[go: up one dir, main page]

CH149940A - Railroad tracks made of stone chips for bedding railway sleepers. - Google Patents

Railroad tracks made of stone chips for bedding railway sleepers.

Info

Publication number
CH149940A
CH149940A CH149940DA CH149940A CH 149940 A CH149940 A CH 149940A CH 149940D A CH149940D A CH 149940DA CH 149940 A CH149940 A CH 149940A
Authority
CH
Switzerland
Prior art keywords
stone
layer
sleepers
layers
bedding
Prior art date
Application number
Other languages
German (de)
Inventor
Sinkovich Desider
Original Assignee
Sinkovich Desider
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinkovich Desider filed Critical Sinkovich Desider
Publication of CH149940A publication Critical patent/CH149940A/en

Links

Landscapes

  • Railway Tracks (AREA)

Description

  

  Bahnkörper aus Steinschlag zur     Bettung    von     Eisenbahnschjye1Den.            Bahnkörper    aus Steinschlag oder Schotter       wurden    bisher durchwegs     derart    hergestellt;  dass die Fugen zwischen den einzelnen       Steinen    der Steinschichten nicht ausgefüllt,  sondern die Schichten höchstens nur nieder  gewalzt wurden, wobei     man    aber sorgfältig  darauf achtete, dass der Schotter möglichst  frei von Staub und Steingrus sei.  



  Diese Herstellungsweise bezweckte einer  seits eine     möglichst    grosse Durchlässigkeit  für die     Entwässerung    und Lüftung des  Oberbaues zu erzielen, was aber eigentlich  nur für     Holzschwellen    von grösserer Bedeu  tung ist,     anderseitqs    sollte damit die Elastizi  tät des Oberbaues erhalten werden.  



       -Demgegenüber    wird gemäss der vorliegen  den     Erfinc'ting    angestrebt, die Standfestig  keit und     Dauerfestigkeit    des     Bahnkörpers     dadurch zu erhöhen,     dass    die Fugen zwischen  den einzelnen Steinen möglichst gut ausge  füllt werden, und zwar mit körnigen Ma  terialien; welche bei Sicherung der Konsi  stenz des Oberbaues und der gehörigen    Festigung der Steinelemente keine     nacli-          teilige        Wirkung    ausüben;

   dadurch     bann    näm  lich das Ansammeln von Wasser im Oberbau  ebenso verhindert     bezw.    die Ableitung er  zielt werden, während     anderseits    die Elasti  zität des Oberbaues noch gesteigert wird.  



  Das Kennzeichen des neuen     Bahnkörper     besteht demnach darin, dass die Fugen zwi  schen den Elementen der Steinlagen durch       eingestampfte    körnige Materialien ausgefüllt  sind, wodurch diese     ElementF,    regen Locker  werden vollständig     gesichert    sind. Ferner  ist auf der obersten Schicht eine     Ausgleichs-          schicht    aus Steingrus aufgetragen, auf wel  cher die Schwellen liegen.  



  Zum Ausfüllen der Fugen dient körniges  Material,     vorteilhaft    feiner     Steingrus.     



  Ein     Ausführungsbeispiel    des     Erfindungs-          gegenstandes    ist in der Zeichnung darge  stellt, und zwar zeigt:       Fig.    1 den Bahnkörper im     Querschnitt     und in       Fig.    2 im     Längsschnitt.         Auf das geebnete und abgeschrägte       Planum    des     Unterbaues    ist gemäss der Zeich  nung vorerst eine Lage Sand oder Kohlen  schlacke 1 von wenigstens 10 cm Stärke aus  gebreitet, welche gleichzeitig auch dazu  dient,

   das Eindringen der     Steine    der     untern          Steinschlagschicht    2 in den     Untergrund    zu  verhüten, die Lagerung der Steine zu festi  gen und ein Aufweichen des Untergrundes       voranzuhalten.    Diese untere Steinschicht be  steht vorteilhaft aus 7 bis 8 cm starken  Steinstücken;     welche    in     Reihern    verlegt wer  den. Darauf wird ein zum Ausfüllen der  Fugen geeignetes Material,     beispielsweise          Steingrus,        gestreut,    welches fest in die  Fugen eingestampft wird, worauf das über  schüssige Material entfernt wird.

   Auf diese  erste Schicht kommt zweckmässig noch eine  zweite, ebensolche Schicht     B.    Nach Ausfül  len der Fugen und     Feststampfen    empfiehlt  es sich, für die folgende Schicht 4 nunmehr       einen:    Steinschlag von kleinerer, beispiels  weise 3 bis 4 cm Korngrösse anzuwenden. Dar  auf kommt noch eine ebensolche zweite  Schicht 5,     welche    in gleicher Weise festge  stampft mit einer 2 bis 3 cm dicken Schicht       Steingrus    überdeckt und horizontal ausge  glichen wird, um darauf die Schwellen 7  zu lagern. An Stelle von zwei gleichen  Schichten 2 und 3     bezw.    4 und 5 könnte.  auch nur     jeeine    Anwendung finden.  



