[go: up one dir, main page]

CN102797480A - Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall - Google Patents

Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall Download PDF

Info

Publication number
CN102797480A
CN102797480A CN2012103070011A CN201210307001A CN102797480A CN 102797480 A CN102797480 A CN 102797480A CN 2012103070011 A CN2012103070011 A CN 2012103070011A CN 201210307001 A CN201210307001 A CN 201210307001A CN 102797480 A CN102797480 A CN 102797480A
Authority
CN
China
Prior art keywords
floor
stress
grid
groove
roadway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103070011A
Other languages
Chinese (zh)
Inventor
靖洪文
杨旭旭
陈坤福
杨圣奇
孟波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN2012103070011A priority Critical patent/CN102797480A/en
Publication of CN102797480A publication Critical patent/CN102797480A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

一种非连续承压格栅砼墙控制高应力软岩巷道底鼓变形方法,在轨道两侧底板处间断开挖倾斜向下的沟槽并浇注非连续承压格栅砼墙,然后在沟槽中浇注钢筋格栅混凝土形成可承受高强压应力及刚度较大的墙体结构,一方面置换了部分软岩的钢筋格栅混凝土与底板软弱岩体胶结在一起,提高了巷道底板的整体性和刚度;另一方面,巷道两侧底角处向内的挤压应力与底板中向上的压应力将较为均匀地作用在格栅砼墙上,使应力的作用效果相互抵消,减少底板围岩的变形量,同时墙体结构还可以抵抗底板岩体中的剪切应力,防止产生剪切滑移破坏。格栅砼墙的非连续布置,可在满足控制效果的前提下,有效减少施工量,施工方法简单快捷。

Figure 201210307001

A method for discontinuous pressure-bearing grid concrete walls to control the deformation of floor drums in high-stress soft rock roadways, cutting and excavating inclined downward grooves at the bottom plates on both sides of the track and pouring discontinuous pressure-bearing grid concrete walls, and then pouring the discontinuous pressure-bearing grid concrete walls, and then The reinforced grid concrete is poured into the groove to form a wall structure that can withstand high compressive stress and high rigidity. On the one hand, the reinforced grid concrete that replaces part of the soft rock is cemented together with the weak rock mass of the floor, improving the integrity of the roadway floor and stiffness; on the other hand, the inward extrusion stress at the bottom corners on both sides of the roadway and the upward compressive stress in the floor will act on the grid concrete wall more evenly, so that the effects of the stress will cancel each other out and reduce the surrounding rock of the floor. At the same time, the wall structure can also resist the shear stress in the floor rock mass and prevent shear slip damage. The discontinuous arrangement of the grid concrete wall can effectively reduce the construction amount under the premise of satisfying the control effect, and the construction method is simple and fast.

Figure 201210307001

Description

非连续承压格栅砼墙控制高应力软岩巷道底鼓变形方法Method for controlling floor heave deformation of high-stress soft rock roadway with discontinuous pressure-bearing grid concrete wall

方法领域method field

本发明涉及控制高应力软岩巷道底鼓变形方法,尤其是一种适用于控制和治理煤矿巷道底板的利用非连续承压格栅砼墙控制高应力软岩巷道底鼓变形方法。 The invention relates to a method for controlling the deformation of the floor heave of a high-stress soft rock roadway, in particular to a method for controlling the deformation of the floor heave of a high-stress soft rock roadway by using a discontinuous pressure-bearing grid concrete wall, which is suitable for controlling and treating the bottom plate of a coal mine roadway.

背景方法background method

巷道底鼓变形破坏是煤矿巷道普遍存在的破坏形式,在深部高应力软岩巷道中尤为突出,而且由于底板是巷道的基础,剧烈的底鼓变形会引起整个巷道的失稳,影响巷道的正常使用,增加维修投入,甚至会造成安全事故。关于巷道底鼓的防治方法,总体上可概括为加固和卸压两大类。加固方法中包括带底拱的U型钢可缩性支架、混凝土砌碹和弧板等全断面支护法以及底板锚杆、底板注浆和锚注结合等;卸压方法有巷道周边卸压法,如帮底开卸压槽和底板深部松动爆破等。这些方法在不同程度上减少了不同条件下的底鼓变形量。但是,当巷道处于高应力状态,巷道围岩较为软弱、破碎的条件下,底板岩体极易发生流变变形或剪切滑移变形,上述方法尚不能有效控制这种巷道的底鼓变形破坏,而且施工过程会妨碍巷道的正常使用,影响整个工程的工期。 Roadway floor heave deformation failure is a common failure mode in coal mine roadways, especially in deep high-stress soft rock roadways, and because the floor is the foundation of the roadway, severe floor heave deformation will cause the instability of the entire roadway and affect the normal operation of the roadway Use, increase maintenance investment, and even cause safety accidents. The prevention and control methods of roadway bottom heave can be generally summarized into two categories: reinforcement and pressure relief. Reinforcement methods include U-shaped steel retractable brackets with bottom arches, concrete masonry and arc plates and other full-section support methods, as well as bottom plate anchors, bottom plate grouting and anchor injection, etc.; pressure relief methods include pressure relief methods around the roadway, Such as opening and unloading pressure grooves on the bottom and loosening blasting in the deep part of the bottom plate. These methods reduce the amount of kick drum deformation under different conditions to varying degrees. However, when the roadway is in a state of high stress and the surrounding rock of the roadway is relatively weak and broken, the floor rock mass is prone to rheological deformation or shear slip deformation. The above methods cannot effectively control the floor heave deformation and damage of this roadway , and the construction process will hinder the normal use of the roadway and affect the construction period of the entire project.

发明内容 Contents of the invention

技术问题:本发明的目的是克服现有技术的不足之处,提供一种施工简单、对巷道正常运行的影响较小、控制效果好的非连续承压格栅砼墙控制高应力软岩巷道底鼓变形方法。 Technical problem: The purpose of this invention is to overcome the deficiencies of the prior art and provide a non-continuous pressure-bearing grid concrete wall to control high-stress soft rock roadway with simple construction, less impact on the normal operation of the roadway, and good control effect Kick drum deformation method.

技术方案:本发明的非连续承压格栅砼墙控制高应力软岩巷道底鼓变形方法: Technical solution: The method for controlling the deformation of the bottom drum of the high-stress soft rock roadway by the non-continuous pressure-bearing grid concrete wall of the present invention:

a、在巷道中轨道两侧底板处,间断开挖向巷道帮部倾斜10°~30°的沟槽,每段沟槽长度为3m~5m,深度为1m~2.5m,宽度为0.5m,间距为1m~2m; a. At the bottom plates on both sides of the track in the roadway, excavate grooves inclined 10°~30° toward the side of the roadway intermittently. The length of each groove is 3m~5m, the depth is 1m~2.5m, and the width is 0.5m. The spacing is 1m~2m;

b、沟槽开挖完成后,将预制的钢筋格栅放置在沟槽中,浇注混凝土,并振捣密实,由沟槽、混泥土与钢筋格栅共同构成非连续承压格栅砼墙; b. After the excavation of the trench is completed, place the prefabricated steel bar grid in the trench, pour concrete, and vibrate compactly, and the discontinuous pressure-bearing grid concrete wall is composed of the trench, concrete and steel bar grid;

c、根据需要进行底板处理巷道的长度,重复步骤a至b,依次或多点同时施工直至非连续承压格栅砼墙施工完毕。 c. According to the length of the bottom plate treatment roadway as required, repeat steps a to b, and construct sequentially or at multiple points at the same time until the construction of the non-continuous pressure-bearing grid concrete wall is completed.

所述的钢筋格栅是由主筋、箍筋和连接筋十字交叉通过焊接制作而成,主筋、箍筋和连接筋的端头弯曲搭接,搭接长度不少于0.1m且联接处为满焊;主筋规格为HRB335,直径为0.022m,间排距为0.22m;箍筋和连接筋的规格为HPB235,直径为0.022m,间距为0.22m;每片钢筋格栅的宽度与沟槽的深度相同,每片钢筋格栅的长度与沟槽的长度相同; The steel bar grid is made by welding the main bars, stirrups and connecting bars in a cross, the ends of the main bars, stirrups and connecting bars are bent and overlapped, the lap length is not less than 0.1m and the connection is full welding; the specification of the main reinforcement is HRB335, the diameter is 0.022m, and the row spacing is 0.22m; The depth is the same, and the length of each steel bar grid is the same as the length of the groove;

有益效果:由于采用了上述技术方案,利用非连续承压格栅砼墙控制高应力软岩巷道底鼓的变形,不但可以有效减少高应力软岩巷道的底鼓变形量,维持巷道底板的稳定,而且施工简单方便、对巷道正常使用影响较小。通过对非连续承压格栅砼墙的利用,沟槽的开挖可以对巷道底角处的高应力进行卸除,并使高应力向深部围岩转移,降低巷道围岩压力;浇注的高强度和大刚度的承压墙置换了部分软弱岩体,提高了巷道底板的整体性和刚度,并使巷道两侧底角处向内的挤压应力与底板中向上的压应力较为均匀地作用在承压墙上,使作用效果相互抵消,减少底板围岩的变形量,同时格栅承压墙还可以抵抗底板岩体中的剪切应力,防止产生剪切滑移破坏。格栅砼墙的非连续布置,可在满足控制效果的前提下,有效减少施工量,并可多点同时施工加快施工进度,也使该方法的应用根据现场实际情况的复杂程度具有可调控性。 Beneficial effects: due to the adoption of the above technical scheme, the use of discontinuous pressure-bearing grid concrete walls to control the deformation of the floor drum of high-stress soft rock roadways can not only effectively reduce the deformation of the floor drum of high-stress soft rock roadways, but also maintain the stability of the roadway floor , and the construction is simple and convenient, and has little impact on the normal use of the roadway. By using the discontinuous pressure-bearing grid concrete wall, the excavation of the trench can remove the high stress at the bottom corner of the roadway, and transfer the high stress to the deep surrounding rock, reducing the pressure of the surrounding rock of the roadway; The high-strength and high-rigidity bearing walls replace part of the weak rock mass, improve the integrity and rigidity of the roadway floor, and make the inward compressive stress at the bottom corners on both sides of the roadway and the upward compressive stress in the bottom plate act more evenly On the bearing wall, the effects of each other are offset to reduce the deformation of the surrounding rock of the floor. At the same time, the grid bearing wall can also resist the shear stress in the rock mass of the floor and prevent shear slip damage. The non-continuous layout of the grid concrete wall can effectively reduce the construction amount under the premise of satisfying the control effect, and can speed up the construction progress at multiple points at the same time, and also makes the application of this method adjustable according to the complexity of the actual situation on site .

附图说明 Description of drawings

图1是本发明的结构布置示意图。 Fig. 1 is a schematic diagram of the structural arrangement of the present invention.

图2是图1的俯视图。 FIG. 2 is a top view of FIG. 1 .

图3是格栅钢筋布置图。 Figure 3 is a layout diagram of the grid reinforcement.

图中:1-巷道,2-轨道,3-巷道帮部,4-沟槽,5-混凝土,6-主筋,7-箍筋,8-连接筋。 In the figure: 1-roadway, 2-track, 3-side of roadway, 4-groove, 5-concrete, 6-main reinforcement, 7-stirrup, 8-connecting reinforcement.

具体实施方式 Detailed ways

下面结合附图对本发明的一个实施例作进一步的描述: An embodiment of the present invention will be further described below in conjunction with accompanying drawing:

本发明利用非连续承压格栅砼墙控制高应力软岩巷道底鼓变形的方法,针对高应力、软弱围岩巷道底板易发生底鼓变形破坏、底板处理施工困难的问题,在轨道两侧底板处间断开挖倾斜向下的沟槽并浇注非连续承压格栅砼墙。沟槽的开挖可卸除巷道底角处的部分应力,并使高应力向岩体深部转移,降低巷道围岩压力。然后在沟槽中浇注钢筋格栅混凝土形成可承受高强压应力及刚度较大的墙体结构,一方面置换了部分软岩的钢筋格栅混凝土与底板软弱岩体胶结在一起,提高了巷道底板的整体性和刚度;另一方面,巷道两侧底角处向内的挤压应力与底板中向上的压应力将较为均匀地作用在格栅砼墙上,使应力的作用效果相互抵消,减少底板围岩的变形量,同时墙体结构还可以抵抗底板岩体中的剪切应力,防止产生剪切滑移破坏。格栅砼墙的非连续布置,可在满足控制效果的前提下,有效减少施工量,并可多点同时施工加快施工进度,可根据现场实际情况的复杂程度具体调控。具体步骤如下: The method of the present invention utilizes the discontinuous pressure-bearing grid concrete wall to control the deformation of the bottom heave of the high-stress soft rock roadway, aiming at the problems that the floor of the roadway with high stress and weak surrounding rocks is prone to deformation and damage of the bottom heave, and the bottom plate is difficult to handle and construct. The bottom plate is intermittently excavated with inclined downward grooves and poured the discontinuous pressure-bearing grid concrete wall. The excavation of the trench can relieve part of the stress at the bottom corner of the roadway, and transfer the high stress to the deep part of the rock mass, reducing the surrounding rock pressure of the roadway. Then pour reinforced grid concrete in the groove to form a wall structure that can withstand high compressive stress and high rigidity. On the one hand, the reinforced grid concrete that replaces part of the soft rock is cemented with the weak rock mass of the floor, improving the floor of the roadway. On the other hand, the inward extrusion stress at the bottom corners on both sides of the roadway and the upward compressive stress in the bottom plate will act on the grid concrete wall more evenly, so that the effect of the stress will cancel each other out and reduce the stress. The deformation of the surrounding rock of the floor, and the wall structure can also resist the shear stress in the rock mass of the floor to prevent shear slip damage. The non-continuous layout of the grid concrete wall can effectively reduce the construction amount under the premise of satisfying the control effect, and can speed up the construction progress at the same time at multiple points, and can be adjusted according to the complexity of the actual situation on site. Specific steps are as follows:

a、首先在在巷道1中轨道2两侧底板处,间断开挖向巷道帮部3倾斜10°~30°的沟槽4,每段沟槽4长度为3m~5m,深度为1m~2.5m,宽度为0.5m,间距为1m~2m; a. First, at the floor on both sides of the track 2 in the roadway 1, intermittently excavate the groove 4 inclined 10°~30° toward the roadway side 3. The length of each groove 4 is 3m~5m, and the depth is 1m~2.5 m, the width is 0.5m, and the spacing is 1m~2m;

b、沟槽4开挖完成后,将预制的钢筋格栅放置在沟槽4中,进而浇注混凝土5,并振捣密实,由沟槽4、混泥土5与钢筋格栅共同构成非连续承压格栅砼墙;所述的钢筋格栅是由主筋6、箍筋7和连接筋8十字交叉通过焊接制作而成,主筋6、箍筋7和连接筋8的端头弯曲搭接,搭接长度不少于0.1m且联接处为满焊;主筋6规格为HRB335,直径为0.022m,间排距为0.22m;箍筋7和连接筋8的规格为HPB235,直径为0.022m,间距为0.22m;每片钢筋格栅的宽度与沟槽(4)的深度相同,每片钢筋格栅的长度与沟槽4的长度相同; b. After the excavation of the trench 4 is completed, the prefabricated steel grid is placed in the trench 4, and then the concrete 5 is poured and compacted by vibrating. The groove 4, the concrete 5 and the steel grid together form a discontinuous bearing Pressed grid concrete wall; the steel bar grid is made by welding the main bars 6, stirrups 7 and connecting bars 8, and the ends of the main bars 6, stirrups 7 and connecting bars 8 are bent and overlapped. The connection length is not less than 0.1m and the joint is fully welded; the specification of the main reinforcement 6 is HRB335, the diameter is 0.022m, and the spacing between rows is 0.22m; the specification of the stirrup 7 and connecting reinforcement 8 is HPB235, the diameter is 0.022m, and the spacing is 0.22m; the width of each steel bar grid is the same as the depth of the groove (4), and the length of each steel bar grid is the same as the length of the groove 4;

c、根据需要进行底板处理巷道的长度,重复上述步骤a至b,依次或多点同时施工直至非连续承压格栅砼墙施工完毕。 c. According to the length of the bottom plate treatment roadway as required, repeat the above steps a to b, and construct sequentially or at multiple points at the same time until the construction of the non-continuous pressure-bearing grid concrete wall is completed.

Claims (2)

1. a discontinuous pressure-bearing grid concrete wall is controlled high stressed soft rock tunnel pucking deformation method, it is characterized in that:
A, in the tunnel base plate place, (1) middle orbit (2) both sides, be interrupted excavation to tilt 10 ° ~ 30 ° groove (4) of tunnel portion of group (3), every section groove (4) length is 3m ~ 5m, the degree of depth is 1m ~ 2.5m, width is 0.5m, spacing is 1m ~ 2m;
After b, groove (4) excavation are accomplished, prefabricated reinforcing bar grid is placed in the groove (4), fluid concrete (5), and vibration compacting constitute discontinuous pressure-bearing grid concrete wall by groove (4), mixed earth (5) with reinforcing bar grid jointly;
C, carry out the length that base plate is handled the tunnel as required, repeating step a to b, successively or multiple spot construct simultaneously and finish until discontinuous pressure-bearing grid concrete wall construction.
2. discontinuous pressure-bearing grid concrete wall control high stressed soft rock according to claim 1 tunnel pucking deformation method; It is characterized in that: described reinforcing bar grid is to be formed through welding production by main muscle (6), stirrup (7) and dowel (8) right-angled intersection; The tip bend overlap joint of main muscle (6), stirrup (7) and dowel (8), lap length is no less than 0.1m and the connection place is a full weld; Main muscle (6) specification is HRB335, and diameter is 0.022m, and an array pitch is 0.22m; The specification of stirrup (7) and dowel (8) is HPB235, and diameter is 0.022m, and spacing is 0.22m; The width of every reinforcing bar grid is identical with the degree of depth of groove (4), and the length of every reinforcing bar grid is identical with the length of groove (4).
CN2012103070011A 2012-08-27 2012-08-27 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall Pending CN102797480A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103070011A CN102797480A (en) 2012-08-27 2012-08-27 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103070011A CN102797480A (en) 2012-08-27 2012-08-27 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall

Publications (1)

Publication Number Publication Date
CN102797480A true CN102797480A (en) 2012-11-28

Family

ID=47196758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103070011A Pending CN102797480A (en) 2012-08-27 2012-08-27 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall

Country Status (1)

Country Link
CN (1) CN102797480A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266899A (en) * 2013-05-31 2013-08-28 山东科技大学 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall
CN103291327A (en) * 2013-05-07 2013-09-11 中国矿业大学 Steel pile method for controlling floor heave of gob-side entry retaining
CN103628898A (en) * 2013-11-15 2014-03-12 山东科技大学 Continuous wall supporting method for preventing floor heaving of roadway
CN103982196A (en) * 2014-05-16 2014-08-13 中国矿业大学(北京) Anchoring and shotcreting roadway two-side concrete spray layer shear failure prevention and control method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4699547A (en) * 1985-03-15 1987-10-13 Seegmiller Ben L Mine truss structures and method
DE3820700A1 (en) * 1988-06-18 1989-12-21 Ruhrkohle Ag Compound anchor support system
CN101509383A (en) * 2009-03-24 2009-08-19 徐州工程学院 Tunnel footing anchor pouring reinforcement anti bottom expanding method and construction technique
CN101915108A (en) * 2010-06-22 2010-12-15 中国矿业大学 A method of controlling the floor drum of the dynamic pressure roadway
CN101886545B (en) * 2010-07-05 2011-11-30 北京科技大学 Method for treating bottom heave of soft rock roadway by using micro broken stone pipe cast pile
CN102444407A (en) * 2011-12-12 2012-05-09 中铁二局股份有限公司 Method for controlling deformation of construction of lower step of high-ground-stress weak surrounding rock tunnel
CN101839140B (en) * 2010-03-31 2012-05-23 中国矿业大学 Method for reinforcing roadway floor by grouting

