CN104775417B - The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation - Google Patents

The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation Download PDF

Info

Publication number
CN104775417B
CN104775417B CN201510192767.3A CN201510192767A CN104775417B CN 104775417 B CN104775417 B CN 104775417B CN 201510192767 A CN201510192767 A CN 201510192767A CN 104775417 B CN104775417 B CN 104775417B
Authority
CN
China
Prior art keywords
mattress layer
pressure cell
reinforcing bar
composite foundation
major diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510192767.3A
Other languages
Chinese (zh)
Other versions
CN104775417A (en
Inventor
彭涛
邓安
李耀家
高晓峰
许可
伍雨寒
任东兴
谢炎冰
刘旅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Chengdu Survey Design and Research Co Ltd
Original Assignee
CREEC Chengdu Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Chengdu Survey Design and Research Co Ltd filed Critical CREEC Chengdu Survey Design and Research Co Ltd
Priority to CN201510192767.3A priority Critical patent/CN104775417B/en
Publication of CN104775417A publication Critical patent/CN104775417A/en
Application granted granted Critical
Publication of CN104775417B publication Critical patent/CN104775417B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/08Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Analytical Chemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of mattress layer of major diameter rigid pile composite foundation and major diameter rigid pile composite foundation, for solving the existing ropy problem of ground mattress layer.The upper surface of the mattress layer of the present invention is provided with least one upper pressure cell, the lower surface of the mattress layer is provided with least one lower pressure cell, the upper pressure cell and lower pressure cell are correspondingly arranged up and down, and reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer.The present invention can monitor the compacting situation of each position of mattress layer so that the mattress layer of each position can uniformly be tamped, and improve the quality of mattress layer by setting pressure cell on the upper and lower surface of mattress layer.

