CN201151909Y - Deep foundation pit composite structure annular inner support - Google Patents
Deep foundation pit composite structure annular inner support Download PDFInfo
- Publication number
- CN201151909Y CN201151909Y CNU2007200882093U CN200720088209U CN201151909Y CN 201151909 Y CN201151909 Y CN 201151909Y CN U2007200882093 U CNU2007200882093 U CN U2007200882093U CN 200720088209 U CN200720088209 U CN 200720088209U CN 201151909 Y CN201151909 Y CN 201151909Y
- Authority
- CN
- China
- Prior art keywords
- steel
- foundation ditch
- vertical supporting
- support bar
- reinforced concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
- 239000002131 composite material Substances 0.000 title 1
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 58
- 239000010959 steel Substances 0.000 claims abstract description 58
- 239000004567 concrete Substances 0.000 claims description 16
- 238000003466 welding Methods 0.000 claims description 2
- 239000011150 reinforced concrete Substances 0.000 abstract description 10
- 238000010276 construction Methods 0.000 abstract description 9
- 238000009412 basement excavation Methods 0.000 abstract description 4
- 238000000034 method Methods 0.000 abstract description 4
- 238000012544 monitoring process Methods 0.000 abstract 1
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 229910052742 iron Inorganic materials 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 208000015181 infectious disease Diseases 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
Images
Landscapes
- Foundations (AREA)
Abstract
The utility model provides a deep basal pit integrated configuration annular inner support, includes reinforced concrete annular beam, stand and bracing piece, the stand erects in the foundation ditch bottom, and reinforced concrete annular beam is located the stand upper end, the bracing piece is located between reinforced concrete annular beam and the vertical supporting construction of foundation ditch, characterized by the bracing piece is steel structural rod, and its both ends are connected with reinforced concrete annular beam and the vertical supporting construction of foundation ditch respectively. The utility model discloses can simplify construction process, reduction of erection time, reduce cost implements deep basal pit excavation process and atress in-process, can in time adjust steel construction support member according to the foundation ditch monitoring condition, makes the member atress more reasonable, optimize.
Description
Technical field
The utility model relates to building, municipal engineering field, relates in particular in the deep foundation ditch combining structure annular to support.
Background technology
The annular inner supporting structure that the interior support of traditional deep foundation pit support is adopted mainly be made up of annular girder, column and support bar, but annular girder and support bar all adopts single reinforced concrete structure.Support in this reinforced concrete structure annular and have following problems: 1, annular girder in the annular inner supporting structure and support bar all adopt reinforced concrete structure can cause the construction period long; 2, full steel bar concrete annular inner supporting structure is removed long in time limit; 3, influence basement construction; Noise is big when 4, abolishing, and is big to the influence of surrounding enviroment; 5, full steel bar concrete annular inner supporting structure integral body is from great, and column and stand column pile are many, the cost height; 6, soil excavation inconvenience.
The utility model content
The purpose of this utility model is in order to solve the deficiency that the above-mentioned background technology exists, to propose interior support of deep foundation ditch combining structure annular of a kind of steel work and reinforced concrete structure combination, make it can simplify construction technology, the reduction of erection time, reducing cost.
For achieving the above object, the utility model adopts following technical scheme: support in a kind of deep foundation ditch combining structure annular, comprise steel bar concrete annular girder, column and support bar, described column is erected in the foundation ditch bottom, steel bar concrete annular girder position is by upright supports, described support bar is characterized in that described support bar is the steel work bar between steel bar concrete annular girder and the vertical supporting and protection structure of foundation ditch, its two ends are connected with the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch respectively.
What the link position of described steel work support bar and the vertical supporting and protection structure of foundation ditch preferably was arranged in the vertical supporting and protection structure of foundation ditch encloses the purlin place.
Weld with the metallic object that is embedded in the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch respectively at described steel work support bar two ends.
Preferred steel pipe of described steel work support bar or deformed steel.
