[go: up one dir, main page]

CN204456058U - A kind of constructing structure reducing building base subsidence speed - Google Patents

A kind of constructing structure reducing building base subsidence speed Download PDF

Info

Publication number
CN204456058U
CN204456058U CN201520073307.4U CN201520073307U CN204456058U CN 204456058 U CN204456058 U CN 204456058U CN 201520073307 U CN201520073307 U CN 201520073307U CN 204456058 U CN204456058 U CN 204456058U
Authority
CN
China
Prior art keywords
pile
steel pipe
building
micro
settlement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201520073307.4U
Other languages
Chinese (zh)
Inventor
李洪波
刘富均
刘黎明
万加勤
王丽斌
丁雷
柳文涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Original Assignee
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC filed Critical Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority to CN201520073307.4U priority Critical patent/CN204456058U/en
Application granted granted Critical
Publication of CN204456058U publication Critical patent/CN204456058U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型提供一种降低建筑基础沉降速率的施工结构,包括建筑地板,在建筑地板的边沿形成有地板沉降区域,其特征在于:在地板沉降区域下方布设有微型钢管桩以及高压旋喷桩,建筑地板底部填筑膨胀混凝土层,膨胀混凝土层内铺设有钢筋,微型钢管桩延伸到膨胀混凝土层下方的桩体为瓜米石桩体,高压旋喷桩延伸到膨胀混凝土层下方的桩体为水泥土桩体,在微型钢管桩以及高压旋喷桩的中部设置有延伸出建筑地板表面的水泥注浆管,本实用新型的技术效果:本实用新型施工结构施工方便、结构简单,减小建筑基础沉降速率,控制不均匀沉降,以确保基础结构的安全可靠。

The utility model provides a construction structure for reducing the settlement rate of building foundations, which includes a building floor, and a floor settlement area is formed on the edge of the building floor. The bottom of the building floor is filled with an expanded concrete layer, and steel bars are laid in the expanded concrete layer. The pile body of the micro-steel pipe pile extending to the bottom of the expanded concrete layer is a melon stone pile body, and the high-pressure rotary grouting pile extends to the pile below the expanded concrete layer. The body is a cement-soil pile body, and a cement grouting pipe extending from the surface of the building floor is arranged in the middle of the micro-steel pipe pile and the high-pressure jet grouting pile. The technical effect of the utility model: the construction structure of the utility model is convenient in construction and simple in structure. Reduce the settlement rate of the building foundation and control the uneven settlement to ensure the safety and reliability of the foundation structure.

Description

一种降低建筑基础沉降速率的施工结构A Construction Structure for Reducing the Settlement Rate of Building Foundation

技术领域technical field

本实用新型涉及建筑基础施工领域,具体的说是一种降低建筑基础沉降速率的施工结构。The utility model relates to the field of building foundation construction, in particular to a construction structure for reducing the settlement rate of building foundations.

背景技术Background technique

随着建筑行业的快速发展,地下空间开发利用是当前城市立体化发展的重要方式,近几十年来,虽然我国城市地下空间开发建设规模和强度越来越大,但地下空间的规划、管理及法规建设严重滞后,相对完整和科学的地下空间地价体系评估技术方法研究鲜有所见,已成为制约城市地下空间可持续开发利用与科学管理的重要瓶颈。国内外学者通过研究和试验发现,建筑基础沉降分析理论和实践尚存大量问题。理论计算与实践结果的较大差异,过大范围的经验系数等等,都使建筑基础沉降计算成为建筑基础理论研究的难题。With the rapid development of the construction industry, the development and utilization of underground space is an important way for the current urban three-dimensional development. In recent decades, although the scale and intensity of urban underground space development and construction in my country have become larger and larger, the planning, management and The construction of laws and regulations is seriously lagging behind, and relatively complete and scientific research on the evaluation techniques and methods of underground space land price system is rarely seen, which has become an important bottleneck restricting the sustainable development, utilization and scientific management of urban underground space. Scholars at home and abroad have found through research and experiments that there are still many problems in the theory and practice of building foundation settlement analysis. The large difference between theoretical calculation and practical results, too large range of empirical coefficients, etc., all make the calculation of building foundation settlement a difficult problem in the theoretical research of building foundation.

