[go: up one dir, main page]

CN102954623B - Waterproof sealing sleeve construction process for ground source heat pump buried pipe penetrating large bottom plate of building - Google Patents

Waterproof sealing sleeve construction process for ground source heat pump buried pipe penetrating large bottom plate of building Download PDF

Info

Publication number
CN102954623B
CN102954623B CN201110247035.1A CN201110247035A CN102954623B CN 102954623 B CN102954623 B CN 102954623B CN 201110247035 A CN201110247035 A CN 201110247035A CN 102954623 B CN102954623 B CN 102954623B
Authority
CN
China
Prior art keywords
water
waterproof
loose joint
pipe
steel sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201110247035.1A
Other languages
Chinese (zh)
Other versions
CN102954623A (en
Inventor
陈雷
居学文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Dfun Air-Conditional Equipment & Engineering Technology Co Ltd
Original Assignee
Shanghai Dfun Air-Conditional Equipment & Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Dfun Air-Conditional Equipment & Engineering Technology Co Ltd filed Critical Shanghai Dfun Air-Conditional Equipment & Engineering Technology Co Ltd
Priority to CN201110247035.1A priority Critical patent/CN102954623B/en
Publication of CN102954623A publication Critical patent/CN102954623A/en
Application granted granted Critical
Publication of CN102954623B publication Critical patent/CN102954623B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pipe Accessories (AREA)
  • Non-Disconnectible Joints And Screw-Threaded Joints (AREA)

Abstract

A waterproof sealing sleeve construction process for a ground source heat pump buried pipe penetrating a large bottom plate of a building mainly includes utilizing a waterproof sleeve and relevant components. A water stop steel plate or a water stop wing ring outside a steel sleeve pipe is compactly welded on the steel sleeve and welded on a steel reinforcing bar of the large bottom plate. The water stop plate is casted by the concrete, and rising of underground water is effectively prevented, a rubber water stop ring in the steel sleeve is tensioned and limited by a movable joint without deformation, and water is guaranteed to be stopped from entering the water stop ring. A movable joint component is tightly connected with the steel sleeve in a screw manner to prevent possible water leakage, and ejection out and falling off of waterproof materials under pressure are avoided as well. Waterproof sludge is pulled in front of the water stop ring and a water-ward surface of the sleeve, so that the sleeve can be sealed more tightly under pressure of the underground water. Screw threads can be screwed off directly on a backwater side, a sealing ring can be replaced or the waterproof sludge for sealing can be replenished, so that the sleeve can be maintained easily. The waterproof sealing sleeve construction process guarantees the buried pipe to be capable of penetrating the large bottom plate, is capable of adapting to sedimentation of the building within a certain range, and drawn breakage of the buried HDPE (high-density polyethylene) pipe due to the sedimentation is avoided, and infiltration of the underground water can be effectively separated.

Description

Ground buried pipe of ground source heat pump is worn building base plate waterproof gland cover pipe construction technique
Technical field
This technology belongs to the underground pipe construction technology field of earth-source hot-pump system.
Energy-conservation and the renewable energy utilization system that earth-source hot-pump system is encouraged as country, in down town and building dense region can be difficult to carry out because implementing the building periphery lack of space of underground pipe, therefore, some engineering project can be considered can before large construction of bottom plates, complete at the concrete of building the construction of underground pipe before architecture construction, and hopefully pipe laying can both guarantee self not to be compromised overall structure performance and the water resistance that also guarantees the large base plate of building.
Background technology
Conventionally under large base plate during the pipe laying of construction ground, conventional construction method is after underground pipe is constructed in foundation ditch, packet combining is linked horizontal tube, and horizontal tube is drawn by the side under large base plate, under foundation ditch, go out retaining wall place common steel sleeve is set, and turn between retaining wall and gravity dam and be incorporated into equipment machine room, and at the equipment machine room jacket pipe of setting up defences.Such construction, is easy to the fracture of spot pipe laying when building settlement.And because underground pipe divides into groups, at this moment, if any one ground buried via hole causes because constructing leaking accidentally, whole group, so that pipe laying cannot be used more, even cause the failure of earth-source hot-pump system.
The steel sleeve that conventional method arranges, in fact in use cannot provide underground pipe to adapt to the naturally flexible of building settlement, the infiltration of the underground water that is also difficult to avoid pressure between underground pipe and sleeve pipe.
Owing to there is no rational arrangement and method for construction, be difficult to guarantee that underground pipe realized hermetic waterproof when passing through floors, and be also easy to cause underground pipe cannot digest building settlement in floor, thereby cause underground pipe to destroy.
And according to the construction technology of conventional water string, be difficult to guarantee the infiltration in sleeve pipe, be also difficult to guarantee underground pipe stretching in sleeve pipe.
Because common vertical tube is to be extensively distributed under large base plate, therefore most scientific rational method is to guarantee that the total length in the buried loop of each group is balanced as far as possible.But due to the water string that underground pipe is worn large base plate that is exclusively used in without suitable, therefore, in Practical Project construction, be difficult to implement the arrangement and method for construction that ground source heat pump imbedded pipe is worn large base plate on directly.
Just because of above reason, heating and ventilation project teacher and structural engineer oppose that the underground pipe of earth source heat pump is implemented under large base plate conventionally, and this has also caused finally cannot implementing earth-source hot-pump system.
Therefore in order to advance more effectively, more widely the enforcement of earth-source hot-pump system, it is a kind of more reasonable, simple in construction, can to invent, and can take into account and guarantee underground pipe free-extension and effectively prevent construction technology measure and the sleeve pipe of the Groundwater infiltration of pressure in sleeve pipe, be highly significant.
Summary of the invention
Ground buried pipe of ground source heat pump is worn the water string construction technology of the large base plate of building
This technique mainly consists of water string and associated component.
Normally the external diameter of pipe laying is that D32mm(can have multiple caliber) high density polyethylene (HDPE) plastic conduit (HDPE), need the large base plate of passing through building.The object of the construction technology of our invention is: guarantee that underground pipe can pass through large base plate, and can adapt to the sedimentation of the building of certain limit, therefore sedimentation does not cause buried HDPE pipe to be pulled off; Effectively cut off the infiltration of basement.
Take D32mmHDPE pipe as example, we select the steel pipe of DN40, and comprise by formations such as articulation, watertight rubber sealing rings, and Socket welding are connected on to steel plate for sealing water (or on water-proof wing-ring) in construction.
Accompanying drawing explanation
Accompanying drawing is that ground buried pipe of ground source heat pump is worn building base plate water string assembly cutaway view
Main contents comprise:
1, be welded on the steel sleeve on steel plate for sealing water (or water-proof wing-ring);
2, steel sleeve has outer silk in the non-side that meets water;
3, the outer silk of steel sleeve connects firmly with the loose joint pipe fitting (loose joint pipe fitting A) of the inside and outside silk of a band, the internal thread of this pipe fitting
Closely be connected by screw thread with the outer silk of steel sleeve, inside twine the thick white paint of raw material band or flax silk;
4, the outer silk part of the loose joint pipe fitting A of inside and outside silk is closely connected by screw thread with the loose joint joint (parts C) with internal thread; And another part of this group loose joint assembly (loose joint pipe box B) is with reverse projection, be together closely connected in loose joint joint C with loose joint pipe fitting A;
5, in the middle of pipe fitting A and pipe fitting B, special-purpose rubber O-ring seal is set, this seal ring is the rubber O-ring seal of lining steel plate, and its internal diameter is slightly less than the external diameter of underground pipe, and external diameter is slightly larger than the internal diameter (underground pipe of relative D32 of loose joint joint C, the internal diameter of this seal ring is 30mm, and external diameter is 55mm;
6, in the gap of this seal ring and pipe fitting A, smear waterproof oil sludge or marine glue;
7, underground pipe passes said modules, and clogs waterproof oil sludge at the upstream face of steel sleeve;
According to above sleeve pipe, form, can prevent all sidedly the overflow of underground water, major function is:
1, the steel plate for sealing water outside steel sleeve or water-proof wing-ring are closely welded on steel sleeve, and are welded on the reinforcing bar of large base plate.This seal plate is by concreting, effectively stoped underground water on invade;
2, the rubber O-ring seal in steel sleeve, by pipe fitting B and pipe fitting A by loose joint joint C tension, spacing and modification has nowhere guaranteed that water can not pass through seal ring;
3, loose joint assembly is to connect by silk with steel sleeve and close-connected, can not seep water thus, has also avoided waterproof material under pressure to be ejected, to come off;
4, before seal ring and sleeve pipe upstream face filling waterproof oil sludge, make to be subject to after groundwater pressure, seal tightr;
5, this sleeve pipe can be directly at outward winding screw thread change sealing ring or supplementary water-tight greasy filth of back side, can guarantee that sleeve pipe can keep in repair easily.

Claims (2)

1. ground buried pipe of ground source heat pump is worn a building base plate waterproof sealing casing construction method, it is characterized in that, comprises step: 1.1, underground pipe, and underground pipe is HDPE pipe, PPR pipe or PB tubing, underground pipe is through the steel sleeve that is welded with steel plate for sealing water or water-proof wing-ring; 1.2, steel sleeve has outer silk at non-upstream face; The outer silk of steel sleeve connects with the loose joint pipe fitting A of the inside and outside silk of a band, and the internal thread of loose joint pipe fitting A is closely connected by screw thread with the outer silk of steel sleeve, inside twines the thick white paint of raw material band or flax silk; 1.3, the outer silk part of the loose joint pipe fitting A of inside and outside silk is closely connected by screw thread with the loose joint joint C with internal thread; Loose joint pipe fitting B is with reverse projection, is together closely connected in loose joint joint C with loose joint pipe fitting A, forms one group of loose joint assembly; 1.4, in the middle of loose joint pipe fitting A and loose joint pipe fitting B, rubber O-ring seal is set, the rubber O-ring seal that described rubber O-ring seal is lining steel plate, its internal diameter is slightly less than the external diameter of underground pipe, and external diameter is slightly larger than the internal diameter of loose joint joint C; 1.5, in the gap of described rubber O-ring seal and described loose joint pipe fitting A, smear waterproof oil sludge or marine glue; And clog waterproof oil sludge at the upstream face of steel sleeve; The anti-water surface of described steel sleeve is not at upstream face, but at back side; The aerial part of described steel sleeve has screw thread, effectively fixedly loose joint assembly; What be used for waterproof is one group of loose joint assembly of clamping down on mutually, and can directly keep in repair; Described rubber O-ring seal is fixedly secured by loose joint assembly, and existing self rigidity of the rubber O-ring seal of this lining steel plate, has again the sealing of rubber; The waterproof material of filling can be tightr when being subject to groundwater pressure; Described steel sleeve is to allow internal pipeline longitudinal stretching in certain distance, prevents pipeline break; Steel plate for sealing water outside described steel sleeve or water-proof wing-ring are closely welded on steel sleeve, and be welded on ground buried pipe of ground source heat pump wear building base plate reinforcing bar on.
2. ground buried pipe of ground source heat pump according to claim 1 is worn building base plate waterproof sealing casing construction method, it is characterized in that described steel plate for sealing water is by concreting, effectively stoped underground water on invade; Rubber O-ring seal in steel sleeve, by loose joint pipe fitting B and loose joint pipe fitting A by loose joint joint C tension, spacing and distortion has nowhere guaranteed that water can not pass through rubber O-ring seal; Loose joint assembly is to connect by silk with steel sleeve and close-connected, can not seep water thus, has also avoided waterproof material under pressure to be ejected, to come off; Described steel sleeve is not only applicable to the construction method of water string of wearing building base plate of underground pipe, is applicable to too the waterproof of the basement wall poling that waterproof requirement is higher, the waterproof of side wall poling and pass through water pipeline, the light current pipeline of pond, roofing, the waterproof construction method of forceful electric power cable; Selection for pipeline steel pipe, copper pipe or cable in described steel sleeve.
CN201110247035.1A 2011-08-26 2011-08-26 Waterproof sealing sleeve construction process for ground source heat pump buried pipe penetrating large bottom plate of building Expired - Fee Related CN102954623B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110247035.1A CN102954623B (en) 2011-08-26 2011-08-26 Waterproof sealing sleeve construction process for ground source heat pump buried pipe penetrating large bottom plate of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110247035.1A CN102954623B (en) 2011-08-26 2011-08-26 Waterproof sealing sleeve construction process for ground source heat pump buried pipe penetrating large bottom plate of building

Publications (2)

Publication Number Publication Date
CN102954623A CN102954623A (en) 2013-03-06
CN102954623B true CN102954623B (en) 2014-12-10

Family

ID=47763764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110247035.1A Expired - Fee Related CN102954623B (en) 2011-08-26 2011-08-26 Waterproof sealing sleeve construction process for ground source heat pump buried pipe penetrating large bottom plate of building

Country Status (1)

Country Link
CN (1) CN102954623B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103162021B (en) * 2013-04-07 2015-03-18 中建城市建设发展有限公司 Underground structure outer wall feed-through sleeve waterproof device and construction method thereof
CN103742729A (en) * 2013-12-26 2014-04-23 李�浩 Method for arranging wall passing pipes of valve well in ground source heat pump system
CN103836268A (en) * 2014-02-28 2014-06-04 中天建设集团有限公司 Construction method for mounting waterproof sleeve of external concrete wall of basement
CN104154328B (en) * 2014-07-30 2016-04-06 天津市热电设计院有限公司 A kind of Direct-Buried Heating Pipeline anchor block hole cage stiffening rib
CN106703136B (en) * 2017-01-24 2018-12-14 河海大学 A kind of impervious constructional device of toilet floor pre-embedded downcomer
CN108505545B (en) * 2017-02-28 2020-05-08 河南省建筑设计研究院有限公司 Waterproof method for building foundation raft penetrating through underground pipe group
CN108306232A (en) * 2017-12-20 2018-07-20 国网山东省电力公司聊城供电公司 A kind of mechanical fasteners formula cable waterproof clutch and its application method
CN109235491A (en) * 2018-08-13 2019-01-18 中冶天工集团有限公司 A kind of extrusion type sealed device and its installation method for pipe gallery penetration pipe
CN109027506B (en) * 2018-09-10 2020-02-07 张家港爱力星材料有限公司 Pipeline construction method without hot-melting direct-insertion connection
CN109440815A (en) * 2018-11-16 2019-03-08 上海朗绿建筑科技股份有限公司 A kind of underground pipe method for arranging and structure
CN110145646A (en) * 2019-04-24 2019-08-20 北京市亚太安设备安装有限责任公司 A kind of mounting structure of fire-fighting water pipeline
CN110966464B (en) * 2019-10-31 2021-11-12 吉林省热力工程设计研究有限责任公司 Special composite sleeve device for heating power
CN113638433B (en) * 2021-06-29 2023-03-14 中铁电气化局集团北京建筑工程有限公司 Construction method for foundation raft penetrating through ground source side circulating pipe of ground source heat pump system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09273667A (en) * 1996-04-04 1997-10-21 Nkk Corp Wall piercing structure of buried pipe
GB2408782A (en) * 2003-11-25 2005-06-08 Petrotechnik Ltd Connection between a pipe and a wall
CN1628225A (en) * 2002-07-26 2005-06-15 安东-胡梅尔管理有限公司 Threaded sleeve, matching sleeveand clamping screw joint of clamping insertion
JP2006226359A (en) * 2005-02-16 2006-08-31 Hayakawa Rubber Co Ltd Water shut off device for pipe penetration part of wall, water shut off structure and water shut off method
CN2888220Y (en) * 2006-03-02 2007-04-11 朱建华 Waterproof sealed casing device
CN201731178U (en) * 2010-07-02 2011-02-02 松原市明悟节能设备有限公司 Rigid waterproof sleeve

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09273667A (en) * 1996-04-04 1997-10-21 Nkk Corp Wall piercing structure of buried pipe
CN1628225A (en) * 2002-07-26 2005-06-15 安东-胡梅尔管理有限公司 Threaded sleeve, matching sleeveand clamping screw joint of clamping insertion
GB2408782A (en) * 2003-11-25 2005-06-08 Petrotechnik Ltd Connection between a pipe and a wall
JP2006226359A (en) * 2005-02-16 2006-08-31 Hayakawa Rubber Co Ltd Water shut off device for pipe penetration part of wall, water shut off structure and water shut off method
CN2888220Y (en) * 2006-03-02 2007-04-11 朱建华 Waterproof sealed casing device
CN201731178U (en) * 2010-07-02 2011-02-02 松原市明悟节能设备有限公司 Rigid waterproof sleeve

Also Published As

Publication number Publication date
CN102954623A (en) 2013-03-06

Similar Documents

Publication Publication Date Title
CN102954623B (en) Waterproof sealing sleeve construction process for ground source heat pump buried pipe penetrating large bottom plate of building
CN106149764B (en) A kind of precast assembly pipe gallery bell and spigot waterproof construction
CN204477493U (en) A kind of waterproof jacking pipe joints bellmouth jointing structure
CN202580323U (en) Two-side flexible waterproof sleeve pipe
CN201731178U (en) Rigid waterproof sleeve
CN102619227B (en) Grouting device, assembly and grouting method for single pipe pile foundation of offshore wind turbine generating set
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN202227357U (en) Water-reducing tube well structure
CN203514481U (en) Inspection well
CN210106788U (en) Pipe jacking structure of circular open caisson
CN111585229A (en) Flexible waterproof sealing structure for wall penetration of underground direct-buried cable or optical cable and construction method
CN105697886B (en) The plugging structure of pre-buried cable tube in a kind of concrete walls body
CN214280883U (en) Elastomer high-voltage cable plugging device
CN110808564B (en) Concrete cable trench construction process
CN105019941B (en) Composite, water-drain blind pipe can be safeguarded
CN217579825U (en) Prefabricated pin-connected panel rainwater box culvert suitable for integrative machine of strutting
CN204267894U (en) The plugging structure of pre-buried cable trunk in a kind of concrete wall
CN202580324U (en) Waterproof structure of upstream face of flexible through-wall pipe
CN214412221U (en) Prefabricated waterproof fixed joint for cable working well
CN212453000U (en) Water stop structure for connecting drainage pipeline and inspection well
CN203834522U (en) Waterproof structure for concrete box culvert deformation joint
CN203668912U (en) Structure for embedding drain pipe in concrete
CN218437182U (en) Municipal administration utility tunnel
CN112066102A (en) Hydraulic engineering pipe connection sealing device
RU2423579C1 (en) Method to create watertight coupling of pipeline with barrier concrete or reinforced concrete wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141210

Termination date: 20150826

EXPY Termination of patent right or utility model