CN101929340B - Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process - Google Patents

Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process Download PDF

Info

Publication number
CN101929340B
CN101929340B CN200910227790A CN200910227790A CN101929340B CN 101929340 B CN101929340 B CN 101929340B CN 200910227790 A CN200910227790 A CN 200910227790A CN 200910227790 A CN200910227790 A CN 200910227790A CN 101929340 B CN101929340 B CN 101929340B
Authority
CN
China
Prior art keywords
grouting
pipe
pipe shed
construction
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910227790A
Other languages
Chinese (zh)
Other versions
CN101929340A (en
Inventor
闫昕岭
李国栋
吕振铎
郭成方
李雪峰
申天存
张自新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PINGDINGSHAN COAL MINING CONSTRUCTION GROUP CO Ltd
Original Assignee
PINGDINGSHAN COAL MINING CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PINGDINGSHAN COAL MINING CONSTRUCTION GROUP CO Ltd filed Critical PINGDINGSHAN COAL MINING CONSTRUCTION GROUP CO Ltd
Priority to CN200910227790A priority Critical patent/CN101929340B/en
Publication of CN101929340A publication Critical patent/CN101929340A/en
Application granted granted Critical
Publication of CN101929340B publication Critical patent/CN101929340B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

煤矿井下平斜巷管棚预注浆超前支护施工工艺,包括以下步骤:(1)止浆墙的施工;(2)管棚钻孔施工包括布孔,造孔;(3)管棚钻孔洗孔施工;(4)管棚安装施工;(5)管棚预注浆施工;(6)然后按照步骤(2)~(5)循环,施工一个管棚钻孔,安装一个孔,注浆一个孔,直至注浆结束;工作面管棚预注浆9m,掘进6m、预留3m超前距或者掘进7m、预留2m超前距;向前掘进后,再次管棚预注浆时,按步骤(2)~(5)施工时,不再施工止浆墙,在工作面迎头直接喷射混凝土即可,直至巷道施工完该区段为止。本发明工艺结构简单,施工速度快,成本低,安全可靠,风险小,还能确保巷道质量,经济效益极为明显。The construction technology of pre-grouting and advanced support for pipe sheds in horizontal and inclined lanes in coal mines includes the following steps: (1) construction of grout-stop walls; (2) pipe shed drilling construction including hole layout and hole making; (3) pipe shed drilling (4) Pipe shed installation and construction; (5) Pipe shed pre-grouting construction; (6) Then follow the steps (2) to (5) cycle, construct a pipe shed drilling, install a hole, inject Grout one hole until the grouting is completed; pre-grout the pipe shed on the working face for 9m, excavate 6m, reserve 3m ahead distance or excavate 7m, reserve 2m ahead distance; During the construction of steps (2) to (5), the grout stop wall is no longer constructed, and the concrete can be sprayed directly on the working face until the section of the roadway is completed. The invention has the advantages of simple process structure, fast construction speed, low cost, safety and reliability, low risk, and can ensure the quality of the roadway, and the economic benefit is extremely obvious.

