[go: up one dir, main page]

CN104676110A - On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit - Google Patents

On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit Download PDF

Info

Publication number
CN104676110A
CN104676110A CN201510040803.4A CN201510040803A CN104676110A CN 104676110 A CN104676110 A CN 104676110A CN 201510040803 A CN201510040803 A CN 201510040803A CN 104676110 A CN104676110 A CN 104676110A
Authority
CN
China
Prior art keywords
steel
cable
excavation
channel
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510040803.4A
Other languages
Chinese (zh)
Inventor
蔡科
吴立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Geosciences
Original Assignee
China University of Geosciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Geosciences filed Critical China University of Geosciences
Priority to CN201510040803.4A priority Critical patent/CN104676110A/en
Publication of CN104676110A publication Critical patent/CN104676110A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/02Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种基坑开挖状况下高压电缆贝雷架原地悬吊保护方法,涉及建筑技术领域,包括如下步骤:(1)贝雷架立柱锚固段,(2)搭设贝雷架结构,(3)电缆下局部开挖,(4)形成悬吊系统,(5)悬吊电缆,(6)拆除原有电缆槽,(7)基坑开挖,(8)新建电缆沟、拆除悬吊系统,本发明所述的所有高压电缆的悬吊保护系统均必须在相应位置的基坑开挖前完成,高压电缆悬吊保护系统施工时,还邀请电力部门有关人员现场监督及指导,同时配合电力部门实施电缆及电缆接头的外包保护,充分保障了施工安全。The invention discloses an in-situ suspension protection method of a high-voltage cable bailey frame under the excavation condition of a foundation pit, relates to the technical field of construction, and comprises the following steps: (1) the anchorage section of the bailey frame column, (2) erecting the bailey frame structure, (3) partial excavation under the cable, (4) forming a suspension system, (5) suspending the cable, (6) removing the original cable trench, (7) excavating the foundation pit, (8) building a new cable trench, Remove the suspension system, all the suspension protection systems for high-voltage cables described in the present invention must be completed before the excavation of the foundation pit at the corresponding position. During the construction of the suspension protection system for high-voltage cables, relevant personnel from the electric power department are also invited to supervise and guide on-site At the same time, cooperate with the power department to implement outsourcing protection of cables and cable joints, which fully guarantees construction safety.

Description

一种基坑开挖状况下高压电缆贝雷架原地悬吊保护方法A protection method for in-situ suspension of high-voltage cable bailey under the condition of foundation pit excavation

技术领域technical field

本发明涉及建筑技术领域,更具体地说,本发明涉及一种基坑开挖状况下高压电缆贝雷架原地悬吊保护方法。The invention relates to the field of construction technology, and more specifically, the invention relates to a method for in-situ suspension protection of a high-voltage cable bailey under the condition of foundation pit excavation.

背景技术Background technique

基坑在基础设计位置按基底标高和基础平面尺寸所开挖的土坑。开挖前应根据地质水文资料,结合现场附近建筑物情况,决定开挖方案,并作好防水排水工作。开挖不深者可用放边坡的办法,使土坡稳定,其坡度大小按有关施工程规定确定。开挖较深及邻近有建筑物者,可用基坑壁支护方法,喷射混凝土护壁方法,大型基坑甚至采用地下连续墙和柱列式钻孔灌注桩连锁等方法,防护外侧土层坍入。The foundation pit is the earth pit excavated at the foundation design position according to the base elevation and foundation plane size. Before excavation, the excavation plan should be determined according to the geological and hydrological data, combined with the conditions of the nearby buildings, and the waterproof and drainage work should be done well. If the excavation is not deep, the side slope can be used to stabilize the soil slope, and the slope size is determined according to the relevant construction regulations. For those with deep excavation and nearby buildings, the foundation pit wall support method, shotcrete retaining wall method, and large foundation pit even adopt methods such as underground diaphragm wall and column-type bored pile interlocking to prevent the outer soil layer from collapsing. .

