CN104963656B - A kind of casing programme and its installation method for natural petroleum gas field - Google Patents

A kind of casing programme and its installation method for natural petroleum gas field Download PDF

Info

Publication number
CN104963656B
CN104963656B CN201510151847.4A CN201510151847A CN104963656B CN 104963656 B CN104963656 B CN 104963656B CN 201510151847 A CN201510151847 A CN 201510151847A CN 104963656 B CN104963656 B CN 104963656B
Authority
CN
China
Prior art keywords
oil pipe
well
layer sleeve
casing programme
inner layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510151847.4A
Other languages
Chinese (zh)
Other versions
CN104963656A (en
Inventor
张海山
罗勇
宫吉泽
陈伟宁
郭士生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC China Ltd Shanghai Branch
Original Assignee
China National Offshore Oil Corp CNOOC
CNOOC China Ltd Shanghai Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, CNOOC China Ltd Shanghai Branch filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201510151847.4A priority Critical patent/CN104963656B/en
Publication of CN104963656A publication Critical patent/CN104963656A/en
Application granted granted Critical
Publication of CN104963656B publication Critical patent/CN104963656B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The present invention relates to natural petroleum gas field field, disclose a kind of casing programme and its installation method for natural petroleum gas field, the casing programme includes outer layer sleeve (10), the inner layer sleeve (20) for setting and being stretched out from the outer layer sleeve (10) along the length direction of the outer layer sleeve (10) and the oil pipe (30) for extending along the length direction of the inner layer sleeve (20) and being stretched out from the inner layer sleeve (20), the periphery and bottom of the pipeline section of at least stretching inner layer sleeve (20) of the oil pipe (30) are provided with the first well cementation layer (40) for cementing the well, the oil pipe (30) and the corresponding position of the first well cementation layer (40) are provided with the oil gas input structure for making oil gas enter the oil pipe (30).In the present invention, the oil pipe for being served only for production in casing programme of the prior art is doubled as being production casing, so as to reduce the consumption of tubing, cost is reduced.