Description

The coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process
Technical field
The present invention relates to a kind of coal mine underground flat inclined tunnel and pass coal seam, half-edge coal seam, incompetent bed, structure zone of fracture and the bright inclined shaft of surface soil layer and pass building, arterial railway supply line and riverbed section, use the work plane pipe shed pre-grouting advance support construction process.
Background technology
Coal is the main energy sources of China's industry and the national economic development.China's superficial part coal resources reduce because of continuing exploitation in a large number at present, and the mining depth of mine is more and more darker.The coal resources buried depth of China is 2.95 trillion tons below 1000m, accounts for 53% of coal resources total amount.The coal mining degree of depth increases with the speed of annual 8-12m at present.A lot of at present existing a plurality of work planes enter into the degree of depth of 1000m to 1500m.(the ground topsoil is crossed architectural complex, crosses the railway division and is crossed riverbed section etc. for Deep Mine and ground " three times engineerings ".) development and utilization be China's mining industry development trend from now on.The coal seam that runs in the work progress of mine deep, half-edge coal seam, incompetent bed, structure zone of fracture and the bright inclined shaft of topsoil are crossed building, railway division, riverbed section etc., in case the top board roof fall accident takes place, abnormally dangerous.How fast, safety a series of Science and Technology problems such as passes through, and become the great theory and technology problem of mining industry circle.
Summary of the invention
The object of the invention is to provide a kind of coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process; Taking off coal seam, half-edge coal seam, incompetent bed, structure zone of fracture and the bright inclined shaft of topsoil etc.; Through the preparatory slip casting of work facial canal canopy formula; Can prevent effectively that the tunnel from caving in, large tracts of land roof fall, wall caving, the accident of stopping takes place; Construction technology is simple in structure, and speed of application is fast, and cost is low, and is safe and reliable, and risk is little, can also guarantee roadway quality.
To achieve these goals, the present invention adopts following technical scheme:.The coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process may further comprise the steps:
(1) construction of wall for grouting: do drill site in face of the headwork, extend out the ditching groove by design size to the tunnel outline line, assemble wall for grouting one, the wall for grouting both sides assemble with work stone, middle dead slot concreting; Before assembling,, aqueduct is installed water is derived the place of tunnel water outlet; Wall for grouting assembles in the process, according to design orientation, inclination angle, and pre-buried orifice tube between 250~400mm outside the waste section in tunnel; Orifice tube exposes 150mm, apart from flange 100mm place, welds a joint that has screw thread in advance; Wall for grouting assembles back injection concrete and fills and leads up tunnel and wall for grouting periphery joining place; After solidifying 24 hours,, reinforce wall for grouting earlier the aqueduct slip casting shutoff of pre-buried water guide;
(2) pipe canopy drilling construction: evenly deployment tube canopy boring of 300~500mm periphery outside the waste section in driving face arch, the pipe canopy spacing of wells is 250~400mm, the degree of depth is 9m;
The cloth hole: the cloth hole method that pipe shed pre-grouting adopts " perimeter hole and mider hole " to combine, " perimeter hole " make in the outer 5m scope of tunnel net section and are consolidated into integral body, and " mider hole " carries out the reinforcement grouting and reinforcing to integral body; Surface soil layer zone of fracture rock crack is consolidated into firm integral body with the slurries filling is full, is consolidated into firm integral body to pipe canopy and tunnel-surrounding country rock;
Pore-creating: in the time of the construction wall for grouting, by the orifice tube of design orientation, inclination angle pre-buried good " perimeter hole "; " mider hole " not pre-buried orifice tube, directly construction on the wall; Put up workbench, rig handling fixation to the workbench; Construction drill, when running into broken dirt bed and not advancing, cleaning bottom of hole repeatedly, repeatedly slip-casting is until constructing to projected depth;
(3) pipe canopy boring hole flushing construction: after pore-creating reaches projected depth, connect the hole flushing pipeline, clean up mud and drilling cuttings in the boring with water under high pressure;
(4) pipe canopy installation: slowly down at the bottom of the hole, dock pipe boron steel pipe the flange on the pre-buried orifice tube with double buckle flange on managing the boron steel pipe tightly, use bolt; Behind all the other inlet well pore-formings, the telescopic type hole packer is installed, and is tightened the big nut on the hole packer, it is closely knit that rubber cushion and borehole circumference are fully meshed, the fixation of pipe boron steel pipe;
(5) pipe shed pre-grouting construction: grouting pipeline is installed; At any time adjust flow, concentration of slurry according to the slip casting situation; Let in the pipe canopy boring slurries along the outside overfall of boring during slip casting; Make to be full of after slurries and the slip casting soil layer around the pipe boron steel pipe or zone of fracture forms firm integral body, grouting pressure reaches the design grouting pressure, can stop slip casting;
(6) then according to step (2)~(5) circulation, a hole is installed in the pipe canopy boring of constructing, and finish until slip casting in hole of slip casting; Work plane pipe shed pre-grouting 9m, driving 6m, the leading distance of reservation 3m are perhaps tunneled 7m, are reserved the leading distance of 2m; Forward behind the driving, once more during pipe shed pre-grouting, (2) set by step~(5) construction, the wall for grouting of no longer constructing get final product at the work plane direct injection concrete of meeting head on, till roadway construction finishes this section.
Described step (5) appearance is run, the processing of spillage: in the slip casting process, find race, spillage phenomenon, the method for can run according to the scene, the spillage situation being taked to stick with paste, stop, put notes is handled, to reduce slurries loss.
The grouting pressure of design is 8~10MPa in the described step (5).
Evenly deployment tube canopy boring of 400~500mm periphery outside the waste section in driving face arch in the described step (2), the pipe canopy spacing of wells is 300~400mm.
Evenly deployment tube canopy boring of 300~400mm periphery outside the waste section in driving face arch in the described step (2), the pipe canopy spacing of wells is 250~300mm.
Slip casting in the described step (5) utilizes the two fluid grouting principle to adopt the cement-sodium silicate slurries full the filling of tunnel-surrounding 5m scope inner pore.
The present invention has the following advantages:
1. coal mine underground flat inclined tunnel work facial canal canopy formula pre-grouting advance support of the present invention was being taken off coal seam, half-edge coal seam, incompetent bed, structure zone of fracture and the bright inclined shaft of surface soil layer through building, arterial railway main line and riverbed section.In tunneling construction, prevention back large tracts of land is caved in and is seriously taken out group, takes out the top, and the pipe canopy spacing of wells is controlled by 250~400mm; The degree of depth is pressed the 9m construction, and 9m pipe canopy pipe is installed, and annotates the biliquid slurry and reinforces; Full the crack of tunnel-surrounding, pore filling; And be consolidated into integral body with periphery, and increased the supporting capacity in tunnel, improve surrounding rock stability.Total collapse, large tracts of land roof fall and wall caving have been avoided in the tunnelling process.
2. coal mine underground flat inclined tunnel work facial canal canopy formula pre-grouting advance support construction process is simple in structure, and speed of application is fast, and cost is low, and is safe and reliable, and risk is little, can also guarantee roadway quality.Economic benefit is very obvious, and the social benefit of bringing thus that safety realized is then more considerable.
In the step (1), flange purposes: dock with the equivalent diameter of pipe canopy pipe welding and to fix the closed orifices pipe.Pre-buried orifice tube effect: pipe canopy pipe is scurried out when preventing slip casting.The joint purposes of band screw thread: the top valve that diameter 25mm is arranged, slip casting play scavenging action when just having begun, and close upper valve when air has been arranged the back pulp.
In the step (5), in the slip casting process, pressure advances to starch smooth and easy for a short time, explain strong, the space is big; Can annotate single liquid slurry, increase liquid slurry concentration, boost gradually; Increase flow rate of grouting, with the thick slurries of high pressure the water content in the crack is swapped out as early as possible, along with slurries inject injecting cement paste continually.The pressure big crack of fast explanation injecting cement paste of rising is annotated in fact basically, in order to be full of the slurries state that reaches capacity in the injecting cement paste, can reduce concentration of slurry, reduces flow, and raising pressure makes that tiny empty crack is full of slurries in the injecting cement paste.
The specific embodiment
Coal mine underground flat inclined tunnel work facial canal canopy formula pre-grouting advance support construction process of the present invention comprises the wall for grouting construction, pipe canopy drilling construction, pipe canopy boring hole flushing construction, pipe canopy fabrication and installation construction and pipe shed pre-grouting construction.
As a kind of improvement of patented technology of the present invention, 400~500mm periphery cloth hole outside taking off coal seam, half-edge coal seam, incompetent bed, the waste section in work plane arch, structure zone of fracture tunnel, the pipe canopy spacing of wells 300~400mm.Pipe canopy bore direction, inclination angle and orientation, tunnel, inclination angle are consistent, and join ¢ 89mm auger stem or ¢ 50mm round drill rod with ZDY1200S type (or SGZ150 type) all-hydraulic drill, make ¢ 90mm boring; ¢ 75mm * 9m pipe canopy pipe is installed; Two fluid grouting is reinforced, and utilizes the two fluid grouting principle full fracture filling in the tunnel-surrounding 5m scope, and is consolidated into one; Increase the supporting capacity of roadway surrounding rock; Be consolidated into firm integral body to pipe canopy pipe and tunnel-surrounding country rock, strengthened the support coefficient of country rock, improved surrounding rock stability.Driving 7m stays the leading distance of 2m.When for the second time construction pipe canopy is holed preparatory slip casting, in advance on section, spray the thick concrete of 300mm, directly cloth hole construction, circulation successively at 2m.Bypassed traditional beat advance anchor bolt->driving->anchor net spray temporary lining->take out top (or taking out group)->with round log stop the top->frame U type metal shed->be sprayed onto construction technology such as design thickness (or formwork erection, build concrete) again.
Further improvement as patented technology of the present invention; Bright inclined shaft is crossed building, arterial railway main line and riverbed section etc. through surface soil layer; 300~400mm periphery is evenly arranged comb canopy boring outside the waste section in driving face arch; Pitch of holes 250~300mm, Guan Peng orientation, inclination angle and orientation, tunnel, inclination angle are consistent.With the auger stem drill bit that all-hydraulic drill is joined ¢ 89mm, make the boring of ¢ 90mm pipe canopy, ¢ 75mm * 9m pipe canopy pipe is installed; Two fluid grouting is reinforced; Utilize the two fluid grouting principle to adopt the cement-sodium silicate slurries full, and be consolidated into one, increase tunnel supporting capacity on every side the filling of tunnel-surrounding 5m scope inner pore; Be consolidated into firm integral body to pipe canopy pipe and tunnel-surrounding, improve the stability of periphery.Driving 6m stays the leading distance of 3m, successively circulation.Overcome traditional a large amount of excavation open channels, wall caving is repaiied a large amount of side slopes in the construction, drops into too much support form, the human and material resources of labor, financial resources, and construction is complicated, has a big risk.
In the time of practical implementation, roadway head is cleaned out, it is smooth that head-on wall expands brush, and waste section reaches design size to extending out brush, and the materials barnacle is built wall for grouting one, by design orientation, inclination angle pre-buried ¢ 108mm orifice tube.Work plane is for the second time before the pipe roof construction, and the tunnel that requires to have constructed is carried out permanent support and segmentation and carried out can carrying out the pipe roof construction second time after grouting behind shaft or drift lining reinforces.
1. the construction of wall for grouting
Do drill site to 3m in face of the headwork, extend out the groove that digs 200mm to the tunnel outline line, assemble wall for grouting one by design size, wall for grouting thickness 1.0m, both sides assemble each 300mm of thickness with work stone, and it is C that middle dead slot 400mm builds label 25Concrete.Before assembling,, aqueduct is installed water is derived the place of tunnel water outlet.Wall for grouting assembles in the process; According to design orientation, inclination angle; Pre-buried ¢ 108mm * 1.5m orifice tube between 300~400mm outside the waste section in tunnel, orifice tube exposes 150mm, apart from flange 100mm place; One of welding in advance has screw thread, and (joint of ¢ 25mm * 60mm), wall for grouting assemble the back and spray concrete and fill and lead up the peripheral joining place of tunnel and wall for grouting.After solidifying 24 hours,, reinforce wall for grouting earlier the aqueduct slip casting shutoff of pre-buried water guide.
2. job practices
Set up workbench firmly at work plane.Hydraulic drill rig lifted by crane on the workbench fix, proofreaded bore direction and inclination angle, fastening drilling cramp, spud in advance 200mm at a slow speed after, recalibrate the orientation and the inclination angle of boring, can continue to creep into.If in the drilling construction process, run into collapse hole or zone of fracture of foundry loam soil layer and do not pull out of hole during drilling depth, cover the stifled dish of ¢ 108mm double buckle flange (be welded with ¢ 25mm * 50mm on the stifled dish and be with threaded joint); Tighten with bolt, connect grouting pipeline and carry out slip casting, when grouting pressure reaches 5~8MPa, stop slip casting; Carrying out cleaning bottom of hole creeps into; (cleaning bottom of hole) creeps into repeatedly, and repeatedly slip-casting is until the projected depth of constructing.After receiving brill, in the boring of pipe canopy, ¢ 75mm * 9m pipe boron steel pipe is installed (is managed canopy Guan Yitou and be drilled with colored hole, length 1m with electric drill; The other end is welded with the stifled dish of ¢ 108mm flange, welding ¢ 25mm in the middle of the stifled dish * 60mm band wire connection head).Connect grouting pipeline, the beginning grouting and reinforcing.Before the slip casting; Open the ¢ 25mm ball valve on the ¢ 25mm * 60mm joint of flange 100mm place welding on the pre-buried orifice tube; Let in the pipe canopy boring slurries along the outside overfall of boring during slip casting, make to be full of after slurries and the slip casting soil layer around the pipe canopy pipe or zone of fracture forms firm integral body.Sealing of hole pressure controls to about 10MPa.The pipe canopy of constructing is holed, and a hole is installed, and finish until slip casting in hole of slip casting.Work plane pipe shed pre-grouting 9m, driving 6m reserves the leading distance of 3m.After tunneling 6m forward, once more during pipe shed pre-grouting, by former working procedure construction (wall for grouting of no longer constructing get final product at the work plane thick concrete of direct injection 300mm of meeting head on), till roadway construction finishes this section.