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4699547A (en) * 1985-03-15 1987-10-13 Seegmiller Ben L Mine truss structures and method
DE3820700A1 (en) * 1988-06-18 1989-12-21 Ruhrkohle Ag Compound anchor support system
CN101509383A (en) * 2009-03-24 2009-08-19 徐州工程学院 Tunnel footing anchor pouring reinforcement anti bottom expanding method and construction technique
CN101839140B (en) * 2010-03-31 2012-05-23 中国矿业大学 Method for reinforcing roadway floor by grouting
CN101915108A (en) * 2010-06-22 2010-12-15 中国矿业大学 A method of controlling the floor drum of the dynamic pressure roadway
CN101886545B (en) * 2010-07-05 2011-11-30 北京科技大学 Method for treating bottom heave of soft rock roadway by using micro broken stone pipe cast pile
CN102444407A (en) * 2011-12-12 2012-05-09 中铁二局股份有限公司 Method for controlling deformation of construction of lower step of high-ground-stress weak surrounding rock tunnel

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291327A (en) * 2013-05-07 2013-09-11 中国矿业大学 Steel pile method for controlling floor heave of gob-side entry retaining
CN103291327B (en) * 2013-05-07 2019-05-03 中国矿业大学 A steel pile method for controlling the bottom drum of gob-side entry retaining
CN103266899A (en) * 2013-05-31 2013-08-28 山东科技大学 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall
CN103628898A (en) * 2013-11-15 2014-03-12 山东科技大学 Continuous wall supporting method for preventing floor heaving of roadway
CN103628898B (en) * 2013-11-15 2016-01-20 山东科技大学 A kind of for preventing the diaphragm wall supporting method of Floor Heave in Roadway
CN103982196A (en) * 2014-05-16 2014-08-13 中国矿业大学(北京) Anchoring and shotcreting roadway two-side concrete spray layer shear failure prevention and control method
CN103982196B (en) * 2014-05-16 2016-01-20 中国矿业大学(北京) Bolting and shotcrete roadway two helps concrete spray coating shear failure prevention and controls

Similar Documents

Publication Publication Date Title
CN101852083B (en) Quick supporting method for large-deformation roadway easy to fall, break and loosen and apparatus thereof
CN104863614B (en) Method for primary support with corrugated steel plate and concrete combined structure taking place of steel grating
CN102587922B (en) A construction method for arc-guided roof lifting in oblique inclined shafts in soft and broken rock formations
CN106638673B (en) A kind of construction method of compound retaining structure
CN104389628B (en) Landslide location tunnel reinforcement device and reinforced construction method
CN108915700A (en) A kind of association type Floor Heave in Roadway administering method
CN108412519A (en) The slight large deformation single-track tunnel suspension device of highlands soft rock and construction method
CN102852528A (en) Method for controlling floor heave through inverted arch anchoring beam
CN103982197B (en) A kind of deep tunnel discontinuous bivalve reinforcement means
CN208267862U (en) A kind of bracing means at tunnel road surface crack
CN106121675A (en) Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch
CN102797478A (en) Method for preventing bottom squeeze of soft rock roadway by using distributed shear-resistant slip-resistant reinforced concrete pile
CN105421810A (en) Prefabricated panel reinforced masonry structure and construction method thereof
CN111335915A (en) Section steel supporting structure and method for repairing damage of tunnel inverted arch crown
CN102797480A (en) Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall
CN109236322B (en) A kind of artificial floor for preventing soft rock roadway floor bulge and its construction and maintenance method
CN106014443A (en) Method for preventing roadway floor heaving and wall sliding of gob-side entry retaining
CN110273436A (en) Open trench tunnel utilizes support pile and bear down on one float Structure and its construction method of crown beam
CN102425155A (en) Method for reinforcing shallow layer of overlying rock mass in goaf
CN107191001A (en) Tear down and build the strengthening of foundation construction method of house foundation
CN106049563B (en) Earthquake is damaged pier footing reinforcing system
CN103266899A (en) Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall
CN113803092B (en) Supporting device and method for broken soft rock roadway based on steel pipe concrete support
CN106121645A (en) The method that coal column group is left in a kind of step structure residual exploiting field of filling second mining
CN103291328A (en) Swelling rock roadway bottom plate treatment method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20121128