Description

A kind of casing programme and its installation method for natural petroleum gas field
Technical field
The present invention relates to natural petroleum gas field instrument, in particular it relates to a kind of well bore for natural petroleum gas field Structure and its installation method.
Background technology
With the development of economy and society, the exploitation dynamics of offshore oil natural gas is increasing.And opened in petroleum gas During adopting, casing programme is played and its important effect, briefly, casing programme are built upon ground and subterranean oil gas-bearing formation Between a gas channel.
Casing programme of the prior art includes outermost surface pipe, the protective casing in intermediate layer and innermost layer Production casing, the outside of production casing is provided with cement sheath.The surface pipe, protective casing and production casing formation one Passage, is provided with the oil pipe for conveying oil gas in the passage.
However, when exploiting middle-size and small-size and marginal field using above-mentioned casing programme, cost is higher, it is difficult to realize oil Gas economic is effectively developed.For this reason, it may be necessary to a kind of simple in construction, lower-cost casing programme be provided, to realize oil Gas economic is effectively developed.
The content of the invention
It is an object of the invention to provide a kind of casing programme and its installation method for natural petroleum gas field, to overcome Cost is higher in the prior art, it is difficult to realize the problem of petroleum gas economical and effective is developed.
To achieve these goals, the present invention provides a kind of casing programme for natural petroleum gas field, the well bore knot Structure include outer layer sleeve, along the outer layer sleeve length direction set and from the outer layer sleeve stretch out inner layer sleeve and Length direction extension and the oil pipe that stretches out from the inner layer sleeve along the inner layer sleeve, described at least stretching of the oil pipe The periphery and bottom of the pipeline section of inner layer sleeve are provided with the first well cementation layer for cementing the well, the oil pipe and the first well cementation layer Corresponding position is provided with the oil gas input structure for making oil gas enter the oil pipe.
Preferably, the pipeline section at least stretching out the outer layer sleeve of the periphery of the outer layer sleeve and the inner layer sleeve Periphery is equipped with the second well cementation layer, the second well cementation layer of the inner layer sleeve and second well cementation of the outer layer sleeve Layer is connected with each other, and the second well cementation layer of the inner layer sleeve is connected with each other with the described first well cementation layer.
Preferably, it is described first well cementation layer and second well cementation layer be cement layer.
Preferably, the oil gas input structure is the perforation to be formed on the oil pipe and the first well cementation layer.
Preferably, the upper initiating terminal of the inner layer sleeve, the upper initiating terminal of the outer layer sleeve and the oil pipe is upper Initiating terminal is respectively positioned on the pithead position of the casing programme.
Preferably, length direction of the casing programme including the well head from the casing programme along the oil pipe is set gradually Safety valve, side-pocket mandrel and circulating valve on the oil pipe.
Preferably, the oil pipe include the first oil pipe and along first oil pipe length direction extension and with described the Second oil pipe of one tubing seal connection.
Preferably, first oil pipe is located at the second oil pipe top, and second oil pipe is stretched from the inner layer sleeve Go out, the safety valve, side-pocket mandrel and circulating valve are arranged on first oil pipe and the safety valve, eccentric work Cylinder and circulating valve be respectively can cement the well formula storm valve, the formula that can cement the well side-pocket mandrel and the formula circulating valve that can cement the well.
The present invention also provides a kind of installation method of the casing programme for natural petroleum gas field, and the casing programme is Above-mentioned casing programme, the installation method comprises the following steps:
S1:By the outer layer sleeve tripping in into the first well being drilled;
S2:By the inner layer sleeve tripping in into the second well being drilled;
S3:By the oil pipe tripping in into the third wellbore being drilled;
S4:Described first is set to consolidate in the periphery of the pipeline section at least stretching out the inner layer sleeve of the oil pipe and bottom Well layer, and form the oil gas for making oil gas enter the oil pipe in the oil pipe position corresponding with the described first well cementation layer Input structure.
The present invention also provides a kind of installation method of the casing programme for natural petroleum gas field, and the casing programme is Above-mentioned casing programme, the installation method comprises the following steps:
S1:By the outer layer sleeve tripping in into the first well being drilled;
S2:By the inner layer sleeve tripping in into the second well being drilled;
S3:By the second oil pipe tripping in into the third wellbore being drilled;
S4:Described first is set in the pipeline section periphery at least stretching out the inner layer sleeve of second oil pipe and bottom Well cementation layer, and formed in second oil pipe position corresponding with the described first well cementation layer for making oil gas enter the oil pipe Oil gas input structure;
S5:Length direction tripping in by first oil pipe along second oil pipe simultaneously connects with second tubing seal Connect.
In the present invention, it is production casing that the oil pipe for being served only for production in casing programme of the prior art, which is doubled as, from And the consumption of tubing is reduced, reduce cost.