建筑基础的沉降能够影响建筑结构的安全,市面上也出现的能够降低建筑基础沉降速率的施工结构,但是现有的施工结构施工困难,结构复杂,降低建筑基础沉降速率的效果不够显著。The settlement of the building foundation can affect the safety of the building structure. There are also construction structures on the market that can reduce the settlement rate of the building foundation. However, the existing construction structures are difficult to construct and have complex structures, and the effect of reducing the settlement rate of the building foundation is not significant enough.

实用新型内容Utility model content

本实用新型根据现有技术的不足提供一种降低建筑基础沉降速率的施工结构,结构简单、施工方便、保证了建筑结构安全,达到了降低建筑基础沉降速率的效果。According to the deficiencies of the prior art, the utility model provides a construction structure for reducing the settlement rate of the building foundation. The structure is simple, the construction is convenient, the safety of the building structure is ensured, and the effect of reducing the settlement rate of the building foundation is achieved.

本实用新型的技术方案:一种降低建筑基础沉降速率的施工结构,包括建筑地板,在建筑地板的边沿形成有地板沉降区域,其特征在于:在地板沉降区域下方布设有微型钢管桩以及高压旋喷桩,建筑地板底部填筑膨胀混凝土层,膨胀混凝土层内铺设有钢筋,微型钢管桩延伸到膨胀混凝土层下方的桩体为瓜米石桩体,高压旋喷桩延伸到膨胀混凝土层下方的桩体为水泥土桩体,在微型钢管桩以及高压旋喷桩的中部设置有延伸出建筑地板表面的水泥注浆管。The technical scheme of the utility model: a construction structure for reducing the settlement rate of the building foundation, including a building floor, and a floor settlement area is formed on the edge of the building floor, which is characterized in that a micro-steel pipe pile and a high-pressure Rotary grouting piles, the bottom of the building floor is filled with an expanded concrete layer, and steel bars are laid inside the expanded concrete layer. The pile body that extends to the bottom of the expanded concrete layer is a melon stone pile body, and the high-pressure rotary grouted pile extends to the expanded concrete layer. The pile body below is a cement-soil pile body, and a cement grouting pipe extending out of the building floor surface is arranged in the middle of the micro-steel pipe pile and the high-pressure rotary grouting pile.

所述微型钢管桩桩体的外围安装有微型钢管,微型钢管两两之间通过外箍接头连接。Micro-steel pipes are installed on the periphery of the micro-steel pipe pile body, and the two micro-steel pipes are connected by outer hoop joints.

所述微型钢管桩和高压旋喷桩的间距为2.5m~3.8m。The distance between the micro-steel pipe pile and the high-pressure rotary grouting pile is 2.5m-3.8m.

所述高压旋喷桩的桩径为600mm,桩长为30m;微型钢管桩的桩径为220mm,桩长为17.5~21.5m。The pile diameter of the high-pressure rotary grouting pile is 600mm, and the pile length is 30m; the pile diameter of the micro steel pipe pile is 220mm, and the pile length is 17.5-21.5m.

所述微型钢管的直径为194mm,壁厚为5mm,微型钢管节长3m。The diameter of the micro-steel pipe is 194mm, the wall thickness is 5mm, and the length of the micro-steel pipe is 3m.

本实用新型的技术效果:结构简单、施工方便、保证了建筑结构安全,高压旋喷桩加固岩土基础中可塑、软塑粉质粘土层和淤泥层;微型钢管桩加固了岩土基础中软弱粘土层,作加固地基和筏板抗拔、减小差异沉降处理,最终达到减小建筑基础沉降速率,控制不均匀沉降,以确保基础结构的安全可靠。The technical effect of the utility model: simple structure, convenient construction, ensuring the safety of the building structure, plastic and soft plastic powdery clay layer and silt layer in the rock-soil foundation reinforced by high-pressure rotary jetting piles; miniature steel pipe piles strengthen the rock-soil foundation The weak clay layer is used to strengthen the foundation and raft to resist pullout and reduce differential settlement, so as to reduce the settlement rate of the building foundation and control uneven settlement to ensure the safety and reliability of the foundation structure.

