[go: up one dir, main page]

CN101915108A - A method of controlling the floor drum of the dynamic pressure roadway - Google Patents

A method of controlling the floor drum of the dynamic pressure roadway Download PDF

Info

Publication number
CN101915108A
CN101915108A CN 201010217011 CN201010217011A CN101915108A CN 101915108 A CN101915108 A CN 101915108A CN 201010217011 CN201010217011 CN 201010217011 CN 201010217011 A CN201010217011 A CN 201010217011A CN 101915108 A CN101915108 A CN 101915108A
Authority
CN
China
Prior art keywords
floor
roadway
dynamic pressure
hydraulic expansion
pressure water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010217011
Other languages
Chinese (zh)
Inventor
柏建彪
王襄禹
李文峰
侯朝炯
张科学
闫帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN 201010217011 priority Critical patent/CN101915108A/en
Publication of CN101915108A publication Critical patent/CN101915108A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

一种控制动压巷道底鼓的方法,在采动高应力环境中的巷道底板上,以巷道横截面中心为界对称向两帮方向施工不同纵向夹角α的钻孔后,安装水力膨胀锚杆,向水力膨胀锚杆内注高压水,当高压注水达到30MPa时,停止高压注水;按排距逐排施工,直至完成整个采动高应力环境中的巷道底板易发生底鼓巷道的施工。水力膨胀锚杆锚固力随围岩性质的差异变化不大,特别适用于动压巷道底板的支护,为控制动压巷道底鼓提供了一种新的途径。其施工方法简单,操作方便,成本低,劳动强度小,安装效率高,无污染,经济效益显著。

Figure 201010217011

A method for controlling the floor heave of a dynamic pressure roadway. On the roadway floor in a high-stress mining environment, the center of the roadway cross-section is used as a boundary to symmetrically drill holes with different longitudinal angles α in the direction of the two sides, and then install hydraulic expansion anchors. When the high-pressure water injection reaches 30MPa, stop the high-pressure water injection; construct row by row according to the row spacing, until the construction of the roadway floor prone to floor drum in the high-stress mining environment is completed. The anchoring force of the hydraulic expansion bolt has little change with the difference in the nature of the surrounding rock, and it is especially suitable for the support of the floor of the dynamic pressure roadway, which provides a new way for controlling the floor heave of the dynamic pressure roadway. The construction method is simple, the operation is convenient, the cost is low, the labor intensity is small, the installation efficiency is high, no pollution, and the economic benefit is remarkable.

Figure 201010217011

Description

一种控制动压巷道底鼓的方法 A method of controlling the floor drum of the dynamic pressure roadway

技术领域technical field

本发明涉及一种控制巷道底鼓的方法,尤其是一种适用于采动高应力环境中的巷道底鼓的控制方法。The invention relates to a method for controlling the floor heave of a roadway, in particular to a method for controlling the floor heave of a roadway in a high-stress mining environment.

背景技术Background technique

底鼓是煤矿井巷中常发生的一种动力现象。巷道掘进后,围岩由三向应力状态转变为二向应力状态,在复杂的集中应力影响下,底板岩层拉伸破坏形成底鼓。大量实测数据表明,巷道变形大约有2/3体现为底鼓。底鼓的主要危害是缩小了巷道断面,致使行人、运输、供排水、井下通风等都受到影响,因底鼓而造成巷道报废的现象也时有发生,严重影响矿山的安全生产。Bass drum is a dynamic phenomenon that often occurs in coal mine shafts. After the roadway is excavated, the surrounding rock changes from a three-dimensional stress state to a two-dimensional stress state. Under the influence of complex concentrated stress, the floor rock layer is stretched and destroyed to form a floor heave. A large number of measured data show that about 2/3 of the roadway deformation is reflected in the floor drum. The main hazard of the bottom drum is that it reduces the section of the roadway, which affects pedestrians, transportation, water supply and drainage, and underground ventilation.