  Beim Aufbau werden zweckmässig     nach          Ausbreitung    der     Schotterschicht    4 in der  Mitte Balken verlegt,     damit'naeh    Fertigstel  lung des Oberbaues und nach Entfernung  dieser Balken an deren Stelle ein     vertiefter          Streifen    8 entsteht, wodurch ein Aufliegen  der Schwellen in der     Mitte    und daraus ent  stehende Brüche vermieden werden.  



  Der beschriebene Bahnkörper ist insbe  sondere zur     Bettung    von     Eisenbetonschwel-          len    berufen, welche demnach unmittelbar nur  auf der     Stei        ngrusschicht    6- aufliegen, welch  letztere     viel    leichter auszugleichen ist, als  eine     Steinschlagschicht,    wobei - da der  Oberbau in seiner ganzen Masse vollständig  fest ist - sich das bisher übliche Unter  schlagen der Schienenschwellen mit Steinen         erübrig    ; der Steingrus     l#:ann    dagegen je     naeli     Bedarf, zum Ausgleichen einfach unter  schüttet werden.

   Nachdem aber die untern  Steinschichten keine Fugen aufweisen, wird  die obere Grusschicht - welche bei der bis  herigen Bauweise, wenn überhaupt angewen  det, infolge der     Erschütterungen    des Bahn  dammes allmählich in den Fugen ver  schwand - unverändert an der Oberfläche  liegen bleiben.  



  Demnach bildet die     Grusschicht    eine be  ständige Stütze der     Schienenschwellen        und     kommen diese niemals mit dem groben Stein  schlag 5 in Berührung, was bei Holzschwel  len ein Ausfressen und bei Betonschwellen  ein Ausbrechen der     Kanten    zur Folge hatte.  Durch das Ausschalten des ohnehin sehr un  zuverlässigen Unterschlages von Steinen, was  sich bei .der Herstellung des beschriebenen  Bahnkörpers erübrigt,     wird    daher nicht nur  eine Ersparnis an Oberbaumaterial und Ar  beit .erzielt, sondern auch dessen     viel    bessere  Auflage und sichere Unterstützung gewähr  leistet.  



  Nachdem die Schwellen verlegt und in  einer Ebene ausgeglichen sind und der Ober  bau sich     unter    der allmählich     gesteigerten     Belastung entsprechend gesetzt hat, erfolgt  zweckmässig nach nochmaligem Ausgleichen  der Schwellen die     Verfüllung    der Schwellen  zwischenräume und vor den. Schwellen  köpfen mit möglichst viel Grus enthaltendem  Steinschlag, welcher ebenfalls in 5     cm          starken:    Schichten, mit Ausnahme des mitt  leren: Streifens 8, festgestampft wird.  



  Eine derart hergestellte     Bettung    wird bei       Regengüssen    überhaupt nicht durchnässt, da  die kleinen Poren des Baues grössere Wasser  mengen plötzlich nicht aufnehmen     können,     bei andauerndem Regen wird aber     das     durchsickernde Wasser auf den zwischen den  einzelnen     Schichten,    befindlichen     ebenen     Flächen immer Ableitung finden, bevor es  noch den     Unterbau    erreichen könnte.  



  Der beschriebene     Bahnkörper    weist eine  bedeutend günstigere Verteilung des Schwel  lendruckes auf das     Planum    auf. Diese Ver  hältnisse sind in     Fig.    2 dargestellt. Von den      untern Schwellenkanten verteilt sich der       Druck    durch die     Schotterbettung    unter einem  Übertragungswinkel a = 60  , und durch die       Sandbettung    unter einem Winkel     ss    = 45    entsprechend den Begrenzungslinien<I>d, d'.</I>  Der Schwellendruck wird somit auf den gan  zen Unterbau     gleichmässig    übertragen,

   was  bei der bekannten reinen     Schotterbettung     nur durch eine entsprechend höhere     Bettung     erzielt     würde.  



  Railroad tracks made of stone chips for bedding railroad tracks. Railway bodies made of rockfall or gravel have been consistently produced in this way so far; that the joints between the individual stones of the stone layers were not filled, but rather that the layers were only rolled down, but careful attention was paid to the fact that the ballast was as free as possible from dust and stone gravel.



