CN102209183A - system and method for monitoring program making process and cost - Google Patents

system and method for monitoring program making process and cost Download PDF

Info

Publication number
CN102209183A
CN102209183A CN2010101352495A CN201010135249A CN102209183A CN 102209183 A CN102209183 A CN 102209183A CN 2010101352495 A CN2010101352495 A CN 2010101352495A CN 201010135249 A CN201010135249 A CN 201010135249A CN 102209183 A CN102209183 A CN 102209183A
Authority
CN
China
Prior art keywords
program
cost
control device
information
task
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010101352495A
Other languages
Chinese (zh)
Other versions
CN102209183B (en
Inventor
曹志强
刘磊
刘希伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Digital Video Beijing Ltd
Original Assignee
China Digital Video Beijing Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Digital Video Beijing Ltd filed Critical China Digital Video Beijing Ltd
Priority to CN201010135249.5A priority Critical patent/CN102209183B/en
Publication of CN102209183A publication Critical patent/CN102209183A/en
Application granted granted Critical
Publication of CN102209183B publication Critical patent/CN102209183B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Stored Programmes (AREA)

Abstract

The invention, which belongs to the production technical field of a TV station program, discloses a system and a method for monitoring a program making process and a program making cost. In the prior art, because the completion situation of a program making task and cost information of the program making can not be known timely, a potential safety hazard exists and costs of finished programs can not be checked. According to the monitoring method provided in the invention, a selected topic is established by a topic selection device, and the established selected topic is sent to a control device; a production program task /production program tasks is/ are sent to a or a plurality of production devices by the control device according to the content of the selected topic; After the production device /the production devices receive/ receives the task/ the tasks, a program is produced; and result information of program production and cost information of program production are feedbacked to the control device; and the task completion state/ states and cost information are updated by the control device according to the information feedbacked by the production device/devices. According to the invention, information of a program making flow can be grasped timely, and the check on the program cost can be realized easily.

Description

The supervisory control system and the method for a kind of program making process and cost
Technical field
The invention belongs to the station synchronization production technical field, be specifically related to the supervisory control system and the method for a kind of program making process and cost.
Background technology
In station synchronization manufacturing process, selected topic project staff can create the selected topic according to factors such as program source, types in planning first phase program, issue the relevant collection of material task of including for simultaneously acceptance system, acquisition system, manufacturing system etc.After task issues, all be the people who belongs to different departments because the task reception staff waits with the practical operation personnel, often be dispersed in different rooms and floor even strange land, traditional communication mode often can not be reacted the actual implementation status of task timely.The project staff is after the task of issuing for the selected topic, and compiling single member needs scheduling programs, and programme needs broadcasting list to give broadcast after finishing.Whether owing to can't in time recognize the performance of task, unclear actual program making meeting is not gone wrong, can change, and therefore usually in the festival-gathering of volume monocycle a large amount of work that repeat repeatedly takes place.And ageing very strong program tends to therefore produce the program that directly broadcasts without the volume list in a large number because execution information can not be grasped to have influence on completely to be compiled single and broadcast.Because programme is inconsistent with actual broadcast record, thereby there is hidden danger in fail safe.
In addition, because the information of each link is all disperseed in the program making process, therefore cause and can't carry out cost accounting to final finished product program, transaction has a negative impact to program.
Summary of the invention
At the defective that exists in the prior art, the purpose of this invention is to provide the supervisory control system and the method for a kind of program making process and cost.This system and method can solve the problem that the task executions state can't be monitored and program making cost accounting information dispersion lacks in the program making process.
To achieve these goals, the technical solution used in the present invention is as follows:
The supervisory control system of a kind of program making process and cost comprises:
Titles selector is used for creating the selected topic;
Control device is used for issuing the program making task according to the selected topic that titles selector is created;
Generating apparatus is used for the task of issuing according to control device and generates program, and program is generated object information and program manufacturing cost feedback information is given control device;
Described control device also is used for after receiving the information that generating apparatus returns, updating task completion status information and cost information.
The supervisory control system of aforesaid program making process and cost, wherein, generating apparatus comprises the device of including that is used to include program, is used to gather the employing device of program, and the producing device that is used to programme.
The supervisory control system of aforesaid program making process and cost, wherein, generating apparatus immediately program is generated object information after program generates and program manufacturing cost feedback information is given control device.
The method for supervising of a kind of program making process and cost may further comprise the steps:
The selected topic of creating the selected topic and will creating sends to control device;
Control device sends the program task that generates according to selected topic content to one or more generating apparatus;
After generating apparatus receives task, generate program, and program generated object information and program manufacturing cost feedback information is given control device;
Control device is according to generating apparatus feedack updating task completion status and cost information.
The method for supervising of aforesaid program making process and cost, wherein, the mode of generating apparatus generation program comprises includes, gathers and make.
The method for supervising of aforesaid program making process and cost wherein, generates program object information and program manufacturing cost feedback information immediately and gives control device after program generates.
System and method of the present invention, in the program making process, by setting up the mode of task implementation status and cost information immediate feedback mechanism, can not have the compartment of terrain and trigger next step flow process, make selected topic project staff and compile single member grasp programming process information in time, reasonably arrange work.Simultaneously, by the unified management of cost information, the cost that whole program is made each link comes into plain view, and can realize at an easy rate the cost of program is adjusted.
Description of drawings
Fig. 1 is the structured flowchart of supervisory control system in the embodiment;
Fig. 2 is the structure and the data flow diagram of supervisory control system in the embodiment;
Fig. 3 is the flow chart of method for supervising in the embodiment;
Fig. 4 is the structure chart of data object in the embodiment.
Embodiment
Below in conjunction with embodiment and accompanying drawing, describe the present invention.
The present invention is mainly used in the station synchronization production field, and Fig. 1 is the structured flowchart of a kind of execution mode of supervisory control system of the present invention.This system comprises titles selector 11, the control device 12 that is connected with titles selector 11, and the generating apparatus 13 that is connected with control device 12.
Titles selector 11 is used for creating the selected topic, and the selected topic that will create sends to control device 12.Titles selector 11 can be provided with a plurality of according to system's needs.Control device 12 is used for issuing the program making task according to the selected topic that titles selector 11 is created to generating apparatus 13.The task that generating apparatus 13 is used for issuing according to control device 12 generates program, and the cost information of object information that immediately program is generated and program generation feeds back to control device 12.Control device 12 after receiving the information that generating apparatus 13 returns, the cost information that the completion status information of updating task and program generate.
Generating apparatus 13 comprises multiple arrangement, sets according to the different modes that program generates.In the present embodiment, generating apparatus 13 comprises includes device 131, harvester 132 and producing device 133.Include device 131 and be used to include program, harvester 132 is used to gather program, and producing device 133 is used to programme.Generating apparatus 13 can be expanded according to other modes that program generates.
In said system, control device 12 is core apparatus, and unified interface externally is provided, and other install according to the interface specification calling interface.Like this, control device 12 can insert other devices at an easy rate, convenient expansion.Control device 12 is collected all titles selectors 11 and is selected a topic, and according to the selected topic program generation task is handed down to include, gather, generating apparatus 13 such as making, again that various generating apparatus 13 feedacks are unified to control device 12, updating task is finished object information and cost information.
Fig. 2 is an example of system shown in Figure 1.Control device 12 with include device 131, harvester 132 and producing device 133 and be connected.Control device 12 is selected a topic according to titles selector 11, task is handed down to includes device 131, harvester 132 and/or producing device 133.Include, after collection and/or producing device receive task, generate program, and object information and cost information are fed back to control device 12.
Fig. 3 is the method flow diagram that adopts system shown in Figure 1 monitor programme manufacturing process and cost of manufacture.This method may further comprise the steps:
(1) creates the selected topic of selecting a topic and will create and send to control device.
(2) control device sends the program task that generates according to selected topic content to one or more generating apparatus.
(3) after generating apparatus receives task, generate program, and will generate object information and manufacturing cost feedback information to control device.
The mode of generating apparatus generation program comprises includes, gathers and make, and correspondence is included device, harvester and producing device respectively.Receive the task of including if include device, then begin to include program according to the task of including, will include object information after finishing and include the cost information immediate feedback and give control device when including.If harvester receives acquisition tasks, then begin to gather program according to acquisition tasks, after finishing, collection gives control device with collection result information and the immediate feedback of acquisition cost information.If producing device receives the making task, then begin to programme according to the making task, after completing, will make object information and the immediate feedback of cost of manufacture information and give control device.
(4) control device is according to generating apparatus feedack updating task completion status and cost information.
Fig. 4 is the structure chart of data object in the present embodiment.Selected topic information comprises selected topic state information and selected topic cost information, and selected topic cost information is formed by including cost, acquisition cost and cost of manufacture etc.Selected topic information externally provides unified interface.This structure has made things convenient for the expansion of selected topic information subclass, and the expansion of selected topic cost information subclass.If increase other guide in the selected topic information, the mode of perhaps forming selected topic cost information increases, and then is easy to new content is added in the system.
Obviously, those skilled in the art can carry out various changes and modification to the present invention and not break away from the spirit and scope of the present invention.Like this, if of the present invention these are revised and modification belongs within the scope of claim of the present invention and equivalent technology thereof, then the present invention also is intended to comprise these changes and modification interior.

Claims (6)

1. the supervisory control system of program making process and cost comprises:
Titles selector (11) is used for creating the selected topic;
Control device (12) is used for issuing the program making task according to the selected topic that titles selector (11) is created;
Generating apparatus (13) is used for the task of issuing according to control device (12) and generates program, and program is generated object information and program manufacturing cost feedback information is given control device (12);
Described control device (12) also is used for after receiving the information that generating apparatus (13) returns, updating task completion status information and cost information.
2. the supervisory control system of program making process as claimed in claim 1 and cost, it is characterized in that: described generating apparatus (13) comprise be used to include program include device (131), be used to gather the employing device (132) of program, and the producing device that is used to programme (133).
3. the supervisory control system of program making process as claimed in claim 1 or 2 and cost is characterized in that: described generating apparatus (13) immediately program is generated object information after program generates and program manufacturing cost feedback information is given control device (12).
4. the method for supervising of program making process and cost is characterized in that may further comprise the steps:
The selected topic of creating the selected topic and will creating sends to control device;
Control device sends the program task that generates according to selected topic content to one or more generating apparatus;
After generating apparatus receives task, generate program, and program generated object information and program manufacturing cost feedback information is given control device;
Control device is according to generating apparatus feedack updating task completion status and cost information.
5. the method for supervising of program making process as claimed in claim 4 and cost is characterized in that: the mode of generating apparatus generation program comprises includes, gathers and make.
6. as the method for supervising of claim 4 or 5 described program making processes and cost, it is characterized in that: after program generates, immediately program is generated object information and program manufacturing cost feedback information and give control device.
CN201010135249.5A 2010-03-29 2010-03-29 system and method for monitoring program making process and cost Expired - Fee Related CN102209183B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010135249.5A CN102209183B (en) 2010-03-29 2010-03-29 system and method for monitoring program making process and cost

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010135249.5A CN102209183B (en) 2010-03-29 2010-03-29 system and method for monitoring program making process and cost

Publications (2)

Publication Number Publication Date
CN102209183A true CN102209183A (en) 2011-10-05
CN102209183B CN102209183B (en) 2014-06-04

Family

ID=44697828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010135249.5A Expired - Fee Related CN102209183B (en) 2010-03-29 2010-03-29 system and method for monitoring program making process and cost

Country Status (1)

Country Link
CN (1) CN102209183B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020110274A1 (en) * 2001-01-26 2002-08-15 Hiroshi Yamamoto Image processing method
CN1416263A (en) * 2002-11-26 2003-05-07 廖作全 System for controlling and managing post production facilities in TV station

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020110274A1 (en) * 2001-01-26 2002-08-15 Hiroshi Yamamoto Image processing method
CN1416263A (en) * 2002-11-26 2003-05-07 廖作全 System for controlling and managing post production facilities in TV station

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
皇甫潇红: "电视编辑机房制作设备管理系统设计方案", 《广播电视信息》, 31 May 2008 (2008-05-31), pages 88 - 90 *

Also Published As

Publication number Publication date
CN102209183B (en) 2014-06-04

Similar Documents

Publication Publication Date Title
CN108536100A (en) Intelligent MES end stations manufacturing monitoring system
CN104494653B (en) A kind of track traffic synthetic monitoring system
CN108305008A (en) A kind of working method of online resource sharing service platform
CN101867226B (en) Wide-area distribution type data collection method for dispatching automation system
EP3690561B1 (en) Method and system for 3d visually monitoring a building, and memorizer
EP3167528A1 (en) System and method for determining the suitability of a plurality of electrical producers and consumers which are operated in a network as a virtual power plant for providing control power
CN104639587A (en) Robot fault monitoring system and method based on Internet of Things
CN106130185A (en) A kind of monitoring system of electric substation modeling method based on status monitoring information
CN103019201A (en) Remote control method and device based on three-dimensional virtual scene
CN114374604B (en) Offline mode intelligent home configuration method, storage medium and system
CN111597183A (en) Intelligent negative difference early warning system for steel rolling and early warning method thereof
CN104484751A (en) Dynamic optimization method and device for production planning and resource allocation
CN111221310A (en) System and method for acquiring utilization rate of sewing workshop
CN115241977A (en) An integrated load precision control system for grid-saving and ground-distribution
CN104463465A (en) Real-time monitoring cluster processing method based on distributed models
CN111667250A (en) Cloud-based management method and system for automatic test execution machine
CN101807075A (en) Automatic control system of hot rolled strip steel leveling unit
CN105204481B (en) A kind of clothes manufacture pull type SC management system
CN101149680A (en) Dynamically changing, graphic configuration resource management method
CN103699760B (en) A kind of multilayer closed-loop main station detection data source simulation method
CN102209183B (en) system and method for monitoring program making process and cost
CN103731319B (en) Distribution scheduling platform remote control trouble intelligent diagnosing method
JP2014203116A (en) Remote monitoring control system and remote monitoring control method
CN106059073A (en) Programmed control method based on cooperative misoperation prevention of master station and substation
CN101206475A (en) On-line equipment auxiliary managerial method and system using said method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140604

Termination date: 20170329