Description

The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation
Technical field
The invention belongs to major diameter rigid pile composite foundation technical field, and in particular to a kind of major diameter rigid pile is compoundly The mattress layer and major diameter rigid pile composite foundation of base.
Background technology
When subsoil can not meet requirement of the building to ground, it is necessary to carry out basement process, artificial foundation is formed, To ensure the safety and normal use of building.Main methods of the composite foundation as artificial foundation are buildings frequently with Artificial foundation's method.
Composite foundation is mainly that subsoil part soil during basement process is strengthened or is replaced or in day Reinforcement material is set in right ground, stabilization zone is by the subsoil soil body and reinforcement artificial foundation dimerous, on top Under structural loads, the effect of the subsoil soil body and reinforcement shared load, the condition of form compound foundation be matrix and Reinforcement shares load jointly in the presence of load, by both compatibilities of deformation.
Composite foundation be generally divided into Composite Foundation of Soil cement Mixing Piles, high pressure jet grouting pile composite foundation, sand pile ground, Vibroflotation pile composite foundation, soil and dirt both close pile composite foundation, CFG Compound Foundation and rammed concrete pile Composite foundation.
CFG stakes are English Cement Fly-ash Gravel abbreviations, CFG are meant, by rubble, stone Bits, sand, flyash mixed cement plus water mix, and have the variable intensity stake of some strength made of various forming machinery.CFG stakes It is a kind of Low Intensity Concrete Piles, the bearing capacity collective effect of inter-pile soil can be made full use of, and load can be transmitted to deep foundation base In, there is preferable technical skills and economic effect.
By adjusting cement mixing content and proportioning, its strength grade changes between C15-C25, is between rigid pile and flexibility A kind of pile-type between stake.CFG stakes and inter-pile soil form CFG pile composite foundation cooperations together, by mattress layer, therefore can root According to composite foundation character and calculate progress engineering design.CFG stakes do not have to typically calculate arrangement of reinforcement, and also using Industry Waste feed powder Coal ash and aggregate chips make admixture, reduce further construction costs, and therefore, CFG stakes have extremely strong practicality.
Such as the utility model patent of Application No. 201320732862.4 discloses a kind of spiral pump pressure CFG stakes, including CFG pile bodies, block is provided with CFG pile bodies, sandy gravel stratum is provided with block, ground is provided with above sandy gravel stratum; Sandy gravel stratum thickness is 0.5~3m.
CFG pile constructing process mainly includes the following steps that:
1st, stake machine enters scene, determines bracket height and immersed tube length according to designing pile length, immersed tube embedded depth, and carry out Equipment assembles;
2nd, stake machine is just that adjustment immersed tube is perpendicular to the ground, it is ensured that perpendicularity deviation meets technological requirement(Ordinary circumstance is sagging Straight degree deviation is not more than 1%);
3rd, starter motor, the predetermined absolute altitude in immersed tube road, shut down;
4th, made a record during immersed tube, the electric current often to sink on 1m recording ammeters once, and to being given at soil layer change Explanation;
5th, the concrete perfusion into pipe immediately after shutting down, until concrete is concordant with charging aperture, after pile, laitance thickness is not It is advisable more than 10cm;
6th, starter motor, 5-10s of vibration staying, start tube drawing, pipe-drawn speed is generally 1.2-1.5m/min, such as pre- mud or Muck soil, pipe-drawn speed should also slow down, and anti-plug is not allowed during tube drawing;, must be aerial during tube drawing such as feeding deficiency Feed intake, to ensure that top mark up to arrives design requirement after pile;
7th, immersed tube extracts ground, after confirming the requirement of pile composite design, is bound with bulk material or wet cohesive soil.
Due to the restriction of pile body diameter, making that the topside area of its pile body is small, and area replacement ratio is relatively low, pile-soil stress is larger, The punching failure of stake is easily lead to, therefore, bulk material is needed at the top of pile body or wet cohesive soil binds, in industry It is called mattress layer.
Such as the patent of invention of Application No. 201410217327.4 discloses a kind of expand at the base expanding and base expanding CFG pile composite foundations of top Reason method, the composite foundation include pile body, pile cover, stake bottom, mattress layer, mattress thickness are set between pile cover and building basis Degree takes 0.4~0.6 times of pile body diameter, and the width of mattress layer is more than building bottom of foundation width 400mm, and mattress layer uses grain Middle sand of the footpath less than 30mm, coarse sand, graded sand and stone and rubble laying, its sand coarse aggregate ratio are that 3: 7 bottoms are compacting filler, and compacting is filled out Expect the brickbat for 50~100mm of diameter, broken concrete, cement mixture, rubble, cobble and slag or its combination, stake bottom Volume is 0.5m3~1.8m3
Existing mattress layer is mostly directly to mattress layer material(Middle sand, coarse sand, rubble etc.)Compacting processing is carried out, however, Because the soft degree of the earth's surface soil body is inconsistent, and the variable thickness of mattress layer material-paving causes, and causes each position of mattress layer The tightness degree put is inconsistent, so as to cause whole mattress layer of poor quality.
The content of the invention
The present invention can not cause mattress to solve prior art to mattress layer stress deformation measuring method imperfection The ropy problem of layer, and the mattress layer and major diameter rigid pile composite foundation of a kind of major diameter rigid pile composite foundation are provided, The uniform force of each position of mattress layer is enabled to, improves the quality of mattress layer, so as to improve whole major diameter rigid pile The bearing capacity of composite foundation.
