CN104929529A - Ground drilling machine stabilizing frame and mounting method thereof - Google Patents
Ground drilling machine stabilizing frame and mounting method thereof Download PDFInfo
- Publication number
- CN104929529A CN104929529A CN201410109119.2A CN201410109119A CN104929529A CN 104929529 A CN104929529 A CN 104929529A CN 201410109119 A CN201410109119 A CN 201410109119A CN 104929529 A CN104929529 A CN 104929529A
- Authority
- CN
- China
- Prior art keywords
- angle steel
- rig
- anchor pole
- parallel
- corner bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Earth Drilling (AREA)
Abstract
The invention discloses a ground drilling machine stabilizing frame and a mounting method thereof, and relates to the technical field of exploration drilling machine stabilizing frames. The ground drilling machine stabilizing frame comprises two parallel sleepers mounted on a ground rock. A stabilizing frame body is fixed on the sleepers and comprises a corner bracket baseplate and a corner bracket arranged on the corner bracket baseplate. Through holes are formed in the corner bracket baseplate. The corner bracket comprises two triangular steel angles with same structures. Each triangular steel angle is composed of an oblique steel angle and a vertical steel angle. The bottoms of the oblique steel angles and the vertical steel angles are fixed on the corner bracket baseplate. The top ends of the triangular steel angles are fixed by a transverse steel angle. A pair of parallel steel angles is welded between the two vertical steel angles. Two parallel steel rods are welded on the parallel steel angles vertically. A drilling machine is fixedly mounted on the parallel steel rods. The ground drilling machine stabilizing frame and the mounting method thereof have the advantages that the drilling machine can be fixed on the ground rock firmly, construction of ground drilling at any angles can be completed, and the ground drilling machine stabilizing frame is simple in structure, high in strength, small in size and flexible.
Description
[technical field]
The present invention relates to exploratory drilling rig stabilizing bracket technical field, in particular, the present invention relates to a kind of earth's surface rig stabilizing bracket and mounting method thereof.
[background technology]
In recent years, " tunnel brill " exploration is promoted in China mine, develop very fast, KY150 series rig is rig the most frequently used in mine down-hole " tunnel brill " investigation and prospecting, and with reference to shown in Fig. 1, rig 1 passes through the effect of rig holder 2 and rig fixed support 3, be fixed in tunnel 4, the features such as it has that volume is little, maneuverability, comprehensive, multi-angle construction, being applicable to construction exploration in tunnel, down-hole, being widely used by domestic and international bargh.
Along with the exploitation year by year of old mine, resource exhaustion problem is more aobvious serious, carries out mine Peripheral Prospecting, sets up and widen standby mineral resources, is the only way solving resource environment constraint.Face this development pattern, KY150 series rig exposes shortcomings, as: rig " stabilizing bracket " can only be firm in tunnel, down-hole, and really cannot be firm at mining area ground, and this shortcoming has fettered the usage space of KY150 series rig greatly.
[summary of the invention]
The object of the invention is to the deficiency effectively overcoming above-mentioned technology, a kind of earth's surface rig stabilizing bracket is provided, this earth's surface rig stabilizing bracket effectively prevent rig can only be firm in tunnel, down-hole, and defect that can not be firm on earth's surface, its structure is simple, intensity is high, volume is little, maneuverability.
Technical scheme of the present invention is achieved in that it comprises two parallel sleepers be arranged on surface rock, and have rockbolt installation hole in sleeper, be interspersed with the anchor pole for fixing sleeper in this rockbolt installation hole, its improvements are:
Described sleeper is fixed with stabilizing bracket, and this stabilizing bracket is made up of corner bracket chassis and the corner bracket be arranged on corner bracket chassis, and described corner bracket chassis is provided with through hole, and the position of this through hole is corresponding with the position in rockbolt installation hole;
Described corner bracket comprises the identical triangle angle steel of two structures, this triangle angle steel is made up of oblique angle steel and vertical angle steel, and the bottom of oblique angle steel and vertical angle steel is all fixed on corner bracket chassis, the top of two triangle angle steel is fixed by a horizontal angle steel;
Be welded with pair of parallel angle steel between described two vertical angle steel, and this is to parallel angle steel being vertically welded with two parallel round steel, rig is then fixedly mounted on described parallel round steel.
In such a configuration, the top of described anchor pole is set in the through hole on sleeper installing hole and corner bracket chassis, and fixed by a nut, the remainder of described anchor pole is then imbedded in surface rock, and the angle of the remainder of the top of anchor pole and anchor pole is 135 °.
In such a configuration, described every bar sleeper has two rockbolt installation holes, the aperture in this rockbolt installation hole is 30mm, and described surface rock has four corresponding boltholes, the hole depth of this bolthole is 1000mm.
In such a configuration, the total length of described anchor pole is 1300mm, and the 1000mm place of described anchor pole is bent to the bent angle of 45 °.
In such a configuration, described sleeper is of a size of: height × wide × length=200mm × 200mm × 1200mm.
In such a configuration, described corner bracket chassis is square, and corner bracket chassis is of a size of: 1000mm × 1000mm.
In such a configuration, the length of described vertical angle steel is 1400mm, and the cross sectional dimensions of described oblique angle steel and vertical angle steel is: 80mm × 80mm.
In such a configuration, the diameter of described parallel round steel is 80mm, and the spacing of two parallel round steel center lines is 250mm.
In such a configuration, fixing gusset is provided with between parallel angle steel and corner bracket chassis.
Present invention further teaches a kind of mounting method being applicable to above-mentioned earth's surface rig stabilizing bracket, concrete, this mounting method includes following step:
A, need construction probing region surface rock on construction drill, formed bolthole, the construction angle of bolthole is 45 °, and the position of bolthole is thought corresponding with the position of the through hole on the rockbolt installation hole on sleeper and corner bracket chassis;
B, to be inserted by anchor pole in the bolthole of having constructed, insertion depth is 1000mm, and after anchor pole fixedly completes, the surplus of 300mm is left in ground rock outside;
C, the sleeper being height × wide × length=200mm × 200mm × 1200mm by two specifications are set on anchor pole, and sleeper plays cushioning effect;
D, on the vertical angle steel of stabilizing bracket, weld two parallel angle steel, vertical welding two parallel round steel on two parallel angle steel, after this position of corresponding for the through hole on corner bracket chassis anchor pole is installed and fall, with nut, stabilizing bracket is locked on anchor pole;
E, rig to be arranged on the parallel round steel of stabilizing bracket, then to complete drilling construction by rig.
Beneficial effect of the present invention is: the earth's surface rig stabilizing bracket that one, the present invention disclose effectively overcomes existing KY150 series rig and firmly can only construct in tunnel, down-hole, and the deficiency firmly can not constructed on earth's surface, can be good at realizing firmly constructing on earth's surface; Two, earth's surface of the present invention rig stabilizing bracket technique simple, adopt angle steel to be welded, make structure more rationally, securement strength is high; Three, the material of earth's surface rig stabilizing bracket is corrosion-resistant, long service life, and cost performance is high; Four, earth's surface of the present invention rig stabilizing bracket volume is little, lightweight, maneuverability, and fitting operation is convenient; Five, its interlock performance is good, and adjustable extent is large, is applicable to the arbitrarily angled drilling operation in earth's surface.
[accompanying drawing explanation]
Fig. 1 is the working state figure of rig in prior art;
Fig. 2 is schematic perspective view of the present invention.
[detailed description of the invention]
Below in conjunction with drawings and Examples, the invention will be further described.
With reference to shown in Fig. 2, for a kind of earth's surface rig stabilizing bracket that the present invention discloses, this earth's surface rig stabilizing bracket comprises two parallel sleepers 20 be fixedly mounted on surface rock 10, in the present embodiment, sleeper 20 is of a size of: height × wide × length=200mm × 200mm × 1200mm, there are in each sleeper 20 two rockbolt installation holes respectively, the aperture in rockbolt installation hole is 30mm, surface rock 10 have four corresponding boltholes, the hole depth of this bolthole is 1000mm, is interspersed with the anchor pole 30 for fixing sleeper 20 in the rockbolt installation hole of sleeper 20.
Described sleeper 20 is fixed with stabilizing bracket, and this stabilizing bracket is made up of corner bracket chassis 401 and the corner bracket be arranged on corner bracket chassis 401, and the corner bracket chassis 401 described in the present embodiment is square, and corner bracket chassis 401 is of a size of: 1000mm × 1000mm; Corner bracket chassis 401 is provided with four through holes, and the position of this through hole is corresponding with the position in rockbolt installation hole, the top of above-mentioned anchor pole 30 is set in the through hole on sleeper installing hole and corner bracket chassis 401, and fixed by a nut, the remainder of described anchor pole 30 is then imbedded in surface rock 10, and the angle of the remainder of the top of anchor pole 30 and anchor pole 30 is 135 °; In anchor pole 30 manufacturing process, the total length of anchor pole 30 is 1300mm, after the 1000mm place 45-degree-buckling of anchor pole 30, namely forms above-mentioned anchor pole 30.
Further, we are described in detail the concrete structure of corner bracket, corner bracket comprises the identical triangle angle steel 40 of two structures, this triangle angle steel 40 is made up of oblique angle steel 402 and vertical angle steel 403, and the bottom of oblique angle steel 402 and vertical angle steel 403 is all fixed on corner bracket chassis 401, the mode of general employing welding is fixed, and oblique angle steel 402, vertical angle steel 403 and corner bracket chassis 401 constitute the structure of right-angled triangle, and this structure has good firm performance.Continue with reference to Fig. 1, the top of two triangle angle steel 40 is fixed by a horizontal angle steel 404, pair of parallel angle steel 50 is welded with between two vertical angle steel 403, this be arranged in parallel with above-mentioned horizontal angle steel 404 to parallel angle steel 50, in addition, to parallel angle steel 50 being vertically welded with two parallel round steel 60,70, rig is fixedly mounted on described parallel round steel 60, is provided with fixing gusset 80 between parallel angle steel 50 and corner bracket chassis 10.Wherein, the length of described vertical angle steel 403 is 1400mm, and the cross sectional dimensions of vertical angle steel 403 and oblique angle steel 402 is: 80mm × 80mm; The diameter of parallel round steel 60 is 80mm, and the spacing of two parallel round steel 60 center lines is 250mm.
Rig 70 is stabilized on surface rock 10 by above-mentioned structure by the present invention, and can complete the construction of earth's surface all angles boring, its structure is simple, intensity is high, volume is little, maneuverability, can be suitable on the surface rock of various environment.
In addition, we carry out detailed explanation in conjunction with the mounting method of said structure to earth's surface of the present invention rig stabilizing bracket and illustrate, concrete the comprising the following steps: of this mounting method
A, need construction probing region surface rock 10 on construction drill, formed bolthole, the construction angle of bolthole is 45 °, and the position of bolthole is corresponding with the position of the through hole on the rockbolt installation hole on sleeper 10 and corner bracket chassis 10;
B, to be inserted by anchor pole 30 in the bolthole of having constructed, insertion depth is 1000mm, and after anchor pole 30 fixedly completes, the surplus of 300mm is left in ground rock 10 outside;
C, the sleeper being height × wide × length=200mm × 200mm × 1200mm by two specifications are set on anchor pole 10, and sleeper 20 plays cushioning effect;
D, on the vertical angle steel 403 of stabilizing bracket weld two parallel angle steel 50, the parallel round steel 60 of vertical welding two on two parallel angle steel 50, after this position of corresponding for the through hole on corner bracket chassis 401 anchor pole 30 is installed and fall, with nut, stabilizing bracket is locked on sleeper 20;
E, rig 70 is arranged on the parallel round steel 60 of stabilizing bracket, then completes drilling construction by rig 70.
By above-mentioned describe known, the mounting method of a kind of earth's surface rig stabilizing bracket that the present invention discloses and this earth's surface rig stabilizing bracket, the earth's surface rig stabilizing bracket of this kind of structure effectively overcomes KY150 series rig can only be firm in tunnel, down-hole, and deficiency that can not be firm on earth's surface, and the earth's surface rig stabilizing bracket of this kind of structure has that structure is simple, intensity is high, volume is little, the advantage of maneuverability, earth's surface probing effectively can be implemented.
Described above is only preferred embodiment of the present invention, and above-mentioned specific embodiment is not limitation of the present invention.In technological thought category of the present invention, can occur various distortion and amendment, all those of ordinary skill in the art, according to describing retouching, the amendment made above or equivalent replacing, all belong to the scope that the present invention protects.
Claims (10)
1. an earth's surface rig stabilizing bracket, it comprises two parallel sleepers be arranged on surface rock, has rockbolt installation hole in sleeper, is interspersed with the anchor pole for fixing sleeper, it is characterized in that in this rockbolt installation hole:
Described sleeper is fixed with stabilizing bracket, and this stabilizing bracket is made up of corner bracket chassis and the corner bracket be arranged on corner bracket chassis, and described corner bracket chassis is provided with through hole, and the position of this through hole is corresponding with the position in rockbolt installation hole;
Described corner bracket comprises the identical triangle angle steel of two structures, this triangle angle steel is made up of oblique angle steel and vertical angle steel, and the bottom of oblique angle steel and vertical angle steel is all fixed on corner bracket chassis, the top of two triangle angle steel is fixed by a horizontal angle steel;
Be welded with pair of parallel angle steel between described two vertical angle steel, and this is to parallel angle steel being vertically welded with two parallel round steel, rig is then fixedly mounted on described parallel round steel.
2. a kind of earth's surface according to claim 1 rig stabilizing bracket, it is characterized in that: the top of described anchor pole is set in the through hole on sleeper installing hole and corner bracket chassis, and fixed by a nut, the remainder of described anchor pole is then imbedded in surface rock, and the angle of the remainder of the top of anchor pole and anchor pole is 135 °.
3. a kind of earth's surface according to claim 2 rig stabilizing bracket, it is characterized in that: described every bar sleeper has two rockbolt installation holes, the aperture in this rockbolt installation hole is 30mm, and described surface rock has four corresponding boltholes, the hole depth of this bolthole is 1000mm.
4. a kind of earth's surface according to claim 3 rig stabilizing bracket, is characterized in that: the total length of described anchor pole is 1300mm, and the 1000mm place of described anchor pole is bent to the bent angle of 45 °.
5. a kind of earth's surface according to claim 1 rig stabilizing bracket, is characterized in that: described sleeper is of a size of: height × wide × length=200mm × 200mm × 1200mm.
6. a kind of earth's surface according to claim 1 rig stabilizing bracket, is characterized in that: described corner bracket chassis is square, and corner bracket chassis is of a size of: 1000mm × 1000mm.
7. a kind of earth's surface according to claim 1 rig stabilizing bracket, is characterized in that: the length of described vertical angle steel is 1400mm, and the cross sectional dimensions of described oblique angle steel and vertical angle steel is: 80mm × 80mm.
8. a kind of earth's surface according to claim 1 rig stabilizing bracket, it is characterized in that: the diameter of described parallel round steel is 80mm, the spacing of two parallel round steel center lines is 250mm.
9. a kind of earth's surface according to claim 1 rig stabilizing bracket, is characterized in that: be provided with fixing gusset between described parallel angle steel and corner bracket chassis.
10. be suitable for, with a mounting method for earth's surface according to claim 1 rig stabilizing bracket, it is characterized in that: the method comprises the following steps:
A, need construction probing region surface rock on construction drill, formed bolthole, the construction angle of bolthole is 45 °, and the position of bolthole is corresponding with the position of the through hole on the rockbolt installation hole on sleeper and corner bracket chassis;
B, to be inserted by anchor pole in the bolthole of having constructed, insertion depth is 1000mm, and after anchor pole fixedly completes, the surplus of 300mm is left in ground rock outside;
C, the sleeper being height × wide × length=200mm × 200mm × 1200mm by two specifications are set on anchor pole, and sleeper plays cushioning effect;
D, on the vertical angle steel of stabilizing bracket, weld two parallel angle steel, vertical welding two parallel round steel on two parallel angle steel, after this position of corresponding for the through hole on corner bracket chassis anchor pole is installed and fall, with nut, stabilizing bracket is locked on anchor pole;
E, rig to be arranged on the parallel round steel of stabilizing bracket, then to complete drilling construction by rig.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410109119.2A CN104929529B (en) | 2014-03-21 | 2014-03-21 | A kind of earth's surface rig stabilizing bracket and its installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410109119.2A CN104929529B (en) | 2014-03-21 | 2014-03-21 | A kind of earth's surface rig stabilizing bracket and its installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104929529A true CN104929529A (en) | 2015-09-23 |
CN104929529B CN104929529B (en) | 2017-11-10 |
Family
ID=54116923
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410109119.2A Active CN104929529B (en) | 2014-03-21 | 2014-03-21 | A kind of earth's surface rig stabilizing bracket and its installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104929529B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110159191A (en) * | 2019-05-30 | 2019-08-23 | 国网河南省电力公司内乡县供电公司 | The device of wired pipe is excavated under a kind of road surface |
CN111963068A (en) * | 2020-09-24 | 2020-11-20 | 重庆地质矿产研究院 | Mountain Mobile Detachable Drilling Platform |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4024924A (en) * | 1975-07-07 | 1977-05-24 | Parker Drilling Company, Inc. | Drilling rig with independent table structure |
CN2255499Y (en) * | 1996-07-08 | 1997-06-04 | 张传国 | Practical omnibearing mini-sized drilling machine |
CN101886400A (en) * | 2010-07-01 | 2010-11-17 | 江苏新誉重工科技有限公司 | Foundation of wind generating set |
CN202023516U (en) * | 2011-04-13 | 2011-11-02 | 东北石油大学 | Similar model prototype for gear rack drilling machine |
CN102305025A (en) * | 2011-09-21 | 2012-01-04 | 鹤壁煤电股份有限公司第六煤矿 | Anchor cable rig bracket |
CN102900360A (en) * | 2011-07-28 | 2013-01-30 | 华北电网有限公司 | Combined type digging and drilling machine |
CN203213114U (en) * | 2013-03-27 | 2013-09-25 | 中国水利水电第七工程局成都水电建设工程有限公司 | Quadrupod for grouting |
CN203808851U (en) * | 2014-03-21 | 2014-09-03 | 中国有色集团抚顺红透山矿业有限公司 | Earth surface drilling machine stabilization frame |
-
2014
- 2014-03-21 CN CN201410109119.2A patent/CN104929529B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4024924A (en) * | 1975-07-07 | 1977-05-24 | Parker Drilling Company, Inc. | Drilling rig with independent table structure |
CN2255499Y (en) * | 1996-07-08 | 1997-06-04 | 张传国 | Practical omnibearing mini-sized drilling machine |
CN101886400A (en) * | 2010-07-01 | 2010-11-17 | 江苏新誉重工科技有限公司 | Foundation of wind generating set |
CN202023516U (en) * | 2011-04-13 | 2011-11-02 | 东北石油大学 | Similar model prototype for gear rack drilling machine |
CN102900360A (en) * | 2011-07-28 | 2013-01-30 | 华北电网有限公司 | Combined type digging and drilling machine |
CN102305025A (en) * | 2011-09-21 | 2012-01-04 | 鹤壁煤电股份有限公司第六煤矿 | Anchor cable rig bracket |
CN203213114U (en) * | 2013-03-27 | 2013-09-25 | 中国水利水电第七工程局成都水电建设工程有限公司 | Quadrupod for grouting |
CN203808851U (en) * | 2014-03-21 | 2014-09-03 | 中国有色集团抚顺红透山矿业有限公司 | Earth surface drilling machine stabilization frame |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110159191A (en) * | 2019-05-30 | 2019-08-23 | 国网河南省电力公司内乡县供电公司 | The device of wired pipe is excavated under a kind of road surface |
CN111963068A (en) * | 2020-09-24 | 2020-11-20 | 重庆地质矿产研究院 | Mountain Mobile Detachable Drilling Platform |
CN111963068B (en) * | 2020-09-24 | 2022-03-29 | 重庆地质矿产研究院 | Movable detachable drilling platform for mountainous region |
Also Published As
Publication number | Publication date |
---|---|
CN104929529B (en) | 2017-11-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203808851U (en) | Earth surface drilling machine stabilization frame | |
CN203625893U (en) | Rock-embedded cast-in-place pile | |
CN104929529A (en) | Ground drilling machine stabilizing frame and mounting method thereof | |
CN103410529B (en) | A kind of support of tunnel arch springing ruggedized construction for weak surrounding rock and construction method | |
CN203867601U (en) | Tunnel arch replacing construction supporting structure | |
CN102748046B (en) | Double-layer anchor plate | |
CN206144464U (en) | A controlling means for improving diving drill machine straightness that hangs down | |
CN206960679U (en) | A kind of portable mobile wireless electric wave underground electro magnetic wave perradiator transmitting coil support | |
CN205918362U (en) | Take drill bit of bore bit | |
CN204386521U (en) | Unload the supporting seat of pipe machine | |
CN204386522U (en) | The drilling rod supporting seat unloading pipe machine | |
CN208517947U (en) | Steel pipe column can be recycled in combined type | |
CN207499888U (en) | A kind of support device of constructing tunnel arch roof-bolter | |
CN221609931U (en) | Modular drill rod limiting device | |
CN103806443B (en) | A kind of pile tube for ground minor installation and manufacture method thereof | |
CN204419158U (en) | A kind of nearly drill bit bracing or strutting arrangement | |
CN104563881A (en) | Novel reamer | |
CN103266856B (en) | Rotary drilling rig and follow-up frame thereof | |
CN210335906U (en) | Drilling core sample display rack | |
CN203701082U (en) | Tube pile for small ground facilities | |
CN219012650U (en) | Broken stratum supporting equipment in gold mine district | |
CN104533322B (en) | Unload the support seat of pipe machine | |
CN220415386U (en) | Sand pebble stratum existing tunnel structure protection structure | |
JP5126758B1 (en) | Concrete boundary block | |
CN213331140U (en) | Temporary supporting device for coal mining and tunneling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |