CN103924944B - Well abandoning operation method for coal-bed gas horizontal wells - Google Patents

Well abandoning operation method for coal-bed gas horizontal wells Download PDF

Info

Publication number
CN103924944B
CN103924944B CN201310408912.8A CN201310408912A CN103924944B CN 103924944 B CN103924944 B CN 103924944B CN 201310408912 A CN201310408912 A CN 201310408912A CN 103924944 B CN103924944 B CN 103924944B
Authority
CN
China
Prior art keywords
well
horizontal
sealing
cement mortar
drilling tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310408912.8A
Other languages
Chinese (zh)
Other versions
CN103924944A (en
Inventor
杨勇
王风锐
郎淑敏
崔树清
吴国栋
周立春
刘永峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NORTH CHINA PETROLEUM ADMINISTRATION BUREAU
Original Assignee
NORTH CHINA PETROLEUM ADMINISTRATION BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NORTH CHINA PETROLEUM ADMINISTRATION BUREAU filed Critical NORTH CHINA PETROLEUM ADMINISTRATION BUREAU
Priority to CN201310408912.8A priority Critical patent/CN103924944B/en
Publication of CN103924944A publication Critical patent/CN103924944A/en
Application granted granted Critical
Publication of CN103924944B publication Critical patent/CN103924944B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a well abandoning operation method for coal-bed gas horizontal wells, and belongs to the field of coal-bed gas exploitation. The well abandoning operation method includes that a drilling tool reenters the tail end of a main horizontal hole from a horizontal well, and sufficient circulation is carried out by the aid of clear water; the required quantity of cement slurry is computed according to the size and the length of the hole of a sealed well section, construction is optimized by means of controlling the initial setting time of the cement slurry, the cement slurry with the conventional density rho which is higher than or equal to 1.80g/cm<3> and is lower than or equal to 2.0g/cm<3> is prepared on the ground and is compressed into the well from a water hole of the drilling tool, and the main hole is sealed in a sectioned manner; the drilling tool in the well is tripped out and the well is shut down and waits on cement setting for 48-72 hours whenever a well section is sealed, so that the cement slurry in the well can be sufficiently set and solidified; the drilling tool is tripped into the well to detect plug surfaces, the previous steps are repeatedly carried out after the plug surfaces are qualified until all mudstone sections, including mudstone sections in casings, of the well are completely sealed, a wellhead is shut down, whether the pressure of the well is 10MPa or not is tested, the drilling tool is tripped out of the well after the pressure of the well is qualified, and well abandoning sealing operation is completed. The well abandoning operation method has the advantages that the main and branch mudstone sections are sealed by the aid of cement, accordingly, the integrity of coal-bed top plates and bottom plates can be recovered, and large-scale coal mining is unaffected after gas exploitation is completed.

Description

A kind of coal bed gas horizontal well abandoned well operational method
Technical field
The present invention relates to a kind of master props up the horizontal well abandoned well operational method in roof mud stone or base plate mud stone, belong to coal Layer gas exploitation field.
Background technology
Coal-bed gas exploitation is the first step of coal resources comprehensive mining, for ensureing making full use of of coal resources, needs over the ground Environment caused by the extraction of face, security risk carry out maximum elimination.Coal bed gas multi-branch horizontal is exploitation coal bed gas resource Main well type.For the main horizontal well in stable roof mud stone or base plate mud stone, when coal-bed gas exploitation terminate or because When accident needs discarded, there is presently no a kind of abandoned well method for this well type, to guarantee roof and base plate mud stone Integrality, thus prevent the potential safety hazard in later stage colliery scale recovery process.
Content of the invention
It is an object of the invention to provide a kind of coal bed gas horizontal well abandoned well operational method is it is adaptable to main in roof mud Rock or the horizontal well of base plate mud stone, to guarantee the integrality of roof and base plate mud stone.
The purpose of the present invention is realized by following proposal: a kind of coal bed gas horizontal well abandoned well operational method, its feature It is, when coal bed gas horizontal well group has a bite multi-branched horizontal well and a bite cave well, abandoned well operation comprises the following steps:
(1) drilling tool is reentried to a main horizontal hole end from horizontal well, is fully circulated with drilling fluid, and by the survey in drilling tool Measuring appratus are pulled out, and drilling fluid continues cycling through, and observe metering and import and export discharge capacity and fluidity;
(2) according to institute's sealing well section borehole size, cement slurry volume needed for length computation, excellent according to the presetting period of cement mortar Change construction, ground prepares 1.80≤ρ≤2.0g/cm3The cement mortar of conventional density, cement mortar is pressed into well from drilling tool water hole Interior, master is propped up with well section before well end and nearest branch's side tracking point, branches end to next side tracking point well section, Remote branch side tracking point well section in sleeve pipe carries out sealing successively;
(3) every certain well section of sealing, acts drilling tool closing well in well and waits solidifying 48-72 hour, so that cement mortar in well is fully solidified Cementing;
(4) enter under drilling tool pressurization 30kn visit plug face, qualified after, repeat the above steps until by full well mud stone section sealing to cover Manage interior 30 meters to complete, close testing pressure of well head 10mpa, qualified rear goes out drilling tool, completes abandoned well sealing operation.
A kind of coal bed gas horizontal well abandoned well operational method is it is characterised in that when coal bed gas horizontal well group has a bite multiple-limb When horizontal well and a bite near-end cave well, a bite far-end cave well, abandoned well operation comprises the following steps:
(1) hole capacity of calculated level well mud stone section, in horizontal well well head with adding the brill of tracer and sealing agent Circulation is set up between well liquid and far-end cave well well head;
(2) ground metering imports and exports discharge capacity, according to the consumption of sealing well section volume and circulation well cleanup, from ground prepare ρ≤ 1.45g/cm3Low-density cement mortar, close near-end cave well well head, be pressed into low-density cement mortar from horizontal well well head, until Cement slurry volume is filled to sleeve pipe, stops operation, and closes horizontal well and far-end cave well well head is waited and coagulated;
(3) treat that in well, cement mortar fully solidifies cementing, the solidifying 48-72 hour of time, horizontal well and far-end cave well well head are respectively Pressure testing 20mpa, qualified after complete abandoned well sealing operation.
A kind of coal bed gas horizontal well abandoned well operational method is it is characterised in that when coal bed gas horizontal well group has a bite multiple-limb When horizontal well and a bite near-end cave well, a bite far-end cave well, abandoned well operation can also complete according to the following steps:
(1) followed with adding the clear water of tracer and sealing agent to set up between far-end cave well well head and horizontal well well head Ring;
(2) ground metering imports and exports discharge capacity, according to the consumption of sealing well section volume and circulation well cleanup, from ground prepare ρ≤ 1.45g/cm3Low-density cement mortar, close near-end cave well well head, be pressed into low-density cement mortar from far-end cave well well head, Until cement mortar is filled to sleeve pipe, stop operation, close far-end cave well and horizontal well well head is waited and coagulated;
(3) treat that in well, cement mortar fully solidifies cementing, the solidifying 48-72 hour of time, horizontal well and far-end cave well well head are respectively Pressure testing 10mpa, qualified after complete abandoned well sealing operation.
The invention has the beneficial effects as follows: master, branch's mud stone section cement are carried out sealing by the present invention, recover coal seam top Plate, the integrality of base plate, do not affect gas production and terminate the scale exploitation of rear colliery.
Brief description
Fig. 1 is the coal bed gas horizontal well group structural representation having a bite multi-branched horizontal well and a bite cave well;
Fig. 2 is the coal bed gas horizontal well having a bite multi-branched horizontal well and a bite near-end cave well, a bite far-end cave well Group structural representation;
Fig. 3 is after the coal bed gas horizontal well group having a bite multi-branched horizontal well and a bite cave well implements abandoned well sealing operation Schematic diagram;
Fig. 4 is the coal bed gas horizontal well having a bite multi-branched horizontal well and a bite near-end cave well, a bite far-end cave well Group implements the post-job schematic diagram of abandoned well sealing.
In figure: 1. horizontal well;2. near-end cave well;3. far-end cave well;4. branch's mud stone section;5. split seam section;6. Main mud stone section.
Specific embodiment
With reference to specific embodiment, the present invention is described further.Fig. 1 can have a bite multiple-limb as the present embodiment The coal bed gas horizontal well group structural representation of horizontal well and a bite cave well, Fig. 2 can have a bite multiple-limb water as the present embodiment Horizontal well and the coal bed gas horizontal well group structural representation of a bite near-end cave well, a bite far-end cave well, Fig. 3 can be used as this enforcement Example has a bite multi-branched horizontal well and the coal bed gas horizontal well group of a bite cave well to implement the post-job schematic diagram of abandoned well sealing, figure 4 can have a bite multi-branched horizontal well and the coal bed gas level of a bite near-end cave well, a bite far-end cave well as the present embodiment Well group implements the post-job schematic diagram of abandoned well sealing.
As shown in figure 1, in the horizontal well group that a bite multi-branched horizontal well (1) and a bite cave well (2) combine, horizontal well Main is drilled with multiple horizontal branch, and horizontal segment is totally by branch's mud stone section (4), split seam section (5), main mud stone section (6) three Individual part composition.
Drilling tool is reentried to main horizontal hole end from horizontal well (1), is fully circulated normally with clear water, and by drilling tool Measuring instrument is pulled out, and clear water continues cycling through, and observes metering and imports and exports discharge capacity and fluidity, after normal, according to institute's sealing well section well Eye size, cement slurry volume needed for length computation, according to the presetting period Optimizing construction of cement mortar, ready uncovered stand is used on ground Cube slack tank prepares required conventional density (1.80≤ρ≤2.0g/cm3) cement mortar, by under become owner of the drilling tool of end , to well to well section before main well end and nearest branch's side tracking point, branches end is to next sidetracking for infusion Point well section, farthest branch side tracking point well section in sleeve pipe carries out sealing successively, the complete certain well section of every sealing, above carries drilling tool to sealing Well section above 1-3 rice reacting cycle well-flushing, cement mortar unnecessary in drilling tool is washed out, and acts drilling tool closing well in well and waits solidifying 72 hours.
Under enter drilling tool pressurization 30kn visit plug face, qualified after, repeat the above steps until by full well mud stone section sealing to sleeve pipe Interior 30 meters complete, and again enter down drilling tool and visit after cement plug face reaches requirement, close horizontal well (1), proximal-distal well (2) well head divides Other pressure testing 10mpa, qualified rear goes out drilling tool, completes abandoned well sealing operation, sees Fig. 3.
Meanwhile, present invention also offers another kind of abandoned well construction method, as shown in Fig. 2 in a bite multi-branched horizontal well (1) In the horizontal well group combining with a bite near-end cave well (2), a bite far-end cave well (3), horizontal well master props up and is drilled with multiple levels Branch, horizontal segment is totally made up of branch's mud stone section (4), split seam section (5), (6) three parts of main mud stone section.
When needing abandoned well, the hole capacity of calculated level well mud stone section, in horizontal well (1) well head with adding a certain amount of energy With the naked eye identification, color more obvious tracer and a certain amount of there is closure coal seam effect sealing agent clear water and far-end cave well (3) set up circulation between well head.
Situations such as ground metering imports and exports discharge capacity with returning outlet fluidity, according to the use of institute's sealing well section volume and circulation well cleanup Amount, prepares a certain amount of low-density (ρ≤1.45g/cm from ground with ready uncovered cube slack tank3) cement mortar, close Near-end cave well (2) well head, pumps into low-density cement mortar from horizontal well (1) well head, until pump into the water in well from ground metering Mud amount is filled to sleeve pipe, stops operation, and closes horizontal well (1) and far-end cave well (3) well head is waited and coagulated.
Treat that in well, cement mortar fully solidifies cementing, solidifying 72 hours of time, horizontal well (1) and far-end cave well (3) well head are respectively Pressure testing 10mpa, qualified after complete abandoned well sealing operation, see Fig. 4.
Also can with the naked eye can be known with a certain amount of with addition between far-end cave well (3) well head and horizontal well (1) well head Not, color more obvious tracer and a certain amount of there is closure coal seam effect sealing agent clear water set up circulation.
Situations such as ground metering imports and exports discharge capacity with returning outlet fluidity, according to the use of institute's sealing well section volume and circulation well cleanup Amount, prepares a certain amount of low-density (ρ≤1.45g/cm from ground with ready uncovered cube slack tank3) cement mortar, close Cave well well head 2, pumps into low-density cement mortar from cave well 3 well head, until from ground metering pump into cement slurry volume in well to In sleeve pipe, stop operation, close horizontal well (1) and far-end cave well (3) well head is waited and coagulated.
Treat that in well, cement mortar fully solidifies cementing, solidifying 72 hours of time, horizontal well (1) and far-end cave well (3) well head are respectively Pressure testing 20mpa, qualified after complete abandoned well sealing operation, see Fig. 4.

Claims (3)

1. a kind of coal bed gas horizontal well abandoned well operational method is it is characterised in that when coal bed gas horizontal well group has a bite multiple-limb water When horizontal well and a bite cave well, abandoned well operation comprises the following steps:
(1) drilling tool is reentried to a main horizontal hole end from horizontal well, is fully circulated with drilling fluid, and by the measuring instrument in drilling tool Device is pulled out, and drilling fluid continues cycling through, and observes metering and imports and exports discharge capacity and fluidity;
(2) according to institute's sealing well section borehole size, cement slurry volume needed for length computation, the presetting period according to cement mortar optimizes applies Work, ground prepares 1.80≤ρ≤2.0g/cm3The cement mortar of conventional density, by cement mortar in drilling tool water hole press-in well, right Well section before main well end and nearest branch's side tracking point, branches end to next side tracking point well section, farthest point Prop up side tracking point well section in sleeve pipe and carry out sealing successively;
(3) every certain well section of sealing, acts drilling tool closing well in well and waits solidifying 48-72 hour, so that cement mortar in well is fully solidified cementing;
(4) enter under drilling tool pressurization 30kn visit plug face, qualified after, repeat the above steps until by full well mud stone section sealing to sleeve pipe 30 meters complete, and close testing pressure of well head 10mpa, and qualified rear goes out drilling tool, completes abandoned well sealing operation.
2. a kind of coal bed gas horizontal well abandoned well operational method according to claim 1 is it is characterised in that work as coal bed gas level When well group has a bite multi-branched horizontal well and a bite near-end cave well, a bite far-end cave well, abandoned well operation has two kinds of construction parties Method, the construction method of the first abandoned well operation comprises the following steps:
(1) hole capacity of calculated level well mud stone section, in horizontal well well head with adding the drilling fluid of tracer and sealing agent Circulation is set up and the well well head of far-end cave between;
(2) ground metering imports and exports discharge capacity, according to the consumption of sealing well section volume and circulation well cleanup, from ground prepare ρ≤ 1.45g/cm3Low-density cement mortar, close near-end cave well well head, be pressed into low-density cement mortar from horizontal well well head, until Cement slurry volume is filled to sleeve pipe, stops operation, and closes horizontal well and far-end cave well well head is waited and coagulated;
(3) treat that in well, cement mortar fully solidifies cementing, the solidifying 48-72 hour of time, horizontal well and the pressure testing respectively of far-end cave well well head 20mpa, qualified after complete abandoned well sealing operation.
3. a kind of coal bed gas horizontal well abandoned well operational method according to claim 1 is it is characterised in that work as coal bed gas level When well group has a bite multi-branched horizontal well and a bite near-end cave well, a bite far-end cave well, second abandoned well job execution side Method completes according to the following steps:
(1) with adding the clear water of tracer and sealing agent to set up circulation between far-end cave well well head and horizontal well well head;
(2) ground metering imports and exports discharge capacity, according to the consumption of sealing well section volume and circulation well cleanup, from ground prepare ρ≤ 1.45g/cm3Low-density cement mortar, close near-end cave well well head, be pressed into low-density cement mortar from far-end cave well well head, Until cement mortar is filled to sleeve pipe, stop operation, close far-end cave well and horizontal well well head is waited and coagulated;
(3) treat that in well, cement mortar fully solidifies cementing, the solidifying 48-72 hour of time, horizontal well and the pressure testing respectively of far-end cave well well head 10mpa, qualified after complete abandoned well sealing operation.
CN201310408912.8A 2013-09-11 2013-09-11 Well abandoning operation method for coal-bed gas horizontal wells Expired - Fee Related CN103924944B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310408912.8A CN103924944B (en) 2013-09-11 2013-09-11 Well abandoning operation method for coal-bed gas horizontal wells

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310408912.8A CN103924944B (en) 2013-09-11 2013-09-11 Well abandoning operation method for coal-bed gas horizontal wells

Publications (2)

Publication Number Publication Date
CN103924944A CN103924944A (en) 2014-07-16
CN103924944B true CN103924944B (en) 2017-01-18

Family

ID=51143310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310408912.8A Expired - Fee Related CN103924944B (en) 2013-09-11 2013-09-11 Well abandoning operation method for coal-bed gas horizontal wells

Country Status (1)

Country Link
CN (1) CN103924944B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912480B (en) * 2015-04-30 2018-02-09 中煤科工集团西安研究院有限公司 Coal bed gas near-end docks the brill completion method of horizontal well
CN105089529B (en) * 2015-07-28 2017-10-27 西南石油大学 A kind of safe circulating valve coordinates the method for former well formation testing tubing string cementing plug abandoned well
CN109372465A (en) * 2018-09-29 2019-02-22 中国石化江汉油田分公司江汉采油厂 A kind of method for blocking for empty well cylinder abandoned well
CN111058794B (en) * 2019-11-26 2021-09-28 中国石油天然气股份有限公司 Control method and device for applying back pressure to annulus

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3850249A (en) * 1972-07-19 1974-11-26 Chevron Res Method for delaying the setting of an acid-settable liquid in a terrestrial zone
US4289354A (en) * 1979-02-23 1981-09-15 Edwin G. Higgins, Jr. Borehole mining of solid mineral resources
CN1924291A (en) * 2006-07-27 2007-03-07 山东省煤田地质局第二勘探队 Process for gas collection by a well with one mouth and multiple branches drilled along coal layer
CN101936142A (en) * 2010-08-05 2011-01-05 北京奥瑞安能源技术开发有限公司 Aerated underbalanced drilling method for coal-bed gas
CN102116140A (en) * 2011-01-25 2011-07-06 煤炭科学研究总院西安研究院 Construction method for enhancing extraction effect of ground coal bed gas

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7104320B2 (en) * 2003-12-04 2006-09-12 Halliburton Energy Services, Inc. Method of optimizing production of gas from subterranean formations

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3850249A (en) * 1972-07-19 1974-11-26 Chevron Res Method for delaying the setting of an acid-settable liquid in a terrestrial zone
US4289354A (en) * 1979-02-23 1981-09-15 Edwin G. Higgins, Jr. Borehole mining of solid mineral resources
CN1924291A (en) * 2006-07-27 2007-03-07 山东省煤田地质局第二勘探队 Process for gas collection by a well with one mouth and multiple branches drilled along coal layer
CN101936142A (en) * 2010-08-05 2011-01-05 北京奥瑞安能源技术开发有限公司 Aerated underbalanced drilling method for coal-bed gas
CN102116140A (en) * 2011-01-25 2011-07-06 煤炭科学研究总院西安研究院 Construction method for enhancing extraction effect of ground coal bed gas

Also Published As

Publication number Publication date
CN103924944A (en) 2014-07-16

Similar Documents

Publication Publication Date Title
CN108952796B (en) Comb-shaped bottom plate through-layer drilling fracturing permeability-increasing-based modular extraction method
CN108756841B (en) Shale repeated fracturing treatment method
CN102877884B (en) The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method
CN103195468A (en) System process for conducting efficient strengthened extraction in surrounding rock
CN203808945U (en) Water plugging and controlling technical tubular column for open hole screen pipe completion horizontal well root
CN103924944B (en) Well abandoning operation method for coal-bed gas horizontal wells
CN105181927B (en) The hypotonic coal seam hydraulic fracture simulation experiment method of multi- scenarios method
CN102704984A (en) Borehole high-concentration gas extraction and drainage method and device thereof
CN103993902B (en) A kind of mash gas pumping drilling two step slip-casting hole-sealing method
CN106930713A (en) Casing pipe damage repairing method
CN103510964A (en) Method for performing backfill grouting on pea gravel by adoption of shield type TBM in construction process
CN113073966B (en) Shale gas horizontal well casing middle-casing-fixing repeated fracturing method
CN102536269A (en) Underground grouting and water-plugging process
CN209179725U (en) A solid-liquid two-phase hole sealing device for gas drainage drilling
CN108952760A (en) A kind of intelligent circulation increasing-pressure-releasing type dynamic grouting system and method
CN102561989A (en) Coal mine underground hydraulic fracturing hole sealing method
CN103590817B (en) The abandoned oil gas well administering method in coal mining region
CN109098750B (en) A device and construction method in which an underground gas extraction hole doubles as a coal seam water injection hole
CN105201483A (en) Environment-friendly downhole stratum fracturing method
CN110454123A (en) A kind of more wells collaboration energizations of LOW PERMEABILITY RESERVOIR are handled up method
CN102102503A (en) Sand prevention method for four-inch small hole
CN109578058B (en) Method for improving gas extraction concentration of extraction borehole through auxiliary drilling
CN104929565A (en) Double-layered grouting guide pipe
CN104612649A (en) Method and device for fracturing and permeability and yield increasing of coal-bed gas well of low-pressure and low permeability reservoir by means of chemical permeability increasing
CN105569602A (en) Method for sealing channeling outside oil well pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant