[go: up one dir, main page]

CN103195468A - System process for conducting efficient strengthened extraction in surrounding rock - Google Patents

System process for conducting efficient strengthened extraction in surrounding rock Download PDF

Info

Publication number
CN103195468A
CN103195468A CN2013101121776A CN201310112177A CN103195468A CN 103195468 A CN103195468 A CN 103195468A CN 2013101121776 A CN2013101121776 A CN 2013101121776A CN 201310112177 A CN201310112177 A CN 201310112177A CN 103195468 A CN103195468 A CN 103195468A
Authority
CN
China
Prior art keywords
hole
boring
pressure
sealing
coal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101121776A
Other languages
Chinese (zh)
Inventor
周东平
徐涛
周声才
覃乐
王文春
何兴玲
沈大富
余模华
郭臣业
王联
何苗
周俊杰
李栋
张迪
张翠兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Energy Technology Investment Group Co Ltd
Original Assignee
Chongqing Energy Technology Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Energy Technology Investment Group Co Ltd filed Critical Chongqing Energy Technology Investment Group Co Ltd
Priority to CN2013101121776A priority Critical patent/CN103195468A/en
Publication of CN103195468A publication Critical patent/CN103195468A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses system process for conducting efficient strengthened extraction in a surrounding rock. The system process includes that a common drilling machine is used for forming a drill hole through a pneumatic impacter in the surrounding rock, namely a top plate or a base plate, of a coal reservoir, wherein strengthened extraction is planned to be implemented on the coal reservoir, a plurality of spray holes for communicating a coal rock stratum and the drill hole are sprayed through a hydraulic sand blasting perforation method, a plurality of observing holes are distributed with the drill hole as a center, and hole sealing processing is conducted on the drill hole and the observing holes; and fracture is conducted through the drill hole, a fracture affecting range is determined through monitoring pressure change conditions of the observing holes, and operation of draining while extracting with negative pressure through the drill hole and the observing holes is conducted. Preferentially, hole sealing operation is conducted through a grouting hole sealing method. The system process has the advantage that a problem of hole collapsing, drilling machine blocking and the like during hole drilling in a minge layer can be solved; exposing area of a coal mass is increased due to branch holes formed by high-pressure spraying; and hydraulic fracture presses coal and rock mass among cracks, original cracks in a coal layer are fully opened, extend and are communicated with one another, large-range of pressure relief of the coal mass is achieved, and gas extraction rate is improved.

Description

A kind of system process of in country rock, efficiently strengthening extraction
Technical field
The present invention relates to a kind of method, particularly a kind of system process of in country rock, efficiently strengthening extraction for easily projecting coal bed local or regional extinction.
Background technology
It mainly is to adopt parallel boring, oblique boring, grid type boring, shallow bore hole destressing borehole, high-order boring, goaf pipe laying, layer-through drilling, the boring of suitable layer, graded crossing boring etc. to carry out gas pumping that traditional coal mine gas is administered, but effect depends primarily on the original gas permeability of coal seam reservoirs, the borehole engineering amount is big, gas pumping concentration is low, and the extinction time is long.For improving the coal seam reservoirs gas permeability, adopt waterpower measures such as high-pressure water jet reaming, waterpower are extruded, deep hole high pressure water injection, hydraulic slotted liner technique method, hydraulic flushing in hole, waterpower slotting, obtained certain effect, but their anti-reflection being limited in scope, and easily bring out outstanding accident, generally do not promoted.Using for reference under the coal mine of the wellfracturing of oil field and ground coal bed gas well pressure break fracturing administers gas and becomes current emerging technology and used by research more and more widely, investigate current numerous technologies, present colliery underground fracture all adopts pressure break of long drilled holes, fracturing fracture is inhomogeneous, often form single short wide seam, gas production is not high, or effect can not keep lastingly.
Chinese patent publication number CN1534164A, open October 6 2004 date, invention and created name " the long-range pressure relief gas pumping mining method of the soft high seam of the high gas of low-permeable ".The extraction lane that this method is included in seat earth has layer extraction boring of wearing of getting a plurality of latticed settings in the soft high seam along layer separation fracture upward, gas pressure relief is along coming together in extraction boring along layer separation fracture, by the extraction pipeline extraction, to realize the purpose of extraction release.Obviously, this method drilling hole amount is many, and a plurality of drill sites need be set, and extraction time is long, and only be adapted to can be by adopting the soft seam that forms along layer separation fracture.Chinese patent publication number CN101022575A, open February 5 2007 date, invention and created name " projecting coal bed down to the regional gas pumping method of shielding that goes forward one by one along layer long drilled holes ".This method by superficial part to the deep, by the present low gas district to high gas district, descend to the inclination long drilled holes, take out in advance coal-bed gas by last bank face machine lane or the construction of waist lane, to reduce coal seam gas-bearing capacity, regional eliminating is except the outburst hazard in coal seam, realize projecting coal bed tunnel mechanization driving and safety and high efficiency, it is only applicable to soft high seam, and mainly is to realize gas pumping by boring, has deficiencies such as drill hole density is big, gas pumping efficient is low, the extraction time is long.Chinese patent publication number CN201826748U, open May 11 2011 date, invention and created name " a kind of device that creeps into the profound gas pumping of weak seam hole along layer ", this device comprises radial nozzles and the axial nozzle that is arranged on the drill bit, utilize hard coal layering or the roof and floor characteristics of boring easily, optionally utilize axial nozzle in hard coal layering or roof and floor, to carry out pulsing jet boring and the mode from hard coal layering or roof and floor to the soft seam slot, to increase the gas pumping scope.But for the band gas of extraction coal road, owing to the slot scope causes the slot time long greatly, cause tunnelling time long, efficient is low.Therefore, the existing coal-bed gas method of taking out in advance is not suitable for the coal mine gas hazard management to effect and the efficient requirement of coal road band gas pumping, is restricting the production efficiency of colliery, China southwest weak seam to a certain extent.
Summary of the invention
The object of the invention is at above-mentioned the deficiencies in the prior art, and a kind of system process of efficiently strengthening extraction in country rock is provided, and the common rig of this technology utilization is installed air hammer and constructed in country rock, with avoid bit freezing, problems such as the hole of collapsing, spray orifice; Utilize high pressure slurries sealing of hole, the high pressure when both bearing pressure break, that is not holed again faces upward the restriction of bowing; Scale pressure break behind the abrasive perforating can realize that release on a large scale is anti-reflection and the crack is anti-reflection, to shorten the extinction time and to improve the gas recovery ratio.
For achieving the above object, the present invention adopts following technical scheme.
A kind of system process of efficiently strengthening extraction in country rock may further comprise the steps:
A, be in top board or the base plate at the country rock of the coal seam reservoirs of intend to implement strengthening extraction, utilize common rig by hollow drill pipe air hammer to be installed and form drilling tool and execute on request and bore boring, utilize the boring of compressed air purge after the boring, withdraw from drilling tool then;
B, pull down air hammer and with drilling rod and the injector head formation hydraulic jeting device that is sealedly and fixedly connected, and injector head is delivered to set depth position in the boring;
C, hydraulic jeting device is connected with the fracturing pump group, makes it form complete high-pressure system;
D, start the pressure testing of fracturing pump group, pressure testing is included in to be set the following duration of operating pressure and is no less than the sand of 5min, medium than not being higher than 5%;
E, carry out the high pressure abrasive perforating to form spray-hole in the setting phase place of set depth of boring, spray-hole runs through the casing hole wall of boring and stretches into coal seam reservoirs; The monitoring field condition is unusual if system pressure occurs in real time, then stops to spray and taking corresponding measure, makes it recover normal back and continues the abrasive perforating operation;
F, rotation injection apparatus are to next phase place, and repeated execution of steps e finishes until boring all spray-holes injections on the same degree of depth;
G, movable spray device arrive spray site, repeated execution of steps e ~ f, and all spray-holes in boring spray to be finished; Wherein, the distance that is positioned at the inner end of sealing of hole section of the spray-hole of outermost end and boring is no less than 5m;
H, centered by boring, arrange the investigation hole of some and spacing, investigate the hole and be used for the later stage and carry out determining of pressure break influence basin;
I, adopt the injection hole sealing mode to form the sealing of hole section in boring and the aperture of investigating the hole, and connect and can long-range demonstration investigate the pressure meter that hole internal pressure and indication range are not less than 50MPa investigating outer end of hole;
J, a continuous week and observe every day at least one times and the recording manometer readings, and be depicted as pressure curve;
K, will hole is connected with the fracturing pump group, and boring is carried out the pressing crack construction operation as the pressure break hole; During pressure break, remote observation is investigated the pressure changing in hole and is compared with the pressure curve data, determines the pressure break influence basin with change value of pressure; The pressure break influence basin reaches requirement execution in step l, otherwise, continue pressure break;
L, stop fracturing work, in boring and investigate outside the aperture, hole air water pulp separator and gas monitor equipment all are installed, and with gas pumping equipment by air water divide slag from device respectively with boring with investigate the hole and be connected;
M, carry out draining limit, limit negative pressure band and take out operation, regularly the gas outburst risk of target area is verified, if up to standard, execution in step n then; If not up to standard, continue to carry out this step;
N, stop extraction.
Investigating position, the quantity in hole among the present invention should determine according to coal road section size and coal seam geological condition; Compressed air air pressure 〉=the 1.2MPa of purge boring.
The sealing of hole section that described injection hole sealing mode forms in the aperture in boring or investigation hole, comprise that formation forms described sealing of hole section by the outer section of section, sealing of hole stage casing and sealing of hole in the sealing of hole that arranges from inside to outside, wherein, section is made up of inner termination, organic slurry sealing of hole section and cotton yarn sealing of hole section in the sealing of hole; The sealing of hole stage casing forms by the cement grout of perfusion label 〉=425; The outer section of sealing of hole is made up of organic slurry sealing of hole section and outer end plug; Aperture in boring or investigation hole also is provided with Grouting Pipe and the water injection pipe that is connected to one, on Grouting Pipe or water injection pipe, be provided with a plurality of support chips by fixedly connected mode, the outlet of Grouting Pipe inner end is positioned at the sealing of hole stage casing, the aperture that the outer end of Grouting Pipe is positioned at boring or investigates the hole is outward for being connected with filling system, the inner outlet of water injection pipe runs through the sealing of hole section and stretches in boring or the investigation hole, the inner outlet of water injection pipe is positioned at boring or investigates outside the aperture in hole, water injection pipe outer end in the pressure break hole is respectively applied to be connected with the fracturing pump group during with pressure break in jetting, is connected with the air water pulp separator when the negative pressure band is taken out; Be connected with pressure meter with the air water pulp separator when being positioned at the water injection pipe outer end of investigating the hole and taking out for the negative pressure band; When the pressure observed and recorded, be connected with pressure meter.
Utilize this method in casing, to execute and bore a plurality of borings for pressure break, and centered by boring, lay a plurality of investigations hole, to implement large-scale pressure break and to strengthen the extraction operation by a plurality of pressure breaks hole and investigation hole, realize the purpose of regional protrusion-dispelling.Concrete scope is determined according to load capacity and the coal rock layer character of fracturing pump group group.
The invention has the beneficial effects as follows: be chosen in the top board that constitutes the coal seam casing or the base plate and hole, avoided in the cherry coal layering, holing and occurred the problems such as hole, bit freezing of collapsing easily, simultaneously, coal and rock is formed branched hole by high-pressure injection, increase the exposed area of coal body; Utilize branch to carry out the directed fracturing of high pressure on an empty stomach, press the coal and rock between the through cracks seam, make in the coal seam original crack fully open, extend, connect mutually, make coal body release on a large scale anti-reflection, improve the gas pumping rate, guarantee tunnelling work safety, shorten the time of tunnelling, improve seam mining efficient.
Description of drawings
Figure l is process chart of the present invention.
Fig. 2 is the structural representation of the present invention after middle boring 3 jettings form spray-hole 5.
Fig. 3 is sealing of hole and the relevant schematic diagram of fracturing technology among the present invention.
The specific embodiment
The present invention is further illustrated below in conjunction with accompanying drawing, but therefore do not limit the present invention among the described scope of embodiments.
Referring to Fig. 1, Fig. 2, Fig. 3, a kind of system process of efficiently strengthening extraction in country rock 6 may further comprise the steps:
A, be in top board or the base plate at the country rock 6 of the coal seam reservoirs 8 of intend to implement strengthening extraction, utilize common rig by hollow drill pipe 1 air hammer to be installed and form drilling tool and execute on request and bore boring 3, utilize compressed air purge boring 3 after the boring 3, withdraw from drilling tool then;
B, pull down air hammer and with drilling rod 1 and the injector head 7 formation hydraulic jeting device that is sealedly and fixedly connected, and injector head 7 is delivered to set depth positions in the boring 3;
C, hydraulic jeting device is connected with the fracturing pump group 4 of injection and frac system, makes it form complete high-pressure system;
D, start 4 pressure testings of fracturing pump group, pressure testing is included in to be set the following duration of operating pressure and is no less than the sand of 5min, medium than not being higher than 5%;
E, carry out the high pressure abrasive perforating to form spray-hole 5 in the setting phase place of boring 3 set depths, spray-hole 5 runs through 6 layers of hole wall of country rock of boring 3 and stretches into coal seam reservoirs 8; The monitoring field condition is unusual if system pressure occurs in real time, then stops to spray and taking corresponding measure, makes it recover normal back and continues the abrasive perforating operation;
F, rotation injection apparatus are to next phase place, and repeated execution of steps e finishes until boring 3 all spray-holes 5 injections on the same degree of depth;
G, movable spray device arrive spray site, repeated execution of steps e ~ f, and all spray-holes 5 in boring 3 spray to be finished; Wherein, the distance of the inner end of the sealing of hole section 2 of the spray-hole 5 that is positioned at outermost end and boring 3 is no less than 5m;
H, to hole centered by 3, arrange the investigation hole of some and spacing, investigate the hole and be used for the later stage and carry out determining of pressure break influence basin;
I, adopt the injection hole sealing mode to form sealing of hole section 2 in boring 3 and the aperture of investigating the hole, and connect and can long-range demonstration investigate the pressure meter that hole internal pressure and indication range are not less than 50MPa investigating outer end of hole;
J, a continuous week and observe every day at least one times and the recording manometer readings, and be depicted as pressure curve;
K, will hole 3 is connected with fracturing pump group 4, and boring 3 is carried out the pressing crack construction operation as the pressure break hole; During pressure break, remote observation is investigated the pressure changing in hole and is compared with the pressure curve data, determines the pressure break influence basin with change value of pressure; The pressure break influence basin reaches requirement execution in step l, otherwise, continue pressure break;
L, stop fracturing work, in boring 3 and investigate outside the aperture, hole air water pulp separator and gas monitor equipment all are installed, and gas pumping equipment is connected with boring 3 and investigation hole respectively by the air water pulp separator;
M, carry out draining limit, limit negative pressure band and take out operation, regularly the gas outburst risk of target area is verified, if up to standard, execution in step n then; If not up to standard, continue to carry out this step;
N, stop extraction.
The sealing of hole section 2 that described injection hole sealing mode forms in the aperture in boring 3 or investigation hole, comprise that the outer section 23 of section 21, sealing of hole stage casing 22 and sealing of hole is formed sealing of hole sections 2 in the sealing of hole that formation arranges from inside to outside, wherein, section 21 is made up of inner termination 21a, organic slurry sealing of hole section 21b and cotton yarn sealing of hole section 21c in the sealing of hole; Sealing of hole stage casing 22 forms by the cement grout of perfusion label 〉=425; The outer section of sealing of hole 23 is made up of organic slurry sealing of hole section 23a and outer end plug 23b; Aperture in boring 3 or investigation hole also is provided with Grouting Pipe 11 and the water injection pipe 10 that is connected to one, on Grouting Pipe 11 or water injection pipe 10, be provided with a plurality of support chips 14 by fixedly connected mode, the outlet of Grouting Pipe 11 inner ends is positioned at sealing of hole stage casing 22, the aperture that the outer end of Grouting Pipe 11 is positioned at boring 3 or investigates the hole is outward for being connected with filling system, the inner outlet of water injection pipe 10 runs through sealing of hole section 2 and stretches in boring 3 or the investigation hole, the inner outlet of water injection pipe 10 is positioned at boring 3 or investigates outside the aperture in hole, and water injection pipe 10 outer ends in the pressure break hole are respectively applied to be connected gentle grain slag eliminator with fracturing pump group 4 and connect; Being positioned at water injection pipe 10 outer ends of investigating the hole is used for being connected with pressure meter with the air water pulp separator.
Compressed air air pressure 〉=the 1.2MPa of described purge boring 3.
The position in described investigation hole, quantity should be determined according to coal road section size and coal seam geological condition.
Injection in the present embodiment and frac system also are provided with switch board 12 and relief valve 13 except being provided with fracturing pump group 4.
Filling system in the present embodiment is provided with slurry mixing tank 15, grouting pump 16, second relief valve 17 and system pressure table 18 etc.
In concrete regional protrusion-dispelling is used, can utilize this method in 6 layers on country rock, to execute and bore a plurality of borings 3 for pressure break, and to hole centered by 3, lay a plurality of investigations hole, to implement large-scale pressure break and to strengthen the extraction operation by a plurality of pressure breaks hole and investigation hole, realize the purpose of regional protrusion-dispelling.
Though more than combine accompanying drawing and described embodiments of the present invention, but those of ordinary skill in the art can recognize also in the scope to claims and make various variations or modification that these modifications and variations are interpreted as within scope of the present invention and intention.

Claims (4)

1. a system process of efficiently strengthening extraction in country rock is characterized in that, may further comprise the steps:
A, in the country rock (6) of the coal seam reservoirs (8) of intend to implement strengthening extraction, utilizing common rig by hollow drill pipe (1) air hammer to be installed forms drilling tool and executes brill boring (3) on request, boring (3) utilizes compressed air purge boring (3) after reaching set depth, withdraws from drilling tool then;
B, pull down air hammer and with drilling rod (1) and injector head (7) the formation hydraulic jeting device that is sealedly and fixedly connected, and injector head (7) is delivered to the interior set depth position of boring (3);
C, hydraulic jeting device is connected with the fracturing pump group (4) of injection and frac system, makes it form complete high-pressure system;
D, the pressure testing of startup fracturing pump group (4), pressure testing is included in the sand ratio≤5% of setting following duration of operating pressure 〉=5min, medium;
E, carry out the high pressure abrasive perforating to form spray-hole (5) in the setting phase place of boring (3) set depth, spray-hole (5) runs through country rock (6) layer hole wall of boring (3) and stretches into coal seam reservoirs (8); The monitoring field condition is unusual if system pressure occurs in real time, then stops to spray and taking corresponding measure, makes it recover normal back and continues the abrasive perforating operation;
F, rotation injection apparatus are to next phase place, and repeated execution of steps e finishes until all spray-holes (5) injection of boring (3) on the same degree of depth;
G, movable spray device are to spray site, and repeated execution of steps e ~ f, all spray-holes (5) in boring (3) spray and finish; Wherein, the distance 〉=5m of the inner end of the sealing of hole section (2) of the spray-hole (5) that is positioned at outermost end and boring (3);
H, centered by boring (3), arrange the investigation hole of some and spacing, investigate the hole and be used for the later stage and carry out determining of pressure break influence basin;
I, adopt the injection hole sealing mode to form sealing of hole section (2) in boring (3) and the aperture of investigating the hole, and investigate that outer end of hole connects can long-range demonstration investigation hole internal pressure and the pressure meter of indication range 〉=50MPa;
J, a continuous week and observe every day at least one times and the recording manometer readings, and be depicted as pressure curve;
K, will hole (3) are connected with fracturing pump group (4), and boring (3) is carried out the pressing crack construction operation as the pressure break hole; During pressure break, remote observation is investigated the pressure changing in hole and is compared with the pressure curve data, determines the pressure break influence basin with change value of pressure; The pressure break influence basin reaches requirement execution in step l, otherwise, continue pressure break;
L, stop fracturing work, in boring (3) and investigate outside the aperture, hole air water pulp separator and gas monitor equipment all are installed, and gas pumping equipment is connected with boring (3) and investigation hole respectively by the air water pulp separator;
M, carry out draining limit, limit negative pressure band and take out operation, regularly the gas outburst risk of target area is verified, if up to standard, execution in step n then; If not up to standard, continue to carry out this step;
N, stop extraction.
2. the system process of in country rock, efficiently strengthening extraction according to claim 1, it is characterized in that, the sealing of hole section (2) that described injection hole sealing mode forms in the aperture in boring (3) or investigation hole, comprise that formation forms described sealing of hole section (2) by section (21), sealing of hole stage casing (22) and sealing of hole in the sealing of hole that arranges from inside to outside outer section (23), wherein, section (21) is made up of inner termination (21a), organic slurry sealing of hole section (21b) and cotton yarn sealing of hole section (21c) in the sealing of hole; Sealing of hole stage casing (22) forms by the cement grout of perfusion label 〉=425; The outer section of sealing of hole (23) is made up of organic slurry sealing of hole section (23a) and outer end plug (23b); Aperture in boring (3) or investigation hole also is provided with Grouting Pipe (11) and the water injection pipe (10) that is connected to one, upward be provided with a plurality of support chips (14) by fixedly connected mode in Grouting Pipe (11) or water injection pipe (10), the outlet of Grouting Pipe (11) inner end is positioned at sealing of hole stage casing (22), and the outer end of Grouting Pipe (11) is positioned at boring (3) or investigates outside the aperture in hole; The inner outlet of water injection pipe (10) is passed sealing of hole section (2) and is stretched in boring (3) or the investigation hole, and the inner outlet of water injection pipe (10) is positioned at boring (3) or investigates outside the aperture in hole.
3. the system process of efficiently strengthening extraction in country rock according to claim 1 is characterized in that, the compressed air air pressure 〉=1.2MPa of described purge boring (3).
4. the technology of the efficient reinforcement extraction of carrying out in country rock according to claim 1 is characterized in that, the position in described investigation hole, quantity should be determined according to coal road section size and coal seam geological condition.
CN2013101121776A 2013-04-02 2013-04-02 System process for conducting efficient strengthened extraction in surrounding rock Pending CN103195468A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101121776A CN103195468A (en) 2013-04-02 2013-04-02 System process for conducting efficient strengthened extraction in surrounding rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101121776A CN103195468A (en) 2013-04-02 2013-04-02 System process for conducting efficient strengthened extraction in surrounding rock

Publications (1)

Publication Number Publication Date
CN103195468A true CN103195468A (en) 2013-07-10

Family

ID=48718267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101121776A Pending CN103195468A (en) 2013-04-02 2013-04-02 System process for conducting efficient strengthened extraction in surrounding rock

Country Status (1)

Country Link
CN (1) CN103195468A (en)

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103899349A (en) * 2014-04-23 2014-07-02 重庆市能源投资集团科技有限责任公司 Coal seam gas extraction method and extraction hole radial drilling guide device
CN103899348A (en) * 2014-04-23 2014-07-02 重庆市能源投资集团科技有限责任公司 Method for fast extracting gas on coalface
CN104374589A (en) * 2014-10-31 2015-02-25 河南理工大学 Method for accurately measuring gas phase fracture disturbance range
CN104929588A (en) * 2015-07-15 2015-09-23 连云港黄海机械股份有限公司 Non-excavation underground buried pipe gas conveying device for coal bed gas exploitation
CN106593528A (en) * 2017-01-22 2017-04-26 成都理工大学 Air pressure fracturing high stress blocking method for large deformation of tunnel and device thereof
CN106703805A (en) * 2016-12-02 2017-05-24 中国矿业大学 Drilling up rock drilling all-in-one machine based on high pressure froth medium
CN107083945A (en) * 2017-06-13 2017-08-22 中铁十九局集团矿业投资有限公司 A kind of roof fracturing system and its implementation
CN107121036A (en) * 2017-06-08 2017-09-01 刘冲 Di Chou lanes return air connection lane deep hole blasting method
CN107201828A (en) * 2017-06-21 2017-09-26 青岛林川工程技术咨询有限公司 A kind of uncompacted restorative procedure of prestress hole path pressure grouting
CN107401402A (en) * 2017-09-05 2017-11-28 中国矿业大学(北京) A kind of mash gas pumping drilling stability fixed point monitoring attending device and method
CN109268060A (en) * 2018-09-20 2019-01-25 中国矿业大学 One kind is based on the quick-fried note integrated regional anti-burst method of strong and weak strong structure
CN109723382A (en) * 2019-01-12 2019-05-07 江西理工大学 A kind of construction method of horizontal guide hole
WO2019228042A1 (en) * 2018-07-03 2019-12-05 安徽理工大学 Hydraulic perforation unmanned gas extraction method
CN111535791A (en) * 2020-05-08 2020-08-14 中煤科工集团西安研究院有限公司 Efficient gas extraction method for broken soft low-permeability coal seam well upper and lower combined fracturing area
CN111608707A (en) * 2020-04-29 2020-09-01 临沂矿业集团菏泽煤电有限公司 Rock burst dangerous roadway support method based on double-cylinder protection theory
CN111608663A (en) * 2020-04-29 2020-09-01 临沂矿业集团菏泽煤电有限公司 Omnibearing pressure relief method for rock burst dangerous roadway of thick coal seam working face
CN112253067A (en) * 2020-08-26 2021-01-22 煤科集团沈阳研究院有限公司 Cross fracturing cooperative permeability increasing method for grid drilling of thick coal seam
CN112431591A (en) * 2020-10-20 2021-03-02 重庆市能源投资集团科技有限责任公司 Automatic control system for comprehensive mechanized coal mining of three-soft two-large inclined medium-thickness coal seam
CN113047899A (en) * 2021-04-09 2021-06-29 中国矿业大学 Deep hole multistage loosening blasting cracking method
CN113417639A (en) * 2021-07-28 2021-09-21 西安科技大学 Hard coal seam water injection scour prevention method and system
CN114151078A (en) * 2021-12-02 2022-03-08 中国铁建重工集团股份有限公司 Water jet waste rock layer cut device
CN116411964A (en) * 2023-05-26 2023-07-11 中国矿业大学 Hydraulic fracturing cutting cooperative device suitable for hard rock and use method
CN117684592A (en) * 2024-02-02 2024-03-12 中国冶金地质总局第三地质勘查院 Method for treating serial layer polluted water well

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101382073A (en) * 2007-09-29 2009-03-11 永城煤电集团有限责任公司 Fast tunneling method for three-soft low-permeability high-gas coal seam
CN102287163A (en) * 2011-09-08 2011-12-21 重庆市能源投资集团科技有限责任公司 Drilling-sealing method and sealing device of coal mine underground ultrahigh pressure fracturing hole
CN102493833A (en) * 2011-11-25 2012-06-13 重庆市能源投资集团科技有限责任公司 Depressurized extraction method for cutting through roof or floor of coal seam by abrasive water jet
CN102619552A (en) * 2012-02-24 2012-08-01 煤炭科学研究总院沈阳研究院 Directional hydraulic pressing penetration, permeability increase and outburst elimination method of guide groove
CN102733844A (en) * 2012-04-27 2012-10-17 徐州中矿安达矿山科技有限公司 Hole sealing structure and hole sealing method as well as expansive cement for sealing hole
WO2012174586A2 (en) * 2011-06-24 2012-12-27 Ian Gray Mining method for gassy and low permeability coal seams

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101382073A (en) * 2007-09-29 2009-03-11 永城煤电集团有限责任公司 Fast tunneling method for three-soft low-permeability high-gas coal seam
WO2012174586A2 (en) * 2011-06-24 2012-12-27 Ian Gray Mining method for gassy and low permeability coal seams
CN102287163A (en) * 2011-09-08 2011-12-21 重庆市能源投资集团科技有限责任公司 Drilling-sealing method and sealing device of coal mine underground ultrahigh pressure fracturing hole
CN102493833A (en) * 2011-11-25 2012-06-13 重庆市能源投资集团科技有限责任公司 Depressurized extraction method for cutting through roof or floor of coal seam by abrasive water jet
CN102619552A (en) * 2012-02-24 2012-08-01 煤炭科学研究总院沈阳研究院 Directional hydraulic pressing penetration, permeability increase and outburst elimination method of guide groove
CN102733844A (en) * 2012-04-27 2012-10-17 徐州中矿安达矿山科技有限公司 Hole sealing structure and hole sealing method as well as expansive cement for sealing hole

Cited By (36)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103899348A (en) * 2014-04-23 2014-07-02 重庆市能源投资集团科技有限责任公司 Method for fast extracting gas on coalface
CN103899349A (en) * 2014-04-23 2014-07-02 重庆市能源投资集团科技有限责任公司 Coal seam gas extraction method and extraction hole radial drilling guide device
CN104374589B (en) * 2014-10-31 2019-01-25 河南理工大学 A method to accurately measure the disturbance range of gas fracturing
CN104374589A (en) * 2014-10-31 2015-02-25 河南理工大学 Method for accurately measuring gas phase fracture disturbance range
CN104929588A (en) * 2015-07-15 2015-09-23 连云港黄海机械股份有限公司 Non-excavation underground buried pipe gas conveying device for coal bed gas exploitation
WO2018099262A1 (en) * 2016-12-02 2018-06-07 中国矿业大学 Rock drilling, swelling and chiselling combined machine based on high-pressure foam medium
RU2685355C1 (en) * 2016-12-02 2019-04-17 Китайский Университет Горного Дела И Технологии Integrated device for drilling, decompaction and chiseling of rock based on high-pressure foam
CN106703805A (en) * 2016-12-02 2017-05-24 中国矿业大学 Drilling up rock drilling all-in-one machine based on high pressure froth medium
CN106593528A (en) * 2017-01-22 2017-04-26 成都理工大学 Air pressure fracturing high stress blocking method for large deformation of tunnel and device thereof
CN107121036A (en) * 2017-06-08 2017-09-01 刘冲 Di Chou lanes return air connection lane deep hole blasting method
CN107083945A (en) * 2017-06-13 2017-08-22 中铁十九局集团矿业投资有限公司 A kind of roof fracturing system and its implementation
CN107201828A (en) * 2017-06-21 2017-09-26 青岛林川工程技术咨询有限公司 A kind of uncompacted restorative procedure of prestress hole path pressure grouting
CN107401402A (en) * 2017-09-05 2017-11-28 中国矿业大学(北京) A kind of mash gas pumping drilling stability fixed point monitoring attending device and method
WO2019228042A1 (en) * 2018-07-03 2019-12-05 安徽理工大学 Hydraulic perforation unmanned gas extraction method
CN109268060A (en) * 2018-09-20 2019-01-25 中国矿业大学 One kind is based on the quick-fried note integrated regional anti-burst method of strong and weak strong structure
CN109268060B (en) * 2018-09-20 2020-06-16 中国矿业大学 Explosion-injection integrated region outburst prevention method based on strong and weak structure
CN109723382A (en) * 2019-01-12 2019-05-07 江西理工大学 A kind of construction method of horizontal guide hole
CN109723382B (en) * 2019-01-12 2020-04-17 江西理工大学 Construction method of horizontal diversion hole
CN111608663A (en) * 2020-04-29 2020-09-01 临沂矿业集团菏泽煤电有限公司 Omnibearing pressure relief method for rock burst dangerous roadway of thick coal seam working face
CN111608707A (en) * 2020-04-29 2020-09-01 临沂矿业集团菏泽煤电有限公司 Rock burst dangerous roadway support method based on double-cylinder protection theory
CN111535791A (en) * 2020-05-08 2020-08-14 中煤科工集团西安研究院有限公司 Efficient gas extraction method for broken soft low-permeability coal seam well upper and lower combined fracturing area
CN112253067A (en) * 2020-08-26 2021-01-22 煤科集团沈阳研究院有限公司 Cross fracturing cooperative permeability increasing method for grid drilling of thick coal seam
CN112253067B (en) * 2020-08-26 2021-12-10 中煤科工集团沈阳研究院有限公司 Cross fracturing cooperative permeability increasing method for grid drilling of thick coal seam
CN112431591B (en) * 2020-10-20 2023-02-21 重庆市能源投资集团科技有限责任公司 Automatic control system for comprehensive mechanized coal mining of three-soft two-large inclined medium-thickness coal seam
CN112431591A (en) * 2020-10-20 2021-03-02 重庆市能源投资集团科技有限责任公司 Automatic control system for comprehensive mechanized coal mining of three-soft two-large inclined medium-thickness coal seam
CN113047899A (en) * 2021-04-09 2021-06-29 中国矿业大学 Deep hole multistage loosening blasting cracking method
CN113047899B (en) * 2021-04-09 2022-02-01 中国矿业大学 Deep hole multistage loosening blasting cracking method
CN113417639B (en) * 2021-07-28 2023-10-20 西安科技大学 Method and system for preventing water injection of hard coal seam from rushing
CN113417639A (en) * 2021-07-28 2021-09-21 西安科技大学 Hard coal seam water injection scour prevention method and system
CN114151078A (en) * 2021-12-02 2022-03-08 中国铁建重工集团股份有限公司 Water jet waste rock layer cut device
CN114151078B (en) * 2021-12-02 2024-04-19 中国铁建重工集团股份有限公司 Water jet gangue layer slitting device
CN116411964A (en) * 2023-05-26 2023-07-11 中国矿业大学 Hydraulic fracturing cutting cooperative device suitable for hard rock and use method
CN116411964B (en) * 2023-05-26 2024-01-02 中国矿业大学 Hydraulic fracturing cutting cooperative device suitable for hard rock and use method
US12188339B2 (en) 2023-05-26 2025-01-07 China University Of Mining And Technology Hydraulic fracturing and cutting cooperative device suitable for hard rock and use method thereof
CN117684592A (en) * 2024-02-02 2024-03-12 中国冶金地质总局第三地质勘查院 Method for treating serial layer polluted water well
CN117684592B (en) * 2024-02-02 2024-04-19 中国冶金地质总局第三地质勘查院 Method for treating serial layer polluted water well

Similar Documents

Publication Publication Date Title
CN103195468A (en) System process for conducting efficient strengthened extraction in surrounding rock
CN108643877B (en) Method for increasing permeability and extracting gas by staged fracturing of long borehole in underground coal seam
CN101575983B (en) Directional fracturing permeability improvement outburst elimination method in coal mine and device thereof.
CN112324337B (en) A whole-process gas drainage method for comb-shaped drilling along the top of the soft coal seam floor
CN108843241B (en) Cave pressure relief mining system for tectonic coal in-situ coal bed gas horizontal well
CN103104222B (en) Ground peupendicular hole combines extraction coal bed gas method with concordant long drilled holes
CN108798516B (en) Cave pressure relief mining method for tectonic coal in-situ coal bed gas horizontal well
CN111594258A (en) Technical method for quickly extracting gas to reach standard by using broken soft low-permeability outburst coal seam instead of roadway through holes
CN111535791B (en) Efficient gas extraction method for broken soft low-permeability coal seam well upper and lower combined fracturing area
CN101082283A (en) Gob-side entry retaining Y-shaped ventilation goaf roof pressure relief gas extraction method
CN104806217A (en) Combined separated layer fracturing, grouping and layer-combining mining method for coal bed well group
CN110671145A (en) Large-mining-width thick coal seam mining composite grouting method
CN109209472A (en) The coal seam pressure relief anti-burst method that a kind of punching, explosion, water filling intercouple
CN105804786B (en) A kind of weak seam bottom plate layer-through drilling pressure rushes anti-reflection method
CN104879159A (en) Gas permeability-increase extraction device and method for soft coal seam stoping face
CN108756884A (en) Coal mine tight roof full face ground shifts to an earlier date outburst elimination method
CN103643994A (en) Method for controlling water inrush and sand inrush under coal mine
CN106437823B (en) Method for eliminating outburst and standard exceeding of coal mine gas explosion
CN103470242A (en) Oilfield horizontal well volume fracturing method
CN102926774A (en) Bolting and grouting process for governing roadway floor heave
AU2021447461A1 (en) Extra-thick coal seam upper layer old goaf roof reconstruction method and construction method
CN103075181B (en) Bedding long drilling hole seam cutting and hole washing integral coal bed gas extraction method
CN117108258A (en) Accurate advanced gas treatment method for large area of underground thick coal seam of coal mine
CN117722179A (en) Water-retaining and anti-flushing coal mining method based on pressure relief fracture grouting to reconstruct anti-flushing water-resisting layer
CN111119978B (en) A method of drilling coal seam gas extraction by hydraulic slitting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130710