[go: up one dir, main page]

CN102535488B - Waterproof construction method for bottom plate of high-water-level basement - Google Patents

Waterproof construction method for bottom plate of high-water-level basement Download PDF

Info

Publication number
CN102535488B
CN102535488B CN201210065838.XA CN201210065838A CN102535488B CN 102535488 B CN102535488 B CN 102535488B CN 201210065838 A CN201210065838 A CN 201210065838A CN 102535488 B CN102535488 B CN 102535488B
Authority
CN
China
Prior art keywords
ditch
basement
dewatering well
water
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210065838.XA
Other languages
Chinese (zh)
Other versions
CN102535488A (en
Inventor
吴丙同
陈庆军
莫春宇
何岸
林少群
刘达鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG ZHONGCHENG CONSTRUCTION GROUP CO Ltd
South China University of Technology SCUT
Original Assignee
GUANGDONG ZHONGCHENG CONSTRUCTION GROUP CO Ltd
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG ZHONGCHENG CONSTRUCTION GROUP CO Ltd, South China University of Technology SCUT filed Critical GUANGDONG ZHONGCHENG CONSTRUCTION GROUP CO Ltd
Priority to CN201210065838.XA priority Critical patent/CN102535488B/en
Publication of CN102535488A publication Critical patent/CN102535488A/en
Application granted granted Critical
Publication of CN102535488B publication Critical patent/CN102535488B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a waterproof construction method for a bottom plate of a high-water-level basement. The method comprises the following steps of: (1) partitioning water on a soil layer in a depth range of a foundation pit from the periphery of the foundation pit by using a waterproof curtain of a foundation pit support, and forming drainage ditches on the ground surface of the foundation pit support and at the bottom periphery of the foundation pit; (2) forming more than one dredging ditch below partitioning positions among pile bearing platforms, wherein the distance between the bottom of each pile bearing platform and the top of the dredging ditch is 500 to 1,000mm; and (3) forming a corresponding dewatering well at the periphery of the foundation pit according to a water outlet end of the dredging ditch, and arranging a submerged pump in the dewatering well, wherein the submerged pump is communicated with the drainage ditches through water suction pipes. The invention also discloses a waterproof system for the bottom plate of the high-water-level basement. By the method and the system, the problems of low dryness of flexible waterproof layer construction surfaces, over-high cost of jet grouting piles, high water seepage degree, high labor consumption, high material consumption and the like in the prior art are solved; and the system has the characteristics of effectively dewatering the basement, shortening construction periods, saving the cost and conveniently controlling construction quality, along with a simple structure, low manufacturing cost and the like.

Description

一种高水位地下室底板防水施工方法A waterproof construction method for basement floor with high water level

技术领域technical field

本发明涉及土木工程的地下室底板防水施工技术领域,具体来说是一种高水位地下室底板防水施工方法及其系统。The invention relates to the technical field of basement floor waterproof construction in civil engineering, in particular to a high water level basement floor waterproof construction method and a system thereof.

背景技术Background technique

随着建筑设计地下工程水平的提高,地下室的使用功能将不仅用于地下防空、地下车库等用途。由于城市建筑用地的紧缺和跟随国际建筑物往地下扩大空间的流行趋势,建筑使用空间(层)往地下深扩展,地下办公,地下商业购物广场日趋多样化。目前我国长江、珠江三角洲冲积层地质低洼地区的建筑地下室多层化,使用功能多样化日趋突出。地下功能使用要求越高,地下室防水等级要求就越高;地下水位越高水压力越大,施工难度也就越大。With the improvement of the level of underground engineering in architectural design, the use function of the basement will not only be used for underground air defense, underground garages and other purposes. Due to the shortage of urban construction land and following the popular trend of international buildings to expand space underground, the building use space (layer) is deeply expanded underground, and underground offices and underground commercial shopping plazas are becoming more and more diverse. At present, the basements of buildings in the low-lying alluvial areas of the Yangtze River and Pearl River Delta in my country are multi-layered, and the diversification of functions is becoming more and more prominent. The higher the requirements for the use of underground functions, the higher the requirements for the waterproof level of the basement; the higher the groundwater level, the greater the water pressure, and the greater the difficulty of construction.

高等级防水的地下室底板防水层一般采用外防外贴方法。其防水结构由迎水面到结构层依次是柔性防水层→保护层→卷材(干铺)粘贴层→保护层→结构层;而最前沿的第一层柔性防水层是合成高分子防水涂膜或聚氨酯涂膜,其水泥沙浆批挡基层的干燥度要求很高,基层干燥度越高,质量就越好。The waterproof layer of the basement floor with high-level waterproof generally adopts the method of external anti-external sticking. Its waterproof structure is flexible waterproof layer→protective layer→roll material (dry laying) adhesive layer→protective layer→structural layer from the water-facing surface to the structural layer; and the first flexible waterproof layer at the forefront is a synthetic polymer waterproof coating film Or polyurethane coating film, the dryness of the cement mortar batch blocking base is very high, the higher the dryness of the base, the better the quality.

处于高地下水水位的基坑,特别是越靠近江河、湖泊、海边区域的饱和淤泥质土层,设置止水帷幕并不能完全保证基底土的干燥,因为巨大的水压力会使地下室底板的工作垫层(砼垫层)和桩承台结构的砖模水渗透性加大,导致基底渗水。因此,其基面就难以达到柔性防水层合成高分子防水涂膜或聚氨酯涂膜施工要求的干燥度,施工质量难以保证。For foundation pits with high groundwater levels, especially the saturated muddy soil layers closer to rivers, lakes, and seaside areas, the installation of water-stop curtains cannot completely guarantee the drying of the base soil, because the huge water pressure will make the working pad of the basement floor Layer (concrete cushion) and the brick mold water permeability of the pile cap structure increase, resulting in water seepage of the base. Therefore, it is difficult for the base surface to reach the dryness required for the construction of the flexible waterproof layer synthetic polymer waterproof coating film or polyurethane coating film, and the construction quality is difficult to guarantee.

工程中针对基底渗水的问题,最直接的方法就是采用井点降水,即在基坑四周或内部设置降水井点,把地下水位降低到施工面以下,但是对于对地下水较为敏感的周边地质环境,该方法并不适用。此外可以采用旋喷桩止水,即在渗水的位置做旋喷桩,在基底处形成一道止水层。这种做法可以有效解决基底渗水的问题,保证基底的干燥度,但是这种方法的缺点是成本偏高,而且要花费大量的时间,况且对于处于高地下水位的基坑,渗水情况更为严重,这种方法的缺点更加突显。还可以在混凝土垫层下增设100~200mm砂卵石垫层。面积大的基坑还应在砂石垫层中设置纵横向盲沟,以利于将水向两侧边沟排出抽走。该方法可以保证将基底渗水迅速排走,但是在基坑面积较大的情况下,该做法比较费工费料。The most direct way to solve the problem of basement seepage in engineering is to use well point dewatering, that is, set dewatering well points around or inside the foundation pit to lower the groundwater level below the construction surface. However, for the surrounding geological environment that is more sensitive to groundwater, This method is not applicable. In addition, rotary spray piles can be used to stop water, that is, rotary spray piles can be installed at the position of water seepage to form a water-stop layer at the base. This approach can effectively solve the problem of base water seepage and ensure the dryness of the base, but the disadvantage of this method is that the cost is high and it takes a lot of time. Moreover, for foundation pits with high groundwater levels, the seepage situation is more serious , the shortcomings of this method are more prominent. A 100-200mm sand and pebble cushion can also be added under the concrete cushion. For foundation pits with a large area, vertical and horizontal blind ditches should also be set in the sand and gravel cushion to facilitate the drainage of water to the side ditches on both sides. This method can ensure that the base seepage water is quickly drained away, but in the case of a large foundation pit area, this method is more labor-intensive and material-intensive.

发明内容Contents of the invention

本发明的目的在于克服以上现有技术存在的不足,提供了一种结构简单、造价便宜、有效降水、缩减工期、节约成本及便于施工质量控制的高水位地下室底板防水施工方法。The purpose of the present invention is to overcome the shortcomings of the prior art above, and provide a waterproof construction method for high water level basement floor with simple structure, low cost, effective precipitation, shortened construction period, cost saving and convenient construction quality control.

本发明的另一目的在于提供一种高水位地下室底板防水系统。Another object of the present invention is to provide a waterproof system for basement floor with high water level.

为了达到上述目的,本发明采用以下技术方案:一种高水位地下室底板防水施工方法,包括下列步骤:In order to achieve the above object, the present invention adopts the following technical solutions: a method for waterproofing construction of basement basement with high water level, comprising the following steps:

(1)首先利用基坑支护的止水帷幕,将基坑深度范围土层的水止隔在基坑周边以外,同时在基坑支护的地面及基坑底周边均设置贯通排水沟;(1) First, use the water-stop curtain of the foundation pit support to stop the water in the soil layer in the depth range of the foundation pit from the periphery of the foundation pit, and at the same time set through drainage ditches on the ground supported by the foundation pit and around the bottom of the foundation pit;

(2)在地下室底板桩承台之间的间隔位置下方设置1条以上的用松砖及纤维网砌成的疏水沟,桩承台底部距疏水沟顶部500~1000mm;(2) Set up more than one drainage ditch made of loose bricks and fiber nets below the interval between pile caps on the basement floor, and the distance between the bottom of the pile caps and the top of the drainage ditch is 500-1000mm;

(3)在基坑周边按疏水沟出水口端设置相对应的降水井,降水井设在距离地下室基础最外周边缘的外部,降水井内设置潜水泵,潜水泵通过抽水管与排水沟连通。(3) Corresponding dewatering wells are set at the outlet of the drainage ditch around the foundation pit. The dewatering wells are located outside the outermost edge of the basement foundation. A submersible pump is installed in the dewatering well, and the submersible pump is connected to the drainage ditch through a suction pipe.

作为一种优选的方案,所述步骤(2)中的疏水沟和步骤(3)中的降水井的开挖方法为:基坑土方开挖挖至桩承台一半高度的标高时,根据疏水沟和降水井的平面布置图进行测量放线,完成之后同时进行疏水沟的土方开挖和降水井的土方开挖。As a preferred solution, the excavation method of the drainage ditch in the step (2) and the dewatering well in the step (3) is: when excavating the earthwork of the foundation pit to the elevation of half the height of the pile cap, according to the drainage The groundwork of the drainage ditch and the earthwork excavation of the precipitation well will be carried out at the same time after completion.

为了避开地下室底板结构及防水层位置,所述步骤(3)中的降水井设在距离地下室基础最外周边缘600mm以外。In order to avoid the basement floor structure and the position of the waterproof layer, the dewatering well in the step (3) is set beyond 600mm from the outermost peripheral edge of the basement foundation.

