[go: up one dir, main page]

CH431591A - Process for the production of bridge structures or the like - Google Patents

Process for the production of bridge structures or the like

Info

Publication number
CH431591A
CH431591A CH891365A CH891365A CH431591A CH 431591 A CH431591 A CH 431591A CH 891365 A CH891365 A CH 891365A CH 891365 A CH891365 A CH 891365A CH 431591 A CH431591 A CH 431591A
Authority
CH
Switzerland
Prior art keywords
precast concrete
formwork
parts
concrete parts
concrete
Prior art date
Application number
CH891365A
Other languages
German (de)
Inventor
Friedrich Dipl-Ing Dr Neumayer
Original Assignee
Ast Ed Ing & Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ast Ed Ing & Co filed Critical Ast Ed Ing & Co
Publication of CH431591A publication Critical patent/CH431591A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Description

  

  Verfahren zur Herstellung von Brückentragwerken oder dergleichen    Die Erfindung bezieht sich auf ein Verfahren zur  Herstellung von Brückentragwerken oder dgl.     langge-          streckten    Bauwerken aus Ortsbeton. Solche Brücken  tragwerke werden unter     Vermittlung    eines     Lehrgerüstes     in Schalungen     betoniert,    wobei die zu betonierenden       Abschnitte    durch quer     eingesetzte    Schalungen vonein  ander abgetrennt sind.

   Diese die     Betonierabschnitte    un  terteilenden Schalungen müssen bei dem bekannten Ver  fahren vor der Betonierung des nächstfolgenden Ab  schnittes entfernt werden, was zur Folge hat, dass     immer     das Abbinden des Betons abgewartet     wird,    bevor der  nächste     Betonierabschnitt    in Angriff genommen wer  den kann. Da solche Brückentragwerke Längsbeweh  rungen, seien es     gespannte    oder schlaffe Bewehrungen,  aufweisen, müssen diese Bewehrungen durch diese die       Betonierabschnitte    begrenzenden Schalungen hindurch  geführt werden, wobei diese Schalungen als Abstandhal  ter wirken. Das Entfernen dieser Schalungen wird durch  diese Bewehrungen erschwert.  



  Die Erfindung zielt nun darauf ab, die Nachteile  eines solchen Verfahrens zur Herstellung von Brücken  tragwerken oder dgl. Bauwerken zu vermeiden. Das     er-          findungsgemässe    Verfahren besteht darin, dass die ein  zelnen     Betonierabschnitte    durch Betonfertigteile     abge-          schalt    werden, welche als verlorene Schalungen im Bau  werk verbleiben. Da diese verlorenen Schalungen aus       Betonfertigteilen    bestehen, verbinden sie sich mit dem in  die     Betonierabschnitte    eingebrachten     Ortsbeton,    so dass  sie ohne weiteres im Betonkörper des Brückentragwer  kes oder dgl. verbleiben können.

   Es wird somit das Aus  schalen erspart, und es wird vor allem ermöglicht, dass  die     Betonierarbeiten    fortschreiten können, ohne dass  so lange     zugewartet    werden muss, bis die     Erhärtung    des  Betons so weit fortgeschritten ist, dass die Schalungen  entfernt werden können.

   Es wird dadurch somit nicht  nur das     komplizierte    Ausschalen     erspart,    sondern auch  der Fortgang des Baues     beschleunigt.    Auch bei dem     er-          findungsgemässen        Verfahren    werden zweckmässig die  vorzuspannenden oder schlaffen Bewehrungen durch       Durchbrechungen    der     Betonfertigteile    hindurchgeführt,    wobei die     Betonfertigteile    beim Einbringen des Ortsbe  tons als Abstandhalter dienen.

   Während diese Beweh  rungen bisher beim Ausschalen der die     Betonierab-          schnitte    begrenzenden Schalungen störend wirkten und       Glas    Ausschalen wesentlich erschwerten, ist nun der  Vorteil durch die Erfindung gegeben, dass diese Ab  standhalter im Betonkörper des Brückentragwerkes oder  dgl. verbleiben und daher beim Fortschreiten der     Be-          tonierarbeiten,    solange der Beton noch nicht erhärtet  ist, die richtige Lage der Bewehrungen     gewährleisten.     



