CN105019553A - Bracing structure for annular supports of basement - Google Patents
Bracing structure for annular supports of basement Download PDFInfo
- Publication number
- CN105019553A CN105019553A CN201510284234.8A CN201510284234A CN105019553A CN 105019553 A CN105019553 A CN 105019553A CN 201510284234 A CN201510284234 A CN 201510284234A CN 105019553 A CN105019553 A CN 105019553A
- Authority
- CN
- China
- Prior art keywords
- support
- basement
- floor
- concrete
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/16—Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
- E02D31/04—Watertight packings for use under hydraulic pressure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2200/00—Geometrical or physical properties
- E02D2200/16—Shapes
- E02D2200/1607—Shapes round, e.g. circle
- E02D2200/1621—Shapes round, e.g. circle made from multiple elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种后增地下室结构,特别涉及地下室环形支撑支护结构。 The invention relates to a post-added basement structure, in particular to a basement annular support structure.
背景技术 Background technique
在地下室支护体系中,内支撑支护结构具有安全可靠、经济合理等特点,在基坑工程中得到广泛应用。但常规对撑方式设置的内支撑对地下室土方开挖和地下结构的施工造成极大的不便,产生施工工期延长、经济性差等后果。采用环形支撑替代常规对撑方式的支护结构体系,可以获得较高的经济效益。但是环形支撑在地下室开挖较深时尤其是多道支撑时,第一道环形支撑所受到侧压力通常会超出混凝土极限抗压强度,环形支撑会出现位移过大,环形支撑混凝土发生开裂等不良现象。 In the basement support system, the internal support structure has the characteristics of safety, reliability, and economical rationality, and is widely used in foundation pit engineering. However, the internal support provided by the conventional support method causes great inconvenience to the excavation of basement earthwork and the construction of underground structures, resulting in consequences such as prolonged construction period and poor economic efficiency. Using ring support instead of the support structure system of the conventional support method can obtain higher economic benefits. However, when the ring support is excavated deeply in the basement, especially when there are multiple supports, the lateral pressure on the first ring support usually exceeds the ultimate compressive strength of the concrete, and the ring support will experience excessive displacement, cracking and other defects in the ring support concrete. Phenomenon.
发明内容 Contents of the invention
本发明是提供一种地下室环形支撑支护结构,解决现有技术的问题。 The invention provides a basement annular support structure to solve the problems in the prior art.
为此,本发明设置两道支撑体系,第一道支撑设置在地下室顶部,第二道支撑设置在地下室中部,由于第一道支撑在地下室开挖至底标高部位受力会非常大,根据第一道支撑在施工中的受力特点将环形支撑做成桁架式结构,这种结构刚度较大,抗变形能力强,而第二道支撑体系的受力会明显减少,所以就单纯采用梁式环形支撑。考虑到角部受力会应力集中,因此将四角部位围护结构和环形支撑支顶结构做成混凝土板,以加强角部刚度来抵抗变形。 For this reason, the present invention sets up two support systems, the first support is arranged on the top of the basement, and the second support is arranged in the middle of the basement. Since the first support will bear a very large force when the basement is excavated to the bottom elevation, according to the first The stress characteristics of the first support in construction The circular support is made into a truss structure. This structure has high rigidity and strong deformation resistance, while the force of the second support system will be significantly reduced, so the beam type is simply used. ring support. Considering the stress concentration at the corners, the enclosure structure at the four corners and the ring support roof structure are made of concrete slabs to strengthen the rigidity of the corners to resist deformation.
围护墙宽度为60~80mm,深度为地下室开挖深度2~3倍,围护墙所采用的混凝土为C30或者C30以上,一层环形外支撑离围护墙的距离为1.5~3m,一层环形外支撑宽度为30cm,高度为40~50cm,一层环形内支撑离一层环形外支撑距离为1.2~1.6m,一层环形外支撑与围护墙之间设置支顶撑,支顶撑宽度为30cm,高度为40~50cm,一层环形内支撑宽度为30cm,高度为40~50cm,一层环形外支撑和一层环形内支撑之间设置混凝土桁架腹杆,混凝土桁架腹杆宽度为20cm,高度为40~50cm,一层环形内支撑和一层环形外支撑下面设置支撑柱,支撑柱采用混凝柱或者钢柱,支撑柱尽量设置在工程桩上面,否则支撑柱下面设置临时支撑桩。 The width of the enclosure wall is 60-80mm, and the depth is 2-3 times of the excavation depth of the basement. The concrete used for the enclosure wall is C30 or above. The width of the ring-shaped outer support on the first floor is 30cm, and the height is 40-50cm. The distance between the inner ring support on the first floor and the outer support on the first floor is 1.2-1.6m. The width of the brace is 30cm, and the height is 40-50cm. The width of the inner support of the first layer is 30cm, and the height is 40-50cm. A concrete truss web is set between the outer support of the first floor and the inner support of the first floor. The width of the web of the concrete truss The height is 20cm, and the height is 40-50cm. Support columns are set under the first layer of annular inner support and the first layer of annular outer support. The support columns are concrete columns or steel columns. support piles.
二层环形支撑和围护墙支顶结构采用混凝土板和支顶撑相结合,地下室长边方向1/4长度范围和短边方向1/3长度范围内设置混凝土板,地下室中部位置设置支顶撑,二层支顶撑与一层支顶撑投影位置相同,二层环形支撑的支撑柱和一层环形外支撑的支撑柱相同。 The second-floor circular support and the roof support structure of the enclosure wall adopt a combination of concrete slabs and roof supports. Concrete slabs are set within 1/4 of the length of the long side of the basement and 1/3 of the length of the short side of the basement, and the middle of the basement is set with a roof. Support, the projection position of the second floor support is the same as that of the first floor support, and the support column of the second floor ring support is the same as the support column of the first floor ring outer support.
一层支护撑伸入围护墙内部,与围护墙形成刚性连接,二层支护撑与围护墙 外面的预留钢筋进行焊接,形成铰接结构,以适应围护结构的特点。根据试验情况,一层支护撑与围护墙形成刚性连接后,环形支撑变形均匀且变形相对较小,而围护墙变形相对较大;二层支护撑与围护墙形成铰接结构后,变形相对较大,但围护墙变形相对较小。 The first-floor support extends into the interior of the enclosure wall to form a rigid connection with the enclosure wall, and the second-floor support is welded to the reserved steel bars outside the enclosure wall to form a hinged structure to adapt to the characteristics of the enclosure structure. According to the test results, after the first-floor support and the enclosure wall form a rigid connection, the deformation of the ring support is uniform and relatively small, while the deformation of the enclosure wall is relatively large; after the second-floor support and the enclosure wall form a hinged structure , the deformation is relatively large, but the deformation of the enclosure wall is relatively small.
施工步骤包括: Construction steps include:
(1)围护墙施工。 (1) Enclosure wall construction. the
围护墙不仅要进行护坡,还要防止渗水,围护墙兼作地下室外墙。围护墙施工采用空腹模板,空腹模板通过振动锤竖向往复振动产生的竖向激振力沉入地层,随即向空腹内注满浆液,当振动沉模提升时,浆液在重力作用下从模板下端注入槽孔内,先已沉入地层的模板成为后沉入模板的导向板,两块模板呈现板板相扣的作用,保证了各单板体在一个平面内紧密结合成墙。 The retaining wall should not only protect the slope, but also prevent water seepage. The retaining wall also serves as the basement exterior wall. The construction of the enclosure wall adopts the fasting formwork, and the fasting formwork sinks into the ground through the vertical excitation force generated by the vertical reciprocating vibration of the vibrating hammer, and then fills the hollowing with slurry. The lower end is injected into the slot hole, and the formwork that has sunk into the ground first becomes the guide plate that sinks into the formwork later, and the two formworks show the interlocking effect of the plates, ensuring that the veneers are tightly combined in one plane to form a wall.
施工工艺包括: Construction techniques include:
1)开挖预留槽; 1) Excavate the reserved slot;
2)预钻孔; 2) Pre-drilled holes;
在两块模板的结合处预钻孔,预钻孔直径为90~110cm; Pre-drill holes at the junction of the two templates, the diameter of the pre-drilled holes is 90-110cm;
3)振动沉模; 3) Die sinking by vibration;
启动振锤,将第一块模板沉入地层中,达到设计深度,然后将第二块模板沿施工轴线在第一块前侧与第一块模板紧密并排,以第一块模板为导向板,沉入地层达到设计深度; Start the vibrating hammer, sink the first formwork into the ground to reach the design depth, then place the second formwork closely side by side with the first formwork along the construction axis at the front side of the first formwork, and use the first formwork as a guide plate, sink into the formation to reach the design depth;
4)灌注提升第一块模板; 4) Perfusion lifts the first template;
向第一块模板内灌注浆体,然后边提升边灌注,直至拔出地面,浆体留在槽孔内,灌注提升结束后,要保持浆体达到墙顶设计高程; Pour the slurry into the first template, and then pour it while lifting it until it is pulled out from the ground, and the slurry remains in the slot hole. After the filling and lifting, keep the slurry reaching the design elevation of the top of the wall;
5)再沉入模板; 5) sink into the template again;
以第二块模板为导向板,沉入地层达到设计深度,再灌注提升第二块模板;按以上程序循环施工,即可完成围护墙。 Use the second formwork as a guide plate, sink into the ground to reach the design depth, refill and lift the second formwork; follow the above procedures to complete the enclosure wall.
目前传统工艺是采用挖土开槽、泥浆护壁、清渣、浇筑水下混凝土、处理接缝系列工序,在透水地层中开槽时易于塌孔,围护墙往往达不到厚度和出现断墙现象。而本发明以强大的垂直激振力,将空腹模板沉入土层,模板和浆液起到了护壁作用,施工过程中不但不释放土体应力,而且在振动沉模过程中,将其两侧土体挤压密实,提高了抗渗能力。由于本发明在原土体被模板挤压作用于下完成的。且在提拔模板过程中边提模边注浆,浆液从模板底产注人槽内,加之浆柱压力大于土体侧压力,因此不会出现缩壁和塌壁现象。 At present, the traditional process is to use a series of processes such as excavation and slotting, mud wall protection, slag removal, underwater concrete pouring, and joint treatment. When slotting in permeable strata, the hole is prone to collapse, and the enclosure wall often does not reach the thickness and broken walls. Phenomenon. However, the present invention sinks the fasting formwork into the soil layer with a strong vertical excitation force, and the formwork and the grout play the role of retaining walls. The body is extruded densely, which improves the impermeability. Because the present invention is finished under the extruding action of former soil body by formwork. And in the process of lifting the formwork while grouting, the grout is injected into the groove from the bottom of the formwork, and the pressure of the grout column is greater than the lateral pressure of the soil, so there will be no shrinkage or collapse of the wall.
(2)支撑柱施工。 (2) Support column construction. the
支撑柱下面如无工程桩,先施工临时支撑桩后将支撑柱插入临时支撑桩。若 有工程桩,直接将支撑柱插入临时支撑桩。 If there is no engineering pile under the support column, first construct the temporary support pile and then insert the support column into the temporary support pile. If there are engineered piles, insert the support columns directly into the temporary support piles.
(3)做一层环形外支撑、一层环形内支撑、混凝土桁架腹杆、一层支顶撑。 (3) Make a layer of ring-shaped outer support, a layer of ring-shaped inner support, concrete truss web members, and a layer of top support.
(4)挖土至二层环形支撑底标高部位,做二层环形支撑,围护墙在二层支撑部位局部剥落混凝土,在裸露主筋外面焊接预留钢筋,然后浇筑混凝土板、最后做二层支顶撑。 (4) Excavate the soil to the bottom elevation of the second-floor circular support, and make the second-floor circular support. The concrete of the enclosure wall is partially peeled off at the second-floor support, and the reserved steel bars are welded outside the exposed main reinforcement, and then the concrete slab is poured, and finally the second floor is built. support.
(5)挖土至地下室底板底标高以下10cm,先做素混凝土垫层,再浇筑地下室底板混凝土。 (5) Excavate the soil to 10cm below the bottom elevation of the basement floor, make a plain concrete cushion first, and then pour concrete for the basement floor.
在浇筑地下室底板施工时,对于涌水量大的部位采用疏堵相结合的技术方案,对于涌水量小,水压力小的部位采用强行封堵的方法,在浇捣素混凝土垫层时,局部范围内用掺了速凝剂的混凝土浇捣,混凝土在1~2min即凝固。对于涌水量大的情况,用塑料软管导水至集水坑中,待承台底板浇捣完并达到80%强度时再封闭集水坑。集水坑的封堵按以下进行:把水集中于钢管中,钢管直径为50mm,钢管内壁有螺纹;用螺头旋进钢管中封闭水管,浇筑底板预留坑的混凝土。预留坑的内壁设置凹槽用于止水,后浇混凝土掺U EA膨胀剂,确保新旧混凝土的良好结合。 When pouring the basement floor construction, the technical scheme of combining dredging and plugging is adopted for the parts with large water inflow, and the method of forced sealing is used for the parts with small water inflow and low water pressure. Concrete mixed with quick-setting agent is poured and pounded internally, and the concrete will solidify in 1-2 minutes. For the case of large water gushing, use a plastic hose to guide water into the sump, and close the sump when the bottom plate of the cap is poured and rammed and reaches 80% strength. The plugging of the sump is carried out as follows: Concentrate water in the steel pipe, the steel pipe diameter is 50mm, and the inner wall of the steel pipe is threaded; screw the screw head into the steel pipe to seal the water pipe, and pour the concrete for the reserved pit on the bottom plate. The inner wall of the reserved pit is provided with grooves for water stop, and the post-cast concrete is mixed with UEA expansion agent to ensure a good combination of old and new concrete.
(6)对二层环形支撑、混凝土板、二层支顶撑进行爆破,爆破完毕后拆除支撑柱。 (6) Blast the second-floor ring support, concrete slab, and second-floor roof support, and remove the support columns after the blasting is completed.
采用静态爆破,静态爆破所采用膨胀材料的膨胀力超过30MPa,静态爆破预留孔洞直径为30~40mm,预留孔洞间距为0.3~0.4m控制,端部预留孔洞留置位置距结构底面150mm~200mm,构件横截面上孔洞面积不超过截面面积10%;预留孔洞内钢筋混凝土构件的主筋或者箍筋割断,确保钢筋的束缚力不影响爆破效果。 Static blasting is adopted, the expansion force of the expansion material used in static blasting exceeds 30MPa, the diameter of the holes reserved for static blasting is 30-40mm, the distance between the reserved holes is controlled at 0.3-0.4m, and the distance between the reserved holes at the end and the bottom of the structure is 150mm~ 200mm, the area of holes in the cross-section of the member does not exceed 10% of the cross-sectional area; the main reinforcement or stirrup of the reinforced concrete member in the reserved hole is cut to ensure that the binding force of the reinforcement does not affect the blasting effect.
(7)浇筑二层地下室顶板。 (7) Pouring the roof of the second-floor basement.
(8)对一层环形外支撑、一层环形内支撑、混凝土桁架腹杆、一层支顶撑进行爆破。 (8) Blast the first layer of annular outer support, the first layer of annular inner support, the concrete truss web member, and the first layer of top support.
(9)浇筑一层地下室顶板。 (9) Pouring a basement roof.
附图说明 Description of drawings
图1为一层地下室环形支撑支护结构示意图,图2为二层地下室环形支撑支护结构示意图。 Figure 1 is a schematic diagram of a circular support structure for a first-floor basement, and Figure 2 is a schematic diagram of a circular support structure for a second-floor basement.
各附图中:1、围护墙,2、一层支顶撑,3、一层环形外支撑,4、一层环形内支撑,5、混凝土桁架腹杆,6、支撑柱,7、二层环形支撑,8、混凝土板,9、二层支顶撑。 In the attached drawings: 1. Enclosure wall, 2. First floor support, 3. First floor circular outer support, 4. First floor circular inner support, 5. Concrete truss web, 6. Support column, 7. Second floor Layer ring support, 8, concrete slab, 9, second floor support.
具体实施方式 Detailed ways
某工程为18层大楼,系框筒剪力墙结构,地下室开挖深度为7.2m,地下室 为不规则形状,工程桩为钻孔灌注桩,钻孔灌注桩深度为42m。 A project is an 18-story building with a frame-tube shear wall structure. The excavation depth of the basement is 7.2m, and the basement is irregular in shape.
本实施例设置两道支撑体系,第一道支撑设置在地下室顶部,第二道支撑设置在地下室中部,第一道支撑环形支撑做成桁架式结构,第二道支撑体系采用梁式环形支撑。四角部位围护结构和环形支撑支顶结构做成二层环形支撑8。 In this embodiment, two support systems are set, the first support is set on the top of the basement, the second support is set in the middle of the basement, the first support ring support is made into a truss structure, and the second support system adopts a beam-type ring support. The enclosure structure at the four corners and the ring support roof structure are made into two layers of ring support 8 .
围护墙1宽度为70mm,深度为地下室开挖深度2.5倍,围护墙1所采用的混凝土为C30,一层环形外支撑3离围护墙1的距离为2m,一层环形外支撑3宽度为30cm,高度为45cm,一层环形内支撑4离一层环形外支撑3距离为1.4m,一层环形外支撑3与围护墙1之间设置支顶撑,支顶撑宽度为30cm,高度为45cm,一层环形内支撑4宽度为30cm,高度为45cm,一层环形外支撑3和一层环形内支撑4之间设置混凝土桁架腹杆5,混凝土桁架腹杆5宽度为20cm,高度为45cm,一层环形内支撑4和一层环形外支撑3下面设置支撑柱6,支撑柱6采用混凝柱或者钢柱,支撑柱6尽量设置在工程桩上面,否则支撑柱6下面设置临时支撑桩。 The width of the enclosure wall 1 is 70mm, and the depth is 2.5 times of the excavation depth of the basement. The concrete used for the enclosure wall 1 is C30. The width is 30cm, the height is 45cm, the distance between the first layer of annular inner support 4 and the first layer of annular outer support 3 is 1.4m, and a support is set between the first layer of annular outer support 3 and the enclosure wall 1, and the width of the support is 30cm , a height of 45cm, a layer of annular inner support 4 with a width of 30cm and a height of 45cm, a concrete truss web 5 between the first layer of annular outer support 3 and the first layer of annular inner support 4, the width of the concrete truss web 5 is 20cm, The height is 45cm, and the support column 6 is set under the circular inner support 4 and the external support 3 of the first floor. The support column 6 adopts concrete columns or steel columns. Temporary support piles.
二层环形支撑7和围护墙1支顶结构采用二层环形支撑8和支顶撑相结合,地下室长边方向1/4长度范围和短边方向1/3长度范围内设置混凝土板,地下室中部位置设置支顶撑,二层支顶撑9与一层支顶撑2投影位置相同,二层环形支撑7的支撑柱6和一层环形外支撑3的支撑柱6相同。 The second-floor ring support 7 and the roof support structure of the enclosure wall 1 adopt the combination of the second-floor ring support 8 and the roof support. Concrete slabs are set within 1/4 of the length of the long side of the basement and 1/3 of the length of the short side of the basement. The central position is provided with a top support, and the two-layer top support 9 has the same projection position as the one-layer top support 2, and the support column 6 of the second-layer annular support 7 is identical to the support column 6 of the first-floor annular outer support 3.
一层支护撑伸入围护墙1内部,与围护墙1形成刚性连接,二层支护撑与围护墙1外面的预留钢筋进行焊接,形成铰接结构。 The first layer of support extends into the inside of the enclosure wall 1 to form a rigid connection with the enclosure wall 1 , and the second layer of support is welded with the reserved reinforcement outside the enclosure wall 1 to form a hinged structure.
施工步骤包括: Construction steps include:
(1)围护墙1施工。 (1) Construction of enclosure wall 1.
围护墙1施工采用空腹模板,空腹模板通过振动锤竖向往复振动产生的竖向激振力沉入地层,随即向空腹内注满浆液,当振动沉模提升时,浆液在重力作用下从模板下端注入槽孔内,先已沉入地层的模板成为后沉入模板的导向板,两块模板呈现板板相扣的作用,保证了各单板体在一个平面内紧密结合成墙。 The construction of enclosure wall 1 uses fasting formwork, and the fasting formwork sinks into the ground through the vertical excitation force generated by the vertical reciprocating vibration of the vibrating hammer, and then fills the fasting with slurry. The lower end of the formwork is injected into the slot hole, and the formwork that has sunk into the ground first becomes the guide plate that sinks into the formwork later, and the two formworks show the interlocking effect of the boards, ensuring that the single boards are tightly combined in one plane to form a wall.
施工工艺包括: Construction techniques include:
1)开挖预留槽; 1) Excavate the reserved slot;
2)预钻孔; 2) Pre-drilled holes;
在两块模板的结合处预钻孔,预钻孔直径为100cm; Pre-drill a hole at the junction of the two templates, the diameter of the pre-drilled hole is 100cm;
3)振动沉模; 3) Die sinking by vibration;
启动振锤,将第一块模板沉入地层中,达到设计深度,然后将第二块模板沿施工轴线在第一块前侧与第一块模板紧密并排,以第一块模板为导向板,沉入地层达到设计深度; Start the vibrating hammer, sink the first formwork into the ground to reach the design depth, then place the second formwork closely side by side with the first formwork along the construction axis at the front side of the first formwork, and use the first formwork as a guide plate, sink into the formation to reach the design depth;
4)灌注提升第一块模板; 4) Perfusion lifts the first template;
向第一块模板内灌注浆体,然后边提升边灌注,直至拔出地面,浆体留在槽孔内,灌注提升结束后,要保持浆体达到墙顶设计高程; Pour the slurry into the first template, and then pour it while lifting it until it is pulled out from the ground, and the slurry remains in the slot hole. After the filling and lifting, keep the slurry reaching the design elevation of the top of the wall;
5)再沉入模板; 5) sink into the template again;
以第二块模板为导向板,沉入地层达到设计深度,再灌注提升第二块模板;按以上程序循环施工,即可完成围护墙1。 Use the second formwork as a guide plate, sink into the ground to reach the design depth, refill and lift the second formwork; follow the above procedures to complete the enclosure wall 1.
(2)支撑柱6施工。 (2) Construction of support column 6 .
支撑柱6下面如无工程桩,先施工临时支撑桩后将支撑柱6插入临时支撑桩。若有工程桩,直接将支撑柱6插入临时支撑桩。 If there is no engineering pile below the support column 6, the support column 6 is inserted into the temporary support pile after the construction of the temporary support pile earlier. If there is an engineering pile, the support column 6 is directly inserted into the temporary support pile.
(3)做一层环形外支撑3、一层环形内支撑4、混凝土桁架腹杆5、一层支顶撑2。 (3) Make a layer of annular outer support 3, a layer of annular inner support 4, a concrete truss web member 5, and a layer of top support 2.
(4)挖土至二层环形支撑7底标高部位,做二层环形支撑7,围护墙1在二层支撑部位局部剥落混凝土,在裸露主筋外面焊接预留钢筋,然后浇筑二层环形支撑8、最后做二层支顶撑9。 (4) Excavate the earth to the bottom elevation of the second-floor circular support 7, and make the second-floor circular support 7. The enclosure wall 1 partially peels off the concrete at the second-floor support, welds the reserved steel bars outside the exposed main reinforcement, and then pours the second-floor circular support 8. Finally, make the second floor support and top support 9.
(5)挖土至地下室底板底标高以下10cm,先做素混凝土垫层,再浇筑地下室底板混凝土。 (5) Excavate the soil to 10cm below the bottom elevation of the basement floor, make a plain concrete cushion first, and then pour concrete for the basement floor.
在浇筑地下室底板施工时,对于涌水量大的部位采用疏堵相结合的技术方案,对于涌水量小,水压力小的部位采用强行封堵的方法,在浇捣素混凝土垫层时,局部范围内用掺了速凝剂的混凝土浇捣,混凝土在1~2min即凝固。对于涌水量大的情况,用塑料软管导水至集水坑中,待承台底板浇捣完并达到80%强度时再封闭集水坑。集水坑的封堵按以下进行:把水集中于钢管中,钢管直径为50mm,钢管内壁有螺纹;用螺头旋进钢管中封闭水管,浇筑底板预留坑的混凝土。预留坑的内壁设置凹槽用于止水,后浇混凝土掺U EA膨胀剂,确保新旧混凝土的良好结合。 When pouring the basement floor construction, the technical scheme of combining dredging and plugging is adopted for the parts with large water inflow, and the method of forced sealing is used for the parts with small water inflow and low water pressure. Concrete mixed with quick-setting agent is poured and pounded internally, and the concrete will solidify in 1-2 minutes. For the case of large water gushing, use a plastic hose to guide water into the sump, and close the sump when the bottom plate of the cap is poured and rammed and reaches 80% strength. The plugging of the sump is carried out as follows: Concentrate water in the steel pipe, the steel pipe diameter is 50mm, and the inner wall of the steel pipe is threaded; screw the screw head into the steel pipe to seal the water pipe, and pour the concrete for the reserved pit on the bottom plate. The inner wall of the reserved pit is provided with grooves for water stop, and the post-cast concrete is mixed with UEA expansion agent to ensure a good combination of old and new concrete.
(6)对二层环形支撑7、二层环形支撑8、二层支顶撑9进行爆破,爆破完毕后拆除支撑柱6。 (6) Blast the second-floor ring support 7, the second-floor ring support 8, and the second-floor top support 9, and remove the support column 6 after the blasting is completed.
采用静态爆破,静态爆破所采用膨胀材料的膨胀力为35MPa,静态爆破预留孔洞直径为35mm,预留孔洞间距为0.3~0.4m控制,端部预留孔洞留置位置距结构底面200mm,构件横截面上孔洞面积不超过截面面积10%;预留孔洞内钢筋混凝土构件的主筋或者箍筋割断,确保钢筋的束缚力不影响爆破效果。 Static blasting is adopted, the expansion force of the expansion material used in static blasting is 35MPa, the diameter of the hole reserved for static blasting is 35mm, the distance between the reserved holes is controlled at 0.3-0.4m, the reserved position of the end hole is 200mm from the bottom of the structure, and the transverse The area of holes on the cross-section shall not exceed 10% of the cross-sectional area; the main bars or stirrups of reinforced concrete members in the reserved holes shall be cut off to ensure that the binding force of the steel bars does not affect the blasting effect.
(7)浇筑二层地下室顶板。 (7) Pouring the roof of the second-floor basement.
(8)对一层环形外支撑3、一层环形内支撑4、混凝土桁架腹杆5、一层支顶撑2进行爆破。 (8) Blast the first layer of annular outer support 3, the first layer of annular inner support 4, the concrete truss web 5, and the first layer of top support 2. the
(9)浇筑一层地下室顶板。 (9) Pouring a basement roof.
通过计算机模拟仿真分析,对本结构与其他支护体系进行对比。第一种情况 为采用本实施例,第二种情况为单纯采用内支撑,第三种情况为一层二层采用环形支撑。表1为不同支护体系位移及力学性能对比,表中发现本实施例的支护最大水平位移远远小于第二种情况和第三种情况,分别为第二种情况的38.6%,为第二种情况的57.9%。本实施例的最大轴力显著减少,分别为第二种情况的59.6%,为第二种情况的79.9%。本实施例的最大弯矩显著减少,分别为第二种情况的62.8%,为第二种情况的79.0%。 Through computer simulation analysis, this structure is compared with other support systems. The first kind of situation is to adopt this embodiment, the second kind of situation is to simply adopt inner support, and the third kind of situation is to adopt ring support on the second floor of the first floor. Table 1 is a comparison of the displacement and mechanical properties of different support systems. It is found in the table that the maximum horizontal displacement of the support in this embodiment is far smaller than that of the second and third cases, which are 38.6% of the second case, which is the first 57.9% of the two cases. The maximum axial force of this embodiment is significantly reduced, being 59.6% and 79.9% of the second case, respectively. The maximum bending moment of this embodiment is significantly reduced, being 62.8% and 79.0% of the second case, respectively.
表1不同支护体系位移及力学性能对比 Table 1 Comparison of displacement and mechanical properties of different support systems
经现场检测该地下室在施工过程中结构稳定,支护位移不超过11mm,支撑梁结构稳定,无异常现象发生。 According to the on-site inspection, the structure of the basement is stable during the construction process, the support displacement does not exceed 11mm, the support beam structure is stable, and no abnormal phenomenon occurs.
Claims (7)
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510284234.8A CN105019553B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace supporting construction |
CN201710189849.1A CN106836240B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace construction method for supporting |
CN201710189850.4A CN106958247B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace support system |
CN201710189946.0A CN106894420B (en) | 2015-05-22 | 2015-05-22 | Basement construction method for supporting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510284234.8A CN105019553B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace supporting construction |
Related Child Applications (3)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710189849.1A Division CN106836240B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace construction method for supporting |
CN201710189850.4A Division CN106958247B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace support system |
CN201710189946.0A Division CN106894420B (en) | 2015-05-22 | 2015-05-22 | Basement construction method for supporting |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105019553A true CN105019553A (en) | 2015-11-04 |
CN105019553B CN105019553B (en) | 2017-07-28 |
Family
ID=54409820
Family Applications (4)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510284234.8A Expired - Fee Related CN105019553B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace supporting construction |
CN201710189849.1A Active CN106836240B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace construction method for supporting |
CN201710189850.4A Active CN106958247B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace support system |
CN201710189946.0A Expired - Fee Related CN106894420B (en) | 2015-05-22 | 2015-05-22 | Basement construction method for supporting |
Family Applications After (3)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710189849.1A Active CN106836240B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace construction method for supporting |
CN201710189850.4A Active CN106958247B (en) | 2015-05-22 | 2015-05-22 | Basement annular brace support system |
CN201710189946.0A Expired - Fee Related CN106894420B (en) | 2015-05-22 | 2015-05-22 | Basement construction method for supporting |
Country Status (1)
Country | Link |
---|---|
CN (4) | CN105019553B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108442508A (en) * | 2018-02-24 | 2018-08-24 | 广州大学 | A kind of double confinement ring frame structure systems |
CN109680722A (en) * | 2019-01-24 | 2019-04-26 | 江苏南通三建集团股份有限公司 | The construction method for setting external building access port is directly stayed on outer wall of basement body |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107338799B (en) * | 2017-09-15 | 2018-12-14 | 叶长青 | Large span foundation pit supporting construction |
CN108560582B (en) * | 2018-04-09 | 2023-08-29 | 成都利拓重工机械有限公司 | Movable support shield for urban pipe bag construction and limiting hinge thereof |
CN108487261A (en) * | 2018-04-10 | 2018-09-04 | 江西科技学院 | A kind of arch steel structure support |
CN113550329A (en) * | 2021-09-03 | 2021-10-26 | 朱彦达 | Multilayer basement supporting structure and supporting construction method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09264024A (en) * | 1996-03-29 | 1997-10-07 | Kawasaki Steel Corp | Earth retaining or deadline construction method |
KR100412162B1 (en) * | 2001-09-25 | 2003-12-24 | (주)신성엔지니어링 | Method of construction for excavating the ground by using trusstype support structures |
EP1243702B1 (en) * | 2001-03-13 | 2005-08-10 | Spie Fondations | Buttressing apparatus for an excavation shoring and use of the apparatus |
CN201347558Y (en) * | 2008-12-10 | 2009-11-18 | 广州市设计院 | Ring-shaped bracing structure system of deep and large foundation pit |
CN101666095A (en) * | 2009-09-11 | 2010-03-10 | 朱奎 | Irregular foundation pit support and construction method |
CN102535478A (en) * | 2011-12-30 | 2012-07-04 | 北京工业大学 | Enclosing purlin comprising square steel pipe and light concrete for supporting foundation pit |
CN102828520A (en) * | 2012-09-11 | 2012-12-19 | 中煤科工集团武汉设计研究院中汉岩土工程分公司 | Ring-shaped inner supporting structure used in deep peat soil deep foundation pit |
CN203684233U (en) * | 2013-12-27 | 2014-07-02 | 中铁大桥局集团第一工程有限公司 | Circular support structure for deep foundation pit |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4865300B2 (en) * | 2005-11-07 | 2012-02-01 | 株式会社ピーエス三菱 | Semi-underground road construction method |
CN201151909Y (en) * | 2007-11-15 | 2008-11-19 | 王平 | Deep foundation pit composite structure annular inner support |
KR101036173B1 (en) * | 2010-11-10 | 2011-05-23 | 영인산업 주식회사 | Spherical Supported Chiropractor |
CN202416324U (en) * | 2011-12-21 | 2012-09-05 | 上海建工一建集团有限公司 | Beam and slab structure superposed through top-down beam and down-top slab construction of foundation pit project |
CN103510524A (en) * | 2012-06-26 | 2014-01-15 | 邹宗煊 | Inclined circular annular pile and construction method thereof |
CN203403422U (en) * | 2013-06-06 | 2014-01-22 | 广西建工集团第五建筑工程有限责任公司 | Long-span reinforced concrete inner support structure of rectangular deep foundation pit |
CN103397777B (en) * | 2013-08-06 | 2015-12-02 | 胡彦彬 | A kind of attachment truss-like concrete wall template supports |
CN104264688B (en) * | 2014-10-22 | 2016-06-08 | 广州市城市规划勘测设计研究院 | Manually digging hole non-uniform pile support construction process |
-
2015
- 2015-05-22 CN CN201510284234.8A patent/CN105019553B/en not_active Expired - Fee Related
- 2015-05-22 CN CN201710189849.1A patent/CN106836240B/en active Active
- 2015-05-22 CN CN201710189850.4A patent/CN106958247B/en active Active
- 2015-05-22 CN CN201710189946.0A patent/CN106894420B/en not_active Expired - Fee Related
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09264024A (en) * | 1996-03-29 | 1997-10-07 | Kawasaki Steel Corp | Earth retaining or deadline construction method |
EP1243702B1 (en) * | 2001-03-13 | 2005-08-10 | Spie Fondations | Buttressing apparatus for an excavation shoring and use of the apparatus |
KR100412162B1 (en) * | 2001-09-25 | 2003-12-24 | (주)신성엔지니어링 | Method of construction for excavating the ground by using trusstype support structures |
CN201347558Y (en) * | 2008-12-10 | 2009-11-18 | 广州市设计院 | Ring-shaped bracing structure system of deep and large foundation pit |
CN101666095A (en) * | 2009-09-11 | 2010-03-10 | 朱奎 | Irregular foundation pit support and construction method |
CN102535478A (en) * | 2011-12-30 | 2012-07-04 | 北京工业大学 | Enclosing purlin comprising square steel pipe and light concrete for supporting foundation pit |
CN102828520A (en) * | 2012-09-11 | 2012-12-19 | 中煤科工集团武汉设计研究院中汉岩土工程分公司 | Ring-shaped inner supporting structure used in deep peat soil deep foundation pit |
CN203684233U (en) * | 2013-12-27 | 2014-07-02 | 中铁大桥局集团第一工程有限公司 | Circular support structure for deep foundation pit |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108442508A (en) * | 2018-02-24 | 2018-08-24 | 广州大学 | A kind of double confinement ring frame structure systems |
CN108442508B (en) * | 2018-02-24 | 2023-07-14 | 广州大学 | A Double Constraint Ring Frame Structure System |
CN109680722A (en) * | 2019-01-24 | 2019-04-26 | 江苏南通三建集团股份有限公司 | The construction method for setting external building access port is directly stayed on outer wall of basement body |
Also Published As
Publication number | Publication date |
---|---|
CN106894420A (en) | 2017-06-27 |
CN106958247A (en) | 2017-07-18 |
CN106958247B (en) | 2018-11-09 |
CN106894420B (en) | 2018-08-10 |
CN106836240B (en) | 2018-08-10 |
CN106836240A (en) | 2017-06-13 |
CN105019553B (en) | 2017-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106894420B (en) | Basement construction method for supporting | |
CN205742213U (en) | Foundation pit supporting construction | |
CN105201514B (en) | A kind of water-bearing stratum shaft wall structure and construction method | |
CN103790393B (en) | A kind of construction method of existing building structure integral replacement | |
CN103422510B (en) | Steel pipe frame type cofferdam structure and construction method | |
CN104389315B (en) | Consolidation grouting drilled pile wall and construction method thereof | |
CN106930277A (en) | A kind of construction of manual-excavation cast-in-place pile method | |
CN112081153B (en) | Lifting method of raft foundation high-rise building | |
CN104532957A (en) | Inversed construction method for adding basement in existing building | |
CN112942455A (en) | Reinforcing and lifting method for karst foundation high-rise building | |
CN101560766B (en) | Grid-like underground continuous wall plate and production method thereof | |
KR101187170B1 (en) | Application of under pinning method in remodeling | |
CN112081155A (en) | A method for strengthening and lifting of strip or box-shaped foundation buildings | |
CN106193644B (en) | Basement reconstruction structure with raft foundation building | |
CN107191001A (en) | Tear down and build the strengthening of foundation construction method of house foundation | |
CN112081158B (en) | Construction method for forming reinforced composite pile foundation by advanced grouting of high-rise building | |
CN112081157B (en) | Construction method for forming reinforced composite pile foundation by high-rise building retreating type grouting | |
CN105386779B (en) | The counterfort method of large underground structure is built in shallow embedding rock stratum | |
CN105951874A (en) | Retaining wall reinforcing structure and construction method thereof | |
CN107143149A (en) | A kind of existing masonry structure building sets up the construction method of basement | |
CN103911990B (en) | A kind of underwater pouring pipe column with retaining wall and its construction method | |
CN203782691U (en) | An underwater pouring pipe column with retaining wall and its internal mold system | |
CN105350547A (en) | Method applicable to inter-pile soil support of slope protection pile | |
CN106337421B (en) | A kind of lattice concrete is compound to go along with sb. to guard him piling wall and the construction method based on BIM | |
CN106149731A (en) | Main building basement construction method for supporting with annex |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP02 | Change in the address of a patent holder |
Address after: No. 16, Tongjiang Avenue, Chengguan Town, Nandan county, Hechi City, Guangxi Zhuang Autonomous Region Patentee after: Zhu Kui Address before: Ouhai District of Zhejiang city in Wenzhou province 325000 Rong Road No. 39 Patentee before: Zhu Kui |
|
CP02 | Change in the address of a patent holder | ||
TR01 | Transfer of patent right |
Effective date of registration: 20221216 Address after: 251221 Building A4, Collaborative Development Industrial Park, Dezhou High tech Zone, south of the west section of Tianchen Road, Yucheng National High tech Industrial Development Zone, Dezhou, Shandong Patentee after: Dezhou Paier mechanical equipment Co.,Ltd. Address before: No.16 Tongjiang Avenue, Chengguan Town, Nandan county, Hechi City, Guangxi Zhuang Autonomous Region 547200 Patentee before: Zhu Kui |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170728 |
|
CF01 | Termination of patent right due to non-payment of annual fee |