作为一种优选的方案,所述步骤(2)中的疏水沟施工方法为:先在疏水沟的底部平铺一层厚度为60~120mm的松砖,疏水沟两侧均铺设厚度为120~240mm的松砖,疏水沟的内空宽度为120~160mm,疏水沟的内空松填粒径为20~30mm的碎石,疏水沟的顶部平铺厚度为60~120mm长度为240mm的松砖,顶部的松砖与松砖之间留30~60mm宽的泄水缝,然后在疏水沟的顶部松砖上表面及两侧松砖外表面铺设2~3层纤维网,纤维网为每平方厘米9~16目,同时疏水沟的底部与降水井具有0.5~1%的坡度,使沟内水顺利往降水井排走。As a preferred solution, the construction method of the drainage ditch in the step (2) is: first lay a layer of pine bricks with a thickness of 60-120 mm at the bottom of the drainage ditch, and lay bricks with a thickness of 120-120 mm on both sides of the drainage ditch. 240mm loose bricks, the width of the inner space of the drainage ditch is 120-160mm, the inner space of the drainage ditch is loosely filled with gravel with a particle size of 20-30mm, and the top of the drainage ditch is tiled with loose bricks with a thickness of 60-120mm and a length of 240mm , leave a 30-60mm wide drainage joint between the top pine bricks and pine bricks, and then lay 2-3 layers of fiber mesh on the upper surface of the top pine bricks and the outer surfaces of the pine bricks on both sides of the drainage ditch. 9 to 16 meshes per centimeter, and at the same time, the bottom of the drainage ditch and the dewatering well have a slope of 0.5 to 1%, so that the water in the ditch can be smoothly drained to the dewatering well.

作为一种优选的方案,所述步骤(2)中的疏水沟平面布置为通长贯通结构或非通长贯通结构。只需保证疏水沟出水口端与降水井连通即可。As a preferred solution, the planar arrangement of the hydrophobic grooves in the step (2) is a full-length through structure or a non-through-length through structure. It is only necessary to ensure that the outlet end of the drain ditch is connected with the precipitation well.

作为另一种优选的方案,所述步骤(2)中的疏水沟平面布置为弯转结构,疏水沟出水口端与步骤(3)中的降水井连通。As another preferred solution, the planar arrangement of the drainage ditch in the step (2) is a curved structure, and the outlet end of the drainage ditch communicates with the precipitation well in the step (3).

一种高水位地下室底板防水系统,包括桩承台、疏水沟、排水沟、降水井和潜水泵;其中,桩承台之间的间隔位置下方设置1条以上的用松砖及纤维网砌成的疏水沟,桩承台底部距疏水沟顶部500~1000mm,基坑支护的地面及基坑底周边均设置贯通排水沟,地下室基础最外周边缘的外部设置降水井,疏水沟出水口端与相对应的降水井连通,降水井内设置潜水泵,潜水泵通过抽水管与排水沟连通。A high water level basement floor waterproofing system, comprising pile caps, drains, drainage ditches, dewatering wells and submersible pumps; wherein, at the bottom of the interval between pile caps, there is more than one pine brick and fiber net. The bottom of the pile cap is 500-1000mm away from the top of the drainage ditch. The ground supported by the foundation pit and the periphery of the foundation pit bottom are provided with a through-drainage ditch. The corresponding dewatering wells are connected, and a submersible pump is arranged in the dewatering well, and the submersible pump is connected with the drainage ditch through a suction pipe.

作为一种优选的方案,所述疏水沟为底部铺设1层60~120mm的松砖,两侧均铺设厚度为120~240mm的松砖,其内空宽度为120~160mm,疏水沟的内空松填粒径为20~30mm的碎石,疏水沟的顶部平铺厚度为60~120mm长度为240mm的松砖,顶部的松砖与松砖之间留30~60mm宽的泄水缝,疏水沟的顶部松砖上表面及两侧松砖外表面铺设2~3层纤维网,纤维网为每平方厘米9~16目,同时疏水沟的底部与降水井具有0.5~1%的坡度。As a preferred solution, the drain ditch is laid with a layer of 60-120mm loose bricks at the bottom, and loose bricks with a thickness of 120-240mm are laid on both sides, and the width of the inner space is 120-160mm. Loosely fill gravel with a particle size of 20-30mm, pave loose bricks with a thickness of 60-120mm and a length of 240mm on the top of the drainage ditch, and leave a 30-60mm wide drainage joint between the top loose bricks and loose bricks. The upper surface of the pine bricks on the top of the ditch and the outer surface of the pine bricks on both sides are laid with 2 to 3 layers of fiber mesh, the fiber mesh is 9 to 16 meshes per square centimeter, and the bottom of the drainage ditch and the precipitation well have a slope of 0.5 to 1%.

为了能支撑土壤的压力及能够好的排水,所述降水井包括钢筋笼、加劲环、箍筋及滤水网;其中,箍筋螺旋固接在钢筋笼上,加劲环套设固接在钢筋笼上,钢筋笼外部包覆3层以上每平方厘米具有9~12目的滤水网,钢筋笼的长度小于等于4.5m且小于基坑支护的基坑支护桩的入土深度,所述降水井设在距离地下室基础最外周边缘600mm以外。降水井的主要的功能是集水、降水和抽排水,降水井的尺寸是根据疏水沟的排水量设计的。In order to support the pressure of the soil and enable good drainage, the dewatering well includes a reinforcement cage, a stiffening ring, stirrups and a water filter net; wherein, the stirrups are helically fixed on the reinforcement cage, and the stiffening ring is sleeved and fixed on the reinforcement On the cage, the outside of the steel cage is covered with more than 3 layers and has 9 to 12 mesh water filter nets per square centimeter. The length of the steel cage is less than or equal to 4.5m and is less than the depth of the foundation pit supporting piles. The precipitation The well is located 600mm away from the outermost edge of the basement foundation. The main functions of the precipitation well are water collection, precipitation and pumping and drainage. The size of the precipitation well is designed according to the drainage capacity of the drainage ditch.

为了能更好的排水、过滤及不堵塞,还包括行程开关,行程开关设置在潜水泵上方的降水井内壁上,所述潜水泵的扬程为30m以上,直径50mm以上,所述抽水管为硬质PVC管,其硬质PVC管与潜水泵的出水口连接处的减振用300~500mm长软管连接。In order to better drain water, filter and prevent clogging, a travel switch is also included. The travel switch is arranged on the inner wall of the dewatering well above the submersible pump. The head of the submersible pump is more than 30m and the diameter is more than 50mm. Quality PVC pipe, the connection between the hard PVC pipe and the water outlet of the submersible pump is connected with a 300-500mm long hose for vibration reduction.

本发明相对于现有技术,具有如下的优点及效果:Compared with the prior art, the present invention has the following advantages and effects:

1、采用本发明施工方法,能有效降水,为下一道工序提供作业面,避免了以往因降水失败或积水而无法进入一道工序的情况,可以大大缩减工期。1. Adopting the construction method of the present invention can effectively dewater and provide a working surface for the next process, avoiding the failure to enter a process due to precipitation failure or water accumulation in the past, and can greatly reduce the construction period.

2、本发明中的疏水沟和降水井等结构,用材简单、便宜且能有效保证地下室底板防水基层的干燥度,节省了以往因降水失败或积水而导致防水层施工返工产生的费用。2. Structures such as drainage ditch and dewatering well in the present invention use simple and cheap materials and can effectively ensure the dryness of the waterproof base of the basement floor, saving the cost of rework of the waterproof layer construction caused by the failure of precipitation or water accumulation in the past.

3、采用本发明施工方法,保证了地下室底板基层的干燥度及防水层施工的质量,保证了防水层检查及验收的合格率达100%以上,质量优良率达90%以上。3. By adopting the construction method of the present invention, the dryness of the base of the basement floor and the construction quality of the waterproof layer are guaranteed, and the pass rate of waterproof layer inspection and acceptance is more than 100%, and the excellent quality rate is more than 90%.

4、本发明中的纤维网和滤水网均可采用旧的安全网,废物利用,节约成本。4. Both the fiber net and the water filter net in the present invention can adopt the old safety net, waste utilization and cost saving.

5、本发明中的疏水沟的底部与降水井具有0.5~1%的坡度,具有能使水更易向排水沟流动的特点。5. The bottom of the drainage ditch in the present invention has a slope of 0.5-1% with the precipitation well, which has the feature of making water flow to the drainage ditch more easily.

6、本发明中的降水井包括钢筋笼、加劲环、箍筋及滤水网,且钢筋笼的长度小于等于4.5m且小于基坑支护的基坑支护桩的入土深度,具有能有效的支撑土壤压力及便于挖掘机分两级平台挖坑埋设。6. The dewatering well in the present invention comprises a reinforcement cage, a stiffening ring, stirrups and a water filter net, and the length of the reinforcement cage is less than or equal to 4.5m and less than the depth of penetration of the foundation pit support piles of the foundation pit support, and has the ability to effectively The supporting soil pressure and the excavator are divided into two levels of platforms to dig pits and bury them.

7、本发明中的抽水管为硬质PVC管避免抽水管因为泥沙而堵塞,且硬质PVC管与潜水泵的出水口连接处的减振用300~500mm长软管连接。7. The suction pipe in the present invention is a hard PVC pipe to prevent the water suction pipe from being blocked by silt, and the vibration damping at the joint between the hard PVC pipe and the water outlet of the submersible pump is connected with a 300-500mm long hose.

附图说明Description of drawings

图1为本发明高水位地下室底板防水系统的结构示意图;Fig. 1 is the structural representation of high water level basement floor waterproofing system of the present invention;

图2为本发明高水位地下室底板防水系统的剖视图;Fig. 2 is the sectional view of high water level basement floor waterproofing system of the present invention;

图3为本发明高水位地下室底板防水系统疏水沟的平面布置图;Fig. 3 is the plane layout drawing of the drainage ditch of the basement floor waterproofing system of the present invention;

图4为本发明高水位地下室底板防水系统疏水沟的截面图;Fig. 4 is the cross-sectional view of the drainage ditch of the waterproof system of the basement basement with high water level of the present invention;

图5为本发明高水位地下室底板防水系统降水井的结构示意图。Fig. 5 is a structural schematic diagram of the dewatering well of the high water level basement floor waterproofing system of the present invention.

图中标号与名称如下:The labels and names in the figure are as follows:

Figure GDA0000398055970000051
Figure GDA0000398055970000051

具体实施方式Detailed ways

为便于本领域技术人员理解,下面结合附图及实施例对本发明作进一步的详细说明。For the convenience of those skilled in the art to understand, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments.

实施例1:Example 1:

如图1~5所示,一种高水位地下室底板防水施工方法,包括下列步骤:As shown in Figures 1 to 5, a waterproof construction method for a basement floor with a high water level comprises the following steps:

(1)首先利用基坑支护的止水帷幕,将基坑18深度范围土层的水止隔在基坑17周边以外,同时在基坑支护的地面17及基坑底周边均设置贯通排水沟1;(1) First, use the water-stop curtain of the foundation pit support to stop the water in the soil layer in the depth range of the foundation pit 18 from the periphery of the foundation pit 17, and at the same time, set a through hole on the ground 17 of the foundation pit support and the periphery of the bottom of the foundation pit. gutter 1;

(2)在地下室底板桩承台之间的间隔位置下方设置1条以上的用松砖及纤维网砌成的疏水沟3,桩承台底部2距疏水沟3顶部500~1000mm;(2) Set up more than one drain ditch 3 made of loose bricks and fiber nets below the interval between the pile caps of the basement floor, and the bottom 2 of the pile caps is 500-1000mm away from the top of the drain ditch 3;

(3)在基坑1周边按疏水沟3出水口端设置相对应的降水井4,降水井4设在距离地下室基础最外周边缘5的外部,降水井4内设置潜水泵6,潜水泵6通过抽水管7与排水沟1连通。(3) Corresponding dewatering wells 4 are arranged at the outlet of the drainage ditch 3 around the foundation pit 1, and the dewatering wells 4 are arranged outside the outermost edge 5 of the basement foundation. It communicates with the drainage ditch 1 through the suction pipe 7 .

其中,高水位是指基坑所处位置靠近江河、湖泊、海边区域的饱和淤泥质土层,地下水位较高,同时由于条件限制不允许采用井点降水,设置止水帷幕并不能完全保证基底土的干燥。Among them, the high water level refers to the saturated muddy soil layer where the foundation pit is located close to rivers, lakes, and seaside areas. The drying of the soil.

如图1所示,所述步骤(2)中的疏水沟3和步骤(3)中的降水井4的开挖方法为:基坑1土方开挖挖至桩承台一半高度的标高时,根据疏水沟3和降水井4的平面布置图进行测量放线,完成之后同时进行疏水沟3的土方开挖和降水井4的土方开挖,所述步骤(3)中的降水井4设在距离地下室基础最外周边缘5的600mm以外。所述步骤(2)中的疏水沟3平面布置为通长贯通结构或非通长贯通结构,本实施例中的疏水沟3均为直线结构。As shown in Figure 1, the excavation method of the drainage ditch 3 in the step (2) and the dewatering well 4 in the step (3) is: when the excavation of the excavation of the foundation pit 1 is excavated to the elevation of half the height of the pile cap, Carry out measuring and setting out according to the floor plan of drain ditch 3 and dewatering well 4, carry out the earth excavation of drain ditch 3 and the earth excavation of dewatering well 4 simultaneously after completion, dewatering well 4 in described step (3) is located at 600mm away from the outermost edge of the basement foundation 5. The planar arrangement of the hydrophobic grooves 3 in the step (2) is a full-length through structure or a non-through-length through structure, and the hydrophobic grooves 3 in this embodiment are all linear structures.

如图4所示,所述步骤(2)中的疏水沟3施工方法为:先在疏水沟3的底部平铺一层厚度为60~120mm的松砖12,疏水沟3两侧均铺设厚度为120~240mm的松砖13,疏水沟3的内空宽度为120~160mm,疏水沟3内空松填粒径为20~30mm的碎石19,疏水沟3的顶部平铺厚度为60~120mm长度为240mm的松砖14,顶部的松砖14与松砖之间留30~60mm宽的泄水缝15,然后在疏水沟的顶部松砖14上表面及两侧松砖13外表面铺设2~3层纤维网16,纤维网16为每平方厘米9~16目,同时疏水沟3的底部与降水井4具有0.5~1%的坡度,使沟内水顺利往降水井排走。纤维网16的作用为:使得土壤的水既能往疏水沟3内排泄又将泥土阻隔于疏水沟3外,保持畅通。As shown in Figure 4, the construction method of the drain ditch 3 in the step (2) is as follows: a layer of loose bricks 12 with a thickness of 60 to 120 mm is tiled at the bottom of the drain ditch 3 first, and a thickness of pine brick 12 is laid on both sides of the drain ditch 3 pine bricks 13 of 120-240 mm, the width of the inner space of the drainage ditch 3 is 120-160 mm, the inner space of the drainage ditch 3 is loosely filled with crushed stones 19 with a particle size of 20-30 mm, and the top tile thickness of the drainage ditch 3 is 60-160 mm. 120mm long pine bricks 14 with a length of 240mm, leave a 30-60mm wide drainage joint 15 between the top pine bricks 14 and pine bricks, and then lay on the upper surface of the top pine bricks 14 of the drainage ditch and the outer surfaces of the pine bricks 13 on both sides 2~3 layers of fiber nets 16, the fiber nets 16 are 9~16 meshes per square centimeter, and the bottom of the drain ditch 3 and the dewatering well 4 have a slope of 0.5~1% simultaneously, so that the water in the ditch is drained to the dewatering well smoothly. The function of the fiber net 16 is: the water of the soil can be drained in the drainage ditch 3 and the soil is blocked outside the drainage ditch 3 to keep it unimpeded.