  This manufacturing method was intended on the one hand to achieve the greatest possible permeability for the drainage and ventilation of the superstructure, which is actually only of greater importance for wooden sleepers, on the other hand, the elasticity of the superstructure should be preserved.



       On the other hand, according to the research at hand, the aim is to increase the stability and fatigue strength of the track body by filling the joints between the individual stones as well as possible with granular materials; which have no adverse effect when the consistency of the superstructure is secured and the stone elements are properly strengthened;

   as a result, namely, the accumulation of water in the superstructure is also prevented or prevented. the derivation he aims, while on the other hand the elasticity of the superstructure is increased.



  The characteristic of the new track body is therefore that the joints between the elements of the stone layers are filled with pulverized granular materials, which means that these elements are completely secured. Furthermore, a leveling layer made of stone gravel is applied to the top layer, on which the sleepers lie.



  Granular material, advantageously fine stone grit, is used to fill the joints.



  An exemplary embodiment of the subject matter of the invention is shown in the drawing, specifically showing: FIG. 1 the track body in cross section and in FIG. 2 in longitudinal section. According to the drawing, a layer of sand or coal slag 1 with a thickness of at least 10 cm is spread over the leveled and bevelled subgrade, which at the same time also serves to

   to prevent the penetration of the stones of the lower rockfall layer 2 into the ground, the storage of the stones to festi conditions and a softening of the ground ahead. This lower stone layer is advantageously made of 7 to 8 cm thick stone pieces; which are laid in rows. A material suitable for filling the joints, for example stone gravel, is sprinkled on top of this and is firmly tamped into the joints, whereupon the excess material is removed.

   On top of this first layer is a second, similar layer B. After filling the joints and tamping down, it is advisable to use a stone chip of a smaller size, for example 3 to 4 cm, for the following layer 4. This is followed by a similar second layer 5, which is stamped in the same way, covered with a 2 to 3 cm thick layer of stone grit and leveled horizontally in order to store the sleepers 7 on it. Instead of two identical layers 2 and 3 respectively. 4 and 5 could. only find an application.



  During construction, beams are expediently laid in the middle after the gravel layer 4 has spread, so that the superstructure is near completion and a recessed strip 8 is created in their place after these beams have been removed, thereby preventing the sleepers from resting in the middle and resulting breaks will.



  The track body described is especially used for bedding reinforced concrete sleepers, which therefore only lie directly on the stone gravel layer 6, which the latter is much easier to level out than a rockfall layer, whereby - since the superstructure is completely solid in its entire mass - the hitherto customary hitting the rail sleepers with stones is superfluous; The stone grus can, however, depending on the need, simply be poured under to compensate.

   But since the lower stone layers have no joints, the upper layer of gravel - which in the previous construction method, if used at all, gradually disappeared into the joints due to the vibrations of the railway embankment - will remain unchanged on the surface.



  Accordingly, the gravel layer forms a constant support of the rail sleepers and they never come into contact with the rough stone impact 5, which resulted in eroding in Holzschwel len and the edges breaking out in concrete sleepers. By eliminating the already very un reliable deposit of stones, which is unnecessary in the production of the railway body described, not only a saving in superstructure material and labor is achieved, but also ensures its much better support and reliable support.



  After the sleepers have been laid and leveled on one level and the superstructure has settled accordingly under the gradually increasing load, it is advisable to fill the sleepers in between and in front of the sleepers after leveling the sleepers again. Sleepers head with stone chips containing as much gravel as possible, which are also tamped down in 5 cm thick layers, with the exception of the middle: strip 8.



  A bedding made in this way is not soaked at all when it rains, because the small pores of the building suddenly cannot absorb larger amounts of water, but when it rains continuously, the seeping water on the flat surfaces between the individual layers will always find its way off before it can could reach the substructure.



  The track body described has a significantly more favorable distribution of the Schwel pressure on the subgrade. These ratios are shown in FIG. From the lower edges of the sleeper, the pressure is distributed through the ballast bedding at a transfer angle a = 60, and through the sand bedding at an angle ss = 45 according to the boundary lines <I> d, d '. </I> The sleeper pressure is thus on the whole evenly transfer the substructure,

   what with the known pure ballast bedding would only be achieved by a correspondingly higher bedding.

 

Claims (1)

PATENTANSPRUCH: Bahnkörper aus Steinschlag zur Bettung von Eisenbahnschwellen, bestehend aus meh reren auf einem Bett aus hartkörnigem Ma terial aufgebauten Steinschichten von ver schiedener Korngrösse, dadurch gekennzeich net, dass die Fugen zwischen den Steinen der einzelnen Schichten mit eingestampftem kör nigem Material völlig ausgefüllt sind und auf der obersten Schicht eine Ausgleichs- schicht aus Steingrus aufgetragen ist, auf welcher die Schwellen liegen. PATENT CLAIM: Track body made of stone chips for bedding railway sleepers, consisting of several stone layers of different grain sizes built up on a bed of hard-grained material, characterized in that the joints between the stones of the individual layers are completely filled with pulped granular material and A leveling layer of stone gravel is applied to the top layer, on which the sleepers lie. UNTERANSPRUCH: Bahnkörper nach Patentanspruch, da durch gekennzeichnet, da.ss die auf das Bett aus hartkörnigem Material verlegten untern Schichten je aus in Reihen verlegten, 7 bis 8 cm starken und die obern Schichten je aus in Reihen verlegten, 3 bis 4 cm starken Steinen bestehen, wobei jede Schicht beson ders mit körnigem Material festgestampft und schliesslich eine zirka 2 cm starke Aus gleichsschicht aus Grus aufgetragen ist, wäh rend die Verfüllung der auf dieser Aus gleichsschicht verlegten Schienenschwellen aus Grus enthaltendem und ebenfalls schich tenweise festgestampftem Steinschlag be steht. SUBClaim: Railway body according to patent claim, characterized in that the lower layers laid on the bed of hard-grained material are each made up of 7 to 8 cm thick stones laid in rows and the upper layers are made up of 3 to 4 cm thick stones laid in rows Each layer is specially tamped with granular material and finally an approx. 2 cm thick equalizing layer of grit is applied, while the rail sleepers laid on this equalizing layer are filled with stone chips, which are also packed in layers and contain grus.
CH149940D 1929-09-25 1930-09-23 Railroad tracks made of stone chips for bedding railway sleepers. CH149940A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
HU149940X 1929-09-25

Publications (1)

Publication Number Publication Date
CH149940A true CH149940A (en) 1931-10-15

Family

ID=10977617

Family Applications (1)

Application Number Title Priority Date Filing Date
CH149940D CH149940A (en) 1929-09-25 1930-09-23 Railroad tracks made of stone chips for bedding railway sleepers.

Country Status (1)

Country Link
CH (1) CH149940A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102006003098B4 (en) * 2005-01-21 2007-09-20 Bonewitz, Wilfried, Dipl.-Ing. Track construction for rail vehicles

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102006003098B4 (en) * 2005-01-21 2007-09-20 Bonewitz, Wilfried, Dipl.-Ing. Track construction for rail vehicles

Similar Documents

Publication Publication Date Title
DE2306428A1 (en) RAILWAY TRACK
DE2063727A1 (en) Method for stabilizing a ballast bed
DE2512691A1 (en) ROAD COVERING FOR ROADS, BRIDGES AND THE LIKE, WHOSE ROAD COVER CONTAINS AN ANTI-FREEZE AGENT
CH149940A (en) Railroad tracks made of stone chips for bedding railway sleepers.
WO2012130425A2 (en) Track way for rail-bound vehicles and track support for such a track way
DE583186C (en) Railway body, consisting of several rockfall layers built up on a bed of sand or slag
EP0216148B1 (en) Bituminous surfacing for roads and process for making bituminous surfacings in the cold state for roads
DE557163C (en) Bedding for railway tracks made of fine-grained natural materials
DE1658308A1 (en) Railroad
DE1104546B (en) Process for the production of a substructure for the ballast gravel that accommodates the sleepers
DE527174C (en) Process for the production of a bituminous gravel surface
DE365518C (en) Process for the production of a covering for traffic routes in the manner of the sand asphalt process
DE10218309B4 (en) Track for railway vehicles with a ballast bed for tracks, process for its manufacture and a binder mixture for use in the process
DE560359C (en) Process for the production of monolithic road surfaces
DE850902C (en) Method for laying the height of sunken concrete fields of the motorway or sunken rail girders u. like
DE2823375A1 (en) Rubber-contg. flooring compsn. for sports and playing grounds - contains quartz sand and cold bitumen-bonded chips
DE689057C (en) Process for the production of mortar-bound road surfaces
DE974948C (en) Process to improve the load-bearing capacity of natural soil layers and artificial heaps by introducing load-bearing material under rocking
AT148214B (en) Road surface.
AT130446B (en) Process for the production of quarry stone paving.
DE736752C (en) Process for producing water-permeable, stable ceilings for places
AT130454B (en) Process for the production of an impregnated, irregular paving.
AT126191B (en) Process for the production of road surfaces using the cold process.
DE637370C (en) Process for the production of wooden paving slabs
CH94381A (en) Process for the production of an inexpensive homogeneous and monolith-like surface for areas which are exposed to traffic or the effects of atmospheric substances.