CN102536297A - Cold conveying system of mine air-conditioning and working method of cold conveying system - Google Patents
Cold conveying system of mine air-conditioning and working method of cold conveying system Download PDFInfo
- Publication number
- CN102536297A CN102536297A CN2012100487333A CN201210048733A CN102536297A CN 102536297 A CN102536297 A CN 102536297A CN 2012100487333 A CN2012100487333 A CN 2012100487333A CN 201210048733 A CN201210048733 A CN 201210048733A CN 102536297 A CN102536297 A CN 102536297A
- Authority
- CN
- China
- Prior art keywords
- cold
- heat exchanger
- cooling
- cold water
- refrigerant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Other Air-Conditioning Systems (AREA)
Abstract
本发明公开了一种矿井空调输冷系统及其工作方法,它包括布置在地面的制冷设备、布置在井下的换热器和布置在井下降温工作点的空冷器,地面制冷设备的蒸发器与井下换热器通过管道形成一个封闭的循环系统,循环系统中充有制冷剂,称为制冷剂循环系统;井下换热器与空冷器通过管道和循环泵形成一个封闭的循环系统,循环系统中充有冷水,称为冷水循环系统。通过上述输冷系统实现井下工作点的降温。本发明系统实现了矿井空调输冷系统能耗低、降温效果好和成本低的目的。
The invention discloses a mine air-conditioning cold delivery system and its working method, which comprises refrigeration equipment arranged on the ground, a heat exchanger arranged in the underground, an air cooler arranged at the cooling working point of the well, the evaporator of the ground refrigeration equipment and the The downhole heat exchanger forms a closed circulation system through pipelines, and the circulation system is filled with refrigerant, which is called a refrigerant circulation system; the downhole heat exchanger and air cooler form a closed circulation system through pipelines and circulation pumps, and the circulation system Filled with cold water, called cold water circulation system. The cooling of the downhole working point is realized through the cooling system mentioned above. The system of the invention realizes the objectives of low energy consumption, good cooling effect and low cost of the mine air-conditioning cooling system.
Description
技术领域 technical field
本发明涉及一矿井空调输冷系统,特别是矿井立井筒内利用制冷剂循环来输送冷量的系统及方法。The invention relates to a mine air-conditioning cold delivery system, in particular to a system and a method for transporting cold energy by refrigerant circulation in a mine vertical shaft.
背景技术 Background technique
目前,我国煤矿开采深度大多在800m以上且逐渐增加,综合机械化程度不断提高,地热和井下设备向井下空气散发的热量显著增加;而从岩石裂隙中涌出的热水或与热水接触的高温围岩放热,不但使矿内气温升高,而且造成湿度增大;矿内高温、高湿环境严重影响井下作业人员的身体健康和生产效率,已造成灾害——热害。矿井热害最终将成为制约矿物开采深度的决定性因素,因此,必须利用矿井空调来实现井下降温除湿以消除井下热害。At present, the mining depth of coal mines in my country is mostly above 800m and is gradually increasing. The degree of comprehensive mechanization continues to increase, and the heat emitted from geothermal heat and underground equipment to the underground air has increased significantly. The heat release of surrounding rocks not only increases the temperature in the mine, but also increases the humidity; the high temperature and high humidity environment in the mine seriously affects the health and production efficiency of underground workers, and has caused disasters - heat damage. Mine heat damage will eventually become the decisive factor restricting the depth of mineral mining. Therefore, mine air conditioners must be used to reduce the temperature and dehumidify the mine to eliminate underground heat damage.
目前,矿井空调的制冷设备可以布置于井下及地面。当制冷设备放置于井下时,需要开挖专门的大型设备硐室,同时要求制冷设备满足煤矿井下防爆标准、设备紧凑化及极高的可靠性,普通技术成熟的制冷设备无法满足这些要求,而且制冷设备放置于井下还有一关键问题是制冷机排热不畅,极大降低了制冷机的制冷系数(cop)。At present, the refrigeration equipment of mine air conditioners can be arranged underground and on the ground. When the refrigeration equipment is placed underground, it is necessary to excavate a special large-scale equipment chamber. At the same time, the refrigeration equipment is required to meet the coal mine explosion-proof standards, compact equipment and high reliability. Commonly mature refrigeration equipment cannot meet these requirements, and Another key problem when the refrigeration equipment is placed underground is that the refrigerator does not discharge heat smoothly, which greatly reduces the refrigeration coefficient (cop) of the refrigerator.