其中,疏水沟3的截面尺寸及布置密度按地下室底板底桩承台所在土层的涌水量计算决定,从而保证涌水量通过地下疏水沟3泄排至降水井4及抽排至排水沟1排走;降水井4的直径及潜水泵6的抽排量按疏水沟的排水量而定。基坑中的降水井在地下室施工完成之后,与地下室侧壁土一起回填,回填前可将其钢筋笼取出重复利用。Among them, the cross-sectional size and layout density of the drainage ditch 3 are determined according to the calculation of the water inflow in the soil layer where the basement bottom pile cap is located, so as to ensure that the water inflow is discharged to the precipitation well 4 through the underground drainage ditch 3 and drained to the drainage ditch 1 row Walk; The diameter of the dewatering well 4 and the pumping capacity of the submersible pump 6 are determined by the displacement of the drainage ditch. After the basement construction is completed, the dewatering well in the foundation pit will be backfilled together with the side wall soil of the basement, and its steel cage can be taken out and reused before backfilling.

一种高水位地下室底板防水系统,包括桩承台、疏水沟3、排水沟1、降水井4和潜水泵6;其中,桩承台之间的间隔位置下方设置1条以上的用松砖及纤维网砌成的疏水沟3,桩承台底部2距疏水沟3顶部500~1000mm,基坑支护的地面17及基坑底周边均设置贯通排水沟1,地下室基础最外周边缘5的外部设置降水井4,疏水沟3出水口端与相对应的降水井4连通,降水井4内设置潜水泵6,潜水泵6通过抽水管7与排水沟1连通。A high water level basement floor waterproofing system, comprising pile caps, drainage ditch 3, drainage ditch 1, dewatering well 4 and submersible pump 6; wherein, one or more loose bricks and The drainage ditch 3 made of fiber mesh, the bottom 2 of the pile cap is 500-1000mm away from the top of the drainage ditch 3, the ground 17 supported by the foundation pit and the periphery of the bottom of the foundation pit are provided with a through drainage ditch 1, the outermost edge 5 of the basement foundation A dewatering well 4 is set, and the outlet end of the drainage ditch 3 communicates with the corresponding dewatering well 4, and a submersible pump 6 is arranged in the dewatering well 4, and the submersible pump 6 communicates with the drainage ditch 1 through a suction pipe 7.

如图4所示,所述疏水沟3为底部铺设1层60~120mm的松砖,两侧均铺设厚度为120~240mm的松砖,其内空宽度为120~160mm,疏水沟3的内空松填粒径为20~30mm的碎石19,疏水沟3的顶部平铺厚度为60~120mm长度为240mm的松砖14,顶部的松砖14与松砖之间留30~60mm宽的泄水缝15,疏水沟的顶部松砖14上表面及两侧松砖13外表面铺设2~3层纤维网16,纤维网16为每平方厘米9~16目,同时疏水沟3的底部与降水井4具有0.5~1%的坡度。纤维网16的作用为:使得土壤的水既能往疏水沟3内排泄又将泥土阻隔于疏水沟3外,保持畅通。As shown in Figure 4, the drainage ditch 3 is laid with a layer of 60-120mm loose bricks at the bottom, and loose bricks with a thickness of 120-240mm are laid on both sides, and the inner width of the drainage ditch 3 is 120-160mm. Fill the void with gravel 19 with a particle size of 20-30 mm, pave loose bricks 14 with a thickness of 60-120 mm and a length of 240 mm on the top of the drainage ditch 3, and leave a 30-60 mm wide gap between the loose bricks 14 on the top and the loose bricks. Drainage joint 15, the top pine brick 14 upper surface of drain ditch and the pine brick 13 outer surfaces of both sides are laid 2~3 layers of fiber net 16, and fiber net 16 is 9~16 meshes per square centimeter, simultaneously the bottom of drain ditch 3 and The precipitation well 4 has a slope of 0.5-1%. The function of the fiber net 16 is: the water of the soil can be drained in the drainage ditch 3 and the soil is blocked outside the drainage ditch 3 to keep it unimpeded.

如图5所示,所述降水井4包括钢筋笼8、加劲环9、箍筋10及滤水网11;其中,箍筋10螺旋焊接在钢筋笼8上,加劲环9套设焊接在钢筋笼8上,钢筋笼8外部包覆3层以上每平方厘米具有9~12目的滤水网11,钢筋笼8的长度小于等于4.5m且小于基坑支护的基坑支护桩的入土深度,所述降水井4设在距离地下室基础最外周边缘5的600mm以外,还包括行程开关,行程开关设置在潜水泵6上方的降水井4内壁上,所述潜水泵6的扬程为30m以上,直径50mm以上,所述抽水管7为硬质PVC管,降水井4的主要作用为集水、降水和抽排水,降水井4的尺寸及潜水泵6的规格均根据实际需要而设定。抽水管7不能用软管,必须用硬质PVC管,以免抽上的水中沙将管堵塞,其硬质PVC管与潜水泵的出水口连接处的减振用300~500mm长软管连接。滤水网11和纤维网16均可采用旧安全网代替,达到废物利用的效果。基坑中的降水井在地下室施工完成之后,与地下室侧壁土一起回填,回填前可将其钢筋笼取出重复利用。As shown in Figure 5, the dewatering well 4 includes a reinforcement cage 8, a stiffening ring 9, a stirrup 10 and a water filter 11; wherein, the stirrup 10 is spirally welded on the reinforcement cage 8, and the stiffening ring 9 is set and welded on the reinforcement On the cage 8, the reinforcement cage 8 is covered with more than 3 layers and has 9 to 12 mesh water filter screens 11 per square centimeter, and the length of the reinforcement cage 8 is less than or equal to 4.5m and less than the depth of the foundation pit support piles for foundation pit support. , the dewatering well 4 is arranged outside the 600mm distance from the outermost peripheral edge 5 of the basement foundation, and also includes a travel switch. The travel switch is arranged on the inner wall of the dewatering well 4 above the submersible pump 6, and the head of the submersible pump 6 is more than 30m. More than 50mm in diameter, the suction pipe 7 is a rigid PVC pipe, and the main functions of the dewatering well 4 are water collection, dewatering and pumping and drainage. The size of the dewatering well 4 and the specifications of the submersible pump 6 are all set according to actual needs. Suction pipe 7 can not be flexible pipe, must use hard PVC pipe, in order to avoid the sand in the water that pumps up pipe is blocked, and the damping of its hard PVC pipe and the water outlet joint of submersible pump is connected with 300~500mm long flexible pipe. Water filter net 11 and fiber net 16 all can adopt old safety net to replace, reach the effect of waste utilization. After the basement construction is completed, the dewatering well in the foundation pit will be backfilled together with the side wall soil of the basement, and its steel cage can be taken out and reused before backfilling.

实施例2:Example 2:

本实施例与实施例1不同之处在于:所述步骤(2)中的疏水沟3平面布置为弯转结构,疏水沟3出水口端与步骤(3)中的降水井4连通。也就是说本实施例中的疏水沟3可以在承台间弯转,只要能够把水送到降水井4即可。The difference between this embodiment and Embodiment 1 lies in that the planar layout of the drain ditch 3 in the step (2) is a curved structure, and the outlet end of the drain ditch 3 communicates with the dewatering well 4 in the step (3). That is to say, the drainage ditch 3 in the present embodiment can be bent between the caps, as long as the water can be sent to the dewatering well 4.

上述具体实施方式为本发明的优选实施例,并不能对本发明进行限定,其他的任何未背离本发明的技术方案而所做的改变或其它等效的置换方式,都包含在本发明的保护范围之内。The specific implementation described above is a preferred embodiment of the present invention, and does not limit the present invention. Any other changes or other equivalent replacement methods that do not deviate from the technical solution of the present invention are included in the scope of protection of the present invention. within.

Claims (5)

1. a high water level waterproof construction method for bottom plate of basement, is characterized in that, comprises the following steps:
(1) first utilize the water-stop curtain of pattern foundation pit supporting structure, by the water of foundation depth scope soil layer, only every beyond foundation ditch periphery, ground and the foundation ditch bottom perimeter at pattern foundation pit supporting structure all arranges perforation gutter simultaneously;
(2) the hydrophobic ditch that more than 1 the loose brick of use and fleece are built into is set below the interval location between basement bottom board pile cap, pile cap bottom is apart from hydrophobic ditch top 500~1000mm, the construction method of described hydrophobic ditch is: the loose brick that is first 60~120mm in the bottom of hydrophobic ditch tiling a layer thickness, the loose brick that the equal laying depth in hydrophobic ditch both sides is 120~240mm, the inner space width of hydrophobic ditch is 120~160mm, the interior empty pine of hydrophobic ditch is filled out the rubble that particle diameter is 20~30mm, the top tiling thickness of hydrophobic ditch is that 60~120mm length is the loose brick of 240mm, between the loose brick at top and loose brick, stay the wide sluicing seam of 30~60mm, then at the top of hydrophobic ditch pine brick upper surface and both sides pine brick external surface, lay 2~3 layers of fleece, fleece is every square centimeter of 9~16 orders, bottom and the dewatering well of hydrophobic ditch have 0.5~1% the gradient simultaneously, water in ditch is drained toward dewatering well smoothly,
(3) at foundation ditch periphery, by hydrophobic ditch water outlet end, corresponding dewatering well is set, dewatering well is located at the outside apart from basement basis outermost peripheral, and submersible pump is set in dewatering well, and submersible pump is communicated with gutter by drinking-water pipe.
2. high water level waterproof construction method for bottom plate of basement according to claim 1, it is characterized in that, the excavation method of the dewatering well in the hydrophobic ditch in described step (2) and step (3) is: when pit earthwork digs to the absolute altitude of half height of pile cap, according to the layout plan of hydrophobic ditch and dewatering well, measure unwrapping wire, after completing, carry out the soil excavation of hydrophobic ditch and the soil excavation of dewatering well simultaneously.
3. high water level waterproof construction method for bottom plate of basement according to claim 1, is characterized in that: the dewatering well in described step (3) is located at apart from beyond the outermost peripheral 600mm of basement basis.
4. high water level waterproof construction method for bottom plate of basement according to claim 1, is characterized in that: the hydrophobic ditch layout in described step (2) is elongated communicating structure or non-elongated communicating structure.
5. high water level waterproof construction method for bottom plate of basement according to claim 1, is characterized in that: the hydrophobic ditch layout in described step (2) is for curving structure, and hydrophobic ditch water outlet end is communicated with the dewatering well in step (3).
CN201210065838.XA 2012-03-13 2012-03-13 Waterproof construction method for bottom plate of high-water-level basement Expired - Fee Related CN102535488B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210065838.XA CN102535488B (en) 2012-03-13 2012-03-13 Waterproof construction method for bottom plate of high-water-level basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210065838.XA CN102535488B (en) 2012-03-13 2012-03-13 Waterproof construction method for bottom plate of high-water-level basement

Publications (2)

Publication Number Publication Date
CN102535488A CN102535488A (en) 2012-07-04
CN102535488B true CN102535488B (en) 2014-03-26

Family

ID=46343393

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210065838.XA Expired - Fee Related CN102535488B (en) 2012-03-13 2012-03-13 Waterproof construction method for bottom plate of high-water-level basement

Country Status (1)

Country Link
CN (1) CN102535488B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103898943B (en) * 2014-03-26 2016-06-15 东莞市建之都建设工程有限公司 A kind of basement water resource Collection utilization method and water circulation utilization system
CN104480964B (en) * 2014-11-24 2016-01-06 广西壮族自治区冶金建设公司 A kind of underground waterproof basic unit local emits water source construction method
CN104805855A (en) * 2015-02-25 2015-07-29 成都格瑞思文化传播有限公司 Drainage device
CN104805856A (en) * 2015-03-31 2015-07-29 成都聚智工业设计有限公司 Water lowering and drainage mechanism
CN106498910B (en) * 2015-07-07 2018-05-11 苏州汇诚智造工业设计有限公司 A kind of force reduction pool bottom construction or strengthening construction automatic drain system
CN105350552A (en) * 2015-09-25 2016-02-24 中国二十冶集团有限公司 Underground water control method for backfilled sediment layer
CN106632871B (en) * 2017-01-04 2018-09-14 广东锦绣天地市政工程有限公司 A kind of anti-plastic-steel sheet pile that fractures of high intensity
CN106836252A (en) * 2017-03-14 2017-06-13 中国十七冶集团有限公司 Tower crane combination precipitation pipe well forms the construction method of natural drainage and recycling
CN108868063A (en) * 2018-06-07 2018-11-23 上海宝冶集团有限公司 A kind of method for constructing terrace
CN108867674A (en) * 2018-08-17 2018-11-23 南京吉士达防水工程有限公司 Basement waterproofing keeps the temperature drainage system
CN112921999A (en) * 2021-01-26 2021-06-08 中建四局第一建筑工程有限公司 Structure of integrated circulating system for recycling rainwater in drainage zone of lower layer of bottom plate of high-water-level basement and construction method of structure

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19935366A1 (en) * 1998-07-29 2000-02-03 Zueblin Ag Foundation pit of floor plate and sidewalls depresses floor plate below sidewall ends and joins these via arched sector of floor plate thickness to resist floor lift via ground-embedded ties.
CN201125391Y (en) * 2007-09-11 2008-10-01 中国建筑第六工程局有限公司 Basement waterproofing drainage structure
CN101446084B (en) * 2007-11-27 2010-06-02 贵阳铝镁设计研究院 Underground building outdoor-indoor water drainage combination structure and method thereof
CN201883450U (en) * 2010-11-25 2011-06-29 中国京冶工程技术有限公司 Coastal deep-foundation anti-seepage waterproof basement structure
CN202440826U (en) * 2012-03-13 2012-09-19 广东中城建设集团有限公司 Waterproof system for high-water level basement foundation slabs

Also Published As

Publication number Publication date
CN102535488A (en) 2012-07-04

Similar Documents

Publication Publication Date Title
CN102535488B (en) Waterproof construction method for bottom plate of high-water-level basement
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN105544576B (en) A kind of foundation pit Yield rainfall relation excavation method
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN109972643A (en) A three-in-one combined precipitation system for foundation pit engineering in water-rich areas
CN110004935A (en) A local deep pit diversion drainage ditch system and construction method
CN110397050B (en) Beam-anchor type light drainage retaining wall and construction method thereof
CN112281882A (en) Method for treating water and sand gushing from substrate
CN111236284A (en) A method and structure for groundwater drainage at the bottom of a basement and surrounding areas
CN105569094A (en) Water discharge and drainage system and construction method adopting basement bottom plate water buoyant force releasing method
CN113931209A (en) Large-area deep foundation pit weakly permeable stratum underground water level control method
CN202440826U (en) Waterproof system for high-water level basement foundation slabs
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN114855846A (en) Underground seepage-proofing pressure-reducing anti-floating blind pipe structure and construction method thereof
CN214245855U (en) Water-proof pressure-control anti-floating structure
CN205662938U (en) Drainage excavation structure falls in foundation ditch
CN112195980A (en) Water-resisting pressure-controlling anti-floating structure and construction method
CN106638641B (en) Base pit dewatering well structure and its construction method
CN113565172B (en) Construction method for pumping and injecting water wells in underground reservoirs of open-pit mine dumps
CN104975610A (en) Expanded-end decompression well, deep foundation pit structure and construction method for expanded-end decompression well
CN113123358B (en) Ship pool deformation prevention and control structure under action of uneven settlement of coal mining and construction method
CN112523272B (en) Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof
CN211547830U (en) Structure for preventing ground from being wetted
JP5669192B2 (en) Quay structure or revetment structure
CN115710913A (en) Foundation pit supporting method for water-rich weak geology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140326