在建筑施工中,根据现场情况及电力部门澄清,原场地内的高压电缆无法迁移至基坑外。此类情况下,电力部门往往会要求,此高压电缆在基坑施工期间须进行原地保护,待永久结构完工后,再将电缆迁移至新电缆沟中。遇到此类情况,目前常用的对高压电缆保护方法是砌隔离墙防护法,此类方法费时费力,成本过高,且占用空间大,阻碍施工进行。During construction, according to the site conditions and clarification from the power department, the high-voltage cables in the original site cannot be moved outside the foundation pit. Under such circumstances, the power department often requires that the high-voltage cables must be protected in situ during the construction of the foundation pit, and the cables will be relocated to new cable trenches after the permanent structure is completed. In such cases, the currently commonly used protection method for high-voltage cables is to build a partition wall protection method. This method is time-consuming, laborious, costly, and takes up a lot of space, which hinders construction.

发明内容Contents of the invention

本发明所要解决的问题是提供一种基坑开挖状况下高压电缆贝雷架原地悬吊保护方法,以解决现有方法费时费力,成本过高,且占用空间大的缺陷。The problem to be solved by the present invention is to provide a method for in-situ suspension protection of high-voltage cable baileys under the excavation of foundation pits, so as to solve the defects of time-consuming, labor-intensive, high cost and large space occupation of existing methods.

为了实现上述目的,本发明采取的技术方案为:1、一种基坑开挖状况下高压电缆贝雷架原地悬吊保护方法,其特征在于,包括如下步骤:In order to achieve the above object, the technical solution adopted by the present invention is: 1. A method for in-situ suspension protection of high-voltage cable bailey under the condition of foundation pit excavation, which is characterized in that it includes the following steps:

(1)贝雷架立柱锚固段:首先在基坑原地面按坐标位施工人工挖孔桩,立柱锚固端截面为φ1200mm的人工挖孔桩至基坑底,并入强风化岩5m或中风化3m或微风化2m终孔,然后在桩顶埋设贝雷架立柱;(1) The anchorage section of the column of the Bailey frame: firstly, construct the artificial excavated piles according to the coordinates on the original ground of the foundation pit, and the artificial excavated piles with a cross-section of φ1200mm at the anchorage end of the columns to the bottom of the foundation pit, and merge them into the strong weathered rock 5m or moderately weathered 3m or slightly weathered 2m end hole, and then bury the Bailey frame column on the top of the pile;

(2)搭设贝雷架结构:在桩顶埋设2根I 50b工字钢,并架设2根I 50b工字钢横梁、40b#工字钢主梁及14#槽钢,40b#工字钢主梁与2根I 50b工字钢横梁螺栓连接,搭设贝雷架主梁、贝雷架次梁、贝雷架檩条;(2) Set up the Bailey frame structure: bury 2 I 50b I-beams on the top of the pile, and erect 2 I 50b I-beams, 40b# I-beam main beam and 14# channel steel, 40b# I-beam The main beam is bolted to two I 50b I-beam beams, and the Bailey frame main beam, Bailey frame secondary beam, and Bailey frame purlins are erected;

(3)电缆下局部开挖:分段在槽钢正下方局部开挖至管线槽底部,在管线槽下方掏土成洞打通,并及时插入14#槽钢支承管线槽;(3) Partial excavation under the cable: excavate partly directly under the channel steel to the bottom of the pipeline trough, dig out soil under the pipeline trough to make a hole, and insert the 14# channel steel supporting pipeline trough in time;

(4)形成悬吊系统:采用20圆钢将托架与工字钢主梁上的槽钢联结,两端用螺丝收紧,形成悬吊系统;(4) Form a suspension system: use 20 round steel to connect the bracket with the channel steel on the I-beam main beam, and tighten the two ends with screws to form a suspension system;

(5)悬吊电缆:浅开挖至管线底,边人工破除电缆沟中隔板及侧板边及时穿入纵向角钢、木板等托住电缆沟中隔板对应位置人工破除,穿入横向角钢、纵向角钢、木板等托住电缆。所有的钢结构必须有可靠的接地,接地地阻≤1欧姆;(5) Suspension cables: excavate shallowly to the bottom of the pipeline, manually remove the partitions and side plates in the cable trench, and timely penetrate the longitudinal angle steel, wooden boards, etc. to support the corresponding positions of the partitions in the cable trench, manually remove them, and penetrate the horizontal angle steel , longitudinal angle steel, planks, etc. to support the cables. All steel structures must have reliable grounding, grounding resistance ≤ 1 ohm;

