CN102713074B - Connected wall structure consisting of steel pipe sheet piles and steel sheet pile, and method of constructing same - Google Patents
Connected wall structure consisting of steel pipe sheet piles and steel sheet pile, and method of constructing same Download PDFInfo
- Publication number
- CN102713074B CN102713074B CN201180005274.4A CN201180005274A CN102713074B CN 102713074 B CN102713074 B CN 102713074B CN 201180005274 A CN201180005274 A CN 201180005274A CN 102713074 B CN102713074 B CN 102713074B
- Authority
- CN
- China
- Prior art keywords
- sheet pile
- steel
- steel pipe
- steel sheet
- pipe sheet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/08—Locking forms; Edge joints; Pile crossings; Branch pieces
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/06—Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
- E02B3/066—Quays
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Composite Materials (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Revetment (AREA)
Abstract
本发明通过形成能够允许一定程度的施工误差的连结结构,从而提供一种施工性优异且能够降低施工成本的、合理的钢管板桩与钢板桩的连结壁结构及其构筑方法。在由钢板桩(2)将隔开间隔地被进行了打桩的钢管板桩(1)彼此连结以形成连结壁结构时,在钢管板桩(1)的侧部设置具有在长度方向上连续的狭缝(3a)的连结构件(3)并从长度方向将钢板桩(2)的端部嵌合于狭缝(3a)部分。在该连结部设有用于吸收钢管板桩(1)彼此的施工误差的规定的游隙(u)。通过在钢管板桩(1)与钢板桩(2)的连结部设置能够吸收施工误差的充分的空间,从而即使钢管板桩(2)由于施工而产生打桩延长、打桩收缩,也能够容易地对钢板桩(2)的端部进行嵌合和设置。
The present invention provides a reasonable connection wall structure of steel pipe sheet piles and steel sheet piles and a construction method thereof, which are excellent in workability and can reduce construction costs by forming a connection structure that allows a certain degree of construction error. When the steel pipe sheet piles (1) piled at intervals are connected to each other by the steel sheet piles (2) to form a connected wall structure, the steel pipe sheet piles (1) are provided on the side with The connection member (3) of the slit (3a) fits the end of the steel sheet pile (2) into the slit (3a) from the longitudinal direction. A predetermined play (u) for absorbing construction errors between the steel pipe sheet piles (1) is provided at the connecting portion. By providing a sufficient space at the joint between the steel pipe sheet pile (1) and the steel sheet pile (2), which can absorb construction errors, even if the steel pipe sheet pile (2) undergoes piling extension or piling contraction due to construction, it can be easily corrected. The end parts of the steel sheet pile (2) are fitted and installed.
Description
技术领域 technical field
本发明涉及一种用于防波堤、挡土墙这样的挡土壁等的钢管板桩与钢板桩的连结壁结构及其构筑方法。 The present invention relates to a connection wall structure of steel pipe sheet piles and steel sheet piles used for retaining walls such as breakwaters and retaining walls, and a construction method thereof.
背景技术 Background technique
在防波堤、挡土墙这样的挡土壁中,由于土压力、水压力而作用有欲使挡土构件弯曲的力,其结果,挡土壁向力的作用方向产生弯曲变形,根据不同的情况,会担心产生滑动、倒塌。 In retaining walls such as breakwaters and retaining walls, forces that intend to bend the retaining members act due to earth pressure and water pressure. As a result, the retaining wall is bent and deformed in the direction of the force. , there will be worries about slipping and collapsing.
在挡土壁的设计中,为了不产生上述的滑动、倒塌而埋没到足够的深度,并且,为了将壁的变形量抑制到构造物所规定的允许值以下而应用具有充分的截面刚性的壁构件,从经济性的观点出发,在满足上述条件的范围内来决定最适合的构件、截面、长度。并且,由于壁高、地基条件、地震时的震度的不同会导致壁构件贯入地基的长度变长,因此,构件的充分优异的施工性很重要。 In the design of the retaining wall, a wall with sufficient cross-sectional rigidity should be used to prevent the above-mentioned sliding and collapse from occurring to a sufficient depth, and to suppress the deformation of the wall below the allowable value specified by the structure. For members, from the viewpoint of economic efficiency, the most suitable member, section, and length are determined within the range satisfying the above conditions. In addition, since the wall member penetrates into the foundation length due to differences in wall height, foundation conditions, and seismic intensity during an earthquake, it is important to have sufficiently excellent workability of the member.
通常,作为挡土壁,具有如图6所示那样的、(a)自立式结构(日文:自立式構造:重力式挡土墙结构)、(b)锚定式(日文:控え式)结构、(c)水平撑式(日文:切梁式)结构,根据用途而分开使用。特别是,在背面用地受到限制而不能确保充分的空间的情况下等,应用(a)的自立式结构。 Usually, as a retaining wall, as shown in Figure 6, (a) self-supporting structure (Japanese: self-supporting structure: gravity retaining wall structure), (b) anchor type (Japanese: control え type) structure, (c) Horizontal support type (Japanese: cut beam type) structure, which is used separately according to the purpose. In particular, the self-supporting structure of (a) is applied when a sufficient space cannot be secured due to restrictions on the backside site.
在自立式结构中,作为一例,例如使用如图7所示那样的帽(hat)形钢板桩2,但是,在具有较高壁高的防波堤、挡土墙且壁所允许的变形量较小而需要充分的壁刚性的情况下等,大多使用如图8所示那样的在钢管上设置有嵌合用的连结构件3而成的、截面刚性优异的钢管板桩1。 In a self-supporting structure, as an example, a hat-shaped steel sheet pile 2 as shown in Fig. 7 is used, however, in a breakwater or a retaining wall with a relatively high wall height, the allowable deformation amount of the wall is small On the other hand, when sufficient wall rigidity is required, steel pipe sheet piles 1 having excellent cross-sectional rigidity in which connecting members 3 for fitting are provided on steel pipes as shown in FIG. 8 are often used.
钢板桩和钢管板桩具有优异的向地基贯入的贯入性,且与现场的需要相对应地存在各种施工方法。例如,在要求高速施工的情况下,使用振动打桩(vibratory hammer)方法等,并且,在附近存在民房等的城市区域,钢板桩和钢管板桩是能够应用可进行低振动、低噪音施工的液压压入方法等的、施工性优异的壁构件。 Steel sheet piles and steel pipe sheet piles have excellent penetrability into the foundation, and various construction methods exist according to the needs of the site. For example, when high-speed construction is required, the vibratory hammer method, etc. are used, and in urban areas where there are residential buildings nearby, steel sheet piles and steel pipe sheet piles are hydraulic pressure that can be used for low-vibration and low-noise construction. A wall member with excellent workability, such as by press-fitting method.
并且,作为以往技术,在非专利文献1(アルセロール·ミッタル公司的商品目录)中,记载有如下技术:将如图9所示那样的在钢管板桩1上设置的钩状截面的接头构件33与Z形钢板桩(将两张Z形钢板桩32连结起来而实质上形成为与图7的钢板桩相同的形态的钢板桩)的接头32c嵌合而形成壁结构。 In addition, as a prior art, Non-Patent Document 1 (catalogue of Alselor Mitterl Co., Ltd.) describes a technique in which a joint member 33 with a hook-shaped cross-section provided on a steel pipe sheet pile 1 as shown in FIG. 9 A wall structure is formed by fitting with the joint 32c of the Z-shaped steel sheet pile (the steel sheet pile which connected two Z-shaped steel sheet piles 32 and formed substantially the same form as the steel sheet pile of FIG. 7).
并且,在专利文献1中,作为使用了钢管板桩与直线板桩而成的防波堤,记载有通过以下方式而构成的防波堤,即,在隔开规定间隔而设置的钢管板桩之间,将直线板桩夹设在从该钢管板桩的下端部到与海底地基面相同或略上方的位置。 In addition, Patent Document 1 describes, as a breakwater using steel pipe sheet piles and linear sheet piles, a breakwater configured by placing steel pipe sheet piles at predetermined intervals between steel pipe sheet piles. The linear sheet pile is interposed from the lower end of the steel pipe sheet pile to a position equal to or slightly above the seabed ground surface.
另外,在专利文献2中,作为异型壁体结构构件的连结结构,记载有如下的连结结构:将具有狭缝的筒状接头安装于板桩壁彼此连接的交叉位置的壁面,该板桩壁是通过将多个钢板桩以接头彼此嵌合的方式形成的,使另一个板桩壁的钢板桩的端部能够嵌合于该筒状接头的狭缝。 In addition, Patent Document 2 describes, as a connection structure of special-shaped wall structural members, a connection structure in which a cylindrical joint having a slit is attached to a wall surface at an intersection position where sheet pile walls are connected. It is formed by fitting together several steel sheet piles by joints, and the edge part of the steel sheet pile of the other sheet pile wall can be fitted in the slit of this cylindrical joint.
专利文献1:日本特开平02-213508号公报 Patent Document 1: Japanese Patent Application Laid-Open No. 02-213508
专利文献2:日本专利第4231429号公报 Patent Document 2: Japanese Patent No. 4231429
非专利文献1:“Steel Sheet Piling General Catalogue2008”,ArcelorMittal,2008年,p.34。 Non-Patent Document 1: "Steel Sheet Piling General Catalog 2008", ArcelorMittal, 2008, p.34.
在上述非专利文献1所述的壁结构中,通常,首先隔开规定间隔来对钢管板桩进行打桩,之后,以使钢管板桩彼此连结的形式对钢板桩进行打桩。 In the wall structure described in the above-mentioned non-patent document 1, steel pipe sheet piles are usually piled at predetermined intervals first, and then the steel sheet piles are piled so as to connect the steel pipe sheet piles.
但是,由于连结部的空间狭小,施工时难以使连结部嵌合,为了进行连结部的嵌合,需要另行设置对位用的模板并在严密的管理的基础上进行打桩等。因此,存在施工成本的增加、花费现场的作业劳力和时间的问题。 However, due to the narrow space of the joints, it is difficult to fit the joints during construction. In order to fit the joints, it is necessary to separately install a template for alignment and perform pile driving on the basis of strict management. Therefore, there is a problem that the construction cost increases, and labor and time for on-site work are required.
并且,由于情况的不同,由于施工时的打桩延长(elongation due to driving)、打桩收缩(shrinkage due to driving)而不能嵌合构件,而不得不在暂时拔出已设置的构件后,再次进行打桩等,因而,有可能导致大幅的施工成本的上升、工期延长。 In addition, depending on the situation, due to elongation due to driving or shrinkage due to driving during construction, the components cannot be fitted, and the installed components have to be pulled out temporarily, and the piles must be driven again, etc. , Therefore, it may lead to a substantial increase in construction costs and an extension of the construction period.
另一方面,也考虑沿壁方向交替地对钢管构件与钢板桩进行打桩,但是,该情况下,也由于连结部的空间狭小而消耗打桩劳力和时间、每个构件需要进行打桩机械的更换等,由此导致消耗施工劳力和时间且施工成本较大地增加的情况,故此不合理。 On the other hand, it is also conceivable to alternately drive steel pipe members and steel sheet piles along the wall direction, but in this case, too, due to the narrow space at the connection portion, piling labor and time are consumed, and piling machines need to be replaced for each member, etc. , which leads to the consumption of construction labor and time and the situation that the construction cost is greatly increased, so it is unreasonable.
并且,考虑到止水性,由于没有设置用于充分地填充止水材料的空间,因而,作为壁也难以发挥充分的止水功能。 In addition, in consideration of water-stopping properties, since there is no space for sufficiently filling the water-stopping material, it is difficult to exhibit a sufficient water-stopping function as a wall.
在将钢管板桩与直线板桩连结的结构即专利文献1所述的发明中,也存在与非专利文献1所述的发明相同的问题。 In the invention described in Patent Document 1, which is a structure in which steel pipe sheet piles and linear sheet piles are connected, problems similar to those in the invention described in Non-Patent Document 1 exist.
发明内容 Contents of the invention
本发明谋求解决上述那样的以往技术中的问题,其目的在于通过将由钢板桩将隔开间隔地进行打桩的钢管板桩彼此连结而成的钢管板桩与钢板桩的连结壁结构设成能够允许一定程度的施工误差的连结结构,从而提供一种施工性优异且能够降低施工成本的、合理的钢管板桩与钢板桩的连结壁结构及其构筑方法。 The present invention seeks to solve the above-mentioned problems in the prior art, and its object is to set the connection wall structure of the steel pipe sheet pile and the steel sheet pile, which is formed by connecting steel pipe sheet piles piled at intervals with steel sheet piles, to allow A connection structure with a certain degree of construction error, thereby providing a reasonable connection wall structure of steel pipe sheet piles and steel sheet piles and a construction method thereof that are excellent in constructability and can reduce construction costs.
本申请的技术方案1的发明是一种钢管板桩与钢板桩的连 结壁结构,其是由钢板桩将隔开间隔地被进行了打桩的钢管板桩彼此连结而成的,其特征在于,通过在上述钢管板桩的侧部设置具有在长度方向上连续的狭缝的连结构件并从长度方向将上述钢板桩的端部嵌合于上述狭缝部分,从而使上述连结构件与钢板桩的端部连结,在该连结构件与钢板桩的端部的连结部设有用于吸收上述钢管板桩彼此的施工误差的游隙。 The invention of claim 1 of the present application is a connecting wall structure of steel pipe sheet piles and steel sheet piles, which is formed by connecting steel pipe sheet piles piled at intervals by steel sheet piles, and is characterized in that , by providing a connecting member having a continuous slit in the longitudinal direction on the side of the steel pipe sheet pile and fitting the end of the steel sheet pile into the slit portion from the longitudinal direction, the connecting member and the The end part of the steel sheet pile is connected, and the connection part of this connection member and the end part of a steel sheet pile is provided with the play for absorbing the construction error of said steel pipe sheet piles.
原则上,本发明设想首先隔开规定间隔来对钢管板桩进行打桩,之后,以使钢管板桩彼此连结的形式将钢板桩打桩于钢管板桩彼此之间,该情况下,即使存在钢管板桩的打桩装置或打桩方法与钢板桩的打桩装置或打桩方法不同的情况,也能够在不逐一改变装置或打桩方法的情况下连续地进行施工。 In principle, the present invention conceives that steel pipe sheet piles are first piled at predetermined intervals, and then the steel pipe sheet piles are piled between the steel pipe sheet piles so that the steel pipe sheet piles are connected to each other. In this case, even if there are steel pipe sheet piles Even when the piling device or the piling method of the pile is different from the piling device or the piling method of the steel sheet pile, construction can be continuously performed without changing the device or the piling method one by one.
在此基础上,在将钢板桩的端部嵌合于设置于钢管板桩的连结构件的狭缝部分时,由于已经形成有规定的游隙,因而,即使在打桩的钢管板桩彼此的间隔中具有一定程度的施工误差,也能够沿壁方向调整钢板桩的设置位置,并能够顺利地进行施工。 On this basis, when the end of the steel sheet pile is fitted into the slit portion of the connecting member provided on the steel pipe sheet pile, since a predetermined play is already formed, even if the steel pipe sheet piles to be piled are separated Even if there is a certain degree of construction error in the interval, the installation position of the steel sheet pile can be adjusted along the wall direction, and construction can be carried out smoothly.
即,在非专利文献1所述的发明中,不得不使用特殊的模板而以较高精度进行施工,施工变得困难,最坏是存在不能施工的情况,相对于此,在本发明中,不要求那样过度的施工管理,能够改善施工性,并能够谋求工期的缩短、成本的降低。 That is, in the invention described in Non-patent Document 1, construction has to be performed with high precision using a special formwork, and construction becomes difficult, and at worst, construction may not be possible. On the other hand, in the present invention, Such excessive construction management is not required, and the workability can be improved, and the construction period can be shortened and the cost can be reduced.