附图说明Description of drawings

图1是本实用新型地板结构示意图;Fig. 1 is a schematic diagram of floor structure of the present utility model;

图2是本实用新型整体结构示意图;Fig. 2 is a schematic diagram of the overall structure of the utility model;

图3是本实用新型桩体结构示意图;Fig. 3 is a schematic diagram of the utility model pile body structure;

图4是本实用新型微型钢管连接示意图。Fig. 4 is a schematic diagram of the connection of the micro-steel pipe of the present invention.

图中标号分别表示:1—建筑地板,2—沉降区域,3—微型钢管桩,4—高压旋喷桩,5—钢筋,6—膨胀混凝土层,7—瓜米石桩体,8—水泥土桩体,9—微型钢管,10—外箍接头,11—水泥注浆管。The labels in the figure respectively indicate: 1—building floor, 2—settlement area, 3—miniature steel pipe pile, 4—high pressure jet grouting pile, 5—rebar, 6—expanded concrete layer, 7—guami stone pile body, 8— Cement-soil pile body, 9—miniature steel pipe, 10—outer hoop joint, 11—cement grouting pipe.

具体实施方式Detailed ways

下面结合附图对本实用新型进一步说明:Below in conjunction with accompanying drawing, the utility model is further described:

如图1至图4所示,一种降低建筑基础沉降速率的施工结构,包括建筑地板1,在建筑地板1的边沿形成有地板沉降区域2,其特征在于:在地板沉降区域2下方布设有微型钢管桩3以及高压旋喷桩4,建筑地板1底部填筑膨胀混凝土层6,膨胀混凝土层6内铺设有钢筋5,微型钢管桩3延伸到膨胀混凝土层6下方的桩体为瓜米石桩体7,高压旋喷桩4延伸到膨胀混凝土层6下方的桩体为水泥土桩体8,在微型钢管桩3以及高压旋喷桩4的中部设置有延伸出建筑地板1表面的水泥注浆管11。As shown in Figures 1 to 4, a construction structure for reducing the settlement rate of building foundations includes a building floor 1, and a floor settlement area 2 is formed on the edge of the building floor 1, and it is characterized in that: below the floor settlement area 2, there are The micro-steel pipe pile 3 and the high-pressure rotary grouting pile 4, the bottom of the building floor 1 is filled with an expanded concrete layer 6, and steel bars 5 are laid in the expanded concrete layer 6, and the pile body extending to the bottom of the expanded concrete layer 6 is a melon. Rice stone pile body 7, high-pressure rotary grouting pile 4 extending to the pile body below the expanded concrete layer 6 is cement soil pile body 8, in the middle of the micro-steel pipe pile 3 and high-pressure rotary grouting pile 4 is provided with a surface that extends out of the building floor 1 The cement grouting pipe 11.

所述微型钢管桩3桩体的外围安装有微型钢管9,微型钢管9两两之间通过外箍接头10连接。The periphery of the pile body of the micro-steel pipe pile 3 is equipped with micro-steel pipes 9, and the two micro-steel pipes 9 are connected by outer hoop joints 10.

所述微型钢管桩3和高压旋喷桩4的间距为2.5m~3.8m。The distance between the micro-steel pipe pile 3 and the high-pressure jet spray pile 4 is 2.5m-3.8m.

所述高压旋喷桩4的桩径为600mm,桩长为30m;微型钢管桩3的桩径为220mm,桩长为17.5~21.5m。The pile diameter of the high-pressure rotary grouting pile 4 is 600mm, and the pile length is 30m; the pile diameter of the micro steel pipe pile 3 is 220mm, and the pile length is 17.5-21.5m.

所述微型钢管9的直径为194mm,壁厚为5mm,微型钢管节长3m。The diameter of the micro-steel pipe 9 is 194mm, the wall thickness is 5mm, and the section length of the micro-steel pipe is 3m.