3, construction technology
(1). cloth hole: the cloth hole method that pipe shed pre-grouting adopts " periphery and middle part " to combine." perimeter hole " makes in the outer 5m scope of tunnel net section and is consolidated into integral body, and " mider hole " carries out the reinforcement grouting and reinforcing to integral body.Surface soil layer zone of fracture rock crack is consolidated into firm integral body with the slurries filling is full, increases the supporting capacity of roadway surrounding rock rock mass, be consolidated into firm integral body to pipe canopy and tunnel-surrounding country rock, raising country rock resistance to overturning.
(2). pore-creating: in the time of the construction wall for grouting, by the orifice tube of design orientation, inclination angle pre-buried good " perimeter hole "; " mider hole " not pre-buried orifice tube, directly construction on the wall.Put up workbench, rig handling fixation to the workbench.Construction drill, when running into broken dirt bed and not advancing, cleaning bottom of hole repeatedly, repeatedly slip-casting is until constructing to projected depth.
(3). hole flushing: after pore-creating reaches projected depth, connect the hole flushing pipeline, clean up mud and drilling cuttings in the boring with water under high pressure.
(3). the mounting pipe canopy: after hole flushing finishes, artificial pipe boron steel pipe slowly down at the bottom of the hole, dock the flange on the pre-buried orifice tube with double buckle flange on managing the boron steel pipe tightly, use bolt; Behind all the other inlet wells (reinforcement injected hole) pore-forming, the special-purpose hole packer of ¢ 80mm * 3m telescopic type is installed, is tightened the big nut on the hole packer with spanner, it is closely knit that rubber cushion and borehole circumference are fully meshed, and lets rubber cushion fully play effect, the fixation of pipe boron steel pipe.
(4). the installation of grouting pipeline: after pipe canopy pipe installed, the peace spherical valve connected double-liquid high pressure slip-casting pipe, threeway blender, four-way and pressure-relief valve earlier.
(5). tube shed grouting: carry out proportioning according to the slip casting situation, adjust flow, concentration of slurry at any time, note changing grouting pressure with variation, reach the design grouting pressure (8~10MPa), can stop slip casting.
(6). run, the processing of spillage: in the slip casting process, as find to run, the spillage phenomenon, can run according to the scene, methods such as the spillage situation is taked to stick with paste, stop, some notes handle, and lose with the minimizing slurries, reach the slip casting intended purposes.
4, the selection of grouting parameter
(1). the preparation of cement grout: the water/binder ratio of cement grout is 1: 1 (weight ratio).
(2). the volume ratio of cement grout and water glass slurries is 1: 0.6~0.8.
(3) .QBZ-BI type waterproof agent dosage is 3% of a cement weight.
(4). grouting pressure: according to the developmental state and the anti-pressure ability of rock stratum, topsoil, whole hole pressure is by 8~10MPa control.Grouting pressure is the energy of slurries diffusions filling, and the size of grouting pressure depends on size, the topsoil space degree of inlet well hydrostatic pressure.
(5). the diffusion radius: the diffusion radius of slurries is different and different with topsoil, space, rock stratum under the constant situation of pressure, and the diffusion radius of slurries has than big-difference.Therefore, rationally confirm the diffusion radius of slurries, to economical with materials, reduction of erection time, ensuring the quality of products is significant.In conjunction with slip casting experience in the past, grout spreading range is pressed 5m control.
(6). grouting amount: normal grouting amount is to confirm according to the hole that adds solid volume, porosity, slurries setting time, rock stratum of slip casting and the connection situation in crack.Do not run in slip casting under the situation of slurry, make the biliquid slurry inside and outside the tunnel, form curtain as far as possible, full firm integral body, the raising slip casting globality effect of being consolidated into of pore filling.
The curtain-grouting injection rate is calculated as follows: Q=Vna
Q-grouting amount m3, V-need filling and injecting slurry volume m in the formula 3
The n-porosity gets 6%, a-slurries loss coefficient (1.2~1.5) gets 1.4
5. grouting equipment and material are selected:
Pipe shed pre-grouting facilities plan list 1
Figure GSB00000835973400091
Pipe shed pre-grouting material planning list 2
Title The specification title Unit Quantity Remarks
Orifice tube ¢108mm×1.5m Root 1/ every hole Processing
Steel pipe ¢75mm×9m Root 1/ every hole Make pipe canopy pipe
Grouting Pipe ¢80mm×3m Root 1/ every hole The special-purpose hole packer of telescopic type
Flange ¢108mm Individual 1/ every hole
The stifled dish of flange ¢108mm Cover 1/ every hole The stifled dish processing of double buckle flange
Ball valve ¢25mm Individual 3/ every hole
Drilling rod ¢50mm×1.0m Root 100 Round drill rod
Drilling rod ¢90mm×1.5m Root 100 Auger stem
Drill bit ¢89mm Individual 10 Augers
Drill bit ¢91mm Individual 10
(1). cement: select the P.042.5 Portland cement of level of label for use.
(2). water glass: modulus is 2.8~3.2, concentration is the water glass of 38~42 Baume degrees.
(3). additive: really must control QBZ-BI type waterproof agent.
(4). other: I type cement anchoring agent (Gu effective).