In order to solve the above technical problems, the technical solution adopted in the present invention is:
A kind of mattress layer of major diameter rigid pile composite foundation, it is characterised in that the upper surface of the mattress layer is provided with At least one upper pressure cell, the lower surface of the mattress layer are provided with least one lower pressure cell, the upper pressure cell and push Power box is correspondingly arranged up and down, and reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer.Mattress layer is arranged on pile body Top, those skilled in the art can be appreciated and understood that, will not be repeated here.
An at least reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer.
The reinforcing bar is uniformly connected with reinforcing rib meter.
The periphery of the reinforcing bar is connected with hangnail.
The periphery for being arranged on reinforcing bar at the hangnail interval.
A kind of major diameter rigid pile composite foundation, including pile body and the mattress layer for being arranged on pile body upper end, the mattress layer Lower section at least provided with a pile body, it is characterised in that the upper surface of the mattress layer is provided with least one upper pressure cell, The lower surface of the mattress layer is provided with least one lower pressure cell, and the upper pressure cell and lower pressure cell are correspondingly arranged up and down, Reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer.
An at least reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer.
The reinforcing bar is uniformly connected with reinforcing rib meter.
The periphery of the reinforcing bar is connected with hangnail.
The periphery for being arranged on reinforcing bar at the hangnail interval.
Compared with prior art, the invention has the advantages that:
The mattress layer of the major diameter rigid pile composite foundation of the present invention, by setting pressure on the upper and lower surface of mattress layer Box, the compacting situation of each position of mattress layer can be monitored so that the mattress layer of each position can uniformly be tamped, and improve cotton-padded mattress The quality of bed course.
Reinforcing bar is provided with the mattress layer of invention simultaneously, if the mattress layer discontinuity of adjacent position, passes through reinforcing bar energy Enough drive mattress layer material to slide, so as to disperse the distribution of material in mattress layer, improve the quality of mattress layer.
Reinforcing rib meter is also associated with the reinforcing bar of the present invention, the stress feelings of each position inside mattress layer can be monitored in time Condition, it is easy to the adjustment of compacting process, so as to improve the quality of mattress layer.
The CFG pile composite foundations of the present invention, pass through the improvement to mattress layer, it is possible to increase the quality of mattress layer, so as to carry The quality of high composite foundation.
Brief description of the drawings
Fig. 1 is the structural representation of the embodiment of mattress layer one of the present invention;
Fig. 2 is the structural representation of another embodiment of the mattress layer of the present invention;
Fig. 3 is the structural representation of an embodiment of the composite foundation of the present invention;
Fig. 4 is the structural representation of another embodiment of the composite foundation of the present invention;
Marked in figure:1st, mattress layer, 2, pile body, 3, lower pressure cell, 4, upper pressure cell, 5, reinforcing bar, 6, reinforcing rib meter, 7, fall Thorn.
Embodiment
With reference to embodiment, the invention will be further described, and described embodiment is only a present invention part Embodiment, it is not whole embodiments.Based on the embodiment in the present invention, one of ordinary skill in the art is not making Other embodiments used obtained under the premise of creative work, belong to protection scope of the present invention.
With reference to Fig. 1, Fig. 2, the mattress layer of major diameter rigid pile composite foundation of the invention, the upper surface of mattress layer 1 is set There is at least one upper pressure cell 4, the lower surface of the mattress layer 1 is provided with least one lower pressure cell 3, the upper pressure cell 4 It is correspondingly arranged with lower pressure cell about 3, reinforcing bar 5 is equipped with the horizontal direction of the interior edge mattress layer 1 of mattress layer 1.Mattress layer 1 The top of pile body is arranged on, those skilled in the art can be appreciated and understood that, will not be repeated here.It is of the invention only to exist The lower surface of mattress layer 1 sets lower pressure cell, and mainly the compacting situation of the lower surface of mattress layer is monitored.
Mattress is during construction, because the soft degree of ground layer soil body differs, while the material when laying mattress layer The variable thickness of accumulation so that the compacting of each position of mattress layer is inconsistent, causes mattress layer of poor quality.
The mattress layer of the major diameter rigid pile composite foundation of the present invention, by setting pressure on the upper and lower surface of mattress layer 1 Box, the compacting situation of each position of mattress layer can be monitored so that the mattress layer of each position can uniformly be tamped, and improve cotton-padded mattress The quality of bed course.
Reinforcing bar 5 is provided with the mattress layer of invention simultaneously, if the discontinuity of mattress layer 1 of adjacent position, passes through reinforcing bar 5 Mattress layer material can be driven to slide, so as to disperse the distribution of material in 1 layer of mattress, improve the quality of mattress layer.Wherein this hair Bright told about upper and lower pressure cell, reinforcing rib meter belong to prior art products, and those skilled in the art can understand and manage Solution, will not be repeated here.
An at least reinforcing bar 5 is equipped with the horizontal direction of the interior edge mattress layer 1 of mattress layer 1, the quantity of reinforcing bar can basis The thickness of mattress layer is laid, and those skilled in the art can be appreciated and understood that, will not be repeated here.
As a kind of preferable mode of the present invention, reinforcing bar 5 is uniformly connected with reinforcing rib meter 6, can monitored in time in mattress layer The stressing conditions of each position in portion, are easy to the adjustment of compacting process, so as to improve the quality of mattress layer.
In order to improve regulating power of the reinforcing bar to the material of mattress layer 1, the periphery of reinforcing bar 5 is connected with hangnail 7, carried by hangnail The regulating power of high reinforcing bar, further improve the practicality of the present invention.
As a kind of preferable mode of the present invention, the periphery for being arranged on reinforcing bar 5 that hangnail 7 is spaced.
With reference to Fig. 3 and Fig. 4, present invention also offers a kind of major diameter rigid pile composite foundation, including pile body 2 and it is arranged on The mattress layer 1 of the upper end of pile body 2, the lower section of the mattress layer 1 are set at least provided with a pile body 2, the upper surface of the mattress layer 1 At least one upper pressure cell 4 is equipped with, the lower surface of the mattress layer 1 is provided with least one lower pressure cell 3, the upper pressure cell 4 and lower pressure cell be correspondingly arranged about 3, be equipped with reinforcing bar 5 in the horizontal direction of the interior edge mattress layer 1 of mattress layer 1.The present invention CFG pile composite foundations the improvement also improvement to mattress layer, before done detailed description, will not be repeated here.
Embodiment one
The mattress layer of the major diameter rigid pile composite foundation of the present embodiment, the upper surface of the mattress layer are provided with least one Individual upper pressure cell, the lower surface of the mattress layer are provided with least one lower pressure cell, on the upper pressure cell and lower pressure cell Under be correspondingly arranged, be equipped with reinforcing bar in the horizontal direction of the mattress layer interior edge mattress layer.
Embodiment two
The mattress layer of the major diameter rigid pile composite foundation of the present embodiment, the upper surface of the mattress layer are provided with least one Individual upper pressure cell, the lower surface of the mattress layer are provided with least one lower pressure cell, on the upper pressure cell and lower pressure cell Under be correspondingly arranged, an at least reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer.
Embodiment three
The mattress layer of the major diameter rigid pile composite foundation of the present embodiment, the upper surface of the mattress layer are provided with least one Individual upper pressure cell, the lower surface of the mattress layer are provided with least one lower pressure cell, on the upper pressure cell and lower pressure cell Under be correspondingly arranged, an at least reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer;The reinforcing bar uniformly connects It is connected to reinforcing rib meter.
Example IV
The mattress layer of the major diameter rigid pile composite foundation of the present embodiment, the upper surface of the mattress layer are provided with least one Individual upper pressure cell, the lower surface of the mattress layer are provided with least one lower pressure cell, on the upper pressure cell and lower pressure cell Under be correspondingly arranged, an at least reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer;The reinforcing bar uniformly connects It is connected to reinforcing rib meter;The periphery of the reinforcing bar is connected with hangnail.
Embodiment five
The mattress layer of the major diameter rigid pile composite foundation of the present embodiment, the upper surface of the mattress layer are provided with least one Individual upper pressure cell, the lower surface of the mattress layer are provided with least one lower pressure cell, on the upper pressure cell and lower pressure cell Under be correspondingly arranged, an at least reinforcing bar is equipped with the horizontal direction of the mattress layer interior edge mattress layer;The reinforcing bar uniformly connects It is connected to reinforcing rib meter;The periphery of the reinforcing bar is connected with hangnail;The periphery for being arranged on reinforcing bar at the hangnail interval.
Embodiment six
The major diameter rigid pile composite foundation of the present embodiment, including pile body and the mattress layer for being arranged on pile body upper end, it is described At least provided with a pile body, the upper surface of the mattress layer is provided with least one upper pressure cell, described for the lower section of mattress layer The lower surface of mattress layer is provided with least one lower pressure cell, and the upper pressure cell and lower pressure cell are correspondingly arranged up and down, described Reinforcing bar is equipped with the horizontal direction of mattress layer interior edge mattress layer.
Embodiment seven
The major diameter rigid pile composite foundation of the present embodiment, including pile body and the mattress layer for being arranged on pile body upper end, it is described At least provided with a pile body, the upper surface of the mattress layer is provided with least one upper pressure cell, described for the lower section of mattress layer The lower surface of mattress layer is provided with least one lower pressure cell, and the upper pressure cell and lower pressure cell are correspondingly arranged up and down, described Reinforcing bar is equipped with the horizontal direction of mattress layer interior edge mattress layer;The reinforcing bar is uniformly connected with reinforcing rib meter.
Embodiment eight
The major diameter rigid pile composite foundation of the present embodiment, including pile body and the mattress layer for being arranged on pile body upper end, it is described At least provided with a pile body, the upper surface of the mattress layer is provided with least one upper pressure cell, described for the lower section of mattress layer The lower surface of mattress layer is provided with least one lower pressure cell, and the upper pressure cell and lower pressure cell are correspondingly arranged up and down, described Reinforcing bar is equipped with the horizontal direction of mattress layer interior edge mattress layer;The reinforcing bar is uniformly connected with reinforcing rib meter;Outside the reinforcing bar Enclose and be connected with hangnail.