Other features and advantages of the present invention will be described in detail in subsequent embodiment part.
Brief description of the drawings
Accompanying drawing is, for providing a further understanding of the present invention, and to constitute a part for specification, with following tool Body embodiment is used to explain the present invention together, but is not construed as limiting the invention.In the accompanying drawings:
Fig. 1 is the schematic diagram for the casing programme for natural petroleum gas field that embodiments of the present invention are provided.
Fig. 2 is the schematic diagram for the casing programme for natural petroleum gas field that another embodiment of the present invention is provided.
Description of reference numerals
10:Outer layer sleeve; 20:Inner layer sleeve; 30:Oil pipe;
31:First oil pipe; 32:Second oil pipe; 40:First well cementation layer;
50:Second well cementation layer; 60:Perforation; 70:Safety valve;
80:Side-pocket mandrel; 90:Circulating valve. 100:Tail pipe is hung;
200:Float collar; 300:Float shoe.
Embodiment
The embodiment of the present invention is described in detail below in conjunction with accompanying drawing.It should be appreciated that this place is retouched The embodiment stated is merely to illustrate and explain the present invention, and is not intended to limit the invention.
In the present invention, in the case where not making opposite explanation, the noun of locality used such as " upper and lower, left and right " is typically referred to Upper and lower, left and right shown in refer to the attached drawing;" inside and outside " refers to the inside and outside of the profile relative to each part in itself.
The present invention is the cost existed based on casing programme of the prior art when exploiting middle-size and small-size and marginal field It is higher, it is difficult to which that realizing the problem of petroleum gas economical and effective is developed, there is provided simple in construction, the lower-cost well bore knot of one kind Structure, with reference to Fig. 1 and Fig. 2, the present invention will be described in detail.
As shown in figure 1, including outer layer sleeve 10, along outer provided by the present invention for the casing programme of natural petroleum gas field The length direction of layer sleeve pipe 10 is set and the inner layer sleeve 20 stretched out from outer layer sleeve 10 and the length side along inner layer sleeve 20 The oil pipe 30 stretched out to extension and from inner layer sleeve 20, the periphery and bottom of the pipeline section at least stretching out inner layer sleeve 20 of oil pipe 30 Portion is provided with the first well cementation layer 40 for cementing the well, and the corresponding position of the well cementation layer 40 of oil pipe 30 and first is provided with for making oil gas Into the oil gas input structure of oil pipe 30.
It should be noted that above-mentioned outer layer sleeve 10 can be the surface pipe of casing programme in the prior art, internal layer set Pipe 20 can be the protective casing of casing programme in the prior art.Furthermore it is possible to set float collar 200 and float shoe in the lower end of oil pipe 300, wherein float collar 200 is arranged on away from casing string (tubing string of the oil pipe 30 namely in the present invention) 20~30 meters of end, is risen The effect of retainer ring and back pressure valve, float shoe 300 is arranged on casing string (tubing string of the oil pipe 30 namely in the present invention) end, Play guide shoe and back pressure valve.It should be noted that so-called back pressure valve is a kind of interior jet-preventing tool in drilling process, It is a ball-and-seat, can prevents formation fluid from entering by bit port in drilling tool when blowout.So-called guide shoe refers to use What the pig iron, cement or hardwood were made is connected on a cone of casing string bottom, scrapes or inserts to prevent sleeve pipe base opening from touching The borehole wall, to shaft bottom under guiding sleeve (referring to oil pipe 30 here) is smooth.
In the present invention, it is production casing that the oil pipe for being served only for production in casing programme of the prior art, which is doubled as, from And the consumption of tubing is reduced, reduce cost.Casing programme of the prior art is additionally, since with two passages, that is, is used Annular space between the oil pipe and oil pipe and production casing of production of hydrocarbons, and the casing programme in the present invention only has one Individual passage, the i.e. oil pipe 30 for production of hydrocarbons, it is seen that the space that the casing programme in the present invention takes is smaller, in other words, The borehole size for being used to install outer layer sleeve 10, inner layer sleeve 20 and oil pipe 30 in the present invention has subtracted relative to prior art Small (this point is better able to explanation by table 1 below), therefore the engineering time is significantly reduced, and save drilling fluid and solid Well material.
Table 1:The comparison of casing programme of the prior art and the casing programme of the present invention
Through comparing, each borehole size of casing programme of the invention is to should be less than casing programme of the prior art Each borehole size, so that the casing programme in the present invention has advantages below:1) caving pressure on stratum will be reduced, well Wall is difficult unstability and collapsed;2) overall rate of penetration is significantly improved, the activity duration shorten (because, borehole size reduces, on The rate of penetration of portion's well section is increased substantially, and only bottom shortens rate of penetration after slim-hole size into and just has decline);3) due to Each borehole size reduces, so as to correspond ground sleeve pipe (outer layer sleeve 10, inner layer sleeve 20 and oil pipe 30) size Reduce, and then shell material weight is greatly reduced, reduce tubing expense.
In order to realize well cementation, the periphery of the outer layer sleeve 10 and the pipe at least stretching out outer layer sleeve 10 of inner layer sleeve 20 The periphery of section is equipped with the second well cementation layer 50, the second well cementation layer 50 of inner layer sleeve 20 and the second well cementation layer 50 of outer layer sleeve 10 It is connected with each other, and the second well cementation layer 50 of inner layer sleeve 20 is connected with each other with the first well cementation layer 40, wherein, the first well cementation He of layer 40 The material of second well cementation layer 50 can have a variety of, and the material of the such as first well cementation well cementation layer 50 of layer 40 and second can be cement.
Wherein, the oil gas input structure in casing programme is used for by oil-gas transportation into oil pipe 30, and for example oil gas is inputted Structure can be the perforation 60 cemented the well by perforator formation in oil pipe 30 and first on layer 40.
For easy for installation, Stability Analysis of Structures, the upper initiating terminal of the inner layer sleeve 20, the upper initiating terminal of outer layer sleeve 10 with And the upper initiating terminal of oil pipe 30 is respectively positioned on the pithead position of casing programme.
In addition, the operation in order to meet casing programme, the casing programme is included from the well head of casing programme along oil pipe 30 Length direction is successively set on safety valve 70, side-pocket mandrel 80 and circulating valve 90 on oil pipe 30.And in view of well cementation Problem, prevents that well cementing material (such as cement mortar) passes through shadow when safety valve 70, side-pocket mandrel 80 and circulating valve 90 during well cementation Respective service behaviour is rung, preferably described safety valve 70, side-pocket mandrel 80 and circulating valve 90 are respectively the formula underground that can cement the well Safety valve, the formula that can cement the well side-pocket mandrel and the formula circulating valve that can cement the well.Herein it should be noted that so-called formula underground peace of cementing the well Full valve, the formula that can cement the well side-pocket mandrel and the formula circulating valve that can cement the well refer to that cement mortar passes through storm valve, bias in well cementation During the downhole tools such as seating nipple, the normal of these instruments is not influenceed to use.
The oil pipe 30 can include the first oil pipe 31 and along the first oil pipe 31 length direction extension and with first oil The second oil pipe 32 that pipe 31 is tightly connected, specifically, the first oil pipe 31 are located at the top of the second oil pipe 32, and the second oil pipe 32 is from internal layer Sleeve pipe 20 is stretched out, and now safety valve 70, side-pocket mandrel 80 and circulating valve 90 can be arranged on the first oil pipe 31.Herein It should be noted that being tightly connected between the first oil pipe 31 and the second oil pipe 32 can be by setting in the upper end of the second oil pipe 32 Put tail pipe and hang 100,100 corresponding structures are hung with the tail pipe while being set in the lower end of the first oil pipe 31, so as to realize first Being tightly connected between the oil pipe 32 of oil pipe 31 and second.
According to another aspect of the present invention, the present invention also provides a kind of casing programme for natural petroleum gas field Installation method, casing programme here can be above-mentioned casing programme, and the installation method comprises the following steps:
S1:By the tripping in of outer layer sleeve 10 into the first well being drilled;
S2:By the tripping in of inner layer sleeve 20 into the second well being drilled;
S3:By the tripping in of oil pipe 30 into the third wellbore being drilled;
It should be noted that above-mentioned second well is in the lower section of the first well and diameter is less than first well, so that Form shoulder hole;Above-mentioned third wellbore is in the lower section of the second well and diameter is less than second well, so as to form shoulder hole.
S4:In the periphery and bottom of the pipeline section at least stretching out inner layer sleeve 20 of oil pipe 30, the first well cementation layer 40 is set, And form the oil gas input structure for making oil gas enter oil pipe 30 in the corresponding position of the well cementation layer 40 of oil pipe 30 and first.
The above method has advantages below:Outer layer sleeve 10, inner layer sleeve 20 and oil pipe 30 are installed using the above method, Make 30 times tripping in of oil pipe to its well, operation procedure is simple, and short time limit, expense is low, can preferably improve the exploitation of oil gas field Benefit, meanwhile, in the corresponding casing programme of the program, to prevent that well cementing material (such as cement mortar) is by safety valve during well cementation 70th, side-pocket mandrel 80 and respective service behaviour is influenceed during circulating valve 90, preferably described safety valve 70, side-pocket mandrel 80 And circulating valve 90 is respectively can cement the well formula storm valve, the formula that can cement the well side-pocket mandrel and the formula circulating valve that can cement the well.
According to a further aspect of the invention, the present invention also provides a kind of casing programme for natural petroleum gas field Installation method, casing programme here can be above-mentioned casing programme, and the installation method comprises the following steps:
S1:By the tripping in of outer layer sleeve 10 into the first well being drilled;
S2:By the tripping in of inner layer sleeve 20 into the second well being drilled;
S3:By the tripping in of the second oil pipe 32 into the third wellbore being drilled;
As described above, above-mentioned second well is in the lower section of the first well and diameter is less than first well, so as to be formed Shoulder hole;Above-mentioned third wellbore is in the lower section of the second well and diameter is less than second well, so as to form shoulder hole.
S4:In the pipeline section periphery and bottom of at least stretching out inner layer sleeve 20 of the second oil pipe 32, first well cementation is set Layer 40, and formed in the second oil pipe 32 and the corresponding position of the first well cementation layer 40 for making the oil gas of oil gas into oil pipe 30 defeated Enter structure;
S5:Length direction tripping in by the first oil pipe 31 along the second oil pipe 32 is simultaneously tightly connected with the second oil pipe 32.
This method has advantages below:First oil pipe on top is also arranged on when being cemented the well due to the second oil pipe 32 without tripping in 31, and the downhole tools such as safety valve 70, side-pocket mandrel 80 and circulating valve 90 are provided with the first oil pipe 31, therefore, well cementation Material (cement mortar) will not be impacted to the performance of these instruments, so as to use conventional safety valve 70, eccentric work Cylinder 80 and circulating valve 90 without use can cement the well formula storm valve, the formula that can cement the well side-pocket mandrel and the formula that can cement the well circulation Valve, job safety, economic and reliable, and also according to actual needs, the later stage can play out the first oil pipe 31 at any time, carry out well workover or sidetracking Deng operation.
The casing programme that the present invention is provided, not only saves expense in drilling process, while also being saved in completion practice Expense, specifically, it is production casing to double as oil pipe in the present invention, after drillng operation terminates tripping in oil pipe 30, drill ship Well site can be just withdrawn, the operation of oil pipe cable perforation can be carried out in production platform, the expense for renting drill ship can be reduced;Moreover, Casing programme well control risk is small in the present invention, because tearing preventer group and rise pipe open, installing in production tree device procedures, ground Layer is not connected with pit shaft;Perforating job is after the completion of the installation of production tree equipment, pressure testing, and well control risk is small in operation process;Meanwhile, The casing programme of the present invention is conducive to reservoir protection, because directly being gone into operation without kill-job after perforation, perforation after tripping in oil pipe, saves The kill-job activity duration, no well killing fluid is contacted with stratum, and the time of contact on completion fluid and stratum is greatly reduced, completion fluid is several Without leakage, the injury to stratum is reduced.
Beneficial effects of the present invention will be hereafter illustrated by specific embodiment, the oil pipe 30 in the embodiment is wrapped The first oil pipe 31 and the second oil pipe 32 are included, the finishing drilling well depth of the casing programme is 3613m, specifically, first, bores size (diameter) Well (the first well i.e. above) for 311.15mm is simultaneously drilled into 1457m, then that outer layer sleeve 10 is (a diameter of 244.48mm) tripping in is to 1452m;Secondly, size (diameter) is bored for 215.9mm well (the second well i.e. above) and is drilled into 2960m, then by the (a diameter of 177.8) tripping in 2950m of inner layer sleeve 20;Finally, bore size for 152.4mm well (i.e. Third wellbore above) and 3650m is drilled into, then by the (a diameter of 88.9) tripping in 3608m of the second oil pipe 32.
Above-mentioned drilling completion operation is substantially smooth, and gas well yield has reached expected volume, and saves expense, reduces Activity duration, huge economic benefit is realized, be embodied in following several respects:
1) tubing and casing expense is saved, specifically, under the conditions of identical well depth, casing programme and prior art in the present invention In casing programme compare, oil pipe 30 and sleeve pipe (outer layer sleeve 10 and inner layer sleeve 20) gross weight used compared with prior art reduce 135.74 tons (about 33%);
2) Master Costs such as drilling fluid and cementing slurry are reduced, specifically, the casing programme in the present invention is more existing Casing programme wellbore volume in technology reduces more than 50%, thus, related landwaste handling, drilling fluid, completion fluid expense About half is reduced, moreover, sleeve pipe (outer layer sleeve 10 and inner layer sleeve 20) annular volume of the casing programme in the present invention is reduced More than 50%, thus, related cementing slurry expense reduces 43% in original basis;
3) requirement of cleaning well cementation is met, specifically, the well cementation of the second oil pipe 32 in casing programme in the present invention Smoothly, later stage perforating job removes unobstructed, and the pipe string internal wall of the second oil pipe 32 does not remain cement mortar for operation.
4) significantly shorten and be drilled the well operations time, it is specifically, 27.39 days casing programme drilling well durations in the present invention, complete 4.92 days well durations, compared with casing programme of the prior art, the casing programme drilling well duration shortens 4.2%, completion period Shorten 44.78%, significantly reduce brill Completion cost, realize cost-effective exploitation.
The preferred embodiment of the present invention is described in detail above in association with accompanying drawing, still, the present invention is not limited to above-mentioned reality The detail in mode is applied, in the range of the technology design of the present invention, a variety of letters can be carried out to technical scheme Monotropic type, these simple variants belong to protection scope of the present invention.
It is further to note that each particular technique feature described in above-mentioned embodiment, in not lance In the case of shield, it can be combined by any suitable means.
In addition, various embodiments of the present invention can be combined randomly, as long as it is without prejudice to originally The thought of invention, it should equally be considered as content disclosed in this invention.

Claims (6)

1. a kind of casing programme for natural petroleum gas field, it is characterised in that the casing programme include outer layer sleeve (10), Set along the length direction of the outer layer sleeve (10) and the inner layer sleeve (20) stretched out from the outer layer sleeve (10) and edge The length direction extension of the inner layer sleeve (20) and the oil pipe (30) stretched out from the inner layer sleeve (20), the oil pipe (30) At least stretching inner layer sleeve (20) pipeline section periphery and bottom be provided with for cement the well first well cementation layer (40), institute State oil pipe (30) and the corresponding position of the first well cementation layer (40) is provided with for making oil gas enter the oil pipe (30) Oil gas input structure, length direction of the casing programme including the well head from the casing programme along the oil pipe (30) is set successively Safety valve (70), side-pocket mandrel (80) and circulating valve (90) on the oil pipe (30) are put, the oil pipe (30) includes First oil pipe (31) and along first oil pipe (31) length direction extend and be tightly connected with first oil pipe (31) The second oil pipe (32), first oil pipe (31) is located at the second oil pipe (32) top, and second oil pipe (32) is from institute Inner layer sleeve (20) stretching is stated, the safety valve (70), side-pocket mandrel (80) and circulating valve (90) are arranged at described the On one oil pipe (31) and the safety valve (70), side-pocket mandrel (80) and circulating valve (90) be respectively can cement the well formula underground peace Full valve, the formula that can cement the well side-pocket mandrel and the formula circulating valve that can cement the well.
2. the casing programme according to claim 1 for natural petroleum gas field, it is characterised in that the outer layer sleeve (10) periphery and the periphery of the pipeline section of at least stretching outer layer sleeve (10) of the inner layer sleeve (20) is equipped with second Well cementation layer (50), the second well cementation layer (50) of the inner layer sleeve (20) is consolidated with described the second of the outer layer sleeve (10) Well layer (50) is connected with each other, and the second well cementation layer (50) and described first well cementation layer (40) phase of the inner layer sleeve (20) Connect.
3. the casing programme according to claim 2 for natural petroleum gas field, it is characterised in that first well cementation Layer (40) and second cement the well layer (50) be cement layer.
4. the casing programme according to claim 1 for natural petroleum gas field, it is characterised in that the oil gas input Structure is the perforation (60) formed on the oil pipe (30) and the first well cementation layer (40).
5. the casing programme according to claim 4 for natural petroleum gas field, it is characterised in that the inner layer sleeve (20) the upper initiating terminal of upper initiating terminal, the upper initiating terminal of the outer layer sleeve (10) and the oil pipe (30) is respectively positioned on described The pithead position of casing programme.
6. the installation method of a kind of casing programme for natural petroleum gas field, it is characterised in that the casing programme is power Profit requires the casing programme described in any one in 1-5, and the installation method comprises the following steps:
S1:By the outer layer sleeve (10) tripping in into the first well being drilled;
S2:By the inner layer sleeve (20) tripping in into the second well being drilled;
S3:By the second oil pipe (32) tripping in into the third wellbore being drilled;
S4:Set described in the pipeline section periphery of at least stretching inner layer sleeve (20) of second oil pipe (32) and bottom First well cementation layer (40), and formed in second oil pipe (32) and the corresponding position of the first well cementation layer (40) for making Oil gas enters the oil gas input structure of the oil pipe (30);
S5:Length direction tripping in by first oil pipe (31) along second oil pipe (32) and with second oil pipe (32) It is tightly connected.
CN201510151847.4A 2015-04-01 2015-04-01 A kind of casing programme and its installation method for natural petroleum gas field Active CN104963656B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510151847.4A CN104963656B (en) 2015-04-01 2015-04-01 A kind of casing programme and its installation method for natural petroleum gas field

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510151847.4A CN104963656B (en) 2015-04-01 2015-04-01 A kind of casing programme and its installation method for natural petroleum gas field

Publications (2)

Publication Number Publication Date
CN104963656A CN104963656A (en) 2015-10-07
CN104963656B true CN104963656B (en) 2017-10-03

Family

ID=54217717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510151847.4A Active CN104963656B (en) 2015-04-01 2015-04-01 A kind of casing programme and its installation method for natural petroleum gas field

Country Status (1)

Country Link
CN (1) CN104963656B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593382A (en) * 2017-02-09 2017-04-26 撒占东 Method for collecting natural gas from producing well
CN106968650B (en) * 2017-03-21 2019-03-15 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 A method of administering surface pipe and gas-bearing formation casing annulus has channeling
CN108049816A (en) * 2017-12-11 2018-05-18 中国海洋石油集团有限公司 The narrow pressure window well four of deep water opens time Casing Program Design Method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050067163A1 (en) * 2003-09-25 2005-03-31 George Flint R. Monobore release for tubing conveyed perforating
CN101649740B (en) * 2009-09-03 2011-08-31 周福宝 Ground bored well body structure for gas extraction
CN203685139U (en) * 2013-12-26 2014-07-02 中国海洋石油总公司 Integrated pipe column for perforation, fracture and oil extraction for directional well on the sea
CN104405281B (en) * 2014-10-20 2016-02-03 山西蓝焰煤层气集团有限责任公司 One crosses goaf casing drilling process
CN204571946U (en) * 2015-04-01 2015-08-19 中国海洋石油总公司 A kind of casing programme for natural petroleum gas field

Also Published As

Publication number Publication date
CN104963656A (en) 2015-10-07

Similar Documents

Publication Publication Date Title
US7325609B2 (en) Completion apparatus and methods for use in hydrocarbon wells
EP0840834B1 (en) Apparatus and process for drilling and completing multiple wells
US9371694B2 (en) Permanent bypass whipstock assembly for drilling and completing a sidetrack well and preserving access to the original wellbore
CN201705219U (en) Lateral drilling gravel pack completion string
NO334494B1 (en) Method and apparatus for feeding and drilling a bore
RU2663840C2 (en) Well system and well finishing method
CN105952378A (en) Tree-shape structure well drilling and completion and yield increasing method
CN105275417A (en) Method for running in and out coiled tubing production string
NO333764B1 (en) One-hole borehole and method for completing the same
CN104963656B (en) A kind of casing programme and its installation method for natural petroleum gas field
US9816358B2 (en) Lining of well bores with expandable and conventional liners
NO20131114A1 (en) System and method high pressure high temperature feedback
CN205858311U (en) A kind of bore hole staged fracturing completion tubular column
CN204571946U (en) A kind of casing programme for natural petroleum gas field
CN102635335A (en) Well structure for delaying casing damage on fault
CN204186371U (en) Staged fracturing tool pipe column with first-section perforated casing sliding sleeve
CN208330212U (en) A kind of CBM Drilling casing programme
NO20110860A1 (en) High integrity suspension and seal for casing
CN106223898A (en) Two horizontal well cementing and completion integrated pipe column devices that open
RU2355873C1 (en) Well operating procedure
US11530595B2 (en) Systems and methods for horizontal well completions
US11506022B2 (en) Methods for well construction and completion
CN114183070A (en) Drilling method without drilling and closing under pressure
CN111058792A (en) Coiled tubing perforation-free under-pressure operation-free well completion device and method
US12163392B2 (en) Back pressure valve capsule

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 100010 Beijing, Chaoyangmen, North Street, No. 25, No.

Co-patentee after: Shanghai Branch of China National Offshore Oil Corporation

Patentee after: China Offshore Oil Group Co., Ltd.

Address before: 100010 Beijing City, Dongcheng District Chaoyangmen No. 25 North Street CNOOC building

Co-patentee before: Shanghai Branch of China National Offshore Oil Corporation

Patentee before: China National Offshore Oil Corporation

CP03 Change of name, title or address