所以目前制冷设备一般布置于地面,在地面可选用普通制冷机,制冷系数高,减小制冷耗电量,运行管理及设备维修方便,冷量输送有冷风输送式、冷水输送式、冰输送式。上述三种冷量输送方式系统布置形式及存在的不足是:Therefore, at present, refrigeration equipment is generally arranged on the ground, and ordinary refrigerators can be used on the ground, which have a high cooling coefficient, reduce cooling power consumption, and facilitate operation management and equipment maintenance. . The system layout and existing deficiencies of the above three cold delivery methods are:
1、冷风输送式:1. Cold air conveying type:
冷风输送式系统布置形式是:将制冷风设备和空冷器布置在地面,用风管将冷风送到井下降温工作点。存在的不足,一是由于风量及风管尺寸过大,存在安装不便及输送能耗偏高的不足;二是冷量损失大,降温效果差;三是输送到井下的风需要靠矿井风机抽放到井上,增加了矿井风机电耗。The layout form of the cold air conveying system is: arrange the cooling air equipment and the air cooler on the ground, and use the air pipe to send the cold air to the downhole cooling working point. The existing deficiencies are: first, due to the large air volume and air duct size, there are inconvenient installation and high energy consumption; second, the loss of cooling capacity is large, and the cooling effect is poor; third, the wind transported underground needs to be pumped by mine fans. Putting it on the well will increase the power consumption of the mine fan.
2、冰输送式:2. Ice conveying type:
冰输送式系统布置形式是:将制冰设备布置在地面,将地面制取的冰用输冰管道送到井下降温工作点,吸收热量降温,存在的不足,一是由于需要制冷机降低蒸发温度(低于-5℃)来制冰,所以降低了制冷机的制冷系数(COP),存在制冰、输冰系统设备复杂;二是碎冰在输送过程中易堵塞输冰管道的不足,三是输送到井下的冰溶化成水后需用水泵排到井上,造成水源浪费,大大提高了降温成本。The layout form of the ice conveying system is: the ice making equipment is arranged on the ground, and the ice produced on the ground is sent to the cooling point in the well through the ice delivery pipeline to absorb heat and cool down. (lower than -5°C) to make ice, so the cooling coefficient (COP) of the refrigerator is reduced, and there are complicated ice making and ice delivery system equipment; second, the crushed ice is easy to block the ice delivery pipeline during the delivery process; After the ice transported to the underground is melted into water, it needs to be drained to the well by a water pump, which causes waste of water and greatly increases the cost of cooling.
3、冷水输送式:3. Cold water conveying type:
冷水输送式系统布置形式是:在地面布置制冷水设备和换热器,在井下降温工作点设置空冷器,将井上制取的冷水通过冷水循环管道与空冷器接通,冷水循环使空冷器散发冷气,从空冷器出来的水再回到换热器换热后进入制冷水设备,相比冷风输送可减小管道直径。但也存在以下不足:一是由于冷水管道在深度达800m以上的矿井立井筒内,水静压力过大,常规管道难以承受;二是由于水静压力过大,需要设置专门的高低压转换器或者高压换热器,此类设备主要依靠于国外进口,费用昂贵;所以这种方式不可取,不能大面积推广。三是冷水在循环过程中需要高压水泵进行循环,增加了降温成本。The layout of the cold water delivery system is as follows: arrange cooling water equipment and heat exchangers on the ground, install an air cooler at the cooling point of the well, connect the cold water produced on the well with the air cooler through the cold water circulation pipeline, and circulate the cold water to make the air cooler For cold air, the water coming out of the air cooler returns to the heat exchanger for heat exchange and then enters the cooling water equipment. Compared with cold air delivery, the pipe diameter can be reduced. But there are also the following deficiencies: First, because the cold water pipeline is in the mine shaft with a depth of more than 800m, the hydrostatic pressure is too large for conventional pipelines; Or high-pressure heat exchangers, such equipment is mainly imported from abroad, which is expensive; so this method is not advisable and cannot be promoted on a large scale. The third is that the cold water needs a high-pressure water pump to circulate during the circulation process, which increases the cost of cooling.
发明内容 Contents of the invention
本发明的目的是克服现有矿井空调输冷系统存在能耗高、降温效果差和成本偏高的技术缺陷,提供一种新的矿井空调输冷系统及方法。The purpose of the present invention is to overcome the technical defects of high energy consumption, poor cooling effect and high cost in the existing mine air-conditioning cooling system, and provide a new mine air-conditioning cooling system and method.
为实现上述目的,本发明采取的技术方案及其工作原理:In order to achieve the above object, the technical scheme and working principle thereof taken by the present invention:
一种矿井空调输冷系统,它包括制冷设备、换热器和空冷器,其特征在于,所述的制冷设备布置在地面,换热器布置在井下,空冷器布置在井下降温工作点;地面制冷设备的蒸发器与井下换热器通过管道形成一个封闭的循环系统,循环系统中充有制冷剂,称为制冷剂循环系统;井下换热器与空冷器通过管道和循环泵形成一个封闭的循环系统,循环系统中充有冷水,称为冷水循环系统。A mine air-conditioning cooling system, which includes refrigeration equipment, heat exchangers and air coolers, characterized in that the refrigeration equipment is arranged on the ground, the heat exchanger is arranged underground, and the air cooler is arranged at the cooling working point of the mine; The evaporator of the refrigeration equipment and the downhole heat exchanger form a closed circulation system through the pipeline, and the circulation system is filled with refrigerant, which is called the refrigerant circulation system; the downhole heat exchanger and the air cooler form a closed circulation system through the pipeline and the circulation pump. The circulatory system, which is filled with cold water, is called a cold water circulatory system.
上述制冷剂优选氟利昂和氨。The above-mentioned refrigerants are preferably Freon and ammonia.
该系统的工作方法是:开启地面制冷设备,制冷剂通过制冷剂进程管道进入井下换热器管程,与换热器壳程中的冷水进行冷热交换发生液-气相变,从而蒸发变为气态,气态制冷剂在蒸发压力作用下,经制冷剂回程管道自动上升至地面制冷设备的蒸发器内,在制冷设备的制冷作用下发生气-液相变成为液态制冷剂,液态制冷剂在重力作用下携带冷量经制冷剂进程管道输送至井下换热器,重新蒸发为气态制冷剂,以此循环流动实现冷量向井下换热器自动输送;同时开启井下冷水循环泵,将换热器冷水输送到空冷器,以此循环流动实现工作点的降温。The working method of the system is: turn on the ground refrigeration equipment, the refrigerant enters the tube side of the downhole heat exchanger through the refrigerant process pipe, exchanges heat with the cold water in the shell side of the heat exchanger, and undergoes a liquid-gas phase change, thereby evaporating into Gas state, under the action of evaporation pressure, the gaseous refrigerant automatically rises to the evaporator of the ground refrigeration equipment through the refrigerant return pipeline, and the gas-liquid phase changes into a liquid refrigerant under the cooling action of the refrigeration equipment. Under the action of gravity, the cold energy carried is transported to the downhole heat exchanger through the refrigerant process pipeline, where it is re-evaporated into a gaseous refrigerant, and the circulating flow realizes the automatic delivery of cold energy to the downhole heat exchanger; at the same time, the underground cold water circulation pump is turned on to transfer the heat The cold water of the device is sent to the air cooler, and the circulating flow realizes the cooling of the working point.