(6)拆除原有电缆槽:待悬吊系统施工完毕方能将原电缆管槽拆除,距离电缆2m范围内必须采用人工方式拆除,严禁机械拆除;(6) Remove the original cable trough: the original cable trough can only be removed after the construction of the suspension system is completed. It must be removed manually within 2m from the cable, and mechanical removal is strictly prohibited;

(7)基坑开挖:继续分层开挖土方至基坑底,施工地下室结构至地面,在钢构柱位置预留孔洞。为确保立柱的稳定性、减小土方侧压力对立柱的稳定性影响,土方开挖必须分区段分层开挖,每个区段按1.5米深度进行分层开挖,每个区段在衔接面必须用挖掘机切成45°倾斜面,保证区段衔接面土体的稳定性;(7) Excavation of the foundation pit: Continue to excavate the earth in layers to the bottom of the foundation pit, construct the basement structure to the ground, and reserve holes at the positions of the steel columns. In order to ensure the stability of the column and reduce the influence of the lateral pressure of the earthwork on the stability of the column, the excavation of the earthwork must be excavated in layers, and each section is excavated in layers at a depth of 1.5 meters. The surface must be cut into a 45° inclined surface with an excavator to ensure the stability of the soil at the joint surface of the section;

(8)新建电缆沟、拆除悬吊系统:在电缆原址铺设新管槽,并拆除悬吊系统的型钢梁,浇筑预留孔洞。(8) Build a new cable trench and remove the suspension system: Lay a new pipe trench at the original site of the cable, remove the steel beams of the suspension system, and pour reserved holes.

优选的,所述步骤(1)中的贝雷架立柱的截面为2根I 50b工字钢,于锚固端顶部埋设。Preferably, the section of the Bailey frame column in the described step (1) is 2 I 50b I-beams, which are buried at the top of the anchoring end.

优选的,所述步骤(2)中的贝雷架主梁为贝雷架立柱顶横向架设的两根I 50b工字钢。Preferably, the main girder of the Bailey frame in the described step (2) is two I 50b I-beams that are horizontally erected on the top of the column of the Bailey frame.

优选的,所述步骤(2)中的贝雷架次梁为两条40b#工字钢,梁顶面标高为-0.17m,两条工字钢间距为2.5~4m,跨度为8.5~10m。Preferably, the Bailey secondary beam in the step (2) is two 40b# I-beams, the beam top elevation is -0.17m, the distance between the two I-beams is 2.5-4m, and the span is 8.5-10m.

优选的,所述步骤(2)中的贝雷架檩条为铺设在两条工字钢次梁上的14#槽钢,且对应地在此槽钢正下方的电缆底部穿过一条14#槽钢。Preferably, the Bailey frame purlin in the step (2) is a 14# channel steel laid on two I-beam secondary beams, and correspondingly the cable bottom directly below the channel steel passes through a 14# channel steel.

优选的,所述步骤(5)中通过Φ20圆钢连接两14#槽钢形成悬挂系统,以此悬吊电缆,槽钢纵向间距为2.5~4m不等;电缆下部的14#槽钢上密铺4cm厚木板,木板两侧搭在L50×5角钢上,角钢沿着管线方向纵向铺设在槽钢上。Preferably, in said step (5), two 14# channel steels are connected by Φ20 round steel to form a suspension system, so as to suspend the cable, and the longitudinal spacing of the channel steels is 2.5~4m; Lay 4cm thick wooden planks, the two sides of the plank are laid on the L50×5 angle steel, and the angle steel is laid longitudinally on the channel steel along the direction of the pipeline.

有益效果:本发明所述的基坑开挖状况下高压电缆贝雷架原地悬吊保护方法在基坑开挖深度为17.5m,基坑内拟原址保护的高压电缆长度达到84m的情况下,为确保高压电缆安全,而采用贝雷架横跨基坑的悬吊式保护方案,对高压电缆进行保护,本保护方法的所有高压电缆的悬吊保护系统均必须在相应位置的基坑开挖前完成,高压电缆悬吊保护系统施工时,还邀请电力部门有关人员现场监督及指导,同时配合电力部门实施电缆及电缆接头的外包保护,充分保障了施工安全。本保护方法省时省力,成本底下,且占地较小,不干扰施工。Beneficial effects: under the condition of foundation pit excavation, the method for in-situ suspension protection of high-voltage cable bailey frame under the condition of foundation pit excavation is 17.5m, and the length of the high-voltage cable to be protected in the foundation pit reaches 84m. In order to ensure the safety of high-voltage cables, the suspension protection scheme of Bailey frame across the foundation pit is adopted to protect the high-voltage cables. All the suspension protection systems of high-voltage cables in this protection method must be excavated in the foundation pit at the corresponding position During the construction of the high-voltage cable suspension protection system, relevant personnel from the power department were invited to supervise and guide on-site, and at the same time cooperated with the power department to implement outsourced protection of cables and cable joints, which fully guaranteed construction safety. The protection method saves time and labor, has low cost, occupies a small area, and does not interfere with construction.

具体实施方式Detailed ways

实施例1:Example 1:

该方法分八步进行,先进行(1)贝雷架立柱锚固段:首先在基坑原地面按坐标位施工人工挖孔桩,立柱锚固端截面为φ1200mm的人工挖孔桩至基坑底,并入强风化岩5m终孔,然后在桩顶埋设贝雷架立柱;(2)搭设贝雷架结构:在桩顶埋设2根I 50b工字钢,并架设2根I 50b工字钢横梁、40b#工字钢主梁及14#槽钢,40b#工字钢主梁与2根I 50b工字钢横梁螺栓连接,搭设贝雷架主梁、贝雷架次梁、贝雷架檩条,贝雷架主梁为贝雷架立柱顶横向架设的两根I50b工字钢,贝雷架次梁为两条40b#工字钢,梁顶面标高为-0.17m,两条工字钢间距为2.5m,跨度为8.5m,贝雷架檩条为铺设在两条工字钢次梁上的14#槽钢,且对应地在此槽钢正下方的电缆底部穿过一条14#槽钢;然后进行(3)电缆下局部开挖:分段在槽钢正下方局部开挖至管线槽底部,在管线槽下方掏土成洞打通,并及时插入14#槽钢支承管线槽;再进行(4)形成悬吊系统:采用20圆钢将托架与工字钢主梁上的槽钢联结,两端用螺丝收紧,形成悬吊系统;再进行(5)悬吊电缆:浅开挖至管线底,边人工破除电缆沟中隔板及侧板边及时穿入纵向角钢、木板等托住电缆沟中隔板对应位置人工破除,穿入横向角钢、纵向角钢、木板等托住电缆。所有的钢结构必须有可靠的接地,接地地阻≤1欧姆;再进行(6)拆除原有电缆槽:待悬吊系统施工完毕方能将原电缆管槽拆除,距离电缆2m范围内必须采用人工方式拆除,严禁机械拆除;再进行(7)基坑开挖:继续分层开挖土方至基坑底,施工地下室结构至地面,在钢构柱位置预留孔洞。为确保立柱的稳定性、减小土方侧压力对立柱的稳定性影响,土方开挖必须分区段分层开挖,每个区段按1.5米深度进行分层开挖,每个区段在衔接面必须用挖掘机切成45°倾斜面,保证区段衔接面土体的稳定性;最后进行(8)新建电缆沟、拆除悬吊系统:在电缆原址铺设新管槽,并拆除悬吊系统的型钢梁,浇筑预留孔洞。The method is carried out in eight steps. First, (1) the anchorage section of the column of the Bailey frame: firstly, the artificial excavated pile is constructed on the original ground of the foundation pit according to the coordinate position, and the artificial excavated pile with the cross section of the anchorage end of the column is φ1200mm to the bottom of the foundation pit. Merge into the 5m end hole of strong weathered rock, and then bury the Bailey frame column on the pile top; (2) Build the Bailey frame structure: bury 2 I 50b I-beams on the pile top, and erect 2 I 50b I-beam beams , 40b# I-beam main beam and 14# channel steel, 40b# I-beam main beam is connected with two I 50b I-beam beam bolts, and the Bailey frame main beam, Bailey frame beam, and Bailey frame purlin are set up. The main girder of the Bailey frame is two I50b I-beams horizontally erected on the top of the column of the Bailey frame, and the secondary beam of the Bailey frame is two 40b# I-beams. The elevation of the beam top is -0.17m, and the distance between the two I-beams is 2.5m, with a span of 8.5m, the Bailey frame purlin is 14# channel steel laid on two I-steel secondary beams, and correspondingly passes through a 14# channel steel at the bottom of the cable directly below the channel steel; then Carry out (3) partial excavation under the cable: excavate partly directly under the channel steel to the bottom of the pipeline trough in sections, dig out soil under the pipeline trough to make a hole, and insert the 14# channel steel supporting pipeline trough in time; then carry out (4 ) to form a suspension system: use 20 round steel to connect the bracket with the channel steel on the I-beam main beam, tighten the two ends with screws to form a suspension system; then carry out (5) suspension cables: shallow excavation to At the bottom of the pipeline, while manually removing the partitions and side plates in the cable trench, penetrate the longitudinal angle steel, wooden boards, etc. to support the corresponding positions of the partitions in the cable trench, manually remove them, and penetrate the horizontal angle steel, longitudinal angle steel, wooden boards, etc. to support the cables. All steel structures must have reliable grounding, ground resistance ≤ 1 ohm; then proceed to (6) Remove the original cable duct: the original cable duct can only be removed after the construction of the suspension system is completed, and must be used within 2m from the cable Manual demolition, mechanical demolition is strictly prohibited; then (7) Excavation of the foundation pit: Continue to excavate the earth in layers to the bottom of the foundation pit, construct the basement structure to the ground, and reserve holes at the steel structure columns. In order to ensure the stability of the column and reduce the influence of the lateral pressure of the earthwork on the stability of the column, the excavation of the earthwork must be excavated in layers, and each section is excavated in layers at a depth of 1.5 meters. The surface must be cut into a 45° inclined surface with an excavator to ensure the stability of the soil at the joint surface of the section; finally (8) build a new cable trench and remove the suspension system: lay a new pipe groove at the original site of the cable, and remove the suspension system For steel beams, holes are reserved for pouring.

实施例2:Example 2:

按所述的相同步骤重复进行实施例1,不同之处在于:步骤(1)贝雷架立柱锚固段:并入中风化岩3m终孔,然后在桩顶埋设贝雷架立柱,步骤(2)搭设贝雷架结构:贝雷架次梁为两条40b#工字钢,梁顶面标高为-0.17m,两条工字钢间距为3m,跨度为9m。Repeat embodiment 1 by the same steps as described, the difference is: step (1) Bailey frame column anchor section: merge into the middle weathered rock 3m end hole, then bury the Bailey frame column at the pile top, step (2) ) to erect the Bailey frame structure: the Bailey frame beam is two 40b# I-beams, the beam top elevation is -0.17m, the distance between the two I-beams is 3m, and the span is 9m.

实施例3:Example 3:

按所述的相同步骤重复进行实施例1,不同之处在于:步骤(1)贝雷架立柱锚固段:并入微风化岩2m终孔,然后在桩顶埋设贝雷架立柱,步骤(2)搭设贝雷架结构:贝雷架次梁为两条40b#工字钢,梁顶面标高为-0.17m,两条工字钢间距为4m,跨度为10m。Repeat embodiment 1 by the same steps as described, the difference is: step (1) Bailey frame column anchorage section: merge into the micro-weathered rock 2m end hole, then bury the Bailey frame column at the top of the pile, step (2) ) to erect the Bailey frame structure: the Bailey frame beam is two 40b# I-beams, the elevation of the beam top is -0.17m, the distance between the two I-beams is 4m, and the span is 10m.

以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明的说明书内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。The above is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process conversion made by using the content of the description of the present invention, or directly or indirectly used in other related technical fields, All are included in the scope of patent protection of the present invention in the same way.

Claims (6)

1. a high voltage cable Bailey bracket original place suspension protection method under excavation of foundation pit situation, is characterized in that, comprise the steps:
(1) Bailey bracket column anchoring section: first press coordinate position construction artificial digging pile at foundation ditch original ground, column anchored end cross section is that the artificial digging pile of φ 1200mm is at the bottom of foundation ditch, be incorporated to the whole hole of strong-weathered rock 5m or middle weathering 3m or gentle breeze 2m, then bury Bailey bracket column underground on stake top;
(2) Bailey bracket structure is set up: bury 2 I 50b I-steel underground on stake top, and set up 2 I 50b I-steel crossbeams, 40b# I-steel girder and 14# channel-section steels, 40b# I-steel girder is connected with 2 I 50b I-steel transom bolts, sets up Bailey bracket girder, Bailey bracket secondary beam, Bailey bracket purlin;
(3) local excavation under cable: segmentation is immediately below channel-section steel bottom local excavation to chase, and soil digging cavitation is got through below chase, and insert 14# channel-section steel support column wire casing in time;
(4) form Suspension System: adopt 20 round steel to be connect by the channel-section steel on bracket and I-steel girder, two ends screw tightens up, form Suspension System;
(5) pendant cables: be shallowly excavated at the bottom of pipeline, limit is manually abolished cable channel central diaphragm and side plate limit and is penetrated sole bar angle, plank etc. in time and hold cable channel central diaphragm corresponding position and manually abolish, and penetrates horizontal angle steel, sole bar angle, plank etc. and holds cable.All steel structure must have reliable ground connection, ground connection ground resistance≤1 ohm;
(6) remove original wire way: system construction to be suspended is complete can be removed former cable tube seat, manual type must be adopted to remove within the scope of distance cable 2m, forbid mechanical removal;
(7) excavation of foundation pit: continue at the bottom of the stage excavation earthwork to foundation ditch, construction basement structure to ground, at steel pile position reserving hole.For guaranteeing the stability of column, reducing the stability influence of earthwork side pressure column, the necessary sectional stage excavation of earth excavation, each section carries out stage excavation by 1.5 meters of degree of depth, each section must cut plane of inclination at 45 ° with excavator at interface, ensures the stability of the section interface soil body;
(8) newly-built cable channel, dismounting Suspension System: lay new tube seat in cable former address, and remove the section steel beam of Suspension System, build reserving hole.
2. according to high voltage cable Bailey bracket original place suspension protection method under a kind of excavation of foundation pit situation according to claim 1, it is characterized in that: the cross section of the Bailey bracket column in described step (1) is 2 I 50b I-steel, buries underground in anchored end top.
3. according to high voltage cable Bailey bracket original place suspension protection method under a kind of excavation of foundation pit situation according to claim 1, it is characterized in that: the Bailey bracket girder in described step (2) is two I 50b I-steel that Bailey bracket column top is laterally set up.
4. according to high voltage cable Bailey bracket original place suspension protection method under a kind of excavation of foundation pit situation according to claim 1; it is characterized in that: the Bailey bracket secondary beam in described step (2) is two 40b# I-steel; top surface of the beam absolute altitude is-0.17m; article two, I-steel spacing is 2.5 ~ 4m, and span is 8.5 ~ 10m.
5. according to high voltage cable Bailey bracket original place suspension protection method under a kind of excavation of foundation pit situation according to claim 1; it is characterized in that: the Bailey bracket purlin in described step (2) is the 14# channel-section steel be laid on two I-steel secondary beams, and through a 14# channel-section steel bottom cable accordingly immediately below this channel-section steel.
6. according to high voltage cable Bailey bracket original place suspension protection method under a kind of excavation of foundation pit situation according to claim 1, it is characterized in that: connect two 14# channel-section steels by Φ 20 round steel in described step (5) and form suspension system, with this pendant cables, channel-section steel longitudinal pitch be 2.5 ~ 4m not etc.; Close paving 4cm thick plank on the 14# channel-section steel of cable bottom, plank both sides ride on the angle steel of L50 × 5, and angle steel is longitudinally laid on channel-section steel along pipeline direction.
CN201510040803.4A 2015-01-22 2015-01-22 On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit Pending CN104676110A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510040803.4A CN104676110A (en) 2015-01-22 2015-01-22 On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510040803.4A CN104676110A (en) 2015-01-22 2015-01-22 On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit

Publications (1)

Publication Number Publication Date
CN104676110A true CN104676110A (en) 2015-06-03

Family

ID=53311529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510040803.4A Pending CN104676110A (en) 2015-01-22 2015-01-22 On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit

Country Status (1)

Country Link
CN (1) CN104676110A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105546278A (en) * 2015-12-23 2016-05-04 国家电网公司 Method for protecting underground pipeline during pipe ditch excavation
CN105570539A (en) * 2015-12-21 2016-05-11 广州机施建设集团有限公司 Construction method of pipeline protection structure
CN105604064A (en) * 2015-12-21 2016-05-25 广州机施建设集团有限公司 Construction method of comprehensive pipeline protection system supporting system
CN105782576A (en) * 2016-04-21 2016-07-20 中铁建大桥工程局集团第四工程有限公司 Temporary pipeline lower hoisting bracket and trench excavating pipeline protection method
CN107587528A (en) * 2017-08-27 2018-01-16 中铁二十四局集团有限公司 It is a kind of to protect the design and construction method across the underground high voltage cable box culvert of foundation ditch
CN107653787A (en) * 2017-08-27 2018-02-02 中铁二十四局集团有限公司 It is a kind of to protect the construction method across the underground high voltage cable box culvert of foundation ditch
CN108895203A (en) * 2018-06-21 2018-11-27 中国十七冶集团有限公司 A kind of pipeline mounting structures and its construction method for across pipe gallery
CN109577667A (en) * 2018-05-02 2019-04-05 国网福建省电力有限公司厦门供电公司 A kind of high-tension cable electricity well original position suspension protection method
CN109654294A (en) * 2018-11-21 2019-04-19 中铁十八局集团有限公司 A kind of integrated protection system and its construction method applied to intersection complex grid
CN109653244A (en) * 2018-11-21 2019-04-19 中铁十八局集团有限公司 Intersect the Bailey truss system and its construction method of protection applied to complicated tube cable
CN110445077A (en) * 2018-05-02 2019-11-12 国网福建省电力有限公司厦门供电公司 A kind of high-tension cable power channel original position suspension protection method
CN110593268A (en) * 2018-06-12 2019-12-20 中铁十八局集团有限公司 Underground pipeline excavation construction technology based on support piles and bailey frames for protection
CN111021363A (en) * 2019-12-31 2020-04-17 广东顺德电力设计院有限公司 Method and system for protecting cable by using bailey truss
CN111173027A (en) * 2019-12-25 2020-05-19 北京正和恒基滨水生态环境治理股份有限公司 Construction method for reinforcing and protecting existing pipeline
CN112095619A (en) * 2020-09-08 2020-12-18 中建一局集团第二建筑有限公司 Protection device for underground original pipeline and construction method thereof
CN112962613A (en) * 2021-02-19 2021-06-15 济南轨道交通集团有限公司 Sedimentation automatic compensation type foundation pit-crossing underground pipeline protection construction method and system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3780833B2 (en) * 2000-09-05 2006-05-31 鹿島建設株式会社 Construction method of underground structure
CN101929159A (en) * 2010-08-12 2010-12-29 中建七局(上海)有限公司 Protective method of pipelines in natural gas pipeline full-section excavation construction
CN202099804U (en) * 2011-05-19 2012-01-04 长业建设集团有限公司 Bailey bracket hanging and underpining system for foundation-pit-spanning pipe lines

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3780833B2 (en) * 2000-09-05 2006-05-31 鹿島建設株式会社 Construction method of underground structure
CN101929159A (en) * 2010-08-12 2010-12-29 中建七局(上海)有限公司 Protective method of pipelines in natural gas pipeline full-section excavation construction
CN202099804U (en) * 2011-05-19 2012-01-04 长业建设集团有限公司 Bailey bracket hanging and underpining system for foundation-pit-spanning pipe lines

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张海峰: "城市车站主体结构顶部电力管廊悬吊保护施工技术", 《现代城市轨道交通》 *
龚胜: "复杂环境中明挖隧道管线悬吊保护实例", 《广东土木与建筑》 *

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105570539B (en) * 2015-12-21 2018-03-20 广州机施建设集团有限公司 The construction method of pipeline protection structure
CN105570539A (en) * 2015-12-21 2016-05-11 广州机施建设集团有限公司 Construction method of pipeline protection structure
CN105604064A (en) * 2015-12-21 2016-05-25 广州机施建设集团有限公司 Construction method of comprehensive pipeline protection system supporting system
CN105546278A (en) * 2015-12-23 2016-05-04 国家电网公司 Method for protecting underground pipeline during pipe ditch excavation
CN105782576A (en) * 2016-04-21 2016-07-20 中铁建大桥工程局集团第四工程有限公司 Temporary pipeline lower hoisting bracket and trench excavating pipeline protection method
CN105782576B (en) * 2016-04-21 2018-01-16 中铁建大桥工程局集团第四工程有限公司 Fluted tube line guard method is excavated below interim pipeline
CN107653787A (en) * 2017-08-27 2018-02-02 中铁二十四局集团有限公司 It is a kind of to protect the construction method across the underground high voltage cable box culvert of foundation ditch
CN107587528B (en) * 2017-08-27 2019-04-12 中铁二十四局集团有限公司 It is a kind of to protect the design and construction method across the underground high voltage cable box culvert of foundation pit
CN107587528A (en) * 2017-08-27 2018-01-16 中铁二十四局集团有限公司 It is a kind of to protect the design and construction method across the underground high voltage cable box culvert of foundation ditch
CN107653787B (en) * 2017-08-27 2019-07-26 中铁二十四局集团有限公司 It is a kind of to protect the construction method across the underground high voltage cable box culvert of foundation pit
CN110445077A (en) * 2018-05-02 2019-11-12 国网福建省电力有限公司厦门供电公司 A kind of high-tension cable power channel original position suspension protection method
CN109577667A (en) * 2018-05-02 2019-04-05 国网福建省电力有限公司厦门供电公司 A kind of high-tension cable electricity well original position suspension protection method
CN110593268B (en) * 2018-06-12 2022-04-01 中铁十八局集团有限公司 Underground pipeline excavation construction method based on support pile and bailey truss protection
CN110593268A (en) * 2018-06-12 2019-12-20 中铁十八局集团有限公司 Underground pipeline excavation construction technology based on support piles and bailey frames for protection
CN108895203A (en) * 2018-06-21 2018-11-27 中国十七冶集团有限公司 A kind of pipeline mounting structures and its construction method for across pipe gallery
CN109653244A (en) * 2018-11-21 2019-04-19 中铁十八局集团有限公司 Intersect the Bailey truss system and its construction method of protection applied to complicated tube cable
CN109653244B (en) * 2018-11-21 2019-10-22 中铁十八局集团有限公司 Intersect the Bailey truss system and its construction method of protection applied to complicated tube cable
CN109654294B (en) * 2018-11-21 2019-10-08 中铁十八局集团有限公司 A kind of integrated protection system and its construction method applied to intersection complex grid
WO2020103351A1 (en) * 2018-11-21 2020-05-28 中铁十八局集团有限公司 Bailey support system applied to crossed protection of complicated pipe cable and construction method therefor
CN109654294A (en) * 2018-11-21 2019-04-19 中铁十八局集团有限公司 A kind of integrated protection system and its construction method applied to intersection complex grid
US11473262B2 (en) 2018-11-21 2022-10-18 China Railway 18 Bureau Group Co., Ltd. Bailey support system applied to cross protection of complex pipes and cables and construction method thereof
CN111173027A (en) * 2019-12-25 2020-05-19 北京正和恒基滨水生态环境治理股份有限公司 Construction method for reinforcing and protecting existing pipeline
CN111021363A (en) * 2019-12-31 2020-04-17 广东顺德电力设计院有限公司 Method and system for protecting cable by using bailey truss
CN112095619A (en) * 2020-09-08 2020-12-18 中建一局集团第二建筑有限公司 Protection device for underground original pipeline and construction method thereof
CN112962613A (en) * 2021-02-19 2021-06-15 济南轨道交通集团有限公司 Sedimentation automatic compensation type foundation pit-crossing underground pipeline protection construction method and system

Similar Documents

Publication Publication Date Title
CN104676110A (en) On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit
KR102709067B1 (en) Method for constructing deep pit local freezing reinforcement in gravel layer containing a large amount of moisture
CN106907159B (en) Shallow-buried underground excavation subway station separated open type structure and construction method thereof
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN104060615B (en) Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle
CN105780779A (en) Externally arranged, compacted and grouted Larsen steel sheet pile composite retaining structure and use method thereof
CN207892615U (en) A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN111236241B (en) Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method
CN112127370A (en) Reverse plugging method for non-construction fender post part of main body fender structure of station
CN105370289A (en) Ultra-long shallow-buried excavation construction method for existing pipeline in complex environment
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN108035360A (en) A kind of method for pattern foundation pit supporting structure
CN104196036B (en) Foundation pit supporting structure and method based on old underground outdoor wall structure
CN110735641B (en) Construction method of transfer passage of underpass pipeline
CN108978673A (en) A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
Mangushev et al. Examples of the construction of deep excavation ditches in weak soils
CN114439060B (en) Method for reinforcing foundation of high-rise civil house with brick-concrete structure
CN220377332U (en) Trapezoidal composite soil nailing wall supporting structure
CN217811059U (en) Combined temporary foundation pit supporting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150603