动压巷道底鼓控制问题一直是困扰煤矿生产和建设的重大难题之一。近年来,国内外很多学者和煤矿技术人员对巷道底鼓的机理、防治措施等进行了卓有成效的研究,提出了很多底鼓控制技术,如加固底板、封闭金属支架、底板锚杆、底板注浆、巷旁充填和卸压煤柱等,这些研究成果对控制巷道底鼓具有很好的指导作用。然而,上述底鼓控制方法或多或少存在着施工速度慢、工艺复杂、经济成本高、控制效果有限、劳动强度大等缺陷,如加固底板虽然可以起到一定的抑制底鼓的作用,但在动压巷道中材料消耗大、支护费用高、工程量大;在高应力、松软底板的条件下,封闭式金属支架底梁往往无法充分发挥其承载能力,致使向巷道内鼓起,失去控制底鼓的能力;很多情况下,底板锚杆由于在松软底板岩层中锚固基础差而锚固力不足或延伸量与底鼓量不匹配而失效;底板注浆可加固底板较浅部岩层,如注浆达不到底板岩层的破坏深度,则上部已加固岩层会被下部岩层顶起,因此,注浆控制底鼓的作用也是有限的;而巷旁充填法和卸压煤柱法施工程序复杂,时间长,对回采工作面影响较大,且控制效果十分有限。The problem of bottom drum control in dynamic pressure roadway has always been one of the major problems plaguing the production and construction of coal mines. In recent years, many scholars and coal mine technicians at home and abroad have carried out fruitful research on the mechanism and prevention measures of roadway floor heave, and proposed many floor heave control technologies, such as reinforced floor, closed metal bracket, floor anchor rod, floor grouting , roadside filling and pressure relief coal pillars, etc. These research results have a good guiding role in controlling the roadway floor heave. However, the above-mentioned bottom drum control methods have more or less defects such as slow construction speed, complicated process, high economic cost, limited control effect, and high labor intensity. For example, although the reinforced floor can play a certain role in suppressing the bottom drum, but In the dynamic pressure roadway, the material consumption is large, the support cost is high, and the engineering volume is large; under the condition of high stress and soft floor, the closed metal support bottom beam often cannot fully exert its bearing capacity, resulting in bulging into the roadway and losing The ability to control the bottom heave; in many cases, floor anchors fail due to poor anchorage in soft floor rock formations, insufficient anchoring force, or a mismatch between the amount of extension and the amount of floor heave; floor grouting can reinforce shallower layers of the floor, such as If the grouting fails to reach the failure depth of the floor rock layer, the upper reinforced rock layer will be lifted by the lower rock layer. Therefore, the role of grouting to control the bottom heave is also limited; and the construction procedures of the roadside filling method and the pressure relief coal pillar method are complicated , the time is long, it has a great influence on the mining face, and the control effect is very limited.

发明内容Contents of the invention

技术问题:本发明的目的是克服已有技术的不足,提供一种施方法简单、操作方便、成本低、劳动强度小、安装效率高的控制动压巷道底鼓的方法。Technical problem: The purpose of the present invention is to overcome the deficiencies of the prior art and provide a method for controlling the floor drum of a dynamic pressure roadway with simple application, convenient operation, low cost, low labor intensity and high installation efficiency.

技术方案:本发明控制动压巷道底鼓的方法,步骤如下:Technical solution: The method for controlling the bottom drum of the dynamic pressure roadway according to the present invention, the steps are as follows:

(1)在采动高应力环境中的巷道底板上,以巷道横截面中心为界对称向两帮方向间隔施工一排钻孔,钻孔的孔径为28~42mm,钻孔的长度为1200~2800mm,一排钻孔的纵向夹角α为0°、15°、25°、30°、45°、60°;(1) On the floor of the roadway in the environment of high mining stress, a row of drill holes is constructed symmetrically to the two sides with the center of the roadway cross section as the boundary. 2800mm, the longitudinal angle α of a row of drilling holes is 0°, 15°, 25°, 30°, 45°, 60°;

(2)在施工完成的各钻孔中分别安装水力膨胀锚杆,水力膨胀锚杆直径为25~30mm;(2) Install hydraulic expansion anchor rods in each borehole after construction, and the diameter of the hydraulic expansion anchor rods is 25-30mm;

(3)通过水管连接水力膨胀锚杆的注液口和高压注水泵,向水力膨胀锚杆内注高压水,当高压注水泵的压力表达到30MPa时,关闭高压注水泵;(3) Connect the liquid injection port of the hydraulic expansion anchor and the high-pressure water injection pump through the water pipe, inject high-pressure water into the hydraulic expansion anchor, and when the pressure of the high-pressure water injection pump reaches 30MPa, turn off the high-pressure water injection pump;

(4)待高压注水泵卸压后,卸下高压注水泵,完成一个段区内控制动压巷道底鼓的施工;(4) After the high-pressure water injection pump is depressurized, the high-pressure water injection pump is removed to complete the construction of the bottom drum of the controlled dynamic pressure roadway in a section;

(5)重复上述步骤,按排距逐排施工,直至完成整个采动高应力环境中的巷道底板易发生底鼓巷道的施工。(5) Repeat the above steps, and construct row by row according to the row spacing, until the construction of the roadway floor prone to floor drum in the whole mining high stress environment is completed.

所述间隔施工一排钻孔的间距为500~2000mm;所述排距为600~2000mm。The spacing of a row of drilled holes in the interval construction is 500-2000 mm; the row spacing is 600-2000 mm.

有益效果:通过采用水力膨胀锚杆加固巷道底板,阻止巷道底板塑性区发展以及控制巷道底板岩体峰后碎胀、剪切错动变形,达到控制动压巷道底鼓的目的。水力膨胀锚杆用于控制动压巷道底鼓较其他粘结式锚杆的显著优点在于:水力膨胀锚杆为全长锚固,可在杆体全长范围内限制围岩扩容变形;水力膨胀锚杆与被锚固体(煤、岩体)为摩擦式锚固,钻孔内残留的煤(岩)粉、污水不影响锚杆锚固力。水力膨胀锚杆锚固力随围岩性质的差异变化不大,特别适用于动压巷道底板的支护,为控制动压巷道底鼓提供了一种新的途径。其施工方法简单,操作方便,成本低,劳动强度小,安装效率高,无污染,经济效益显著。Beneficial effects: by using hydraulic expansion bolts to reinforce the roadway floor, preventing the development of the plastic zone of the roadway floor and controlling post-peak crushing and shearing deformation of the roadway floor rock mass, the purpose of controlling the bottom heave of the roadway under dynamic pressure is achieved. Compared with other bonded anchors, the hydraulic expansion bolt is used to control the bottom heave of the roadway with significant advantages: the hydraulic expansion bolt is full-length anchored, which can limit the expansion and deformation of the surrounding rock within the entire length of the rod body; the hydraulic expansion bolt It is frictional anchoring with the anchored body (coal, rock mass), and the residual coal (rock) powder and sewage in the drill hole will not affect the anchoring force of the bolt. The anchoring force of the hydraulic expansion bolt does not change much with the difference in the nature of the surrounding rock, and it is especially suitable for the support of the bottom plate of the dynamic pressure roadway, which provides a new way for controlling the floor heave of the dynamic pressure roadway. The construction method is simple, the operation is convenient, the cost is low, the labor intensity is small, the installation efficiency is high, no pollution, and the economic benefit is remarkable.

附图说明Description of drawings

图1是本发明的底鼓钻孔位置示意图。Fig. 1 is a schematic diagram of the drilling position of the bottom drum of the present invention.

图2是本发明的水力膨胀锚杆施工连接示意图。Fig. 2 is a schematic diagram of the construction and connection of the hydraulic expansion bolt of the present invention.

图中:1-巷道,2-钻孔,3-水力膨胀锚杆,4-底板,5-两帮,6-注液口,7-水管,8-高压注水泵。In the figure: 1-roadway, 2-drilling, 3-hydraulic expansion bolt, 4-bottom plate, 5-two gangs, 6-liquid injection port, 7-water pipe, 8-high pressure water injection pump.

具体实施方式Detailed ways

下面结合附图对本发明的一个实施例作进一步的描述:An embodiment of the present invention will be further described below in conjunction with accompanying drawing:

图1所示,矩形巷道1为例,对某矿进行控制动压巷道底鼓的方法,根据现场实际情况,在巷道底板4按照不同的纵向夹度α安装水力膨胀锚杆3,然后注水,以阻止底板塑性区发展以及控制底板岩体峰后碎胀、剪切错动变形,实现控制动压巷道底鼓。具体步骤如下:As shown in Figure 1, the rectangular roadway 1 is taken as an example. The method of controlling the bottom drum of the dynamic pressure roadway in a certain mine is based on the actual situation on site. Install the hydraulic expansion bolt 3 on the roadway floor 4 according to different longitudinal clamps α, and then inject water. In order to prevent the development of the plastic zone of the floor and control the post-peak fracture expansion and shear displacement deformation of the rock mass of the floor, realize the control of the floor heave of the dynamic pressure roadway. Specific steps are as follows:

1、钻孔:在采动高应力环境中易发生巷道底鼓的巷道底板4上,以巷道1横截面中心为界对称向两帮5方向的纵向夹角α依次为15°、25°、45°,在巷道底板4上向下间隔500~2000mm施工一排钻孔2,钻孔2的孔径为28~42mm,钻孔2的长度为1200~2800mm,根据现场实际情况,一排钻孔2的纵向夹角α可以从0°、15°、25°、30°、45°、60°中按升序排列组合选择;1. Drilling: On the floor 4 of the roadway where the roadway bottom drum is prone to occur in the high-stress environment of mining, the longitudinal angle α in the direction of the two sides 5 is symmetrically bounded by the center of the cross-section of the roadway 1. 45°, construct a row of boreholes 2 at intervals of 500-2000mm downward on the roadway floor 4, the diameter of the boreholes 2 is 28-42mm, and the length of the boreholes 2 is 1200-2800mm. According to the actual situation on site, a row of boreholes The longitudinal angle α of 2 can be selected from 0°, 15°, 25°, 30°, 45°, 60° in ascending order;

2、安装水力膨胀锚杆:在施工完成的各钻孔2中分别安装水力膨胀锚杆3,将水力膨胀锚杆3送入钻孔2的底部,水力膨胀锚杆3直径为25~30mm;2. Install hydraulic expansion anchors: install hydraulic expansion anchors 3 in each borehole 2 after construction, and send hydraulic expansion anchors 3 to the bottom of borehole 2. The diameter of hydraulic expansion anchors 3 is 25-30mm;

3、注高压水:通过水管7连接水力膨胀锚杆3的注液口6和高压注水泵8,向水力膨胀锚杆3内注高压水,注液压力不小于30MPa,注液时间大于5min,并确保初锚力在100kN以上;当高压注水泵8的压力表达到30MPa时,关闭高压注水泵8;3. Inject high-pressure water: connect the liquid injection port 6 of the hydraulic expansion anchor 3 and the high-pressure water injection pump 8 through the water pipe 7, inject high-pressure water into the hydraulic expansion anchor 3, the injection pressure is not less than 30MPa, and the injection time is greater than 5min. And ensure that the initial anchor force is above 100kN; when the pressure of the high-pressure water injection pump 8 reaches 30MPa, turn off the high-pressure water injection pump 8;

4、待高压注水泵8卸压后,卸下高压注水泵8,完成一个段区内控制动压巷道底鼓的施工;4. After the pressure of the high-pressure water injection pump 8 is released, the high-pressure water injection pump 8 is removed to complete the construction of the bottom drum of the roadway with controlled dynamic pressure in a section;

5、重复上述步骤,按排距为600~2000mm的距离逐排施工,直至完成整个采动高应力环境中的巷道底板4易发生底鼓巷道的施工。5. Repeat the above steps, and construct row by row according to the row spacing of 600-2000mm, until the construction of the roadway floor 4 prone to floor drum in the whole mining high-stress environment is completed.

Claims (3)

1. method of controlling floor heave of dynamic pressure tunnel, it is characterized in that: step is as follows:
(1) on the roadway floor in adopting high stress environment (4), with tunnel (1) cross-section center is that bound pair claims to help (5) direction gang drill hole (2) of constructing at interval to two, the aperture of boring (2) is 28~42mm, the length of boring (2) is 1200~2800mm, and the longitudinal angle α in a gang drill hole (2) is 0 °, 15 °, 25 °, 30 °, 45 °, 60 °;
(2) in each boring (2) that construction is finished hydraulic expansion anchor pole (3) is installed respectively, hydraulic expansion anchor pole (3) diameter is 25~30mm;
(3) by the liquid injection port (6) and the high pressure water-injection pump (8) of water pipe (7) connection hydraulic expansion anchor pole (3) afterbody, in hydraulic expansion anchor pole (3), annotate water under high pressure, when the pressure meter of high pressure water-injection pump (8) reaches 30MPa, close high pressure water-injection pump (8);
(4) treat high pressure water-injection pump (8) release after, unload high pressure water-injection pump (8), finish the construction of a section district inner control floor heave of dynamic pressure tunnel;
(5) repeat above-mentioned steps, construct by row, the construction in pucking tunnel easily takes place until finishing the whole roadway floor of adopting in the high stress environment (4) by array pitch.
2. the method for control floor heave of dynamic pressure tunnel according to claim 1 is characterized in that: the construct spacing in a gang drill hole (2) of described interval is 500~2000mm.
3. the method for control floor heave of dynamic pressure tunnel according to claim 1 is characterized in that: described array pitch is 600~2000mm.
CN 201010217011 2010-06-22 2010-06-22 A method of controlling the floor drum of the dynamic pressure roadway Pending CN101915108A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010217011 CN101915108A (en) 2010-06-22 2010-06-22 A method of controlling the floor drum of the dynamic pressure roadway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010217011 CN101915108A (en) 2010-06-22 2010-06-22 A method of controlling the floor drum of the dynamic pressure roadway

Publications (1)

Publication Number Publication Date
CN101915108A true CN101915108A (en) 2010-12-15

Family

ID=43322722

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010217011 Pending CN101915108A (en) 2010-06-22 2010-06-22 A method of controlling the floor drum of the dynamic pressure roadway

Country Status (1)

Country Link
CN (1) CN101915108A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102797480A (en) * 2012-08-27 2012-11-28 中国矿业大学 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall
CN102852528A (en) * 2012-04-01 2013-01-02 中国矿业大学 Method for controlling floor heave through inverted arch anchoring beam
CN102877857A (en) * 2012-09-24 2013-01-16 山西晋城无烟煤矿业集团有限责任公司 Deep hole pre-grouting top plate reinforcement method for large-mining height working face under special geological conditions
CN102913255A (en) * 2012-11-09 2013-02-06 中国矿业大学(北京) Method for preventing bottom board of deep-seated heading from bulging and deforming
CN103016057A (en) * 2012-12-20 2013-04-03 大同煤矿集团有限责任公司 Prevention method for dynamic pressure area of working face
CN103266899A (en) * 2013-05-31 2013-08-28 山东科技大学 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall
CN104141496A (en) * 2014-06-21 2014-11-12 西安科技大学 Rectangular roadway surrounding rock deformation and failure control method
CN104879127A (en) * 2015-04-24 2015-09-02 中国矿业大学 Method for replacing coal column by floor heaving top connecting
CN108756930A (en) * 2018-05-31 2018-11-06 天地科技股份有限公司 A method of administering Floor Heave in Roadway and bottom plate bump using townhouse pile foundation
CN108979666A (en) * 2018-07-11 2018-12-11 河北工程大学 A kind of method of steel tube concrete pile control Floor Heave in Roadway
CN109139057A (en) * 2018-10-29 2019-01-04 六盘水师范学院 A kind of coal cutting roadway bottom plate water suction pucking administering method
CN112196619A (en) * 2020-10-30 2021-01-08 吕梁学院 Hard bottom plate roadway floor heave deformation intercepting energy absorption type prevention and control method
CN112664251A (en) * 2020-12-30 2021-04-16 开滦(集团)有限责任公司 Hydraulic expansion type grouting anchor rod and anchoring method
CN113090280A (en) * 2021-04-09 2021-07-09 中国矿业大学 Method for revealing roadway floor heave mechanism of double-roadway arrangement system
CN113638756A (en) * 2021-09-09 2021-11-12 辽宁工程技术大学 Anchor cable supporting method for treating roadway floor heave and anchor cable

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3020673A1 (en) * 1979-05-31 1980-12-11 Johannes Petrus Antonius Roest Deep round underground gallery support - involves narrow peripheral zones more compressible than surrounding rock (NL 2.12.80)
SU1481420A1 (en) * 1986-05-26 1989-05-23 Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела Method of preventing rock swelling in mine workings
SU1627708A1 (en) * 1988-12-12 1991-02-15 Институт горного дела им.А.А.Скочинского Method of supporting mine workings
CN1865660A (en) * 2006-06-16 2006-11-22 中国矿业大学 Construction method for weakening zone of floor plate wall rock
CN201254993Y (en) * 2008-07-24 2009-06-10 义马煤业(集团)有限责任公司 O-shaped composite supporting construction for tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3020673A1 (en) * 1979-05-31 1980-12-11 Johannes Petrus Antonius Roest Deep round underground gallery support - involves narrow peripheral zones more compressible than surrounding rock (NL 2.12.80)
SU1481420A1 (en) * 1986-05-26 1989-05-23 Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела Method of preventing rock swelling in mine workings
SU1627708A1 (en) * 1988-12-12 1991-02-15 Институт горного дела им.А.А.Скочинского Method of supporting mine workings
CN1865660A (en) * 2006-06-16 2006-11-22 中国矿业大学 Construction method for weakening zone of floor plate wall rock
CN201254993Y (en) * 2008-07-24 2009-06-10 义马煤业(集团)有限责任公司 O-shaped composite supporting construction for tunnel

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《煤炭科学与技术》 19920831 胡长仁等 水力膨胀锚杆在采掘面的应用 4-6 1-3 , 第8期 2 *
《煤炭科学技术》 20081231 汪健民 五阳煤矿回采巷道底鼓防治技术实践 16-18 1-3 第36卷, 第12期 2 *
《矿业工程》 20061031 黄胜等 浅谈巷道底鼓的防治措施 27-29 1-3 第4卷, 第5期 2 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852528A (en) * 2012-04-01 2013-01-02 中国矿业大学 Method for controlling floor heave through inverted arch anchoring beam
CN102797480A (en) * 2012-08-27 2012-11-28 中国矿业大学 Method for controlling bottom squeeze deformation of high-stress soft rock roadway by using discontinuous pressure-bearing grating concrete wall
CN102877857A (en) * 2012-09-24 2013-01-16 山西晋城无烟煤矿业集团有限责任公司 Deep hole pre-grouting top plate reinforcement method for large-mining height working face under special geological conditions
CN102913255A (en) * 2012-11-09 2013-02-06 中国矿业大学(北京) Method for preventing bottom board of deep-seated heading from bulging and deforming
CN103016057A (en) * 2012-12-20 2013-04-03 大同煤矿集团有限责任公司 Prevention method for dynamic pressure area of working face
CN103016057B (en) * 2012-12-20 2015-05-06 大同煤矿集团有限责任公司 Prevention method for dynamic pressure area of working face
CN103266899A (en) * 2013-05-31 2013-08-28 山东科技大学 Method for controlling floor heave deformation of soft rock roadway by means of anchor pile continuous wall
CN104141496A (en) * 2014-06-21 2014-11-12 西安科技大学 Rectangular roadway surrounding rock deformation and failure control method
CN104879127A (en) * 2015-04-24 2015-09-02 中国矿业大学 Method for replacing coal column by floor heaving top connecting
CN104879127B (en) * 2015-04-24 2017-03-15 中国矿业大学 A kind of pucking connects the method that overhead changes coal column
CN108756930A (en) * 2018-05-31 2018-11-06 天地科技股份有限公司 A method of administering Floor Heave in Roadway and bottom plate bump using townhouse pile foundation
CN108979666A (en) * 2018-07-11 2018-12-11 河北工程大学 A kind of method of steel tube concrete pile control Floor Heave in Roadway
CN108979666B (en) * 2018-07-11 2024-04-02 河北工程大学 Method for controlling tunnel floor heave by concrete filled steel tube pile
CN109139057A (en) * 2018-10-29 2019-01-04 六盘水师范学院 A kind of coal cutting roadway bottom plate water suction pucking administering method
CN112196619A (en) * 2020-10-30 2021-01-08 吕梁学院 Hard bottom plate roadway floor heave deformation intercepting energy absorption type prevention and control method
CN112664251A (en) * 2020-12-30 2021-04-16 开滦(集团)有限责任公司 Hydraulic expansion type grouting anchor rod and anchoring method
CN113090280A (en) * 2021-04-09 2021-07-09 中国矿业大学 Method for revealing roadway floor heave mechanism of double-roadway arrangement system
CN113638756A (en) * 2021-09-09 2021-11-12 辽宁工程技术大学 Anchor cable supporting method for treating roadway floor heave and anchor cable

Similar Documents

Publication Publication Date Title
CN101915108A (en) A method of controlling the floor drum of the dynamic pressure roadway
Liu et al. Research on roof damage mechanism and control technology of gob-side entry retaining under close distance gob
Kang et al. Application of a combined support system to the weak floor reinforcement in deep underground coal mine
Yang et al. Failure mechanism and control technology of water-immersed roadway in high-stress and soft rock in a deep mine
Fangtian et al. Whole section anchor–grouting reinforcement technology and its application in underground roadways with loose and fractured surrounding rock
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
Yu et al. Field investigations of high stress soft surrounding rocks and deformation control
Chen et al. Study on repair control technology of soft surrounding rock roadway and its application
CN203756206U (en) Novel soft-rock roadway floor heave governing structure
CN108678769A (en) Deep Gateway anchor note cuts top master control and stays lane method
CN102704965B (en) One prevents violent mining influence back to collapse method for leakage
CN107083977A (en) A kind of grouting strengthening method of many granularities of argillaceous soft rock tunnel subregion
CN115030722B (en) Goaf lag filling efficient water retention coal mining method
CN102877858B (en) Reinforcing method for crushed top plate of coal face
CN205189893U (en) Be used for a lane coal column to wearing reinforced (rfd) supporting construction
CN109026024B (en) Roadway roof deformation control method under high-level stress action
CN205532656U (en) Deep well weak surrounding rock roadway support device
Jiang et al. Failure mechanism analysis and support design for deep composite soft rock roadway: a case study of the Yangcheng coal mine in China
CN102425155B (en) A superficial reinforcement method of overlying rock mass in goaf
He et al. Research on spatiotemporal evolution law of surrounding rock fractures and hierarchical collaborative control technology in high-stress soft rock roadway: A case study
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
Lu et al. Cemented backfilling mining technology for gently inclined coal seams using a continuous mining and continuous backfilling method
CN117167085A (en) Anchor injection supporting method for coal pillar-free mining roadway retaining
Li et al. Influence research for softening and swelling of weakly cemented soft rock on the stability of surrounding rock in roadway
CN204457810U (en) The two strong housing support system of soft-rock tunnel available buffer gradual change type

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20101215