本发明由于采取以上技术方案,具有以下优点:The present invention has the following advantages due to the adoption of the above technical scheme:
1、由于采用制冷剂循环来实现冷量输送,冷量传输依靠制冷剂相变过程,单位质量流量的制冷剂其冷量输送能力远大于冷风、冷水的输送方式,因此输送相同冷量时,制冷剂循环流量远小于冷风及冷水的流量,液态制冷剂管道管径远小于冷水管径。1. Due to the use of refrigerant circulation to realize cold delivery, the cold delivery depends on the phase change process of the refrigerant. The cooling delivery capacity of the refrigerant per unit mass flow is much greater than that of cold air and cold water. Therefore, when delivering the same cooling, The refrigerant circulation flow is much smaller than the cold air and cold water flow, and the liquid refrigerant pipe diameter is much smaller than the cold water pipe diameter.
2、由于液态制冷剂依靠重力作用由地面制冷设备蒸发器流动至井下换热器,同时气态制冷剂由井下换热器流动至地面的动力为蒸发压力差,无需其它动力设备,降温成本大大降低。2. Since the liquid refrigerant flows from the evaporator of the ground refrigeration equipment to the downhole heat exchanger relying on gravity, and the power of the gaseous refrigerant flowing from the downhole heat exchanger to the ground is the evaporation pressure difference, no other power equipment is needed, and the cooling cost is greatly reduced .
3、由于将换热器设置在井下,缩短了冷量的经冷水输送的路程,减小了冷量输送损失及冷水循环泵的电耗,提高了冷量输送效率,从而提高了降温效果。3. Since the heat exchanger is installed underground, the cold water transport distance is shortened, the cold transport loss and the power consumption of the cold water circulation pump are reduced, and the cold transport efficiency is improved, thereby improving the cooling effect.
4、由于液态制冷剂管道的管径细,同等壁厚及管材下管径越小,其抗压能力越强,此外,可视制冷剂流量大小,把液态制冷剂管道做成并联的多根管径更小的管道,以此来克服液态制冷剂管道内液体静压力,这样换热器选用普通的换热器即可,不需要设置专门的高低压转换器或者高压换热器,费用大大降低,易于大面积推广。4. Since the diameter of the liquid refrigerant pipeline is thin, the smaller the diameter of the pipe with the same wall thickness and the lower the pipe material, the stronger the pressure resistance. In addition, depending on the flow rate of the refrigerant, the liquid refrigerant pipeline is made into multiple parallel connections Pipes with smaller diameters are used to overcome the static pressure of the liquid in the liquid refrigerant pipes, so that the heat exchanger can use ordinary heat exchangers, and there is no need to set up special high-low pressure converters or high-pressure heat exchangers, which costs a lot Reduced and easy to promote in a large area.
5、由于井下换热器内制冷剂流量小,可以采用管径小的铜管,适当加大铜管的壁厚可克服液态制冷剂液体静压力的作用,换热器采用铜管提高传热系数。5. Due to the small flow of refrigerant in the downhole heat exchanger, copper tubes with small diameters can be used. Appropriately increasing the wall thickness of the copper tubes can overcome the static pressure of the liquid refrigerant. The heat exchanger uses copper tubes to improve heat transfer coefficient.
6、本发明中所采用的制冷剂可以是氟利昂或者是氨,适应性广。6. The refrigerant used in the present invention can be Freon or ammonia, which has wide adaptability.
本发明作为一种新型的输冷系统,可以广泛用于其他矿山的降温。As a novel cooling system, the present invention can be widely used in cooling other mines.
附图说明 Description of drawings
图1为本发明的系统图。Fig. 1 is a system diagram of the present invention.
图中:1-液体制冷剂管道,2-气态制冷剂管道,3-制冷设备,4-换热器,5-冷水循环泵,6-冷水循环管道,7-空冷器。In the figure: 1-liquid refrigerant pipeline, 2-gas refrigerant pipeline, 3-refrigeration equipment, 4-heat exchanger, 5-cold water circulation pump, 6-cold water circulation pipeline, 7-air cooler.
具体实施方式 Detailed ways
如图1所示,一种矿井空调输冷系统,是在地面布置有制冷设备3,在井下布置有换热器4,在井下降温工作点布置有空冷器7;其中,换热器7一侧流动制冷剂、另一侧流动冷水,地面制冷设备3的蒸发器入口和井下换热器4的制冷剂出口之间用气态制冷剂管道2连通,地面制冷设备3的蒸发器出口和井下换热器4的制冷剂入口之间用液态制冷剂管道1连通,从而构成一封闭的管路系统,且在该管路系统内充注一定量的液态制冷剂;井下换热器4的冷水侧与井下降温工作点的空冷器7通过冷水循环管道6连通,且在循环管道6上串接有冷水循环泵5,从而实现冷水在空冷器4中循环,使井下降温工作点得到降温。As shown in Figure 1, a mine air-conditioning cooling system is arranged with
该系统的工作方法是:开启地面制冷设备3,液态制冷剂在井下换热器4进行热交换发生液-气相变,从而蒸发变为气态,气态制冷剂在井下换热器4内的蒸发压力作用下,经气态制冷剂管道2自动上升至地面制冷设备3的蒸发器内,气态制冷剂在制冷设备的制冷作用下发生气-液相变,吸收冷量冷凝为液态制冷剂,液态制冷剂在重力作用下携带冷量经液态制冷剂管道1靠自重输送至井下换热器4,重新蒸发为气态制冷剂,以此循环流动实现冷量向井下换热器4自动输送;同时开启井下冷水循环泵5,将换热器4冷水输送到空冷器7,以此循环流动实现工作点的降温。The working method of this system is: turn on the
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100487333A CN102536297A (en) | 2012-02-20 | 2012-02-20 | Cold conveying system of mine air-conditioning and working method of cold conveying system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100487333A CN102536297A (en) | 2012-02-20 | 2012-02-20 | Cold conveying system of mine air-conditioning and working method of cold conveying system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102536297A true CN102536297A (en) | 2012-07-04 |
Family
ID=46344170
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100487333A Pending CN102536297A (en) | 2012-02-20 | 2012-02-20 | Cold conveying system of mine air-conditioning and working method of cold conveying system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102536297A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306705A (en) * | 2013-06-13 | 2013-09-18 | 中国科学院工程热物理研究所 | Refrigeration system for mine cooling |
CN104005784A (en) * | 2014-06-12 | 2014-08-27 | 中煤科工集团重庆研究院有限公司 | Cold and hot water pressure exchange system applied to deep heat damage mine |
CN104314602A (en) * | 2014-08-15 | 2015-01-28 | 张惠忠 | Underground comprehensive refrigerating method |
CN107366547A (en) * | 2016-05-13 | 2017-11-21 | 中国矿业大学(北京) | A kind of high-temperature mine air intake crossheading air cooling facility optimization placement method |
CN111322103A (en) * | 2020-05-12 | 2020-06-23 | 山东澳神热泵空调有限公司 | Mine air conditioner cold conveying system convenient to maintain |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201074522Y (en) * | 2007-09-07 | 2008-06-18 | 武汉星田热环境控制技术有限公司 | Low-temperature refrigeration cooling device for mine |
CN101344009A (en) * | 2008-08-29 | 2009-01-14 | 中国科学院广州能源研究所 | Mine Cooling System and Cooling Method |
CN101749043A (en) * | 2008-12-19 | 2010-06-23 | 刘应江 | Temperature differential mine air conditioner cold-heat source energy system |
CN102182491A (en) * | 2011-03-21 | 2011-09-14 | 山东新巨龙能源有限责任公司 | Construction method of cooling water circulation system of underground concentrated cooling unit |
PL209924B1 (en) * | 2005-11-07 | 2011-11-30 | Kghm Cuprum Społka Z Ograniczoną Odpowiedzialnością Ct Badawczo Rozwojowe | Two-stage air conditioning system for cooling air in the underground mine headings |
CN202832620U (en) * | 2012-02-20 | 2013-03-27 | 河南理工大学 | Coldness conveying system of mine air-conditioning |
-
2012
- 2012-02-20 CN CN2012100487333A patent/CN102536297A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
PL209924B1 (en) * | 2005-11-07 | 2011-11-30 | Kghm Cuprum Społka Z Ograniczoną Odpowiedzialnością Ct Badawczo Rozwojowe | Two-stage air conditioning system for cooling air in the underground mine headings |
CN201074522Y (en) * | 2007-09-07 | 2008-06-18 | 武汉星田热环境控制技术有限公司 | Low-temperature refrigeration cooling device for mine |
CN101344009A (en) * | 2008-08-29 | 2009-01-14 | 中国科学院广州能源研究所 | Mine Cooling System and Cooling Method |
CN101749043A (en) * | 2008-12-19 | 2010-06-23 | 刘应江 | Temperature differential mine air conditioner cold-heat source energy system |
CN102182491A (en) * | 2011-03-21 | 2011-09-14 | 山东新巨龙能源有限责任公司 | Construction method of cooling water circulation system of underground concentrated cooling unit |
CN202832620U (en) * | 2012-02-20 | 2013-03-27 | 河南理工大学 | Coldness conveying system of mine air-conditioning |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306705A (en) * | 2013-06-13 | 2013-09-18 | 中国科学院工程热物理研究所 | Refrigeration system for mine cooling |
CN103306705B (en) * | 2013-06-13 | 2016-05-18 | 中国科学院工程热物理研究所 | Mine cooling refrigeration system |
CN104005784A (en) * | 2014-06-12 | 2014-08-27 | 中煤科工集团重庆研究院有限公司 | Cold and hot water pressure exchange system applied to deep heat damage mine |
CN104314602A (en) * | 2014-08-15 | 2015-01-28 | 张惠忠 | Underground comprehensive refrigerating method |
CN107366547A (en) * | 2016-05-13 | 2017-11-21 | 中国矿业大学(北京) | A kind of high-temperature mine air intake crossheading air cooling facility optimization placement method |
CN111322103A (en) * | 2020-05-12 | 2020-06-23 | 山东澳神热泵空调有限公司 | Mine air conditioner cold conveying system convenient to maintain |
CN111322103B (en) * | 2020-05-12 | 2021-06-04 | 山东澳神热泵空调有限公司 | Mine air conditioner cold conveying system convenient to maintain |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100580225C (en) | Deep mining mine cooling device | |
CN103306705B (en) | Mine cooling refrigeration system | |
CN103216255B (en) | Compressed air cold conveying cooling system for mine and cooling method thereof | |
CN201074522Y (en) | Low-temperature refrigeration cooling device for mine | |
CN103913316B (en) | A kind of water-ethylene glycol type water source heat pump units performance testing device | |
CN103410549B (en) | Utilize the System and method for that residual heat of electric power plant is lowered the temperature for mine ventilation | |
CN102536297A (en) | Cold conveying system of mine air-conditioning and working method of cold conveying system | |
CN101344009A (en) | Mine Cooling System and Cooling Method | |
CN104236164A (en) | Ultra-high temperature cascade water source heat pump system | |
CN102434995A (en) | R32 air-cooling cold water heat pump unit adopting EVI (Economizer Vapor Injection) compressor | |
CN203161278U (en) | Mine vacuum cooling system | |
CN202018103U (en) | Multi-connected ground source convertible frequency air conditioner | |
CN202970756U (en) | Mining liquid nitrogen temperature reducing device | |
CN202382470U (en) | R32 air-cooled water chiller heat pump unit with EVI (enhanced vapor injection) compressor | |
CN205027017U (en) | Direct evaporative ice slurry circulation dynamic ice making device | |
CN111456797A (en) | Closed Circulation System and Working Method of Cooling Mine by Cooling by Surface Cooler | |
CN101907331A (en) | Mining air-condition refrigerating capacity transmission system and implementation scheme | |
CN201794605U (en) | Mine working face cooling device adopting geothermal energy | |
CN202832620U (en) | Coldness conveying system of mine air-conditioning | |
CN203349414U (en) | Air conditioner system | |
CN202149555U (en) | Computer room air-conditioning system adopting double cold sources (air and soil) and fixed-point air supply mode | |
CN212457129U (en) | Device for conveying cold source | |
CN209704620U (en) | A kind of hot and cold, dynamic Combined type pit cooling device | |
CN203907839U (en) | Water dispenser for heating and cooling with air-conditioner refrigerant | |
CN202284833U (en) | Parallel-connected double-pump type ice storage refrigerating system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120704 |