Claims (6)

1. the mattress layer of major diameter rigid pile composite foundation, it is characterised in that the upper surface of the mattress layer is provided with least one Individual upper pressure cell, the lower surface of the mattress layer are provided with least one lower pressure cell, on the upper pressure cell and lower pressure cell Under be correspondingly arranged, be equipped with reinforcing bar in the horizontal direction of the mattress layer interior edge mattress layer;The mattress layer interior edge mattress layer An at least reinforcing bar is equipped with horizontal direction;The reinforcing bar is uniformly connected with reinforcing rib meter;The periphery of the reinforcing bar is connected with down Thorn;The periphery for being arranged on reinforcing bar at the hangnail interval.
2. major diameter rigid pile composite foundation, including pile body and the mattress layer for being arranged on pile body upper end, the lower section of the mattress layer At least provided with a pile body, it is characterised in that the upper surface of the mattress layer is provided with least one upper pressure cell, the cotton-padded mattress The lower surface of bed course is provided with least one lower pressure cell, and the upper pressure cell and lower pressure cell are correspondingly arranged up and down, the cotton-padded mattress Reinforcing bar is equipped with the horizontal direction of bed course interior edge mattress layer.
3. major diameter rigid pile composite foundation according to claim 2, it is characterised in that the mattress layer interior edge mattress layer Horizontal direction on be equipped with an at least reinforcing bar.
4. major diameter rigid pile composite foundation according to claim 3, it is characterised in that the reinforcing bar is uniformly connected with steel Muscle meter.
5. according to any described major diameter rigid pile composite foundation of claim 2-4, it is characterised in that outside the reinforcing bar Enclose and be connected with hangnail.
6. major diameter rigid pile composite foundation according to claim 5, it is characterised in that the hangnail interval is arranged on The periphery of reinforcing bar.
CN201510192767.3A 2015-04-22 2015-04-22 The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation Active CN104775417B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510192767.3A CN104775417B (en) 2015-04-22 2015-04-22 The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510192767.3A CN104775417B (en) 2015-04-22 2015-04-22 The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation

Publications (2)

Publication Number Publication Date
CN104775417A CN104775417A (en) 2015-07-15
CN104775417B true CN104775417B (en) 2017-12-26

Family

ID=53617158

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510192767.3A Active CN104775417B (en) 2015-04-22 2015-04-22 The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation

Country Status (1)

Country Link
CN (1) CN104775417B (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2710008B2 (en) * 1993-12-28 1998-02-10 株式会社国土基礎 Steel pipe pile with wing for load test
JP5984085B2 (en) * 2012-01-16 2016-09-06 株式会社グレイプ Foundation structure and foundation construction method
CN103556620B (en) * 2013-09-26 2015-06-10 南京雨桩建筑科技有限公司 Method for enhancing bearing capacity of composite foundation and rigid pile thereof
CN204530662U (en) * 2015-04-22 2015-08-05 中冶成都勘察研究总院有限公司 The mattress layer of major diameter rigid pile composite foundation and major diameter rigid pile composite foundation

Also Published As

Publication number Publication date
CN104775417A (en) 2015-07-15

Similar Documents

Publication Publication Date Title
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN104153380B (en) A kind of antiseepage cofferdam structure and construction technology
CN105019422B (en) Topsoil is cured in situ the foundation construction method that carrying is combined with stake
CN104404838B (en) The above railway collapsible loess subgrade substrate treating method of speed 200km
CN106522948A (en) Short-wall waste rock gluing continuous mining and continuous filling mining method
CN102146679A (en) Construction method for complex geological section earth pressure balance shield passing middle air shaft
CN105421449B (en) Construction method of composite pile composed of nail-shaped active material plastic sleeve and concrete stiffened core
CN113186766A (en) Shallow soft soil foundation foam light soil embankment structure and construction method
CN106320120A (en) Construction process for pile slab type non-soil roadbed highway
CN103469701B (en) On-the-spot integrated form is prepared Foam lightweight soil and is filled high ferro roadbed construction method
CN114411761A (en) Advanced pre-support system for planned subway tunnel during construction of newly-built building and pre-support construction method
CN104480956B (en) A kind of minor diameter mold-bagged concrete pile composite foundation
CN106087880B (en) A kind of dam that 300 meter level is high and its construction technology
CN103276716B (en) A kind of changeover portion CFG stake and mattress layer composite foundation stabilization construction method
CN107034894A (en) Post-tensioned prestressed tension beam recoverable pattern foundation pit supporting structure prefabricated pile and preparation method thereof and construction method
CN104695417B (en) A kind of manufacture method of grouting behind shaft or drift lining broken stone pile
CN105839620A (en) Plastic-sleeve bamboo-reinforcement cemented soil pile and construction method thereof
CN107142902B (en) High head and large flow tunneling boring damming method
CN110004787A (en) Pier storage yard road concrete surface construction method
CN102409660A (en) Multi-section expanded head granular material pile composite foundation prestress construction method
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method
CN104775417B (en) The mattress layer and major diameter rigid pile composite foundation of major diameter rigid pile composite foundation
CN106958176A (en) Quick prefabricated pin-connected panel soft base processing method
CN115467672B (en) A construction method for shield tunneling in shallow backfill area with close side penetration of bridge pile foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant