CN201151909Y - Deep foundation pit composite structure annular inner support - Google Patents

Deep foundation pit composite structure annular inner support Download PDF

Info

Publication number
CN201151909Y
CN201151909Y CNU2007200882093U CN200720088209U CN201151909Y CN 201151909 Y CN201151909 Y CN 201151909Y CN U2007200882093 U CNU2007200882093 U CN U2007200882093U CN 200720088209 U CN200720088209 U CN 200720088209U CN 201151909 Y CN201151909 Y CN 201151909Y
Authority
CN
China
Prior art keywords
steel
foundation ditch
vertical supporting
support bar
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
CNU2007200882093U
Other languages
Chinese (zh)
Inventor
王平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=40127587&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN201151909(Y) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Individual filed Critical Individual
Priority to CNU2007200882093U priority Critical patent/CN201151909Y/en
Application granted granted Critical
Publication of CN201151909Y publication Critical patent/CN201151909Y/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model provides a deep basal pit integrated configuration annular inner support, includes reinforced concrete annular beam, stand and bracing piece, the stand erects in the foundation ditch bottom, and reinforced concrete annular beam is located the stand upper end, the bracing piece is located between reinforced concrete annular beam and the vertical supporting construction of foundation ditch, characterized by the bracing piece is steel structural rod, and its both ends are connected with reinforced concrete annular beam and the vertical supporting construction of foundation ditch respectively. The utility model discloses can simplify construction process, reduction of erection time, reduce cost implements deep basal pit excavation process and atress in-process, can in time adjust steel construction support member according to the foundation ditch monitoring condition, makes the member atress more reasonable, optimize.

Description

Support in the deep foundation ditch combining structure annular
Technical field
The utility model relates to building, municipal engineering field, relates in particular in the deep foundation ditch combining structure annular to support.
Background technology
The annular inner supporting structure that the interior support of traditional deep foundation pit support is adopted mainly be made up of annular girder, column and support bar, but annular girder and support bar all adopts single reinforced concrete structure.Support in this reinforced concrete structure annular and have following problems: 1, annular girder in the annular inner supporting structure and support bar all adopt reinforced concrete structure can cause the construction period long; 2, full steel bar concrete annular inner supporting structure is removed long in time limit; 3, influence basement construction; Noise is big when 4, abolishing, and is big to the influence of surrounding enviroment; 5, full steel bar concrete annular inner supporting structure integral body is from great, and column and stand column pile are many, the cost height; 6, soil excavation inconvenience.
The utility model content
The purpose of this utility model is in order to solve the deficiency that the above-mentioned background technology exists, to propose interior support of deep foundation ditch combining structure annular of a kind of steel work and reinforced concrete structure combination, make it can simplify construction technology, the reduction of erection time, reducing cost.
For achieving the above object, the utility model adopts following technical scheme: support in a kind of deep foundation ditch combining structure annular, comprise steel bar concrete annular girder, column and support bar, described column is erected in the foundation ditch bottom, steel bar concrete annular girder position is by upright supports, described support bar is characterized in that described support bar is the steel work bar between steel bar concrete annular girder and the vertical supporting and protection structure of foundation ditch, its two ends are connected with the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch respectively.
What the link position of described steel work support bar and the vertical supporting and protection structure of foundation ditch preferably was arranged in the vertical supporting and protection structure of foundation ditch encloses the purlin place.
Weld with the metallic object that is embedded in the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch respectively at described steel work support bar two ends.
Preferred steel pipe of described steel work support bar or deformed steel.
The utlity model has following advantage:
1, the annular girder body adopts reinforced concrete structure, and other support bar adopts steel work, and it has given full play to the advantage of two kinds of structures, maximize favourable factors and minimize unfavourable ones, and the reinforced concrete structure convenient formation, material pressurized performance is good; Steel work is easy for installation as other straightway support bar, tension, pressure all can, the integral construction cycle is short.
2, interior support integral deadweight is light, and the column and the stand column pile of employing are few, and cost is low.
3, soil excavation is convenient.
4, the steel work support part divides dismounting convenient, and is little to underground cell structure construction infection, and the duration is short.
5, it is little to ambient influnence that dismounting is divided in the steel work support part.
6, because steel work has solderability, from heavy and light, stress performance good (pressurized, tension are all excellent), in implementing Deep Excavation and loading process, can monitor situation according to foundation ditch, in time adjust the steel work supporting rod, make rod member more reasonable stress, optimization.
Description of drawings
Fig. 1 is the vertical view that the utility model is positioned at deep foundation ditch.
Fig. 2 is an A-A sectional view among Fig. 1.
The specific embodiment
Referring to Fig. 1 and Fig. 2, the utility model comprises steel bar concrete annular girder 1, column 2 and support bar 3, and described column 2 is erected in the foundation ditch bottom, its upper end bearing bar concrete annular girder 1, and column 2 preferably adopts steel work, as the shaped steel of steel pipe, profile iron and so on.Described support bar 3 is the steel work bar, between steel bar concrete annular girder 1 and the vertical supporting and protection structure 4 of foundation ditch, its two ends respectively be embedded in steel bar concrete annular girder and the vertical supporting and protection structure of foundation ditch in enclose purlin place 5 be connected the metallic object welding.Described steel work support bar is deformed steels such as steel pipe or H shaped steel i iron, channel-section steel, angle steel, and the combination between the combination between the combination between steel pipe and the steel pipe, deformed steel and the deformed steel or steel pipe and the deformed steel.

Claims (4)

1, supports in a kind of deep foundation ditch combining structure annular, comprise steel bar concrete annular girder, column and support bar, described column is erected in the foundation ditch bottom, the steel bar concrete annular girder is by upright supports, described support bar is between steel bar concrete annular girder and the vertical supporting and protection structure of foundation ditch, it is characterized in that described support bar is the steel work bar, its two ends are connected with the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch respectively.
2, according to supporting in the described deep foundation ditch combining structure of claim 1 annular, what the link position that it is characterized in that described steel work support bar and the vertical supporting and protection structure of foundation ditch was arranged in the vertical supporting and protection structure of foundation ditch encloses the purlin place.
3, according to supporting in claim 1 or the 2 described deep foundation ditch combining structure annulars, it is characterized in that described steel work support bar two ends respectively with the metallic object welding that is embedded in the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch.
4, according to supporting in claim 1 or the 2 described deep foundation ditch combining structure annulars, it is characterized in that described steel work support bar is steel pipe or deformed steel, and the combination between the combination between the combination between steel pipe and the steel pipe, deformed steel and the deformed steel or steel pipe and the deformed steel.
CNU2007200882093U 2007-11-15 2007-11-15 Deep foundation pit composite structure annular inner support Ceased CN201151909Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200882093U CN201151909Y (en) 2007-11-15 2007-11-15 Deep foundation pit composite structure annular inner support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200882093U CN201151909Y (en) 2007-11-15 2007-11-15 Deep foundation pit composite structure annular inner support

Publications (1)

Publication Number Publication Date
CN201151909Y true CN201151909Y (en) 2008-11-19

Family

ID=40127587

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200882093U Ceased CN201151909Y (en) 2007-11-15 2007-11-15 Deep foundation pit composite structure annular inner support

Country Status (1)

Country Link
CN (1) CN201151909Y (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102322065A (en) * 2011-08-03 2012-01-18 华丰建设股份有限公司 Support in the road, the end of foundation pit supporting construction
CN102747735A (en) * 2012-07-06 2012-10-24 中国十七冶集团有限公司 Treatment method for abnormal deformation of deep foundation pit concrete support piling
CN102828520A (en) * 2012-09-11 2012-12-19 中煤科工集团武汉设计研究院中汉岩土工程分公司 Ring-shaped inner supporting structure used in deep peat soil deep foundation pit
CN102852150A (en) * 2012-10-12 2013-01-02 上海强劲地基工程股份有限公司 Superposed inner support structure for foundation pit support
CN103046556A (en) * 2011-10-17 2013-04-17 五冶集团上海有限公司 Inside-support-free ring-shaped enclosure structure and manufacturing method thereof
CN103711131A (en) * 2013-12-26 2014-04-09 中铁十三局集团第六工程有限公司 Ultra-soft soil large-area deep foundation pit guard post support changing method
CN104372797A (en) * 2014-10-11 2015-02-25 成都聚智工业设计有限公司 Foundation pit structure
CN104863160A (en) * 2015-04-09 2015-08-26 成都绿迪科技有限公司 Foundation pit supporting structure
CN106522241A (en) * 2016-12-14 2017-03-22 上海建工建集团有限公司 Deep foundation pit supporting method of ultrahigh floor height type basement structure
CN106958247A (en) * 2015-05-22 2017-07-18 朱奎 Basement annular brace support system
CN108442406A (en) * 2018-03-29 2018-08-24 中冶成都勘察研究总院有限公司 A kind of semi-inverse method internal support of foundation pit structure and its construction method
CN110158615A (en) * 2019-06-17 2019-08-23 中交第三公路工程局有限公司 High water level system of deep foundation pit support and its construction method
CN110485434A (en) * 2019-09-18 2019-11-22 建研地基基础工程有限责任公司 A kind of assembled annular steel construction internal support structure system and design method for deep foundation pit support
CN115288155A (en) * 2022-08-19 2022-11-04 中国一冶集团有限公司 Efficient building method of square-round combined ultra-deep permanent foundation pit supporting structure

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102322065A (en) * 2011-08-03 2012-01-18 华丰建设股份有限公司 Support in the road, the end of foundation pit supporting construction
CN102322065B (en) * 2011-08-03 2013-08-28 华丰建设股份有限公司 Bottom channel inner support of foundation pit supporting structure
CN103046556A (en) * 2011-10-17 2013-04-17 五冶集团上海有限公司 Inside-support-free ring-shaped enclosure structure and manufacturing method thereof
CN102747735A (en) * 2012-07-06 2012-10-24 中国十七冶集团有限公司 Treatment method for abnormal deformation of deep foundation pit concrete support piling
CN102828520A (en) * 2012-09-11 2012-12-19 中煤科工集团武汉设计研究院中汉岩土工程分公司 Ring-shaped inner supporting structure used in deep peat soil deep foundation pit
CN102852150A (en) * 2012-10-12 2013-01-02 上海强劲地基工程股份有限公司 Superposed inner support structure for foundation pit support
CN102852150B (en) * 2012-10-12 2014-08-13 上海强劲地基工程股份有限公司 Superposed inner support structure for foundation pit support
CN103711131A (en) * 2013-12-26 2014-04-09 中铁十三局集团第六工程有限公司 Ultra-soft soil large-area deep foundation pit guard post support changing method
CN104372797B (en) * 2014-10-11 2016-02-10 深圳市路桥建设集团有限公司 Foundation pit structure
CN104372797A (en) * 2014-10-11 2015-02-25 成都聚智工业设计有限公司 Foundation pit structure
CN104863160A (en) * 2015-04-09 2015-08-26 成都绿迪科技有限公司 Foundation pit supporting structure
CN106958247A (en) * 2015-05-22 2017-07-18 朱奎 Basement annular brace support system
CN106522241A (en) * 2016-12-14 2017-03-22 上海建工建集团有限公司 Deep foundation pit supporting method of ultrahigh floor height type basement structure
CN106522241B (en) * 2016-12-14 2019-04-12 上海建工一建集团有限公司 The method for supporting deep foundation pit of the high basement structure of super large layer
CN108442406A (en) * 2018-03-29 2018-08-24 中冶成都勘察研究总院有限公司 A kind of semi-inverse method internal support of foundation pit structure and its construction method
CN110158615A (en) * 2019-06-17 2019-08-23 中交第三公路工程局有限公司 High water level system of deep foundation pit support and its construction method
CN110485434A (en) * 2019-09-18 2019-11-22 建研地基基础工程有限责任公司 A kind of assembled annular steel construction internal support structure system and design method for deep foundation pit support
CN110485434B (en) * 2019-09-18 2021-07-23 建研地基基础工程有限责任公司 Fabricated annular steel structure inner support structure system for deep foundation pit supporting and design method
CN115288155A (en) * 2022-08-19 2022-11-04 中国一冶集团有限公司 Efficient building method of square-round combined ultra-deep permanent foundation pit supporting structure
CN115288155B (en) * 2022-08-19 2023-10-27 中国一冶集团有限公司 Efficient construction method of square and round combined ultra-deep permanent foundation pit supporting structure

Similar Documents

Publication Publication Date Title
CN201151909Y (en) Deep foundation pit composite structure annular inner support
CN201581409U (en) Combined tower crane foundation of cross beam supported by steel latticework columns in deep foundation pit
CN102839675A (en) Long-span pre-stress fish belly sill for foundation pit support and mounting method thereof
CN201296994Y (en) Multifunctional precast arch piece
CN201896318U (en) Tower crane foundation section and steel latticed column connecting structure
CN101851923A (en) Support pillar construction and erection method
CN206034479U (en) Tower crane relay handling supporter device
CN208440996U (en) A kind of novel inlet pipe
CN202755368U (en) Long span pre-stressing force fish-belly beam used for retaining and protecting foundation pit
CN215829426U (en) Foundation ditch construction supports optimization device
CN204783489U (en) Lattice formula aerogenerator pylon
CN204059947U (en) A kind of self-stabilization type outer wall formwork of basement support system
CN209585099U (en) A kind of substation truss assembled pile foundation using flanged joint
CN204645037U (en) A kind of anchor pier structure of lining cutting built-in type prestress anchorage cable
CN202298627U (en) Foundation pit supporting structure
CN210152295U (en) Can have enough to meet need reverse construction method steel-pipe column guiding device that hangs down of bolt formula
CN201896319U (en) Conversion platform for connecting tower crane basic section with steel lattice piles
CN202266065U (en) Heliostat pillar
CN203160800U (en) Lattice type steel rib concrete-filled steel tube composite component
CN211547754U (en) High slope anchor bolt support working platform
CN209412811U (en) A kind of filling pile structure
CN101642637A (en) Whirlwind tank and construction method thereof
CN201826326U (en) Foundation of deep-excavation tower crane
CN220927926U (en) Assembled spiral anchor foundation
CN219690497U (en) Energy-saving environment-friendly high-strength prestressed concrete pipe pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C35 Partial or whole invalidation of patent or utility model
IW01 Full invalidation of patent right

Decision date of declaring invalidation: 20101216

Decision number of declaring invalidation: 15775

Granted publication date: 20081119