CN100451247C - Bomb-shelter reinforcing construction process - Google Patents
Bomb-shelter reinforcing construction process Download PDFInfo
- Publication number
- CN100451247C CN100451247C CNB200610017568XA CN200610017568A CN100451247C CN 100451247 C CN100451247 C CN 100451247C CN B200610017568X A CNB200610017568X A CN B200610017568XA CN 200610017568 A CN200610017568 A CN 200610017568A CN 100451247 C CN100451247 C CN 100451247C
- Authority
- CN
- China
- Prior art keywords
- hole
- bomb
- shelter
- wall
- construction process
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 25
- 238000010276 construction Methods 0.000 title claims abstract description 16
- 238000000034 method Methods 0.000 title claims description 15
- 239000002689 soil Substances 0.000 claims abstract description 23
- 239000011449 brick Substances 0.000 claims abstract description 13
- 239000004567 concrete Substances 0.000 claims abstract description 11
- 238000007569 slipcasting Methods 0.000 claims description 33
- 241000209094 Oryza Species 0.000 claims description 16
- 235000007164 Oryza sativa Nutrition 0.000 claims description 16
- 235000009566 rice Nutrition 0.000 claims description 16
- 239000007921 spray Substances 0.000 claims description 16
- 239000004570 mortar (masonry) Substances 0.000 claims description 10
- 238000005192 partition Methods 0.000 claims description 4
- 235000003181 Panax pseudoginseng Nutrition 0.000 claims description 2
- 244000131316 Panax pseudoginseng Species 0.000 claims description 2
- 239000002002 slurry Substances 0.000 abstract description 8
- 238000005516 engineering process Methods 0.000 abstract description 2
- 238000005507 spraying Methods 0.000 abstract 2
- 238000010009 beating Methods 0.000 abstract 1
- 230000000694 effects Effects 0.000 description 8
- 239000004568 cement Substances 0.000 description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 5
- 238000005259 measurement Methods 0.000 description 4
- 239000004575 stone Substances 0.000 description 4
- 239000011230 binding agent Substances 0.000 description 3
- 238000004140 cleaning Methods 0.000 description 3
- 238000007596 consolidation process Methods 0.000 description 3
- 239000010881 fly ash Substances 0.000 description 3
- 238000007789 sealing Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000001514 detection method Methods 0.000 description 2
- 230000008676 import Effects 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 239000010815 organic waste Substances 0.000 description 2
- 235000019353 potassium silicate Nutrition 0.000 description 2
- 238000004080 punching Methods 0.000 description 2
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 description 2
- 125000006850 spacer group Chemical group 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 1
- 235000011941 Tilia x europaea Nutrition 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 239000003638 chemical reducing agent Substances 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 239000004571 lime Substances 0.000 description 1
- 201000010041 presbyopia Diseases 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention discloses air raid shelter reinforcing technology that includes the following steps: beating away a certain width corresponding to cavity ground and spraying concrete to form reinforcing frame; boring on the cavity wall to make the soil pressure near or equal to original oil layer soil pressure; lining with bricks on one side of reinforcing frame, spraying concrete to form reinforce separating with the frame; alternately boring on the ceiling; filling slurry to the space. The invention has the advantages of short construction period and good reinforcing effect.
Description
Technical field
The invention belongs to technical field of building construction, particularly a kind of bomb-shelter reinforcing construction process.
Background technology
The bomb shelter of building in early days is in bad repair with age, and structural strength is poor, can't directly use or directly construct in ground in the above, and scrapping or continuing to utilize all needs to carry out consolidation process.Existing reinforced construction method has two kinds, and the first excavates backfill, promptly hole top is excavated, and be that 3: 7 backfill is tamped with lime and native ratio then; It two is to build arch ring in the hole by laying bricks or stones, supports bomb shelter wall and top cover.Method one engineering quantity is big, and is long in time limit, the cost height; The method two arch ring can not directly contact with the hole body, in fact can't prop up the hole body, misses fire.
Summary of the invention
The object of the invention is to provide the bomb-shelter reinforcing construction process that a kind of duration is short, consolidation effect is good.
