧面和两支脚面,其中,所述两侧面相互平行,并与所述顶面垂直相交;所述两支脚面位于同一平面上,并分别与所述两侧面垂直相交;所述顶面与所述轨道梁相接触,所述两支脚面用于安装所述磁悬浮工程接触轨。As a further preference of the present invention, the channel bodies are all hollow structures, and each of the channel bodies includes a top surface, two side surfaces and two leg surfaces, wherein the two side surfaces are parallel to each other and parallel to the top surface. The surfaces are vertically intersected; the two legs are located on the same plane and are perpendicular to the two sides; the top surface is in contact with the track beam, and the two legs are used to install the contact rail of the magnetic levitation project .
作为本发明的进一步优选,所述连接钢筋上还设置有锚钉连接件,所述锚钉连接件的端部所处平面与所述槽道本体的所述两支脚面所处平面相重合,所述锚钉连接件上还设置有锚钉固定孔,用于将该接触轨预埋槽道与所述轨道梁的模板相连接。As a further preference of the present invention, the connecting steel bar is also provided with an anchor connector, the plane where the end of the anchor connector is located coincides with the plane where the two legs of the channel body are located, An anchor fixing hole is also provided on the anchor connector, which is used to connect the pre-embedded channel of the contact rail with the formwork of the track beam.
作为本发明的进一步优选,每个所述槽道本体上设置有至少两个安装孔,这些安装孔的直径均为14mm;任意一个所述槽道本体的安装孔的中心轴线位于同一平面内,这些安装孔的中心轴线沿该槽道本体的轴向方向分布;所述两个槽道本体其安装孔中心轴线所处平面相互平行,这两个槽道本体其安装孔中心轴线所处平面之间的距离为125mm。As a further preference of the present invention, each channel body is provided with at least two installation holes, and the diameter of these installation holes is 14 mm; the central axis of any one of the channel body installation holes is located in the same plane, The central axes of these mounting holes are distributed along the axial direction of the channel body; the planes where the central axes of the mounting holes of the two channel bodies are parallel to each other, The distance between them is 125mm.
作为本发明的进一步优选,每个所述槽道本体的轴向方向长度均为330mm。As a further preference of the present invention, the axial length of each channel body is 330 mm.
作为本发明的进一步优选,所述连接钢筋的直径为10mm。As a further preference of the present invention, the diameter of the connecting steel bar is 10 mm.
作为本发明的进一步优选,所述固定件为铆钉。As a further preference of the present invention, the fixing member is a rivet.
作为本发明的进一步优选,所述锚钉连接件为铝单质或铝合金。As a further preferred embodiment of the present invention, the anchor connector is aluminum or aluminum alloy.
作为本发明的进一步优选,所述槽道本体均采用镀锌钢材料。As a further preference of the present invention, the channel bodies are all made of galvanized steel.
通过本发明所构思的以上技术方案,与现有技术相比,具有以下优点:Compared with the prior art, the above technical scheme conceived by the present invention has the following advantages:
1)适合接触轨的接口安装。1) Suitable for interface installation of contact rail.
2)固定件(尤其是铆钉形式的固定件)占用空间少,且安全可靠。2) The fixing parts (especially the fixing parts in the form of rivets) occupy less space and are safe and reliable.
3)便于与预制轨道梁的固定。3) It is convenient to fix with the prefabricated track beam.
4)槽道本体的轴向方向长度满足接触轨在竖向的移动调整量。4) The axial length of the channel body satisfies the vertical movement adjustment of the contact rail.
5)槽道本体采用镀锌钢材料、锚钉连接件采用铝材料,使该磁悬浮工程接触轨预埋槽道一方面强度高、耐腐蚀,另一方面也便于在轨道梁中预埋(尤其是便于与轨道梁模板间的连接与拆卸)。5) The channel body is made of galvanized steel and the anchor connectors are made of aluminum, so that the pre-embedded channel of the contact rail of the magnetic levitation project has high strength and corrosion resistance on the one hand, and is also convenient to be embedded in the track beam (especially It is convenient to connect and disassemble with the track beam formwork).
本发明中的磁悬浮工程接触轨预埋槽道适用于轨道交通,尤其是中低速磁悬浮线路。预埋槽道方便后期接触轨安装,提高了工程安装效率。在轨道梁上不打孔安装接触轨,避免了对轨道梁的破坏,安全可靠。The pre-embedded channel of the contact rail of the magnetic levitation engineering in the present invention is suitable for rail transit, especially for medium and low speed magnetic levitation lines. The pre-buried channel facilitates the later installation of the contact rail and improves the efficiency of engineering installation. The contact rail is installed without drilling holes on the track beam, which avoids damage to the track beam and is safe and reliable.