建筑基础发生不均匀沉降后,首先在建筑地板上进行高压旋喷桩和微型钢管桩的桩位布设。高压旋喷桩:人工开挖建筑地板,清除混凝土和钢筋后,采用金刚石钻探开孔,孔径220mm,高压喷射注浆采用旋喷单管工艺,P.O42.5普硅水泥作固化剂,水泥掺入比15%-30%,注浆压力不小于22Mpa,水灰比0.75。桩端进入中密砂层1.5m,停灰标高为地板底。施工结束7天后开始封闭桩头,清除浮浆及残余,补焊地板加强筋,预留高压注浆管,浇灌C40膨胀砼捣实至板顶。砼养护20天后进行高压注浆,水灰比0.9,目的是防止桩体收缩,减缓地板沉降。After uneven settlement of the building foundation, the high-pressure jet grouting piles and micro-steel pipe piles are first laid out on the building floor. High-pressure rotary grouting piles: manually excavate the building floor, remove concrete and steel bars, and use diamond drilling to drill holes with a diameter of 220mm. The mixing ratio is 15%-30%, the grouting pressure is not less than 22Mpa, and the water-cement ratio is 0.75. The pile tip enters the medium-dense sand layer for 1.5m, and the ash-stopping elevation is the bottom of the floor. Seven days after the completion of the construction, the pile head was closed, the floating slurry and residues were removed, the floor reinforcement was repaired and welded, the high-pressure grouting pipe was reserved, and C40 expansive concrete was poured and compacted to the top of the slab. After 20 days of concrete curing, high-pressure grouting is carried out, and the water-cement ratio is 0.9. The purpose is to prevent the shrinkage of the pile body and slow down the settlement of the floor.

微型钢管桩:采用金刚石钻探开孔,孔径220mm,深17.5~21.5m,成孔后放入直径194mm、壁厚5mm的钢管,钢管节长3m,采用外箍焊接,内置注浆管,同步安装。钢管安放完毕后,从注浆管中注入清水,排出管中泥浆,人工投入瓜米石至管口,再压注水泥浆至管口,水灰比为0.6。注浆7天后开始封闭桩头,清除浮浆及残余,补焊地板加强筋,浇灌C40膨胀砼捣实至板顶。Miniature steel pipe piles: diamond drilling is used to drill holes with a diameter of 220mm and a depth of 17.5-21.5m. After the hole is formed, a steel pipe with a diameter of 194mm and a wall thickness of 5mm is placed. The length of the steel pipe is 3m. Install. After the steel pipe is placed, inject clean water from the grouting pipe, discharge the mud in the pipe, manually put melon stones into the pipe mouth, and then press grout to the pipe mouth. The water-cement ratio is 0.6. After 7 days of grouting, start to close the pile head, remove the laitance and residue, repair and weld the floor reinforcement, pour C40 expansive concrete and tamp it to the top of the slab.

实施例:武汉王家墩公园项目位于王家墩CBD商务区西北角,主要由5座人工山峰和A、B两座半埋式地下建筑组成,地质主要为:淤泥质粘土层、粉质粘土层较厚,土层起伏较大,承载力较差,对基础沉降有较大影响。其中B地下建筑结构为钢筋混凝土结构,长114m,宽72米,高12米,建筑顶部覆土高度5米。该建筑地基处理方法采用砂石桩+砂石垫层+堆载预压的方式。B地建筑建成后(后浇带未封),东、西方向沉降差异明显,影响结构安全,主要特征是基础沉降速率大,基础沉降区域不均匀。选择采用本实用新型重点解决该建筑沉降速率过大的问题。本实用新型,对地基局部调整,可以改良基础沉降;施工成本可控,较经济实惠,总体工期影响不大;选择科学合理处理手段,保证可靠性,符合多方利益;可行性、经济性、可靠性较好。Example: The Wuhan Wangjiadun Park project is located in the northwest corner of the Wangjiadun CBD business district. It is mainly composed of 5 artificial peaks and two semi-buried underground buildings A and B. The geology is mainly: silty clay layer and silty clay layer. thick, the soil layer undulates greatly, and the bearing capacity is poor, which has a great influence on the settlement of the foundation. Among them, the underground building structure of B is a reinforced concrete structure, 114m long, 72m wide, 12m high, and the top of the building is covered with soil at a height of 5m. The building foundation treatment method adopts the method of sand and gravel pile + sand and gravel cushion + surcharge preloading. After the building of site B is completed (the post-pouring zone is not sealed), the settlement difference between the east and west directions is obvious, which affects the structural safety. The main characteristics are the high settlement rate of the foundation and the uneven settlement area of the foundation. The utility model is selected to focus on solving the problem of excessive settlement rate of the building. The utility model can improve the settlement of the foundation through partial adjustment of the foundation; the construction cost is controllable, more economical and affordable, and the overall construction period is not greatly affected; scientific and reasonable treatment methods are selected to ensure reliability and meet the interests of multiple parties; it is feasible, economical and reliable sex is better.

