Zhou et al., 2023 - Google Patents
IEDW: A BIM-based indoor electric distribution wiring algorithm using graph theory and capacity-limited multiple traveling salesman problem solverZhou et al., 2023
- Document ID
- 8989101172014585438
- Author
- Zhou X
- Sun K
- Wang Q
- Wang J
- Huang X
- Zhou W
- Publication year
- Publication venue
- Advanced Engineering Informatics
External Links
Snippet
Abstract Building Information Modeling (BIM) has emerged as a new paradigm for the construction industry. The combination of electric distribution systems design and BIM is the future development trend of architectural design. The traditional electric distribution wiring …
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/50—Computer-aided design
- G06F17/5009—Computer-aided design using simulation
- G06F17/5036—Computer-aided design using simulation for analog modelling, e.g. for circuits, spice programme, direct methods, relaxation methods
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/50—Computer-aided design
- G06F17/5086—Mechanical design, e.g. parametric or variational design
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/50—Computer-aided design
- G06F17/5004—Architectural design, e.g. building design
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/50—Computer-aided design
- G06F17/5068—Physical circuit design, e.g. layout for integrated circuits or printed circuit boards
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/50—Computer-aided design
- G06F17/509—Network design, e.g. positioning, routing, graphs
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F2217/00—Indexing scheme relating to computer aided design [CAD]
- G06F2217/02—Component-based CAD
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F2217/00—Indexing scheme relating to computer aided design [CAD]
- G06F2217/78—Power analysis and optimization
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F2217/00—Indexing scheme relating to computer aided design [CAD]
- G06F2217/04—CAD in a network environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06Q—DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management, e.g. organising, planning, scheduling or allocating time, human or machine resources; Enterprise planning; Organisational models
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06Q—DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation, e.g. linear programming, "travelling salesman problem" or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B15/00—Systems controlled by a computer
- G05B15/02—Systems controlled by a computer electric
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Kim et al. | Developing a physical BIM library for building thermal energy simulation | |
| Lin et al. | The IFC-based path planning for 3D indoor spaces | |
| Guo et al. | Evolutionary approach for spatial architecture layout design enhanced by an agent-based topology finding system | |
| Peng et al. | Computational network design from functional specifications | |
| Di Filippo et al. | Generative Design for project optimization (S). | |
| Gourlis et al. | A holistic digital twin simulation framework for industrial facilities: BIM-based data acquisition for building energy modeling | |
| Strug et al. | Reasoning about accessibility for disabled using building graph models based on BIM/IFC | |
| Ślusarczyk et al. | An extended hierarchical graph-based building model for design and engineering problems | |
| CN114004000A (en) | System for intelligent pipeline arrangement based on BIM technology | |
| CN116187175A (en) | Neural Network Recognition Method for Substation and Distribution Station Based on Electrical Industry Knowledge Graph | |
| Zhou et al. | IEDW: A BIM-based indoor electric distribution wiring algorithm using graph theory and capacity-limited multiple traveling salesman problem solver | |
| CN111241619B (en) | A rule-driven collaborative interactive space layout automatic design method | |
| Morris et al. | Unified system modeling and simulation via constraint hypergraphs | |
| Hua | A case-based design with 3D mesh models of architecture | |
| Adão et al. | Procedural generation of traversable buildings outlined by arbitrary convex shapes | |
| Li et al. | A constraint based generative system for floor layouts | |
| You et al. | Civil Engineering Simulation and Safety Detection of High‐Rise Buildings Based on BIM | |
| Hijazi | Integrated management of indoor and outdoor utilities by utilizing BIM and 3DGIS | |
| Wu et al. | A knowledge graph model for performance-based generative design and its applications in accelerated design | |
| Chen et al. | Digital twin warehouse management platform developed based on Unity3D | |
| Nithyanantham et al. | MCP4IFC: IFC-Based Building Design Using Large Language Models | |
| CN114117800A (en) | Modelica-based power grid flow calculation method and device | |
| Das et al. | Automated Service Core Generator in Autodesk Dynamo | |
| Wen et al. | Knowledge driven rule-based building geometric digital twin construction–state of art review | |
| Madrazo et al. | BARCODE HOUSING SYSTEM |