The utlity model has following advantage:
1, the annular girder body adopts reinforced concrete structure, and other support bar adopts steel work, and it has given full play to the advantage of two kinds of structures, maximize favourable factors and minimize unfavourable ones, and the reinforced concrete structure convenient formation, material pressurized performance is good; Steel work is easy for installation as other straightway support bar, tension, pressure all can, the integral construction cycle is short.
2, interior support integral deadweight is light, and the column and the stand column pile of employing are few, and cost is low.
3, soil excavation is convenient.
4, the steel work support part divides dismounting convenient, and is little to underground cell structure construction infection, and the duration is short.
5, it is little to ambient influnence that dismounting is divided in the steel work support part.
6, because steel work has solderability, from heavy and light, stress performance good (pressurized, tension are all excellent), in implementing Deep Excavation and loading process, can monitor situation according to foundation ditch, in time adjust the steel work supporting rod, make rod member more reasonable stress, optimization.
Description of drawings
Fig. 1 is the vertical view that the utility model is positioned at deep foundation ditch.
Fig. 2 is an A-A sectional view among Fig. 1.
The specific embodiment
Referring to Fig. 1 and Fig. 2, the utility model comprises steel bar concrete annular girder 1, column 2 and support bar 3, and described column 2 is erected in the foundation ditch bottom, its upper end bearing bar concrete annular girder 1, and column 2 preferably adopts steel work, as the shaped steel of steel pipe, profile iron and so on.Described support bar 3 is the steel work bar, between steel bar concrete annular girder 1 and the vertical supporting and protection structure 4 of foundation ditch, its two ends respectively be embedded in steel bar concrete annular girder and the vertical supporting and protection structure of foundation ditch in enclose purlin place 5 be connected the metallic object welding.Described steel work support bar is deformed steels such as steel pipe or H shaped steel i iron, channel-section steel, angle steel, and the combination between the combination between the combination between steel pipe and the steel pipe, deformed steel and the deformed steel or steel pipe and the deformed steel.
Claims (4)
1, supports in a kind of deep foundation ditch combining structure annular, comprise steel bar concrete annular girder, column and support bar, described column is erected in the foundation ditch bottom, the steel bar concrete annular girder is by upright supports, described support bar is between steel bar concrete annular girder and the vertical supporting and protection structure of foundation ditch, it is characterized in that described support bar is the steel work bar, its two ends are connected with the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch respectively.
2, according to supporting in the described deep foundation ditch combining structure of claim 1 annular, what the link position that it is characterized in that described steel work support bar and the vertical supporting and protection structure of foundation ditch was arranged in the vertical supporting and protection structure of foundation ditch encloses the purlin place.
3, according to supporting in claim 1 or the 2 described deep foundation ditch combining structure annulars, it is characterized in that described steel work support bar two ends respectively with the metallic object welding that is embedded in the vertical supporting and protection structure of steel bar concrete annular girder and foundation ditch.
4, according to supporting in claim 1 or the 2 described deep foundation ditch combining structure annulars, it is characterized in that described steel work support bar is steel pipe or deformed steel, and the combination between the combination between the combination between steel pipe and the steel pipe, deformed steel and the deformed steel or steel pipe and the deformed steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007200882093U CN201151909Y (en) | 2007-11-15 | 2007-11-15 | Deep foundation pit composite structure annular inner support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007200882093U CN201151909Y (en) | 2007-11-15 | 2007-11-15 | Deep foundation pit composite structure annular inner support |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201151909Y true CN201151909Y (en) | 2008-11-19 |
Family
ID=40127587
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2007200882093U Ceased CN201151909Y (en) | 2007-11-15 | 2007-11-15 | Deep foundation pit composite structure annular inner support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201151909Y (en) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102322065A (en) * | 2011-08-03 | 2012-01-18 | 华丰建设股份有限公司 | Support in the road, the end of foundation pit supporting construction |
CN102747735A (en) * | 2012-07-06 | 2012-10-24 | 中国十七冶集团有限公司 | Treatment method for abnormal deformation of deep foundation pit concrete support piling |
CN102828520A (en) * | 2012-09-11 | 2012-12-19 | 中煤科工集团武汉设计研究院中汉岩土工程分公司 | Ring-shaped inner supporting structure used in deep peat soil deep foundation pit |
CN102852150A (en) * | 2012-10-12 | 2013-01-02 | 上海强劲地基工程股份有限公司 | Superposed inner support structure for foundation pit support |
CN103046556A (en) * | 2011-10-17 | 2013-04-17 | 五冶集团上海有限公司 | Inside-support-free ring-shaped enclosure structure and manufacturing method thereof |
CN103711131A (en) * | 2013-12-26 | 2014-04-09 | 中铁十三局集团第六工程有限公司 | Ultra-soft soil large-area deep foundation pit guard post support changing method |
CN104372797A (en) * | 2014-10-11 | 2015-02-25 | 成都聚智工业设计有限公司 | Foundation pit structure |
CN104863160A (en) * | 2015-04-09 | 2015-08-26 | 成都绿迪科技有限公司 | Foundation pit supporting structure |
CN106522241A (en) * | 2016-12-14 | 2017-03-22 | 上海建工建集团有限公司 | Deep foundation pit supporting method of ultrahigh floor height type basement structure |
CN106958247A (en) * | 2015-05-22 | 2017-07-18 | 朱奎 | Basement annular brace support system |
CN108442406A (en) * | 2018-03-29 | 2018-08-24 | 中冶成都勘察研究总院有限公司 | A kind of semi-inverse method internal support of foundation pit structure and its construction method |
CN110158615A (en) * | 2019-06-17 | 2019-08-23 | 中交第三公路工程局有限公司 | High water level system of deep foundation pit support and its construction method |
CN110485434A (en) * | 2019-09-18 | 2019-11-22 | 建研地基基础工程有限责任公司 | A kind of assembled annular steel construction internal support structure system and design method for deep foundation pit support |
CN115288155A (en) * | 2022-08-19 | 2022-11-04 | 中国一冶集团有限公司 | Efficient building method of square-round combined ultra-deep permanent foundation pit supporting structure |
-
2007
- 2007-11-15 CN CNU2007200882093U patent/CN201151909Y/en not_active Ceased
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102322065A (en) * | 2011-08-03 | 2012-01-18 | 华丰建设股份有限公司 | Support in the road, the end of foundation pit supporting construction |
CN102322065B (en) * | 2011-08-03 | 2013-08-28 | 华丰建设股份有限公司 | Bottom channel inner support of foundation pit supporting structure |
CN103046556A (en) * | 2011-10-17 | 2013-04-17 | 五冶集团上海有限公司 | Inside-support-free ring-shaped enclosure structure and manufacturing method thereof |
CN102747735A (en) * | 2012-07-06 | 2012-10-24 | 中国十七冶集团有限公司 | Treatment method for abnormal deformation of deep foundation pit concrete support piling |
CN102828520A (en) * | 2012-09-11 | 2012-12-19 | 中煤科工集团武汉设计研究院中汉岩土工程分公司 | Ring-shaped inner supporting structure used in deep peat soil deep foundation pit |
CN102852150A (en) * | 2012-10-12 | 2013-01-02 | 上海强劲地基工程股份有限公司 | Superposed inner support structure for foundation pit support |
CN102852150B (en) * | 2012-10-12 | 2014-08-13 | 上海强劲地基工程股份有限公司 | Superposed inner support structure for foundation pit support |
CN103711131A (en) * | 2013-12-26 | 2014-04-09 | 中铁十三局集团第六工程有限公司 | Ultra-soft soil large-area deep foundation pit guard post support changing method |
CN104372797B (en) * | 2014-10-11 | 2016-02-10 | 深圳市路桥建设集团有限公司 | Foundation pit structure |
CN104372797A (en) * | 2014-10-11 | 2015-02-25 | 成都聚智工业设计有限公司 | Foundation pit structure |
CN104863160A (en) * | 2015-04-09 | 2015-08-26 | 成都绿迪科技有限公司 | Foundation pit supporting structure |
CN106958247A (en) * | 2015-05-22 | 2017-07-18 | 朱奎 | Basement annular brace support system |
CN106522241A (en) * | 2016-12-14 | 2017-03-22 | 上海建工建集团有限公司 | Deep foundation pit supporting method of ultrahigh floor height type basement structure |
CN106522241B (en) * | 2016-12-14 | 2019-04-12 | 上海建工一建集团有限公司 | The method for supporting deep foundation pit of the high basement structure of super large layer |
CN108442406A (en) * | 2018-03-29 | 2018-08-24 | 中冶成都勘察研究总院有限公司 | A kind of semi-inverse method internal support of foundation pit structure and its construction method |
CN110158615A (en) * | 2019-06-17 | 2019-08-23 | 中交第三公路工程局有限公司 | High water level system of deep foundation pit support and its construction method |
CN110485434A (en) * | 2019-09-18 | 2019-11-22 | 建研地基基础工程有限责任公司 | A kind of assembled annular steel construction internal support structure system and design method for deep foundation pit support |
CN110485434B (en) * | 2019-09-18 | 2021-07-23 | 建研地基基础工程有限责任公司 | Fabricated annular steel structure inner support structure system for deep foundation pit supporting and design method |
CN115288155A (en) * | 2022-08-19 | 2022-11-04 | 中国一冶集团有限公司 | Efficient building method of square-round combined ultra-deep permanent foundation pit supporting structure |
CN115288155B (en) * | 2022-08-19 | 2023-10-27 | 中国一冶集团有限公司 | Efficient construction method of square and round combined ultra-deep permanent foundation pit supporting structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201151909Y (en) | Deep foundation pit composite structure annular inner support | |
CN201581409U (en) | Combined tower crane foundation of cross beam supported by steel latticework columns in deep foundation pit | |
CN102839675A (en) | Long-span pre-stress fish belly sill for foundation pit support and mounting method thereof | |
CN201296994Y (en) | Multifunctional precast arch piece | |
CN201896318U (en) | Tower crane foundation section and steel latticed column connecting structure | |
CN101851923A (en) | Support pillar construction and erection method | |
CN206034479U (en) | Tower crane relay handling supporter device | |
CN208440996U (en) | A kind of novel inlet pipe | |
CN202755368U (en) | Long span pre-stressing force fish-belly beam used for retaining and protecting foundation pit | |
CN215829426U (en) | Foundation ditch construction supports optimization device | |
CN204783489U (en) | Lattice formula aerogenerator pylon | |
CN204059947U (en) | A kind of self-stabilization type outer wall formwork of basement support system | |
CN209585099U (en) | A kind of substation truss assembled pile foundation using flanged joint | |
CN204645037U (en) | A kind of anchor pier structure of lining cutting built-in type prestress anchorage cable | |
CN202298627U (en) | Foundation pit supporting structure | |
CN210152295U (en) | Can have enough to meet need reverse construction method steel-pipe column guiding device that hangs down of bolt formula | |
CN201896319U (en) | Conversion platform for connecting tower crane basic section with steel lattice piles | |
CN202266065U (en) | Heliostat pillar | |
CN203160800U (en) | Lattice type steel rib concrete-filled steel tube composite component | |
CN211547754U (en) | High slope anchor bolt support working platform | |
CN209412811U (en) | A kind of filling pile structure | |
CN101642637A (en) | Whirlwind tank and construction method thereof | |
CN201826326U (en) | Foundation of deep-excavation tower crane | |
CN220927926U (en) | Assembled spiral anchor foundation | |
CN219690497U (en) | Energy-saving environment-friendly high-strength prestressed concrete pipe pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C35 | Partial or whole invalidation of patent or utility model | ||
IW01 | Full invalidation of patent right |