本实用新型的一种降低建筑基础沉降速率的施工结构,结构简单、施工方便、保证了建筑结构安全,高压旋喷桩加固岩土基础中可塑、软塑粉质粘土层和淤泥层;微型钢管桩加固岩土基础中软弱粘土层,作加固地基和筏板抗拔、减小差异沉降处理,最终达到减小建筑基础沉降速率,控制不均匀沉降,以确保基础结构的安全可靠。A construction structure for reducing the settlement rate of building foundations of the utility model has simple structure, convenient construction, and ensures the safety of building structures. Plastic and soft plastic powdery clay layers and silt layers in rock-soil foundations reinforced by high-pressure rotary grouting piles; micro-steel Pipe piles are used to strengthen the weak clay layer in the rock-soil foundation, to strengthen the foundation and raft to resist pullout, and to reduce differential settlement, so as to reduce the settlement rate of the building foundation and control uneven settlement to ensure the safety and reliability of the foundation structure.

Claims (5)

1.一种降低建筑基础沉降速率的施工结构,包括建筑地板(1),在建筑地板(1)的边沿形成有地板沉降区域(2),其特征在于:在地板沉降区域(2)下方布设有微型钢管桩(3)以及高压旋喷桩(4),建筑地板(1)底部填筑膨胀混凝土层(6),膨胀混凝土层(6)内铺设有钢筋(5),微型钢管桩(3)延伸到膨胀混凝土层(6)下方的桩体为瓜米石桩体(7),高压旋喷桩(4)延伸到膨胀混凝土层(6)下方的桩体为水泥土桩体(8),在微型钢管桩(3)以及高压旋喷桩(4)的中部设置有延伸出建筑地板(1)表面的水泥注浆管(11)。1. A construction structure for reducing the rate of settlement of building foundations, comprising a building floor (1), forming a floor settlement zone (2) on the edge of the building floor (1), characterized in that: the floor settlement zone (2) is arranged below the floor settlement zone (2) There are micro-steel pipe piles (3) and high-pressure jet grouting piles (4), the bottom of the building floor (1) is filled with an expanded concrete layer (6), and steel bars (5) are laid in the expanded concrete layer (6), and the micro-steel pipe piles (3) The pile body extending to the bottom of the expanded concrete layer (6) is a melon stone pile body (7), and the pile body extended to the bottom of the expanded concrete layer (6) by the high-pressure rotary grouting pile (4) is a cement-soil pile body ( 8), a cement grouting pipe (11) extending out of the surface of the building floor (1) is provided in the middle of the miniature steel pipe pile (3) and the high-pressure jet grouting pile (4). 2.根据权利要求1所述的一种降低建筑基础沉降速率的施工结构,其特征在于:所述微型钢管桩(3)桩体的外围安装有微型钢管(9),微型钢管(9)两两之间通过外箍接头(10)连接。2. A kind of construction structure that reduces building foundation settlement rate according to claim 1, is characterized in that: the periphery of described micro-steel pipe pile (3) pile body is equipped with micro-steel pipe (9), micro-steel pipe (9) Connect by outer hoop joint (10) between two. 3.根据权利要求1所述的一种降低建筑基础沉降速率的施工结构,其特征在于:所述微型钢管桩(3)和高压旋喷桩(4)的间距为2.5m~3.8m。3. A construction structure for reducing the settlement rate of building foundations according to claim 1, characterized in that the distance between the miniature steel pipe piles (3) and the high-pressure jet grouting piles (4) is 2.5m to 3.8m. 4.根据权利要求1所述的一种降低建筑基础沉降速率的施工结构,其特征在于:所述高压旋喷桩(4)的桩径为600mm,桩长为30m;微型钢管桩(3)的桩径为220mm,桩长为17.5~21.5m。4. a kind of construction structure that reduces building foundation settlement rate according to claim 1, is characterized in that: the pile diameter of described high-pressure rotary grouting pile (4) is 600mm, and pile length is 30m; Miniature steel pipe pile (3 ) with a pile diameter of 220mm and a pile length of 17.5-21.5m. 5.根据权利要求2所述的一种降低建筑基础沉降速率的施工结构,其特征在于:所述微型钢管(9)的直径为194mm,壁厚为5mm,微型钢管节长3m。5. A construction structure for reducing the settlement rate of building foundations according to claim 2, characterized in that: the micro-steel pipe (9) has a diameter of 194mm, a wall thickness of 5mm, and a length of 3m of the micro-steel pipe section.
CN201520073307.4U 2015-02-03 2015-02-03 A kind of constructing structure reducing building base subsidence speed Expired - Lifetime CN204456058U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520073307.4U CN204456058U (en) 2015-02-03 2015-02-03 A kind of constructing structure reducing building base subsidence speed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520073307.4U CN204456058U (en) 2015-02-03 2015-02-03 A kind of constructing structure reducing building base subsidence speed

Publications (1)

Publication Number Publication Date
CN204456058U true CN204456058U (en) 2015-07-08

Family

ID=53662967

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520073307.4U Expired - Lifetime CN204456058U (en) 2015-02-03 2015-02-03 A kind of constructing structure reducing building base subsidence speed

Country Status (1)

Country Link
CN (1) CN204456058U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049410A (en) * 2016-06-16 2016-10-26 苏州杰姆斯特机械有限公司 Underground soil layer reinforcing method of building construction
CN109098167A (en) * 2017-06-20 2018-12-28 九州职业技术学院 The processing construction and its construction method of old mining area depth mud
CN111576466A (en) * 2020-05-26 2020-08-25 山东泉顺达装配式建筑有限公司 Pile beam foundation structure and construction method
CN113742918A (en) * 2021-09-06 2021-12-03 中国科学院地理科学与资源研究所 Method for evaluating recreation bearing capacity of national park based on system dynamics model

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049410A (en) * 2016-06-16 2016-10-26 苏州杰姆斯特机械有限公司 Underground soil layer reinforcing method of building construction
CN109098167A (en) * 2017-06-20 2018-12-28 九州职业技术学院 The processing construction and its construction method of old mining area depth mud
CN111576466A (en) * 2020-05-26 2020-08-25 山东泉顺达装配式建筑有限公司 Pile beam foundation structure and construction method
CN113742918A (en) * 2021-09-06 2021-12-03 中国科学院地理科学与资源研究所 Method for evaluating recreation bearing capacity of national park based on system dynamics model
CN113742918B (en) * 2021-09-06 2023-10-20 中国科学院地理科学与资源研究所 Method for evaluating national park recreation bearing capacity based on system dynamics model

Similar Documents

Publication Publication Date Title
CN102277867B (en) A construction method of collapsible loess foundation
CN103422501B (en) Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN204401385U (en) A kind of road structure processing Deep Thick Soft Ground karst foundation
CN101881181A (en) Mine goaf tailing-filled concrete enclosing wall
CN106593470A (en) High-permeability water-rich sand shield terminal reinforcing system and construction method thereof
CN204456058U (en) A kind of constructing structure reducing building base subsidence speed
CN108412016A (en) Underground tube body assures construction method
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN104328788B (en) Double rows slip casting stake with draw shotcrete layer combined supporting construction method
CN206070508U (en) Device for reinforcing foundation
CN205876322U (en) Rich water sand cobble stratum shield constructs business turn over hole system of consolidating
CN105735323B (en) The inverse deep footing groove enclosing structure for making to combine with Percussion Piles of spray anchor and its construction method
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN112144559A (en) Construction method of piezo-transformer tube well in high water-rich loess sandy pebble formation
CN103276645B (en) Precast pile, beam and slab renovation technology for diseases of existing line tunnel base
CN207862925U (en) A kind of slip casting casing device
CN103469828A (en) Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN206299392U (en) A kind of high osmosis water-rich sand layer shield end reinforcement system
CN102359101A (en) Foundation treatment method for collapsible soil
CN103993609B (en) The multi-functional fast hard concrement manual repair foundation pit waterproof curtain of silicon ash sand guide drainage
CN106917331B (en) Water-stopping reinforced roadbed structure for deep-buried karst region and construction method thereof
CN206736650U (en) A kind of road structure of deep-lying karst area water sealing consolidation
CN204510861U (en) Whole building mobile route ground anti-settling structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20150708

CX01 Expiry of patent term