Geotechnical considerations in the design of the MOCB mining method at Konkola No. 3 shaftLipalile, M.*, Naismith, AW** & Tonono, 2005
View PDF- Document ID
- 17054294677880166352
- Author
- Lipalile, M.*, Naismith, AW** & Tonono A
- Publication year
- Publication venue
- Journal of the Southern African Institute of Mining and Metallurgy
External Links
Snippet
Konkola No 3 shaft experienced severe mining-induced stress and time-related deterioration in ground conditions in an area where an over-cut and bench (OCB) mining method was used to extract a shallow dipping wide orebody. This caused an unacceptable …
- 238000005065 mining 0 title abstract description 58
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Lay-outs therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/25—Methods for stimulating production
- E21B43/26—Methods for stimulating production by forming crevices or fractures
- E21B43/263—Methods for stimulating production by forming crevices or fractures using explosives
- E21B43/2635—Methods for stimulating production by forming crevices or fractures using explosives by means of nuclear energy
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Lay-outs therefor
- E21C41/26—Methods of surface mining; Layouts therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C47/00—Machines for obtaining or the removal of materials in open-pit mines
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D15/00—Props; Chocks, e.g. made of flexible containers filled with backfilling material
- E21D15/48—Chocks or the like
- E21D15/483—Chocks or the like made of flexible containers, e.g. inflatable, with or without reinforcement, e.g. filled with water, backfilling material or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Wagner | Deep mining: a rock engineering challenge | |
Rahimi et al. | Ground behaviour analysis, support system design and construction strategies in deep hard rock mining–Justified in Western Australian's mines | |
Sandbak et al. | Ground support strategies at the turquoise ridge joint venture, Nevada | |
Abdellah et al. | Stability assessment of underground openings using different rock support systems | |
Lang | Span design for entry-type excavations | |
Babets et al. | Multifactorial analysis of a gateroad stability at goaf interface during longwall coal mining–A case study | |
Li et al. | Behaviors and Overlying Strata Failure Law for Underground Filling of a Gently Inclined Medium‐Thick Phosphate Deposit | |
Ozturk | Support design of underground openings in an asphaltite mine | |
Ran | Safe mining practices under wide spans in underground non-caving mines–Case studies | |
Henning | Evaluation of long-hole mine design influences on unplanned ore dilution | |
Marlow et al. | Shotcrete ribs and cemented rock fill ground control methods for stoping in weak squeezing rock at Wattle Dam Gold Mine | |
Zhang et al. | The Stability of Gob‐Side Entry Retaining in a High‐Gas‐Risk Mine | |
Yu et al. | Innovative Control Technique for the Floor Heave in Goaf‐Side Entry Retaining Based on Pressure Relief by Roof Cutting | |
Adams et al. | Assessment of a new mine layout incorporating concrete pillars as regional support | |
Lipalile, M.*, Naismith, AW** & Tonono | Geotechnical considerations in the design of the MOCB mining method at Konkola No. 3 shaft | |
Ghasemi | Numerical studies of mining geometry and extraction sequencing in Lappberget, Garpenberg | |
Gautam et al. | Strata Control by Roof Blasting for Bord and Pillar Mining Method in Mechanized Depillaring Panels | |
Sandbak et al. | Ground support strategies for weak ground masses at the Turquoise Ridge Joint Venture, Nevada | |
Banjwa | Review of geotechnical challenges experienced within a weak kimberlite zone: a case study at Cullinan diamond mine | |
Pyy et al. | Mining between graphite schist and variable quality backfill | |
Adams et al. | On the merits of modified sublevel caving mining method–a case study | |
Moulding et al. | Managing the onset of accelerated deformation in capital development at Agnew Gold Mine | |
Langston et al. | Extraction of a Remnant Sill Pillar Under Challenging Ground Conditions at the Stillwater Mine, Nye, MT | |
Chen et al. | Mining system for remaining coal of final highwall | |
Board | Ground support from a corporate perspective |