Why were 800 m of the Boßler Tunnel built twice?–TBM passing a shotcrete section: Warum wurde der Boßlertunnel auf 800 m zweimal gebaut?–Durchfahrt einer …

Goldberger et al., 2017

Document ID
8313480427470068877
Author
Goldberger H
Esslinger C
Lützerath T
Müller J
Galli M
Publication year
Publication venue
Geomechanics and Tunnelling

External Links

Snippet

Impermeable tunnels are usually built conventionally with drill and blast or excavators followed by an inner lining or by mechanized tunnelling method with a segment lining. A combination of both methods on certain sections is commonly used for large tunnels due to …
Continue reading at onlinelibrary.wiley.com (other versions)

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Lay-outs therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B37/00Making, maintaining, renewing, or taking-up the ballastway or the track, not provided for in a single one of groups E01B27/00 - E01B35/00
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS

Similar Documents

Publication Publication Date Title
CN212563261U (en) Half cut single-pressure type open cut tunnel advances hole protective structure fast
Spyridis et al. Design of SCL structures in London/Entwurf von Tunnelbauwerken in Spritzbeton‐Bauweise am Beispiel London
Goldberger et al. Why were 800 m of the Boßler Tunnel built twice?–TBM passing a shotcrete section: Warum wurde der Boßlertunnel auf 800 m zweimal gebaut?–Durchfahrt einer TVM durch eine Spritzbetonstrecke
Wagner et al. The challenges of contract SBT1. 1 “Tunnel Gloggnitz"/Die Herausforderungen des Bauloses SBT1. 1 Tunnel Gloggnitz
Daller et al. Special features of tendering contract SBT2. 1–Fröschnitzgraben Tunnel/Besonderheiten der Ausschreibung des Bauloses SBT2. 1–Tunnel Fröschnitzgraben
Incecik et al. Tunnel T26 on the Ankara–Istanbul high speed rail route–Tunnelling under difficult conditions: Der Tunnel T26 auf Schnellstrecke Ankara–Istanbul–Vortrieb unter schwierigen geologischen Verhältnissen
Vetter et al. Refurbishment of the Kuckuckslay tunnel–Current experience in the use of the” Tunnel‐im‐Tunnel‐Methode “
Ehrbar et al. Grouting works at the Gotthard Base Tunnel/Injektionsmaßnahmen am Gotthard‐Basistunnel
DE3803120C2 (en)
Suchmann et al. Intersection U2xU5–Tunnelling works at the lot U2/22
Raderbauer The autobahn ring Biel east branch/Autobahnumfahrung Biel Ostast
Flora et al. Brenner Base Tunnel exploratory tunnel Ahrental‐Pfons–interaction between tunnel boring machine and rock mass as well as measures to manage fault zones
Blauhut et al. Lower Tuxbach diversion–A high pressure diversion tunnel: Excavation and lining design for internal pressure greater than 20 bar
Bodenstab et al. Solution Concepts for Mining and Geomechanical Challenges Involved in Safe Long-Term Closure of the Saale Shaft in the Teutschenthal Mine.
Harer et al. The main Koralm Tunnel contracts–current state of works/Die Großbaulose des Koralmtunnels–Aktueller Stand der Arbeiten
Gamper et al. Jenbach Tunnel–a shallow hydroshield drive
Lienhart et al. Feuerbach and Bad Cannstatt Tunnels–special requirements of the inner‐city Location and difficult geotechnical Conditions
Schreitl et al. How Asfinag decides construction methods/Baumethodenentscheidung bei der Asfinag
Herzeg et al. St. Kanzian tunnel chain–Current state of works: Tunnelkette St. Kanzian–Aktueller Stand der Arbeiten
Vigl System solutions for headraces of high head hydropower plants/Systemlösungen für Kraftabstiege von Hochdruck‐Wasserkraftanlagen: Design, structural design and construction considerations/Entwurf, Bemessung und baupraktische Aspekte
Gasser et al. The Stockholm bypass project
Trunk et al. Jet grouting in tunnelling/Düsenstrahlverfahren im Tunnelbau
DE3632189C3 (en) Pressurized water gallery
Schmidt et al. Planning and excavation of a special-profile, deep-level face start-up road at Prosper-Haniel colliery
Rengshausen et al. Metro Doha Green Line–More than 30 km of tunnel in 18 months: Metro Doha Green Line–Mehr als 30 km Tunnel in 18 Monaten