技术方案2是根据技术方案1的钢管板桩与钢板桩的连结壁结构,其特征在于,上述连结构件内填充有止水材料。 Claim 2 is the connection wall structure of the steel pipe sheet pile and the steel sheet pile according to claim 1, wherein the connection member is filled with a water-stop material.
这是在壁结构中需要止水功能的情况,在连结构件与钢板桩的端部的连结部分预先确保设置游隙和填充止水材料所需的充分的空间,从而能够对壁结构赋予止水性。 This is a case where a water-stop function is required in the wall structure, and a sufficient space for providing play and filling the water-stop material is secured in advance at the connection portion between the connecting member and the end of the steel sheet pile, and the wall structure can be given a water-stop function. watery.
技术方案3是根据技术方案1或2的钢管板桩与钢板桩的连结壁结构,其特征在于,在上述钢板桩的端部设有用于防止上 述钢板桩的端部从上述狭缝脱出的止挡构件。 Claim 3 is the connecting wall structure between a steel pipe sheet pile and a steel sheet pile according to Claim 1 or 2, wherein a stopper for preventing the end of the steel sheet pile from slipping out of the slit is provided at the end of the steel sheet pile. stop member.
特别是,在施工中,止挡构件具有较大的用于防止钢板桩的端部从连结构件的狭缝脱出而脱离的效果。 In particular, during construction, the stopper member has a large effect for preventing the end of the steel sheet pile from slipping out from the slit of the connection member and detaching.
技术方案4是根据技术方案1、2或3的钢管板桩与钢板桩的连结壁结构,其特征在于,上述连结构件是大致圆形,其外径Φ(mm)与板厚t(mm)之间的关系满足式(1)的关系。 Claim 4 is the connecting wall structure of steel pipe sheet piles and steel sheet piles according to Claim 1, 2, or 3, wherein the connecting member is approximately circular, and its outer diameter Φ (mm) is equal to the plate thickness t (mm ) satisfies the relationship of formula (1).
式1 Formula 1
70+2t≤Φ≤270···(1) 70+2t≤Φ≤270···(1)
通常在钢板桩的两端部具有爪部(接头),但是,若连结构件的内径为70mm以上(外径为(70+2t)mm以上),则不要求过度的施工管理就能够容易与钢板桩相嵌合。另一方面,在接头构件的直径过大时,有可能对施工性产生妨碍,但是,若接头构件的直径为270mm以下,则施工性良好。 Usually, there are claws (joints) at both ends of the steel sheet pile, but if the inner diameter of the connecting member is 70 mm or more (the outer diameter is (70+2t) mm or more), it can be easily integrated without requiring excessive construction management. The steel sheet piles are fitted together. On the other hand, if the diameter of the joint member is too large, the workability may be hindered. However, if the diameter of the joint member is 270 mm or less, the workability is good.
技术方案5是根据技术方案4的钢管板桩与钢板桩的连结壁结构,其特征在于,上述连结构件的外径Φ(mm)与板厚t(mm)还满足式(2)的条件。 Technical solution 5 is the connecting wall structure of steel pipe sheet piles and steel sheet piles according to technical solution 4, which is characterized in that the outer diameter Φ (mm) and plate thickness t (mm) of the above connecting member also satisfy the conditions of formula (2) .
式2 Formula 2
其中,Φ是连结构件的外径, where Φ is the outer diameter of the connecting member,
t是连结构件的板厚, t is the plate thickness of the connecting member,
σy是连结构件所用的钢材的屈服应力, σ y is the yield stress of the steel used in the connecting structure,
Py是使钢板桩达到屈服的作用载荷, P y is the applied load to bring the steel sheet pile to yield,
b是连结构件与钢板桩相嵌合的长度方向的长度。 b is the length in the longitudinal direction where the connecting member and the steel sheet pile are fitted.
若钢制壁的接头构件的形状还满足式(2),则更有效地降低材料成本 If the shape of the joint member of the steel wall also satisfies formula (2), the material cost can be reduced more effectively
技术方案6是根据技术方案1至5的钢管板桩与钢板桩的连结壁结构,其特征在于,上述钢板桩是在与轴向呈直角的截面中的两端部具有平坦的区间的钢板桩。 Claim 6 is the connection wall structure of a steel pipe sheet pile and a steel sheet pile according to Claims 1 to 5, wherein the steel sheet pile is a steel sheet pile having flat sections at both ends of a cross section perpendicular to the axial direction. .
作为这种在两端部具有平坦的区间的钢板桩的代表,能够使用图7所示那样的帽形钢板桩等。 A hat-shaped steel sheet pile etc. as shown in FIG. 7 can be used as a representative of the steel sheet pile which has such a flat section in both end parts.
在该情况下,通过将游隙设为与平坦部的宽度相对应的间隔,从而能够允许与该间隔相对应的施工误差。 In this case, by making the play an interval corresponding to the width of the flat portion, it is possible to allow a construction error corresponding to the interval.
技术方案7是根据技术方案1至6的钢管板桩与钢板桩的连结壁结构,其特征在于,上述钢板桩为U形钢板桩。 Claim 7 is a connection wall structure of a steel pipe sheet pile and a steel sheet pile according to Claims 1 to 6, wherein the steel sheet pile is a U-shaped steel sheet pile.
在两端部不具有平坦的区间的U形钢板桩的情况下,通过利用连结部的游隙来使U形钢板桩沿壁结构的前后方向位移,从而能够顺利地进行连结作业。 In the case of the U-shaped steel sheet pile which does not have a flat section at both ends, the connecting work can be smoothly performed by displacing the U-shaped steel sheet pile in the front-rear direction of the wall structure using the play of the connecting portion.
技术方案8是根据技术方案1至7的钢管板桩与钢板桩的连结壁结构,其特征在于,使上述钢板桩的连结位置从上述钢管板桩的中性轴偏心。 Claim 8 is the connection wall structure of a steel pipe sheet pile and a steel sheet pile according to Claims 1 to 7, wherein the connection position of the steel sheet pile is eccentric from the neutral axis of the steel pipe sheet pile.
这主要是为了进行壁结构的壁面位置的调整,利用游隙来提高施工性的效果基本上与技术方案1至7的情况相同。 This is mainly for adjusting the position of the wall surface of the wall structure, and the effect of improving the workability by using the clearance is basically the same as that of technical proposals 1 to 7.
技术方案9是技术方案1至8中任一项所述的钢管板桩与钢板桩的连结壁结构的构筑方法,其特征在于,首先隔开规定间隔来对上述钢管板桩进行打桩,之后,以使上述钢管板桩彼此连结的形式对上述钢板桩进行打桩。 Claim 9 is a method for constructing a connecting wall structure between steel pipe sheet piles and steel sheet piles according to any one of claims 1 to 8, wherein the steel pipe sheet piles are first driven at predetermined intervals, and then, The said steel sheet pile is piled so that the said steel pipe sheet pile may be connected.
在本发明中,通过形成用于在钢管板桩与钢板桩的连结部确保与施工误差相对应的游隙的结构,从而即使在打桩的钢管板桩彼此的间隔中产生一定程度的施工误差,也能够直接进行连结,能够构筑施工性优异的钢管板桩与钢板桩的连结壁结构。 In the present invention, by forming a structure for ensuring play corresponding to construction errors in the connection between the steel pipe sheet pile and the steel sheet pile, even if a certain degree of construction error occurs in the interval between the steel pipe sheet piles to be piled, Direct connection is also possible, and a connection wall structure of a steel pipe sheet pile and a steel sheet pile excellent in workability can be constructed.
并且,在要求止水性的情况下,通过向设有游隙的空间填充止水材料,从而能够容易地进行应对。 In addition, when water-stopping properties are required, it is possible to easily respond by filling the space provided with play with a water-stopping material.
对于施工时的钢板桩端部的脱出,通过在钢板桩的连结部设置止挡构件,从而能够防止钢板桩端部从钢管板桩的连结部脱离。 When the steel sheet pile edge part falls out at the time of construction, it can prevent that a steel sheet pile edge part falls out from the connection part of a steel pipe sheet pile by providing a stopper member in the connection part of a steel sheet pile.
附图说明 Description of drawings
图1表示本发明的一实施方式的钢管板桩与钢板桩的连结部的结构,其中,图1的(a)是没有施工误差的情况下的俯视图,图1的(b)是钢管板桩的间隔小于设计的情况下的俯视图,图1的(c)是钢管板桩的间隔大于设计的情况下的俯视图。 Fig. 1 shows the structure of the connecting portion between a steel pipe sheet pile and a steel sheet pile according to an embodiment of the present invention, wherein Fig. 1(a) is a plan view without construction errors, and Fig. 1(b) is a steel pipe sheet pile The top view when the spacing is smaller than the design, and (c) in Figure 1 is the top view when the spacing of the steel pipe sheet piles is larger than the design.
图2的(a)、图2的(b)是分别表示设置于钢管板桩的连结构件的例子的俯视图。 (a) of FIG. 2 and (b) of FIG. 2 are plan views which each show the example of the connection member provided in the steel pipe sheet pile.
图3的(a)~图3的(d)是表示用于连结钢管板桩之间的钢板桩的俯视图,其中,图3的(a)是帽形钢板桩的情况,图3的(b)是直线形钢板桩的情况,图3的(c)是U形钢板桩的情况,图3的(d)是Z形钢板桩的情况。 Fig. 3(a) to Fig. 3(d) are plan views showing steel sheet piles for connecting between steel pipe sheet piles, wherein Fig. 3(a) is a hat-shaped steel sheet pile, and Fig. 3(b ) is a case of a linear steel sheet pile, (c) of FIG. 3 is a case of a U-shaped steel sheet pile, and (d) of FIG. 3 is a case of a Z-shaped steel sheet pile.
图4的(a)~图4的(c)是分别表示在钢板桩端部的连结部设置有止挡构件的情况下的例子的俯视图。 (a) of FIG. 4 - (c) of FIG. 4 is a top view which shows the example in the case where a stopper member was provided in the connection part of the steel sheet pile edge part, respectively.
图5的(a)、图5的(b)表示使钢板桩相对于钢管板桩偏心并连结于钢管板桩的情况下的结构的俯视图,其中,图5的(a)是帽形钢板桩的情况,图5的(b)是直线形钢板桩的情况。 Fig. 5(a) and Fig. 5(b) are plan views showing the structure in which the steel sheet pile is eccentric to the steel pipe sheet pile and connected to the steel pipe sheet pile, and Fig. 5(a) is a hat-shaped steel sheet pile The case of Fig. 5 (b) is the case of linear steel sheet piles.
图6的(a)~图6的(c)表示以往的通常的挡土结构的例子,其中,图6的(a)是自立式结构的剖视图,图6的(b)是锚定式结构的剖视图,图6的(c)是水平撑结构的立体图。 Figure 6(a) to Figure 6(c) show examples of conventional common soil retaining structures, wherein Figure 6(a) is a cross-sectional view of a self-supporting structure, and Figure 6(b) is an anchored structure As a cross-sectional view, (c) of FIG. 6 is a perspective view of the horizontal brace structure.
图7是表示以往的帽形钢板桩的形态的剖视图。 Fig. 7 is a cross-sectional view showing the form of a conventional hat-shaped steel sheet pile.
图8是表示以往的钢管板桩壁的一例的俯视图。 Fig. 8 is a plan view showing an example of a conventional steel pipe sheet pile wall.
图9表示由以往的钢管板桩与Z形钢板桩构成的连结壁结构的一例(非专利文献1所述的结构),其中,图9的(a)是连结壁结构的俯视图,图9的(b)是详细表示钢管板桩与Z形钢板桩的接头部分的俯视图。 Fig. 9 shows an example of a connecting wall structure composed of a conventional steel pipe sheet pile and a Z-shaped steel sheet pile (the structure described in Non-Patent Document 1), wherein (a) of Fig. 9 is a plan view of the connecting wall structure, and Fig. (b) is a plan view which shows the joint part of a steel pipe sheet pile and a Z-shaped steel sheet pile in detail.
图10是图1的实施方式的连结部中的应力分布的分析图。 FIG. 10 is an analysis diagram of the stress distribution in the connecting portion of the embodiment in FIG. 1 .
图11是对将连结构件的板厚t固定为11mm并将外径Φ设为100mm、125mm、165.2mm、200mm的情况下的、产生变形或运动时的载荷P与外径Φ的关系进行数值分析而表示的图形。 Figure 11 shows the relationship between the load P and the outer diameter Φ when deformation or movement occurs when the plate thickness t of the connecting member is fixed at 11 mm and the outer diameter Φ is set to 100 mm, 125 mm, 165.2 mm, and 200 mm. Graphics that represent numerical analysis.
图12是将本发明的连结部的结构替换为悬臂梁并进行模型化而成的图。 FIG. 12 is a modeled view in which the structure of the connecting portion of the present invention is replaced by a cantilever beam.
图13是表示利用图12的悬臂梁模型进行分析而求出的连结构件的板厚t与连结构件的直径Φ的关系的图形。 13 is a graph showing the relationship between the plate thickness t of the connecting member and the diameter Φ of the connecting member obtained by analysis using the cantilever beam model in FIG. 12 .
图14是表示将连结构件的外径Φ固定为200mm并将板厚设为11mm、14mm、16mm的情况下的、由接头部的FEM分析结果得出的板厚t与载荷P的关系的图形。 Fig. 14 is a graph showing the relationship between the plate thickness t and the load P obtained from the FEM analysis results of the joint part when the outer diameter Φ of the connecting member is fixed at 200 mm and the plate thickness is set to 11 mm, 14 mm, and 16 mm. graphics.
具体实施方式 Detailed ways
以下,根据附图说明本发明。另外,本发明并不限于以下所示的实施方式。 Hereinafter, the present invention will be described with reference to the drawings. In addition, this invention is not limited to embodiment shown below.
图1表示本发明的一实施方式的钢管板桩与钢板桩的连结部的结构,其中,图1的(a)是没有施工误差的情况下的俯视图,图1的(b)是钢管板桩的间隔小于设计的情况下的俯视图,图1的(c)是钢管板桩的间隔大于设计的情况下的俯视图。 Fig. 1 shows the structure of the connecting portion between a steel pipe sheet pile and a steel sheet pile according to an embodiment of the present invention, wherein Fig. 1(a) is a plan view without construction errors, and Fig. 1(b) is a steel pipe sheet pile The top view when the spacing is smaller than the design, and (c) in Figure 1 is the top view when the spacing of the steel pipe sheet piles is larger than the design.
本发明的连结壁结构是用于将钢管板桩1与钢板桩2连结起来的结构,在其连结部设有用于吸收施工误差的空间。即,在 由钢板桩2将隔开间隔地进行打桩的钢管板桩1彼此连结而形成连结壁结构时,通过在钢管板桩1的侧部设置具有在长度方向上连续的狭缝3a的连结构件3并从长度方向将钢板桩2的端部嵌合于狭缝3a部分,从而使连结构件3与钢板桩2的端部连结,在该连结构件3与钢板桩2的端部的连结部设有用于吸收钢管板桩1彼此的施工误差的游隙u。 The connection wall structure of this invention is a structure for connecting the steel pipe sheet pile 1 and the steel sheet pile 2, and the space for absorbing a construction error is provided in the connection part. That is, when the steel pipe sheet piles 1 piled at intervals are connected by the steel sheet piles 2 to form a connected wall structure, by providing the steel pipe sheet piles 1 side portions with continuous slits 3a in the longitudinal direction, The structural member 3 fits the end of the steel sheet pile 2 into the slit 3a part from the longitudinal direction, so that the connecting member 3 and the end of the steel sheet pile 2 are connected, and the connecting member 3 and the end of the steel sheet pile 2 A play u is provided for absorbing construction errors between the steel pipe sheet piles 1 at the connecting portion.
在钢管板桩1与钢板桩2的连结壁结构中,在不同的情况下,针对钢管板桩1、钢板桩2准备分别不同的施工机械来构筑壁结构。该情况下,考虑施工性而设想以下情况,即,首先对钢管板桩1进行打桩,之后对钢板桩2进行打桩,或者,首先对钢板桩2进行打桩,之后对钢管板桩1进行打桩。 In the connection wall structure of the steel pipe sheet pile 1 and the steel sheet pile 2, when different, the steel pipe sheet pile 1 and the steel sheet pile 2 prepare respectively different construction machines, and construct a wall structure. In this case, the case where the steel pipe sheet pile 1 is first piled and then the steel sheet pile 2 is piled, or the steel pipe sheet pile 2 is first piled and then the steel pipe sheet pile 1 is piled is assumed in consideration of workability.
此时,若钢管板桩1与钢板桩2的连结部的空间较小,则施工变得困难,在最坏的情况下,会担心打桩时由于连结部相互干涉而发生损伤或不能打桩。 At this time, if the space of the connecting portion of the steel pipe sheet pile 1 and the steel sheet pile 2 is small, construction becomes difficult, and in the worst case, there is a fear of damage or failure of pile driving due to mutual interference of the connecting portions during pile driving.
因此,如图1所示,通过在钢管板桩1与钢板桩2的连结部充分地确保与所允许的钢管板桩1彼此的施工误差相对应的空间,能够构筑施工性优异的钢管板桩1与钢板桩2的连结壁结构。另外,在该情况下,出于以较高的施工精度进行施工的目的,也可以一边使用模板来进行对位,一边进行施工。 Therefore, as shown in FIG. 1 , by sufficiently securing a space corresponding to allowable construction errors between the steel pipe sheet piles 1 at the connecting portion of the steel pipe sheet pile 1 and the steel sheet pile 2 , it is possible to construct a steel pipe sheet pile with excellent workability. 1 and the steel sheet pile 2 connection wall structure. In addition, in this case, for the purpose of carrying out construction with high construction precision, you may perform construction while performing alignment using a formwork.
即,通过在钢管板桩1与钢板桩2的连结部设置能够吸收施工误差的充分的空间,从而即使产生钢板桩2的施工打桩延长(参照图1的(b))、打桩收缩(参照图1的(c)),也能够容易地对钢板桩2的端部进行嵌合和设置。 That is, by providing a sufficient space capable of absorbing construction errors in the connecting portion of the steel pipe sheet pile 1 and the steel sheet pile 2, even if the construction of the steel sheet pile 2 is elongated (see (b) in FIG. (c)) of 1, the edge part of the steel sheet pile 2 can be fitted and installed easily.
对于钢管板桩1的连结构件,其并不受特别的限定,只要是为了确保施工性而能够确保充分的空间的构件即可,其例如是将在如图2所示的钢管中设有狭缝3a的构件3(参照图2的(a))、组合角钢43并在角钢43之间形成有狭缝43a的构件(参照图2的 (b))等。 The connecting member of the steel pipe sheet pile 1 is not particularly limited, as long as it is a member that can secure a sufficient space in order to ensure workability, it is, for example, a steel pipe as shown in FIG. A member 3 with a slit 3a (see (a) in FIG. 2 ), a member in which angle steels 43 are combined and a slit 43a is formed between the angle steels 43 (see (b) in FIG. 2 ), and the like.
并且,对于钢板桩,其形状也不受特别限定,只要能够与钢管板桩的连结构件嵌合即可,其例如是图3所示的帽形钢板桩2(参照图3的(a))、直线形钢板桩12(参照图3的(b))、U形钢板桩22(参照图3的(c))、Z形钢板桩32(参照图3的(d))等。 In addition, the shape of the steel sheet pile is not particularly limited, as long as it can be fitted with the connecting member of the steel pipe sheet pile, which is, for example, the hat-shaped steel sheet pile 2 shown in FIG. ), linear steel sheet pile 12 (see (b) of FIG. 3 ), U-shaped steel sheet pile 22 (see (c) of FIG. 3 ), Z-shaped steel sheet pile 32 (see (d) of FIG. 3 ), and the like.
其中,对于图3的(a)所示的、在接头部2b、2c的横向的臂部具有平坦的区间(平坦部2a)的帽形状的钢板桩2,其与通常使用的图3的(c)的U形钢板桩22相比,容易对与钢管板桩施工时的打桩延长、打桩收缩相对应的游隙u进行设定,施工性也优异。 Among them, the hat-shaped steel sheet pile 2 shown in (a) of FIG. 3 , which has a flat section (flat portion 2 a ) in the lateral arm portions of the joint portions 2 b and 2 c , is different from the ( Compared with the U-shaped steel sheet pile 22 of c), it is easy to set the play u corresponding to the piling extension and piling shrinkage during construction of the steel pipe sheet pile, and the workability is also excellent.
此处,以图1的结构(图3的(a)也相同)为例,说明连结构件3的优选形状。 Here, the preferable shape of the connection member 3 is demonstrated taking the structure of FIG. 1 as an example (it is the same in (a) of FIG. 3).
当连结构件3的直径过小时,其与钢板桩2的嵌合变得困难。连结构件3的内径优选为70mm以上。例如,在宽度为900mm的帽形钢板桩中,两端部具有长度大约为50mm的接头部2b、2c,若连结构件3的内径为70mm以上,则不需要过度的施工管理就能够容易地与钢板桩相嵌合。另一方面,从施工性的观点出发,连结构件3的外径优选为270mm以下。 When the diameter of the connection member 3 is too small, fitting with the steel sheet pile 2 becomes difficult. The inner diameter of the connecting member 3 is preferably 70 mm or more. For example, in a hat-shaped steel sheet pile with a width of 900mm, both ends have joints 2b and 2c with a length of about 50mm, and if the inner diameter of the connecting member 3 is 70mm or more, it can be easily installed without excessive construction management. Compatible with steel sheet piles. On the other hand, from the viewpoint of constructability, the outer diameter of the connecting member 3 is preferably 270 mm or less.
并且,图1的壁体的承载能力由钢板桩2的屈服或连结构件3的变形(参照图10)中的任何一个决定。即,在一个发生屈服或变形的情况下,另一个在强度上存在余量。因此,可以说使上述的屈服和变形基本上同时产生的条件(形状)的效率最高。以下,使用计算例来说明这种条件。 Moreover, the bearing capacity of the wall body of FIG. 1 is determined by yield of the steel sheet pile 2, or deformation|transformation (refer FIG. 10) of the connection member 3. That is, when one yields or deforms, the other has a margin in strength. Therefore, it can be said that the condition (shape) in which the above-mentioned yielding and deformation occur substantially simultaneously is the most efficient. Hereinafter, such a condition will be described using a calculation example.
图11表示对将连结构件3的板厚t固定为11mm并将外径Φ设为100mm、125mm、165.2mm、200mm时的、产生变形或运动时的载荷P与外径Φ的关系进行数值分析而求出的结果。在 该分析例中,将钢材的屈服应力设为相当于普通钢的σ=400N/mm2,而且,为了使连结构件3与钢板桩2在长度方向(在图10中来说,是与纸面垂直的方向)的全长(计算上,将1mm设为单位长度)上相嵌合,应用了双线性(biliner)的模型。 Fig. 11 shows numerical values of the relationship between the load P and the outer diameter Φ when deformation or movement occurs when the plate thickness t of the connecting member 3 is fixed at 11 mm and the outer diameter Φ is set to 100 mm, 125 mm, 165.2 mm, and 200 mm. The results obtained from the analysis. In this analysis example, the yield stress of the steel is set to σ=400N/mm 2 equivalent to ordinary steel, and in order to make the connection member 3 and the steel sheet pile 2 in the A bilinear (biliner) model is applied to the overall length (in terms of calculation, 1mm is set as the unit length) in the direction perpendicular to the paper surface.
在图11中,在外径Φ为125mm的前后,直线的斜率发生变化。这示出了在达到载荷P时的上述变形或运动在外径Φ为125mm的前后变得不同,具体而言,这示出了:在Φ<125mm处,主要是钢板桩2发生屈服,在Φ>125mm处,主要是连结构件3发生变形。 In FIG. 11 , the slope of the straight line changes before and after the outer diameter Φ is 125 mm. This shows that the above-mentioned deformation or motion when the load P is reached becomes different before and after the outer diameter Φ is 125mm. Specifically, it shows that at Φ<125mm, the steel sheet pile 2 mainly yields, and at Φ > 125mm, mainly because the connecting member 3 is deformed.
接着,求出图11那样的斜率变化点处的连结构件3的外径Φ与板厚t的关系。此处,对于连结部的结构,为了简化,设想在图12那样的悬臂梁(长度为L,进深方向长度为b,板厚为t)的顶端施加有载荷P的模型。另外,严密地说,长度L表示从连结构件3与钢管板桩1的钢管主体被固定的部位到载荷作用于连结构件3的狭缝3a的部位的长度,但是,此处,为了简化,将该长度L等同为连结构件3的外径而进行了研究。 Next, the relationship between the outer diameter Φ of the connecting member 3 and the plate thickness t at the slope change point as shown in FIG. 11 is obtained. Here, in order to simplify the structure of the connection part, assume a model in which a load P is applied to the tip of a cantilever beam (length L, depth direction length b, plate thickness t) as shown in FIG. 12 . Strictly speaking, the length L represents the length from the portion where the connecting member 3 and the steel pipe body of the steel pipe sheet pile 1 are fixed to the portion where the load acts on the slit 3a of the connecting member 3, but here, for the sake of simplification, , this length L was considered as the outer diameter of the connecting member 3 .
在该模型中,梁的固定端发生的弯曲力矩M、梁的截面刚性I及梁产生的应力σ分别由式(a)~式(c)表示。 In this model, the bending moment M occurring at the fixed end of the beam, the section rigidity I of the beam, and the stress σ generated by the beam are represented by formulas (a) to (c) respectively.
数学式(3) Mathematical formula (3)
M=P·L ···(a) M=P·L···(a)
数学式(4) Mathematical formula (4)
数学式(5) Mathematical formula (5)
其中,b是进深方向长度, Among them, b is the length in the depth direction,
t是梁(连结构件3)的板厚, t is the plate thickness of the beam (connecting member 3),
Y是从中性轴(neutral axis)到梁端的距离即t/2。 Y is the distance from the neutral axis to the end of the beam, t/2.
此处,在将板桩达到屈服的作用载荷设为Py时,板桩发生屈服时作用于单侧的梁的载荷为Py/2。此处,上述斜率变化点是梁(连结构件)与板桩发生同时变形/屈服的条件,即,其是在载荷Py/2作用于梁时、梁的应力达到屈服应力σy的条件。因此,在将上述条件代入式(c)中进行变形时,得到数学式(6)。 Here, when the applied load for the sheet pile to yield is P y , the load acting on the beam on one side when the sheet pile yields is P y /2. Here, the above-mentioned slope change point is the condition for simultaneous deformation/yielding of the beam (connected structural member) and the sheet pile, that is, it is the condition for the stress of the beam to reach the yield stress σ y when the load P y /2 is applied to the beam . Therefore, when the above conditions are substituted into the formula (c) and modified, the mathematical formula (6) is obtained.
数学式(6) Mathematical formula (6)
并且,根据由上述悬臂梁模型导出的式(d),将梁的长度L替换为连结构件3的外径Φ(即,下述式(2)’),并验证将该式应用于图1的结构时的准确性。 And, according to the formula (d) derived from the above cantilever beam model, the length L of the beam is replaced by the outer diameter Φ of the connecting member 3 (that is, the following formula (2)'), and the application of this formula to Fig. 1 when the structure is accurate.
数学式(7) Mathematical formula (7)
其中,Φ是连结构件3的外径, Wherein, Φ is the outer diameter of the connecting member 3,
t是连结构件3的板厚, t is the plate thickness of the connecting member 3,
σy是连结构件3所用的钢材的屈服应力, σy is the yield stress of the steel used in the connecting member 3,
Py是使钢板桩2达到屈服的作用载荷, Py is the applied load to make the steel sheet pile 2 yield,
b是连结构件3与钢板桩2相嵌合的长度方向的长度。 b is the length of the longitudinal direction in which the connection member 3 and the steel sheet pile 2 are fitted.
图11中的斜率变化点处的作用载荷Py为Py=0.125(kN/mm)。而且,在将进深长度b设为b=1(mm)并将连结构件所用的钢材的屈服应力σy设为如上所述设想为普通钢的情况下的σy=400(N/mm2),在将上述条件代入式(2)’时,得到下述关系。即, The applied load Py at the slope change point in FIG. 11 is Py=0.125 (kN/mm). Furthermore, assuming that the depth b is b=1 (mm) and the yield stress σy of the steel material used for the connecting member is σy=400 (N/mm 2 ) when it is assumed that ordinary steel is used as described above, When the above conditions are substituted into the formula (2)', the following relationship is obtained. Right now,
数学式(8) Mathematical formula (8)
在将t=11(mm)代入式(2)”时,Φ≈129.5(mm),这与由FEM分析得出的解、即Φ=125mm非常高度地一致(参照图13)。 When t=11(mm) is substituted into the formula (2), Φ≈129.5(mm), which is very highly consistent with the solution obtained from FEM analysis, that is, Φ=125mm (see FIG. 13 ).
并且,作为其他的验证,进行了在将连结构件3的外径固定为Φ=200mm、将板厚设为Φ=200mm并将板厚设为11mm、14mm、16mm时的FEM分析。将其结果表示在图14中。根据图14可知,在板厚为14mm的前后处,直线的斜率发生变化。另一方面,根据式(2)”,在代入Φ=200mm时的板厚t为t≈13.7mm,该例子也与利用FEM分析而求出的斜率变化点非常高度地一致。 Furthermore, as another verification, FEM analysis was performed when the outer diameter of the connecting member 3 was fixed at Φ=200 mm, the plate thickness was Φ=200 mm, and the plate thicknesses were 11 mm, 14 mm, and 16 mm. The results are shown in FIG. 14 . From FIG. 14 , it can be seen that the slope of the straight line changes before and after the plate thickness is 14 mm. On the other hand, from Equation (2)", the plate thickness t when Φ=200mm is substituted is t≈13.7mm, and this example also agrees very highly with the slope change point obtained by FEM analysis.
对于实际的钢管板桩1,在进行连结构件3的加工时、安装 时,考虑到连结构件3的直径、狭缝宽度或焊接等存在一定程度的偏差。优选将钢管板桩1设为连结构件3的板厚t与斜率变化点的板厚同等或大于斜率变化点的板厚的结构、即满足式(2)的结构。 For the actual steel pipe sheet pile 1, when processing and installing the connecting member 3, it is considered that there is a certain degree of deviation in the diameter, slit width or welding of the connecting member 3. Preferably, the steel pipe sheet pile 1 is a structure in which the plate thickness t of the connecting member 3 is equal to or greater than the plate thickness at the slope change point, that is, a structure that satisfies the formula (2).
数学式(9) Mathematical formula (9)
另外,钢板桩构件的长度不必为与钢管板桩1相同的长度,其也可以短于钢管板桩1的长度,作为壁,其只要具有壁高以上的长度而使背面土不会流出即可。 In addition, the length of the steel sheet pile member does not have to be the same as that of the steel pipe sheet pile 1, and may be shorter than the length of the steel pipe sheet pile 1. As a wall, it only needs to have a length greater than the wall height so that the soil on the back side does not flow out. .
并且,在期望壁构造物具有止水功能的情况下,通常向连结部填充止水材料并实施止水处理。此处,在连结部的空间狭小的情况下,由于止水材料的填充困难而不能充分地进行填充,因而,会担心不能充分地发挥止水功能。 And, when it is desired that the wall structure has a water-stopping function, usually, a water-stopping material is filled into the connecting portion and a water-stopping treatment is performed. Here, when the space of the connecting portion is narrow, filling of the water-stop material is difficult and cannot be sufficiently filled, so there is a concern that the water-stop function cannot be sufficiently exhibited.
因此,为了在钢管板桩1与钢板桩2的连结部填充止水材料而形成为设有充分的空间的连结壁结构,从而能够期待充分的止水功能,并且,能够减低止水处理的施工成本、劳力和时间。 Therefore, in order to fill the connection portion of the steel pipe sheet pile 1 and the steel sheet pile 2 with a connection wall structure with a sufficient space for filling the connection portion of the steel pipe sheet pile 1 and the steel sheet pile 2, a sufficient water sealing function can be expected, and the construction of water sealing treatment can be reduced. cost, labor and time.
作为止水处理,存在以下方法,即,在对壁进行设置后,以喷水方法等挖掘连结部,向内部填充灰浆、止水材料。因此,作为钢管板桩与钢板桩的连结部的空间,最好为能够利用喷水方法进行挖掘的大小。 As the water-stopping treatment, there is a method of digging the connecting portion with a water spray method or the like after installing the wall, and filling the inside with mortar and a water-stopping material. Therefore, as the space of the connection part of a steel pipe sheet pile and a steel sheet pile, it is preferable that it is the size which can excavate by the water jet method.
作为钢管板桩1的连结构件3的一例,存在如图2的(a)所示那样的、在通常使用的直径为Φ165.2mm的钢管中设有大约30mm的狭缝3a的钢管型连结构件,通过应用该钢管型连结构件,从而即使在与钢板桩2连结后,也能够充分地填充止水用的填充材料。 As an example of the connecting member 3 of the steel pipe sheet pile 1, there is a steel pipe type connecting member in which a generally used steel pipe with a diameter of Φ165.2 mm is provided with a slit 3 a of about 30 mm, as shown in FIG. 2( a ). By applying this steel pipe-type connecting member to the structural member, even after the steel sheet pile 2 is connected, the filling material for water stop can be sufficiently filled.
通过在钢管板桩1与钢板桩2的连结部设置充分大的空间,从而提高了打桩性、止水处理的作业性,但是,在空间过于大时,会担心打桩时连结部脱离。 By providing a sufficiently large space at the connecting portion of the steel pipe sheet pile 1 and the steel sheet pile 2, the piling performance and the workability of the water stop treatment are improved. However, if the space is too large, there is a concern that the connecting portion will come off during pile driving.
因此,如图4的(a)~图4的(c)所示,通过在钢板桩2的接头部2c(爪部)设置止挡构件4,从而能够防止该钢板桩2的接头部2c从钢管板桩1的连结部脱离。 Therefore, as shown in (a) to (c) of FIG. The connecting portion of the steel pipe sheet pile 1 is separated.
作为此时的止挡构件4,考虑使用圆钢、异形棒钢、扁钢等,也可以使用这以外的构件,并不特别限定。此外,不必在钢板桩2的长度方向整个全长上设置止挡构件4,通过对止挡构件4进行离散配置,从而能够抑制加工成本、构件设置时产生的钢板桩2的变形量等。 As the stopper member 4 at this time, it is conceivable to use round steel, deformed bar steel, flat steel, etc., but members other than these can also be used, and it is not particularly limited. Moreover, it is not necessary to provide the stopper member 4 over the entire length in the longitudinal direction of the steel sheet pile 2, and by disposing the stopper member 4 discretely, it is possible to suppress processing cost, deformation amount of the steel sheet pile 2 that occurs during member installation, and the like.
由于图5的(a)表示使帽形钢板桩2相对于钢管板桩1偏心并连结于钢管板桩1的情况,通过使钢板桩2的位置从钢管板桩1的中心轴线偏心并使作为壁的面对齐,在壁前面设置装饰板的情况下等,提高了施工性。 Since (a) of FIG. 5 shows the case where the hat-shaped steel sheet pile 2 is eccentrically connected to the steel pipe sheet pile 1 and connected to the steel pipe sheet pile 1, by making the position of the steel sheet pile 2 eccentric from the central axis of the The face of the wall is aligned, and when a decorative board is installed in front of the wall, etc., the workability is improved.
同样,图5的(b)表示使直线形钢板桩12相对于钢管板桩1偏心并连结于钢管板桩1的情况。 Similarly, (b) of FIG. 5 shows the case where the linear steel sheet pile 12 is eccentrically connected to the steel pipe sheet pile 1 with respect to the steel pipe sheet pile 1 .
附图标记说明Explanation of reference signs
1、钢管板桩;2、钢板桩(帽形钢板桩);2a、平坦部;2b、2c、接头部;3、连结构件;3a、狭缝;4、止挡构件;12、直线形钢板桩;12b、接头部;22、U形钢板桩;22b、接头部;32、Z形钢板桩;32b、32c、接头部;33、接头构件;43、角钢;43a、狭缝;u、游隙。 1. Steel pipe sheet pile; 2. Steel sheet pile (hat-shaped steel sheet pile); 2a, flat part; 2b, 2c, joint part; 3. Connecting member; 3a, slit; 4. Stop member; 12. Linear Steel sheet pile; 12b, joint part; 22, U-shaped steel sheet pile; 22b, joint part; 32, Z-shaped steel sheet pile; 32b, 32c, joint part; 33, joint member; 43, angle steel; 43a, slit; u, clearance.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410602239.6A CN104404915B (en) | 2010-04-01 | 2011-01-12 | The cross section defining method of coupling member |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010084944 | 2010-04-01 | ||
JP2010-084944 | 2010-04-01 | ||
PCT/JP2011/050312 WO2011125347A1 (en) | 2010-04-01 | 2011-01-12 | Connected wall structure consisting of steel pipe sheet piles and steel sheet pile, and method of constructing same |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410602239.6A Division CN104404915B (en) | 2010-04-01 | 2011-01-12 | The cross section defining method of coupling member |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102713074A CN102713074A (en) | 2012-10-03 |
CN102713074B true CN102713074B (en) | 2015-03-25 |
Family
ID=44762314
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410602239.6A Active CN104404915B (en) | 2010-04-01 | 2011-01-12 | The cross section defining method of coupling member |
CN201180005274.4A Expired - Fee Related CN102713074B (en) | 2010-04-01 | 2011-01-12 | Connected wall structure consisting of steel pipe sheet piles and steel sheet pile, and method of constructing same |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410602239.6A Active CN104404915B (en) | 2010-04-01 | 2011-01-12 | The cross section defining method of coupling member |
Country Status (6)
Country | Link |
---|---|
EP (1) | EP2554751A4 (en) |
JP (1) | JP4998646B2 (en) |
CN (2) | CN104404915B (en) |
MY (1) | MY164688A (en) |
TW (1) | TWI448608B (en) |
WO (1) | WO2011125347A1 (en) |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5633502B2 (en) * | 2011-11-28 | 2014-12-03 | 新日鐵住金株式会社 | Wall structure |
US11053655B2 (en) * | 2013-09-03 | 2021-07-06 | Lawrence S. Maxwell | Modular grid foundation |
CN104120699B (en) * | 2014-05-20 | 2016-04-27 | 中交第二航务工程局有限公司 | Steel sheet pile bucket base man-made island dado structure |
JP6394180B2 (en) * | 2014-08-26 | 2018-09-26 | 新日鐵住金株式会社 | Steel pipe sheet pile joint structure |
JP6690118B2 (en) * | 2014-12-11 | 2020-04-28 | 日本製鉄株式会社 | Retaining wall |
CN106836126A (en) * | 2016-12-07 | 2017-06-13 | 孟展 | New water and soil conservation protecting tube |
CN208280125U (en) * | 2017-09-22 | 2018-12-25 | 震东机械设备有限公司 | interlock system |
CN108149673B (en) * | 2018-02-01 | 2024-02-20 | 刘德奇 | Concrete pile and continuous seepage-proofing water-stop wall spliced by adopting same |
CN109763455B (en) * | 2018-12-29 | 2024-04-09 | 中交水运规划设计院有限公司 | Permeable breakwater |
CN109610476B (en) * | 2019-01-31 | 2024-05-17 | 上海宝钢工程咨询有限公司 | Steel pipe Larson sheet pile precipitation building envelope |
CN109736347B (en) * | 2019-03-28 | 2021-02-12 | 中交第一航务工程局有限公司 | Construction process of underwater foundation trench mud-blocking wall |
CN113789796A (en) * | 2021-07-05 | 2021-12-14 | 长沙理工大学 | Construction method of steel sheet pile cofferdam in high flow velocity sand and gravel area |
CN114837194A (en) * | 2022-05-15 | 2022-08-02 | 中冶建工集团有限公司 | Construction method for improving stability of PC (polycarbonate) composite pile |
CN115419090A (en) * | 2022-09-03 | 2022-12-02 | 无锡大诚建设有限公司 | Steel sheet pile cofferdam of stable in structure |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB190914951A (en) * | 1909-06-26 | 1910-01-27 | Richard Henry Annison | Improvements in Locking Bars and Sheeting for Constructional Work. |
CN2275119Y (en) * | 1996-08-29 | 1998-02-25 | 湖南省公路桥梁建设总公司 | Tongue-and-groove steel pipe pile |
JP2000136532A (en) * | 1998-10-30 | 2000-05-16 | Nippon Steel Corp | Rotary press-fitting sheet pile and method of constructing rotary press-fitting sheet pile |
JP2002129550A (en) * | 2000-10-20 | 2002-05-09 | Nkk Corp | Underground pillar row wall member and underground pillar row wall construction method |
CN1837512A (en) * | 2006-04-07 | 2006-09-27 | 上海市政工程设计研究总院 | Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same |
CN201428137Y (en) * | 2009-07-03 | 2010-03-24 | 东南大学 | A waterproof sheet pile cofferdam |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57133919A (en) * | 1981-02-13 | 1982-08-18 | Kajima Corp | Construction of underground continuous wall |
JPS5989120U (en) * | 1982-12-02 | 1984-06-16 | 住友金属工業株式会社 | Seawall made of steel pipes and arcuate steel plates |
DE3615601C1 (en) * | 1986-05-09 | 1987-08-06 | Strabag Bau Ag | Pipe support screed for a combined sheet pile |
JPH0757940B2 (en) * | 1988-06-21 | 1995-06-21 | 川崎製鉄株式会社 | Revetment method using π type steel sheet pile |
JPH0621443B2 (en) * | 1989-02-14 | 1994-03-23 | 東亜建設工業株式会社 | Breakwater using steel pipe sheet pile and straight sheet pile |
JP4542290B2 (en) * | 2001-08-31 | 2010-09-08 | 新日本製鐵株式会社 | Rehabilitation revetment structure and rehabilitation method of aging sheet pile revetment |
JP4231429B2 (en) | 2003-02-19 | 2009-02-25 | 新日本製鐵株式会社 | Connection structure for deformed wall components |
-
2011
- 2011-01-12 MY MYPI2012700454A patent/MY164688A/en unknown
- 2011-01-12 CN CN201410602239.6A patent/CN104404915B/en active Active
- 2011-01-12 EP EP11765249.5A patent/EP2554751A4/en not_active Withdrawn
- 2011-01-12 CN CN201180005274.4A patent/CN102713074B/en not_active Expired - Fee Related
- 2011-01-12 JP JP2011545518A patent/JP4998646B2/en not_active Expired - Fee Related
- 2011-01-12 WO PCT/JP2011/050312 patent/WO2011125347A1/en active Application Filing
- 2011-02-10 TW TW100104403A patent/TWI448608B/en not_active IP Right Cessation
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB190914951A (en) * | 1909-06-26 | 1910-01-27 | Richard Henry Annison | Improvements in Locking Bars and Sheeting for Constructional Work. |
CN2275119Y (en) * | 1996-08-29 | 1998-02-25 | 湖南省公路桥梁建设总公司 | Tongue-and-groove steel pipe pile |
JP2000136532A (en) * | 1998-10-30 | 2000-05-16 | Nippon Steel Corp | Rotary press-fitting sheet pile and method of constructing rotary press-fitting sheet pile |
JP2002129550A (en) * | 2000-10-20 | 2002-05-09 | Nkk Corp | Underground pillar row wall member and underground pillar row wall construction method |
CN1837512A (en) * | 2006-04-07 | 2006-09-27 | 上海市政工程设计研究总院 | Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same |
CN201428137Y (en) * | 2009-07-03 | 2010-03-24 | 东南大学 | A waterproof sheet pile cofferdam |
Also Published As
Publication number | Publication date |
---|---|
HK1171483A1 (en) | 2013-03-28 |
EP2554751A4 (en) | 2017-01-11 |
TW201139792A (en) | 2011-11-16 |
JPWO2011125347A1 (en) | 2013-07-08 |
MY164688A (en) | 2018-01-30 |
TWI448608B (en) | 2014-08-11 |
CN102713074A (en) | 2012-10-03 |
EP2554751A1 (en) | 2013-02-06 |
WO2011125347A1 (en) | 2011-10-13 |
JP4998646B2 (en) | 2012-08-15 |
CN104404915B (en) | 2016-01-20 |
CN104404915A (en) | 2015-03-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102713074B (en) | Connected wall structure consisting of steel pipe sheet piles and steel sheet pile, and method of constructing same | |
JP3747198B2 (en) | Steel pipe sheet pile foundation | |
KR20100068597A (en) | A shoring method using arch plate pile and h-pile | |
JP2013136922A (en) | Earth retaining wall supporting method, earth retaining wall supporting structure, and underground skeleton constructing method | |
JP4450240B2 (en) | Joining structure of mountain retaining H-shaped steel pile and its joining method | |
JP3701280B2 (en) | Yamadome support | |
EP2848739A1 (en) | Steel wall | |
JP6642977B2 (en) | Pile foundation structure | |
JP6650257B2 (en) | Mountain retaining structure and construction method thereof | |
JP4812324B2 (en) | Retaining wall and its construction method | |
JP2013159913A (en) | Joint part for steel pipe sheet pile to be used for steel pipe sheet pile method | |
JP2013015015A (en) | Structure and construction method for earth retaining wall | |
JP2018188874A (en) | Earth retaining structure and construction method | |
JP2013177787A (en) | Method for constructing steel pipe sheet pile foundation | |
JP6477586B2 (en) | Steel sheet pile wall | |
JP5939622B2 (en) | Retaining wall | |
JP5637657B2 (en) | Retaining wall and its reinforcement method | |
KR101262631B1 (en) | Prefab type land-side protection wall device | |
JP4724680B2 (en) | Column base structure | |
JP5582104B2 (en) | Underground wall structure | |
JP2021021225A (en) | Support structure of earth-retaining wall and support method of earth-retaining wall | |
JP2987371B2 (en) | Underground diaphragm wall | |
JP6515290B2 (en) | Seismic quay structure | |
JP7551456B2 (en) | How to build an earth retaining structure | |
KR102603493B1 (en) | Cap module-based column wall for building foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
REG | Reference to a national code |
Ref country code: HK Ref legal event code: DE Ref document number: 1171483 Country of ref document: HK |
|
ASS | Succession or assignment of patent right |
Owner name: NIPPON STEEL + SUMITOMO METAL CORPORATION Free format text: FORMER OWNER: CHUGAI SEIYAKU KABUSHIKI KAISHA Effective date: 20130426 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20130426 Address after: Tokyo, Japan, Japan Applicant after: Nippon Steel Corporation Address before: Osaka Japan Applicant before: Sumitomo Metal Industries Ltd. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
REG | Reference to a national code |
Ref country code: HK Ref legal event code: GR Ref document number: 1171483 Country of ref document: HK |
|
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: Tokyo, Japan, Japan Patentee after: Nippon Iron & Steel Corporation Address before: Tokyo, Japan, Japan Patentee before: Nippon Steel Corporation |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150325 Termination date: 20210112 |
|
CF01 | Termination of patent right due to non-payment of annual fee |