附图说明Description of drawings
图1A是磁悬浮工程接触轨预埋槽道的主视图,图1B是接触轨预埋槽道的俯视图,图1C是接触轨预埋槽道的左视图;Fig. 1A is the front view of the pre-buried channel of the contact rail in the maglev engineering, Fig. 1B is a top view of the pre-buried channel of the contact rail, and Fig. 1C is a left view of the pre-buried channel of the contact rail;
图2是预埋槽道与轨道梁模板的固定示意图;Fig. 2 is a fixed schematic diagram of the embedded channel and the track beam formwork;
图3是预埋槽道长度和接触轨底座调整范围示意图。Fig. 3 is a schematic diagram of the length of the embedded channel and the adjustment range of the base of the contact rail.
图中各附图标记的含义如下:1为槽道本体,2为连接钢筋,3为安装孔,4为铆钉,5为锚钉连接件,6为锚钉固定孔,7为铝锚钉,8为轨道梁,9为轨道梁模板,10为接触轨,11为接触轨底座。The meanings of the reference marks in the figure are as follows: 1 is the channel body, 2 is the connecting steel bar, 3 is the installation hole, 4 is the rivet, 5 is the anchor connector, 6 is the anchor fixing hole, 7 is the aluminum anchor, 8 is a track beam, 9 is a track beam template, 10 is a contact rail, and 11 is a contact rail base.
具体实施方式detailed description
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。此外,下面所描述的本发明各个实施方式中所涉及到的技术特征只要彼此之间未构成冲突就可以相互组合。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not constitute a conflict with each other.
实施例1Example 1
如图2、图3所示,磁悬浮工程接触轨预埋槽道,包括两个并排安装的槽道本体,所述槽道本体通过连接钢筋相互连接,每个所述槽道本体上均设置有安装孔,这些安装孔的位置一一对应(即,一个槽道本体上安装孔的位置与另一个槽道本体上安装孔的位置在槽道本体长度方向上的投影相互重合,安装孔的位置一一对应),用于安装固定件与所述轨道梁固定相连。As shown in Figure 2 and Figure 3, the pre-buried channel of the contact rail of the maglev engineering includes two channel bodies installed side by side. The channel bodies are connected to each other through connecting steel bars, and each channel body is provided with Mounting holes, the positions of these mounting holes correspond to each other (that is, the position of the mounting hole on one channel body and the projection of the position of the mounting hole on the other channel body on the length direction of the channel body coincide with each other, and the position of the mounting hole One-to-one correspondence), used to install the fixture and fixedly connect with the track beam.
本实施例中的磁悬浮工程接触轨预埋槽道预埋在轨道梁两侧,如图1A、1B和1C所示,该接触轨安装底座孔间距为125mm(即,这两个槽道本体其安装孔中心轴线所处平面之间的平面间距为125mm),至少包括4个定位孔(即每个槽道本体上至少有两个安装孔),每个定位孔的直径均为14mm,满足M12螺栓与接触轨底座的安装。该预埋槽道采用两根槽道并排安装,并采用两根10mm直径的钢筋进行连接固定,使两根槽道在125mm间距下固定不变。The pre-buried channel of the contact rail of the magnetic levitation engineering in this embodiment is pre-embedded on both sides of the track beam, as shown in Figures 1A, 1B and 1C, the hole spacing of the contact rail installation base is 125mm (that is, the two channel bodies The plane spacing between the planes where the central axis of the mounting hole is located is 125mm), including at least 4 positioning holes (that is, there are at least two mounting holes on each channel body), and the diameter of each positioning hole is 14mm, meeting M12 Installation of bolts and contact rail base. The pre-buried channel is installed side by side with two channels, and is connected and fixed by two steel bars with a diameter of 10mm, so that the two channels are fixed at a distance of 125mm.
铆钉选择M12的圆形钢结构(铆钉直径优选为12mm),受力方面与M12螺栓与接触轨底座的安装配套。横向相比扁钢减小了占用空间,尽量避免与轨道梁结构钢筋的冲突。The rivets are M12 round steel structures (the diameter of the rivets is preferably 12mm), and the force is matched with the installation of the M12 bolts and the base of the contact rail. Compared with the flat steel in the horizontal direction, the occupied space is reduced, and the conflict with the structural steel bars of the track beams is avoided as much as possible.
由于轨道梁采用混凝土结构,为提高该接触轨预埋槽道与轨道梁的连接强度,接触轨预埋槽道优选在轨道梁混凝土浇筑阶段即预埋在轨道梁中,与轨道梁形成整体,因此,为便于该接触轨预埋槽道的安装施工以及安装精度,在混凝土浇筑阶段,该接触轨预埋槽道往往需要通过轨道梁钢模板进行定位与施工。为便于具体的施工操作,可以在固定两根槽道的10mm直径的钢筋中间焊接一块L形的钢片,钢片一端和轨道梁模板内侧紧贴,钢片紧贴面设计一个小孔,用于铝锚钉与钢模板固定,后期拆卸模板时将铝锚钉拉断即可。Since the track beam adopts a concrete structure, in order to improve the connection strength between the busbar pre-buried channel and the track beam, the busbar pre-buried channel is preferably embedded in the track beam during the concrete pouring stage of the track beam, and forms a whole with the track beam. Therefore, in order to facilitate the installation and installation accuracy of the contact rail pre-buried channel, the contact rail pre-buried channel often needs to be positioned and constructed through the track beam steel formwork during the concrete pouring stage. In order to facilitate specific construction operations, an L-shaped steel sheet can be welded between the 10mm-diameter steel bars that fix the two channels. One end of the steel sheet is closely attached to the inner side of the track beam formwork, and a small hole is designed on the surface of the steel sheet. The aluminum anchors are fixed to the steel formwork, and the aluminum anchors can be broken when the formwork is disassembled later.
槽道长度优选为330mm,接触轨底座可以在槽道本体上灵活调整位置(如图3所示),满足轨道梁上部空间的安装要求及接触轨固定要求。The length of the channel is preferably 330mm, and the position of the contact rail base can be flexibly adjusted on the channel body (as shown in Figure 3), which meets the installation requirements of the upper space of the track beam and the contact rail fixing requirements.
槽道材质采用Q235B钢,具有良好的强度和防腐性能,Q235B钢表面还可以采用3级热镀锌处理。The channel is made of Q235B steel, which has good strength and anti-corrosion performance. The surface of Q235B steel can also be treated with 3-grade hot-dip galvanizing.
具有以下优点:Has the following advantages:
1)槽道间距125mm,尤其适合接触轨底座孔间距125mm安装要求。1) The channel spacing is 125mm, which is especially suitable for the installation requirements of the contact rail base hole spacing of 125mm.
2)改变铆钉为M12圆钢形式,占用空间少,且安全可靠。2) Change the rivets to M12 round steel, which takes up less space and is safe and reliable.
3)采用一种铝锚钉与预制轨道梁的固定方式。3) A fixing method of aluminum anchors and prefabricated track beams is adopted.
4)槽道长度选择330mm,满足接触轨在竖向的移动调整量。4) The length of the channel is selected as 330mm to meet the vertical movement adjustment of the contact rail.
5)材料选择Q235B强度高,3级热镀锌耐腐蚀。5) The material selection is Q235B with high strength and grade 3 hot-dip galvanized for corrosion resistance.
城市轨道交通磁悬浮系统车辆是悬浮模式,采用轨道梁结构,轨道梁上面敷设F轨;车辆牵引动力电源采用敷设在轨道梁两侧的正负极接触轨供电;接触轨采用C型结构,授流方式为侧面授流。轨道梁一般采用预制预应力桥梁结构,不允许在轨道梁上采用打孔安装锚栓方式;而接触轨需固定在轨道梁两侧,本发明中的接触轨预埋槽道解决了不打孔安装接触轨的需求;该预埋槽道需满足接触轨安装,并适用于在轨道梁的预埋。The vehicle of the urban rail transit maglev system is in the suspension mode, adopting the track beam structure, and the F rail is laid on the track beam; the traction power supply of the vehicle is powered by the positive and negative contact rails laid on both sides of the track beam; The way is side flow. The track beam generally adopts prefabricated prestressed bridge structure, and it is not allowed to use the method of drilling and installing anchor bolts on the track beam; while the contact rail needs to be fixed on both sides of the track beam. The contact rail pre-buried channel in the present invention solves the problem of not drilling holes The requirements for installing contact rails; the embedded channel needs to meet the installation of contact rails and is suitable for pre-embedding in track beams.
本领域的技术人员容易理解,以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。Those skilled in the art can easily understand that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention, All should be included within the protection scope of the present invention.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510987872.6A CN105442395B (en) | 2015-12-24 | 2015-12-24 | A pre-buried channel of contact rail for magnetic levitation engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510987872.6A CN105442395B (en) | 2015-12-24 | 2015-12-24 | A pre-buried channel of contact rail for magnetic levitation engineering |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105442395A CN105442395A (en) | 2016-03-30 |
CN105442395B true CN105442395B (en) | 2017-08-01 |
Family
ID=55552993
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510987872.6A Active CN105442395B (en) | 2015-12-24 | 2015-12-24 | A pre-buried channel of contact rail for magnetic levitation engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105442395B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105970744A (en) * | 2016-07-05 | 2016-09-28 | 北京交通大学 | Base for suspension type monorail traffic track beam |
CN108660873A (en) * | 2018-06-11 | 2018-10-16 | 中铁二院工程集团有限责任公司 | A kind of pre-buried steel-rail structure of suspension type monorail traffic |
CN109441461A (en) * | 2018-12-17 | 2019-03-08 | 中国水利水电第四工程局有限公司 | A kind of Double shield TBM step device and application method |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3546107A1 (en) * | 1985-12-24 | 1987-06-25 | Halfeneisen Gmbh & Co Kg | ANCHOR RAIL FOR CONSTRUCTION TECHNOLOGY |
CN101537801B (en) * | 2009-04-24 | 2010-12-29 | 江苏华威线路设备集团有限公司 | Device for installing contact net in tunnel in electrified railway engineering |
CN202573857U (en) * | 2012-05-16 | 2012-12-05 | 中铁电气化局集团有限公司 | Insulation support device of middle and low speed magnetic suspension side current collecting steel-aluminum composite contact rail |
CN103144553B (en) * | 2013-03-21 | 2014-12-24 | 中铁电气化局集团有限公司 | Overhead contact rail insulating suspension device |
CN104631627A (en) * | 2013-11-13 | 2015-05-20 | 山东天工岩土工程设备有限公司 | Novel toothed pre-buried channel |
-
2015
- 2015-12-24 CN CN201510987872.6A patent/CN105442395B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN105442395A (en) | 2016-03-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105442395B (en) | A pre-buried channel of contact rail for magnetic levitation engineering | |
CN102912693B (en) | Floating track bed precast slab and construction method for precast slab assembled floating track bed | |
CN102518300B (en) | Embedded conical bearing joint type steel structure support and construction method thereof | |
CN106049271B (en) | A kind of bridge inspection car orbit connection device and its construction method | |
CN103993745A (en) | Integral transfer girder hoisting device and hoisting method thereof | |
CN202073033U (en) | Concrete seam expansion/constriction apparatus | |
CN206174487U (en) | Pre -cast screw fixing device | |
CN108221511A (en) | A kind of magnetic floating traffic gapless track | |
CN207975335U (en) | Pre-buried channel flow | |
CN203403336U (en) | Bolt sleeve-pre-buried support of rail transit contact rail insulating support base | |
CN202954266U (en) | Novel rail transit vibration isolation floating ballast bed precast slab | |
CN206887629U (en) | A kind of novel steel rail support groove and hump marshalling station concrete slab sleeper | |
CN103701074A (en) | Cable bridge and mounting method thereof | |
CN203766764U (en) | Subway platform reinforcing device | |
CN208843546U (en) | A kind of structure adjusting stairway shaft length | |
CN104832708B (en) | Pipeline pre-installing frame | |
CN203100878U (en) | Framework for truck scale | |
CN110206064A (en) | Piping lane support and system | |
CN212639721U (en) | Limiter | |
CN205231680U (en) | Urban rail transit engineering cable support | |
CN204778385U (en) | Track fixed structure of single track calabash | |
CN109371766B (en) | Connecting method for curved concrete track beam | |
CN204002841U (en) | A kind of outrigger formula mobile formwork for support of tunnel wall pouring construction | |
CN203173636U (en) | Extending type installation structure of elevator guide rail supports | |
CN205775865U (en) | A kind of continuous rigid frame bridge closure segment pre-buried base of pushing tow top board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
OL01 | Intention to license declared |