Claims (6)

1.煤矿井下平斜巷管棚预注浆超前支护施工工艺,其特征在于:包括以下步骤:1. The construction technology of pre-grouting and advanced support for pipe sheds in horizontal and inclined roadways in coal mines, which is characterized in that it includes the following steps: (1)止浆墙的施工:把掘进工作面前做钻场,按设计尺寸向巷道轮廓线外扩挖沟槽,垒砌一道止浆墙,止浆墙两边用料石垒砌,中间空槽浇筑混凝土;垒砌前,将巷道出水的地方,安装引水管将水导出;止浆墙垒砌过程中,根据设计方位、倾角,在巷道荒断面外250~400mm之间预埋孔口管,孔口管外露150mm,距法兰盘100mm处,事先焊接一个带有丝扣的接头,止浆墙垒砌好后喷射砼把巷道与止浆墙周边衔接处填平,凝固24小时后,先把预埋导水的引水管注浆封堵,加固止浆墙;(1) Construction of the slurry wall: use the front of the excavation work as a drilling site, expand the trench to the outside of the roadway outline according to the design size, and build a slurry wall. The two sides of the slurry wall are built with material stones, and the middle is empty Concrete pouring; before building, install water diversion pipes at the water outlet of the roadway to lead the water out; during the construction of the grout wall, according to the design orientation and inclination angle, the orifice pipe is pre-buried between 250-400mm outside the barren section of the roadway, The orifice pipe is exposed 150mm, 100mm away from the flange, and a joint with a screw is welded in advance. After the grout wall is built, spray concrete to fill the joint between the roadway and the grout wall. After 24 hours of solidification, first Grouting and sealing the pre-buried water diversion pipes, and strengthening the grout-stop wall; (2)管棚钻孔施工:在掘进工作面拱部荒断面外300~500mm周边均匀布置管棚钻孔,管棚钻孔间距为250~400mm,深度为9m;(2) Pipe shed drilling construction: uniformly arrange pipe shed drilling holes around 300-500mm outside the barren section of the arch section of the excavation working face, the spacing of the pipe shed drilling holes is 250-400mm, and the depth is 9m; 布孔:管棚预注浆采用“周边孔与中部孔”相结合的布孔法,“周边孔”使巷道净断面外5m范围内固结成整体,“中部孔”对整体进行补强注浆加固;将地表土层破碎带岩层裂隙用浆液充填饱满固结成坚固整体,把管棚与巷道周边围岩固结成坚固整体;Hole layout: The pre-grouting of the pipe shed adopts the hole layout method combining "peripheral holes and middle holes". Slurry reinforcement; fill the cracks in the rock strata in the broken surface soil layer with slurry to form a solid whole, and consolidate the pipe shed and the surrounding rock around the roadway into a solid whole; 造孔:施工止浆墙的同时,按设计方位、倾角预埋好“周边孔”的孔口管;“中部孔”不预埋孔口管,直接在墙上施工;搭好工作台,把钻机吊运到工作台上固定牢固;施工钻孔,遇到破碎泥土层不进时,反复扫孔,反复注浆,直至施工至设计深度;Hole making: While constructing the grout stop wall, the orifice pipes of the "peripheral holes" are pre-embedded according to the design orientation and inclination angle; the "middle hole" does not pre-embed the orifice pipes, and is directly constructed on the wall; the workbench is set up, and the The drilling rig is hoisted to the workbench and fixed firmly; when the construction drilling encounters the broken soil layer and cannot enter, the hole is repeatedly swept and grouted repeatedly until the construction reaches the design depth; (3)管棚钻孔洗孔施工:造孔达到设计深度后,连接洗孔管路,用高压水把钻孔内泥浆及钻屑清洗干净;(3) Drilling and washing construction of the pipe shed: After the hole reaches the design depth, connect the washing pipeline, and clean the mud and cuttings in the drilling with high-pressure water; (4)管棚安装施工:把管棚钢管慢慢下到孔底,把预埋孔口管上的法兰盘与管棚钢管上的子母扣法兰盘对接严实,用螺栓固定;其余注浆钻孔成孔后,安装伸缩型封孔器,并把封孔器上的大螺母拧紧,使胶垫与钻孔周边充分啮合密实,把管棚钢管固定牢固;(4) Pipe shed installation and construction: Slowly lower the pipe shed steel pipe to the bottom of the hole, connect the flange plate on the pre-buried orifice pipe with the snap button flange plate on the pipe shed steel pipe tightly, and fix it with bolts; the rest After the hole is drilled by grouting, install the telescopic hole sealer, and tighten the big nut on the hole sealer, so that the rubber pad and the periphery of the drill hole are fully meshed and dense, and the steel pipe of the pipe shed is fixed firmly; (5)管棚预注浆施工:安装注浆管路,根据注浆情况随时调整流量、浆液浓度,注浆时让管棚钻孔中浆液顺着钻孔向外回浆,使管棚钢管周围充满浆液与注浆后土层或破碎带形成坚固的整体,注浆压力达到设计注浆压力,即可停止注浆;(5) Pre-grouting construction of the pipe shed: Install the grouting pipeline, adjust the flow rate and slurry concentration at any time according to the grouting situation, and let the grout in the pipe shed drill hole return to the outside along the drill hole during grouting, so that the pipe shed steel pipe The surrounding area is filled with grout and the soil layer or broken zone after grouting forms a solid whole. When the grouting pressure reaches the design grouting pressure, the grouting can be stopped; (6)然后按照步骤(2)~(5)循环,施工一个管棚钻孔,安装一个孔,注浆一个孔,直至注浆结束;工作面管棚预注浆9m,掘进6m、预留3m超前距或者掘进7m、预留2m超前距;向前掘进后,再次管棚预注浆时,按步骤(2)~(5)施工,不再施工止浆墙,在工作面迎头直接喷射混凝土即可,直至巷道施工完该区段为止。(6) Then cycle according to steps (2) to (5), construct a pipe shed drilling, install a hole, and grout a hole until the grouting is completed; the working face pipe shed pre-grouting 9m, excavation 6m, reserved 3m advance distance or 7m excavation, reserve 2m advance distance; after forward excavation, when pre-grouting pipe shed again, follow steps (2) to (5) for construction, do not construct grout stop wall, and spray directly head-on on the working face Concrete will suffice until the section of the roadway is completed. 2.根据权利要求1所述的煤矿井下平斜巷管棚预注浆超前支护施工工艺,其特征在于:所述的步骤(5)出现跑、漏浆的处理:在注浆过程中,发现跑、漏浆现象,可根据现场跑、漏浆情况采取糊、停、点注的方法处理,以减少浆液损失。2. The construction technology of pipe shed pre-grouting advance support in horizontal and inclined lanes in coal mines according to claim 1, characterized in that: the processing of run-off and grout leakage in said step (5): in the grouting process, If running and leaking are found, the method of pasting, stopping and point injection can be adopted according to the situation of running and leaking on site, so as to reduce the loss of slurry. 3.根据权利要求1或2任一项所述的煤矿井下平斜巷管棚预注浆超前支护施工工艺,其特征在于:所述的步骤(5)中设计的注浆压力为8~10MPa。3. According to any one of claims 1 and 2, the construction technology of pre-grouting and advanced support for pipe sheds in horizontal and inclined roadways in coal mines is characterized in that: the grouting pressure designed in the described step (5) is 8-8. 10MPa. 4.根据权利要求3所述的煤矿井下平斜巷管棚预注浆超前支护施工工艺,其特征在于:所述的步骤(2)中在掘进工作面拱部荒断面外400~500mm周边均匀布置管棚钻孔,管棚钻孔间距为300~400mm。4. The construction technology of pipe shed pre-grouting advance support in horizontal and inclined lanes in coal mines according to claim 3, characterized in that: in the step (2), in the excavation working face, the surrounding area is 400-500 mm outside the barren section of the arch. Evenly arrange the drill holes in the pipe shed, and the distance between the drill holes in the pipe shed is 300-400mm. 5.根据权利要求3所述的煤矿井下平斜巷管棚预注浆超前支护施工工艺,其特征在于:所述的步骤(2)中在掘进工作面拱部荒断面外300~400mm周边均匀布置管棚钻孔,管棚钻孔间距为250~300mm。5. The construction technology of pipe shed pre-grouting advance support in horizontal and inclined roadways in coal mines according to claim 3, characterized in that: in the step (2), it is around 300-400 mm outside the barren section of the arch of the excavation face Evenly arrange the drill holes in the pipe shed, and the distance between the drill holes in the pipe shed is 250-300mm. 6.根据权利要求1、2、4或5任一项所述的煤矿井下平斜巷管棚预注浆超前支护施工工艺,其特征在于:所述的步骤(5)中的注浆利用双液注浆原理采用水泥-水玻璃浆液把巷道周边5m范围内孔隙充填饱满。6. According to any one of claims 1, 2, 4 or 5, the construction technology of pre-grouting and advanced support for pipe sheds in horizontal and inclined roadways in coal mines is characterized in that: the grouting in the described step (5) utilizes The principle of double-liquid grouting uses cement-sodium silicate slurry to fill the pores within 5m around the roadway.
CN200910227790A 2009-12-31 2009-12-31 Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process Expired - Fee Related CN101929340B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910227790A CN101929340B (en) 2009-12-31 2009-12-31 Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910227790A CN101929340B (en) 2009-12-31 2009-12-31 Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process

Publications (2)

Publication Number Publication Date
CN101929340A CN101929340A (en) 2010-12-29
CN101929340B true CN101929340B (en) 2012-08-29

Family

ID=43368730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910227790A Expired - Fee Related CN101929340B (en) 2009-12-31 2009-12-31 Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process

Country Status (1)

Country Link
CN (1) CN101929340B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756898A (en) * 2018-06-06 2018-11-06 中铁六局集团有限公司 Using the front pre-grouting construction method of HSC grouting materials

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102128038B (en) * 2011-01-26 2013-11-13 北京中铁瑞威基础工程有限公司 Quick construction method for tunnel pipe shed
CN102182498A (en) * 2011-03-23 2011-09-14 彬县水帘洞煤炭有限责任公司 Comprehensive laneway-supporting method for cracked area in coal mine
CN102182471B (en) * 2011-03-23 2013-05-29 彬县水帘洞煤炭有限责任公司 Advance support method for coal mine tunnel high-risk area
CN102226406B (en) * 2011-05-10 2013-09-18 中铁十二局集团第一工程有限公司 Construction method of super-long advanced anchor bars
CN102493822B (en) * 2011-12-29 2014-04-02 中铁二十三局集团有限公司 Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN102704950B (en) * 2012-06-21 2014-06-11 山东黄金矿业(莱州)有限公司三山岛金矿 Support method used in passing water guide fracture structure in mine exploration
CN102808627A (en) * 2012-09-07 2012-12-05 中国建筑第八工程局有限公司 Underground excavation construction method of steel pipe shed
CN102966359A (en) * 2012-11-09 2013-03-13 山西潞安环保能源开发股份有限公司 Working face ventilation oxidization zone roof control method
CN103821538B (en) * 2013-12-26 2016-09-07 安徽理工大学 J-type horizontal assistant branched hole surface advance grouting paste-making method
CN104790971B (en) * 2015-04-03 2017-06-23 核工业井巷建设集团公司 A kind of advanced pre-add solid method of steel tube shed of the small spacing ground constructing tunnel of shallow embedding
CN105587321A (en) * 2015-12-22 2016-05-18 大同煤矿集团有限责任公司 Collapse column bypassing extraction process
CN105484753B (en) * 2015-12-29 2018-01-23 龙口矿业集团有限公司 The Supporting Method for Drifting of high hydraulic pressure big flow crushed zone
CN106368709B (en) * 2016-09-30 2019-04-23 首钢集团有限公司 A construction method of a vertical shaft
CN106968677A (en) * 2017-03-28 2017-07-21 中国五冶集团有限公司 Method for tunnel construction based on pipe shed support
CN107339108B (en) * 2017-06-26 2019-02-19 中铁十二局集团有限公司 Construction method of subway tube shed in sandy area with enriched groundwater
CN108035738A (en) * 2017-12-08 2018-05-15 中国矿业大学 The anchoring process of more anchor pole simultaneous quantitative slip castings
CN108104840B (en) * 2017-12-14 2019-09-06 中铁四局集团有限公司 One-by-one drilling hole and grouting hole forming method for advanced pipe shed of pebble accumulation layer tunnel and application
CN108678666B (en) * 2018-07-28 2024-02-02 江苏徐工工程机械研究院有限公司 Multifunctional drilling machine and pipe shed mounting device
CN111042820B (en) * 2019-12-27 2021-06-15 中南大学 Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method
CN112855223B (en) * 2021-04-06 2024-05-10 中国矿业大学 Coal roadway-advanced curtain space integrated grouting method after penetrating goaf wall
CN114635727A (en) * 2022-02-25 2022-06-17 华亭煤业集团有限责任公司 Method for improving anchoring effect through outlet water anchoring drilling hole pre-treatment
CN117145523B (en) * 2023-10-31 2023-12-26 煤炭工业太原设计研究院集团有限公司 Sylvite inclined shaft mudstone section roof-falling treatment reinforcing structure and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4193715A (en) * 1978-05-12 1980-03-18 The Eastern Company Mine roof support method and apparatus
CN101235719A (en) * 2008-02-29 2008-08-06 李明远 Prevacuated decompressed soft rock laneway support technology
CN101285385A (en) * 2008-05-29 2008-10-15 中交第二公路勘察设计研究院有限公司 Undermining method for three-dimensional pipe-roof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4193715A (en) * 1978-05-12 1980-03-18 The Eastern Company Mine roof support method and apparatus
CN101235719A (en) * 2008-02-29 2008-08-06 李明远 Prevacuated decompressed soft rock laneway support technology
CN101285385A (en) * 2008-05-29 2008-10-15 中交第二公路勘察设计研究院有限公司 Undermining method for three-dimensional pipe-roof

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
JP特开平6-288196A 1994.10.11
JP特开平8-326489A 1996.12.10
吕继中.超前小管棚注浆施工技术在隧硐工程中的应用.《建筑》.2007,(第08期),第25页. *
张保林.管棚预注浆技术在斜井泥化带施工中的应用.《煤炭工程》.2007,(第05期),第42-43页. *
张文彬.采用注浆加固、管棚支护工艺过陷落柱.《煤矿现代化》.2006,(第05期),第9-10页. *
牟欣河等.引硫济金工程引水隧洞CH1+182处塌方处理.《甘肃水利水电技术》.2001,第37卷(第02期),第150-151、154页. *
陆记霞等.玉蒙铁路秀山隧道涌水涌砂地段施工技术.《隧道建设》.2009,第29卷(第03期),第349-341页. *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756898A (en) * 2018-06-06 2018-11-06 中铁六局集团有限公司 Using the front pre-grouting construction method of HSC grouting materials

Also Published As

Publication number Publication date
CN101929340A (en) 2010-12-29

Similar Documents

Publication Publication Date Title
CN101929340B (en) Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process
CN103410527B (en) Preliminary bracing construction method for tunnel with surrounding rocks containing collapsible loess and soft rocks
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN101852083B (en) Quick supporting method for large-deformation roadway easy to fall, break and loosen and apparatus thereof
CN101748741B (en) Construction method of concrete supporting structure
CN101408106B (en) Small tube shed pre-grouting method
CN111119935B (en) A multi-layer grouting reinforcement method for surrounding rock of soft and broken structure of roadway
CN110185457B (en) TBM (Tunnel boring machine) horizontal pilot tunnel construction method
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN110195604B (en) Construction method for tunnel main tunnel TBM (tunnel boring machine) tunneling section
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN105041325A (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN109595004B (en) Tunnel two-expansion four-expansion excavation method
CN105781573A (en) Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN103089275A (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN101864960A (en) Carst region double-arch road tunnel construction method
CN110984999A (en) Tunnel shaft construction method
CN110284889A (en) A kind of flat pilot tunnel Enlargement excavation method of TBM
CN112663625A (en) Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
CN108374672A (en) A method of reinforcing Deep Mine soft coal level roadway surrounding rock
CN112963156A (en) Composite reinforcing method and composite reinforcing structure for shallow tunnel in soil-rock composite stratum
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN113622934B (en) Advanced support system and method for open TBM heading machine for poor geology of coal mine roadway
CN113137235B (en) Construction method of high-ground-stress soft rock extrusion large-deformation tunnel
CN102877470B (en) Combined soil nailing construction method for supporting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120829