  Es ist bekannt, Brückentragwerke aus Fertigteilen       zusammenzusetzen.    Dies hat jedoch den     Nachteil    eines  sehr grossen Gewichtes der Fertigteile, welche auf die  Baustelle     transportiert    und in ihre Lage gebracht wer  den müssen. Bei dem erfindungsgemässen Verfahren  jedoch kann das Gewicht dieser     Betonfertigteile    auf ein       Minimum        reduziert    werden, da diese     Betonfertigteile     nur die Aufgabe einer die     Betonierabschnitte    begren  zenden Schalung erfüllen müssen.

   Betonfertigteile,  welche zur Durchführung des erfindungsgemässen Ver  fahrens dienen, sind daher gemäss der     Erfindung    schei  benförmig mit einem der     Querschnittsform    des Bau  werkes entsprechenden Umriss ausgebildet, wobei sie  die entsprechenden     Durchbrechungen    für den Durch  tritt der Bewehrungen aufweisen. Ein solcher scheiben  förmiger     Betonfertigteil    weist ein sehr     geringes    Gewicht  auf, so dass die Nachteile einer     üblichen    Baukonstruk  tion aus     Betonfertigteilen    nicht in Betracht gezogen wer  den müssen.  



  In der Zeichnung ist die     Erfindung    anhand eines       Ausführungsbeispieles    schematisch .erläutert.  



       Fig.    1 zeigt einen Querschnitt durch     eine    Eisen  bahnbrücke und     Fig.2    eine Seitenansicht derselben.       Fig.    3 und 4 zeigen einen     Betonfertigteil    mit den     Armie-          rungen    vor der Einbringung des Ortsbetons, wobei     Fig.    3  eine Ansicht und     Fig.    4 einen Schnitt nach     Linie        IV-IV     der     Fig.    3 darstellt.

       Fig.    5 zeigt die     Abschalung    eines       Betonierabschnittes    im     Querschnitt    durch ein Brücken  tragwerk nach     Fig.    1 und 2,     Fig.    6 zeigt die Brücke  während des Baues.

        Bei der in     Fig.    1 und 2     dargestellten        Eisenbahn-          brücke    stellt 1 den Ortsbeton und 3 die scheibenförmi  gen     Betonfertigteile        dar.    Bei dem Ausführungsbeispiel  nach     Fig.    1 und 2 entspricht der Umriss der     Beton-          fertigteile    der     Querschnittsform    des Bauwerkes und es  ragen diese     Betonfertigteile    3 etwa um die Stärke der       Schalung    über den     Ortsbetonkörper    1 vor.

   Die     Seiten-          begrenzungen    der     Betonfertigteile    3 sind jedoch par  allel zu den Seitenbegrenzungen des     Ortsbetonkörpers     des Brückentragwerkes, so     dass    die Seitenschalungen  an die     Betonfertigteile    angelegt werden können,

   welche       Betonfertigteile    nach Art einer Schablone den     Quer-          schnitt    des Bauwerkes     bestimmen.        Seitlich    weisen die       scheibenförmigen    Betonfertigteile 3 eine auskragende       Konsole    4 für die Abstützung     eines    Gehsteiges 5 auf.  



       Fig.    3 und 4 zeigen nun einen Betonfertigteil 3.  Dieser     scheibenförmige    Betonfertigteil 3 weist Durch  brechungen 6 für die     Durchführung    der     vorzuspannen-          den        Bewehrungen    7 und     Durchbrechungen    8     für        die     Durchführung von     schlaffen    Bewehrungen 9 auf, so  dass der     Betonfertigteil    3 beim     Einbringen    des Orts  betons gleichzeitig als     Abstandhalter    für die Beweh  rungen 7 und 8 dient.

   Oben und unten weist der     Beton-          fertigteil    3 überdies noch Nischen 10 auf, welche nicht  als durchgehende     Durchbrechungen        ausgebildet    sind und  lediglich zur besseren Verbindung mit dem Ortsbeton  nach Art einer     Verdübelung    dienen. An den beiden  Seiten wird     diese    Aufgabe durch die     Durchbrechungen     8     übernommen.     



       Fig.    5 zeigt die     Abschalung        eines        Betonierabschnit-          tes        zwischen    zwei     Fertigteilscheiben    3. Die Aussenscha  lungen bestehen im wesentlichen aus lotrecht stehenden  Trägern 11 und daran befestigten     Schalttafeln    12. Die  Träger 11 werden über     Zugschliessen    13 zusammenge  halten. Die richtige Lage der     Schalungselemente    wird  durch     Führungsträger    14, die von Fertigteil 3 zu Fertig  teil 3 gespannt sind, gewährleistet.

   Die Innenschalung  kann beispielsweise mittels eines     Schalungswagens,    ähn  lich wie er im     Stollenbau    verwendet wird, hergestellt  werden. Auf zwei Längsträgern 15 läuft ein auf Rädern  16 fortzubewegendes     Gerüst    17,     das    auf     Spindeln    18  die     Schalungselemente    19 trägt. 20 stellt die Rüstträger  des     Lehrgerüstes    dar.  



       Fig.    6     zeigt    einen Bauzustand während des Vor  baues des Brückentragwerkes.     Im    vierten Feld 21 wer  den auf vorbereitete     Gerüstjoche    22     Rüstträger    20 aus  dem ersten Feld 23 versetzt,

   während im dritten Feld 24    auf dem bereits verlegten     Schalungsboden    25 die     Fer-          tigteilscheiben    3 versetzt und     durch    die nicht darge  stellten Führungsträger 14 in ihrer Lage     festgehalten          sind.    Weiter wird in     diesem    Feld die     Spannbewehrung     7 und     anschliessend    die     schlaffe    Bewehrung 9     verlegt.     Im     zweiten    Feld 26 wird     abschnittsweise    die Schalung  11, 12     (Fig.    5)

   aufgebaut und nach Betonieren und Er  härten des Betons ins nächste Feld weiterversetzt. Nach  Erhärten des letzten Abschnittes des zweiten Feldes 26  wird eine Anzahl von     Spannsträngen    7     angespannt    und       damit    die     Tragfähigkeit    des Feldes für das Trägereigen  gewicht und die Kranlast hergestellt.     Im    ersten Feld ist  das     Tragwerk    fertiggestellt, die Rüstträger 20 sind be  reits ausgebaut.



  Method for producing bridge structures or the like. The invention relates to a method for producing bridge structures or similar elongated structures made of in-situ concrete. Such bridge structures are concreted in formwork with the help of a falsework, with the sections to be concreted being separated from each other by formwork inserted across.

   This formwork dividing the concreting sections must be removed in the known Ver before concreting the next section, with the result that the concrete is always waited for setting before the next concreting section can be tackled. Since such bridge structures have longitudinal reinforcements, be it tensioned or slack reinforcement, these reinforcements must be passed through these formwork delimiting the concreting sections, these formworks acting as a spacer. The removal of these formwork is made difficult by these reinforcements.



  The invention aims to avoid the disadvantages of such a method for producing bridges or similar structures. The method according to the invention consists in that the individual concreting sections are shut off by precast concrete parts which remain in the building as permanent formwork. Since these lost formwork consists of precast concrete parts, they combine with the in-situ concrete introduced into the concreting sections so that they can easily remain in the concrete body of the Brückentragwer kes or the like.

   The formwork is thus saved and, above all, it is made possible that the concreting work can proceed without having to wait until the concrete has hardened so far that the formwork can be removed.

   This not only saves the complicated formwork removal, but also speeds up the construction process. In the method according to the invention, too, the reinforcements to be prestressed or slack are expediently passed through openings in the precast concrete parts, the precast concrete parts serving as spacers when the local concrete is introduced.

   While these reinforcements previously had a disruptive effect when stripping the formwork delimiting the concreting sections and made stripping glass much more difficult, the invention now has the advantage that these spacers remain in the concrete body of the bridge structure or the like and therefore remain as the loading progresses. concrete work, as long as the concrete has not yet hardened, ensure the correct position of the reinforcements.



  It is known to assemble bridge structures from prefabricated parts. However, this has the disadvantage of a very large weight of the prefabricated parts which have to be transported to the construction site and placed in their position. In the method according to the invention, however, the weight of these precast concrete parts can be reduced to a minimum, since these precast concrete parts only have to fulfill the task of a formwork limiting the concreting sections.

   Precast concrete parts, which are used to carry out the process according to the invention, are therefore designed according to the invention disc-shaped with an outline corresponding to the cross-sectional shape of the building, and they have the corresponding openings for the reinforcement to pass through. Such a disc-shaped precast concrete part has a very low weight, so that the disadvantages of a conventional Baustruk tion made of precast concrete parts do not have to be taken into account.



  The invention is illustrated schematically in the drawing using an exemplary embodiment.



       Fig. 1 shows a cross section through a railway bridge and Fig.2 shows a side view of the same. 3 and 4 show a precast concrete part with the reinforcements before the in-situ concrete is placed, FIG. 3 showing a view and FIG. 4 showing a section along line IV-IV of FIG.

       Fig. 5 shows the shuttering of a concrete section in cross section through a bridge structure according to FIGS. 1 and 2, Fig. 6 shows the bridge during construction.

        In the railway bridge shown in FIGS. 1 and 2, 1 represents the in-situ concrete and 3 represents the disc-shaped precast concrete parts. In the exemplary embodiment according to FIGS. 1 and 2, the outline of the precast concrete parts corresponds to the cross-sectional shape of the structure and these precast concrete parts 3 protrude about the thickness of the formwork over the in-situ concrete body 1.

   However, the side boundaries of the precast concrete elements 3 are parallel to the side boundaries of the in-situ concrete structure of the bridge structure, so that the side formwork can be placed on the precast concrete elements,

   which precast concrete elements determine the cross-section of the building like a template. At the side, the disc-shaped precast concrete parts 3 have a cantilevered bracket 4 for supporting a sidewalk 5.



       3 and 4 now show a precast concrete part 3. This disc-shaped precast concrete part 3 has openings 6 for the implementation of the prestressing reinforcements 7 and openings 8 for the implementation of slack reinforcements 9, so that the precast concrete part 3 when the in-situ concrete is introduced at the same time as a spacer for the reinforcements 7 and 8 serves.

   Above and below, the precast concrete part 3 also has niches 10, which are not designed as continuous openings and merely serve for better connection with the in-situ concrete in the manner of dowelling. This task is taken over by the openings 8 on both sides.



       5 shows the shuttering of a concrete section between two prefabricated panels 3. The outer shuttering consists essentially of vertical supports 11 and switchboards 12 attached to them. The supports 11 are held together by means of tension locks 13. The correct position of the formwork elements is ensured by guide beams 14, which are stretched from prefabricated part 3 to prefabricated part 3.

   The inner formwork can be produced, for example, by means of a formwork carriage, similar to the one used in tunnel construction. A scaffold 17 which is to be moved on wheels 16 and which carries the formwork elements 19 on spindles 18 runs on two longitudinal beams 15. 20 shows the support for the falsework.



       Fig. 6 shows a state of construction during the construction of the bridge structure. In the fourth field 21 who moves the prepared scaffold yokes 22 armature 20 from the first field 23,

   while in the third field 24 on the already laid shuttering base 25, the prefabricated part panes 3 are offset and are held in their position by the guide supports 14 (not shown). The prestressed reinforcement 7 and then the slack reinforcement 9 are also laid in this field. In the second field 26 the formwork 11, 12 (Fig. 5)

   built up and moved to the next field after concreting and hardening of the concrete. After hardening of the last section of the second field 26, a number of tension cords 7 is tensioned and thus the load-bearing capacity of the field for the carrier's own weight and the crane load is established. In the first field, the supporting structure has been completed, and the support beams 20 have already been expanded.

 

Claims (1)

PATENTANSPRUCH I Verfahren zur Herstellung von Brückentragwerken oder dgl. langgestreckten Bauwerken aus Ortsbeton, dadurch gekennzeichnet, dass die einzelnen Betonierab- schnitte durch Betonfertigteile abgeschalt werden, welche als verlorene Schalungen im Bauwerk verbleiben. PATENT CLAIM I A method for producing bridge structures or similar elongated structures made of in-situ concrete, characterized in that the individual concreting sections are shut off by precast concrete parts which remain in the structure as lost formwork. PATENTANSPRUCH II Betonfertigteil zur Durchführung des Verfahrens nach Patentanspruch I, dadurch gekennzeichnet, dass er scheibenförmig mit einem der Querschnittsform des Bauwerkes entsprechenden Umriss ausgebildet ist und Durchbrechungen für den Durchtritt der Bewehrungen aufweist. UNTERANSPRÜCHE 1. PATENT CLAIM II Precast concrete part for performing the method according to claim I, characterized in that it is disk-shaped with an outline corresponding to the cross-sectional shape of the structure and has openings for the reinforcement to pass through. SUBCLAIMS 1. Verfahren nach Patentanspruch I, dadurch ge- kennzeichnet, dass die Seitenschalungen an die Beton- fertigteile angelegt werden, wobei die Betonfertigteile nach Art einer Schablone den Querschnitt des Bau werkes bestimmen. 2. Method according to patent claim I, characterized in that the side formwork is placed on the precast concrete parts, the precast concrete parts determining the cross-section of the building like a template. 2. Verfahren nach Patentanspruch I, dadurch ge kennzeichnet, dass die vorzuspannenden und/oder schlaffen Bewehrungen durch Durchbrechungen der Be- tonfertigteile hindurchgeführt werden, wobei die Beton fertigteile beim Einbringen des Ortsbetons als Abstand halter dienen. 3. Betonfertigteil nach Patentanspruch II, dadurch gekennzeichnet, dass -er wenigstens eine auskragende Konsole aufweist. Method according to claim 1, characterized in that the pre-stressed and / or slack reinforcements are passed through openings in the precast concrete parts, the precast concrete parts serving as spacers when the in-situ concrete is introduced. 3. Precast concrete part according to claim II, characterized in that -er has at least one cantilevered console.
CH891365A 1964-07-02 1965-06-25 Process for the production of bridge structures or the like CH431591A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT570464A AT256920B (en) 1964-07-02 1964-07-02 Process for the production of bridge structures or the like.

Publications (1)

Publication Number Publication Date
CH431591A true CH431591A (en) 1967-03-15

Family

ID=3578734

Family Applications (1)

Application Number Title Priority Date Filing Date
CH891365A CH431591A (en) 1964-07-02 1965-06-25 Process for the production of bridge structures or the like

Country Status (2)

Country Link
AT (1) AT256920B (en)
CH (1) CH431591A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970823A (en) * 2016-06-13 2016-09-28 中交第二航务工程局有限公司 Box girder internal template system for large-span ultra-high warping body

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970823A (en) * 2016-06-13 2016-09-28 中交第二航务工程局有限公司 Box girder internal template system for large-span ultra-high warping body

Also Published As

Publication number Publication date
AT256920B (en) 1967-09-11

Similar Documents

Publication Publication Date Title
DE212018000245U1 (en) Connection structure of prestressing concrete frame nodes
DE2756255A1 (en) METHOD OF MANUFACTURING REINFORCED CONCRETE BRIDGES AND REINFORCED CONCRETE BRIDGES
DE1138208B (en) Method and device for setting up multi-storey buildings with a basement
AT398218B (en) CEILING CONSTRUCTION AND METHOD FOR PRODUCING THE SAME
DE6750158U (en) REINFORCED CONCRETE SLAB FOR ERECTING CEILINGS, WALLS AND THE LIKE
CH431591A (en) Process for the production of bridge structures or the like
DE1257818B (en) Process for the segmental production of bridge structures or the like elongated structures made of in-situ concrete and precast concrete component for carrying out the process
DE1060122B (en) Slab ceiling with assembly rigid metal girders serving as reinforcement and formwork remaining in the ceiling
DE2733628A1 (en) PROCESS FOR MANUFACTURING A REINFORCED CONCRETE STRUCTURE WITH STRONG CURVED EXTERIORS IN THE BASE AND PLANE
DE1220990B (en) Method for creating wall fractures
DE554500C (en) Buildings with walls made of panels that are held together by clamping screws
AT163036B (en) Construction method for monolithic hollow stone ceilings
DE919135C (en) Process for the production of ceilings from cylindrical or prismatic shells and reinforced in-situ concrete ribs
AT216725B (en) Method and device for the production of reinforced concrete ceilings, in particular monolithic slab ceilings
DE2124611A1 (en) Method for erecting floor slabs
DE1182411B (en) Method and device for erecting multi-storey buildings with basements
DE930477C (en) Saw roof made of precast reinforced concrete
DE734490C (en) Casting mold for the production of concrete or reinforced concrete ceilings
AT200307B (en) Glass concrete construction, in particular for glass block walls and windows, and processes for their production
DE1221422B (en) Method for erecting walls from posts and wall elements inserted between them, and then erected wall and posts for the wall
DE1945506C (en) Ceiling element
DE2216559A1 (en) MULTI-LAYER CONCRETE SLAB WITH ANCHORING MADE OF REINFORCED CONCRETE JOINT AND ADDITIONAL CONNECTING NEEDLES
DE1910197B1 (en) Process for the production of longer structures, in particular bridge structures, in sections in front of the building and in front of the building in order to carry out the method
DE919595C (en) Process for the production of composite structures, especially for building bridges
DE859220C (en) Prefabricated reinforced concrete ceiling beams