For reaching above-mentioned purpose, the present invention adopts following technical scheme: bomb-shelter reinforcing construction process, comprise following operation: (1) is moved towards along the bomb shelter, hole, bomb shelter wall is chiseled certain width at interval and goed deep into former soil layer certain depth, with ground in the hole wall is chiseled corresponding hole, space on chisel certain width, reach the hole wall earthward and chisel the full concrete of space spray and form stiffening frame; (2) at interval boring on the wall of hole is tamped the gap to slip casting between bomb shelter Dong Bi and its outside soil body, makes its earth bearing strength approaching or equal former soil layer earth bearing strength; (3), join to forming to reinforce along brick wall sprayed mortar and stiffening frame and cut off at stiffening frame one brick on edge wall.
Comprise that also operation (4) is in the boring at interval in the bomb shelter of top, hole, bomb shelter corresponding ground; (5) this space was tamped in slip casting between reinforcing cut off in the bomb shelter.
Operation is spaced apart 15-30 rice in (1), and width 0.3-0.8 rice is chiseled on hole wall and ground, and the hole wall is chiseled the embedded depth 0.3-0.5 of place rice; Spray earlier the place of chiseling, ground during sprayed mortar and spray the hole wall again and chisel the place, from bottom to top spray at the wall place of chiseling in hole; In the operation (2), 1-3 rice bores 3 holes of quincuncial arrangement at interval, and pipe laying in the hole treats that concrete strength reaches at 75% o'clock and begins slip casting, and grouting pressure is not less than 0.4MPa; In the operation (3), brick wall thickness is pseudo-ginseng wall or four or eight walls, reinforces and cuts off thickness 0.3-0.8 rice.
Boring interval 5-15 rice in the operation (4), pipe laying in the hole; Treat in the operation (5) that concrete strength reaches at 75% o'clock and begins slip casting, grouting pressure is not less than 0.4-1.0Mpa.
Once more at crown drill hole, hole, pipe laying, high-pressure slip-casting, grouting pressure is not less than 2.0Mpa after 3-7 days in the slip casting end.
Building a wall and reinforcing and reserve passage space on the partition.
Construct last as earlier in the cleaning underground shelter hole remaining rubbish to the hole.
Among the present invention, form stiffening frame,, make hole, bomb shelter body structure intensity increase greatly by building a wall in framework one side, forming to reinforce by the wall sprayed mortar and cut off by raggle on the ground in bomb shelter Dong Bi and hole, sprayed mortar; By boring on the wall of hole, bomb shelter and between hole body and surrounding soil slip casting make hole wall and surrounding soil one integrated mass, pressure-bearing is strong, can directly come into operation once more.Also can by further in crown drill hole, hole, in the hole, reinforce to cut off between slip casting scrap after tamping.Through above-mentioned consolidation process, gap, vault and a sidewall gap of laying bricks is tamped between the hole wall and the soil body, can bear the load that upper body engineering in future etc. passes over, and can not produce lateral deformation.Mud jacking is closely knit in the hole, after the completion of upper body engineering is come into operation, differential settlement can not take place cause the building cracking phenomena.
The specific embodiment
Embodiment 1, bomb-shelter reinforcing construction process comprise successively:
1, hole wall and soil body interstitial treatment:
(1) to above ground portion:
Organic waste remaining in A, the cleaning underground shelter hole is to the hole.
B, measurement unwrapping wire: the trend of underground shelter is guided on the ground, marked unwrapping wire, determine the present position, ground.
C, boring: 10.0 meters at every interval gets out the aperture of Φ 100mm with auger to the bomb shelter from ground, is drilled into the vault in bomb shelter.Use for check hole wall slip casting effect.
(2) under ground portion:
A, stiffening frame: every interval is a spacer for 20 meters, and the hole wall in bomb shelter is chiseled 0.5 meter wide, and it is thick to go into 0.5 meter of the original soil degree of depth, and ground is chiseled 0.5 meter wide in the hole in addition, and the degree of depth is not less than 0.35 meter and sees original soil.To chiseling place's sprayed mortar, bottom spray earlier is full then sprays both sides again, and spray from lower to upper both sides, forms stiffening frame.
B, punching: three apertures (uniform) are bored with air drill in 2.0 meters at every interval on the wall of hole, be blossom type and arrange.
C, pipe laying: built-in length is eight fens steel pipes of 0.5 meter.
D, sealing of hole: pipe laying and Dong Bi gap are shut with cement (high grade) or water glass or other mixture.
E, slurrying: it is stand-by that cement and soil are prepared mixed liquor by a certain percentage, and water/binder ratio 1: 0.5 can add flyash for increasing flowability.
F, slip casting: concrete strength to be sprayed reaches 75%, begins by the high-pressure slip-casting between hole wall and surrounding soil of pipe laying on the wall of hole, and grouting pressure is not less than 0.4MPa.
G, detection: a, slurries must overflow Φ 100mm aperture; After b, slurries solidified, any part was chiseled the full degree of check slip casting.
2, handle in the body of hole: after the hole wall is finished dealing with, handle the cavity in the body of hole again.
(1) to above ground portion:
A, measurement unwrapping wire: the trend of underground shelter is guided on the ground, marked unwrapping wire, determine the present position, ground.
B, boring: 5.0 meters at every interval gets out the aperture of Φ 100mm with auger, bores the vault in bomb shelter, bores dark about 9.0 meters.Effect: 1. check the slip casting effect in the hole.2. sandblast, the 3. 4. Grouting Pipe import of inlet and outlet mouth of the stone charging mouth of pipe.
(2) under ground portion:
A, build a wall: the side at stiffening frame is built the thick brick wall of 500mm, 20 meters at every interval.
B, spray cut off: sprayed mortar on the brick wall body that puzzles, and nature angle of repose is piled up, and thickness is not less than 500mm, forms one with stiffening frame and becomes reinforcing to cut off.
Can come into operation once more in bomb shelter after above-mentioned processing.
Embodiment 2, bomb-shelter reinforcing construction process comprise successively:
1, hole wall and soil body interstitial treatment:
(1) to above ground portion:
Organic waste remaining in A, the cleaning underground shelter hole is to the hole.
B, measurement unwrapping wire: the trend of underground shelter is guided on the ground, marked unwrapping wire, determine the present position, ground.
C, boring: 10.0 meters at every interval gets out the aperture of Φ 100mm with auger, is drilled into the vault in bomb shelter, uses for check hole wall slip casting effect.
(2) under ground portion:
A, stiffening frame: every interval is a spacer for 20 meters, and the hole wall in bomb shelter is chiseled 0.5 meter wide, and it is thick to go into 0.5 meter of the original soil degree of depth, and ground is chiseled 0.5 meter wide in the hole in addition, and the degree of depth is not less than 0.35 meter and sees original soil.To chiseling place's sprayed mortar, bottom spray earlier is full then sprays both sides again, and spray from lower to upper both sides, forms stiffening frame.
B, punching: three apertures (uniform) are bored with air drill in 2.0 meters at every interval on the wall of hole, be blossom type and arrange.
C, pipe laying: built-in length is eight fens steel pipes of 0.5 meter.
D, sealing of hole: pipe laying and Dong Bi gap are shut with cement (high grade) or water glass or other mixture.
E, slurrying: it is stand-by that cement and soil are prepared mixed liquor by a certain percentage, and water/binder ratio 1: 0.5 can add flyash for increasing flowability.
F, slip casting: concrete strength to be sprayed reaches 75%, and beginning is to hole wall and surrounding soil gap high-pressure slip-casting, and grouting pressure is not less than 0.4MPa.
G, detection: a, slurries must overflow Φ 100mm aperture; After b, slurries solidified, any part was chiseled the full degree of check slip casting.
2, handle in the body of hole: after the hole wall is finished dealing with, handle the cavity in the body of hole again.
(1) to above ground portion:
A, measurement unwrapping wire: the trend of underground shelter is guided on the ground, marked unwrapping wire, determine the present position, ground.
B, boring: 5.0 meters at every interval gets out the aperture of Φ 100mm with auger, bores the vault in bomb shelter.Effect: 1. check the slip casting effect in the hole.2. sandblast, the 3. 4. Grouting Pipe import of inlet and outlet mouth of the stone charging mouth of pipe.
(2), under ground portion:
A, build a wall: the side at stiffening frame is built the thick brick wall of 500mm.
B, spray cut off: sprayed mortar on the brick wall body that puzzles, and nature angle of repose is piled up, and thickness is not less than 500mm, forms one with stiffening frame and becomes reinforcing to cut off.
C, filling: reinforcing heap sand, stone between partition, the ratio of sandstone is 1: 10.
D, pre-buried grouting tube: bury earlier 1 of Φ 25PPR floral tube in the bottom, then from apart from ground, bomb shelter 0.8-1.2 rice upwards, level interval 0.8-1.2 rice, pipe lower end vertical interval 0.8-1.2 rice blossom type arranges Φ 25PPR floral tube.Spacing staggers for 0.5 meter slurry outlet is set on the floral tube, and all floral tubes are drawn the top, hole.
E, slurrying: it is stand-by that cement and soil are prepared mixed liquor by a certain percentage, and water/binder ratio 1: 0.5 can add flyash for increasing flowability.
F, slip casting: concrete strength to be cut off reaches 75%, begins by the floral tube high-pressure slip-casting.All filling is closely knit for each space after guaranteeing slip casting, and grouting pressure is not less than 0.4MPa.The bomb shelter underground is if there is the also necessary slip casting of subsoil drain closely knit.According to on-site actual situations, every section (reinforcing between the partition for adjacent two) reserves a floral tube, prepares to adopt in the above closely knit once more hole of grouting pressure of 1.0Mpa.
For preventing after the slip casting can to add an amount of expansion agent, water reducing agent because of water loss causes the space, the slurries of every section slip casting simultaneously must overflow the Φ 100mm aperture that bores.
G, benefit slurry: reach wall place, hole high-pressure slip-casting in the body of hole and finish to bore Φ 100mm aperture once more after three to seven days, bore ground in the hole, bore and be no less than 10.0 meters deeply, spacing 5-10 rice (deciding) on slip casting effect, then bury floral tube (2.2 meters are bored presbyopia apart from the bottom), rubble and dark with 1.0 meters of high grade rapid setting cement sealing of holes is filled out on top, last high-pressure slip-casting, and grouting pressure is not less than 2.0Mpa.
After above-mentioned processing, scrap in the bomb shelter, its upper ground surface can as the soil body carry out ground construction.
Claims (6)
1, bomb-shelter reinforcing construction process, it is characterized in that, comprise following operation: (1) is moved towards along the bomb shelter, hole, bomb shelter wall is chiseled certain width at interval and goed deep into former soil layer certain depth, with ground in the hole wall is chiseled corresponding hole, space on chisel certain width, reach the hole wall earthward and chisel the full concrete of space spray and form stiffening frame; (2) at interval boring on the wall of hole is tamped the gap to slip casting between bomb shelter Dong Bi and its outside soil body, makes its earth bearing strength approaching or equal former soil layer earth bearing strength; (3), join to forming to reinforce along brick wall sprayed mortar and stiffening frame and cut off at stiffening frame one brick on edge wall.
2, bomb-shelter reinforcing construction process as claimed in claim 1 is characterized in that, comprises that also operation (4) is in the boring at interval in the bomb shelter of top, hole, bomb shelter corresponding ground; (5) this space was tamped in slip casting between reinforcing cut off in the bomb shelter.
3, bomb-shelter reinforcing construction process as claimed in claim 1 is characterized in that, operation is spaced apart 15-30 rice in (1), and width 0.3-0.8 rice is chiseled on hole wall and ground, and the hole wall is chiseled the embedded depth 0.3-0.5 of place rice; Spray earlier the place of chiseling, ground during sprayed mortar and spray the hole wall again and chisel the place, from bottom to top spray at the wall place of chiseling in hole; In the operation (2), 1-3 rice bores 3 holes of quincuncial arrangement at interval, and pipe laying in the hole treats that concrete strength reaches at 75% o'clock and begins slip casting, and grouting pressure is not less than 0.4MPa; In the operation (3), brick wall thickness is pseudo-ginseng wall or four or eight walls, reinforces and cuts off thickness 0.3-0.8 rice.
4, bomb-shelter reinforcing construction process as claimed in claim 2 is characterized in that, boring interval 5-15 rice in the operation (4), pipe laying in the hole; Treat in the operation (5) that concrete strength reaches at 75% o'clock and begins slip casting, grouting pressure is not less than 0.4-1.0Mpa.
5, bomb-shelter reinforcing construction process as claimed in claim 4 is characterized in that, once more at crown drill hole, hole, pipe laying, high-pressure slip-casting, grouting pressure is not less than 2.0Mpa after 3-7 days in the slip casting end.
6, as claim 1 or 3 described bomb-shelter reinforcing construction process, it is characterized in that, building a wall and reinforcing and reserve passage space on the partition.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB200610017568XA CN100451247C (en) | 2006-03-27 | 2006-03-27 | Bomb-shelter reinforcing construction process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB200610017568XA CN100451247C (en) | 2006-03-27 | 2006-03-27 | Bomb-shelter reinforcing construction process |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1936199A CN1936199A (en) | 2007-03-28 |
CN100451247C true CN100451247C (en) | 2009-01-14 |
Family
ID=37953907
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB200610017568XA Expired - Fee Related CN100451247C (en) | 2006-03-27 | 2006-03-27 | Bomb-shelter reinforcing construction process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100451247C (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102409666B (en) * | 2011-11-30 | 2014-05-07 | 李海广 | Construction process of pile foundation in air-raid shelter trend |
CN103046765B (en) * | 2013-01-24 | 2015-07-15 | 李海广 | Construction process for continued application of air-raid shelter |
CN103195090B (en) * | 2013-04-15 | 2015-04-01 | 合肥建工集团有限公司 | Soft-form-shaped strut structure formed by filling concrete through small hole on underground cavity |
CN105401948B (en) * | 2015-10-29 | 2018-07-17 | 中铁二局集团有限公司 | Plateau Cold Area tunnel both sides loose media stratum construction method after a kind of macroseism |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5207038A (en) * | 1990-06-04 | 1993-05-04 | Yermiyahu Negri | Reinforced earth structures and method of construction thereof |
CN1517495A (en) * | 2003-01-24 | 2004-08-04 | 诺比利费拉里有限责任公司 | Continuous redlizing method of underground engieering, tunnel and underground tunnel, reinforced engineering, sealing engineering and drainage work obtained by guide punching |
-
2006
- 2006-03-27 CN CNB200610017568XA patent/CN100451247C/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5207038A (en) * | 1990-06-04 | 1993-05-04 | Yermiyahu Negri | Reinforced earth structures and method of construction thereof |
CN1517495A (en) * | 2003-01-24 | 2004-08-04 | 诺比利费拉里有限责任公司 | Continuous redlizing method of underground engieering, tunnel and underground tunnel, reinforced engineering, sealing engineering and drainage work obtained by guide punching |
Non-Patent Citations (2)
Title |
---|
建筑地基中人防洞的受力分析与加固. 郭立炫.湖南城建高等专科学校学报,第10卷第1期. 2001 |
建筑地基中人防洞的受力分析与加固. 郭立炫.湖南城建高等专科学校学报,第10卷第1期. 2001 * |
Also Published As
Publication number | Publication date |
---|---|
CN1936199A (en) | 2007-03-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109630137B (en) | An a kind of tunnel high position passes through the backfill processing construction method of huge molten chamber | |
CN100585094C (en) | Construction method of circular deep foundation pit support | |
CN109026064B (en) | Construction method for large-span multi-arch tunnel with semi-bright and semi-dark | |
CN114233385B (en) | Treatment method for mud-bursting water of inclined shaft | |
CN103147442B (en) | Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method | |
CN103321653B (en) | Method of treating lining after collapse of underground cavern crown | |
CN107201908B (en) | Construction method for deep-buried central ditch of tunnel in severe cold region | |
CN101280568A (en) | Station pit construction method forming protection for neighboring operated subway interval tunnel | |
CN103821219A (en) | Top pipe construction modification inspection well construction method | |
CN104532957B (en) | Existing building sets up basement reversed construction method | |
CN109736884B (en) | Treatment structure for water gushing in underground river close to tunnel and construction method of treatment structure | |
CN101881181A (en) | Mine goaf tailing-filled concrete enclosing wall | |
CN102108869A (en) | Grout stop pad construction method for kilometer vertical shaft grouting for water control | |
CN109162298A (en) | A kind of construction method of hydrous fluids pipe gallery | |
CN108265706A (en) | Engineering pile in karst cave geology and pile forming process | |
CN102425155B (en) | A superficial reinforcement method of overlying rock mass in goaf | |
CN110847929A (en) | Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting | |
CN114622917A (en) | Construction Methods for Handling Tunnel Collapse | |
CN100451247C (en) | Bomb-shelter reinforcing construction process | |
CN112144559B (en) | Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well | |
CN110821500A (en) | Large-section tunnel excavation and support construction method for penetrating through earth-rock boundary stratum | |
CN204456058U (en) | A kind of constructing structure reducing building base subsidence speed | |
CN107059904A (en) | A kind of underground pipe gallery ponding well excavation method | |
CN103046765B (en) | Construction process for continued application of air-raid shelter | |
CN106638684B (en) | A kind of piping lane backfill soil processing method of Collapsible Loess District |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |